mrp, mrp ii, and erp
DESCRIPTION
MRP, MRP II, and ERP. Overview. MRP, Material Requirements Planning Planning and scheduling technique used for batch production of assembled items. MRP II, Manufacturing Resource Planning ERP, Enterprise Resource Planning - PowerPoint PPT PresentationTRANSCRIPT
15 MRP & ERP
MRP, MRP II, and ERP
15 MRP & ERP
Overview
• MRP, Material Requirements Planning– Planning and scheduling technique used
for batch production of assembled items.• MRP II, Manufacturing Resource
Planning• ERP, Enterprise Resource Planning
– The extensive use of software to integrate record keeping and information sharing throughout an organization.
15 MRP & ERP
• Independent demand: Demand of finished goods.
• Dependent demand: Demand for items that are subassemblies or component parts to be used in the production of finished goods.
• The amount of dependent demand is the function of the amount of independent demand.
Independent vs. Dependent Demand
15 MRP & ERP
• Material requirements planning (MRP): Computer-based information system for ordering and scheduling of dependent demand inventories.– What to order– When to order– How much to order
Material Requirement Planning (MRP)
15 MRP & ERP
MRP Inputs MRP Processing MRP Outputs
Masterschedule
Bill ofmaterials
Inventoryrecords
MRP computerprograms
Changes
Order releasesPlanned-orderschedules
Exception reports
Planning reportsPerformance-controlreports
Inventorytransaction
Primaryreports
Secondaryreports
15 MRP & ERP
• Master Production Schedule– which end items are to be produced,– when they are needed, and– in what quantities.
• Sources of quantities: customer orders, forecasts, orders from warehouses, and external demand.
MPR Inputs: Master Schedule
15 MRP & ERP
MPR Inputs: Master Schedule
1 2 3 4 5 6 7 8 9 10
Procurement
Fabrication
Subassembly
Assembly
Figure 14-4
15 MRP & ERP
MRP Inputs: Bill-of-Materials
Bill of materials: A listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.
Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
15 MRP & ERP
MRP Inputs: Bill-of-Materials
15 MRP & ERP
MRP Inputs: Bill-of-Materials, Example
Example: Use the information presented in the following figure to do the following:
• Determine the quantities of B, C, D, E, and F needed to assemble one X.
• Determine the quantities of these components that will be required to assemble 10 Xs, taking into account the quantities on hand (i.e., in inventory) of various components.
Component On HandB 4
C 10D 8
E 60
15 MRP & ERP
MRP Inputs: Bill-of-Materials, Example
15 MRP & ERP
MRP Inputs: Bill-of-Materials, Example
15 MRP & ERP
MRP Inputs: Bill-of-Materials, Example
15 MRP & ERP
MRP Inputs: Bill-of-Materials, Summary
• Many products have considerably more components.
• Timing is essential (i.e., when must the components be ordered or made).
• The amounts on hand must be netted out (i.e., subtracted from the apparent requirements) to determine the true requirements.
• Accurate records are a prerequisite.– complex and time-consuming
15 MRP & ERP
MRP Inputs: Inventory Records
• Inventory records refer to standard information on the status of each item by time period.– Gross requirements, scheduled receipts, and
expected amount on hand.– Supplier, lead time, and lot size.– Changes due to stock receipts and withdrawals,
canceled orders, and similar events.• Like the bill of materials, inventory records
must be accurate.
15 MRP & ERP
MRP Processing
• MRP processing takes the end item requirements specified by the master schedule and "explodes" them into time-phased requirements for assemblies, parts, and raw materials using the bill of materials offset by lead times.
• The determination of the net requirements (netting) is the core of MRP processing.
15 MRP & ERP
MRP Processing
1 2 3 4 5 6 7 8 9 10 11
Procurement ofraw material D
Procurement ofraw material F
Procurement ofpart C
Procurement ofpart H
Procurement ofraw material I
Fabricationof part G
Fabricationof part E
Subassembly A
Subassembly B
Final assemblyand inspection
Figure 15-8
15 MRP & ERP
MRP Processing: Terminologies
• Gross requirements
• Schedule receipts
• Projected on hand
• Net requirements
• Planned-order receipts
• Planned-order releases
15 MRP & ERP
MRP Processing: Example
• A firm that produces wood shutters and bookcases has received two orders for shutters: one for 100 shutters and one for 150 shutters.– The 100-unit order is due for delivery at the start of week 4 of the
current schedule, and the 150-unit order is due for delivery at the start of week 8.
– There is a scheduled receipt of 70 wood sections in (i.e., at the beginning of) week 1.
• Each shutter consists of two frames and four slatted wood sections. The wood sections are made by the firm, and fabrication takes one week. The frames are ordered, and lead time is two weeks. Assembly of the shutters requires one week.
• Determine the size and timing of planned-order releases necessary to meet delivery requirements under each of these conditions: – Lot-for-lot ordering (i.e., order size equal to net requirements). – Lot-size ordering with a lot size of 320 units for frames and 70 units
for wood sections.
15 MRP & ERP
MRP Processing: Example
• Master Schedule
• Product Directory Tree
15 MRP & ERP
MRP Processing: Example, Lot-for-Lot Ordering
15 MRP & ERP
MRP Processing: Example, Lot-Size Ordering
15 MRP & ERP
MRP Processing: Pegging
• Pegging is the process of identifying the parent items that have generated a given set of material requirements for an item.
15 MRP & ERP
MRP Processing: Pegging, Example
• For example, consider the two product structure trees shown below.
• Suppose that there is a beginning inventory of 110 units of D on hand, and all items have lead times of one week.
• A cancellation of 50 units of C will require the pegging information in the following figure.
15 MRP & ERP
MRP Processing: Pegging, Example
15 MRP & ERP
MRP Processing: Regenerative vs. Net Change
• A regenerative system is updated periodically. It is essentially a batch-type system.– Stable system.– Long lead time.– Less processing load.
• A net change system is continuously updated. Only the changes are explored through the system, level by level; the entire plan would not be regenerated.– Frequent change.– Up-to-date information for planning and control
purposes.
15 MRP & ERP
MRP Primary Outputs
• Planned orders - schedule indicating the amount and timing of future orders.
• Order releases - Authorization for the execution of planned orders.
• Changes to planned orders - revisions of due dates or order quantities, or cancellations of orders.
15 MRP & ERP
MRP Secondary Outputs
• Performance-control reports– missed deliveries and stockouts, and
information for accessing cost performance.
• Planning reports– purchase commitments and information for
future material requirements.
• Exception reports– late and overdue orders, excessive scrap
rates, reporting errors, and nonexistent parts.
15 MRP & ERP
MRP: Other Considerations• Safety Stock / Safety Time: Maintain smooth
operations. • Lot sizing: Minimize the sum of ordering cost (or
setup cost) and holding cost. – Lot-for-lot ordering– Economic order quantity– Fixed-period ordering– Part-period model
15 MRP & ERP
MRP in Services
• MRP applications in services may involve material goods that form a part of the product-service package, or they may involve mainly service components.
• Examples: Food catering and large-scale renovations such as sports stadium or a major hotel.
15 MRP & ERP
• Food catering service– End item => catered food– Dependent demand => ingredients for
each recipe, i.e. bill of materials• Hotel renovation
– Activities and materials “exploded” into component parts
MRP in Services
15 MRP & ERP
Benefits of MRP
• Low levels of in-process inventories
• Ability to track material requirements
• Ability to evaluate capacity requirements
• Means of allocating production time
15 MRP & ERP
Requirements of MRP
• Computer and necessary software• Accurate and up-to-date
– Master schedules– Bills of materials– Inventory records
• Integrity of data
15 MRP & ERP
• Expanded MRP with and emphasis placed on integration– Financial planning
– Marketing
– Engineering
– Purchasing
– Manufacturing
MRP II
15 MRP & ERP
MarketDemand
Productionplan
Problems?
Rough-cutcapacity planning
Yes No YesNo
Finance
Marketing
Manufacturing
Adjustproduction plan
Masterproduction schedule
MRP
Capacityplanning
Problems?Requirements
schedules
Adj
ust m
aste
r sch
edul
e
MRP II
15 MRP & ERP
• Enterprise resource planning (ERP): An expanded effort to integrate standardized record-keeping that will permit information sharing throughout the organization
ERP