mqxf cold-mass assembly and cryostating h. prin, d. duarte ramos, p. ferracin, p. fessia 4 th joint...

19
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014 KEK, Tsukuba

Upload: todd-ward

Post on 29-Dec-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

  • MQXF Cold-mass Assembly and CryostatingH. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia4th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014 KEK, Tsukuba

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsMagnets reception (visual inspection, mechanical and electrical measurement)Cold mass assemblyMagnets alignment on the dedicated bench

    Alignment key installation and welding to the magnet yokeUpper shell positioning

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*MQXFAor MQXFBMQXFAor MCBXFB

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsTack welding the alignment key and the shell to preserve alignment

    Rotation by 180 around the longitudinal axis18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsTransfer inside assembly cradles

    Magnets alignment measurement (at the yoke level)

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*Individual geometrical measurements of straightness in horizontal and vertical planes, twist over full length

    Pitch, yaw and roll angle between magnets

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsBus bars installation and connection

    Instrumentation wires connection (V-Taps, Quench heaters, cryogenic instrumentation)

    Electrical tests (check instrumentation and general wiring) 18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*Wires preparationWires routingWires connectionResistive heaterCryo Thermometer

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsCold bore tube installationHeat exchanger tubes insertionUpper shell installation

    Electrical tests (final check before welding, very important!)

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsTransfer in the welding press

    Longitudinal welding

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsRemoval from the welding pressWelds examination (Visual + X rays)Electrical testsTransfer to finishing benchGeo-magnetic measurements to determine the cold mass main axis

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*Cold mass transfer to the finishing benchTracker in position during measurementsExisting QIMM and DIMM magnetic measurement rotating coil systems

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsWelded cylinder cutting extremities and machining

    Support bases alignment and welding

    Equipped end covers (flanges and bellows) alignment and welding

    Cold bore and heat exchangers alignment and welding to the end covers(Pick-up support alignment and welding if any)18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsCold mass geometry measurement

    Electrical testsWarm magnetic measurements and polarity checks (if different from step 21.)18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*Cold mass finishing benchesGeometric measurement moleLaser tracker

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass assembly stepsCold mass preparation for pressure/leak and cold tests: weld caps on covers apertures

    Weld examination (Visual + X rays)

    Transfer and connect the cold mass into the pressure test tank

    Perform pressure and leak tests

    QA documentation18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*Preparation for leak/pressure and cold testsInsertion in the pressure/leak test tankLeak detection diagram = f (pressure)

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cryostating stepsOnly the main steps are listedThe list is for the most complex cryostat variant, i.e. with jumper and phase separator, thus including a so-called service moduleIntermediate leak checks and electrical tests will be done at critical steps (to be defined)A pressure test may be required at the end, before shipping to the cold test facilityAssuming an LHC type cryostat with support posts and a bottom tray supported shield. The sequence may end up quite different if we need to implement an alternative cryostat design.

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • The examples of the IR quad and LHC main dipole18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cryostating steps (I)Assembly of 1.9 K auxiliary lines, outside the cold masspumping line, aux. bus-bar lines, quench line, etc.Preparation of instrumentation cablespresent LHC choice is to connect all of them to instrumentation feed-box on top of the cryostatAssembly the cold mass onto the bottom tray and cold supports subassemblyWrapping multi-layer insulation (MLI) around the cold massAssembly of the thermal shield shells and auxiliary 70K lines, if anyWrapping MLI around the thermal shieldsInsertion into the vacuum vesselin this phase only 2 lifting points at the extremitiesFastening the cold supports

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cryostating steps (II)Welding of cryogenic piping and phase separatorsAssembly of the instrumentation feed-through (IFS)Splice brazing and welding of bus-bars bypass and temporary cryo circuits for cold testing (those that may not be done during cold mass assembly)Closing of the service module thermal shield and vacuum vesselAssembly of the jumper to the QRL and the IFS boxFinal tests and preparation for transport to SM18 for cold testingCold testStrippingInterfaces preparation for tunnel installationShielding/beam screen insertion

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Appendix18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Computation of deflectionAssumptionsTotal length: 9.5 mMass/m: 1500 kg/mOD: 630 mmVessel thickness:8, 10 and 12 mmOnly the moment of inertia of the vessel is consideredMinimum deflectionC = 2.12 mMaximum deflectionC = 0 m

    18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    TH8 mm10 mm12 mmY min0.20 mm0.16 mm0.14 mmY max9.83 mm7.94 mm6.68 mm

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Computation of deflection18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia

  • Cold mass and cryostatOpen issuesWelding on backing strip on aluminum shells

    Thickness of stainless steel shell (8 or 10 mm)

    Supports of the cold-massConsidered scenario2 (not at the extremities) or 3 supports while inserting the magnet (LHC main dipole scenario)3 support of the cold-mass inside the cryostat2 supports for the cryostat18/11/2014H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia*

    H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia