national cancer institute · national cancer institute rockville| maryland ae senior thesis |...
TRANSCRIPT
![Page 1: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/1.jpg)
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Penn State AE Senior Capstone Project
Justin A. Woishnis | Construction Option
Advisor: James Faust
![Page 2: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/2.jpg)
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Penn State AE Senior Capstone Project
Justin A. Woishnis | Construction Option
Advisor: James Faust
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
PROJECT OUTLINE
![Page 3: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/3.jpg)
NATIONAL CANCER INSTITUTE
Rockville| Maryland
AE Senior Thesis | Justin A. Woishnis | Construction Management |
Project Size| 600,000 S.F. Base Building
575,800 S.F. Parking Garage
Building Function| Office/ Research
Contract Value | $96 Million
Contract Type| Design-Build
Total # of Floors | 8
Owner| The JBG Companies
General Contractor| DAVIS Construction
PROJECT OUTLINE
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
![Page 4: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/4.jpg)
AE Senior Thesis | Justin A. Woishnis
Site Plan
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Existing Site
Base Building
Parking Garage
New Parking Lot
During Construction
Construction Parking
Tenant Parking
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
![Page 5: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/5.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Features
Twin 7-story Towers w/
3-story Connector
Lower-Level including:
• Data Center
• Fitness Center
• Auditorium
Green Roof
Curtain Wall
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
![Page 6: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/6.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Core & Shell
Cast-In-Place Concrete
Structure
Post-Tension Beams
Precast Panel Facade
Batch Plant
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Tower Cranes
![Page 7: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/7.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Problem Background
• LEED Gold Certification
• No Renewable Energy Sources
• Large Energy Consumption
Problem Solution
• Roof-Mounted Solar Photovoltaic Array
• Large Available Roof Areas w/ Minimal Sun
Obstructions
Site/Roof Investigation
Blue- Available Roof
Area: 28,441 S.F.
Red- Penthouse
Area: 4,359 S.F.
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
ANALYSIS TOPIC #1
SOLAR (PV) ARRAY
![Page 8: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/8.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Fall Equinox
September 22nd
Spring
Equinox
March 20th
Winter
Solstice
December 21st
Summer
Solstice
June 20th
10:00 AM 1:00 PM 4:00 PM 10:00 AM 1:00 PM 4:00 PM
Optimum Roof Area = 20,617 S.F.20,617 S.
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Shading Analysis
![Page 9: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/9.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Initial Investigation:
• Full electricity Load = NOT FeasiblE
• 50% Electricity Load = NOT Feasible
• 10% Electricity Load = Still NOT Feasible
Revised Approach:
• Limit Energy Target
• All 24 Hour Lighting
• Main Lobby Entrance, Corridors, Elevator
Lobbies, Stairways and Exit Signs
Type Description Lamps West East West East Total
RC1 9" Aperture Semi-Recessed Downlight 1-F32WTRT 17 25 544 800 1344
RF1 6" Recessed Linear Light Fixture 2-F28T5 3 3 168 168 336
RC2 5 1/2" Aperture Downlight 1-F32WTRT 9 12 288 384 672
RM3 Adjustable Semi-Recessed Wall Washer 1-32W PMH 7 7 224 224 448
JL1C
Decorative Lit Panel w/ Remote LED
Driver/Transformer LED 4.5W/LF 4 4 360 360 720
PM1 Decorative Pendant 1-70W 1 3 70 210 280
JM2 Linear Light Fixture 3-CMH70 4 4 840 840 1680
JM1 Surface Mounted Lobby Fixture 14-CMH20 1 0 280 0 280
RM2 6" Lensed Wall Washer 1-70W, PAR30 3 4 210 280 490
RM1 6" Aperture Downlight 1-70W, PAR30 1 1 210 210 420
JL1A
Decorative Lit Panel w/ Remote LED
Driver/Transformer LED 4.5W/LF 4 4 360 360 720
RF3 10" Recessed Linear Light Fixture 4-F21T5 0 4 0 336 336
3554 4172 7726
Watts Total
Exit Signs ( 2-way) 3.4 408
Exit Signs (1-way) 1.8 281
Elevator 2-F28 2352
