nes 353 examination of machinery in hm surface ships on completion of contractor's sea trials

36
Ministry of Defence Defence Standard 02-353 (NES 353) Issue 1 Publication Date 01 April 2000 Incorporating NES 353 Category 2 Issue 6 Publication Date September 1999 Examination Of Machinery In HM Surface Ships On Completion Of Contractor's Sea Trials

Upload: jeorje

Post on 23-Dec-2015

12 views

Category:

Documents


0 download

DESCRIPTION

Examination Of Machinery In HM Surface Ships

TRANSCRIPT

Page 1: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

Ministry of Defence Defence Standard 02-353 (NES 353)

Issue 1 Publication Date 01 April 2000

Incorporating NES 353 Category 2

Issue 6 Publication Date September 1999

Examination Of MachineryIn HM Surface Ships

On Completion Of Contractor's Sea Trials

DSTAN
DStan is now the publishing authority for all Naval Engineering Standards which are now covered as Defence Standards. Any reference to any other publication authority within this document should be ignored. Any queries regarding this or any other Defence Standard should be referred to the DStan Helpdesk as detailed at the back of this document
Page 2: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

AMENDMENT RECORD

Amd No Date Text Affected Signature and Date

REVISION NOTE

This standard is raised to Issue 1 to update its content.

HISTORICAL RECORD

This standard supersedes the following:

Naval Engineering Standard (NES) 353 Issue 6 dated September 1999

Page 3: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

Ministry of Defence

Naval Engineering Standard

CATEGORY 2

NES 353 Issue 6 September 1999

EXAMINATION OF MACHINERY IN HM SURFACE SHIPS ONCOMPLETION OF CONTRACTOR’S SEA TRIALS

© CROWN COPYRIGHT 1999

Page 4: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

This NES Supersedes

NES 353 Issue 1 December 1979NES 353 Issue 2 October 1981NES 353 Issue 3 1984NES 353 Issue 4 May 1987NES 353 Issue 5 March 1991

Record of Amendments

AMDT INSERTED BY DATE

1

2

3

4

5

Page 5: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

(i)

NAVAL ENGINEERING STANDARD 353

EXAMINATION OF MACHINERY IN HM SURFACE SHIPS

ON COMPLETION OF CONTRACTOR’S SEA TRIALS

ISSUE 6 SEPTEMBER 1999

This Naval Engineering Standard is

authorized for use in MOD contracts

by the Defence Procurement Agency

and the Defence Logistics Organization

Published by:

Sea Technology Group,Defence Procurement Agency,STGSA,Ash 0a, #95,MOD Abbey Wood,BRISTOL, BS34 8JH.

Page 6: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

(ii)

Page 7: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

(iii)

SCOPE

1. This Naval Engineering Standard (NES) applies to the examination of main propulsion andauxiliary machinery on completion of Contractor’s Sea Trials (CST) in HM Surface Ships.

Page 8: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

(iv)

Page 9: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

(v)

FOREWORD

Sponsorship1. This Naval Engineering Standard (NES) is sponsored by the Defence Logistics Organization

(DLO), Ministry of Defence (MOD).

2. Any user of this NES either within MOD or in industry may propose an amendment to it.Proposals for amendments that are not directly applicable to a particular contract are to bemade to the publishing authority identified on Page (i), and those directly applicable to aparticular contract are to be dealt with using contract procedures.

3. If it is found to be unsuitable for any particular requirement MOD is to be informed inwritingof the circumstances.

4. No alteration is to be made to this NES except by the issue of an authorized amendment.

5. Unless otherwise stated, reference in this NES to approval, approved, authorized and similarterms, means by the MOD in writing.

6. Any significant amendments that may be made to this NES at a later date will be indicatedby a vertical sideline. Deletions will be indicated by 000 appearing at the end of the lineinterval.

7. This NES has been reissued to reflect changes in Departmental Nomenclature due to theMOD reorganization and the changes to technical requirements.

