NATIONAL POWER CORPORATIONPROJECT STATUS REPORT
(as of 31 March 2019)
REMARKS
(as of 31 March 2019)
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
1. Rehabilitation of Pulangi IV HEP Reservoir Project (Selective Dredging of Lower Reservoir) - Phase 3
Rehabilitation and Selective Dredging of Lower Reservoir
261,000,000.00 244,880,000.00 Sunwest Construction and Development Corporation
30-Oct-17 Original Expiry:
28-May-18Suspension of
Works:21-Dec-17Revised Contract
100% 100% - Project completed as of 25 July 2018.- Preliminary Project Close-out Report transmitted to Finance on 24 September 2018.
236,160,836.86 96.44% - Fifteen Percent (15%) Advance Payment, 1st and 2nd Progress Billings already claimed.- Final Billing for review and evaluation.
I. PLANT BETTERMENT/REPAIR/REHABILITATION/IMPROVEMENT
Contract Expiry
(per Time Suspension):
16-Jun-18Time Extn:
42C.D.Revised Contract
Expiry per p y pTime Extn.:27-Jul-18
2. Construction of New Mechanized Warehouse for Agus 2 HEP
Construction of New Mechanized Warehouse
18,246,000.00 Original Contract Amt:
15,754,815.00
VO No. 11,079,177.04
MRRM Trading and Construction
19-Jan-18 Original Expiry:
15-Sept-18
Revised Expiry per Ti E t
100% 100% - Project completed as of 26 November 2018.- Preliminary Project Close-Out Report transmitted to concerned groups on 19 March 2019.
16,833,992.04 100% - Fifteen Percent (15%) Advance Payment and Final Billing already claimed.
Revised Contract Amount:
16,833,992.04
Time Extn.:25-Oct-18
3. Rehabilitation of Agus 6 HEP Unit No. 3 Draft Tube Liner
Rehabilitation of Draft Tube Liner
27,068,000.00 Original Contract Amt:
22,586,586.00
VO No. 1
MRRM Trading and Construction
22-Apr-18 Orig. Expiry:18-Sep-18
Revised Contract
100% 100% - Project completed as of 24 October 2018.- Project Close-Out Report transmitted to concerned groups on 18 March 2019.
23,738,356.00 100% - Fifteen Percent (15%) Advance Payment and - Final Billing already claimed.
VO No. 11,151,770.00
Revised Contract Amount:
23,738,356.00
Contract Expiry (Per
Susp/ Resumption):
26-Oct-18
Page 1 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
4. Installation of Concrete Installation of 6,380,000.00 6,385,314.14 BRIMA 28-May-18 24-Oct-18 100% 100% - Project completed as of 12 January - - - Fifteen Percent (15%) Barrier at Units 3, 4 & 5 Tailrace at Agus 6 HEP
Concrete Barriers Construction & Enterprises Revised
Contract Expiry (Per Time Susp./ Resumpt):20 Dec-18
2019.- Project Close-out Report, 75% completed. For transmittal to concerned offices by EO May 2019.
Advance Payment waived by the Contractor. No submitted Final billing yet.
- Liquidated damages will be imposed for all the activities beyond the contract expiry
1. Service Contract for the - Parcellary Survey 2,300,000.00 2,070,000.00 RASA Surveying 13-Jul-14 11-Nov-14 100% 100% Parcellary Survey Contract: 2,070,000.00 100% - 1st and Final BillingII. SPUG TRANSMISSION LINE AND SUBSTATION PROJECTS
1. Service Contract for the Parcellary Survey of Remaining Lots Affected by the Existing Puerto Princesa – Narra 69kV T/L Project
Parcellary Survey 2,300,000.00 2,070,000.00 RASA Surveying and Realty
13 Jul 14 11 Nov 14 100% 100% Parcellary Survey Contract:- Certificate of Final Acceptance was issued to contractor last 23 July 2018.- Preparation of Project Close-out Report partially completed. Documents to be provided by the Contractor already requested. Target completion by middle of April 2019.
2,070,000.00 100% 1st and Final Billing already claimed.
2. Service Contract for the Parcellary Survey of
- Parcellary Survey 2,587,000.00 2,586,980.00 Thetan Computerized
28-Nov-14 16-Apr-15 100% 100% Parcellary Survey Contract:All req ired orks ere completed as
2,586,980.00 100% - Final Billing already claimedParcellary Survey of
Remaining Lots Affected by the Existing Narra - Brooke's Point 69kV T/L Project
Computerized Mapping & Engineering Services
- All required works were completed as of 02 February 2018.- Certificate of Acceptance was issued on 06 March 2018.- Preliminary Project Close-out Report already transmitted to Finance on 9 July 2018.
claimed.- Liquidated damages already imposed for the delays incurred beyond the Contract expiry.
3. Service Contract for the Investigation (Route) and
- Investigation (Route)/Parcellary
4,797,000.00 3,836,600.00 AB Surveying & Development
19-May-15 15-Sep-15 100% 99% Parcellary Survey Contract:- Actual site verification of contractor's
2,685,200.00 69.99% - 1st Progress Billing to 3rd Progress Billing already
Parcellary Survey of the Proposed 70 kms Taytay-El Nido 69kV T/L Project
Survey accomplishments, 80% completed. Completion of evaluation of accomplishment pending approval of the submitted Re-routed Plan & Profile to DDD and completion of finalization of masterlist. For follow-up with DDD.- Finalization of Masterlist, 82.38% completed. - Show Cause Order issued on 24 J 2019
claimed.- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
January 2019.4. Service Contract for the
Parcellary Survey of the Proposed 32kms. Brooke’s Point – Bataraza 69kV T/L Project
- Parcellary Survey 2,104,000.00 2,072,984.00 H. O. Noveloso Surveying
27-Apr-18 Original Expiry:
'1-Aug-18
Revised Expiry per Time Ext.:31-Aug-18
100% 68.69% Parcellary Survey Contract:- Revised Parcellary index map resubmitted for approval on 22 February 2019. Remaining outputs (masterlist and sketch plans) submitted on 7 March 2019. Random check survey conducted on 19-23 March 2019 with observations noted. Some polesites are located near a
- - - No progress billing yet.
- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
creek and RROW of DPWH. Revised outputs to be resubmitted on 12 April 2019.- For site verification upon completion of submission.
Page 2 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
5. Supply, Delivery, - Supply, Delivery, 135,022,000.00 Power Dimension 27-Apr-15 1-Jan-16 100% 100% Construction Stage: 127,717,172.25 95.03% - Fifteen Percent (15%) Construction/ Installation, Test and Commissioning of 69kV Virac (Marinawa) Substation Project
Construction/Installation, Test and Commissioning of 69 kV, 10 MVA Substation and other associated equipment
134,996,496.06(-) 597,197.30
(Variation Order)
Rev. Contract Amt.134,399,298.76
Inc. - Project completed as of 2 May 2018.- Conduct of simulation test by the Contractor completed on 19-20 January 2019.- Inauguration/ Ceremonial Energization conducted on 21 July 2017.- For closure of remaining punchlists (Supply of spare parts and tools). For confirmation with Contractor whether
id it h ll b d d t d f th i
Advance Payment and 1st to 4th Progress Billings already claimed.- Final Billing is under review/evaluation.- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
said items shall be deducted from their Final Billing claim. For follow-up with the Contractor.
Page 3 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
6. Supply, Delivery, - Supply, Delivery, 97,271,000.00 96,942,300.00 SL Development 28-Jun-17 Original 100% 99.96% Construction Stage: 36,378,039.86 37.53% - Fifteen Percent (15%) Construction/ Installation, Test and Commissioning of 5 MVA Codon Load-end Substation Project
Construction/Installation, Test and Commissioning of Works
Construction Corporation
Expiry:23-Apr-18
Revised Contract Expiry
(+71 c. d. Time Ext):03-Jul-18
- Project completed as of 24 January 2019. - Energization for scheduling upon termination of MOU with FICELCO. - CPES Assessment conducted on 26 February 2018 until 4 March 2019 with a satisfactory rating (85.08%). - 23 out of 24 identified punchlist items already rectified. Punchlist JIF No. 23 - T l d S P t t t d li d
Advance Payment and 1st Progress Billing already claimed.
- Liquidated damages will be imposed for the delays incurred beyond the Contract expiry.
Revised Contract
Expiry (Per Work Suspen-
sion):19-Sep-18
Tools and Spare Parts not yet delivered, therefore remain open.- Joint Final Inspection and test of remaining punchlist items conducted on 11-15 March 2019. The report disclosed six (6) test punchlists for the Site Acceptance Test of Power Circuit Breaker.
