Page 1: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

1

Natural & Central Region Customer Group

July 13, 2016

Page 2: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

2

NGPL Maintenance Summary

Maintenance Project Start Date Finish Date SEG / PIN Impacted

A#3 Install Launcher/Receiver 12-Jul-16 21-Jul-16 Segment 13

M/M Pipe Maintenance 14-Jul-16 20-Jul-16 PIN 900975

M/M Pipe Maintenance 21-Jul-16 27-Jul-16 PIN 3414

M/M Pipe Maintenance 28-Jul-16 3-Aug-16 PIN 900964

M/M Pipe Maintenance 4-Aug-16 10-Aug-16 PIN 901225

M/M Pipe Maintenance 11-Aug-16 17-Aug-16 PIN 901217

PIN Maintenance 15-Aug-16 20-Aug-16 PIN 901225

Page 3: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

3

NGPL Upcoming Maintenance

SEGMENT 13 – AMARILLO #3 (CS 198/109) – INSTALL LAUNCHER AND RECEIVER – REMINDER

Natural will be performing maintenance work to install a Launcher and Receiver between Compressor Station 198 located in Marion

County, Iowa and Compressor Station 109 located in Keokuk County, Iowa (Segment 13 of Natural’s Amarillo Mainline). This

maintenance work will be performed in three phases, with the scheduling impact during each phase explained in more detail below. For

purposes of scheduling, the constraint will be at Compressor Station 198 located in Marion County, Iowa. Any gas received upstream of

Compressor Station 198 for delivery downstream of Compressor Station 198 will be impacted for the duration of this outage. In addition,

the Amarillo Mainline Pool (PIN 10566) is located south (upstream) of the constraint. Firm Transport Services (FTS) pathed on the

Amarillo mainline which is utilized for storage injections will be impacted. However, such FTS utilized for storage withdrawals will not be

impacted.

PHASE 1 (Phase 1 completed)

PHASE 2

Phase 2 will begin on gas day Tuesday, July 12, 2016, and continue through gas day Thursday, July 21, 2016. During this phase,

Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 60% of contract MDQ. Actual nomination

levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent days.

Secondary out-of-path Firm and AOR/ITS transports will not be available for the duration of Phase 2.

PHASE 3

Phase 3 will begin on gas day Friday, July 22, 2016, and continue through gas day Monday, July 25, 2016. During this phase, no impact

to any transport services is anticipated. All transport services, including Primary, Secondary in-path, Secondary out-of-path and

AOR/ITS will be available.

The Northern Border Pipeline (PIN 908090) receipt point is not affected and will be available as an alternative for the duration of this

outage.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 4: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

4

NGPL Upcoming Maintenance

SEGMENT 3 - M&M LINE (CS 156) – PIPELINE MAINTENANCE – UPDATE #2

On gas day Thursday, July 14, 2016, and continuing through gas day Wednesday, July

20, 2016 (previously Monday, June 27, 2016 thru Saturday, July 2, 2016), Natural will be

performing pipeline maintenance on the M&M Line near Compressor Station 156 located in

Kiowa County, Oklahoma (Segment 3 of Natural’s Midcontinent Zone). The following location

will be shut in for the duration of this outage.

PIN 900975 CEM Rogers #1-2 Washita

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 5: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

5

NGPL Upcoming Maintenance

SEGMENT 3 - M&M LINE (CS 156) – PIPELINE MAINTENANCE – UPDATE #2

On gas day Thursday, July 21, 2016, and continuing through gas day Wednesday, July

27, 2016, (previously Tuesday, July 5, 2016 thru Sunday, July 10, 2016), Natural will be

performing pipeline maintenance on the M&M Line near Compressor Station 156 located in

Kiowa County, Oklahoma (Segment 3 of Natural’s Midcontinent Zone). The following location

will be shut in for the duration of this outage.

PIN 3414 Linn Newcomb Custer

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 6: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

6

NGPL Upcoming Maintenance

SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #2

On gas day Thursday, July 28, 2016, and continuing through gas day Wednesday,

August 3, 2016, (previously Monday, July 18, 2016 thru Saturday, July 23, 2016), Natural

will be performing pipeline maintenance on the M&M Line near Compressor Station 159

located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone). The

following location will be shut in for the duration of this outage.

PIN 900964 Kaiser Young #1 Woodward

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 7: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

7

NGPL Upcoming Maintenance

SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #2

On gas day Thursday, August 4, 2016, and continuing through gas day Wednesday,

August 10, 2016, (previously Monday, July 25, 2016 thru Saturday, July 30, 2016),

Natural will be performing pipeline maintenance on the M&M Line near Compressor Station

159 located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone).

The following location will be shut in for the duration of this outage.

PIN 901225 Bell Kinley Ruttman #1-12 Wood

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 8: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

8

NGPL Upcoming Maintenance

SEGMENT 4 - M&M LINE (CS 159) – PIPELINE MAINTENANCE – UPDATE #1

On gas day Thursday, August 11, 2016, and continuing through gas day Wednesday,

August 17, 2016, (previously Monday, August 1, 2016 thru Saturday, August 6, 2016),

Natural will be performing pipeline maintenance on the M&M Line near Compressor Station

159 located in Woodward County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone).