Conditions of Release

General8. This Naval Engineering Standard (NES) has been devised solely for the use of the MOD, and

its contractors in the execution of contracts for the MOD. To the extent permitted by law, theMOD hereby excludes all liability whatsoever and howsoever arising (including but withoutlimitation, libability resulting from negligence) for any loss or damage however caused whenthe NES is used for any other purpose.

9. This document is Crown Copyright and the information herein may be subject to Crown orthird party rights. It is not to be released, reproduced or publishedwithout written permissionof the MOD.

10. The Crown reserves the right to amend or modify the contents of thisNES without consultingor informing any holder.

MOD Tender or Contract Process11. This NES is the property of the Crown. Unless otherwise authorized in writing by the MOD

it must be returned on completion of the contract, or submission of the tender, in connectionwith which it is issued.

12. When thisNES is used in connection with aMOD tender or contract, the user is to ensure thathe is in possession of the appropriate version of each document, including related documents,relevant to each particular tender or contract. Enquiries in this connection may be made tothe authority named in the tender or contract.

13. When NES are incorporated into MOD contracts, users are responsible for their correctapplication and for complying with contractual and other statutory requirements.Compliance with an NES does not of itself confer immunity from legal obligations.

Categories of NES14. The Category of this NES has been determined using the following criteria:

a. Category 1. If not applied may have a Critical affect on the following:

Safety of the vessel, its complement or third parties.

Operational performance of the vessel, its systems or equipment.

Page 10: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

(vi)

b. Category 2. If not applied may have a Significant affect on the following:

Safety of the vessel, its complement or third parties.

Operational performance of the vessel, its systems or equipment.

Through life costs and support.

c. Category 3. If not applied may have a Minor affect on the following:

MOD best practice and fleet commonality.

Corporate experience and knowledge.

Current support practice.

Related Documents

15. In the tender and procurement processes the related documents listed in each section andAnnex A can be obtained as follows:

a. British Standards British Standards Institution,389 Chiswick High Road,London, W4 4AL.

b. Defence Standards Directorate of Standardization, Stan BM & DKentigern House, 65 Brown Street,Glasgow, G2 8EX.

c. Naval Engineering Standards DSDC(L), Llangennech, Llanelli, Dyfed,SA14 8YP.

d. Other documents Tender or Contract Sponsor to advise.

16. All applications to the MOD for related documents are to quote the relevant MOD Invitationto Tender or Contract number and date, together with the sponsoring Directorate and theTender or Contract Sponsor.

17. Prime Contractors are responsible for supplying their subcontractors with relevantdocumentation, including specifications, standards and drawings.

Health and Safety

Warning

18. This NES may call for the use of processes, substances and/or procedures that are injuriousto health if adequate precautions are not taken. It refers only to technical suitability and inno way absolves either the supplier or the user from statutory obligations relating to healthand safety at any stage of manufacture or use. Where attention is drawn to hazards, thosequoted may not necessarily be exhaustive.

19. This NES has been written and is to be used taking into account the policy stipulated in JSP430: MOD Ship Safety Management System Handbook.

Additional Information

(No relevant information included).

Page 11: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

(vii)

CONTENTS

Page No

TITLE PAGE (i). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCOPE (iii). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

FOREWORD (v). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sponsorship (v). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Conditions of Release (v). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Categories of NES (v). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Related Documents (vi). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Health and Safety (vi). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Additional Information (vi). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

CONTENTS (vii). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SECTION 1. PERFORMANCE SPECIFICATION 1.1. . . . . . . . . . . . . . . . . .1.1 Aim 1.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1.2 Selection of Machinery for Examination 1.1. . . . . . . . . . . . . . . .1.3 Conduct of Examination 1.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . .1.4 Items to be Examined 1.2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SECTION 2. NATIONAL/INTERNATIONAL REGULATIONS 2.1. . . . . . .

SECTION 3. MILITARY STANDARDS/REQUIREMENTS 3.1. . . . . . . . . . .3.1 Aim 3.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3.2 Selection of Machinery for Examination 3.1. . . . . . . . . . . . . . . .3.3 Items to be Examined 3.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SECTION 4. DESIGN REQUIREMENTS/GUIDANCE 4.1. . . . . . . . . . . . . .