7. Supply, Delivery, - Supply, Delivery, 127,735,050.00 127,901,000.00 SL Development 12-Mar-19 6-Jan-20 - - - Notice of Award issued on 24 January - - pp y yConstruction, Installation, Testing and Commissioning of 5 MVA San Miguel Substation (Catanduanes)
pp y yConstruction/Installation, Test and Commissioning of Works
pConstruction Corporation
y2019.- Notice to Proceed conformed on 5 March 2019.- Kick-off Meeting held last 13 March 2019.- Contractor is yet to mobilize at project site.
8. Supply and Erection/Installation of
Supply and Erection/
143,800,000.00 143,420,721.00 SL Development Construction
5-Mar-18 Original Expiry30-Oct-18
100% 88.25% Construction Stage: - Works suspended as of 23 January
76,266,754.18 53.18% - Fifteen Percent (15%) Advance Payment and 1st
69kV Steel Poles for Virac (Marinawa) – San Miguel 69kV T/L Project, 16kms(Catanduanes)
Installation CorporationRevised Expiry
10- Feb-19
p y2019 due to unsettled ROW issues.- Foundation works, 90.52% completed.- Erection of steel poles, 83.16% completed.- Installation of structure dressing & insulator assemblies and Installation/Stringing of ACSR/OHGW in progress.- ROW Clearing, 13.8/15.70 kms.
yProgress Billing already claimed.
(87.90% completed).- Delivery of steel poles at site in progress.- ROW Clearing, 13.8/15.70 kms.(87.90% completed).- CPES Assessment conducted on 27 February to 4 March 2019 with a satisfactory rating (87.05%).
9 Supply Construction - Supply 145 263 000 00 Orig Contract Amt D M Consunji Inc 1-Mar-17 25-Dec-17 100% 100% - Certificate of Completion (Provisional 140 062 021 24 100% - Fifteen Percent (15%)9. Supply, Construction, Test and Commissioning of Mansalay Switching Station and Expansion of Bansud & San Jose Substation
- Supply, Construction/ Installation, Testing and Commissioning of substation equipment for Mansalay Switching Station, Expansion of Bansud and San Jose Substation
145,263,000.00 Orig. Contract Amt.138,887,809.98
VO No. 12,338,319.13
VO No. 2( 1,164,107.87)
Revised Contract
D. M. Consunji, Inc. 1-Mar-17 25-Dec-17 100% 100% - Certificate of Completion (Provisional Acceptance) issued effective 22 December 2017.- Certificate of Project Turn-Over already signed/approved by SPUG effective 06 July 2018.- All issues/concerns already complied/resolved by the Contractor, Certificate of Final Acceptance will be transmitted to SPUG for
140,062,021.24 100% - Fifteen Percent (15%) Advance Payment, 1st to 4th Progress Billings and Final Billing already claimed.
Jose Substation Revised Contract Amount:
140,062,021.24
transmitted to SPUG for signature/approval. - Preliminary Project Close-Out Report transmitted to Finance last 11 July 2018. A copy of paid voucher for Final Billing will be transmitted to Finance.
Page 4 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
10. Rehabilitation of Calapan- - Rehabilitation of 318,733,000.00 Orig. Contract Amt. D. M. Consunji, Inc. 24-Feb-17 Original 100% 100% Construction Stage: 212,516,373.18 89.07% - Fifteen Percent (15%) Bansud69 kV Transmission Line Project, Schedule 1
69 kV T/L, 44 kms.- Supply, Erection/ Installation Works of Steel Poles, Structure Dressings and other related transmission line hardware.- Dismantling,
ti i d h li
231,796,408.68
VO No. 16,793,176.68
Revised Contract Amount:
238,589,585.36
Contract Expiry:
25-Dec-17Suspension of
Works:16-Sept-17
Resumption of Works:
19-Feb-18R i d
- Calapan-Naujan T/L Section was energized on 25 May 2018 while the Naujan-Victoria T/L Section was energized on 20 June 2018.- Issued Certificate of Final Completion (Provisional Acceptance) effective 25 May 2018.- Certificate of Project Turn-Over already signed/approved by SPUG effective 06 J l 2018
Advance Payment, 1st to 4th Progress Billings already claimed.- Final Billing for payment.
retiring and hauling of existing transmission line materials.
Revised Expiry per
Suspension:25-May-18
July 2018.- Project Close-out Report transmitted to concerned groups on 4 January 2019. - Rectification works, 100% completed.
11. Rehabilitation of Calapan-Bansud69 kV Transmission Line Project, Schedule 2
- Rehabilitation of 69 kV T/L, 42 kms.- Supply, Erection/ Installation Works
298,616,000.00 230,314,703.00 S. L. Development Construction Corp. (SLDCC)
20-Oct-18 14-Aug-19 47.81% 53.85% Construction Stage:- Gathering of necessary documents for application of tree cutting permit in progress. Inventory of trees to be cut
34,547,205.45 15% - Fifteen Percent (15%) Advance Payment already claimed.
of Steel Poles, Structure Dressings and other related transmission line hardware.- Dismantling, retiring and hauling of existing transmission line
t i l
completed.- FAT of Insulator, Conductor and Steel Pole conducted on 14-18 January 2019.- Excavation of workable polesites, 37.88% completed.- Erection of pole structures, 37.88% completed.- Installation of structure dressing and insulator string assemblies, 29.10%
materials. completed.- Stringing of power conductor and OHGW, 1.99 kms completed.- Conducted coordination meeting with the Contractor to discuss the request of ORMECO to restore temporarily the T/L section from ORMECO-Socorro Substation to ORMECO-Pinamalayan Substation. A timeline for the rehabilitation works was formulatedrehabilitation works was formulated.
12. Rehabilitation of Calapan-Puerto Galera 69 kV Transmission Line Project
- Rehabilitation of 69 kV T/L, 41 kms.- Supply, Erection/ Installation works of Steel Poles, Structure Dressings and other related transmission line h d
354,828,000.00 Orig. Contract Amt.337,411,699.00
VO No. 112,385,812.70
Revised Contract Amount:
S. L. Development Construction Corp.
23-Feb-17 Original Expiry:
19-Dec-17
Suspension of Works:
25-Oct-17
R ti f
100% 98.45% Construction Stage:- The Calapan-Puerto Galera 69kV T/L was completed on 28 April 2018, inaugurated and was put into commercial operation on 12 May 2018. - 337 JFI-generated punchlist items composed of 1,492 work items, are being rectified by the Contractor.
1 268 t f 1 492 k it l d
294,272,841.64 84.13% - Fifteen Percent (15%) Advance Payment, 1st and 2nd Progress Billings already claimed.
- Final billing not yet claimed.
hardware.- Dismantling, retiring and hauling of existing transmission line materials
349,797,511.70 Resumption of
Works:03-Jan-18
Revised Expiry per Time Extn:28-Apr-18
- 1,268 out of 1,492 work items already rectified/ completed (85%). - Target completion for rectification works by the Contractor will be scheduled pending shutdown of the energized line. - Certificate of Project Turn Over dated 06 July 2018 already signed and approved by SPUG.
Preliminary Project Close out Report- Preliminary Project Close-out Report already transmitted to concerned groups on 29 November 2018.
Page 5 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
13. Supply, Erection/ - Supply and /
384,135,000.00 289,165,204.20 S. L. Dev't. Const. 9-Feb-16 Original 98.63% 96.67% Construction Stage: 270,431,695.03 93.52% - Fifteen Percent (15%) Installation of Bansud-Mansalay69 kV, SC/SP-CP Transmission Line Project
Erection/Installation of Concrete and Steel Poles, Power Conductors, Structure Dressings and other related transmission line hardware.- 64.53 km. 69 kV, Single Circuit/Steel
Corp. Expiry:04-Dec-16
Revised Expiry per
Work Suspension
No. 1:04-Mar-17
- The Bansud-Mansalay 69kV T/L is under suspension effective on 22 February 2017 due to unresolved Expropriation Cases.
- Joint Final Inspection of completed T/L section conducted on 26 February 2018 to 9 March 2018. 624 punchlist items were identified. For conduct of
tifi ti k l ti f
Advance Payment and 1st to 4th Progress Billing already claimed.
gPole-Concrete Pole Transmission Line Project in two (2) Schedules:Sch. 1: 33 km.Sch. 2: 32 km.