Stairway 2-F28 4256
7297
15023
kW 15.023
Overall Total (Watts)
Count Watts
Main Lobby & Corridor Lighting
TOTAL
Type Description Lamps West East West East Total
RC1 9" Aperture Semi-Recessed Downlight 1-F32WTRT 17 25 544 800 1344
RF1 6" Recessed Linear Light Fixture 2-F28T5 3 3 168 168 336
RC2 5 1/2" Aperture Downlight 1-F32WTRT 9 12 288 384 672
RM3 Adjustable Semi-Recessed Wall Washer 1-32W PMH 7 7 224 224 448
JL1C
Decorative Lit Panel w/ Remote LED
Driver/Transformer LED 4.5W/LF 4 4 360 360 720
PM1 Decorative Pendant 1-70W 1 3 70 210 280
JM2 Linear Light Fixture 3-CMH70 4 4 840 840 1680
JM1 Surface Mounted Lobby Fixture 14-CMH20 1 0 280 0 280
RM2 6" Lensed Wall Washer 1-70W, PAR30 3 4 210 280 490
RM1 6" Aperture Downlight 1-70W, PAR30 1 1 210 210 420
JL1A
Decorative Lit Panel w/ Remote LED
Driver/Transformer LED 4.5W/LF 4 4 360 360 720
RF3 10" Recessed Linear Light Fixture 4-F21T5 0 4 0 336 336
3554 4172 7726
Watts Total
Exit Signs ( 2-way) 3.4 408
Exit Signs (1-way) 1.8 281
Elevator 2-F28 2352
Stairway 2-F28 4256
7297
15023
kW 15.023
Overall Total (Watts)
Count Watts
Main Lobby & Corridor Lighting
TOTAL
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Energy Use Study
U.S. DOE, Annual Energy Review
2009
Average Site Energy Intensity per
Square Foot calculated to be
19,344,000 kwh
![Page 10: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/10.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Total Energy
Assumed 24 Hours/Day Lighting
Energy per Day
• 16 kW * 24 hours = 384 kwh/day
Energy per Month
• 384 kW * 30 days = 11,520 kwh
Energy per Year
• 384 kW * 365 days = 140,160 kwh
Solar Array designed to produce annual wattage of
at least 140,160 kwh
Determining # of Panels to reach output:
SAM (System Advisor Model)
• 372 Total Panels
• Produce 141,293 kwh
• 3 inverter units
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
![Page 11: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/11.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Typical Panel: 5’ spacing & 39° tilt
New SunPower Panel
Panel Section
SPR-305-WHT-U 305
(96 Cell Panels)
Rack System
SunPower T10 Solar Roof Tile
• 10° Tilt
• 11.35 inch Spacing
Sketch of Panel Layout
Shading Considerations:
• Penthouse, Davits, Parapets
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Panel Selection and Layout
![Page 12: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/12.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Total Initial System Cost
(Prior to Rebates/Incentives)
Rebates and Incentives
• Federal Tax Credit: 30% of gross installation
• Montgomery County-High Performance Building Property
Tax Credit:
• LEED-NC Gold = 25% Exemptions Amount (5 year
term)
• Clean Energy Production Tax Credit
• $0.0085/kwh claimed against the state income
tax (5 year term)
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Overall Total Incentive Amounts (5 Year Term) Total
MC- High Performance Property Tax Credit $1,562,500
Clean Energy Production Tax Credit $6,000
Total $1,568,500Payback Period Based on Rebates & Incentives:
• Approximately 3 Years
Incentive Name Description Cost Reduction Adjusted Cost
Initial Cost $1,186,033
Federal Tax Credit 30% of Gross Installation $355,809 $830,224
MC-High Performance Property Tax Credit 25% Exemption Amount $312,500 $517,724
Clean Energy Production Tax Credit $0.0085/kWh $1,200 $516,524
Final Cost $516,524
PV System Cost After Rebates & Incentives (1st Year of Installation)
Initial System cost for Installation
Including First Year Rebates & Incentives
Total Applicable Rebate & Incentive
Costs over 5 Years
Item # of Units Cost
Module 372 $338,344.19
Inverter 3 $52,920.00
Installation 7 $/Wdc
Total $1,186,032.41
Initial PV System Costs
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
System Costs
![Page 13: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/13.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Structural Breadth
Roof Structure Impact
Sources:
• Building Code Requirements for
Structural Concrete (ACI 318-08) and
Commentary
• 8.3- Methods of Analysis
• Pos. & Neg. Moments (int. & Ext. Face)
• 13.6- Direct Design Method
• Design Procedure for One-Way Flat
Slab Reinforcement
Exterior & Interior Bay
“Worst-Case Scenario”
Panel Weight = 52 lbs.
