mta presentation wayne avenue community meeting in silver spring

Upload: aj-metcalf

Post on 05-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    1/30

    Wayne Avenue Community Meeting

    May 26, 2016

    1

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    2/30

    Project Status

    Project is moving forward with cost saving measures

    incorporated into the P3 RFP

    Right-of-Way offers and property settlements are on-

    going

    Selection of Purple Line Transit Partners (PLTP)

    announced on March 2, 2016

    Board of Public Works approved P3 Concessionaire

    Contract on April 6, 2016. Six years of finaldesign/construction and 30-year O&M period

    MTA issued Limited Notice To Proceed to PLTP in April

    2016

    2

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    3/30

    Wayne Avenue – Purple Line Operations

    Purple Line enters Wayne Avenue at Fenton Street, just

    east of station at Silver Spring Library

    Light rail vehicles share center lanes with traffic Left turn lanes added at Cedar Street (eastbound),

    Manchester Road (westbound), and Dale Drive

    Off-peak parking permitted in outside lanes like today

    3

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    4/30

    Wayne Avenue – Purple Line Operations 

    East of Sligo Creek, Purple Line enters short tunnel

    between Wayne Manchester Towers and Kenwood

    House

    Stations located at Dale Drive in front of SSIMS and atManchester Place tunnel portal

    Traffic signal added at tunnel portal near Manchester

    Road

    Montgomery County’s Green Trail will be built along

    north side of Wayne Avenue at the same time as the

    Purple Line

    4

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    5/30

    Wayne Avenue Design Refinements

    Already Implemented Coordinated with Montgomery County Public Schools

    on redesign of school access, parking and drop-offareas with emphasis on student safety

    • No reduction in parking spaces

    • Drop off zone in front of school entrance

    • Design guides pedestrians to intersection

    • Railing along walkway to platform

    • Marked crosswalks

    • Students will have direct access to school building

    Design at SSIMS required retaining wall along WayneAvenue

    5

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    6/30

    Typical Cross-Section –

    Except at Key Intersections

    6

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    7/30

    Dale Drive Station and SSIMS

    7

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    8/30

    Dale Drive Intersection Many options were evaluated throughout Planning and

    Preliminary Engineering

    Two through lanes in each direction are required toaccommodate the peak period traffic demand

    Left turn lanes with separate signal phases are included toimprove traffic operations and safely accommodate left turnmovements across the tracks

    Pedestrian signal phases provide the time required for all users tocross safely

    Prohibiting westbound left turns results in:• An increase in traffic on other neighborhood streets, primarily

    Mansfield Road, and

    • Does not necessarily eliminate left turns. The resultant illegal leftturn movements are unprotected and unsafe for all users.

    8

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    9/30

    9

    Movie file not supported in this format.

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    10/30

    Design Changes & Commitments  Reduction of speed limit along Wayne Avenue to 25 mph between

    Georgia Avenue and Flower Avenue

    All crosswalks at signalized intersections will have pedestrian walksignals

    Road ownership transfers from County to SHA for improved operations

    and control• Bonifant Street• Wayne Avenue• Arliss Street

    − County will remain involved in issues regarding design and operation of theroads, on-street parking regulations, pedestrian crossings and intersectionoperations

    −PLTP to assume maintenance responsibility once construction is completed

    Relocation of Wayne Avenue TPSS to SSIMS

    Pedestrian refuge island on west side of Dale Drive/Wayne Avenueunder study

    10

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    11/30

    Pedestrian Refuge at Wayne Ave. & Dale Drive

    11

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    12/30

    TPSS RenderingView of SSIMS from Wayne Avenue

    12

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    13/30

    Conceptual Landscape Plan

    13

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    14/30

     

    A P3 provides a strong incentive for the Concessionaire to

    build a quality project, since they will be operating and

    maintaining it for many years based on performance

    standards, not detailed in specifications

    Allows the Concessionaire to manage costs and innovate to

    mitigate risks and earn return on investment

    Handback standards protect long-term public interest The Concessionaire is also incentivized to find innovations

    and creative solutions, to complete the project on schedule,

    and to meet the operational requirements of the contract

    Project Delivery

    Benefits of the P3

    14

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    15/30

     

    Project Oversight

    Public Information, Communications and Community

    Outreach (to be supported by PLTP throughout thedesign-build phase)

    General Terms of Third Party Agreements

    Right-of-Way Acquisition Fare Policy, Farebox Revenue and Ridership

    Project Delivery

    Responsibilities to be retained by MTA:

    15

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    16/30

    Purple Line Transit Partners

    16

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    17/30

    Design Refinements & Commitments

    1500Vdc catenary system eliminates 4 TPSSs in Montgomery

    County

    Throughout construction a certified arborist will monitor and

    approve tree protection activities and make reasonable

    efforts to leave priority retention areas undisturbed

    Enhanced pedestrian safety measures on Wayne Avenue

    • Visual and audible active warning devices at the non-signalized

    crosswalk – Wayne and Springvale Road

    Emphasis on minimizing construction and operating noise

    17

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    18/30

    Light Rail Vehicle

    18

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    19/30

    Light Rail VehicleManufactured by CAF 

    Articulated 5-module LRV with

    a total length of 136’

    80 seats are provided

    80% Low Floor

    Specifically designed to meet ADA requirements

    Eight wheelchairs and eight bicycles can be accommodated

    simultaneously

    19

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    20/30

    PLTP Safety Culture/Good Neighbor Policy  PLTP places safety and quality as our top priorities.

    It is our ultimate goal to deliver a high qualitytransit system that satisfies our client and PurpleLine riders.

    It is our policy to be a good neighbor and we arehere to understand the community’s specific issuesand mitigate them as best as possible.

    We look forward to partnering with the MTA andyou as we complete design and build the PurpleLine.

    20

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    21/30

    Regular Community Outreach and Public Meetings

    Mobilization activities and equipment

    Relocation of existing utilities

    Survey and Subsurface Borings

    Special outreach to schools

    What To Expect Before Construction

    21

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    22/30

    Frequent outreach and coordination

    Construction site safety

    Daily noise monitoring Lane shifts and parking restrictions but will

    maintain local access

    What To Expect During Construction

    22

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    23/30

    Tentative Construction Schedule – Wayne AvenueConstruction Activity Start End

    Utility Relocations Fall 2017 Summer 2018

    Stage 1 Roadway Work - Traffic Shifted to South Side

    • Continued utility relocations

     Roadway widening / Track construction• SSIMS retaining walls and parking lot (Summer ‘18)

    • Dale Drive Station

    • Wayne Avenue Bridge

    Summer 2018 Spring 2019

    Stage 2 Roadway Work - Traffic Shifted to North Side

    • Continued utility relocations

    • Roadway widening / Track construction• Wayne Avenue Bridge

    Spring 2019 Winter 2019

    Systems and TPSS Q06 @ SSIMS Spring 2019 Fall 2020

    Testing and Commissioning / Trial Running Fall 2020 Spring 2022

    23

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    24/30

    Mitigating Impacts During Construction Access to all businesses and residences will be maintained.

    The Purple Line Team will develop a Construction Access

    and Mobility Plan depicting all haul routes and access

    points. Designated parking areas for construction workers will be

    provided.

    Deliveries and hauling to and from the project area will be

    confined to the project right of way and will be ondesignated haul routes along the project alignment.

    Dust control including, watering, mulching, vegetative cover,

    barriers and wheel wash stations

    24

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    25/30

    Reducing Noise During Construction

    Low audible equipment back-up alarms

    Noise-attenuated earthmoving and stationary

    equipment Use local power grid when possible to reduce the

    use of temporary generators

    25

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    26/30

    Community Advisory Teams

    26

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    27/30

    Community Advisory Teams

    Structure based on geographic location and a similar set

    of concerns

    Composed of representatives of the community/ civic

    associations, business organizations, and other

    stakeholder groups “Work around the table” format

    CATs will function through the construction period

    One representative and one alternate from each

    community Designation of members from community and business

    organizations is underway

    27

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    28/30

    Spring - Summer 2016 Look Ahead

    Elm Street utility relocation now underway

    Refine schedule

    Survey & soil borings

    Storm Water Management concept plan

    Mobilization of project offices

    Introductory public information meetings

    Property-owner coordination & Real Estate Acquisition

    28

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    29/30

    Next Steps Financial Close – June 2016

    FTA Full Funding Grant Agreement – July 2016

    CATs Kick-off Meetings – Fall 2016

    Commence Construction – Late 2016

    Begin Revenue Service –2022

    29

  • 8/16/2019 MTA Presentation Wayne Avenue Community Meeting in Silver Spring

    30/30

    Questions?

    Please contact Lesli Leath, Public Outreach at:443-451-3706

    [email protected] 

    www.purplelinemd.com

    Mike Madden

    Purple Line Deputy Project Director

    443-451-3718

    [email protected]

    Línea telefónica en español:

    443-451-3705

    Like us on Facebook facebook.com/marylandpurpleline 

    Follow us on Twitter twitter.com/PurpleLineMD

    30

    mailto:[email protected]:[email protected]