national engineering vulnerability assessment of public infrastructure to climate ... · 2020. 12....

37
NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE CHANGE CITY OF WELLAND STORMWATER AND WASTEWATER INFRASTRUCTURE Final Report Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada Prepared by AMEC Environment & Infrastructure February 2012

Upload: others

Post on 26-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE CHANGE

CITY OF WELLAND STORMWATER AND WASTEWATER INFRASTRUCTURE

Final Report

Development of Projected Intensity-Duration-Frequency Curves

for Welland, Ontario, Canada

Prepared by AMEC Environment & Infrastructure

February 2012

Page 2: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then
Page 3: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

   

   

   

   

   

   

   

   

   

   

   

   

   

   

   

   

   

   

 

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table of Contents

1.0 Introduction............................................................................................................ 1

2.0 Data....................................................................................................................... 2

2.1 Historical IDF curve ............................................................................................ 3

2.2 Local Climate Data ............................................................................................. 5

2.3 Projected Climate Data ...................................................................................... 5

3.0 Time Frames ......................................................................................................... 7

4.0 Approach ............................................................................................................... 7

4.1 Candidate Approaches ....................................................................................... 7

4.2 Selected Approach ............................................................................................. 9

4.3 Data Diagnostics .............................................................................................. 10

4.4 Fitting Models ................................................................................................... 11

4.5 Developing Projected Precipitation Intensity Values ........................................ 13

4.6 Treatment of Uncertainty .................................................................................. 15

5.0 Results and Discussion ....................................................................................... 16

5.1 GCM Projections of Precipitation and Temperature ......................................... 16

5.2 Projections of Precipitation Intensities .............................................................. 16

5.3 Interpreting Uncertainty .................................................................................... 21

6.0 References .......................................................................................................... 28

Appendix A: Model Fitting Statistics .............................................................................. 30

AMEC Environment & Infrastructure i

Page 4: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then
Page 5: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

1.0 INTRODUCTION This report provides an overview of the development of projected intensity-duration­frequency curves (IDF curves) for the City of Welland, Ontario, Canada. The objective of the work described here is to develop IDF curves that reflect the changes in the characteristics of precipitation that might be caused by projected changes in climate. Two time frames were specified for projections, namely 2020 and 2050.

Over the last four decades climate scientists have developed a theoretical framework and observational evidence to indicate that the average temperature of the earth is increasing and that part of this increase can be attributed to emissions of greenhouse gases generated by human activities (IPCC, 2007). Modern climate simulation models, referred to as Global Climate Models (GCMs, also referred to as general circulation models), have been used to develop quantitative projections of future changes in temperature, precipitation and other climate variables based on estimates of future emissions of greenhouse gases. These models show a consensus that global average temperature will increase, though the amount of projected temperature increase varies with latitude and is not evenly distributed seasonally. Because increases in global average temperature will increase evaporation, global average precipitation will also increase although there is a high degree of uncertainty regarding the spatial and temporal distribution of those changes in precipitation, and precipitation in some areas of the globe will decrease.

Theory, and analysis of GCM outputs, indicates that warmer temperatures will change the characteristics of precipitation extremes (Kharin, et al., 2007). This scientific information along with recent flood events have motivated infrastructure planners to undertake efforts, like that described herein, to quantify the impact of projected climate change on the IDF curves used as one basis for design of drainage and flood infrastructure.

Welland is located in extreme southeastern Ontario, thirteen kilometers north of the north shore of Lake Erie and eighteen kilometers west of the International Boundary on the Niagara River. Welland is also in close proximity to Lake Ontario, located approximately 23 kilometers south of its south shore. Welland is in the process of rehabilitating and enhancing its wastewater, stormwater and drainage infrastructure.

The climate in Welland has been characterized by observations at a number of weather stations located in proximity to the City, but the longest available record is at Port Colborne, thirteen kilometers south of Welland on the shore of Lake Erie. In 2000, an updated IDF curve was developed based on observations at the Port Colborne station from 1964 through 2000. The documentation for this historical IDF curve included the record of the intensity of annual extreme events for nine event durations ranging from

AMEC Environment & Infrastructure 1

Page 6: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

five minutes to 24 hours. To obtain projected IDF curves, the precipitation intensities in the historical IDF curve were adjusted to reflect projected changes in climate using a statistical modeling technique that is described briefly in the following paragraph and in more detail in the following sections of this report.

The approach selected for this work uses a statistical model that derives the sensitivity of extreme precipitation to climate conditions from the historical climate information for the site. In this case the historical climate was characterized by observations of monthly average temperature and monthly total precipitation at the Port Colborne weather station. The statistical model, which is described in more detail below, was fitted to the local climate data and the historical monthly precipitation maxima using a form of regression. Information about future monthly average temperature and monthly total precipitation was obtained from the output of 112 runs of GCMs. Each GCM run was compared internally to establish a projected future change in temperature and precipitation. These changes were used to adjust the historical record of temperature and precipitation to reflect future conditions. This produced 112 future climate scenarios that were based on the historical record but which reflected the projected future change in climate. This approach, which is referred to as the delta approach is used to reduce some of the inevitable bias inherent in projections of future climate.

The statistical model of extreme precipitation was then run against each of these adjusted records to obtain estimates of climate-impacted extreme precipitation intensities for each of the nine durations and six return intervals. These estimates reflect the bias in the statistical model, so one more run of the statistical model was made against the average historical climate conditions to provide a baseline set of extreme precipitation intensities and this set of baseline intensities was compared against each of the 112 estimates of climate-impacted intensities to determine the change in intensity attributable to the change in climate. These changes were then applied to the values in the historical IDF curve to obtain the final projected values of precipitation intensity.

The 112 projections used to characterize future climate conditions produced an equal number of estimates of projected precipitation intensities. For reporting purposes, these results were aggregated into the mean, maximum and 90th percentile non-exceedance value of precipitation intensity for each duration and return interval.

2.0 DATA This section describes the three data sets used in this work. The objective of the work was to estimate changes to an existing Environment Canada IDF curve rather than to develop a new IDF curve. The nearest location to Welland for which Environment

AMEC Environment & Infrastructure 2

Page 7: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Canada had developed an IDF curve was Port Colborne. Accordingly, the local conditions were characterized with the Port Colborne (6136606) weather station.

2.1 Historical IDF curve The historical IDF curve was obtained from Environment Canada. Figure 1 shows the historical IDF curve. Table 1 shows the underlying data.

In addition to the data included in the IDF file, observations of daily precipitation maxima for the durations in Table 1 were available from Environment Canada for the years 2005, 2006 and 2007.

Figure 1. Historical IDF Curve, Port Colborne 6136606

AMEC Environment & Infrastructure 3

Page 8: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 1. Historical Annual Maximum Precipitation Events Port Colborne, 6136606, mm

Year 5 min

10 min

15 min

30 min 1 h 2 h 6 h 12 h 24 h

1965 5.8 6.3 8.9 13.7 19.8 26.4 33.0 33.0 42.4 1966 6.9 10.7 10.7 10.7 14.0 15.0 22.1 26.2 26.7 1967 7.6 12.2 17.0 26.2 26.7 26.7 26.7 36.1 59.9 1968 8.1 14.5 16.8 19.8 26.9 42.4 81.3 101.3 112.5 1969 6.9 10.2 12.4 12.7 19.8 22.6 32.0 37.3 43.2 1970 8.4 10.9 12.2 16.0 19.3 20.3 26.4 33.3 39.6 1971 8.1 12.4 15.0 21.8 24.6 25.7 26.7 29.5 30.5 1972 5.8 9.4 13.7 17.3 23.4 23.4 27.4 33.8 36.8 1973 7.6 12.7 17.3 25.4 36.6 37.6 39.4 39.9 40.4 1974 6.9 7.9 8.6 11.7 15.2 25.7 29.7 29.7 33.0 1975 12.7 20.3 24.6 31.7 32.0 32.0 32.5 33.5 33.5 1976 4.8 7.9 9.1 11.4 19.0 23.9 23.9 38.1 47.2 1977 12.2 14.5 16.6 33.3 37.6 37.6 42.2 48.0 51.3 1978 6.9 8.8 11.1 15.5 25.7 31.6 35.5 42.0 42.0 1979 8.0 11.4 16.2 26.0 34.2 47.6 80.6 116.4 123.0 1980 11.1 14.8 15.3 17.0 25.5 32.8 33.8 41.9 44.4 1981 8.2 9.6 9.6 11.6 14.4 25.7 32.9 37.2 44.6 1983 8.0 10.5 15.2 27.4 29.3 32.0 44.2 46.5 56.3 1984 9.8 15.0 18.0 26.9 28.9 30.7 30.8 51.8 54.2 1985 7.6 9.5 10.5 12.5 16.2 17.2 23.7 38.9 54.2 1986 12.4 18.4 21.2 24.7 26.5 30.6 35.1 43.0 46.6 1987 8.1 13.0 15.3 21.9 34.8 46.4 56.5 56.5 69.4 1988 8.0 11.3 12.9 14.7 17.0 20.0 22.7 42.7 47.2 1989 8.7 9.9 10.5 10.8 17.9 20.5 20.7 24.2 27.6 1990 7.2 9.0 13.1 21.8 28.0 32.8 35.9 44.9 50.4 1991 14.2 20.0 29.0 34.0 60.0 64.2 65.0 65.0 65.3 1992 6.0 10.4 13.5 20.4 28.4 30.3 32.3 42.9 46.0 1993 6.7 7.5 8.3 12.1 17.6 24.6 42.3 43.8 46.9 1994 7.2 8.5 11.5 14.3 18.3 24.4 50.4 74.6 86.9 1996 7.6 11.1 14.1 25.7 30.8 34.6 36.0 36.0 40.6 1997 7.6 9.6 12.3 15.5 17.6 23.2 45.8 54.2 58.2 1998 3.6 3.9 4.4 5.5 7.1 10.5 18.2 26.2 46.5 1999 9.4 14.1 16.6 20.7 22.2 29.7 38.5 45.0 49.2 2000 6.8 7.4 7.4 8.3 8.5 13.5 24.3 30.3 41.0

AMEC Environment & Infrastructure 4

Page 9: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

2.2 Local Climate Data Local climate data were required to establish the sensitivity of annual extreme precipitation (Table 1) to annual or seasonal average precipitation and temperature. Local climate data were obtained from Environment Canada for the 8 elements shown in Table 2.

