mta presentation wayne avenue community meeting in silver spring
TRANSCRIPT
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
1/30
Wayne Avenue Community Meeting
May 26, 2016
1
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
2/30
Project Status
Project is moving forward with cost saving measures
incorporated into the P3 RFP
Right-of-Way offers and property settlements are on-
going
Selection of Purple Line Transit Partners (PLTP)
announced on March 2, 2016
Board of Public Works approved P3 Concessionaire
Contract on April 6, 2016. Six years of finaldesign/construction and 30-year O&M period
MTA issued Limited Notice To Proceed to PLTP in April
2016
2
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
3/30
Wayne Avenue – Purple Line Operations
Purple Line enters Wayne Avenue at Fenton Street, just
east of station at Silver Spring Library
Light rail vehicles share center lanes with traffic Left turn lanes added at Cedar Street (eastbound),
Manchester Road (westbound), and Dale Drive
Off-peak parking permitted in outside lanes like today
3
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
4/30
Wayne Avenue – Purple Line Operations
East of Sligo Creek, Purple Line enters short tunnel
between Wayne Manchester Towers and Kenwood
House
Stations located at Dale Drive in front of SSIMS and atManchester Place tunnel portal
Traffic signal added at tunnel portal near Manchester
Road
Montgomery County’s Green Trail will be built along
north side of Wayne Avenue at the same time as the
Purple Line
4
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
5/30
Wayne Avenue Design Refinements
Already Implemented Coordinated with Montgomery County Public Schools
on redesign of school access, parking and drop-offareas with emphasis on student safety
• No reduction in parking spaces
• Drop off zone in front of school entrance
• Design guides pedestrians to intersection
• Railing along walkway to platform
• Marked crosswalks
• Students will have direct access to school building
Design at SSIMS required retaining wall along WayneAvenue
5
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
6/30
Typical Cross-Section –
Except at Key Intersections
6
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
7/30
Dale Drive Station and SSIMS
7
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
8/30
Dale Drive Intersection Many options were evaluated throughout Planning and
Preliminary Engineering
Two through lanes in each direction are required toaccommodate the peak period traffic demand
Left turn lanes with separate signal phases are included toimprove traffic operations and safely accommodate left turnmovements across the tracks
Pedestrian signal phases provide the time required for all users tocross safely
Prohibiting westbound left turns results in:• An increase in traffic on other neighborhood streets, primarily
Mansfield Road, and
• Does not necessarily eliminate left turns. The resultant illegal leftturn movements are unprotected and unsafe for all users.
8
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
9/30
9
Movie file not supported in this format.
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
10/30
Design Changes & Commitments Reduction of speed limit along Wayne Avenue to 25 mph between
Georgia Avenue and Flower Avenue
All crosswalks at signalized intersections will have pedestrian walksignals
Road ownership transfers from County to SHA for improved operations
and control• Bonifant Street• Wayne Avenue• Arliss Street
− County will remain involved in issues regarding design and operation of theroads, on-street parking regulations, pedestrian crossings and intersectionoperations
−PLTP to assume maintenance responsibility once construction is completed
Relocation of Wayne Avenue TPSS to SSIMS
Pedestrian refuge island on west side of Dale Drive/Wayne Avenueunder study
10
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
11/30
Pedestrian Refuge at Wayne Ave. & Dale Drive
11
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
12/30
TPSS RenderingView of SSIMS from Wayne Avenue
12
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
13/30
Conceptual Landscape Plan
13
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
14/30
A P3 provides a strong incentive for the Concessionaire to
build a quality project, since they will be operating and
maintaining it for many years based on performance
standards, not detailed in specifications
Allows the Concessionaire to manage costs and innovate to
mitigate risks and earn return on investment
Handback standards protect long-term public interest The Concessionaire is also incentivized to find innovations
and creative solutions, to complete the project on schedule,
and to meet the operational requirements of the contract
Project Delivery
Benefits of the P3
14
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
15/30
Project Oversight
Public Information, Communications and Community
Outreach (to be supported by PLTP throughout thedesign-build phase)
General Terms of Third Party Agreements
Right-of-Way Acquisition Fare Policy, Farebox Revenue and Ridership
Project Delivery
Responsibilities to be retained by MTA:
15
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
16/30
Purple Line Transit Partners
16
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
17/30
Design Refinements & Commitments
1500Vdc catenary system eliminates 4 TPSSs in Montgomery
County
Throughout construction a certified arborist will monitor and
approve tree protection activities and make reasonable
efforts to leave priority retention areas undisturbed
Enhanced pedestrian safety measures on Wayne Avenue
• Visual and audible active warning devices at the non-signalized
crosswalk – Wayne and Springvale Road
Emphasis on minimizing construction and operating noise
17
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
18/30
Light Rail Vehicle
18
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
19/30
Light Rail VehicleManufactured by CAF
Articulated 5-module LRV with
a total length of 136’
80 seats are provided
80% Low Floor
Specifically designed to meet ADA requirements
Eight wheelchairs and eight bicycles can be accommodated
simultaneously
19
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
20/30
PLTP Safety Culture/Good Neighbor Policy PLTP places safety and quality as our top priorities.
