![Page 1: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/1.jpg)
1
Natural & Central Region Customer Group
July 13, 2016
![Page 2: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/2.jpg)
2
NGPL Maintenance Summary
Maintenance Project Start Date Finish Date SEG / PIN Impacted
A#3 Install Launcher/Receiver 12-Jul-16 21-Jul-16 Segment 13
M/M Pipe Maintenance 14-Jul-16 20-Jul-16 PIN 900975
M/M Pipe Maintenance 21-Jul-16 27-Jul-16 PIN 3414
M/M Pipe Maintenance 28-Jul-16 3-Aug-16 PIN 900964
M/M Pipe Maintenance 4-Aug-16 10-Aug-16 PIN 901225
M/M Pipe Maintenance 11-Aug-16 17-Aug-16 PIN 901217
PIN Maintenance 15-Aug-16 20-Aug-16 PIN 901225
![Page 3: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/3.jpg)
3
NGPL Upcoming Maintenance
SEGMENT 13 – AMARILLO #3 (CS 198/109) – INSTALL LAUNCHER AND RECEIVER – REMINDER
Natural will be performing maintenance work to install a Launcher and Receiver between Compressor Station 198 located in Marion
County, Iowa and Compressor Station 109 located in Keokuk County, Iowa (Segment 13 of Natural’s Amarillo Mainline). This
maintenance work will be performed in three phases, with the scheduling impact during each phase explained in more detail below. For
purposes of scheduling, the constraint will be at Compressor Station 198 located in Marion County, Iowa. Any gas received upstream of
Compressor Station 198 for delivery downstream of Compressor Station 198 will be impacted for the duration of this outage. In addition,
the Amarillo Mainline Pool (PIN 10566) is located south (upstream) of the constraint. Firm Transport Services (FTS) pathed on the
Amarillo mainline which is utilized for storage injections will be impacted. However, such FTS utilized for storage withdrawals will not be
impacted.
PHASE 1 (Phase 1 completed)
PHASE 2
Phase 2 will begin on gas day Tuesday, July 12, 2016, and continue through gas day Thursday, July 21, 2016. During this phase,
Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 60% of contract MDQ. Actual nomination
levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent days.
Secondary out-of-path Firm and AOR/ITS transports will not be available for the duration of Phase 2.
PHASE 3
Phase 3 will begin on gas day Friday, July 22, 2016, and continue through gas day Monday, July 25, 2016. During this phase, no impact
to any transport services is anticipated. All transport services, including Primary, Secondary in-path, Secondary out-of-path and
AOR/ITS will be available.
The Northern Border Pipeline (PIN 908090) receipt point is not affected and will be available as an alternative for the duration of this
outage.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 4: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/4.jpg)
4
NGPL Upcoming Maintenance
SEGMENT 3 - M&M LINE (CS 156) – PIPELINE MAINTENANCE – UPDATE #2
On gas day Thursday, July 14, 2016, and continuing through gas day Wednesday, July
20, 2016 (previously Monday, June 27, 2016 thru Saturday, July 2, 2016), Natural will be
performing pipeline maintenance on the M&M Line near Compressor Station 156 located in
Kiowa County, Oklahoma (Segment 3 of Natural’s Midcontinent Zone). The following location
will be shut in for the duration of this outage.
PIN 900975 CEM Rogers #1-2 Washita
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 5: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/5.jpg)
5
NGPL Upcoming Maintenance
SEGMENT 3 - M&M LINE (CS 156) – PIPELINE MAINTENANCE – UPDATE #2
On gas day Thursday, July 21, 2016, and continuing through gas day Wednesday, July
27, 2016, (previously Tuesday, July 5, 2016 thru Sunday, July 10, 2016), Natural will be
performing pipeline maintenance on the M&M Line near Compressor Station 156 located in
Kiowa County, Oklahoma (Segment 3 of Natural’s Midcontinent Zone). The following location
will be shut in for the duration of this outage.