The following location will be shut in for the duration of this outage.

PIN 901217 Berexco Cal-Ray #1 Harper

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 9: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

9

NGPL Upcoming Maintenance

SEGMENT 4 - M&M LINE (CS 159) – METER MAINTENANCE – UPDATE #1

On gas day Monday, August 15, 2016, and continuing through gas day Saturday, August

20, 2016, (previously Monday, July 18, 2016 thru Saturday, July 23, 2016), Natural will be

installing a meter on the M&M Line near Compressor Station 159 located in Woodward

County, Oklahoma (Segment 4 of Natural’s Midcontinent Zone). The following location will be

shut in for the duration of this outage.

PIN 901225 Bell Kinley Ruttman #1-12 Wood

Other than the location listed above, Natural does not anticipate that this work will impact

shippers.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 10: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

10

MEP Maintenance Summary

Maintenance Project Start Date Finish Date SEG / PIN Impacted

ILI Cleaning Tool Run 3-Aug-16 4-Aug-16 SEG 120 / 200

ILI Cleaning Tool Run 24-Aug-16 25-Aug-16 SEG 120 / 200

Page 11: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

11

MEP Upcoming Maintenance

SEGMENTS 120/200 - ILI CLEANING TOOL RUN – (ZONE 1/ZONE 2)

MEP will be performing an ILI Cleaning tool run on the entire 42” mainline of MEP’s pipeline system. This

work will require MEP to restrict throughput capacity in Zone 1 and Zone 2 of its system.

As such, for gas day Wednesday, August 3, 2016, and continuing through gas day Thursday, August

4, 2016, MEP will be scheduling Primary Firm and Secondary-in-path Firm transports to a reduced level

through Segment 120, MEP 2 Atlanta, in Cass County, Texas, to a minimum percentage of 42% for each

contract with primary or secondary in-path firm rights through Segment 120, assuming all such contracts are

nominated at full applicable contract MDQ through the constrained segment. All deliveries downstream of

the constraint in Zone 1 will be impacted, including deliveries in Zone 2.

In addition to the Segment 120 restriction detailed above, for gas day Wednesday, August 3, 2016, and

continuing through gas day Thursday, August 4, 2016, MEP will be scheduling Primary Firm and

Secondary-in-path Firm transports to a reduced level through Segment 200, MEP 4 Vicksburg, in Hinds

County, Mississippi, to a minimum percentage of 75% for each contract with primary or secondary in-path

firm rights through Segment 200, assuming all such contracts are nominated at full applicable contract MDQ

through the constrained segment. All deliveries in Zone 2 will be impacted.

The actual scheduling percentage will depend on the level of nominations received during this outage.

AOR/ITS and Secondary out-of-path Firm transports will not be available. Additionally, all park and loan

transactions under Rate Schedule PALS will not be available during this outage.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 12: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

12

MEP Upcoming Maintenance

SEGMENTS 120/200 - ILI CLEANING TOOL RUN (ZONE 1/ZONE 2)

MEP will be performing an ILI Cleaning tool run on the entire 36” mainline of MEP’s pipeline system. This

work will require MEP to restrict throughput capacity in Zone 1 and Zone 2 of its system.

As such, for gas day Wednesday, August 24, 2016, and continuing through gas day Thursday, August

25, 2016, MEP will be scheduling Primary Firm and Secondary-in-path Firm transports to a reduced level

through Segment 120, MEP 2 Atlanta, in Cass County, Texas, to a minimum percentage of 67% for each

contract with primary or secondary in-path firm rights through Segment 120, assuming all such contracts are

nominated at full applicable contract MDQ through the constrained segment. All deliveries downstream of

the constraint in Zone 1 will be impacted, including deliveries in Zone 2.

In addition to the Segment 120 restriction detailed above, for gas day Wednesday, August 24, 2016, and

continuing through gas day Thursday, August 25, 2016, MEP will be scheduling Primary Firm and

Secondary-in-path Firm transports to a reduced level through Segment 200, MEP 4 Vicksburg, in Hinds

County, Mississippi, to a minimum percentage of 44% for each contract with primary or secondary in-path

firm rights through Segment 200, assuming all such contracts are nominated at full applicable contract MDQ

through the constrained segment. All deliveries in Zone 2 will be impacted.

The actual scheduling percentage will depend on the level of nominations received during this outage.

AOR/ITS and Secondary out-of-path Firm transports will not be available. Additionally, all park and loan

transactions under Rate Schedule PALS will not be available during this outage.

Please contact your Account Director or Scheduling Representative if you have any questions.

Page 13: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

13

Customer Questions

What are scheduling priorities and how do they effect a contract in scheduling?

Why important:

Knowing what your contractual rights are through a constraint in a segment or at a location. Helps determine if you may be cut during a constraint.

Answer:

Priority rights of a contract are determined by looking at the primary path of the contract. Path starts with the Primary receipt location and ends at the Primary delivery location. These rights are then applied to the spot or location of the constraint for scheduling purposes.

Page 14: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

14

Scheduling Priority / Segment

FTS KT with LOC 2 as Primary REC and LOC 3 as Primary DEL

LOC 1

REC

LOC 2

REC

LOC 3

DEL

LOC 4

DEL

Constraint

Example 1: Nom from LOC 2 to LOC 3 – Priority through the constraint is PRIMARY (Up to MDQ)

Example 2: Nom from LOC 1 to LOC 3 or LOC 4 - Priority through the constraint is PRIMARY (Up to MDQ)

Given the “primary path” of this contract and the location of the constraint the contract would always schedule

as primary in the segment.

SEG 1 SEG 2

SEG 3

Page 15: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

15

Scheduling Priority / Segment

FTS KT with LOC 2 as Primary REC and LOC 3 as Primary DEL

LOC 1

REC

LOC 2

REC

LOC 3

DEL

LOC 4

DEL

Constraint

Example 1: Nom from LOC 2 to LOC 3 – Does not go through the constraint – not impacted.

Example 2: Nom from LOC 2 to LOC 4 - Priority through the constraint is Secondary Out-of-Path (SOP)

Given the “primary path” of this contract and the location of the constraint the contract would always schedule

as SOP.

SEG 1 SEG 2 SEG 3

Page 16: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

16

Scheduling Priority / Location

FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL

LOC 1

REC

LOC 2

REC

LOC 3

DEL

LOC 4

DEL

Constraint

If contract is nominated at LOC 3 it will schedule as Secondary In-Path for any constraint at the location.

Reason: LOC 3 is in the primary path of the contract.

SEG 1 SEG 2 SEG 3

Page 17: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

17

Scheduling Priority / Location

FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL

LOC 1

REC

LOC 2

REC

LOC 3

DEL

LOC 4

DEL

Constraint

If contract is nominated at LOC 1 it will schedule as Secondary Out-of-Path for any constraint at the location.

Reason: LOC 1 is outside of the primary path of the contract.

SEG 1 SEG 2 SEG 3

Page 18: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

18

Scheduling Priority / Location

FTS KT with LOC 2 as Primary REC and LOC 4 as Primary DEL

LOC 1

REC

LOC 2

REC

LOC 3

DEL

LOC 4

DEL

Constraint

If contract is nominated at either LOC 2 or 4, it will schedule as Primary for any constraint at the location.

Reason: LOC 2 and 4 are the primary points for the contract.

Constraint

SEG 1 SEG 2 SEG 3

Page 19: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

19

Customer Questions

Is there a DART window that will show what a contracts priority will be through a segment or at a location constraint?

Answer

No, currently there is no DART window reflecting this information for the C. Region pipes.

We are working with our IT group on getting this window developed.

Alternate Solution

Contact your DSR for assistance. For any upcoming maintenance or FMJ outage your DSR can determine what a particular contract rights will be for the constraint.

Page 20: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

20

Customer Questions

Why does the print copy of the MDQ Utilization/Overrun Analysis not match the contract order shown in DART? Also, can the print size be adjusted to make the grid easier to read?

Answer:

This issue has been turned into IT for resolution.

Page 21: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

21

Customer Questions

In the Informational Postings on the EBB why is there no “hour glass” to let you know it is working? Also, while waiting for Informational Postings to be retrieved if I move my cursor it drags the screen. Only solution to making it stop is to close tab and start over.

Answers:

We plan to add an hourglass in the future.

The screen drag issue is new and will require some testing to recreate.

Has anyone else experienced this issue?

Page 22: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

22

Did you Know? Presented by Linda Moore

Shippers can see not only their nominated and scheduled quantities at locations but also the counter party nominated

and scheduled quantities as well any associated cut code.

Starting from the “Scheduled Quantity” window you can get the details for any of the locations by highlighting the

location and doing one of the following:

Double click on the row

Click the “Sched Qty Ship Matrix” box at the top left of the Scheduled Quantity window

Right click on highlighted location and select “Sched Qty Ship Matrix”

Page 23: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

23

Did you Know? Presented by Linda Moore

Shippers can always see their detailed information at a location from the Sched Qty Ship

Matrix.

Page 24: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

24

Did you Know? Presented by Linda Moore

If the shipper would also like to see their counter party nomination and scheduled quantity information they

can do so by clicking on the “Expanded View” option in the Layout options box in the top right of the DART

window.

The counter party information shown (in the far right columns) is:

Page 25: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

25

Did you Know? Presented by Linda Moore

Schedule Quantity Window Tips

By clicking on the column headers you can resort the order.

If you double click on the RR column it will pull the shippers cut codes to the top.

If you hover your cursor over the cut code a pop up box will appear with description of code.

Use a single day date range when checking current activity or a particular cycle for issues.

Multi day range queries will only pull ID3 data

Page 26: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

26

Open Lines

Customer

Questions / Suggestions

Page 27: Natural & Central Region Customer Group · Natural & Central Region Customer Group July 13, 2016. 2 NGPL Maintenance Summary ... July 12, 2016, and continue through gas day Thursday,

27

That’s a wrap!

The Adventure Continues

3rd Quarter – 2016