monthly progress report-october, 201511
TRANSCRIPT
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction of Seven Bridges between Litunde and Marrupa in Niassa
Province, Mozambique
Contract No: 680/DIPRO/2008
Status and Monthly Progress Report No.19
Reporting Period: Until 31 October, 2015
CPG-Civil & Planning Group
Av: Kwame Nkrumah, 1335
Maputo - Mozambique Tel +258 21 414506 / 414508 Fax +258 21 414515 Email: [email protected]
Civil and Planning Group
-
Rehabilitation of Road N14 between Lichinga and Litunde
Construction of Seven Bridges between Litunde and Marrupa.
Page i of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
Table OF CONTENTS
1 INTRODUCTION ....................................................................................................................................... 6
1.1 REPORT STRUCTURE ............................................................................................................... 6
1.2 PROJECT OVERVIEW AND DESCRIPTION OF THE WORKS ........................................................ 6
1.2.1 Overview .......................................................................................................................................... 6
1.2.2 General Works .................................................................................................................................. 7
1.2.3 Road Works ...................................................................................................................................... 7
1.2.4 Drainage Works ................................................................................................................................ 7
1.2.5 Bridge Works .................................................................................................................................... 7
1.3 CONTRACT DETAILS ............................................................................................................... 8
1.4 STATUS OF GUARANTEES AND INSURANCES .......................................................................... 9
2 PHYSICAL PROGRESS OF WORKS .................................................................................................... 11
2.1 OVERALL PROGRESS SUMMARY ........................................................................................... 11
2.2 PROGRESS OF CULVERT CONSTRUCTION .............................................................................. 13
2.3 PLANNED VS. ACTUAL PROGRESS BY WORKS COMPONENT ................................................ 13
2.3.1 Survey &Setting out........................................................................................................................ 14
2.3.2 Traffic Management ....................................................................................................................... 14
2.3.3 Materials Laboratory....................................................................................................................... 15
2.3.4 Engineers Facilities ....................................................................................................................... 15
2.3.5 Major Equipment Mobilization Status ............................................................................................ 15
2.3.6 Drainage Structures & Erosion Protection Works .......................................................................... 16
2.3.7 Railway Crossing ............................................................................................................................ 17
2.3.8 Clearing and Grubbing .................................................................................................................... 17
2.3.9 Earthworks ...................................................................................................................................... 17
2.3.10 Cement Stabilized Sub base ............................................................................................................ 17
2.3.11 Cement stabilized Base ................................................................................................................... 17
2.3.12 Quarry Production .......................................................................................................................... 17
3 FINANCIAL REPORT ............................................................................................................................. 19
3.1 ACCEPTED CONTRACT AMOUNT (ACA) BREAKDOWN ........................................................ 19
3.2 ESTIMATED VALUE OF WORKS COMPLETED TO DATE ......................................................... 19
3.3 CONTRACTORS STATEMENTS .............................................................................................. 20
3.4 INTERIM PAYMENT CERTIFICATES ........................................................................................ 20
3.5 PAYMENTS TO CONTRACTOR ................................................................................................ 20
3.6 PROVISIONAL SUMS EXPENDED ............................................................................................ 21
3.7 PRIME COST SUMS EXPENDED .............................................................................................. 22
3.8 RETENTION MONEY .............................................................................................................. 22
3.9 ACCEPTED CONTRACT AMOUNT ADJUSTMENT .................................................................... 22
3.10 CLAIMS REVIEW .................................................................................................................... 23
3.10.1 Employer Claims ............................................................................................................................ 23
3.10.2 Contractor Claims and Notices ....................................................................................................... 23
3.11 INSTRUCTIONS AND ORDERS ................................................................................................. 23
3.11.1 Site Instructions .............................................................................................................................. 23
3.11.2 Provisional Sum Orders .................................................................................................................. 23
3.11.3 Variation Orders ............................................................................................................................. 23
-
Rehabilitation of Road N14 between Lichinga and Litunde
Construction of Seven Bridges between Litunde and Marrupa.