• Dead Load = 100 psf
• Live Load = 30 psf
• Panel Load = 3 psf
Wu = 0.172 ksf
One-way slab reinforcement Analysis
Rebar Spacing:
• Bottom Bars: 12” to 11”
• Top Bars: 8” to 7”
PT Beam Analysis: (Negligible)
• Panels Less than 3% Total Roof Load
![Page 14: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/14.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Summary & Recommendation
• Large Available Roof Spaces to Implement System
• 372 Panels
• High Efficiency
• Minimal Structural Impact
• Short Payback Period, Optimal to Install System
![Page 15: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/15.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Analysis Topic #2:
Technology Into the Field
Problem Background
• Large Quantity of Similar Materials
• Managing Deliveries/Materials
• Site Congestion
Problem Solution
• Research Technology Applications
• Tablet PC’s for Coordination &
Material Tracking
Possible Applications Overview
• Smart Box
• Tablet PC
• iPad
• Motion F5v
![Page 16: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/16.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Material Tracking
Tablet PC Ideas for Material Tracking
• Precast Panel delivery/Placement
• Punch-List Management
• Steel Erection/Placement
iPad used for construction practices
On-Site Tracking Software
Vela Systems mobile iPad App
• Record Site Conditions and Material Arrivals
• Model Viewing Capabilities
1. Proposed Delivery Date
2. Has Material Been Delivered?
3. Date and Time of Delivery?
4. Quantity?
5. Location on Site
6. Has Material Been Installed?
![Page 17: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/17.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Case Study
MetLife Stadium,
East Rutherford, N.J.
• $998 Million
• 2.2 Million s.f. Football Arena
• Skanska USA Building
• More than 3200 Precast
Concrete Pieces
• Utilized RFID tags for tracking
Benefits
• Aware of Status of all Precast members including:
• Production
• Delivery
• Site Preparation
• Installation Status
• Vela Systems and Tekla Corp. provide a Field BIM/Tablet
solution
• Each Piece Designed and Tracked for One Specific
Location
Results/Feedback
• Efficient Coordination of Fabricated Pieces
• Easily Identify jobsite Laydown area and Site
Accessibility upon Material Arrival
Estimated Savings
• Accelerated Schedule by 10 Days
• Generated $1 Million in Savings
![Page 18: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/18.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Feasibility
Implementing with Analysis Topic #4
• Short Interval Production Schedule (SIPS) for
Façade Re-sequence
• Increased need for Coordination
• Each Day will Require Specific Panels At
Designated Locations
• Tablet PC allows efficient communication
between Field Personnel and Manufacturer
Concerns
• RFID Tag Prices Outweigh Overall Benefit to Project
• Who will absorb the additional costs to pay for the
system?