Table 2. Historical Climate Data Elements Port Colborne, 6136606

Element Description DAILY MAXIMUM TEMPERATURE DAILY MINIMUM TEMPERATURE DAILY HEATING DEGREE DAYS DAILY COOLING DEGREE DAYS

DAILY MEAN TEMPERATURE DAILY TOTAL RAINFALL

DAILY TOTAL SNOWFALL DAILY TOTAL PRECIPITATION

Data for all elements were provided on a daily timestep. The elements in Table 2 were available from July 1, 1964 through February 27, 2011. In addition, maximum daily precipitation was obtained for several durations for variable periods covering the period 1964 through 2000 and 2004 through 2006.

2.3 Projected Climate Data The objective of this study is to estimate the sensitivity of extreme precipitation events at the Port Colborne weather station to projected climate change. Development of information about projected climate conditions involves three elements, which are common to most climate impact studies:

• Emissions scenarios. Projections of future changes in climate attributed to human activity rely on projections of future concentrations of greenhouse gases (GHG), which in turn depend on current concentrations and future rates of GHG emissions. GHG emissions depend, in complex ways, on socio-economic development, technology, demographics and politics. The Intergovernmental Panel on Climate Change (IPCC) has developed a number of “storylines” of future global conditions, which are used as the basis for estimates of future GHG emissions. These storylines are documented in the Special Report on Emissions Scenarios (SRES, Nakicenovic et al., 2000) and are often referred to as SRES scenarios. The IPCC did not assign a likelihood to the SRES scenarios—all are considered equally probable “alternative images of how the future might unfold” (Nakicenovic et al., 2000, Technical

AMEC Environment & Infrastructure 5

Page 10: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Summary). From the four SRES scenario “families” (A1, A2, B1, B2), only the B1, A1B (a member of the A1 family) and A2 scenarios have been used as the basis for projections on many GCMs. These have come to be known, respectively, as the “low”, “medium” and “high” emissions scenarios, based on their impact on climate conditions in the year 2100.

• Global Climate Simulation. More than 20 global climate models are currently being developed, operated and maintained by national meteorological services, climate research centers and universities around the world. These models have been used to develop quantitative projections of future changes in climate variables, including temperature and precipitation, based on the SRES emissions scenarios. Each GCM is different, but many contain similarities in their conceptual approach and may even share simulation methods and codes. A single GCM will be used to generate many projections, each of which differ by the SRES scenario used to force the GCM, but also by the way in which the model run is initialized and constrained.

• Downscaled Climate Projections. GCMs operate on a grid that may range in scale from 100 to 200 miles on a side, and their output is provided at this same resolution. While each GCM grid cell covers from 10,000 to 40,000 square miles, a substantial watershed might cover a few hundred to a several thousand square miles, and many tributaries drain considerably smaller areas. Before GCM output can be used for analysis of local conditions, or for local hydrologic modeling, it must go through a process called downscaling, which relates the large scale GCM data to detailed terrain and observed climate conditions. In addition, GCM projections contain bias, which is exhibited as systematic error in replicating observed conditions, and these biases are usually reduced during downscaling with an ex post calibration process referred to as bias correction.

This project used a set of readily-available downscaled projections obtained from the bias-corrected and spatially downscaled archive developed by Maurer (2007) according to the methods described in Maurer et al. (2009) and Maurer, et al. (2002) and provided through the World Climate Research Programme's Coupled Model Intercomparison Project phase 3 (CMIP3) multi-model dataset (WCRP, 2009). The archive contains 112 model runs or projections of monthly precipitation and temperature, with each projection consisting of an overlap period from 1950 through 1999 and a projection period from 2000 through 2099. Each projection is the output from a run of one of 16 GCMs using one of the B1, A1B or A2 emissions scenarios. The GCMs in the archive are listed in Table 3.

AMEC Environment & Infrastructure 6

Page 11: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 3. GCMs in Maurer Archive (after Maurer et al., 2009) Modeling Group, Country IPCC Model I.D.

1 Bjerknes Centre for Climate Research BCCR-BCM2.0 2 Canadian Centre for Climate Modeling and Analysis CGCM3.1 (T47) 3 Météo-France/Centre National de Recherches Météorologiques,

France CNRM-CM3

4 CSIRO Atmospheric Research, Australia CSIRO-Mk3.0 5 US Dept. of Commerce/NOAA/Geophysical Fluid Dynamics

Laboratory, USA GFDL-CM2.0

6 US Dept. of Commerce/NOAA/Geophysical Fluid Dynamics Laboratory, USA GFDL-CM2.1

7 NASA/Goddard Institute for Space Studies, USA GISS-ER 8 Institute for Numerical Mathematics, Russia INM-CM3.0 9 Institut Pierre Simon Laplace, France IPSL-CM4 10 Center for Climate System Research (The University of Tokyo),

National Institute for Environmental Studies and Frontier Research Center for Global Change (JAMSTEC), Japan

MIROC3. (medres)

11 Meteorological Institute of the University of Bonn, Meteorological Research Institute of KMA ECHO-G

12 Max Planck Institute for Meteorology, Germany ECHAM5/MPI-OM 13 Meteorological Research Institute, Japan MRI-CGCM2.3.2 14 National Center for Atmospheric Research, USA PCM 15 National Center for Atmospheric Research, USA CCSM3 16 Hadley Centre for Climate Prediction and Research/Met Office UK UKMO-HadCM3

3.0 TIME FRAMES Time frames for this work are summarized in Table 4.

Table 4. Project Time Frames Description Time Frame

Climate simulation overlap period 1950-1999 Climate simulation projection period 2000-2099 2020 projection averaging period 2005-2034 2050 projection averaging period 2035-2064

4.0 APPROACH

4.1 Candidate Approaches The Canadian Standards Association has published Technical Guide, Development interpretation and use of rainfall intensity-duration-frequency information: Guideline for Canadian water resources practitioners (Technical Guide, CSA, 2010), which provides background about the methodologies used to develop IDF curves based on current climate and a discussion about methodologies that are potentially applicable to the

AMEC Environment & Infrastructure 7

Page 12: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

development of IDF curves that reflect projected future climate conditions. Appendix 8 of the Technical Guide provides a review of several approaches that have been applied to estimate the sensitivity of extreme precipitation to projected climate change. For detail on the available methods the reader is directed to the Technical Guide and the references therein; the methods are summarized below in several categories:

• Extrapolation of trends. Linear regression is applied to observed historical data to characterize the trend in short-term precipitation extremes and these statistical models are then used to extend the trend to future periods.

• Direct interpretation of GCM output. GCMs provide output at a daily time step and at a grid scale that can range from about 1 to 4 degrees (approximately 100 to 400 km on a side at the equator, with the longitudinal dimension decreasing with increasing latitude). Some studies (e.g. Kharin et al, 2007) have used daily GCM output to characterize daily precipitation extremes. These methods cannot directly address time steps shorter than the time step of the GCM.

• Direct interpretation of Regional Climate Model Output. Regional climate models (RCMs) use a finer grid scale than is used by a GCM (e.g. 25 km for an RCM versus 100-400 km for a GCM). Because RCMs are usually “nested”, that is their spatial scope is relatively local and their boundary conditions are set by the results of a GCM run, use of an RCM is sometimes referred to as “dynamical downscaling.” RCMs also run at a finer temporal resolution than GCMs and some RCMs can produce output at 1-hour time steps. These data have been used directly to characterize short-term precipitation, but cannot directly address time steps shorter than the time step of the RCM. Because RCMs are computationally expensive to run and their spatial extent is limited, there are fewer runs available, and these runs are influenced by the biases of the GCM from which boundary conditions are taken.

• Applying scale factors to climate model output. Scale factors relate short-term precipitation to longer-term precipitation, e.g. monthly average or total precipitation. This is a downscaling method that is similar to linear regression.

• Applying statistical models to climate model output. Statistical models can be developed to represent a functional relationship between short-term precipitation and a predictor variable, usually at a larger temporal and spatial scale (e.g. monthly total precipitation at a GCM or RCM resolution.) The most common statistical model is a linear model developed using regression. Linear models of the parameters of extreme value distributions (e.g. Gumbel, Weibull) have also been used.

• Conditional weather generators applied to climate model output. Weather generators are stochastic models that generate time series of weather conditions.

AMEC Environment & Infrastructure 8

Page 13: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

These models may be parametric (that is they rely on classical statistical distributions described by parameters) or they can be non-parametric (that is they rely on re-sampling analogs of weather from the historical data) or a combination of the two. When applied to investigating climate change impacts, weather generators are usually conditioned on large-scale weather variables using statistical models as described above or using non-parametric techniques like the K-nearest neighbor technique.

In the approaches described above, climate model output may be “raw” output at the native grid scale of the climate model (either a GCM or a RCM) or downscaled output.

Despite the remarkable improvements in the scientific state of knowledge about the processes that drive weather, and ultimately climate, there is considerable uncertainty about the sensitivity of climate to increasing greenhouse gas concentrations. Because of that uncertainty, and because of practical constraints, each of the methods described above have shortcomings. It is fair to say that all of the methods described above rely to some degree on an assumption that the relationships between large-scale and small-scale processes, both in time and space, will continue unchanged into the future. This is true of all approaches that use downscaling, scale factors and statistical models, including weather generators. Climate models simulate climate sensitivity, but even these models contain statistical sub-models and are limited in spatial and temporal resolution. In short, there is no perfect method to project climate impacts, there will be considerable uncertainty regarding those projections, and this uncertainty should always be considered when making long-term decisions about investment, policy or infrastructure.