Page ii of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
3.12 MATERIAL ON SITE ............................................................................................................... 23
4 CONTRACT ADMINISTRATION ......................................................................................................... 27
4.1 CONTRACT SUPERINTENDENCE AND CHANGES .................................................................... 27
4.2 CONTRACTORS ORGANIZATIONAL CHART .......................................................................... 28
4.3 CONTRACT RECORDS ............................................................................................................ 28
4.3.1 Daily Returns .................................................................................................................................. 28
4.3.2 Mobilization of Equipment ............................................................................................................. 28
4.3.3 Labour Return ................................................................................................................................. 28
5 QUALITY ASSURANCE ......................................................................................................................... 30
5.1 PROJECT QUALITY ASSURANCE PLAN (PQAP) .................................................................... 30
5.2 IMPLEMENTATION OF CONTRACTORS QAP ......................................................................... 30
5.2.1 Quality Control Plan ....................................................................................................................... 30
5.3 GENERAL QUALITY CONTROL .............................................................................................. 30
5.3.1 Pre works Compliance Checks ....................................................................................................... 30
5.3.2 Contractors Supervision ................................................................................................................ 30
5.3.3 Engineers Supervision ................................................................................................................... 30
5.4 MATERIAL SAMPLING AND TESTING .................................................................................... 31
5.4.1 Materials from Borrow pits ............................................................................................................. 31
5.4.2 Material from Sub-base and Base Layers ....................................................................................... 31
5.4.3 Aggregates for Surface Dressing .................................................................................................... 31
5.4.4 Crushed Stone Base Aggregates from Stockpiles and the road ...................................................... 31
5.4.5 Concrete Samples from Construction Site ...................................................................................... 31
5.4.6 Bitumen Quality .............................................................................................................................. 31
5.4.7 Prime Coat ...................................................................................................................................... 31
5.4.8 Construction of 1st Seal ................................................................................................................... 31
5.4.9 Construction of 2nd Seal. ................................................................................................................ 31
5.5 SOURCES OF MATERIALS ...................................................................................................... 32
5.6 DESIGN MODIFICATION ......................................................................................................... 32
5.7 ISSUES, PROBLEMS AND SOLUTIONS ..................................................................................... 32
5.7.1 Damaged base layer ........................................................................................................................ 32
5.7.2 Railway Crossing ............................................................................................................................ 32
5.7.3 Non-Conformances ......................................................................................................................... 32
7 ANCILLARY ACTIVITIES ..................................................................................................................... 39
7.1 CLIMATIC & WEATHER CONDITIONS AND CHARTS .............................................................. 39
7.2 LAND ACQUISITION AND UTILITIES RELOCATION ................................................................ 39
7.3 RESETTLEMENT ACTION PLAN (RAP) IMPLEMENTATION .............................................. 39
7.4 OUTSTANDING RESETTLEMENT ACTION PLAN (RAP) ISSUES .................................. 39
7.5 SUBCONTRACTING AND COMPLIANCE WITH ESMP IMPLEMENTATION PLAN ..................... 39
7.6 CORRESPONDENCE ................................................................................................................ 39
7.7 STATUS OF AS-BUILT DRAWINGS ......................................................................................... 39
7.8 RECORD AND MINUTES OF MEETINGS .................................................................................. 39
7.8.1 Minutes of Monthly Site Meeting ................................................................................................... 39
7.8.2 Minutes of Technical Meeting ........................................................................................................ 39
7.8.3 Minutes of EHS .............................................................................................................................. 39
-
Rehabilitation of Road N14 between Lichinga and Litunde
Construction of Seven Bridges between Litunde and Marrupa.
Page iii of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
7.9 VISITS .................................................................................................................................... 40
7.10 PHOTOGRAPHIC RECORD ...................................................................................................... 40
8 RISKS AND MITIGATION MEASURES .............................................................................................. 42
8.1 RISKS TO SUCCESSFUL PROJECT IMPLEMENTATION ............................................. 42
9 SUPERVISION SERVICES ..................................................................................................................... 44
9.1 CONSULTANCY CONTRACT DETAIL ...................................................................................... 44
9.2 ENGINEERS ORGANIZATIONAL STRUCTURE ........................................................................ 44
9.2.1 Organizational Structure and Staffing............................................................................................. 44
9.3 ENGINEERS REPORTING PERIOD ACTIVITY ......................................................................... 45
9.3.1 General Supervision Activities ....................................................................................................... 45
9.4 FINANCIAL DATA, INVOICING, ESTIMATE TO COMPLETION ................................................. 45
9.4.1 Invoices to Date .............................................................................................................................. 45
9.4.2 Invoice Payment Status ................................................................................................................... 46
9.4.3 Contract Sum Adjustment ............................................................................................................... 46
9.4.4 Claims ............................................................................................................................................. 46
9.4.5 Deliverables and Timing ................................................................................................................. 46
9.5 SUPERVISION SERVICE PERFORMANCE REVIEW ................................................................... 46
9.5.1 Factors Affecting Performance ....................................................................................................... 46
9.5.2 Engineers Programme Review ...................................................................................................... 47
9.5.3 Engineers Recommendations. ....................................................................................................... 47
-
Rehabilitation of Road N14 between Lichinga and Litunde
Construction of Seven Bridges between Litunde and Marrupa.