PIN 3414 Linn Newcomb Custer
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 6: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/6.jpg)
6
NGPL Upcoming Maintenance
SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #2
On gas day Thursday, July 28, 2016, and continuing through gas day Wednesday,
August 3, 2016, (previously Monday, July 18, 2016 thru Saturday, July 23, 2016), Natural
will be performing pipeline maintenance on the M&M Line near Compressor Station 159
located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone). The
following location will be shut in for the duration of this outage.
PIN 900964 Kaiser Young #1 Woodward
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 7: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/7.jpg)
7
NGPL Upcoming Maintenance
SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #2
On gas day Thursday, August 4, 2016, and continuing through gas day Wednesday,
August 10, 2016, (previously Monday, July 25, 2016 thru Saturday, July 30, 2016),
Natural will be performing pipeline maintenance on the M&M Line near Compressor Station
159 located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone).
The following location will be shut in for the duration of this outage.
PIN 901225 Bell Kinley Ruttman #1-12 Wood
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 8: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/8.jpg)
8
NGPL Upcoming Maintenance
SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #1
On gas day Thursday, August 11, 2016, and continuing through gas day Wednesday,
August 17, 2016, (previously Monday, August 1, 2016 thru Saturday, August 6, 2016),
Natural will be performing pipeline maintenance on the M&M Line near Compressor Station
159 located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone).
The following location will be shut in for the duration of this outage.
PIN 901217 Berexco Cal-Ray #1 Harper
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 9: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/9.jpg)
9
NGPL Upcoming Maintenance
SEGMENT 4 - M&M LINE (CS 159) – METER MAINTENANCE – UPDATE #1
On gas day Monday, August 15, 2016, and continuing through gas day Saturday, August
20, 2016, (previously Monday, July 18, 2016 thru Saturday, July 23, 2016), Natural will be
installing a meter on the M&M Line near Compressor Station 159 located in Woodward
County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone). The following location will be
shut in for the duration of this outage.
PIN 901225 Bell Kinley Ruttman #1-12 Wood
Other than the location listed above, Natural does not anticipate that this work will impact
shippers.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 10: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/10.jpg)
10
MEP Maintenance Summary
Maintenance Project Start Date Finish Date SEG / PIN Impacted
ILI Cleaning Tool Run 3-Aug-16 4-Aug-16 SEG 120 / 200
ILI Cleaning Tool Run 24-Aug-16 25-Aug-16 SEG 120 / 200
![Page 11: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/11.jpg)
11
MEP Upcoming Maintenance
SEGMENTS 120/200 - ILI CLEANING TOOL RUN – (ZONE 1/ZONE 2)
MEP will be performing an ILI Cleaning tool run on the entire 42” mainline of MEP’s pipeline system. This
work will require MEP to restrict throughput capacity in Zone 1 and Zone 2 of its system.
As such, for gas day Wednesday, August 3, 2016, and continuing through gas day Thursday, August
4, 2016, MEP will be scheduling Primary Firm and Secondary-in-path Firm transports to a reduced level
through Segment 120, MEP 2 Atlanta, in Cass County, Texas, to a minimum percentage of 42% for each
contract with primary or secondary in-path firm rights through Segment 120, assuming all such contracts are
nominated at full applicable contract MDQ through the constrained segment. All deliveries downstream of
the constraint in Zone 1 will be impacted, including deliveries in Zone 2.
In addition to the Segment 120 restriction detailed above, for gas day Wednesday, August 3, 2016, and
continuing through gas day Thursday, August 4, 2016, MEP will be scheduling Primary Firm and
Secondary-in-path Firm transports to a reduced level through Segment 200, MEP 4 Vicksburg, in Hinds
County, Mississippi, to a minimum percentage of 75% for each contract with primary or secondary in-path
firm rights through Segment 200, assuming all such contracts are nominated at full applicable contract MDQ
through the constrained segment. All deliveries in Zone 2 will be impacted.