Recommendation
• Application of RFID Tracking Systems Not Feasible
• Tagging more beneficial for larger-scale projects,
industrial construction or stadiums
![Page 19: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/19.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
CMU Overview
Fully Grouted and Reinforced CMU
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Analysis Topic #3:
Replacing Interior CMU Wall
w/ Precast
Problem Background
• Time-Consuming Installation Process
• Extensive Field Cutting Required
• Scaffolding Increases Safety Concerns
Problem Solution
• Improved Constructability
• Minimize Installation Cost
• Schedule Acceleration Dependent on Building
Enclosure (Analysis Topic #4)
![Page 20: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/20.jpg)
AE Senior Thesis | Justin A. Woishnis
Advantages:
• Durability
• High Strength
• Fire Ratings
• Low Maintenance
Requirements
PROJECT OUTLINE
Disadvantages:
• Very Labor Intensive
• Extensive Field-Cutting
• Corners/Angles
• Scaffolding Required
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Extensive Field-Cutting & Customized Corner Blocks
Non-Linear Wall increases quantity of corner connections
![Page 21: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/21.jpg)
AE Senior Thesis | Justin A. Woishnis
Information Summary
Size: 8” x 8” x 16”
Quantity: 6,544
Crew Size: 6
Daily Output: 80
Cost: $14/S.F.
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
CMU Estimate
Total Square Footage = 5,817 S.F.
Material Cost Unit Quantity $/S.F. Total
CMU Block S.F. 5,817 14 $81,438
Duration Unit Quantity Daily Output Total (Days)
CMU Block Ea. 4,602 80 58
Material Cost
Duration of Installation
Quantity/Duration Estimate Takes into Account Space for 3/8” Mortar Joints
![Page 22: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/22.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Precast Overview
Advantages:
• Substantial Decrease in Installation Time/Cost
of on-site Labor
• Manufactured in Controlled Location
• Decrease in Potential Delays due to
Uncontrollable Site Factors
• Design-Build Delivery Method
Disadvantages:
• Long Lead Time for Engineering/Design
• Increased Coordination with MEP Engineers for
Penetrations
• Early Design of Steel Embed Connection Locations
• Designing to Withstand Blast Loading
Connection Detail of Precast to Concrete to Floor Slab
![Page 23: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/23.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Precast Properties
• Minimum 7” Thick Solid Precast
Panel
• Maximum Width = 12’-0”
• 5-6 Month Lead Time
Information Summary
Size: 12’ x 12’ x 7”
Daily Output: 15-20 Panels
Cost: $15/S.F.
Quantity: 41 Panels
(Based on S.F.)
Duration: 2.73 Days
Non-Linear Orientation of Wall requires
Numerous Customized “L”-Shaped Panels
New Total Quantity: 49 Panels
New Duration : 3.5 Days
Duration Unit Quantity Daily Output Total
Precast Panel Ea. 49 15 3.5 Days
Duration of Installation
Material Cost Unit Quantity $/S.F. Total
Precast Panel S.F. 5,817 15 $87,255
Material Cost
Precast Estimate
![Page 24: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/24.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Options to Minimize Effects
• High Early Strength Concrete Utilized for
Ground & 2nd
Level Slab
• Precast Walls As Additional Shoring
• Minimal Overtime Work To Remain on Schedule
Results/Feasibility
Project Effects
• Delay in 2nd
Level Slab
Construction
• Require Proper Curing of
Ground Level to Support
Wall loads
Material Duration (Days) Cost
CMU 58 $81,438
Precast 3.5 $87,255
SAVINGS 54.5 ($5,817)
Results
Material Cost and Duration Comparisons
![Page 25: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/25.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Site Logistics/Phasing Plan
• Visualize Relationship Between
Trades
• Precast Erection Begins At
North End of Lobby
• Concrete Crew Will Follow
Precast Installation
• Minimal Overall Conflicts
Precast Installation
Screenshots
![Page 26: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/26.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Consideration
• Analysis topic #4 involves New Façade Erection
Sequence
• Enclose Lobby Early in Sequence to allow early
start of Interior Work
• Precast Costs outweighed by New Interior
Finishes Start Date
Summary/Questioning
• Precast Requires Increase in
Design and Coordination
• Lack of Incentive to utilize
Precast
• What makes the Delay for Precast
Worthwhile?