Page iv of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
LIST OF APPENDICES
APPENDIX 1.1 - PROJECT LOCATION MAP
APPENDIX 2.1 - CULVERT SCHEDULE
APPENDIX 3.1 - FINANCIAL PROGRESS, STATUS OF INVOICE AND S-CURVE
APPENDIX 3.2 - CLAIMS REGISTER
APPENDIX 3.3 - SCHEDULE OF STE INSTRUCTION
APPENDIX 4 .1 - CONTRACTORS ORGANIZATIONAL CHART
APPENDIX 4 .2 - EQUIPMENT MOBILIZATION
APPENDIX 4 .3 - LABOUR RETURN
APPENDIX 5 .1 - SCHEDULE OF REQUESTS FOR INSPECTION
APPENDIX 5 .2 - SUMMARY OF LABORATORY TEST RESULTS
APPENDIX 5 .2 - SOURCE OF MATERIAL AND APPROVAL STATUS
APPENDIX 6. 1 - ACCIDENT/INCIDENT MONITORING RECORD
APPENDIX 6.2 - HIV/AIDS AWARENESS AND PREVENTION
APPENDIX 7.1 - WEATHER RECORD
APPENDIX 7.2 - RESETTLEMENT ACTION PLAN
APPENDIX 7.3 - CORRESPONDENCES REGISTER & IMPORTANT CORRESPONDENCES
APPENDIX 7.4 - MINUTES OF TECHNICAL & MONTHLY PROGRESS SITE MEETINGS
APPENDIX 7.5 - MINUTES OF OTHER MEETING
APPENDIX 7.6 - PROJECT PHOTOGRAPHS
APPENDIX 8.1 - ENGINEERS ORGANIZATIONAL CHART
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 5 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
SECTION 1: INTRODUCTION
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 6 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
1 INTRODUCTION
1.1 REPORT STRUCTURE
This report is structured as follows:
Section 1: describes the report layout, gives the project overview, describes the works and presents the Contract data,
Section 2: provides a detailed analysis of the physical progress of the works; evaluates the critical path activities and recommends mitigation measures to counter any
slippages,
Section 3: presents the projects current and projected financial status, Section 4: presents issues related to contract administration, contractors superintendence,
contract records, site instructions and orders,
Section 5: reports on project quality assurance and control issues, Section 6: provides information on the status of the Environmental, Health and Safety matters
on the project,
Section 7: reports on the ancillary activities of the project, Section 8: analyses current risks and presents recommendations for mitigation measures, and Section 9: reports on the Engineers project supervision activities during the reporting period.
1.2 PROJECT OVERVIEW AND DESCRIPTION OF THE WORKS
1.2.1 Overview
Lichinga to Litunde Road Rehabilitation Project stretches for approximately 66 km between
the roundabout in Lulimile suburb of Lichinga and Litunde in Niassa Province; refer to project
location map under Appendix 1-1.
The road is being upgraded by means of widening and strengthening and widening and
resealing of the existing carriageway. The rehabilitated carriageway width will generally
provide for 2 x 3.5m wide traffic lanes, 2 x 0.5m sealed shoulders and 2 x 1.0m cement
stabilized gravel shoulders.
The stretch between Lichinga and Litunde is subdivided in three distinct sections:
1. The first 7 km section, km 0+000 to km 7+140, is an existing 6 m wide surfaced road
that is in fair condition and is to be widened and to receive double seal surface treatment
(DBST) as reseal.
2. From km 7+140 to km 57+870 exists a 4 m wide surfaced road that was resealed not
long ago and that is also in fair condition. In this section the pavement is to be
strengthened, widened and DBST surfaced.
3. From km 57+870 to km 66+200 the road has a width of 6.1 m to km 7.5, that in some
stretches widens to 8 m, with a paved surface in good condition. This section is to be
widened and resealed.
The work consists also of five post stressed girder and slab, one three span and four single span,
bridges that locate outside the project road, but along the same route, between Litunde and
Marrupa.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 7 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
The road between Litunde and Marrupa had been upgraded recently to paved standard. In this
section of the road five bridges, seven bridges as stated in the Contract, are to be constructed
and the approaches widened to a width of 8.0 m.