SECTION 5. CORPORATE EXPERIENCE & KNOWLEDGE 5.1. . . . . . . .

ANNEX A. RELATED DOCUMENTS A.1. . . . . . . . . . . . . . . . . . . . . . . . . .

ANNEX B. ABBREVIATIONS B.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

ANNEX C. PROCUREMENT CHECK LIST C.1. . . . . . . . . . . . . . . . . . . . .

ALPHABETICAL INDEX INDEX 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Page 12: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

(viii)

Page 13: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

1.1

1. PERFORMANCE SPECIFICATION

Related Documents: NES 159 Parts 1 & 2; NES 304 Part 2; NES 305; NES 309; NES 313;NES 314; NES 315; NES 319; NES 320; NES 325; NES 329; NES 332 Parts 1, 2, 3, & 4;NES 344; NES 349; NES 354; NES 366; NES 630; NES 719, Form D313; see alsoAnnex A.

1.1 Aim

a . Machinery is to be opened up following sea trials for internal inspection:

(1) To confirm satisfactory design, manufacture and ‘fitness for purpose’.

(2) To investigate, if necessary, the cause of any shortcomings inperformanceor unusual trials observations.

NOTE: Routine maintenance and rectification of defects is to be carriedout in conjunction with the examination where appropriate.

1.2 Selection of Machinery for Examination

a . The Defence Logistics Oganization (DLO) is to specify the machinery to beexamined in each class of ship in accordance with Section 1.4.

b . After experience with the first ships of any Class or Batch, to assist the MODTrials Officer on whom rests the final decision on the opening-up of any item ofmachinery, DLO are to issue a list of items, for which the extent of examinationmay be increased, reduced or waived subject to the performance of themachinery during CST. This list may be amended from time−to−time.

c . For each ship of a class the extent of the examination may be further amendedby the MOD Trials Officer, in agreement with the Resident Project Officer(RPO), should the performance of machinery during trials so dictate. Theagreed list is to be forwarded by the RPO to the Shipbuilder immediatelyfollowing CST with copies to the MOD Trials Officer.

d . The opening-up of machinery, to facilitate examination, is to be kept to aminimum to ensure a satisfactory installation. Where practicable therequirements of examinations are to be met by routine maintenance activities.

e . The RPO may increase the amount of work to be carried out, if defects arediscovered in the course of the examination.

1.3 Conduct of Examination

a . The Shipbuilder is to be responsible for the following:

(1) Opening-up or otherwise preparing for examination such machinery,equipment or systems as required by the DLO and drawing up aprogramme for the work.

(2) Providing the facilities necessary to ensure a detailed inspection andarranging the attendance of all subcontractors. The Shipbuilder is also toarrange for the attendance of the manufacturer’s representatives wherethe equipment is Government Furnished Equipment (GFE),Embodiment Loan Items (ELI), or Commercial off the Shelf (COTS).

Page 14: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

1.2

(3) Observing cleanliness precautions in accordance with NES 341. Inparticular suitable protection against ingress of dirt is to be provided forany opened-up machinery and for any components or assemblies removedand laid aside. No extraneous work, which may produce dirt such asremoval or application of insulation, preparation for or painting, wiring,drilling or welding, is to be done in any compartment containingopened-up machinery unless approved by the RPO.

(4) Mustering all special tools, lifting gear, cleaning gear and other suchequipment provided for the ship and ensuring that only these are used inthe course of opening-up, cleaning, adjusting and rectifying themachinery. Any defects, difficulties in use or apparent omissions from thekit are to be reported to the RPO.

(5) Rectifying, to the satisfaction of the RPO, any defects disclosed during theexaminations, verifying cleanliness and reinstating the machinery forFinal Machinery Trials (FMT) in accordance with NES 354.

(6) Submitting a report of his findings to the RPO, preferably in the format ofthe Test Form.

1.4 Items to be Examined

a . The following clauses lay down the basis on which the Class Opening-Up List isdrawn up. During the examination of machinery reference is to be made to theNES appropriate to each equipment or system:

(1) Sea Water Heat Exchangers (NES 329):

(a) Immediately after Contractor’s Sea Trial (CST) drain sea water andflush with fresh water.