Work Suspension
No. 2:22-Feb-17 to
Present
rectification works upon resolution of ROW issues.
- Remaining works include erection, guying and dressing of BM267- BM271 (pending resolution of expropriation case filed at Pinamalayan RTC).
14. Mansalay – San Jose 69kV T i i Li
- Supply and E ti /I t ll ti
Sch. 1:281 260 000 00
Sch. 1:221 969 026 25
S. L. Dev't. Const. C
23-Sep-18 Sched. 1:19 J l 19
61.37% 59.76% Construction Stage:I t f t t b t i
54,149,973.08 15% - Fifteen Percent (15%) Ad P t l d69kV Transmission Line
ProjectErection/Installation of Concrete and Steel Poles, Power Conductors, Structure Dressings and other related transmission line hardware.- 60 km. 69 kV, Single Circuit/Steel
281,260,000.00
Sch.2:172,113,000.00
221,969,026.25
Sch.2:
139,033,794.25
Total:361,002,820.50
Corp. 19 Jul-19
Sched. 2:25-May-19
76.95% 66.27%
- Inventory of trees to be cut in progress. - Re-routing of lines in progress.- Re-survey of possible new T/L route for MJ 135 to 226 conducted from 18 March 2019 until 29 March 2019. Schedule 1: - Erection of poles including excavation and hauling in progress. Schedule 2:
Erection of poles including excavation
Advance Payment already claimed.
Single Circuit/Steel Pole-Concrete Pole Transmission Line Project in two (2) Schedules:Sch. 1: 34 km.Sch. 2: 26 km.
- Erection of poles including excavation and hauling in progress.
f f C S % % % f ( %)15. Rehabilitation of Boac-Torrijos 69kV Transmission Line Project, 47 kms.
- Rehabilitation of 69 kV T/L, 47 kms.- Supply, Erection/ Installation Works of Steel Poles, Structure Dressings and other related transmission line hardware.
Dismantling
392,305,000.00 369,550,146.85 D. M. Consunji, Inc. 4-Sep-18 29-Aug-19 58.40% 70.80% Construction Stage:- Construction works in progress.- Excavation of pole setting including anchor block installation, 53.20% completed.- Retirement of T/L materials & hardware and extraction of woodpoles, 85.78% completed.- Hauling/dragging/erection of steel poles
t it i
190,500,752.03 51.55% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed by the Contractor.
- Dismantling, retiring and hauling of existing T/L materials.
at site in progress.- Erection works, 55.94% completed.
16. Supply, Delivery, Construction, Installation, Testing & Commissioning of 5MVA Taytay
- Supply, Delivery, Construction, Installation, Testing & Commissioning
127,995,000.00 126,987,778.48 D. M. Consunji, Inc. 14-Jan-19 9-Nov-19 9.38% 13.63% - Mobilization at site on 22 January 2019.- Site development commenced on 28 January 2019.- Concreting of column (Control House)
19,048,166.77 15% - Fifteen Percent (15%) Advance Payment already claimed by the Contractor.
Substation Project, Poblacion, Taytay, Palawan
completed.- Excavation for Substation equipment in progress.- Concreting of Control House and Bunk House in progress.
Page 6 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
17. Rehabilitation of Minolo - Rehabilitation of 329,686,000.00 318,254,504.95 Hansei Corporation - - - - -The NP Board approved (in principle) (Puerto Galera)-Mamburao 69kV Transmission Line Project, 52 kms.
69 kV T/L, 52 kms.- Supply, Erection/ Installation works of new Steel Poles, Structure Dressings and other related transmission line hardware.- Dismantling,
ti d h li
the award of the project on 28 February 2019. Release of Certification/Attestation and Board Resolution by the Office of the Corporate Secretary (OCS) pending approval of the 2019 General Appropriations Act (GAA)/NG Subsidy (SARO).
- Identification/coordination with Project Aff t d P (PAP ) isorting and hauling
and stockpiling of existing transmission line materials.- Cutting/extraction, hauling and stockpiling of various types of existing pole
Affected Persons (PAPs) in progress.- 163 landowners identified; 16 already coordinated/ negotiated.
existing pole structures to NPC designated stockyard/warehouse.
Page 7 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
III. SPUG CAPACITY ADDITION PROJECTS AND ASSOCIATED FACILITIES1. Supply, Delivery &
Installation, Test and Commissioning of 300 KW & Below Generating Sets for Various SPUG Areas
79,400,000.00 75,334,467.82 Thermopower Incorporated
2-Nov-13 29-Jun-14 100% 93.90%(TPI Accomp.
upon NPC Take Over)
47,245,645.76 62.71% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed.
- Payment of billings/claim on hold until all pending issues are resolved.
Supply, Delivery & Installation, Test and Commissioning of 4.425 MW (25 x 300 KW and Below) D/G sets for the following sites: - 1x300KW Limasawa DPP
- NPC take-over of the contract effective 22 November 2016.
Procurement of Spare Parts for 300kW, 100kW and 50kW Gensets:- Pre-procurement Conference conducted on 19 February 2019. Pre-procurement Report approved on 18 March 2019.
- 2x300KW Rapu-Rapu DPP- 1x300KW J. P. Rizal DPP- 1x300KW Batan DPP- 1x300KW Tandubas DPP- 1x30 KW West Si l DPP
- For revision of Bid Documents.
Simunul DPP- 1x300KW Sibutu DPP- 1x300KW Tandubanak DPP- 2x300 KW Pangutaran DPP- 2x100KW Itbayat DPP
2x100KW- 2x100KW Sabtang DPP- 2x100KW Cagayancillo DPP- 1x100 KW Manuk Mangkaw DPP- 1x100 KW Sacol DPP- 1x75KW Lahuy DPPDPP- 2x50KW Quinalasag DPP- 2x50KW Biasong DPP- 1x50KW Lunang DPP
Page 8 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
2. Supply, Delivery, Supply, Delivery, 252,248,000.00 Orig. Contract Amt. JV of People's Int'l. 14-Mar-16 Original 100% 100% - All 13 units (7.8 MW) were 203,996,938.19 79.77% - 1st to 6th Progress Installation, Test & Commissioning of 13 x 600 KW Diesel Gensets and Associated Electrical Equipment for Various SPUG Areas
Installation, Test & Commissioning of 7.8 MW (13 Units - 600 KW) D/G Sets distributed to the following plant sites:- 2x600 KW San Vicente DPP
2 600 KW P lili
249,714,295.38
Amendment Order No. 1
6,032,622.00
Revised Contract Amount:
255 746 917 40
Enterprises Co. and V&P Eng'g. (China Ltd.)
expiry:09-Jan-17
Revised Expiry:
20-Mar-17(+72 c. d. approved
Time E t i )
commercially operated as of January 2018.- For rectification of remaining punchlist items.- Approval of Certificate of Turn Over & Certificate of Taking Over for Polilio DPP, PB-116, Kalamansig DPP and Ninoy Aquino DPP still pending.- Preliminary Project Close-out Report t itt d t Fi 28 N b
Billings already claimed to-date.
- 2x600 KW Polilio DPP- 1x600 KW Tingloy DPP- 4x600 KW Ticao DPP- 1x600 KW Power Barge 116- 2x600 KW Kalamansig DPP
255,746,917.40 Extension) transmitted to Finance on 28 November 2017.
Warranty Issue/s:- To-date only 12 out 13 genset units are operational with a total of 7.2 MW capacity. Unit No. 5 is unoperational (1x600kW Polilio).- Not operational since 10 March 2019 due to burnt main stator windingKalamansig DPP
- 1x600 KW Ninoy Aquino DPP
due to burnt main stator winding.- Ongoing restoration of the reported burnt stator windings.
Page 9 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
3. Supply, Delivery, Supply, Delivery, 293,000,000.00 289,495,146.47 JV of People's Int'l. 1-Feb-16 Original 100% 100% - Project completed as of 27 March 289,487,947.38 100% - 1st to 5th, Final Billings Installation, Test and Commissioning of 15x600 kW Modular Diesel Generating Sets and Associated Electrical Equipment for Various SPUG Areas
Installation, Test and Commissioning of 9.0 MW (15 Units - 600 KW) D/G Sets distributed to the following plant sites:- 1x600 KW R bl R bl
Enterprises Co. and V&P Engineering (China Ltd.)