The actual scheduling percentage will depend on the level of nominations received during this outage.
AOR/ITS and Secondary out-of-path Firm transports will not be available. Additionally, all park and loan
transactions under Rate Schedule PALS will not be available during this outage.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 12: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/12.jpg)
12
MEP Upcoming Maintenance
SEGMENTS 120/200 - ILI CLEANING TOOL RUN (ZONE 1/ZONE 2)
MEP will be performing an ILI Cleaning tool run on the entire 36” mainline of MEP’s pipeline system. This
work will require MEP to restrict throughput capacity in Zone 1 and Zone 2 of its system.
As such, for gas day Wednesday, August 24, 2016, and continuing through gas day Thursday, August
25, 2016, MEP will be scheduling Primary Firm and Secondary-in-path Firm transports to a reduced level
through Segment 120, MEP 2 Atlanta, in Cass County, Texas, to a minimum percentage of 67% for each
contract with primary or secondary in-path firm rights through Segment 120, assuming all such contracts are
nominated at full applicable contract MDQ through the constrained segment. All deliveries downstream of
the constraint in Zone 1 will be impacted, including deliveries in Zone 2.
In addition to the Segment 120 restriction detailed above, for gas day Wednesday, August 24, 2016, and
continuing through gas day Thursday, August 25, 2016, MEP will be scheduling Primary Firm and
Secondary-in-path Firm transports to a reduced level through Segment 200, MEP 4 Vicksburg, in Hinds
County, Mississippi, to a minimum percentage of 44% for each contract with primary or secondary in-path
firm rights through Segment 200, assuming all such contracts are nominated at full applicable contract MDQ
through the constrained segment. All deliveries in Zone 2 will be impacted.
The actual scheduling percentage will depend on the level of nominations received during this outage.
AOR/ITS and Secondary out-of-path Firm transports will not be available. Additionally, all park and loan
transactions under Rate Schedule PALS will not be available during this outage.
Please contact your Account Director or Scheduling Representative if you have any questions.
![Page 13: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/13.jpg)
13
Customer Questions
What are scheduling priorities and how do they effect a contract in scheduling?
Why important:
Knowing what your contractual rights are through a constraint in a segment or at a location. Helps determine if you may be cut during a constraint.
Answer:
Priority rights of a contract are determined by looking at the primary path of the contract. Path starts with the Primary receipt location and ends at the Primary delivery location. These rights are then applied to the spot or location of the constraint for scheduling purposes.
![Page 14: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/14.jpg)
14
Scheduling Priority / Segment
FTS KT with LOC 2 as Primary REC and LOC 3 as Primary DEL
LOC 1
REC
LOC 2
REC
LOC 3
DEL
LOC 4
DEL
Constraint
Example 1: Nom from LOC 2 to LOC 3 – Priority through the constraint is PRIMARY (Up to MDQ)
Example 2: Nom from LOC 1 to LOC 3 or LOC 4 - Priority through the constraint is PRIMARY (Up to MDQ)
Given the “primary path” of this contract and the location of the constraint the contract would always schedule
as primary in the segment.
SEG 1 SEG 2
SEG 3
![Page 15: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/15.jpg)
15
Scheduling Priority / Segment
FTS KT with LOC 2 as Primary REC and LOC 3 as Primary DEL
LOC 1
REC
LOC 2
REC
LOC 3
DEL
LOC 4
DEL
Constraint
Example 1: Nom from LOC 2 to LOC 3 – Does not go through the constraint – not impacted.
Example 2: Nom from LOC 2 to LOC 4 - Priority through the constraint is Secondary Out-of-Path (SOP)
Given the “primary path” of this contract and the location of the constraint the contract would always schedule
as SOP.