(b) Open up water side, clear and jet tubes, clean tube plates and waterboxes giving special attention to the removal of organic matter.Flush with fresh water and inspect for signs of erosion or corrosion;

(2) Forced Lubrication (FL) Systems (NES 303):

(a) Change all filters, inspect drain tanks or sumps incorporated inself-contained lubricating oil systems.

(b) Presence of foreign matter, particularly metallic particles, is to berecorded and thoroughly investigated.

(3) Air, Fuel, Steam, and Water Systems (NES 314; NES 319; NES 320;NES 332 Parts 1, 2, 3, & 4; NES 344; NES 349; NES 719):

(a) Examine all strainers, filters, steam and weed traps.

(4) Distilled-Water Tanks:

(a) Examine selected tanks.

(5) Automatic Devices:

(a) Examine automatic devices including auto-controlled valves inmain, auxiliary and control systems and selected valves.

Page 15: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

1.3

(6) Couplings:

(a) Examine all bolts in couplings between units of machinery and inshafting for tightness and check torques where specified.Membranes of disc or similar couplings are also to be examined.

(7) Holding Down Arrangements:

(a) Examine all holding down arrangements such as bolts, shock andnoise attenuating mountings, keeps and fastenings, sliding feet andpalms.

(8) Main Shaft (NES 304 Part 2):

(a) Examine all main shaft bearings and main thrust or adjustingbearings. Shaft brakes are to be examined for wear, distortion andclearance.

(9) Steam-Generating Plant (NES 325):

(a) Externally clean the steam-generating plant.

(10) Main and Cruising Propulsion Gas Turbines (NES 309):

(a) Carry out scheduled maintenance operations up to and includingthose required at running hours approximating to twice the loggedhours at the end of CST.

NOTE: Should no official maintenance schedule be available theResident Project Officer (RPO) is to obtain from DLO astatement of maintenance operations and examinations tobe carried out.

(11) Propulsion Diesel Engines (NES 313):

(a) Remove, test and recalibrate injectors.

(b) Examine bores and piston crowns by endoscope through injectorholes.

(c) Examine underside of pistons and liners from the crankcase.

(d) Record crankshaft web deflections and check against specifiedlimits.

(e) Examine internal gearing, timing gear, all pumps and superchargerdrives.

(f) Examine sumps and internal conditions generally. Presence offoreign matter, particularly metallic particles, is to be recorded andthoroughly investigated.

(g) Stripping on−board of engines which have been installed ascomplete units, i.e. have not been stripped and re-erected tofacilitate installation, is to be restricted to the following:

(i) Modifications required to be carried out after installation.

Page 16: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

1.4

(ii) Examinations of a particular cylinder or cylinders because ofunsatisfactory performance during trials or following theexaminations in Clause (11).b. and (11).c. above whenrequired by the MOD Trials Officer.

(iii) Carrying out scheduled maintenance operations.

(h) When engines need to be extensively stripped on−board, anadditional examination of the main and large end bearings is to bemade.

(12) Propulsion Electric Motors:

(a) Check motor brushes, brush gear and clearances.

(13) Propulsion Gearing (NES 305):

(a) Examine all pinion and wheel teeth.

(b) Examine top and bottom halves of selected bearings.

NOTE: In ships other than First−of−Class, the bearingexaminations should be limited to two per gearbox, unlessthere is reason to suspect damage.

(c) Check the clearance of all thrust and location bearings either byinspection or by jacking the located shafts axially through their fullrange of travel.

(d) Check the security of ALL accessible bolted flanges in the maintransmission path by applying 50% of the design torque to at least25%of fasteners in every flange. Anymovement of fasteners is to bereported to the Design Authority.

(e) Check the security of selected internal instrumentation includingthe associated cabling.

(f) Inspect the gearbox sump and drain tank. The presence of anyforeign matter is to be thoroughly investigated and reported to theRPO. (See NES 303 for oil-change requirements).

(g) Examine selected flexible couplings, hydraulic couplings andclutches.