Expiry:27-Oct-16
Revised Expiry per T.E. No.1:16-Nov-16
Revised E i
2017.- All units (9.0MW) already in Commercial Operation.- Project Close-out Report transmitted to Finance on 6 February 2018.- Preliminary Project Close-out Report transmitted to Finance on 6 February 2018. A copy of paid voucher for Final Billing and Retention Money will be t itt d t Fi
and Retention Money already claimed. Liquidated Damages already deducted.
Romblon, Romblon- 2x600 KW San Vicente, Palawan- 2x600 KW Cuyo, Palawan- 2x600 KW Tingloy, Batangas- 2x600 KW Polillo, Quezon
1x600 KW
Expiry per T.E. No.2:25-Jan-17
transmitted to Finance.
- 1x600 KW Casiguran, Aurora- 3x600 KW Sibuyan, Romblon- 1x600 KW Basco, Batanes- 1x600 KW Siasi, Sulu
4. Supply, Delivery, Installation, Test and
Supply, Delivery, Installation, Test
292,940,000.00 Original Contract Amt :
Sunwest Const. and Development
7-Mar-16 Original Expiry:
100% 99.98% - Project completed as of 11 July 2017.- Supplied MAN Genset Units 7, 8, 9 &
281,182,249.85 94.96% - Fifteen Percent (15%) Advance Payment and
Commissioning of5 X 1.0 MW Modular Diesel Generating Sets and Associated Electrical Equipment for Various SPUG Areas Boac DPP
and Commissioning of 5 MW (5 Units - 1.0 MW) Modular Diesel Generating Sets for Boac DPP
288,048,656.97VO 1:
8,050,584.75
Revised Contract Amt.:
296,099,241.72
Corp. 31-Dec-16
Revised Expiry per
Work Suspension:24-Mar-17
11 can be operated at rated capacity of 1MW load respectively. - Operation of supplied Genset Unit 10 is still pending due to defective current transformer. The 1 MW capability test of Genset Unit 10 will be conducted upon installation of the replacement current transformer.- For close-out of remaining punchlist i (JFI d T f N ' Si
1st to 3rd Progress Billing already claimed.
Revised Expiry per Time Extn.:08-May-17
items (JFI and Transformer No. 5's Site Acceptance Test (SAT). - For issuance of Certification that the Contractor's supplied diesel gensets are capable to operate at 1MW (rated capacity).
Page 10 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
5. Supply, Delivery, Supply, Delivery, 82,183,400.00 77,471,398.80 Thermo Power 4-Mar-14 29-Oct-14 100% 80.53% - Project is still under Suspension since 11,620,709.82 15% - Fifteen Percent (15%) Installation, Test and Commissioning of 10 x 600 KW Modular Generator Sets for Various SPUG Areas
Installation, Test and Commissioning of 6 MW (10 Units - 600 kW) Modular D/G Sets distributed to the following Plant Sites:- 2x600 KW K l i DPP
Incorporated 05 February 2015.- 7 out of 10 Gensets already mounted/ installed. Test and Commissioning (T&C) activities already conducted for four (4) genset units.- Reply to arbitration case already filed by NPC-Office of the Legal Counsel (OLC) at Philippine Dispute Resolution Center (PDRC).
Advance Payment already claimed.
- Payment of billings/claim on hold until all pending issues are resolved.
Kalamansig DPP- 2x600 KW Dinagat DPP- 1x600 KW Mapun DPP- 1x600 KW Taytay DPP- 1x600 KW Tingloy DPP
2x600 KW El- 2x600 KW El Nido DPP- 1x600 KW Ticao DPP
6. Supply, Delivery, Installation, Test and Commissioning of 1 x 1.5 MW Modular Generating Sets for Dinagat DPP
Supply, Delivery, Installation, Test and Commissioning of 1.5 MW (1 Unit - 1.5 MW)
71,677,000.00 69,509,183.48 Hi-Tone Construction and Development Corporation
15-Jun-16 Original Expiry:
10-Jan-17
Revised
100% 100% - The 1 x 1.5MW Modular Generating Sets were put into commercial operation as of 20 December 2017.
- Rectification of punchlist items already
50,145,621.17 72.14% - 1st Progress Billing already claimed.
- Contractor's Final Billing under review/evaluation.Sets for Dinagat DPP 1.5 MW)
Containerized Diesel Generator Set for Dinagat DPP
Revised Expiry per Time Extn.
No.1:15-Apr-17
Revised Expiry per Time Extn.
No.2:
Rectification of punchlist items already completed.
- Preliminary Project Close-out Report transmitted to Finance on 29 January 2019.
under review/evaluation.
- Liquidated damages imposed for all activities beyond the contract expiry.
26-Apr-17
Page 11 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
7. 3 x 600KW D/G Sets for Supply, Delivery, 48,976,000.00 46,785,500.00 SEACOM, Inc. 23-Nov-16 Orig Contract 100% 100% - Project completed as of 13 November 46,785,500.00 100% - 1st, 2nd Progress and Power Barge-109(1 Unit) and Power Barge-116(2 Units)
Installation, Test and Commissioning of 1.8 MW (3 Units -600 kW) D/G Sets and Associated Electrical Equipment and devices distributed in the following
l t it
Expiry
20-Jul-17
Revised Contract Expiry
29-Jul-17
2018.- Certificates of Acceptance and Taking Over already approved.- Preliminary Project Close-Out Report already transmitted to Finance.
PB 116- 2 x 600kW gensets for PB 116 in commercial operation.
All hli t it l d tifi d
Final Billings already claimed.
- Liquidated damages already imposed.
plant sites:- 1 x 600 KW for Power Barge 109,Tablas Island, Romblon- 2 x 600 KW for Power Barge 116, Larena, Siquijor
- All punchlist items already rectified.PB 109- 1 x 600kW gensets for PB 109 in commercial operation.
8 C t ti f P C t ti f 19 269 000 00 18 204 599 50 A bit T di & 4 M 16 O i i l 100% 87 10% 2 200 kW G t f L DPP 8 202 810 07 45 06% Fift P t (15%)8. Construction of Power Facilities of2 x 200KW Gensets for Languyan DPP
Construction of Power Facilities
19,269,000.00 18,204,599.50 Ambit Trading & Technical Services
4-May-16 Original Expiry:
29-Dec-16
Revised Expiry per
Suspension28-Jun-17
100% 87.10% - 2x200 kW Gensets for Languyan DPP energized and inaugurated on 10 December 2018. - Negative slippage (12.90%) due to unavailability of Contractor's manpower at site. No significant accomplishment due to insufficient deliveries of construction materials at site.- Remaining Activities:
1 Electrical works: 3 65%
8,202,810.07 45.06% - Fifteen Percent (15%) Advance Payment, 1st and 2nd Progress Billings already claimed.- Request for payment of 3rd Progress Billing under review/validation at Finance.- Liquidated damages for the unperformed activities 1. Electrical works: 3.65%
2. Mechanical works: 7.17% 3. Civil works: 1.73% 4. Architectural works: 0.35%- Pre-test, Test and Commissioning conducted on 22-26 November 2018.
the unperformed activities beyond contract expiry already imposed.
9. Construction of Power Facilities incl. Supply,
Construction of Power Facilities,
20,451,000.00 18,688,992.10 Ambit Trading & Technical Services
4-May-16 Original Expiry:
100% 76.64% - 2x150 kW Gensets for Pandami energized and commercially operated on
13,445,252.58 71.94% - Fifteen Percent (15%) Advance Payment, 1st and pp y,
Erection/ Installation and Test of Balance of Plant for 2 x150KW Pandami DPP
,Supply, Erection/ Installation and Test of Balance of Plant
p y26-Jan-17
Revised Expiry per
Susp.:29-May-17
g y p24 October 2018.- Test and Commissioning was completed on 19 October 2018.- Negative slippage (23.36%) due to insufficient manpower and late delivery of construction materials.- Remaining Activities : 1. Electrical works: 7.12% 2. Mechanical works: 42.75%
y ,2nd Progress Billings already claimed.- Liquidated damages for the unperformed activities beyond contract expiry already imposed.
3. Civil works: 29.51% 4. Architectural works: 1.81%- Partial construction / electro-mechanical materials already delivered at site. For follow-up of remaining deliveries.
Page 12 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
10. Supply, Delivery and Test Supply, Delivery 25,334,000.00 19,639,000.00 JV between IHI 3-Apr-17 29-Sep-17 100% 100% - Supply contract completed on 20 June 12,355,714.29 62.91% - For compliance of lacking of 2 x 200 KW (for Languyan DPP) and 2 x 150 KW (for Pandami DPP) Diesel Genset & Assoc. Elec. Equipment
and Test of 0.7 MW (2 Units - 200 KW & 2 Units - 150 KW) Diesel Generating sets and associated Electrical Equipment for the following project it
Turbo Int'l Trade & Dynamic Power & Marine Industrial Hardware Inc.
