THE NATIONAL BUILDING CODE
OF THEPHILIPPINES (PD 1096)
and its IRR
CHAPTERS III and IVBUILDING PERMIT
TYPES OF CONSTRUCTION
-
8/8/2019 Nbc Chapter III - IV
2/41
BUILDING PERMITBUILDING PERMIT
the written authorization granted by a
building official to an applicant allowing him
to proceed with the constructionof a specificproject after plans, specifications, and other
pertinent documents have been found to be in
conformity with PD 1096 and its IRR
-
8/8/2019 Nbc Chapter III - IV
3/41
ANCILLARY PERMITSANCILLARY PERMITS
permits duly signed and sealed by the
corresponding professionals
the building permit shall be NULL
and VOID ifNOT ACCOMPANIED
by the ANCILLARY PERMITS
the plans and specifications shall besubmitted together with the dulynotarized application for BUILDINGPERMIT
-
8/8/2019 Nbc Chapter III - IV
4/41
ARCHITECTURAL PERMIT
CIVIL/STRUCTURAL PERMIT
ELECTRICAL PERMIT
MECHANICAL PERMIT
SANITARY PERMITPLUMBING PERMIT
ELECTRONICS PERMIT
the following permits will be signed andsealed over printed names by the duly
licensed and registered professional with
respect to their professions
-
8/8/2019 Nbc Chapter III - IV
5/41
ACCESSORY
PERMITS
permits that are issued
by the Building Official
for accessory parts of
the project with very
special functions or use
which are indicated in
the plans andspecifications that
accompany the building
permit application.
bank and records
vaults; swimming
pools; firewallsseparate from the
building/structure;
towers; silos;
smokestacks;chimneys;
commercial/industria
l fixed ovens;
industrial
kilns/furnaces;
water/waste
treatment tanks,
-
8/8/2019 Nbc Chapter III - IV
6/41
ACCESSORY
PERMITS
permits that issued by the
building official for activities
being undertaken prior to or
during the processing of thebuilding permit
ground
preparation and
excavation,
encroachment of
foundation to
public area,fencing, for fence
not exceeding 1.80
meters high,
sidewalkconstruction,
temporary
sidewalk
enclosure and
the coverage is spelled outin the accessory permit form
including the expiry period
-
8/8/2019 Nbc Chapter III - IV
7/41
EXEMPTIONS
sheds, outhouses, greenhouses, children's
playhouses, aviaries, poultry houses, and
the like, not exceeding 6.00 sq. meters in
total area and are completely detached
from any other building and are intended
only for the private use of the owner.
addition of open terraces and patios
resting directly on the ground, not
exceeding 20.00 sq. meters in total floor
area, exclusively for the private use of
1.
2.
MINOR CONSTRUCTIONS
-
8/8/2019 Nbc Chapter III - IV
8/41
installation of window grilles
garden pools for the habitation of water
plants and/or aquarium fish not exceeding
500 millimeters in depth and exclusively
for private use
garden masonry walls other than party
walls not exceeding 1.20 meter in height,foot paths, residential garden walks and/or
driveways
3.
4.
5.
EXEMPTIONS
-
8/8/2019 Nbc Chapter III - IV
9/41
REPAIR WORKS
repair works not affecting or involving
structural member, such as replacement of
deteriorated roofing sheets or tiles,
gutters, downspouts, fascias, ceilingsand/or sidings.repair and/or replacement of non load-
bearing partition walls
repair and/or replacement of any interiorportion or a house not involving
addition or alteration
1.
EXEMPTIONS
-
8/8/2019 Nbc Chapter III - IV
10/41
repair and/or replacement work offlooring
repair ofperimeter fence and walls
repair and/or replacement of plumbing
fixtures, fittings or piping, such as toiletbowls, sinks, lavatories, urinals, bidets,
pipes, faucets, valves for single
detached dwellings and duplexes.
3.
4.
5.