NOTE: Unless malfunction has occurred or is suspected, anin−situ visual inspection for signs of damage oroverheating will normally suffice. The condition of internalthrust bearings is to be checked as at (c) above.

(h) Gearbox sweep readings are to be checked and compared withpre-CST readings.

(14) Desalination Plant (NES 366):

(a) A complete internal examination with sufficient doors open for thepurpose.

(b) An examination of tubes and tube plates in condenser and feedheater, in conventional plants, and in vapour condenser and finalheater of flash plants.

Page 17: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

1.5

(15) Refrigerating and Air Conditioning Machinery (NES 159 Parts 1 & 2):

(a) Gas circuits are to be recharged as necessary as late in programmeas possible before Final Machinery Trial (FMT).

(16) Reciprocating Air Compressors (NES 315):

(a) A cylinder liner piston and large-end bearing of one cylinder are tobe examined. In compound machines the High Pressure (HP)Cylinder is to be examined.

(17) Diesel Driven Generating Sets (NES 313; NES 630)− Before FMT and aslate as possible in the programme, overhaul and restore equipment to ‘asnew’ condition as follows:

(a) If the aggregate of runninghours does not exceed 20%of ‘top overhaul’ hours.

As for Clause 1.4(11) and also drainlub-oil system and refill with fresh oil.

(b) If the aggregate of runninghours exceed 20% of ‘topoverhaul’ hours.

Carry out complete top overhaul inaccordance with maintenanceschedule or alternative approvedinstructions, including oil change.

(18) GasTurbine DrivenGenerating Sets (NES 309)−Before FMT and as lateas possible in the programme, overhaul and restore equipment to ‘as new’condition as follows:

(a) If the aggregate of runninghours does not exceed 10%of ‘major overhaul’ hours.

Carry out all maintenance hoursschedule procedures up to andincluding those prescribed at runninghours approximating to three timesthe logged hours.

(b) If the aggregate of runninghours is between 10% and20% of ‘major overhaul’hours.

As above and drain lub oil system andrefill with fresh oil. Examine and cleanintake demisters, burners andigniters. Examine one combustionchamber for distortion, cracking orcarbon formation. Sight HP turbinesfirst stage blading and recordconditions.

(c) If the aggregate of runninghours exceed 20% of ‘majoroverhaul’ hours.

Carry out complete overhaul as permaintenance schedule or alternativeinstructions including oil change.

(19) Rotating Auxiliary Machinery:

(a) The following are to be carried out on other rotating auxiliarymachinery, except hydraulic units:

(i) Measure weardown of bearings in turbines, gearing andpumps, axial clearances and/or position of turbine rotors andprovide records for the RPO where provision is made formeasurement to be taken without major dismantling andwithout opening up the forced lubricating system or breakingjoints therein.

Page 18: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

1.6

(ii) Examine gearing pinion and wheel teeth.

(iii) Examine and check the tightness on the shaft of the impellerfitted to one of each size or type of axial flow or centrifugalpump.

(iv) Examine all working parts of one equipment of each new type,measure and record as above and take such other records asthe RPO directs for new design auxiliaries not previouslyinstalled in HM Surface Ships.

NOTE: Rotating hydraulic units are only to be opened upwhen performance has been unsatisfactory.

(20) Bilge Pumping Arrangements:

(a) Examine bilge pumping equipment, fittings, mudboxes, etc.

(b) Clean bilges ready for FMT.

(21) Underwater Equipment:

(a) The following are to be carried out at docking immediatelypreceding FMT:

(i) Clean propellers and check blade and hub securingarrangements for tightness.

(ii) Examine typical items of underwater fittings, sea valves, etc.

(iii) Take reading and complete Form D313.

(22) Controllable Pitch Propellers (CPP) System (NES 303):

(a) Examine main system filters.

(b) Examine transfer system filters.

(c) Examine drain tank oil condition.

(d) Take a particle count of a sample of oil taken from each systemsampling point.

Page 19: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

2.1

2. NATIONAL/INTERNATIONAL REGULATIONS

(No relevant information included)

Page 20: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

2.2

Page 21: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

3.1

3. MILITARY STANDARDS/REQUIREMENTS

3.1 Aim

a . Machinery is to be opened up following sea trials for internal inspection:

(1) To confirm satisfactory design, manufacture and ‘fitness for purpose’.