4.2 Selected Approach Based on a review of available methods, and considering the objectives and constraints of the current work, an approach employing extreme value statistics was judged to be the best approach for estimating the sensitivity of short-term precipitation to projected climate. This approach, described in Towler, et al., (2010, published after compilation of the Technical Guide), involves fitting linear models of the parameters of an extreme value distribution of a short-term variable to predictor variables, usually long term variables, referred to as “covariates.” A separate model is developed for each precipitation duration and is called the “intensity model.” The method, which is sometimes referred to as generalized linear models (GLM, Furrer and Kaatz, 2007) allows modeling of variables that do not have a normal distribution as well as discrete variables, such as precipitation occurrence. Towler applied the GLM method to estimating peak streamflow, but the method is generally applicable to a wide range of extreme values in addition to streamflow, including precipitation and maximum sea

AMEC Environment & Infrastructure 9

Page 14: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

level, among others (Katz et al., 2002). Note that Katz, et al. (2002) suggest that the generalized extreme value (GEV) distribution is better fits “heavy tails” to distribution of extreme precipitation, resulting in shorter return intervals, but we have used the Gumbel distribution because this is the distribution that has been used historically by Environment Canada for development of IDF curves (CSA, 2010).

In the approach described below the climate predictor variables used to force the GLM model of climate sensitivity are developed using a delta approach and the final adjusted values of precipitation intensity are in turn calculated by a second application of the delta approach to the output of the GLM model. The delta approach and its application are described below.

4.3 Data Diagnostics A diagnostic analysis was conducted to determine the strength of available long-term climate variables in predicting short-term precipitation. The available long-term climate variables were monthly precipitation depth and monthly average temperature. These variables along with monthly rain depth (liquid precipitation) were also available from the local climate record. These variables were aggregated to seasonal and annual values and were also combined to produce indices (on seasonal and annual time frames) and this suite of variables was tested to evaluate the strength of each candidate predictor. The strength of a predictor was assessed using the coefficient of determination estimated using linear regression. These analyses were made using the statistical package “R” (http://www.r-project.org/).

The results of this analysis revealed that statistically significant predictors could not be found for annual precipitation extremes for most durations. Six explanatory variables were screened for all twelve months, including correlation across months, and for nine durations, for a total of 7776 combinations. Many of these relationships showed little explanatory value, particularly for non-summer months. However, analysis showed that 90% percent of extreme precipitation events occurred during the months of June through October. Table 5 shows the occurrence of extreme precipitation at Port Colborne.

Table 6 shows the coefficient of determination for selected variables for the months of June through October, for all nine durations.

The amount of explained variance was very small for all variables for shorter durations but reasonably significant predictors were found for some of the monthly precipitation maxima. It is important to remember that these linear models will not be used to estimate future precipitation intensities; although the amount of explained variance for a linear model was low for many combinations of predictor variables and precipitation

AMEC Environment & Infrastructure 10

Page 15: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

durations, the candidate predictor variables shown in Table 6 were evaluated for their ability to fit a GLM model using the generalized extreme value distribution as described in the following section.

Table 5. Occurrence of Annual Extreme Precipitation, Port Colborne, 6136606 Occurrence of Annual Extreme Precipitation Event

Duration Apr May Jun July Aug Sep Oct Nov Year 5-min 0 3 4 12 11 9 1 0 40 10-min 0 4 5 11 11 6 3 0 40 15-min 0 4 4 11 9 8 4 0 40 30-min 1 3 5 9 11 6 4 1 40 1-hr 0 2 4 10 10 10 4 0 40 2-hr 1 0 4 8 12 11 4 0 40 6-hr 2 0 5 7 11 8 7 0 40 12-hr 2 2 3 5 8 13 7 0 40 24-hr 2 4 1 8 4 5 2 1 27 Total 8 22 35 81 87 76 36 2 Percent 2.3% 6.3% 10.1% 23.3% 25.1% 21.9% 10.4% 0.6% 100%

Table 6. Coefficient of Determination, Monthly Extreme Precipitation P*T=the product of precipitation and temperature

Duration Month Candidate

Predictor 5-min 10-

min 15-min

30-min

1-hr 2-hr 6-hr 12-hr day

June Precipitation 4.3% 9.6% 15.6% 27.7% 36.3% 39.4% 42.7% 42.0% 54.5% Temperature 7.3% 3.1% 2.9% 2.4% 1.0% 0.3% 3.0% 4.1% 3.0% P*T 6.6% 11.7% 18.5% 33.5% 40.9% 42.1% 39.0% 37.3% 50.3%

July Precipitation 22.8% 28.7% 28.4% 31.5% 38.7% 41.0% 46.7% 54.5% 64.0% Temperature 1.5% 3.2% 4.9% 7.8% 6.8% 5.2% 2.8% 2.2% 21.2% P*T 24.6% 31.6% 31.8% 36.0% 43.5% 46.2% 51.3% 58.3% 64.6%

August Precipitation 21.4% 28.1% 30.1% 44.9% 40.9% 44.1% 52.7% 50.1% 28.7% Temperature 1.2% 1.6% 0.9% 4.8% 1.5% 1.7% 1.4% 0.2% 6.1% P*T 22.1% 29.1% 31.8% 45.0% 43.5% 46.8% 57.3% 56.3% 29.4%

September Precipitation 27.3% 25.0% 30.9% 33.0% 39.8% 49.6% 50.5% 57.0% 50.6% Temperature 1.4% 1.6% 1.8% 1.4% 1.3% 0.9% 0.5% 0.4% 0.4% P*T 29.3% 26.8% 32.9% 34.8% 41.6% 51.5% 52.2% 55.7% 49.7%

October Precipitation 3.8% 7.0% 11.2% 11.9% 18.3% 25.8% 27.5% 25.0% 63.4% Temperature 19.8% 21.7% 20.7% 21.2% 14.7% 8.2% 2.2% 1.4% 0.5% P*T 8.9% 14.0% 19.4% 20.3% 26.6% 31.9% 29.1% 24.8% 54.3%

4.4 Fitting Models For this work the generalized extreme value (GEV) distribution was fit to the historical annual precipitation maxima using potential predictor variables. The GEV distribution

AMEC Environment & Infrastructure 11

Page 16: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

can assume three possible distribution types, known as the Gumbel, Fréchet and Weibull. The Gumbel is the distribution used by Environment Canada to estimate IDF curves; it is a relatively “light-tailed” distribution with a fixed shape. Using the Frechet variant of the GEV would allow a model to be fit to the shape parameter, which would affect the “weight” of the tail, which is of the most interest in modeling extreme values. The strength of predictors was evaluated to condition the shape parameter of the Frechet distribution explicitly, but no variables showed appreciable strength. This may be because there are not a sufficiently large number of annual values to derive a significant relationship. Accordingly, the Gumbel distribution was adopted.

The GEV models were fitted using the extRemes package (http://cran.r­project.org/web/packages/estRemes/extRemes.pdf) in the statistical package “R” (http://www.r-project.org/). Separate models were fit for each of the months June through October and for each duration. For each month/duration three principal predictors were evaluated, average precipitation, average temperature and the product of average temperature and average precipitation. For each month/duration, models based on different predictors were accepted based on statistical significance at a criterion of 0.05; acceptable models were found all month/duration combinations. Where more than one model was accepted, the Akaike Information Criterion (AIC, explained in Towler, et al., 2010) was used to select the best model.

Of the 45 models required, for 32 the best predictor was the product of precipitation and temperature, for 12 models the best predictor was average precipitation and for one model the best predictor was temperature. Table 7 shows the best predictor for each of the combinations of duration and month of the year.

Appendix A provides the parameters and goodness of fit statistics for the models shown in Tables 6 and 7.

Table 7. Best Predictor for a given duration and month of the year. T=Temperature, P=Precipitation, P*T=precipitation * temperature

Month Duration June July August September October

5_min T P*T P P P 10_min P*T P*T P P*T P*T 15_min P*T P*T P*T P*T P*T 30_min P*T P*T P*T P*T P*T

1_hr P*T P*T P*T P*T P*T 2_hr P*T P*T P*T P*T P 6_hr P P*T P*T P*T P*T 12_hr P P*T P*T P P*T 24_hr P P P*T P P*T

AMEC Environment & Infrastructure 12

Page 17: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

4.5 Developing Projected Precipitation Intensity Values The projected values of precipitation intensity, which make up the IDF curve, were developed using two applications of the “delta” method (Hamlet and Lettenmaier, 1999; Miller, et al., 2003). In the delta method, climate projections are used to estimate the change in climate variables and this change is then applied to the observed record. The projected change is determined for each climate projection by comparing the climate condition during the overlap period from the climate condition at some future point in time. The overlap period is the period of time where the model simulation overlaps the observed climate; in the projections used in this work the overlap period is 1950 through 1999. In this work, the climate condition during the overlap period is represented as the average for the period 1950-1999 and the climate condition at the future point in time is represented as a 30-year average centered on that point in time. The projected IDF curves were based on two future time periods, 2020 and 2050. The method for adjusting climate variables is illustrated in Figure 2.

In adjusting precipitation the “delta” is in the form of a ratio as shown in Equation 1.

PPp = Pc P

sf (1) so

Where: Psf is the simulated future precipitation, Pso is the simulated overlap precipitation, Pc is the current observed precipitation and Pp is the projected future precipitation. In adjusting temperature, the “delta” was in the form of an offset, as shown in Equation 2.

Tp = Tc + (Tsf − Tso ) (2)

Where: Tsf is the simulated future temperature, Tso is the simulated overlap temperature, Tc is the current observed temperature and Tp is the projected future temperature.

In this application the delta approach is preferred over using climate projections directly because the delta method reduces the bias inherent in climate simulations.