2. repair and/or replacement work of doorsand windows
REPAIR WORKS
EXEMPTIONS
-
8/8/2019 Nbc Chapter III - IV
11/41
APPLICATION FOR PERMITS
any person desiring to obtain a building
permit and any ancillary/accessory permit/s
together with a Building Permit shall file
application/s therefor on the prescribed
application forms
certified true copy of OCT/TCT, on file
with the Registry of Deeds
Tax Declaration
Current Real Property Tax Receipt
1.
2.
3.
If applicant is the registered owner of the lot:
1.
2.
3.
1.
2.
-
8/8/2019 Nbc Chapter III - IV
12/41
In case the applicant is not the registered
owner of the lot:
certified true copy of OCT/TCT, on file
with the Registry of Deeds
Tax Declaration
Current Real Property Tax Receipt
PLUS:
3.
1.
2.
duly notarized copy of the Contract of
Lease, orDeed ofAbsolute Sale
4.
APPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
13/41
five (5) sets ofsurvey plans, design plans,
specifications and other documentsprepared, signed and sealed over the
printed names of the duly licensed and
registered professionals
a. Geodetic Engineer, in case of lot survey
plans;
b. Architect, in case of architectural
documents, in case of architectural
interior/interior design documents,
either an architect or interior designer mayAPPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
14/41
c. Civil Engineer, in case ofcivil/structural
documents;d. Professional Electrical Engineer, in case of
electrical documents;
e. Professional Mechanical Engineer, in case of
mechanical documents;
f.S
anitary Engineer,in case ofsanitarydocuments;
g. Master Plumber, in case ofplumbing
documents; APPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
15/41
clearances from other agencies involved
a. Department of Public Works and
Highways (DPWH)b. Air Transportation Office (ATO)
c. Housing and Land Use Regulatory
Board (HLURB)d. Local Government Unit (LGU)
e. Department of Tourism (DOT)
f. Department of Environment and Natural
Resources (DENR)
g. Department of Transportation and
Communication (DOTC)
h. Department of Interior and LocalAPPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
16/41
i. Philippine Ports Authority (PPA)
j. Department of Education (DepEd)
k. Department of Health (DOH)l. Philippine Institute of Volcanology and
Seismology (PHIVOLCS)
m. Laguna Lake Development Authority
(LLDA)n. Manila Waterworks and Sewerage System
(MWSS)
o. National Water Resources Board (NWRB)p. Department ofAgrarian Reform (DAR)
q. Department ofAgriculture (DA)
r. Department of Labor and Employment
(DOLE) APPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
17/41
A description of work to be
covered by the permit
Description and ownership
of the lot TCT
The use or occupancy of
proposed work
Estimated cost of proposed
workAPPLICATION FOR PERMIT
-
8/8/2019 Nbc Chapter III - IV
18/41
ARCHITECTURAL DOCUMENTS
Vicinity Map/Location Plan
Site Development Plan
PerspectiveFloor Plans [with complete identification of
rooms or functions]
Elevations
Sections
Reflected Ceiling Plan
Schedule of Doors andWindows
Schedules ofFinishes
Details
a. Architectural Plan/Drawings
-
8/8/2019 Nbc Chapter III - IV
19/41
b. Architectural Interiors/Interior Design
Space Plan/s or Layout/s of Architecturalinterior/sArchitectural Interior Perspective/s
Furniture/furnishing/equipment/processlayout/s.Access plan/s, parking plan/sDetail design of major architectural interior
elements.Plan and layout of interior, wall partitions,furnishing, furniture, equipment/appliances
ARCHITECTURAL DOCUMENTS
-
8/8/2019 Nbc Chapter III - IV
20/41
Interior wall elevations showing: finishes,
switches, doors and convenience outlets,
cross window sections with interior
perspective as viewed from the main
entrance at scale of at least 1:100.Floor/ceiling/wall patterns and finishing
details
L
ist of materials usedCost Estimates
ARCHITECTURAL DOCUMENTS
-
8/8/2019 Nbc Chapter III - IV
21/41
c. Plans and specific locations of all
accessibility facilities of scale of at least 1:100
d. Detailed design of all such accessibility
facilities outside and aroundbuildings/structures
including parking areas, and their safety
requirements all at scale of 1:50 or any
convenientscale.
