MS Project 2000 / 2003

Luke E. ReeseBiosystems and Agricultural Engineering

[email protected] 17, 2009

Page 2: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

What is project management?

…the process of planning, organizing, and managing tasks and resources to accomplish a defined objective, usually within constraints on time, resources, or cost. A project plan can be simple, for example, a list of tasks and their start and finish dates written on a notepad. Or it can be complex, for example, thousands of tasks and resources and a project budget of millions of dollars.

Page 3: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Define the project

1. Set a project start date

2. Enter tasks

3. Enter durations / work

4. Assign resources

5. Link tasks

6. Print the plan

7. Fine-tune the plan

Build the plan

Track and manage

Close the project

8. Set a baseline

9. Enter actuals

10. Adjust the plan

Page 4: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 5: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 6: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 7: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

1

Page 8: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

2

Page 9: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

3

Page 10: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

4

Page 11: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

5

Page 12: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 13: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

6

Page 14: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

7

Page 15: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Gantt Charts

Page 16: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Program Assumptions

Page 17: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 18: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 19: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 20: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 21: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

How do you get started?

• Plan on a piece of paper

• Think of broad sub-project task categories

• Determine all tasks required to complete sub-projects

• Organize sub-projects into a logical flow

• Estimate each task’s duration / effort

• MS Project

Page 22: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 23: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 24: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 25: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 26: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Right Mouse Click

Page 27: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 28: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Right Mouse Click

Page 29: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 30: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 31: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009
Page 32: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

MS Project Web Templates

http://office.microsoft.com/en-us/templates/CT101527321033.aspx?av=ZPJ

Page 33: MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering reesel@msu.edu September 17, 2009

Adding Individual Resources

Click on View Tab, then select View Bar (expand selection if you don’t see this option).

Click on Resource sheet, and a window will open

Type your name under Resource Name, hit enter, then right click on your name.

Click on Resource Information

Set the start and end dates and then click the Working Time tab

Set Base Calendar = 24 hours

Then set available hours for each individual day or by the week (click on M for all Mondays.) This time will then be used to establish work durations.

Plan on a minimum of 10 hours/week (per team member) to successfully complete course objectives.