2018.
- Rectification of all punchlist items completed.
- Completed Project Close-Out Report already transmitted to concerned offices.
requirements for 1st Progress Billing.
- Liquidated damages will be imposed for all unperformed activities beyond the contract expiry.
sites:- 2 x 200 KW for Languyan DPP- 2 x 150 KW for Pandami DPP
Page 13 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
11. Supply, Delivery, Supply, Delivery, 6,444,000.00 5,868,449.06 SEACOM, Inc. 9-May-17 3-Jan-18 100% 100% - Project completed as of 15 March 1,926,332.36 32.83% - 1st Progress Billing Installation, Test and Commissioning of 1 x 90 KW Diesel Genset & Assoc. Elec. Equipment for Rama Cinco DPP
Installation, Test and Commissioning of 0.09 MW (1 Unit - 90 KW) D/G Set for Rama Cinco DPP
2019. - Project commissioned on 20 June 2018.- Preliminary Project Close-out Report transmitted to concerned groups on 16 July 2018.
already claimed.- Final Billing is under review/ evaluation. - Liquidated damages will be imposed for all unperformed activities beyond the contract expiry.
12. Const. of Power Facilities Including Supply,
Construction of Power Facilities
445,518,000.00 444,523,243.15 Joint Venture (JV) of Sunwest and
7-Mar-18 30-Apr-19 98.38% 43.52% - Construction works in progress. • Civil & Architectural Works, 81.15%
66,678,486.18 15% - Fifteen Percent (15%) Advance Payment already
Delivery, Installation, Test and Commissioning of 5 x 1.0MW Containerized Gensets, Auxiliaries and Balance of Plant for Basilan Power Plant
Including Supply, Delivery, Installation, Test and Commissioning of 5 x 1.0MW Containerized Generating Sets, Auxiliaries and Balance of Plant for B il P
Bendimil completed • Electrical Works, 22.70% completed • Mechanical Works, 33.69% completed • Other works, 85.71% completed- Negative slippage (-54.86%) due to lack of approved documents and drawings and unavailability of materials and equipment to be used in the project.- Conduct of FAT for gensets
h d l d 03 18 M 2019
claimed.
Basilan Power Plant
rescheduled on 03-18 May 2019.- Show Cause Order issued on 26 September 2018. - Final Show Cause Order dated 28 November 2018 issued. Contractor was already advised to deliver the electro-mechanical materials/ equipment needed at site.- Target completion on 30 April 2019.
Page 14 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
13. Construction of Power Construction of 41,686,400.00 41,686,400.00 JV of CDJ Builders 21-Feb-18 17-Nov-18 100% 43.41% - 1 x 90KW Tictabon DPP 11,450,960.00 27.47% - Fifteen Percent (15%) Facilities Including Supply, Delivery, Installation, Test and Commissioning of Modular Gensets for the Electrification of Five (5) Barangays (Tictabon, Tumaloptap, Pangapuyan, Manalipa
d G t St C DPP)
Power Facilities Including Supply, Delivery, Installation, Test and Commissioning Works
& Construction Supplies and Dynamic Power & Marine Industrial Hardware, Inc.
• Site development in progress.•Gensets, transformer and electrical appurtenances yet to be delivered at project site.1 x 40 KW Manalipa DPP, 1 x 40kW Tumaloptap DPP and 1 x 10kW Pangapuyan DPP• No activity at the project site due to unavailability the gensets, transformer
d l t i l t t j t
Advance Payment and 1st Progress Billing already claimed.
- Liquidated damages will be imposed for the delays incurred beyond the revised expiry date.
and Great Sta. Cruz DPP) at Zamboanga Del Sur
and electrical appurtenances at project site.1 x 10kW Great Sta. Cruz DPP• Suspended effective 18 October 2018 due to unavailability of required Special Agreement on Protected Areas (SAPA) from DENR. A Field Base Investigation (FBI) Team was created for the expeditious issuance of NCIP/SAPA Certificate Survey conducted on 6Certificate. Survey conducted on 6 March 2019. - Re-test of gensets conducted last 21 February 2019 at Mandaue, Cebu City. SAT Punchlist Nos. 1, 2, & 3 are closed per ESD's verification of results of re-tests.- SAT Punchlist No. 5 - Obtained fuel rates of Tested Genset Nos. 4, 5, 6 ,7 exceeded the Contractor's maximumexceeded the Contractor s maximum guaranteed values (2x10 kW Tested Genset Nos. 6 & 7 and 2x40kW Tested Genset Nos. 4 & 5).
14. Design, Supply, Delivery, Installation, Test and Commissioning of Limasawa Solar
Design, Supply, Delivery, Installation, Test and Commissioning
53,825,000.00 53,764,897.15 Power Dimension Inc.
23-Mar-18 Original Expiry:
17-Nov-18
100% 92.16% - The project is still suspended effective 19 October 2018 due to the unresolved Right-of-Way issues. - Remaining three (3) out of 18 PAPs still
25,640,987.62 47.69% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed.
Photovoltaic (PV) with Energy Storage System (ESS) - Diesel Hybrid Power Plant
Works Revised Expiry per
Work Susp/ Resumption:13-Apr-2019
for negotiation. ROW clearing not yet started. - Show Cause Order issued to the Contractor last 15 August 2018.- Factory Acceptance Test of Power Conversion System (PCS) in China was completed on 12 October 2018. - Five (5) non-conformities identified in the CPES Assessment completed. C t t l d b itt d tiContractor already submitted corrective action plan.
Page 15 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
15. Construction of Power Construction of 23,465,000.00 23,465,000.00 JV of CDJ Builders 2-Apr-18 28-Sep-18 100% 29.26% - The Contractor did not meet the agreed 3,519,750.00 15% - Fifteen Percent (15%) Facilities Including Supply, Delivery, Installation, Test and Commissioning of 2 x 180kW Modular Gensets and Associated Electrical Equipment and BOP for the Electrification of Four (4) Barangays at Naro I l d M b t
Power Facilities Including Supply, Delivery, Installation, Test and Commissioning Works
& Construction Supplies and Dynamic Power & Marine Industrial Hardware, Inc.
extended construction schedule on 31 December 2018. Coordination meeting with the Contractor held last 1 March 2019. New target deliveries for gensets were discussed.- Construction/Civil Works, 50.25%
On-going activities:• Delivery of all materials and equipment
t it
Advance Payment already claimed.
Island Masbate at site.• Hauling, compaction and spreading of filling materials.• Construction of switchyard appurtenances and fuel oil storage tank containment wall.• Construction of perimeter fence including gate and barbed wire, perimeter lighting and flag pole.• Construction of control house• Construction of control house foundation.
- Coordination meeting held last 01 March 2019 to discuss the large delay of the project, and delivery of gensets to the project site. Contractor committed to deliver all gensets and all associated equipment/ accessories/etc. by 01 April 20192019.
16. Construction of Power Facilities including Supply, Delivery, Erection, Installation, Test and Commissioning of 90kW Modular Generating Sets Including BOP for Electrification of 5 Barangays at
Construction of Power Facilities Including Supply, Delivery, Installation, Test and Commissioning Works
10,411,000.00 10,377,000 JV of CDJ Builders & Construction Supplies and Dynamic Power & Marine Industrial Hardware, Inc.
28-Feb-18 26-Aug-18 100% 60.12% -The Contractor did not meet the agreed extended construction schedule on 31 December 2018. Coordination meeting with the Contractor held last 7 February 2019. - Advised the Contractor to expedite the submission of construction drawings, material sample card and other required documents per letters dated 8 January
1,556,550.00 15% - Fifteen Percent (15%) Advance Payment already claimed.
g yTagubanhan Island
p y2019 and 4 February 2019. - Civil works, 95% completed pending genset delivery.- Site Acceptance Test (SAT) conducted on 8-10 January 2019. Rectification of punchlist items completed on 04 February 2019.- Gensets together with GCPP, day tank and water tank already delivered at Iloilo (Mainland) on 21 March 2019.- Target Project Completion by EO March 2019 was not attained. Advised the Contractor to submit its catch-up plan.