(2) To investigate, if necessary, the cause of any shortcomings inperformanceor unusual trials observations.

NOTE: Routine maintenance and rectification of defects is to be carriedout in conjunction with the examination where appropriate.

3.2 Selection of Machinery for Examination

a . The DLO is to specify the machinery to be examined in each class of ship inaccordance with Section 1.4

3.3 Items to be Examined

a . During the examination of machinery reference is to be made to the NESappropriate to each equipment or system.

Page 22: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

3.2

Page 23: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

4.1

4. DESIGN REQUIREMENTS/GUIDANCE

(No relevant information included)

Page 24: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

4.2

Page 25: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

5.1

5. CORPORATE EXPERIENCE & KNOWLEDGE

(No relevant information included)

Page 26: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

5.2

Page 27: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

ANNEX AA.1

ANNEX A.

RELATED DOCUMENTS

A1. The following documents and publications are referred to in this NES:

JSP 430 MOD Ship Safety Management System Handbook

(*)NES 159 Refrigerating Systems and Air Conditioning Plant

Part 1: Design and Installation

Part 2: Testing

NES 303 Lubricating Oil Systems for Propulsion Generation inHM Surface Ships and Submarines

NES 304 Shafting Systems and Propulsors

Part 2: Design Requirements for Main Propulsion ShaftingAuxiliaries

NES 305 Requirements for Gearing − Main Propulsion

NES 309 Requirements for Gas Turbines (Restricted)

NES 313 Diesel Engines for Marine Propulsion and Auxiliary Machinery

NES 314 Compressed Air Systems (Restricted)

NES 315 Requirements for Air Compressors

NES 319 Requirements for Aviation Fuel Systems in HM Surface Ships(Restricted−Commercial)

NES 320 Requirements for Design and Installation of Fuel Systems for GasTurbines and Diesel Engines in HM Surface Ships(Restricted−Commercial)

NES 325 Boilers for Auxiliary Purposes (Once-through Type)

NES 329 Requirments for Heat Exchangers (Restricted)

(*)NES 332 Requirement of Feed, Steam and Drain System for NuclearSubmarine Propulsion and Generating MachineryPart 1: General Requirements

Part 2: Feed Systems

Part 3: Steam Systems

Part 4: Drain Systems

NES 341 Requirements for Cleaning Components and Equipment for FluidSystems

NES 344 Feed Steam and Drain Systems in Ships fitted with Auxiliary Boilers

(*)NES 349 Depth Dependent Sea Water Systems, Submarines

NES 366 Trials and Inspection of Desalination Machinery

NES 630 Requirements for Main 60 Hz Generators (Restricted)

NES 719 Sea Water Systems for HM Surface Ships

Form D313 Report of Final Inspection

Note: * In course of preparation. Until published, guidance should be sought fromDLO/DME ME235

Page 28: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

ANNEX A A.2

A2. It may also be necessary to refer to:

NES 23 Tests and Trials in New Construction Ships (Excluding NuclearSubmarines)Reference may also be made to the NES appropriate to eachequipment or system under trial.

Page 29: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

ANNEX BB.1

ANNEX B.

ABBREVIATIONS

B1. For the purpose of this NES the following abbreviations apply:

CPP Controllable Pitch Propellers

DLO Defence Logistic Organization

DPA Defence Procurement Agency

CST Contractor’s Sea Trial

FL Forced Lubrication

FMT Final Machinery Trial

HP High Pressure

RPO Resident Project Officer

Page 30: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

ANNEX B B.2

Page 31: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

ANNEX CC.1

ANNEX C.