The GLM also exhibits inherent bias. In principal every aspect of the method Environment Canada uses to develop IDF curves could be duplicated which would allow for exact replication of the historical precipitation intensities. However, once the distributions are modified in the GLM framework to include covariates the method and results would deviate from those of Environment Canada. Further, in this application a different statistical package and a different method of fitting (maximum likelihood rather than the method of moments) have been used. Because these differences will introduce bias into the estimates of precipitation intensities, the use a second

AMEC Environment & Infrastructure 13

Page 18: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

application of the delta method was adopted to adjust the historical IDF curve. The calculation is done in the same manner as shown in Equations 1 and 2. The method is illustrated in Figure 3.

Figure 2. Development of Adjusted Observed Climate using the delta method

Simulated Future Climate

Simulated Overlap Climate

“Deltas” (ratio) Adjust

(Eqns. 1 & 2)

Current Climate

Adjusted Observed Climate

Figure 3. Development of the final projected IDF

Observed Climate

Adjusted Observed Climate

Intensity Model

Intensity Model

Baseline IDF

Climate-Impacted

IDF

Historical IDF

IDF Deltas

Projected IDF

Adjust (Eq. 1)

Baseline Case

Climate-impacted Case

For each precipitation duration, the intensity model is run once against the observed climate to generate a baseline intensity estimate. The intensity model is then run again for each climate projection, this time using the adjusted observed climate value

AMEC Environment & Infrastructure 14

Page 19: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

developed from that projection. This generates, for each projection, a climate-impacted probability distribution from which climate impacted precipitation intensities are generated for each return interval. The final projected precipitation intensities are calculated using Equation 1.

Projected and observed intensities are first estimated for each month, each duration and each frequency. Then, for each duration and frequency, the maximum of the monthly intensities is determined. This is done for both the historical and the projected case and the ratio of the calculated historical annual intensity and the calculated projected annual intensity is used to estimate the climate sensitivity of the annual extreme precipitation in the same manner as is shown in Equation 1.

4.6 Treatment of Uncertainty All measurements contain uncertainty, and estimates of future conditions are more uncertain than measurements. Each element of a climate impact analysis contains its own degree of uncertainty. These individual uncertainties do not add up in a straightforward way, but they do interact and each added element does increase the overall uncertainty of the final estimate of impact. The approach adopted for this work is intended to make the uncertainty arising from climate models as apparent as possible, so as to allow well-informed judgments regarding future water resources planning.

In North America, the available projections from global climate models (GCMs) show that temperature is highly likely to increase. However, projections of future precipitation are more uncertain; in some parts of North America model projections disagree on both the sign and magnitude of changes in precipitation. The sources of this uncertainty include the data and structure of the GCMs, the methods used to relate GCM projections to points or small areas on the earth’s surface (downscaling), and the projections of future greenhouse gas emissions. Regardless of its source, uncertainty should at least be recognized and ideally should be quantified when climate projections are used for planning purposes.

As a practical matter, uncertainty in climate projections manifests in disagreement between individual projections of future climate conditions and impacts. There are 112 statistically downscaled projections of future climate conditions (monthly average temperature and precipitation) that are readily available for the Port Colborne area. The most comprehensive picture of uncertainty in future conditions can be obtained by analyzing a large ensemble of projections, as recommended in the CSA Technical Guidelines. Accordingly, all of the available projections have been used to produce, for each duration period and frequency, an ensemble containing 112 estimates of precipitation intensity.

AMEC Environment & Infrastructure 15

Page 20: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Neither the climate projections nor the results have been broken down by according to the SRES emission scenarios because the intention was to represent the uncertainty in climate projections collectively, regardless of source.

The overall results include the ensemble mean, the ensemble maximum and the 90th

percentile non-exceedance value for each intensity estimate. How to interpret the range of projected results is a policy decision; some additional discussion regarding the interpretation of uncertainty is provided in Section 5.3.

5.0 RESULTS AND DISCUSSION

5.1 GCM Projections of Precipitation and Temperature The evolution over time of projected precipitation and temperature for all 112 projections in the Maurer archive is shown as 30-year rolling mean values in Figures 4 and 5.

It is apparent in Figure 4 that there is some model-to-model disagreement over the magnitude of projected precipitation, however the disagreement at this location is substantially less than at locations at lower latitudes and at more interior locations in the continental land mass. Figure 5 illustrates that while individual GCMs may project different magnitudes of future temperature, all GCMs are projecting an increase in temperature

5.2 Projections of Precipitation Intensities Table 8 shows the precipitation intensities from the historical IDF curve from Environment Canada. These precipitation intensities were adjusted by the projected change, as described above, to obtain the projected precipitation intensities, which are shown for the three projection periods in Tables 9 and 10. Projected precipitation intensities are reported as the maximum, mean and 90th percentile of the 112 values estimated.

AMEC Environment & Infrastructure 16

Page 21: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

   

   

Me

an

An

nu

al

Te

mp

era

ture

, d

eg

ree

s C

16.00

14.00

12.00

10.00

8.00

6.00

4.00

2.00

0.00

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Figure 4. Evolution of Projected Precipitation Vertical bar denotes end of overlap period and beginning of projection period

Thin, colored lines represent individual projections. Black line represents mean of all projections.

Me

an

An

nu

al

To

tal

Pre

cip

oit

ati

on

, m

m

1,200

1,000

800

600

400

200

0

Trailing 30-Year Projected Mean Annual Precipitation Port Colborne, ON

1,400

Year

19

79

19

82

19

85

19

88

19

91

19

94

19

97

20

00

20

03

20

06

20

09

20

12

20

15

20

18

20

21

20

24

20

27

20

30

20

33

20

36

20

39

20

42

20

45

20

48

20

51

20

54

20

57

20

60

20

63

20

66

20

69

20

72

20

75

20

78

20

81

20

84

20

87

Overlap Period Projection Period

20

90

20

93

20

96

20

99

Figure 5. Evolution of Projected Temperature Vertical bar denotes end of overlap period and beginning of projection period

Thin, colored lines represent individual projections. Black line represents mean of all projections.

Trailing 30-Year Projected Mean Annual Temperature Port Colborne, ON

Overlap Period Projection Period

19

79

19

82

19

85

19

88

19

91

19

94

19

97

20

00

20

03

20

06

20

09

20

12

20

15

20

18

20

21

20

24

20

27

20

30

20

33

20

36

20

39

20

42

20

45

20

48

20

51

20

54

20

57

20

60

20

63

20

66

20

69

20

72

20

75

20

78

20

81

20

84

20

87

20

90

20

93

20

96

20

99

AMEC Environment & Infrastructure 17

Page 22: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 8. Historical IDF Table, Port Colborne, 6136606 Precipitation intensities over the specified duration, mm/hr

Return Interval, Years Duration 2 5 10 25 50 100

5 min 92.8 116.3 131.8 151.5 166.0 180.5 10 min 64.5 83.6 96.2 112.2 124.1 135.8 15 min 52.1 69.1 80.3 94.5 105.1 115.5 30 min 35.7 48.9 57.6 68.7 76.9 85.0

1 hr 22.9 31.6 37.4 44.7 50.2 55.5 2 hr 13.8 18.6 21.7 25.7 28.6 31.6 6 hr 5.8 8.1 9.5 11.4 12.8 14.2 12 hr 3.5 4.9 5.9 7.1 7.9 8.8 24 hr 2.0 2.8 3.3 3.9 4.4 4.8

AMEC Environment & Infrastructure 18

Page 23: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 9. Projected IDF Table, 2020 Precipitation intensities over the specified duration, mm

Maximum Return Interval, Years

Duration 2 5 10 25 50 100 5 min 133.9 150.6 163.3 180.5 193.5 206.8 10 min 89.9 103.2 113.2 126.7 136.9 147.2 15 min 71.6 83.7 92.6 104.5 114.1 124.3 30 min 49.0 61.2 69.5 80.3 88.4 96.3

1 hr 31.9 39.9 45.5 52.6 58.0 63.2 2 hr 19.2 23.5 26.4 30.3 33.1 36.0 6 hr 8.4 10.6 12.0 13.8 15.2 16.6 12 hr 4.7 6.2 7.4 8.6 9.4 10.2 24 hr 2.8 3.6 4.2 4.8 5.3 5.7

90th Percentile Return Interval, Years

Duration 2 5 10 25 50 100 5 min 113.4 133.1 147.0 165.1 178.7 192.5

10 min 76.6 91.8 102.5 117.2 128.7 140.0 15 min 61.7 75.3 85.7 99.2 109.3 119.6 30 min 42.6 54.7 63.1 74.1 82.2 90.2

1 hr 27.2 35.4 41.1 48.3 53.8 59.1 2 hr 16.6 20.9 23.9 27.8 30.7 33.6 6 hr 7.1 9.3 10.6 12.5 13.9 15.3 12 hr 3.9 5.5 6.6 7.8 8.6 9.5 24 hr 2.4 3.2 3.7 4.3 4.8 5.2

Mean Return Interval, Years

Duration 2 5 10 25 50 100 5 min 104.2 125.3 139.8 158.4 172.3 186.3

10 min 70.8 87.2 98.7 113.9 125.4 136.9 15 min 57.6 72.3 82.9 96.7 107.1 117.4 30 min 39.1 51.8 60.4 71.3 79.5 87.5

1 hr 25.1 33.5 39.2 46.4 51.9 57.2 2 hr 15.2 19.7 22.7 26.7 29.6 32.6 6 hr 6.4 8.7 10.0 11.9 13.3 14.7 12 hr 3.6 5.1 6.2 7.4 8.2 9.1 24 hr 2.2 3.0 3.5 4.1 4.6 5.0

AMEC Environment & Infrastructure 19

Page 24: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 10. Projected IDF Table, 2050 Precipitation intensities over the specified duration, mm