Page 16 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
17. Construction of Power Construction of 13,377,000.00 13,176,345.00 JV of CDJ Builders 2-Apr-18 28-Sep-18 100% 60.48% - Delay/negative slippage due to delayed 1,976,451.75 15% - Fifteen Percent (15% ) Facilities including Supply, Delivery, Erection/Installation, Test and Commissioning of 2x50kW Gensets & Associated Electrical Equipment & BOP for the Electrification of Three (3) B B
Power Facilities Including Supply, Delivery, Installation, Test and Commissioning Works
& Construction Supplies and Dynamic Power & Marine Industrial Hardware, Inc.
submission of documents and drawings, Construction Methodology and FAT Procedures Manual and late delivery of generating sets and other electrical appurtenances at the project site. - Show Cause Order issued to the Contractor on 09 August 2018.- Site Acceptance Test for gensets conducted at Weichai-Cebu on 27-29 D b 2018 A b f fi di
Advance Payment already claimed.
Barangays – Brgy. Gibusong Island, Loreto Province of Dinagat Island Under Off-Grid Electrification
December 2018. A number of findings was identified and each of these was translated into SAT punchlist. Eight (8) SAT punchlists were identified.- SAT Punchlist No. 5 - Obtained fuel rates of Tested Genset Nos. 4, 5, 6 ,7 exceeded the Contractor's maximum guaranteed values ( 2x10 kW Tested Genset Nos. 6 & 7 and 2x40kW Tested Genset Nos 4 & 5)Genset Nos. 4 & 5). - Re-test of gensets conducted last 21 February 2019 at Mandaue, Cebu City. SAT Punchlist Nos. 1, 2, & 3 are closed per ESD's verification of results of re-tests.- Target delivery of gensets scheduled 1st week of March 2019 did not push thru. For re-scheduling.
18. Construction of Power Facilities incl. Supply, Erection/ Installation, Test & Commissioning of Forty Seven (47) Units of Modular Diesel Generating Sets and Electrical Equipment for L on SPUG Areas nder
Construction of Power Facilities incl. Supply, Erection/ Installation, Test & Commissioning Works for the following plant sites
554,685,000.00 538,974,727.18 Sunwest Construction & Dev't. Corp.
7-Jun-18 1-Jun-19 74.71% 30.57% - Factory Acceptance Test conducted last 29 November 2018 to 13 December 2018.- Negative slippage (44.14%)due to late delivery of gensets per approved Implementation Schedule.- Ongoing/Status of activities per site:1. Itbayat DPPAssembl of temporar office
80,846,209.18 15% - Fifteen Percent (15%) Advance Payment already claimed.
Luzon SPUG Areas under Schedule 1
sites:- Sabtang (2x200kW)- Itbayat (2x200kW)- Calayan (2x300kW)- Palanan (2x300kW)- Kabugao (2x200kW &
•Assembly of temporary office2. Sabtang DPP:•Assembly of temporary office3. Araceli DPP•Daytank Support installed.• For delivery of gensets and other materials/equipment.4. Kabugao DPP/Patnanungan DPP• Construction of Seclusion Fence ongoing(2x200kW &
1x100kW)- Jomalig (2x200kW)- Patnanungan (3x300kW)
ongoing.• Concrete pouring for Genset and Transformer Foundation completed.5. Culion DPP• Concreting of genset and transformer foundation completed.• Concreting of cable trench completed.• Installation of electrical flexible hose for grounding materials not yet started.• For delivery of gensets and other For delivery of gensets and other materials/equipment.
Page 17 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
- San Jose 6. Cagayancillo DPP(3x300kW)- Concepcion (3x200kW)Rizal (2x300kW)- Araceli (2x300kW & 1x200kW)- Balabac (3x200kW)- Cagayancillo (2 200kW)
• On-going site grading/excavation works.• Construction of seclusion fence not yet started.7. San Pascual DPP• For 500kW: Steel reinforcement, formworks, concrete pouring.• For 300kW: Steel reinforcement, formworks, concrete pouring. 8 B t DPP(2x200kW)
- Culion (2x500kW & 1x300kW)- Linapacan (2x200kW & 2x100kW)- Rapu-Rapu (2x500kW & 1x300kW)
Batan (2x500kW
8. Batan DPP• Concreting of Transformer pads was completed last 13 March 2019.• Assembly of rebars for seclusion fence footing and pedestal.• Ongoing construction of formworks for genset pad foundations.9. Rapu–Rapu DPP• Concrete pouring of two 500kW Genset Foundation- Batan (2x500kW
& 1x300kW)- San Pascual (Burias), Masbate (1x500kW & 1x300kW)
Foundation • Excavation at Cable Trench • Clearing and grubbing.10. Concepcion DPP• Concrete pouring of Genset and Transformer Foundations to be scheduled • Ongoing construction of Seclusion Fence 11 San Jose DPP11. San Jose DPP• Concrete pouring of Genset and Transformer Foundations.• Ongoing site grading.
Page 18 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
12. Rizal DPP • Concreting of genset and transformer foundations completed.• Construction of seclusion fence completed.• Day tank support and cable tray completed.• For delivery of gensets and other materials/equipment.• Inspection of gensets conducted; G t f R R d Ri l DPPGensets for Rapu-Rapu and Rizal DPP were hauled last 22 March 2019.- Target completion on 01 June 2019.
19. Construction of Power Facilities including Supply, Delivery, Erection, Test and Commissioning of BOP for New Areas
Construction of Power Facilities including Supply, Delivery, Erection, Test and Commissioning
86,443,365.75 86,443,365.75 Junjing Construction and General Merchandise
19-Mar-18 Sched. 1:11-Feb-19
Sched. 2:13-Dec-18
100%
100%
41.36%
43.66%
Schedule 1: (Guiuan, Eastern Samar)Variance: - 58.64%Casuguran DPP (Actual): 47.66 %Cagusuan DPP (Actual): 44.84 %Inapulangan DPP (Actual): 45.13 %Suluan DPP (Actual): 45.99%H b DPP (A t l) 23 20%
25,447,452.92 29.44% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed.
Electrification in Samar Province in Three (3) Schedules (9 Areas)
Works
Sched. 3:14-Sep-18
100% 52.12%
Habag DPP (Actual): 23.20%- Notice of Suspension of Work issued to the Contractor on 06 December 2018. Resumption of Work effective 11 January 2019.Schedule 2 (Dolores & Oras, Eastern Samar) Variance: - 56.34%Hilabaan DPP (Actual):45.58%Tikling DPP (Actual): 41.70%g ( )Sta. Monica DPP (Actual): 43.70%Schedule 3 (San Vicente, Northern Samar)Variance: -47.88%Tarnate DPP (Actual): 52.12% - Gensets delivered at Cebu City on 08 March 2019 (for Sched. II & III sites). Delivery of transformers on site for scheduling.- Site Acceptance Test of gensets for further scheduling (SAT procedures forfurther scheduling (SAT procedures for Gensets and Transformer under evaluation)- Show Cause Order already issued to the Contractor.- Target Project Completion by EO March 2019 was not attained. Advised the Contractor to submit its catch-up plan.
Page 19 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
20. Construction of Power Construction of 28,387,392.96 28,387,392.25 Joint Venture of 14-Jul-15 Original 100% 100% - For closure of punchlist items pending 4,258,108.84 15% - Fifteen Percent (15%) Facilities (Civil Works) including Relocation Works, Supply, Delivery, Erection/ Installation, and Test of Balance of Plant for Calayan DPP
Power Facilities, Relocation works, Supply, Delivery, Erection/Installation and Test of Balance of Plant.
Mega Blue Builders & I.A. Bosque Construction Corp.
Expiry:10-Mar-16 Revised
Expiry per Work Susp.:07-Jun-16 Revised
Expiry per Time Extn.:06 A 16
consolidation of rectified punchlists, i.e. documents/pictures by the Contractor.
Advance Payment and 1st Progress Billing already claimed.
- Liquidated Damages for the unaccomplished activities beyond contract expiry will be imposed.
06-Aug-16
21. Construction of Power Facilities including Supply, Delivery, Erection/Installation, Test & Commissioning of 1x90kW Genset & its Auxiliaries and Associated Electrical
Construction of Power Facilities, Supply, Delivery, Erection/Installation and Commissioning works.
19,500,000.00 19,376,570.87 Power Dimension Inc.
25-Jun-15 21-Dec-15 100% 100% - Commissioned on 31 August 2018.- Inaugurated on 15 November 2018. - Joint Final Inspection conducted on 30 August 2018.- Rectification of three (3) JFI and one (1) T & C Punchlist items completed.- For issuance of Certificate of Acceptance pending compliance of the
14,682,475.72 75.77% - Fifteen Percent (15%) Advance Payment and 1st to 2nd Progress Billings already claimed.