ARCHITECTURAL DOCUMENTS
-
8/8/2019 Nbc Chapter III - IV
22/41
e. Fire Safety Documents
Layout plan of each floor indicating all the
necessary fire-fighting equipment and fire
exits
Details of windows, fire exits with grilledwindows and ladders
Details of fire resistive construction of
enclosures for vertical openings
f. Other related documents
ARCHITECTURAL DOCUMENTS
-
8/8/2019 Nbc Chapter III - IV
23/41
-
8/8/2019 Nbc Chapter III - IV
24/41
verifies lot plan
check compliance to establish easement
determines grades
Verifies that atleast one side of the
lot has direct access to a street or alley
types of construction
req. ofFire Zones and Fire
Resistive Regulation
building projection over public st
access streets/roads and alleys
architectural and interior design
classifications and general req.maximum heightparking and loading/unloading s
corner buildings with chaflan
occupant load
glazing of opening
architectural accessibility fe
light and ventilation
construction of buildings/stru
buildings and other ancillary
structures within
cemeteries and memorial p
general design and
construction req.structural design req.
excavation,foundations,
retaining wallsprefab construction
protection and safety
requirementsabatement/demolition
plastics
signs
evaluates
building/structure
documents as to
compliance to thetechnical
requirements for
E
lectricalR
egulations
evaluates
building/structure
documents as tocompliance to the
technical
requirements for
Mechanical
Regulations
evaluates
building/structuredocuments as to
compliance to the
technicalrequirements under
the Sanitary
Engineering Law (RA
1364)
evaluatesbuilding/structure
documents as to
compliance to thetechnical
requirements under
the Plumbing Law
(RA1378)
evaluates
building/structure
documents as tocompliance to the
technical
requirements
-
8/8/2019 Nbc Chapter III - IV
25/41
ISSUANCE OF BUILDING
PERMITS
15 days upon payment
The Building Official may issue a permit forthe construction of only a part or portionof a building/structure whenever the plansand specifications submitted togetherwith the application do not cover theentire building/structure.
-
8/8/2019 Nbc Chapter III - IV
26/41
TERMS AND CONDITIONSOF PERMITS
Article 1723 of the Civil Code
architect-of-record
engineer in charge ofthe structural plan
liable for any damageswithin 15 years from
the completion of thebuilding/structure
architect-in-charge ofconstruction
engineer in charge of the
construction supervision
liable to any defects in
the plans orspecifications ordefects in the groundshould the building
collapse TERMS AND CONDITIONS OF APERMIT
-
8/8/2019 Nbc Chapter III - IV
27/41
the permit shall be accompanied by thevarious applicable ancillary and accessory
permits, plans and specifications signedand sealed by the corresponding designprofessionals in compliance with the code
and its irr and to all applicable referralcodes and professional regulatory laws
that the proposed construction/ erection/
addition/ alteration/ renovation/conversion/ repair/ moving/ demolition,etc. shall be in conformity with the provisions
of the Code and its IRRTERMS AND CONDITIONS OF APERMIT
-
8/8/2019 Nbc Chapter III - IV
28/41
no building/structure shall be used until the
Building Official has issued a Certificate of
Occupancypartial Certificate of Occupancy - for theuse/occupancy of a portion/s of a building
prior to the completion of the entire building
this permit shall not serve as anexemption from securing writtenclearances from various governmentauthorities exercising regulatory functionaffecting buildings/structures
TERMS AND CONDITIONS OF APERMIT
-
8/8/2019 Nbc Chapter III - IV
29/41
Only licensed and registered contractor
may undertake construction contracts
Contractor's License Law (RA 4566)
TERMS AND CONDITIONS OF APERMIT
Notice of Construction shall be submitted by