• Decision of Utilizing Precast
Dependent on Building Enclosure
![Page 27: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/27.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Problem Background
• Issues with Crane Limitations
• Overtime Costs Endured
• Excessive Crane Movement/Relocating
Problem Solution
• Increase Crane Capacities
• Create more stringent Productivity/Schedule Goals
• Develop New Crane /Façade Sequences for Maximum
Erection Efficiency
Analysis Topic #4:
Alternative Façade Sequence
Cranes unable to perform Numerous Picks
![Page 28: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/28.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Initial Sequence
200 Ton Crane
100 Ton Crane
1. Moves to SE Corner of West Building
• Formwork and Shoring not fully stripped on the east
building.
2. Moves to East Elevation of East Building
• PEPCO permanent power utility ductbank taking place
on the north end of site.
3. Moves to SE Corner of South Elevation
• Elevation coordinated and fabricated last
![Page 29: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/29.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Crane Moves
Short: 30 min.
Long: 1 Day
• Each Position based on
Specific Panel Weights
Overtime 10 Days
• Shockey’s 300 ton Crane
required to make Picks
Capacity $/day Duration Total
100 Ton 1300 1.38 $1,793
200 Ton 2300 3.94 $9,060
Overall Total $10,852
Cost of Crane
Type Time + 1/2 Hours Total
Crane Operator
38.50 1.5 80 $4,620
Foreman
30.55 1.5 80 $3,666
Layout (3)
32.45 1.5 80 $11,682
Welder (3)
42.31 1.5 80 $15,232
Rigger
33.63 1.5 80 $4,036
Truck Driver
20.62 1.5 80 $2,475
Overall Total $41,711
Overtime Costs
Costs Endured During Crane
Movements
Item Total
Overtime $41,711
Labor $3,670
Crane $10,852
Total Cost $56,234
Overall Costs
Type Duration Hours Total
Crane Operator
38.50 1.32 10.56 $407
Foreman
30.55 1.32 10.56 $323
Layout (3)
32.45 1.32 10.56 $1,028
Welder (3)
42.31 1.32 10.56 $1,340
Rigger
33.63 1.32 10.56 $355
Truck Driver
20.62 1.32 10.56 $218
Overall Total $3,670
Cost of "Down Time"- Crane Moves
Costs endured due to Overtime and
Productivity Loss
Crane and Labor Costs Display Money That Could be
Utilized for Erection
![Page 30: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/30.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
New Façade Scheduling &
Sequencing
Considerations
• Many Typical Panels
• Repetitive Nature of Façade and
Installation Practices
New Approach
• Develop SIPS for Façade to
Increase Productivity
• Push Precast Crew to work
Vertically
Short Interval Production Schedule (SIPS)
• Day-to-Day Labor Productivity Requirements
Precast Installation
Trade Sequence
• Precast Erection
• Backwelding
• Punch Windows
• Caulking/Waterproof
Lower Level (LL) Precast
Floor 1-7 Precast (Typical Panels)
Backwelding/Final Welds
Punch Windows
Caulking/Waterproofing
Preview of SIPS
![Page 31: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/31.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Phasing Schedule
• First Complete Lower Level of
Building (Non-Typical)
• Apply SIPS to Levels 1-7 (Typical)
Basis of SIPS
• Elevations
• Crane Positions
• Bay Numbers
New Sequence of Panel Erection New Crane Positioning
![Page 32: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/32.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements Crane Operator Works Overtime
to Move Crane
Cost/Schedule Results
Crane Positioning
Capacity Distance No. of Moves Duration (Days) Total Days
200 Ton
Short 23 0.0625 1.438
Long 0 1 0
300 Ton
Short 2 0.0625 0.125
Long 0 1 0
Overall Total 1.563
Total Hours 12.5
Crane Moves/Relocation
Crane Operator Time + 1/2 Duration (Hours)Total