- Liquidated Damages for the unaccomplished activities beyond contract
Equipment for the electrification of three (3) Barangays at Calaguas Group of Islands, Vinzons, Camarines Norte Under the Off-Grid Electrification
Contractor to submit a verified report showing completed punchlist items.
expiry will be imposed.
22. Const. of Power Facilities incl. Supply, Delivery,
Construction of Power Facilities,
17,800,000.00 16,633,105.50 Power Dimension Inc.
30-Jun-15 26-Dec-15 100% 100% - Commissioned on 6 September 2018.- Joint Final Inspection conducted on 5
13,188,072.99 79.29% - Fifteen Percent (15%) Advance Payment and 1st
Erection/ Installation, Test & Commissioning of 1x100kW Genset & its Auxiliaries and Associated Electrical Equipment for the electrification of six (6) Brgys. at Camandag Island, Sto. Niño, Samar
Supply, Delivery, Erection/ Installation and Commissioning works.
September 2018.- Rectification of three (3) JFI punchlist items completed; Lube Oil Temperature Sensor of D/G set connected to the controller: 100%completed
- Site Inauguration was conducted on 19 March 2019
to 3rd Progress Billings already claimed.
- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
23. Supply, Delivery, Installation and Test of 60m³, 35m³, and 10m³ Fuel Oil Storage Tanks for Various SPUG Power Plants including Construction of Associated Facilities
Supply, Delivery, Installation and Test.
Adjusted ABC:
24,013,287.80(Sch. 1 & 4)
(Total Contract Amount for Schedule 1 and 4)
(Sch. 1)9,416,687.82
EFB Geostrukt Inc. 24-Nov-16 Original Expiry: 11-Apr-
16
Revised Expiry per
Work Susp.:11-Apr-2017
Itbayat:100%
Balatubat:100%
Itbayat:99.79%
Balatubat:100%
Balatubat DPP- Joint Final Inspection conducted last 21 November 2018. - Correction/rectification of punchlist items i.e. spare parts of motor pump, one (1) set of fuel filter/painting works completed. Contractor shall submit a verified report with supporting
10,601,184.72 44.15% - Fifteen Percent (15%) Advance Payment, 1st to 2nd Progress Billing already claimed.
- Liquidated damages will be imposed for all the remaining activities beyond
under Batch 1, Schedule 1
, ,
(Sch. 4)14,596,599.80
24,013,287.62
p p pp gdocuments/photos to close the JFI punchlist.
Itbayat DPP- Show Cause Order issued on 06 July 2017. - Verified the correction of remaining punchlist items on 5-8 March 2019. Remaining punchlist is the gauge
g ythe Contract expiry.
marking on FOST.- Tank calibration conducted 7 March 2019.- Contractor requested for deletion of BOQ Item M.W-2.8 (Spare Parts for the Fuel Transfer Pump for One Year Operation) per manufacturer's recommendation.
Page 20 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
24. Supply, Delivery, Supply, Delivery, 14,649,000.00 24,013,287.80 EFB Geostrukt Inc. 11-Apr-16 Original Ilijan: Ilijan: - Project completed. 9,802,823.78 40.82% - Fifteen Percent (15%) Installation and Test of 60m³, 35m³, and 10m³ Fuel Oil Storage Tanks for Various SPUG Power Plants including Construction of Associated Facilities under Batch 1, Schedule 4
Installation and Test
(for Batch 1, Schedule 4)
(Total Contract Amount for Schedule
1 and 4)
Expiry:06-Dec-16
Revised Expiry per
Work Susp.:22-Mar-2017
100%
Capul:100%
San Antonio:
100%
T k t
100%
Capul:100%
San Antonio:
100%
T k t
- All 18 JFI punchlists already closed. - Letter request for Final Billing from the Contractor not yet submitted.- Preparation of documents and attachments for the Project Close-out Report, 95% completed.
Advance Payment and 1st Progress Billing already claimed.- 2nd Progress Billing is under evaluation by Finance.- Liquidated damages will be imposed for all the remaining activities beyond th C t t iTakut:
100%
Lunang:100%
Takut:100%
Lunang:100%
the Contract expiry.
25. Supply, Delivery, Installation and Test of 60m³, 35m³, and 10m³ Fuel Oil Storage Tanks f V i SPUG P
Supply, Delivery, Installation and Test
6,596,000.40 6,585,890.50 Shieham Construction
23-Mar-16 Original Expiry: 19-
Aug-16
R i d
Kalaman-sig:
100%
Ni
Kalaman-sig:
100%
Ni
- Project completed as of 14 December 2018.Kalamansig DPP- Rectification of punchlist items
l t d/ l d f 4 D b
5,880,259.36 89.29% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed.
for Various SPUG Power Plants including Construction of Associated Facilities under Batch 1, Schedule 6
Revised Expiry per
Work Susp.:17-Jan-2017
Ninoy Aquino:100%
NinoyAquino:100%
completed/closed as of 4 December 2018.Ninoy Aquino DPP- Rectification of punchlist items completed/closed as of 4 December 2018.- Preparation of Project Close-out Report, 90% completed. Compliance of lacking Structure List, As-built drawings, approved Variation Order and audited
- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
approved Variation Order and audited Final Billing will complete the PCR.
Page 21 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
26. Supply, Delivery, Supply, Delivery, 24,794,000.00 28,418,879.83 Dhayang 17-May-16 Original Maripipi: Maripipi: - 86.63% completed. 12,667,857.94 44.58% - Fifteen Percent (15%) Installation and Test of 60m³, 35m³, and 10m³ Fuel Oil Storage Tanks for Various SPUG Power Plants including Construction of Associated Facilities under Batch 2, Schedule 1
Installation and Test
Construction Firm Expiry: 17-May-16
Revised Expiry per
Work Susp.:09-Sep-2017
100%Kerikite:100%
Sto. Niño:100%
Biasong:100%
Costa Rica:100%Bi i
86.23%Kerikite:92.73%
Sto. Niño:93.83%Biasong:82.34%Costa Rica:
81 84%
Remaining works/activities:- For delivery/installation of valves, flow meters, gauges, tank accessories and other remaining piping works, thus, target completion by EO February 2019 was not attained.- Final Show Cause Order issued 15 August 2018.
Advance Payment, 1st to 2nd Progress Billing already claimed.
- Liquidated damages will be imposed for all the remaining activities beyond the contract expiry.
Biri:100%
Almagro:100%Batag:100%San
Vicente:100%
81.84%Biri:
86.39%Almagro:92.21%Batag:81.96%
San Vicente:84 04%84.04%
27. Supply, Delivery, Installation and Test of 60m³, 35m³, and 10m³ Fuel Oil Storage Tanks for Various SPUG Power Plants including Construction of Associated Facilities
d B t h 2 S h d l
Supply, Delivery, Installation and Test
15,069,000.00 17,289,790.00 Ambit Trading & Technical Services, Inc.
4-May-16 Original Expiry: 31-Oct-
16
Revised Expiry per
Work Susp.(Limasawa &
B tb t
Cabul-an:100%
Guiwanon:100%
Libucan:100%Sibolo:100%
B tb t
Cabul-an:47.45%
Guiwanon:43.72%Libucan:38.92%Sibolo:34.22%
B tb t
- Contract was terminated last 11 May 2018.- Inspection and inventory of all remaining works already conducted last 16-31 July 2018. - Coordination meeting was held last 23 November 2018. Remaining works will be undertaken by administration.
5,674,767.69 32.82% - Fifteen Percent (15%) Advance Payment and 1st Progress Billing already claimed.
- For compliance of lacking documentary requirements by the Contractor for the
t f 2 d Punder Batch 2, Schedule 2
Batbatan DPP):
03-Sep-2017
Batbatan:100%
Limasawa:100%
Batbatan:29.24%
Limasawa:4.60%
payment of 2nd Progress Billing.
- Liquidated damages will be imposed for all the remaining activities beyond the Contract expiry.
28. Supply, Supply, Delivery, 87,949,000.00 78,785,120.66 MN Electro 17-Jul-17 Original 100% 100% - Inauguration was conducted last 26 74,357,542.25 94.38% - Fifteen Percent (15%) Erection/Installation and Test of 13.8 kV Distribution Line Extension/Upgrading in Divilacan, Isabela under the Off-Grid Electrification Project with Contract No. Log MSSP 2017-05-042-JPP
Installation and Test
Industrial Supply & Services Inc.