It is our ultimate goal to deliver a high qualitytransit system that satisfies our client and PurpleLine riders.
It is our policy to be a good neighbor and we arehere to understand the community’s specific issuesand mitigate them as best as possible.
We look forward to partnering with the MTA andyou as we complete design and build the PurpleLine.
20
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
21/30
Regular Community Outreach and Public Meetings
Mobilization activities and equipment
Relocation of existing utilities
Survey and Subsurface Borings
Special outreach to schools
What To Expect Before Construction
21
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
22/30
Frequent outreach and coordination
Construction site safety
Daily noise monitoring Lane shifts and parking restrictions but will
maintain local access
What To Expect During Construction
22
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
23/30
Tentative Construction Schedule – Wayne AvenueConstruction Activity Start End
Utility Relocations Fall 2017 Summer 2018
Stage 1 Roadway Work - Traffic Shifted to South Side
• Continued utility relocations
•
Roadway widening / Track construction• SSIMS retaining walls and parking lot (Summer ‘18)
• Dale Drive Station
• Wayne Avenue Bridge
Summer 2018 Spring 2019
Stage 2 Roadway Work - Traffic Shifted to North Side
• Continued utility relocations
• Roadway widening / Track construction• Wayne Avenue Bridge
Spring 2019 Winter 2019
Systems and TPSS Q06 @ SSIMS Spring 2019 Fall 2020
Testing and Commissioning / Trial Running Fall 2020 Spring 2022
23
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
24/30
Mitigating Impacts During Construction Access to all businesses and residences will be maintained.
The Purple Line Team will develop a Construction Access
and Mobility Plan depicting all haul routes and access
points. Designated parking areas for construction workers will be
provided.
Deliveries and hauling to and from the project area will be
confined to the project right of way and will be ondesignated haul routes along the project alignment.
Dust control including, watering, mulching, vegetative cover,
barriers and wheel wash stations
24
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
25/30
Reducing Noise During Construction
Low audible equipment back-up alarms
Noise-attenuated earthmoving and stationary
equipment Use local power grid when possible to reduce the
use of temporary generators
25
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
26/30
Community Advisory Teams
26
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
27/30
Community Advisory Teams
Structure based on geographic location and a similar set
of concerns
Composed of representatives of the community/ civic
associations, business organizations, and other
stakeholder groups “Work around the table” format
CATs will function through the construction period
One representative and one alternate from each
community Designation of members from community and business
organizations is underway
27
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
28/30
Spring - Summer 2016 Look Ahead
Elm Street utility relocation now underway
Refine schedule
Survey & soil borings
Storm Water Management concept plan
Mobilization of project offices
Introductory public information meetings
Property-owner coordination & Real Estate Acquisition
28
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
29/30
Next Steps Financial Close – June 2016
FTA Full Funding Grant Agreement – July 2016
CATs Kick-off Meetings – Fall 2016
Commence Construction – Late 2016
Begin Revenue Service –2022
29
-
8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring
30/30
Questions?
Please contact Lesli Leath, Public Outreach at:443-451-3706
www.purplelinemd.com
Mike Madden
Purple Line Deputy Project Director
443-451-3718
Línea telefónica en español:
443-451-3705
Like us on Facebook facebook.com/marylandpurpleline
Follow us on Twitter twitter.com/PurpleLineMD
30
mailto:[email protected]:[email protected]