38.50 1.5 12.5 $722
Overtime Costs for Crane Moves
Overtime $41,711
Labor $3,670
Crane $10,852
Total Cost $56,234
Overtime $722
Labor $0.00
Crane $0.00
Remaining Total $55,512
Cost Difference
Substantial Savings with
Crane Utilization Plan
Building Original Duration Actual Duration New Duration Total
West 66 54 34 20
East 60 51 34 17
Connector 12 11 11 0
37
Precast Duration Summary
Total Savings (Days)
SIPS Results
• Saves 37 Days for Precast Erection
Type Duration Work Hours Total
Crane Operator
38.50 37 296 $11,396
Foreman
30.55 37 296 $9,043
Layout (3)
32.45 37 296 $28,816
Welder (3)
42.31 37 296 $37,571
Rigger
33.63 37 296 $9,954
Truck Driver
20.62 37 296 $6,104
$102,884
Labor Savings (Precast Crew)
Overall Total
WO GRUBB Crane Rental Costs Duration (37 Days) Total
200-Ton Crawler $20,000 1 Month $20,000
$6,700 3 Weeks $20,100
$2,300 2 Days $4,600
$44,700
Crane Savings
Overall Total
SIPS Results
• Labor and Crane Cost
Savings of $147,584
![Page 33: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/33.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Summary/Questioning
• Crane movements during overtime
• SIPS Schedule for East/West
Building
• Precast Erection Saves 37 days
• Schedule Reduction Saves
$147,584
Consideration
• Combined Use of Analysis topic #3 would prove beneficial
to overall project
• Due to Extensive level of coordination and material
procurement, Lobby South Elevation not Feasible for early
completion
• Confirmed as NOT FEASIBLE by DAVIS Project Engineer
1. Designing and Developing Drawings
2. Cutting Stone (Canada)
3. Shipping Stone (Canada to U.S.)
4. Formwork
5. Casting
![Page 34: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/34.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
Summary of Conclusion/Recommendations
Analysis #1: Solar PV Array
• Rebates and Incentives allow System to be Desirable by
Owner
• 3-Year Payback Period
• Analysis #2: Technology to the Field
• Cost of Systems Does not Outweigh Project Benefits
Analysis #3: Replace Interior CMU Wall w/ Precast
• Substantial Decrease in On-Site Labor
• Deemed Beneficial Solely based on Building Enclosure,
otherwise no incentive to Implement
• Analysis #4: Alternative Façade Sequence
• SIPS Saves Substantial Time and Money
• Larger Crane Sizes increases Erection Efficiency
![Page 35: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/35.jpg)
AE Senior Thesis | Justin A. Woishnis
PROJECT OUTLINE
Academic Acknowledgements
Penn State AE Faculty
• Craig Dubler
• James Faust
• Kevin Parfitt
PACE Roundtable Industry Members
Special Thanks
National Cancer Institute
Family & Friends
Industry Acknowledgements
James G. Davis Construction
• Will Cox
• John Rappoport
• Todd Povell
Nick Carosi, IV- Arban & Carosi
Mark T. Taylor- The Nitterhouse Companies
Jerry D. Davis Jr.- W.O. Grubb
Kurt D. Maldovan- Balfour Beatty
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Project Introduction
Project Background
• Site Overview
• Building properties
Analysis #1: Solar PV Analysis
• Site/Roof Investigation
• Shading Analysis
• Energy Use Study
• Panel Selection and Layout
• System Costs
Structural Breadth
Analysis #2: Technology to the Field
• Material Tracking
• Case Study
• Feasibility
Analysis #3: Interior CMU Wall To Precast
• CMU Overview
• CMU Estimate
• Precast Overview
• Precast Estimate
• Results/Feasibility
Analysis #4: Alternative Façade Sequence
• Initial Sequence
• New Façade Scheduling/Sequence
• Cost/Schedule Results
Summary of Conclusions/Recommendations
Acknowledgements
![Page 36: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/36.jpg)
AE Senior Thesis | Justin A. Woishnis
THANK YOU
QUESTIONS?