PROCUREMENT CHECK LIST(No relevant information included)

Page 32: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

ANNEX C C.2

Page 33: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6

September 1999

INDEX 1

ALPHABETICAL INDEX(NOTE: Page numbers are given)

AAdjusting bearings: 1.3

Air compressors, reciprocating: 1.5

Air conditioning machinery: 1.5

Air, steam, fuel and water systems: 1.2

Automatic devices: 1.2

Auxiliary machinery rotating: 1.5

BBearings, main shaft: 1.3

Bilge pumping arrangements: 1.6

Bolts in couplings and shafting: 1.3

Brakes, shaft: 1.3

CClass opening-up list: 1.2

Cleanliness: 1.2

Compressors, air reciprocating: 1.5

Conduct of examination: 1.1

Controllable Pitch Propeller (CPP) system:1.6

Cruising gas turbines: 1.3

DDesalination plant: 1.4

Design: 1.1, 3.1

Diesel driven generating sets: 1.5

Diesel engines, propulsion: 1.3

Distilled-water tanks: 1.2

EExamination, extent: 1.1

FFacilities: 1.1

Forced lubrication systems: 1.2

Fuel, steam, air and water systems: 1.2

Further examination: 1.1

GGas turbine driven generating sets: 1.5

Gas turbines: 1.3

Gearing, propulsion: 1.4

Generating plant: 1.3

Generating sets, diesel-driven: 1.5

Generating sets, gas-turbine driven: 1.5

HHeat exchangers, sea-water: 1.2

Holding down arrangements: 1.3

IItems to be examined: 1.1, 1.2

LLubrication, forced: 1.2

MMachinery to be examined: 1.1, 3.1

Main gas turbines: 1.3

Main shaftbearings: 1.3brakes: 1.3

OOpening-up of machinery: 1.1, 3.1

PPreparation: 1.1

Propulsion diesel engines: 1.3

Propulsion electric motors: 1.4

Propulsion gearing: 1.4

QQuality Assurance Representative—action in

the event of defects: 1.1

Page 34: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

NES 353Issue 6September 1999

INDEX 2

Quality Assurance requirements: 1.1

RReciprocating air compressors: 1.5

Rectification of defects: 1.1, 1.2, 3.1

Refrigerating machinery: 1.5

Report submission: 1.2

Resident Project Officer: 1.1, 1.2, 1.3, 1.4,1.5, 1.6

Rotating auxiliary machinery: 1.5

Routine maintenance: 1.1, 3.1

SShaft bearings: 1.3

Shipbuilders responsibilities: 1.1

Special tools etc: 1.2

Steam generating plant: 1.3

Steam, air, fuel and water systems: 1.2

TThrust bearings: 1.3

Tools and equipment: 1.2

UUnderwater equipment: 1.6

VVerification ofdesign: 1.1, 3.1installation: 1.1, 3.1quality assurance procedures: 1.1

WWater, steam, air, fuel systems: 1.2

Page 35: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

Inside Rear Cover

Page 36: NES 353 Examination of Machinery in HM Surface Ships on Completion of Contractor's Sea Trials

© Crown Copyright 2000

Copying Only as Agreed with DStan

Defence Standards are Published by and Obtainable from:

Defence Procurement AgencyAn Executive Agency of The Ministry of Defence

Directorate of StandardizationKentigern House65 Brown Street

GLASGOW G2 8EX

DStan Helpdesk

Tel 0141 224 2531/2 Fax 0141 224 2503

Internet e-mail [email protected]

File Reference

The DStan file reference relating to work on this standard is D/DStan/69/02/353.

Contract Requirements

When Defence Standards are incorporated into contracts users are responsible for their correctapplication and for complying with contractual and statutory requirements. Compliance witha Defence Standard does not in itself confer immunity from legal obligations.

Revision of Defence Standards

Defence Standards are revised as necessary by up issue or amendment. It is important thatusers of Defence Standards should ascertain that they are in possession of the latest issue oramendment. Information on all Defence Standards is contained in Def Stan 00-00 Standardsfor Defence Part 3 , Index of Standards for Defence Procurement Section 4 ‘Index of DefenceStandards and Defence Specifications’ published annually and supplemented regularly byStandards in Defence News (SID News). Any person who, when making use of a DefenceStandard encounters an inaccuracy or ambiguity is requested to notify the Directorate ofStandardization (DStan) without delay in order that the matter may be investigated andappropriate action taken.