  • 7/29/2019 MRP Basics

    1/13

    Fundamentals of MRP

    Prof. Prasad Chakrabarti, CFPIM,CSCP(APICS)

  • 7/29/2019 MRP Basics

    2/13

    Planning and Control System

    ProductionPlan

    BusinessPlan

    MasterProductionSchedule

    Planning

    Execution

    MaterialRequirements

    Plan

    ProductionActivity Controland Purchasing

  • 7/29/2019 MRP Basics

    3/13

    Objectives of MRP

    To determine the materials required What is required

    How much is required

    When it is required

    To establish and maintain priorities

  • 7/29/2019 MRP Basics

    4/13

    Inputs to MRP Process

    MPS

    MRP

    Planning Data

    Bill ofMaterial

    InventoryStatus

  • 7/29/2019 MRP Basics

    5/13

    Nature of Demand

    Legs

    206

    Ends

    433

    Sides

    711

    Top

    025

    Hardware Kit

    822

    Table

    100

  • 7/29/2019 MRP Basics

    6/13

    Description: Table

    Part Number: 100

    Part Number Description Quantity Required Unit of Measure

    306 Wooden legs 4 EA

    433 Wooden ends 2 EA711 Wooden sides 2 EA

    025 Table top 1 EA

    822 Hardware 1 Kit

    Bill of Materials

    A bill of material lists all the componentsneeded to make one assembly

    Each part has a unique part number

  • 7/29/2019 MRP Basics

    7/13

    Bill of Materials

    SingleLevel

    Multilevel

    Base

    300

    Top

    025

    Hardware

    Kit

    822

    Table100

    Legs

    306

    Leg Bolts

    326

    Frame

    357

    Base

    300

    Boards

    031

    Glue

    075

    Top

    025

    Hardware

    Kit 822

    Table

    100

  • 7/29/2019 MRP Basics

    8/13

    The MRP Process

    Determines What is needed

    How much is needed

    When to order

    Involves

    MPS data

    Bills of material Inventory status

    Planning data

  • 7/29/2019 MRP Basics

    9/13

    Lead Time, Exploding, and Offsetting

    Lead time: The time from when an order is placed until the partis ready for use

    Exploding: Multiplying the parent requirements by the usage

    quantity through the product tree

    Offsetting: Placing the requirements in their proper time periodsbased on lead time

  • 7/29/2019 MRP Basics

    10/13

    Planned Orders

    Week

    Item Planned Order 1 2 3 4 5

    Number

    B Receipt 50Release

    ReceiptC Release

    Receipt

    D ReleaseReceipt

    E Release

    ReceiptF Release

  • 7/29/2019 MRP Basics

    11/13

    Gross and Net Requirements

    Available inventory must be taken intoaccount

    Net requirements = gross requirements available inventory

    Example:Gross requirements 50 units

    Available inventory 20 units

    Net requirements 30 units

  • 7/29/2019 MRP Basics

    12/13

    Problem 4.3B

    DC

    E F LT = 1 WkLT = 1 Wk

    LT = 1 WkLT = 2 Wks

    LT = 1 Wk

    Item Week

    Number 1 3 4 5

    Gross requirements 50

    Projected available 20 20 20 20 20

    B Net requirements 30

    Planned order receipt 30

    Planned order release 30

    Gross requirements 30Projected available 10

    C Net requirements

    Planned order receipt

    Planned order release

    Gross requirements 30

    Projected available 0 0 0

    D Net requirements 30

    Planned order receipt 30

    Planned order release 30

    Gross requirements

    Projected available

    E Net requirements

    Planned order receipt

    Planned order release

    Gross requirements 20

    Projected available 0

    F Net requirements 20

    Planned order receipt 20

    Planned order release 20

    2

    0

    0

  • 7/29/2019 MRP Basics

    13/13

    Problem 4.3 (Solution)B

    DC

    E F LT = 1 WkLT = 1 Wk

    LT = 1 WkLT = 2 Wks

    LT = 1 Wk

    Item Week

    Number 1 3 4 5

    Gross requirements 50

    Projected available 20 20 20 20 20 0

    B Net requirements 30

    Planned order receipt 30

    Planned order release 30

    Gross requirements 30Projected available 10 10 10 10 0

    C Net requirements 20

    Planned order receipt 20

    Planned order release 20

    Gross requirements 30

    Projected available 0 0 0 0

    D Net requirements 30

    Planned order receipt 30

    Planned order release 30

    Gross requirements 20

    Projected available 0

    E Net requirements 20

    Planned order receipt 20

    Planned order release 20

    Gross requirements 20

    Projected available 0

    F Net requirements 20

    Planned order receipt 20

    Planned order release 20

    2