NATIONAL CANCER INSTITUTE
Rockville| Maryland
![Page 37: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/37.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
PV Rack Specifications
![Page 38: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/38.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
PV Array: Constructability
Sunpower T10 Solar Roof Tiles
• Easy to Install without any need for mechanical roof
Attachments (non-penetrating)
• Large-scale roof tile Arrays can be installed efficiently and
commissioned quickly
• Low-profile design blends into flat roof construction,
operating within the electrical grid network
• Solar Roof Tiles will not interfere with roof drainage
(extremely flexible layout capabilities)
• All Panels Placed on One roof Area, minimizing Wire Runs
![Page 39: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/39.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Structural Load Calculations
Live Loads
Roof Live Load = 30 psf Roof Snow Load = 30 psf
Dead Loads
Roof Slab = 6” thick
[(6”)/(12)] x 150 pcf = 75 psf
Assumed Superimposed Dead Load = 20 psf
Total Dead Load = 95 psf (Used 100 psf)
Panel Loads
Panel Weight = 52 lbs per panel Trib. Area = 20’ x 20’
[(52 lb/panel) * (20 panels)] / (20’ x 20’) ]= 2.6 (Used 3 psf)
Total Loads
DL = 103 psf
LL = 30 psf
Wu = 1.2(0.103) + 1.6(0.030) = 0.172 ksf
![Page 40: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/40.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Property Tax Reduction
Cost of Project = $100,000,000
Property Tax Assumption = 1.25%
100,000,000 * .0125 = $1,250,000 Taxes/Year
LEED-NC Gold = 25% Exemption Amount (5 year term)
Cost Savings of Property Tax per Year = $312,500
![Page 41: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/41.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
Crane and Erection Details
Capacity Distance No. of Moves Duration (Days) Total Days
100 Ton
Short 6 0.0625 0.375
Long 1 1 1
200 Ton
Short 15 0.0625 0.938
Long 3 1 3
Overall Total 5.313
Crane Moves/Relocation
WO GRUBB Crane Rental Per Month Per Week Per Day Mobilization
100-Ton Crawler $11,000 $3,700 $1,300 $10,000
200-Ton Crawler $20,000 $6,700 $2,300 $21,000
300-Ton Crawler $34,000 $11,300 $3,800 $31,000
Crane Pricing
WO GRUBB Crane Rental Per Month Per Week Per Day Mobilization
300-Ton Crawler $34,000 $11,300 $3,800 $31,000
100-Ton Crawler $11,000 $3,700 $1,300 $10,000
Difference of values $23,000 $7,600 $2,500 $21,000
Additional Costs Endured With Larger Crane
Average Daily Erection
Trade Original Quantity New Contract
Quantity/Agreement
Precast Panels 8-10 panels/day Per New Schedule/SIPS
Punch Windows 10-12 units/day Per New Schedule/SIPS
Curtain Wall 8 units/day Per New Schedule/SIPS
Niche/Recessed Bays 8 units/day Per New Schedule/SIPS
![Page 42: NATIONAL CANCER INSTITUTE · NATIONAL CANCER INSTITUTE Rockville| Maryland AE Senior Thesis | Justin A. Woishnis | Construction Management | Project Size| 600,000 S.F. Base Building](https://reader033.vdocuments.us/reader033/viewer/2022060209/5f0449017e708231d40d38cb/html5/thumbnails/42.jpg)
AE Senior Thesis | Justin A. Woishnis
APPENDIX
NATIONAL CANCER INSTITUTE
Rockville| Maryland
SIPS