the owner/permittee to the building officialprior to any construction activity
A Building Permit Sign shall be displayed atthe premises of the construction site for thewhole duration of the project
fees for the permit shall be based on the floor
area of the project on its category, and on acommon fixed construction cost per sq.m
-
8/8/2019 Nbc Chapter III - IV
30/41
-
8/8/2019 Nbc Chapter III - IV
31/41
-
8/8/2019 Nbc Chapter III - IV
32/41
VALIDITY OF A BUILDING PERMIT
NULL and VOID
building or work authorized is
not commenced within one (1)year after issuance
suspended or abandoned atanytime after it has commencedfor a period of 120 days
-
8/8/2019 Nbc Chapter III - IV
33/41
NON-ISSUANCE, SUSPENSIONAND REVOCATION
1.Errors found in plans and specifications
2.Incorrect or inaccurate data supplied
3.Non-compliance with the provisions of the
Code4.Unauthorized change in plans & specifications5.Failure to hire an architect or engineer to
inspect during construction & to keep logbookNotice of non- issuance, suspension or
revocation of building permits shall
always be made in writing, stating the
-
8/8/2019 Nbc Chapter III - IV
34/41
APPEAL
filing of an appeal shall be within 15 daysfrom the date of advice of the non-issuance,suspension, revocation of permits
INSPECTION AND SUPERVISIONOF WORK
Licensed architect or civil engineer
full time
inspection and
supervision of the
construction work
submit the
logbook, duly
signed and sealed,
to the Buildin
-
8/8/2019 Nbc Chapter III - IV
35/41
CERTIFICATE OF OCCUPANCY
The building official issues the Certificate ofOccupancy 30 days AFTER final inspectionand submittal of Certificate of Completion
partial Certificate of Occupancy may beissued for the use or occupancy of a portion
or portions of a building or structure prior tothe completion of the entire building orstructure
-
8/8/2019 Nbc Chapter III - IV
36/41
Final inspection
Building OfficialChief of the Local
Fire Service (CLFS)Issues the Fire Safety
Inspection Certificate
Issues the
Certificate of
Occupancy
Environmental
ManagementBureau
(of the DENR, formerly NPCC)
in case of industrial
buildings, a certificatefrom this agency is
also required
-
8/8/2019 Nbc Chapter III - IV
37/41
TYPES OF CONSTRUCTION
Type I Wood ConstructionType II Wood Construction w/ fireresistant materials (1 hour fire resistive)Type III Masonry & Wood Const. (1 hour
fire resistive)Type IV Steel, Iron, Concrete orMasonry Construction
Type V 4 hour Fire Resistiveno change shall be made in the type of
construction of any building unless the
change is approved by the Building Official
-
8/8/2019 Nbc Chapter III - IV
38/41
REQUIREMENTS ON TYPESOF CONSTRUCTION
A. FIRE RESISTIVE REQUIREMENTS
II IIIexterior bearings;
non-bearing walls1-hour fire resistive
construction4-hour fire resistive
construction
IV VTYPE
1-hour fire resistiveConstruction
3-hr fireresistive
interior bearings;partitions; roofs
1-hour fire resistiverating
2-hr fireresistive
3-hr fireresistive
structuralframing
exterior doorsand windows
1-hour fire resistiverating
-
8/8/2019 Nbc Chapter III - IV
39/41
B. INTERIOR WALL AND CEILING FINISHES
finishes of interior walls and ceilings shall beclassified according to their flame spreadcharacteristic using generally accepted
engineering standards
exemption: materials which areless than 1.00 millimeters in
thickness cemented to the surfaceof walls or ceilings
REQUIREMENTS ON TYPES OF CONSTRUCTION
-
8/8/2019 Nbc Chapter III - IV
40/41
materials requiring to be flame-spread proof
shall be treated with a flame retardanthaving a flame-spread of fifty (50) or less asdetermined by the Tunnel Test
C. Standards used for materials in structuralframework, exterior walls and openings,floors, exits, stairs and roofs, shall begoverned by the pertinent provisions of theFire Code of the Philippines
REQUIREMENTS ON TYPES OF CONSTRUCTION
-
8/8/2019 Nbc Chapter III - IV
41/41
THE END