Page 1: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Report

Galaxy Chemicals Egypt

(S.A.E.)

Project M

By : HSE Supervisor

Alaa shahin

Page 2: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Summary

Statistics from Jun 2010 till today. – Safety Observations- 1144 No's

– Safety walk- 155 No's

– Daily Safety Reports- 155 No’s

– Weekly safety meetings-28 No's

– Weekly Safety Report - 28 No's

– Safety trainings-26 No's

– Safety manuals released-Yes

– Safety Prayer- Yes

– First Aid cases -14 No’s

– Fatal Incidents – 01 No’s

– Safety Pause-11 No's

– Safety Reward- 5 No's

– Emergency cautions- Yes

– Safety monthly celebration :March 2011

Page 3: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Observation

• Safety

observations from

Jun 2010 till today

are 1144 No's

Page 4: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Observation

• Total No of SO’s Points are 1144

• Total No of SO’s Points solved are 1095

• Total No of SO’s Points did not solved are 49

Page 5: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Walk

• Numbers of safety

walk from Jun 2010

till today are 155 No's

• One safety walk daily.

• We show it to Tri

Scope , Offshore and

Poly Plast teams on

the safety meeting to

fix the issues.

Page 6: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Contractors Daily Safety Report

• We make daily safety report for all contractors

Report NO البيان

Staff Members present Galaxy عدد فريق عمل جالكسى

Staff Members present for contractors عدد فريق عمل المقاول الموجود

Head counts of workers اجمالى عدد العمال الموجودين بالموقع

No of Fire Extinguishers عدد طفايات الحريق بالموقع

Near miss found عدد غير الملتزمين بمهمات الوقاية الشخصية بالموقع

Unhealthy of employees عدد العمال المرضى بالموقع

Cigarettes’ smoking عدد العمال الذين قاموا بالتدخين بالموقع

No’s of Tools and tackles عدد المعدات المستخدمة بالموقع

Condition of tools and tackles عدد المعدات التي حالتها غير صالحة للعمل بالموقع

Workers kitchen حالة مطبخ العمال

Is kitchen safe هل المطبخ امن أم ال

Is there a fire extinguisher هل يوجد بالمطبخ طفايات حريق أم ال

Workers rest room condition حالة غرف العمال بالموقع

Whether cleanliness is maintained حالة الجو والنظافة العامة للموقع

Number of training laborers عدد المتدربين من العمال

Number of safety walk for Tri scope عدد جوالت السيفتى لسيفتى المقاول

Number of safety walk for Galaxy عدد جوالت السيفتى بجاالكسى

Page 7: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Daily Safety Report

• No of Daily safety

reports from Jun

2010 till today are

155 No's

Page 8: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Weekly Safety Meeting

• Numbers of

safety meeting

from Jun 2010 till

today are 28 No's

Page 9: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Weekly Safety report

• No of Weekly safety

reports from Jun 2010 till

today are 28 No's

Page 10: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Training

• Numbers of safety

Training from Jun

2010 till today are 26

No's

• We make training (1)

per week for each

contractor.

Page 11: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Manual

We read it and hand it over to the contractor

Tri Scope co.

Offshore co.

Poly Plast co.

Page 12: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Prayer

• Our day at site starts with

Safety prayer in Hindi and

Arabic.

Page 13: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Incidents

• No of Man days worked: 31400

• First Aid cases from Jun 2010 till

today -14 No’s

• Fatal Incidents from Jun 2010 till

today – 01 No’s

Page 14: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Pause

• Safety Pause from Jun 2010

till today are 11 No's

• We give driver a course about

Road Safety

• Its not the car that is safe.

• Its the DRIVER.

What is the car of your dreams ?

Page 15: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety Reward

• Best Safety worker is

given once in 15

days.

• Total 5 workers are

rewarded with this

award.

Page 16: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

EMERGENCY

EMERGENCY

Page 17: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Police Station

Tel: 122

Attaqa Police Station

Tel: 062/3360342

EMERGENCY

Page 18: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• The nearest Engine point.

• The fire fitting truck .

• Tel: 180

• Civil defense department Tel: 062/3331011 - 062/3331021

EMERGENCY

Page 19: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• The nearest hospital

• Medical Center Hospital

• Tel:0181633566

• 062/3365116-062/3365117

EMERGENCY

Page 20: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• The nearest ambulance

point.

• Tel: 123

EMERGENCY

Page 21: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• First Aid box present with

Galaxy as well as with all

vendors.

First Aid

Page 22: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• We Give First Aid to All

Workers at site.

EMERGENCY

Page 23: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

• Total Number of Fire

Extinguishers at Galaxy

Chemical Egypt (S.A.E.) are

27 No's

• Audit is done for once in week

for all fire extinguisher.

EMERGENCY

Page 24: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety monthly celebration

Safety monthly

celebration

March 2011

Page 25: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Following are the activities done in celebration:

• Safety Poster competition.

• Safety Slogan competition.

• Safety Quiz competition.

• Safety Speech competition.

Safety monthly celebration

Page 26: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety monthly celebration

Page 27: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety monthly celebration

Page 28: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Safety monthly celebration

Page 29: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Future Plans

• Put Emergency siren, its

voice should be higher

than any Voice in the site

by 15 dB.

• Cooperation with the

another factories and

build bridges with

surrounding companies in

case of Emergency.

Page 30: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Future Plans

• Emergency plan.

• Make a Emergency

training for workers.

Page 31: Monthly Safety Report- (Mr. Shekhar viset) Project M (03-2011)

Thank you