Maximum Return Interval, Years

Duration 2 5 10 25 50 100 5 min 142.8 158.2 170.4 187.1 200.0 213.1

10 min 95.7 108.2 117.9 131.1 141.2 151.4 15 min 75.9 87.4 96.2 107.9 116.8 125.7 30 min 50.4 62.5 70.8 81.5 89.5 97.5

1 hr 32.8 40.8 46.3 53.4 58.8 64.0 2 hr 19.8 24.0 26.9 30.7 33.5 36.5 6 hr 8.7 10.9 12.2 14.1 15.5 16.8 12 hr 4.8 6.4 7.5 8.7 9.5 10.4 24 hr 2.8 3.7 4.3 4.9 5.4 5.8

90th Percentile Return Interval, Years

Duration 2 5 10 25 50 100 5 min 121.0 139.6 153.0 170.8 184.2 197.7

10 min 81.5 96.0 106.4 120.2 131.1 141.5 15 min 65.3 78.2 88.0 101.3 111.4 121.5 30 min 45.1 57.3 65.7 76.6 84.7 92.7

1 hr 29.2 37.3 42.7 49.9 55.3 60.5 2 hr 17.6 21.9 24.8 28.7 31.5 34.5 6 hr 7.5 9.7 11.1 13.0 14.4 15.8 12 hr 4.2 5.7 6.8 8.1 8.9 9.8 24 hr 2.5 3.3 3.9 4.5 5.0 5.4

Mean Return Interval, Years

Duration 2 5 10 25 50 100 5 min 108.9 129.1 143.3 161.7 175.4 189.2

10 min 73.6 89.4 100.4 115.0 126.2 137.4 15 min 59.6 74.0 84.2 97.8 108.1 118.4 30 min 40.5 53.1 61.6 72.6 80.6 88.7

1 hr 26.1 34.3 40.0 47.2 52.6 57.9 2 hr 15.8 20.2 23.2 27.1 30.0 33.0 6 hr 6.7 8.9 10.3 12.2 13.6 15.0 12 hr 3.7 5.2 6.3 7.6 8.4 9.3 24 hr 2.2 3.1 3.6 4.2 4.7 5.1

AMEC Environment & Infrastructure 20

Page 25: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

5.3 Interpreting Uncertainty Uncertainty reflects imperfection in our state of knowledge, as distinguished from variability, which is the effect of random processes. In practice, such a distinction is not clear cut, as, for example, the variability in atmospheric processes leads to considerable uncertainty about tomorrow’s weather. Nevertheless, it is important to respect the distinction, because while variability can be addressed in quantitative ways, uncertainty must be addressed, at least in part, by subjective judgment (Vick, 2002). Accordingly, deciding how to use the results of this work in the face of uncertainty will be a policy decision. Some background on the sources of uncertainty and suggestions on how to consider the results herein are provided in the following paragraphs.

Barsugli, et al. (2009) identified the following sources of uncertainty in projections of future climate conditions:

Climate Drivers—The anthropogenic component of climate drivers is greenhouse gas emissions which are formally quantified in emission scenarios. These scenarios in turn depend on projections of future socio-economic, demographic and technical factors.

Climate Sensitivity—This is represented by the climate models themselves. The imperfections in climate models arise from coarse resolution, limitations in simulation of feedback mechanisms, limited knowledge of initial conditions and a number of other factors.

Downscaling—This is required because of the coarse resolution of climate models and the local nature of impact assessments. All downscaling techniques introduce uncertainty.

In addition, there is uncertainty in the models used to assess impact. These can include hydrologic models, statistical models (as is the case in this work), hydraulic models and operations models.

Wilby and Harris (2006) found that the greatest uncertainty in climate impact studies arose from the climate models themselves, followed, in order, by the downscaling method, the hydrology model structure, hydrology model parameters (i.e. the calibration of the model) and finally by the uncertainty in future emissions scenarios.

Uncertainty in climate drivers and climate sensitivity can be represented by using a large number (an ensemble) of climate projections. Fortunately, reasonably large ensembles of climate projections are available and can be obtained with a relatively low effort. However, the readily available projections of climate conditions are derived using one downscaling technique, so the uncertainty inherent in downscaling is not represented in the projection ensemble. This uncertainty may be considerable.

AMEC Environment & Infrastructure 21

Page 26: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

The additional uncertainty arising from impact models is not ordinarily evaluated in impact studies, as using multiple hydrologic models, each with multiple calibrations along with multiple hydraulic or operations models is simply too costly for most agencies. However, it is important to recognize that decision-makers have routinely relied on the results of impact models as the basis for planning and operational decisions, and thus have implicitly accepted the uncertainties in those models.

This work involves a statistical model that, strictly speaking, serves as a second downscaling method. The model takes as inputs projections of climate conditions, downscaled to average conditions over a 1/8th degree grid cell and further downscales those conditions to a single point, in this case the Port Colborne station. The model also relates monthly average conditions to monthly, and eventually annual, extreme events. The model assumes that there is a causal relationship between seasonal values of the predictor variables (total precipitation and average temperature) and seasonal maximum precipitation intensities, and that that relationship will remain unchanged as climate evolves. It can be safely assumed that in strict terms this assumption will not hold up, but it is the basis, at some level, of all estimates of future conditions.

The results presented herein represent one estimate of the range of future extreme precipitation intensity. That range is informed by the range of future projections of monthly average climate conditions, which themselves reflect the range of emissions scenarios and the different degrees of climate sensitivity among the GCMs. However, it is exceedingly important to recognize that an ensemble of projections, such as the one used in this study, may not capture the full range of uncertainty. That is, there is some unknown and unknowable probability that the actual future conditions are not contained in the range of projections in any given ensemble. Further, as noted above, there is additional uncertainty inherent in the downscaling technique and the statistical model that are not reflected in the currently-available ensembles.

Accordingly, the results of this work should be used in combination with all relevant sources of information using careful professional judgment.

5.4 Applying These Results

Table 11 shows a comparison of the existing Welland (1963) IDF curve with the current Port Colborne (2000) IDF curve. The changes are relative to the 1963 curve, so a negative value indicates that the precipitation intensity in the 2000 curve is lower than the value in the 1963 curve for the corresponding duration/return interval. Blank cells are combinations of duration and return interval that are not available in the 1963 curve.

AMEC Environment & Infrastructure 22

Page 27: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 11. Comparison of 1963 IDF curve with 2000 IDF curve Percent change in 2000 curve compared to 1963 curve

Return Interval, Years Duration 2 5 10 25 50 100

5 min n/a n/a n/a n/a n/a n/a 10 min -17% -11% -9% -3% -6% n/a 15 min -18% -12% -7% -2% -5% n/a 30 min -12% -8% -6% -3% -5% n/a

1 hr -2% -6% -7% -8% -10% n/a 2 hr 1% -6% -15% -18% -41% n/a 6 hr 9% -2% -11% -11% -18% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

Table 11 shows that the 1963 curve was conservative relative to the estimates made in the 2000 curve. Thus, adoption of the 2000 curve would effect a relaxation of planning standards for many types of infrastructure.

Tables 12 and 13 show the same comparison for the projected values for both 2020 and 2050.

Review of Tables 11 through 13 show that the 1963 curves were conservative relative to the current estimates and even relative to the projected values for many duration/return interval combinations. In those instances, it is reasonable to retain the 1963 intensities. However, doing so does not insure that those intensities will be appropriate, it simply maintains current practice.

When considering how to interpret the projected values the first thing to consider is whether to use the 2020 or 2050 estimates. For most duration/return-interval combinations there is not a large difference in estimated intensity between 2020 and 2050 (a maximum of 7% and an average of about 3%). Therefore, it is reasonable to use estimates from either time frame, but a mildly conservative choice would be to use the 2050 estimates.

AMEC Environment & Infrastructure 23

Page 28: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 12. Comparison of 1963 IDF Curve With Projected 2020 IDF Curve Percent change in 2020 curve compared to 1963 curve

Maximum Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a 10 min 15% 10% 8% 9% 4% n/a 15 min 13% 6% 7% 8% 3% n/a 30 min 21% 15% 14% 14% 9% n/a

1 hr 36% 19% 13% 9% 4% n/a 2 hr 40% 19% 4% -3% -32% n/a 6 hr 58% 28% 12% 8% -3% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

90th Percentile Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a 10 min -2% -2% -3% 1% -3% n/a 15 min -3% -4% -1% 3% -1% n/a 30 min 5% 3% 4% 5% 1% n/a

1 hr 16% 6% 2% 0% -4% n/a 2 hr 21% 5% -6% -11% -37% n/a 6 hr 34% 12% -1% -2% -11% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

Mean Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a

10 min -9% -7% -6% -2% -5% n/a 15 min -9% -8% -4% 0% -3% n/a 30 min -4% -3% -1% 1% -2% n/a

1 hr 7% 0% -3% -4% -7% n/a 2 hr 11% -1% -11% -15% -39% n/a 6 hr 21% 5% -6% -7% -15% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

AMEC Environment & Infrastructure 24

Page 29: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table 13. Comparison of 1963 IDF Curve with Projected 2050 IDF Curve Percent change in 2050 curve compared to 1963 curve

Maximum Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a 10 min 23% 15% 12% 13% 7% n/a 15 min 19% 11% 11% 12% 6% n/a 30 min 24% 17% 16% 15% 10% n/a

1 hr 40% 21% 15% 10% 5% n/a 2 hr 44% 21% 6% -2% -31% n/a 6 hr 63% 32% 14% 10% -1% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

90th Percentile Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a 10 min 5% 2% 1% 3% -1% n/a 15 min 3% -1% 2% 5% 1% n/a 30 min 11% 7% 8% 9% 4% n/a

1 hr 25% 11% 6% 3% -1% n/a 2 hr 28% 11% -2% -8% -35% n/a 6 hr 41% 18% 4% 1% -8% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

Mean Return Interval, Years

Duration 2 5 10 25 50 100 5 min n/a n/a n/a n/a n/a n/a

10 min -6% -5% -4% -1% -4% n/a 15 min -6% -6% -3% 1% -2% n/a 30 min 0% 0% 1% 3% -1% n/a

1 hr 11% 2% -1% -2% -6% n/a 2 hr 15% 2% -9% -13% -38% n/a 6 hr 26% 8% -4% -5% -13% n/a 12 hr n/a n/a n/a n/a n/a n/a 24 hr n/a n/a n/a n/a n/a n/a

The projected values, shown in Tables 9 and 10, display significant differences across the mean, the 90th percentile value and the maximum value. Conventionally, the maximum value is often excluded as the basis for planning decisions because it represents a single estimate and is therefore quite sensitive to error or artifacts. Quantile values, such as the 90th percentile value reported in Tables 9 and 10, and the

AMEC Environment & Infrastructure 25

Page 30: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

mean, are estimated in the context of all values and are therefore not as volatile. This is reflected in Tables 9 and 10 where there is a much larger difference between the 90th

percentile value and the maximum than there is between the mean and the 90th

percentile value. The range between the 90th percentile and the maximum reflects only 10% of the GCM projections, whereas the difference between the 90th percentile value and the mean reflects approximately 40% of the GCM projections. Accordingly, it is probably appropriate to consider using the 90th percentile value as an upper bound when considering how to develop new planning guidance. It is important to consider, however, that using a value above the mean can be considered a conservative choice since approximately 50% of the projected futures resulted in intensities lower than the reported mean value.

When making decisions that will be affected by climate, it is important to consider that our understanding of climate and climate change will increase with time, so a decision that can be delayed may benefit from new and better information. For decisions that must be made now, it is important to consider the lifetime of the decision. Decisions with shorter lifetimes, less than about 20 years, for example, will have less exposure to the impacts of climate change. Decisions with longer lifetimes, around fifty years or more, for example, are much more likely to exist in a substantially different climate. The degree of rigor of analysis in decision-making should take into account the decision lifetime.

It is also appropriate to consider the nature of the consequences of the failure of infrastructure. If the consequence of failure is destruction of infrastructure or property, then more conservatism is warranted than would be the case where a failure results in temporary inconvenience.

Finally, it is crucially important to ask if these projected intensities make sense given the broad experience with infrastructure in Welland. Welland has used the existing IDF curve for almost 50 years—how well has it protected people and property in that considerable period? Is there evidence that the current practice is substantially under- or over-protective? Are there particular durations of storms that are particularly damaging? Consideration should be given to expected costs versus expected reductions in losses. Anecdotal information regarding recent storm events should also be considered. There is considerable spatial variability in precipitation, but measurements of precipitation are made at point locations. Flood and drainage infrastructure and natural watersheds, on the other hand, integrate the effect of precipitation over larger areas and reflect the shape and motion of storms, so if historical storms have overwhelmed infrastructure designed based on the current IDF curve, that event provides evidence that the precipitation intensities in the current IDF curve may underestimate the impact of actual precipitation events and suggests a more

AMEC Environment & Infrastructure 26

Page 31: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

conservative interpretation of the available information. Given all these considerations, it is entirely appropriate to develop an official IDF curve that is a hybrid of the existing curve, projected values, and values set based on judgment, considering all of the available information.

AMEC Environment & Infrastructure 27

Page 32: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

6.0 REFERENCES Barsugli, J., Anderson, C., Smith, J., Vogel, J. (2009). Options for Improving Climate

Modeling to Assist Water Utility Planning for Climate Change. Water Utility Climate Alliance, Denver, Colorado.

Canadian Standards Association (2010). Technical Guide. Development, interpretation and use of rainfall intensity-duration-frequency (IDF) information: Guideline for Canadian water resources practitioners. Review Draft.

Furrer, E. M. and R. W. Katz (2007). Generalized linear modeling approach to stochastic weather generators. Climate Research, Vol. 34: 129-144, 2007.

Hamlet, A.F., and D.P. Lettenmaier (1999). Effects of climate change on hydrology and water resources in the Columbia River Basin. Journal of the American Water Resources Association 35(6):1597–1623

Intergovernmental Panel on Climate Change (IPCC) (2007). Climate Change 2007: The Physical Science Basis. Contribution of Working Group I to the Fourth Assessment Report of the Intergovernmental Panel on Climate Change [Solomon, S., D. Qin, M. Manning, Z. Chen, M. Marquis, K.B. Averyt, M. Tignor and H.L. Miller (eds.)]. Cambridge University Press, Cambridge, United Kingdom and New York, NY, USA.

Katz, R. W., M. B. Parlange and P. Naveau (2002). Statistics of extremes in hydrology. Advances in Water Resources 25 (2002) 1287–1304

Kharin, V.V., F.W. Zwiers, X. Zhang and G.C. Hegerl (2007). Changes in temperature and precipitation extremes in the IPCC ensemble of global coupled model simulations. Journal of Climate, 20 (8), 1419-1444.

Maurer, E.P., A.W. Wood, J.C. Adam, D.P. Lettenmaier, and B. Nijssen (2002). A long­term hydrologically-based data set of land surface fluxes and states for the conterminous United States, Journal of Climate, 15:3237-3251.

Maurer, E. P., L. Brekke, T. Pruitt, and P. B. Duffy (2007). 'Fine-resolution climate projections enhance regional climate change impact studies', Eos Trans. AGU, 88(47), 504. http://www.engr.scu.edu/~emaurer/global_data/. Accessed January 17, 2011.

Maurer E. P., Adam J. C. and A. W. Wood (2009). Climate model based consensus on the hydrologic impacts of climate change to the Rio Lempa basin of Central America. Hydrol. Earth Syst. Sci., 13, 183–194, 2009

AMEC Environment & Infrastructure 28

Page 33: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Miller, N.L., K. Bashford, and E. Strem (2003). “Potential Climate Change Impacts on California Hydrology,” Journal of the American Water Resources Association, 39, 771–784.

Nakicenovic, Nebojša, Ogunlade Davidson, G. Davis, A. Grübler, T. Kram, E. Lebre La Rovere, B. Metz, T. Morita, W. Pepper, H. Pitcher, A. Sankovski, P. Shukla, R. Swart, R. Watson, Z. Dadi (eds). Intergovernmental Panel on Climate Change (IPCC) (2000). Emissions Scenarios. A Special Report of Working Group III of the Intergovernmental Panel on Climate Change. Cambridge University Press, Cambridge, UK and New York, NY, 599 pp. Available online http://www.grida.no/climate/ipcc/emission/index.htm.

Towler, E., Rajagopalan, B., Gilleland, E., Summers, S., Yates, D., and R. W. Katz (2010). Modeling hydrologic and water quality extremes in a changing climate: A statistical approach based on extreme value theory. Water Resources Research, Vol. 46, W11504, doi:10.1029/2009WR008876, 2010

Vick, S. G. (2002). Degrees of Belief: Subjective Probability and Engineering Judgment. Reston Virginia: ASCE Press.

Wilby R. L. and I. Harris (2006). A framework for assessing uncertainties in climate change impacts: Low-flow scenarios for the River Thames, UK, Water Resources Research, Vol. 42, W02419, 2006.

World Climate Research Programme's (WCRP) (2009). Coupled Model Intercomparison Project phase 3 (CMIP3) multi-model dataset. Archive of downscaled climate projections; served at: http://gdo-dcp.ucllnl.org/downscaled_cmip3_projections/.

AMEC Environment & Infrastructure 29

Page 34: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

APPENDIX A: MODEL FITTING STATISTICS Table A-2 shows the statistics resulting from fitting models to nine precipitation durations for five months. Table A-1 provides descriptions of the abbreviations used in Table A-2.

Table A-1. Description of Abbreviations Abbreviation Description

No Cov. Distribution fitted with no covariates. This is the conventional distribution, fitted using the method of maximum likelihood.

P Linear model of location parameter fitted using precipitation as the covariate

T Linear model of location parameter fitted using temperature as the covariate

P*T Linear model of location parameter fitted using the product of precipitation and temperature as the covariate

Mu0 Value of the intercept for the location parameter in the fitted linear model.

Mu1 Value of the slope for the location parameter in the fitted linear model.

Sigma Value of the shape parameter. Mu0 SE Standard error for the estimate of the intercept of

the location parameter. Mu1 SE Standard error for the estimate of the slope of the

location parameter. Sigma SE Standard error of the estimate of shape parameter.

AIC Akaike Information Criterion. p.val Estimate of statistical significance.

Models were accepted if the estimate of statistical significance was less than 5%. These values are highlighted green in Table A-2. The best model was that with the lowest Akaike Information Criterion (AIC). The predictor labels for the selected models are highlighted yellow in Table A-2.