Expiry:31-Dec-17
Revised per Time Extn:12-Jan-18
July 2018. Project energized on 19-21 June 2018.
- Preparation of Project Close-out and Handover Package Reports 100% completed.
Advance Payment, 1st to 2nd Progress Billings and Final Billing already claimed.- Liquidated Damages for the unaccomplished activities beyond contract expiry already imposed.
29. Supply, Delivery, Installation / Erection of two (2) units twenty (20) ft. Collapsible Containerized Control Room for Tambo and Tabao, Lubang, Occ. Mindoro under PR No.: SO OPD16 005
Supply, Delivery, Installation/Erection
1,084,981.48 1,084,981.48 Skaff Construkt, Inc.
15-May-17 Original Expiry:
11-Sep-17Suspension of
Work:17-Aug-17
Resumption of Work:
14 Feb 18
100% 100% - Project completed as of 17 April 2018.- Certificate of Project Turn Over dated 19 December 2018 transmitted to SPUG for approval on 21 December 2018. - Preparation of Project Close-out Report in progress.
- - - Contractor's First and Final Billing for review/ evaluation. Contractor yet to submit original Delivery Receipts for attachment in the Final Billing.
- Liquidated Damages for the unaccomplishedSO-OPD16-005 14-Feb-18
Revised Expiry per
Suspension of Work:
11-Mar-18
the unaccomplished activities beyond contract expiry will be imposed.
Page 22 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
30. Supply, Delivery & Test of Supply, Delivery & 32,248,000.00 27,409,610.08 Sunwest Const. 25-Jul-16 21-Nov-16 100% 100% - Project completed. 15,145,921.15 55.26% - 1st Progress Billing 12 x 80kW Modular Diesel Generating Sets for SPUG-LOD, Minuyan, Bulacan; SPUG-VOD, Cebu City; SPUG-MOD, Davao City & Zamboanga City.
Test and Development Corp.
- Preparation of Certificate of Turn Over for the project in progress.
- Preparation of Project Close-out Report in progress.
already claimed.
- Contractor's Final Billing for review/evaluation. Informed the Contractor to submit original Delivery Receipts for attachment in the final billing.
Li id t d D f- Liquidated Damages for the unaccomplished activities beyond contract expiry will be imposed.
Page 23 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
31. Contract for the Supply, Supply, Delivery & 194,300,377.58 194,300,377.58 HI-TONE 3-Jan-17 31-Jul-17 100% 100% - All D/G sets intended for LOD, VOD 59,137,386.56 30.44% - 1st Progress Billing (80%) Delivery, and Test of 31 Units of Quick Response Modular Diesel Gensets and Associated Electrical Equipment for SPUG Areas (LVMP16Z646Ss / SO-OPD16-007) covered by Contract No. LOG MSSP 2016-11-125-JPP
Test Construction and Dev’t. Corp.
and MOD were delivered and tested.- Contractor completed the re-test and reconfiguring of the malfunctioning ICNT Mint (Multi Function Controller) as of 08 November 2018.- Delivery of remaining coolant for MOD (Davao) completed. Coolants intended for Zamboanga already delivered on 20 February 2019.
already claimed.
- Final Billing under review/evaluation. Lacking documents such as delivery receipts and Inspection Reports already submitted by the Contractor.
Li id t d d- Liquidated damages already imposed for all the remaining activities beyond the Contract expiry.
1. Construction of SPUG- Bicol Operation’s Warehouse at Ligao City, Albay
Construction 9,530,000.00 8,720,514.84 Verzontal Builders, Inc.
7-Sep-18 Original Expiry:
22-Nov-18
100% 96.38% - Submission of construction methodology, material sample card, brochures/catalogs & material testing approval, 98.97% completed.
8,098,411.82 92.87% - Fifteen (15%) Percent Advance Payment and 1st Progress Billing already claimed.
IV. SPUG OFFICES/QUARTERS/WAREHOUSE
Revised Expiry per
Work Susp/ Resumption:29-Jan-2019
- Delivery, installation of gate valve, hose bibb pipes, fittings and accessories, 96.77% completed.- Painting works, 100% completed.- Plastering works, 100% completed.- Delays/Slippage is due to late delivery/ procurement of materials at site.
- 2nd Progress Billing already claimed.
2. Construction of SPUG B h l Offi d St ff
Supply, Delivery & T t
8,865,000.00 7,991,615.71 RN Engineering 24-Sep-18 Original E i
64.67% 44.06% - Resumption of Work effective 7 J 2019 S i f W k
- Fifteen Percent (15%) Ad P t dBohol Office and Staff
HouseTest Expiry:
21 January 2019
Revised Expiry:
5 May 2019
January 2019. Suspension of Work was issued effective 25 September 2018 due to pending issuance of Forestry Land-Use Agreement (FLAG).- Construction works in progress. - For submission of requirements for the application for Building Permit; meeting conducted on 3 March 2019.
Advance Payment under review/ evaluation.
3. Construction of Operator's Construction 2,064,000.00 2,056,009.33 Shieham Const. & 31-Oct-18 28-Jan-19 100% 71.43% - Construction/ Fabrication/ Installation 308,401.40 15% - Fifteen Percent (15%) Quarter and Office in Languyan DPP
Enterprises works in progress. Delays due to insufficient delivery of construction materials at site.
- Contractor yet to submit material sample cards.
- Implementation Schedule submitted by the Contractor already approved.
Advance Payment already claimed.
Page 24 of 25
REMARKS
PROJECTTITLE
DESCRIPTION/DETAILS
APPROVED BUDGET FOR
THE CONTRACT(ABC)
(PhP)
P.O./CONTRACT
AMOUNT
(PhP)
CONTRACTOR/SUPPLIER
CONTRACT IMPLEMENTATION
SCHEDULE
ACCOMPLISHMENTS(STATUS/UPDATES) BUDGET UTILIZATION
DATESTART
DATECOMPLETION
ACTUAL(%) REMARKS UTILIZATION
(PHP)UTILIZATION
(%)TARGET
(%)
4. Sacol DPP Renovation & Renovation 16, 775,687.02 Shieham Const. & 17-Jan-19 15-Jul-19 29.80% 6.37% - Site mobilization on 11 February 2019. - - - Fifteen Percent (15%) Facilities Improvement Enterprises - Lay-out and excavation of powerhouse
footing foundation in progress. - Temporary relocation of existing gensets for the renovation of powerhouse in progress. - Installation and fabrication of reinforcement bars for column and footing in progress. - Excavation of Powerhouse footing f d ti (C1 F1 & C2 F2) i
Advance Payment under review/evaluation.
foundation (C1-F1 & C2-F2) in progress.- Concrete pouring at the powerhouse footing foundation. - Excavation of foundation of seclusion fence. - Delay/negative slippage due to delayed submission of material sample cards and testing results of materials and insufficient construction materials delivereddelivered.
5. Tandubanak DPP Renovation & Facilities Improvement
Renovation 24,672,128.86 Shieham Const. & Enterprises
17-Jan-19 12-Nov-19 - - - Implementation Schedule already routed for approval.
- Contractor has not yet mobilized at site due to unavailability of boat to transport construction materials. Contractor already advised to expedite the mobilization.
- Release of Fifteen Percent (15%) Advance Payment already requested by the Contractor. Under review/evaluation by the implementing group.
6. Construction of New Rizal DPP, Punta Baja, Rizal, Palawan
Construction 57,332,000.00 56,701,348.00 I. A. Bosque Construction Corporation
21-Mar-19 15-Jan-20 - - - Contract awarded to I. A. Bosque Const. Corp. on 30 October 2018 NP Board Resolution No. 2018-44. Notice to Proceed dated 11 January 2019 already issued last 22 February 2019 and conformed by the Contractor on 14 March 2019.- Kick-off meeting held on 18 March 2019.- EMD to secure the required Environmental Compliance Certificate (ECC).
Prepared by: Reviewed by: Approved by: Noted by:
(Original Signed) (Original Signed)
PE A PCAD Manager PCAD Officer in Charge PMD Officer in Charge PESJOHNNY FELIX P. VILLAREAL NOEMI F. DASALLA ISAGANI G. RABARA BIENVENIDO G. MAÑALAC
(Original Signed) (Original Signed)
PE A, PCAD Manager, PCAD Officer-in-Charge, PMD Officer-in-Charge, PES