SEG 1 SEG 2 SEG 3
![Page 16: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/16.jpg)
16
Scheduling Priority / Location
FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL
LOC 1
REC
LOC 2
REC
LOC 3
DEL
LOC 4
DEL
Constraint
If contract is nominated at LOC 3 it will schedule as Secondary In-Path for any constraint at the location.
Reason: LOC 3 is in the primary path of the contract.
SEG 1 SEG 2 SEG 3
![Page 17: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/17.jpg)
17
Scheduling Priority / Location
FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL
LOC 1
REC
LOC 2
REC
LOC 3
DEL
LOC 4
DEL
Constraint
If contract is nominated at LOC 1 it will schedule as Secondary Out-of-Path for any constraint at the location.
Reason: LOC 1 is outside of the primary path of the contract.
SEG 1 SEG 2 SEG 3
![Page 18: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/18.jpg)
18
Scheduling Priority / Location
FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL
LOC 1
REC
LOC 2
REC
LOC 3
DEL
LOC 4
DEL
Constraint
If contract is nominated at either LOC 2 or 4, it will schedule as Primary for any constraint at the location.
Reason: LOC 2 and 4 are the primary points for the contract.
Constraint
SEG 1 SEG 2 SEG 3
![Page 19: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/19.jpg)
19
Customer Questions
Is there a DART window that will show what a contracts priority will be through a segment or at a location constraint?
Answer
No, currently there is no DART window reflecting this information for the C. Region pipes.
We are working with our IT group on getting this window developed.
Alternate Solution
Contact your DSR for assistance. For any upcoming maintenance or FMJ outage your DSR can determine what a particular contract rights will be for the constraint.
![Page 20: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/20.jpg)
20
Customer Questions
Why does the print copy of the MDQ Utilization/Overrun Analysis not match the contract order shown in DART? Also, can the print size be adjusted to make the grid easier to read?
Answer:
This issue has been turned into IT for resolution.
![Page 21: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/21.jpg)
21
Customer Questions
In the Informational Postings on the EBB why is there no “hour glass” to let you know it is working? Also, while waiting for Informational Postings to be retrieved if I move my cursor it drags the screen. Only solution to making it stop is to close tab and start over.
Answers:
We plan to add an hourglass in the future.
The screen drag issue is new and will require some testing to recreate.
Has anyone else experienced this issue?
![Page 22: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/22.jpg)
22
Did you Know? Presented by Linda Moore
Shippers can see not only their nominated and scheduled quantities at locations but also the counter party nominated
and scheduled quantities as well any associated cut code.
Starting from the “Scheduled Quantity” window you can get the details for any of the locations by highlighting the
location and doing one of the following:
Double click on the row
Click the “Sched Qty Ship Matrix” box at the top left of the Scheduled Quantity window
Right click on highlighted location and select “Sched Qty Ship Matrix”
![Page 23: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/23.jpg)
23
Did you Know? Presented by Linda Moore
Shippers can always see their detailed information at a location from the Sched Qty Ship
Matrix.
![Page 24: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/24.jpg)
24
Did you Know? Presented by Linda Moore
If the shipper would also like to see their counter party nomination and scheduled quantity information they
can do so by clicking on the “Expanded View” option in the Layout options box in the top right of the DART
window.
The counter party information shown (in the far right columns) is:
![Page 25: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/25.jpg)
25
Did you Know? Presented by Linda Moore
Schedule Quantity Window Tips
By clicking on the column headers you can resort the order.
If you double click on the RR column it will pull the shippers cut codes to the top.
If you hover your cursor over the cut code a pop up box will appear with description of code.
Use a single day date range when checking current activity or a particular cycle for issues.
Multi day range queries will only pull ID3 data
![Page 26: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/26.jpg)
26
Open Lines
Customer
Questions / Suggestions
![Page 27: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,](https://reader033.vdocuments.us/reader033/viewer/2022050200/5f542f2cdf9f5877f535e436/html5/thumbnails/27.jpg)
27