AMEC Environment & Infrastructure 30

Page 35: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

Table A-2. Model fitting statistics June 5_min

No Cov. P T P*T Mu0 3.66 2.69 -4.65 3.76 Mu1 0.01 0.45 7.6E-05 Sigma 1.73 1.69 1.54 1.80 Mu0 SE 0.31 0.82 3.09 0.68 Mu1 SE 0.01 0.17 0.00 Sigma SE 0.22 0.21 0.20 0.24 AIC 151.93 150.32 145.65 151.91 p.val 20.45% 1.22% 90.04%

July 5_min No Cov. P T P*T

Mu0 4.05 1.36 4.16 1.11 Mu1 0.04 0.00 2.1E-03 Sigma 2.76 2.23 2.76 2.06 Mu0 SE 0.47 0.71 9.12 0.60 Mu1 SE 0.01 0.42 0.00 Sigma SE 0.35 0.28 0.35 0.29 llh -97.78 -90.17 -97.78 -89.33 AIC 197.55 182.35 197.55 180.65 p.val 0.01% 98.61% 0.00%

August 5_min No Cov. P T P*T

Mu0 4.15 1.98 11.74 4.21 Mu1 0.03 -0.36 -2.37E-18 Sigma 2.31 2.11 2.24 2.12 Mu0 SE 0.40 0.88 6.01 0.67 Mu1 SE 0.01 0.28 0.00 Sigma SE 0.29 0.26 0.28 0.24 AIC 183.83 176.52 182.30 184.52 p.val 0.68% 21.55% 40.78%

September 5_min No Cov. P T P*T

Mu0 3.73 1.80 -3.05 2.97 Mu1 0.02 0.39 5.7E-04 Sigma 2.06 1.88 2.01 1.93 Mu0 SE 0.36 0.77 5.52 0.62 Mu1 SE 0.01 0.32 0.00 Sigma SE 0.28 0.25 0.27 0.29 AIC 169.52 161.25 168.03 163.50 p.val 0.40% 22.32% 1.41%

October 5_min No Cov. P T P*T

Mu0 2.11 1.33 -0.41 1.89 Mu1 0.01 0.23 3.2E-04 Sigma 1.21 1.12 1.17 1.14 Mu0 SE 0.21 0.41 1.42 0.29 Mu1 SE 0.00 0.13 0.00 Sigma SE 0.17 0.16 0.17 0.17 AIC 137.89 133.87 134.67 135.09 p.val 4.47% 7.23% 9.37%

10_min No Cov. P T P*T

Mu0 5.26 3.12 -4.55 3.85 Mu1 0.03 0.53 1.2E-03 Sigma 2.56 2.42 2.41 2.39 Mu0 SE 0.45 1.17 5.20 0.99 Mu1 SE 0.01 0.28 0.00 Sigma SE 0.33 0.31 0.31 0.31 AIC 181.81 177.98 178.43 177.48 p.val 5.03% 6.59% 3.75%

10_min No Cov. P T P*T

Mu0 5.67 1.80 3.64 1.83 Mu1 0.06 0.09 2.9E-03 Sigma 3.96 3.20 3.97 3.12 Mu0 SE 0.68 1.00 13.36 0.93 Mu1 SE 0.01 0.62 0.00 Sigma SE 0.50 0.40 0.50 0.40 llh -111.63 -103.60 -111.62 -102.39 AIC 225.27 209.19 225.24 206.78 p.val 0.01% 86.90% 0.00%

10_min No Cov. P T P*T

Mu0 6.14 2.82 14.27 3.65 Mu1 0.04 -0.38 1.5E-03 Sigma 3.63 3.39 3.60 3.33 Mu0 SE 0.62 1.42 9.41 1.26 Mu1 SE 0.02 0.44 0.00 Sigma SE 0.46 0.42 0.45 0.42 AIC 218.81 211.97 218.07 212.30 p.val 0.89% 39.11% 1.07%

10_min No Cov. P T P*T

Mu0 5.25 2.42 -5.84 3.38 Mu1 0.03 0.65 1.4E-03 Sigma 2.84 2.49 2.74 2.48 Mu0 SE 0.50 1.00 7.50 0.82 Mu1 SE 0.01 0.43 0.00 Sigma SE 0.39 0.34 0.38 0.37 AIC 193.51 183.17 191.40 182.99 p.val 0.13% 14.58% 0.12%

10_min No Cov. P T P*T

Mu0 2.98 1.64 -0.33 2.15 Mu1 0.02 0.30 1.1E-03 Sigma 1.81 1.63 1.76 1.63 Mu0 SE 0.31 0.58 2.02 0.46 Mu1 SE 0.01 0.18 0.00 Sigma SE 0.27 0.25 0.26 0.25 AIC 168.55 162.94 165.82 162.23 p.val 1.79% 9.87% 1.20%

15_min No Cov. P T P*T

Mu0 6.22 3.18 -4.30 3.11 Mu1 0.04 0.57 2.3E-03 Sigma 2.88 2.62 2.74 2.55 Mu0 SE 0.51 1.27 6.02 1.14 Mu1 SE 0.02 0.32 0.00 Sigma SE 0.38 0.35 0.36 0.36 AIC 191.90 185.52 188.97 183.83 p.val 1.15% 8.74% 0.45%

15_min No Cov. P T P*T

Mu0 6.87 2.58 2.48 2.64 Mu1 0.07 0.20 3.2E-03 Sigma 4.61 3.82 4.62 3.69 Mu0 SE 0.79 1.19 15.68 1.14 Mu1 SE 0.01 0.73 0.00 Sigma SE 0.58 0.48 0.58 0.47 llh -117.51 -110.29 -117.47 -109.10 AIC 237.01 222.57 236.93 220.20 p.val 0.01% 77.85% 0.00%

15_min No Cov. P T P*T

Mu0 7.16 2.98 14.66 3.66 Mu1 0.05 -0.35 2.1E-03 Sigma 4.47 4.18 4.45 4.11 Mu0 SE 0.76 1.75 11.68 1.61 Mu1 SE 0.02 0.55 0.00 Sigma SE 0.57 0.52 0.57 0.52 AIC 235.57 228.40 235.17 228.15 p.val 0.74% 52.79% 0.65%

15_min No Cov. P T P*T

Mu0 6.48 2.50 -7.72 3.02 Mu1 0.04 0.83 2.3E-03 Sigma 3.68 3.15 3.53 3.10 Mu0 SE 0.64 1.26 9.23 1.13 Mu1 SE 0.01 0.53 0.00 Sigma SE 0.51 0.42 0.49 0.45 AIC 211.56 199.20 209.29 197.72 p.val 0.04% 13.24% 0.02%

15_min No Cov. P T P*T

Mu0 3.72 1.92 0.12 2.33 Mu1 0.02 0.33 1.7E-03 Sigma 2.19 1.93 2.14 1.94 Mu0 SE 0.38 0.69 2.32 0.57 Mu1 SE 0.01 0.21 0.00 Sigma SE 0.32 0.29 0.32 0.31 AIC 182.08 175.14 179.66 173.88 p.val 0.84% 11.94% 0.42%

AMEC Environment & Infrastructure 31

Page 36: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

AMEC Environment & Infrastructure 32

Table A-2. (continued) Model fitting statistics June

No Cov. P T P*T No Cov. P T P*T No Cov. P T P*TMu0 8.55 4.46 -1.83 4.99 Mu0 10.46 5.29 2.89 5.58 Mu0 12.68 5.67 9.51 5.81Mu1 0.06 0.56 2.8E-03 Mu1 0.07 0.41 3.7E-03 Mu1 0.10 0.17 5.3E-03Sigma 3.68 3.43 3.56 3.36 Sigma 4.13 3.82 4.07 3.70 Sigma 5.05 4.42 5.05 4.39Mu0 SE 0.64 1.72 7.87 1.59 Mu0 SE 0.72 2.03 9.33 1.89 Mu0 SE 0.88 2.30 11.51 2.26Mu1 SE 0.02 0.42 0.00 Mu1 SE 0.03 0.50 0.00 Mu1 SE 0.03 0.62 0.00Sigma SE 0.50 0.45 0.49 0.46 Sigma SE 0.57 0.51 0.57 0.51 Sigma SE 0.71 0.61 0.71 0.63AIC 211.87 205.10 210.18 203.79 AIC 221.37 213.18 220.72 212.41 AIC 237.57 226.04 237.49 225.21

p.val 0.93% 19.43% 0.45% p.val 0.42% 42.00% 0.28% p.val 0.07% 77.97% 0.04%

JulyNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 8.57 2.65 -2.62 2.46 Mu0 10.60 3.08 3.02 2.65 Mu0 13.08 4.21 9.22 3.06Mu1 0.09 0.52 4.4E-03 Mu1 0.12 0.35 5.8E-03 Mu1 0.14 0.18 7.2E-03Sigma 6.10 5.02 6.12 4.86 Sigma 7.21 5.76 7.24 5.60 Sigma 8.46 6.73 8.47 6.37Mu0 SE 1.04 1.66 21.31 1.63 Mu0 SE 1.23 1.88 25.38 1.89 Mu0 SE 1.45 2.17 29.75 2.14Mu1 SE 0.02 0.99 0.00 Mu1 SE 0.02 1.18 0.00 Mu1 SE 0.03 1.38 0.00Sigma SE 0.79 0.66 0.79 0.64 Sigma SE 0.92 0.74 0.93 0.73 Sigma SE 1.05 0.85 1.06 0.79llh -129.56 -122.56 -129.42 -121.52 llh -135.25 -126.86 -135.20 -125.67 llh -140.66 -131.98 -140.64 -130.55

AIC 261.13 247.12 260.85 245.04 AIC 272.50 255.72 272.40 253.33 AIC 283.31 265.97 283.28 263.10 p.val 0.02% 59.52% 0.01% p.val 0.00% 75.10% 0.00% p.val 0.00% 86.98% 0.00%

AugustNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 9.41 1.62 24.54 1.75 Mu0 11.60 2.11 31.58 1.59 Mu0 14.03 2.34 36.45 1.97Mu1 0.10 -0.71 4.7E-03 Mu1 0.12 -0.94 6.2E-03 Mu1 0.15 -1.06 7.5E-03Sigma 6.02 5.30 5.99 5.11 Sigma 7.64 6.74 7.58 6.54 Sigma 9.28 8.08 9.22 7.89Mu0 SE 1.03 2.35 16.07 2.20 Mu0 SE 1.30 2.96 20.51 2.93 Mu0 SE 1.58 3.51 25.34 3.50Mu1 SE 0.03 0.76 0.00 Mu1 SE 0.03 0.97 0.00 Mu1 SE 0.04 1.20 0.00Sigma SE 0.77 0.64 0.76 0.62 Sigma SE 1.01 0.84 1.00 0.83 Sigma SE 1.24 1.03 1.22 1.03

AIC 258.42 244.65 257.54 243.37 AIC 279.27 266.12 278.32 264.30 AIC 294.26 280.24 293.50 278.11 p.val 0.02% 34.71% 0.01% p.val 0.03% 33.18% 0.01% p.val 0.02% 38.48% 0.01%

SeptemberNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 8.31 2.72 -7.76 2.55 Mu0 10.65 2.67 -9.30 3.06 Mu0 13.73 2.69 -3.46 3.12Mu1 0.06 0.94 3.8E-03 Mu1 0.09 1.16 5.1E-03 Mu1 0.13 1.00 7.3E-03Sigma 5.04 4.29 4.89 4.09 Sigma 6.51 5.23 6.31 5.05 Sigma 7.73 5.52 7.59 5.40Mu0 SE 0.88 1.75 12.33 1.62 Mu0 SE 1.14 2.14 16.11 1.97 Mu0 SE 1.35 2.28 18.69 2.12Mu1 SE 0.02 0.71 0.00 Mu1 SE 0.02 0.93 0.00 Mu1 SE 0.02 1.08 0.00Sigma SE 0.70 0.59 0.68 0.58 Sigma SE 0.90 0.71 0.88 0.70 Sigma SE 1.04 0.73 1.03 0.73

AIC 235.45 222.42 233.79 220.48 AIC 252.96 236.33 251.44 234.73 AIC 264.40 239.55 263.56 238.00 p.val 0.03% 19.72% 0.01% p.val 0.00% 21.73% 0.00% p.val 0.00% 35.92% 0.00%

OctoberNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 5.05 2.96 -0.40 3.22 Mu0 7.15 4.57 2.33 5.09 Mu0 9.56 5.76 5.97 6.47Mu1 0.03 0.50 2.1E-03 Mu1 0.03 0.44 2.4E-03 Mu1 0.05 0.33 3.7E-03Sigma 3.07 2.82 2.98 2.75 Sigma 4.04 3.78 4.00 3.81 Sigma 4.65 4.10 4.64 4.22Mu0 SE 0.53 0.99 3.37 0.83 Mu0 SE 0.69 1.31 4.22 1.16 Mu0 SE 0.80 1.38 5.04 1.30Mu1 SE 0.01 0.30 0.00 Mu1 SE 0.01 0.38 0.00 Mu1 SE 0.01 0.45 0.00Sigma SE 0.46 0.43 0.45 0.42 Sigma SE 0.60 0.56 0.59 0.57 Sigma SE 0.67 0.60 0.67 0.62AIC 206.85 201.78 204.23 201.00 AIC 225.53 220.97 224.19 220.80 AIC 233.22 224.87 232.71 225.30p.val 2.44% 10.52% 1.56% p.val 3.27% 24.82% 2.97% p.val 0.39% 47.44% 0.49%

30_min 1_hr 2_hr

30_min 1_hr 2_hr

30_min 1_hr 2_hr

30_min 1_hr 2_hr

30_min 1_hr 2_hr

Page 37: NATIONAL ENGINEERING VULNERABILITY ASSESSMENT OF PUBLIC INFRASTRUCTURE TO CLIMATE ... · 2020. 12. 9. · in intensity attributable to the change in climate. These changes were then

Development of Projected Intensity-Duration-Frequency Curves for Welland, Ontario, Canada

AMEC Environment & Infrastructure 33

Table A-2. (continued) Model fitting statistics June

No Cov. P T P*T No Cov. P T P*T No Cov. P T P*TMu0 16.25 5.58 32.96 6.37 Mu0 18.48 7.02 38.18 7.46 Mu0 19.67 4.99 43.56 5.69Mu1 0.15 -0.90 7.7E-03 Mu1 0.16 -1.06 8.6E-03 Mu1 0.21 -1.28 1.1E-02Sigma 7.36 6.18 7.23 6.30 Sigma 8.30 6.71 8.15 6.84 Sigma 9.33 6.33 9.17 6.48Mu0 SE 1.28 3.05 16.62 3.00 Mu0 SE 1.44 3.03 18.62 2.98 Mu0 SE 1.62 2.73 20.90 2.59Mu1 SE 0.04 0.89 0.00 Mu1 SE 0.04 1.00 0.00 Mu1 SE 0.03 1.12 0.00Sigma SE 1.01 0.82 0.99 0.83 Sigma SE 1.13 0.88 1.10 0.90 Sigma SE 1.27 0.89 1.24 0.92AIC 264.12 249.48 263.11 250.64 AIC 272.89 256.36 271.75 257.69 AIC 280.78 255.87 279.53 257.30

p.val 0.01% 31.48% 0.02% p.val 0.00% 28.46% 0.01% p.val 0.00% 26.31% 0.00%

JulyNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 16.08 5.00 20.45 3.99 Mu0 17.17 2.58 20.66 2.40 Mu0 19.47 5.55 32.05 5.86Mu1 0.17 -0.20 8.8E-03 Mu1 0.23 -0.16 1.1E-02 Mu1 0.22 -0.58 1.0E-02Sigma 9.90 7.54 9.88 7.28 Sigma 10.74 7.38 10.73 7.30 Sigma 10.37 6.47 10.30 6.63Mu0 SE 1.70 2.40 33.60 2.41 Mu0 SE 1.84 2.53 36.58 2.50 Mu0 SE 1.77 2.22 32.12 2.21Mu1 SE 0.03 1.56 0.00 Mu1 SE 0.03 1.69 0.00 Mu1 SE 0.03 1.49 0.00Sigma SE 1.20 0.92 1.21 0.88 Sigma SE 1.31 0.89 1.32 0.87 Sigma SE 1.33 0.86 1.33 0.88llh -145.94 -135.43 -145.92 -134.21 llh -149.02 -134.65 -149.02 -133.98 llh -149.50 -132.85 -149.42 -133.09

AIC 293.87 272.86 293.85 270.41 AIC 300.05 271.29 300.03 269.96 AIC 301.00 267.70 300.85 268.18 p.val 0.00% 86.81% 0.00% p.val 0.00% 89.21% 0.00% p.val 0.00% 69.87% 0.00%

AugustNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 18.45 2.31 59.74 0.42 Mu0 20.18 3.21 55.34 0.96 Mu0 23.52 5.17 118.49 4.43Mu1 0.21 -1.95 1.1E-02 Mu1 0.22 -1.66 1.2E-02 Mu1 0.24 -4.48 1.2E-02Sigma 11.76 9.78 11.60 9.39 Sigma 12.66 10.59 12.54 10.21 Sigma 12.58 7.89 11.09 7.79Mu0 SE 2.00 4.25 32.58 4.34 Mu0 SE 2.15 4.58 35.29 4.71 Mu0 SE 2.14 3.05 33.62 3.09Mu1 SE 0.05 1.54 0.00 Mu1 SE 0.05 1.67 0.00 Mu1 SE 0.03 1.59 0.00Sigma SE 1.56 1.22 1.51 1.19 Sigma SE 1.64 1.29 1.61 1.27 Sigma SE 1.61 1.05 1.47 1.04

AIC 312.44 294.31 310.85 291.48 AIC 317.17 299.73 316.10 296.53 AIC 315.69 282.21 308.58 280.87 p.val 0.00% 20.81% 0.00% p.val 0.00% 30.09% 0.00% p.val 0.00% 0.77% 0.00%

SeptemberNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 19.00 5.31 4.48 5.76 Mu0 22.57 5.54 19.39 6.35 Mu0 23.89 6.96 23.48 7.75Mu1 0.16 0.85 9.1E-03 Mu1 0.20 0.18 1.1E-02 Mu1 0.20 0.02 1.1E-02Sigma 9.94 6.84 9.78 6.72 Sigma 12.68 9.03 12.67 8.94 Sigma 12.89 7.54 12.89 7.79Mu0 SE 1.74 2.55 24.81 2.37 Mu0 SE 2.22 3.24 32.55 3.10 Mu0 SE 2.25 2.42 31.83 2.44Mu1 SE 0.02 1.44 0.00 Mu1 SE 0.03 1.88 0.00 Mu1 SE 0.02 1.84 0.00Sigma SE 1.33 0.89 1.31 0.88 Sigma SE 1.71 1.15 1.71 1.14 Sigma SE 1.73 1.07 1.74 1.11

AIC 283.29 256.33 282.80 255.25 AIC 300.83 274.02 300.82 275.13 AIC 301.90 266.32 301.90 268.87 p.val 0.00% 48.69% 0.00% p.val 0.00% 91.07% 0.00% p.val 0.00% 98.17% 0.00%

OctoberNo Cov. P T P*T No Cov. P T P*T No Cov. P T P*T

Mu0 13.94 8.75 5.50 8.68 Mu0 16.39 9.75 4.57 10.10 Mu0 18.76 9.28 5.26 8.71Mu1 0.07 0.77 6.2E-03 Mu1 0.09 1.07 7.4E-03 Mu1 0.13 1.23 1.2E-02Sigma 6.49 5.57 6.31 5.47 Sigma 7.80 6.34 7.47 6.31 Sigma 9.50 7.28 9.16 6.86Mu0 SE 1.13 1.72 7.29 1.67 Mu0 SE 1.36 1.92 8.58 1.85 Mu0 SE 1.66 2.18 10.20 2.09Mu1 SE 0.02 0.65 0.00 Mu1 SE 0.02 0.76 0.00 Mu1 SE 0.02 0.91 0.00Sigma SE 0.89 0.78 0.88 0.78 Sigma SE 1.05 0.89 1.03 0.89 Sigma SE 1.27 1.01 1.26 0.97AIC 253.66 243.39 252.36 242.22 AIC 265.25 252.77 263.48 252.35 AIC 280.02 261.94 278.36 258.21p.val 0.14% 25.48% 0.07% p.val 0.04% 18.25% 0.03% p.val 0.00% 19.86% 0.00%

6_hr 12_hr 24_hr

6_hr 12_hr 24_hr

6_hr 12_hr 24_hr

6_hr 12_hr 24_hr

6_hr 12_hr 24_hr