1.2.2 General Works
The main activities carried out under this item of the contract are:
Establishment on site of camp, offices, stores and plant including removal on completion of works.
Provision of offices, housing, transport and communications for the Engineers supervisory staff,
Provision of a joint laboratory,
1.2.3 Road Works
The road works included in this contract consist mainly of the following:
Clearing and grubbing of the road reserve. Setting out of the works, including level control and measurement of the works. Mass earthworks including rock fill and pioneer layer, Construction of concrete lined drains, chutes, inlet and outlet structure, subsoil drainage
systems, open channel and concrete kerbs.
Construction of selected layer, cement stabilized gravel subbase and base layer consisting of 50% gravel and 50% crushed stone mix, required to rehabilitate the
existing road.
Construction of prime coat and double seal surfacing Construction of ancillary works including stone pitching, gabions, road markings, road
signs, marker and kilometre posts, guardrails and landscaping and grassing.
Accommodation of traffic and construction of diversions where required. Maintenance of the works where required.
1.2.4 Drainage Works
As per design drawing recommendations for drainage, structures are as follows:
Total No. of Culverts = 56
New Culverts = 7
Replaced = 2
Extension Required = 47
1.2.5 Bridge Works
There are a total of five High Level Double Carriage (HLDC) bridges along the same route but
outside the project road section between Litunde and Marrupa which consist of post stressed
girder and slab as shown in Table 1.1 below.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 8 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
Table 1.1: Bridges Details
Bridge Name
Location
from km
66+200
Location
from km
0+000
Type Span
Messenguesse km 199+557 km 265+757 Single Span Post stressed
Girder & Slab
35m
Lureco km 166+444 km 232+644 Single Span Post stressed
Girder & Slab
40m
Necoleze km 114+508 km 180+708 Single Span Post stressed
Girder & Slab
35m
Uriate km 99+997 km 166+197 Single Span Post stressed
Girder & Slab
35m
Lugenda km 83+026 km 149+226 Three Span Post stressed
Girder & Slab
3x40 , Total
Length = 120
m
All the bridges are to be constructed adjacent to existing crossings, outside the existing
alignment and at a raised level (HLDC) which will result in mass earthworks for the
construction of abutment embankment fills after realignment.
The bridge railings are designed to be constructed in reinforced concrete.
1.3 CONTRACT DETAILS
Contract Name The Rehabilitation of Road N14 between Litunde to Lichinga (66 km) and the
Construction of Seven Bridges between Litunde and Marrupa in Niassa
Province, Mozambique
Contract No. 680/DIPRO/2008
Contract Amount MZM 1,271,280,675.49 (One Billion Two Hundred Seventy One Million Two
Hundred Eighty Thousand Six Hundred Seventy Five Meticais and Forty Nine
Cents), inclusive of contingencies and IVA
Currency Proportion 80% Foreign Portion (Euro); 20 % Local Portion (Meticais); Exchange Rate 1
Euro = MZM 37.79
Employer Administrao Nacional de Estradas
Contractor CMC/CMCAA Joint Venture, Maputo, Mozambique
Consultant at commencement
of the works SNC- Lavalin International Inc. CANADA
Consultant after
recommencement of
suspended works
CPG-Civil and Planning Group since March 2015
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 9 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
Date of Letter of Acceptance 1st February 2011
Date of Commencement 20th February 2012
Duration of Contract 24 Months, 731 days
Expected Date of Completion 20th February 2014
Time Elapsed to Date 1348 days (31 October, 2015)
Extension of Time TBA
Revised Completion Date TBA
Estimated Contract Price to
Date
33,640,663.55
1.4 STATUS OF GUARANTEES AND INSURANCES
Table 1.2: Contract Guarantees and Insurance Details
Item Ref. No Date
Effected
Bank/Insurance Company Amount
(MZM)
Amount
(Euro)
End/Release
Date
Remarks
Performance Guarantee
No.
01GR8999/6027356
23rd Feb.
2011
Bank Intesa Sanpaolo SpA
c/o Banca Infrastructtura Innovazione e Sviluppo
SpA, Via Montebello,
18 20121 Milano, Italy.
25,425,613.51 2,691,253.08 28 days from
the date of issue
of the certificate
of completion,
foreseen on 4th April 2014
Expired
Amendment No. 01 to
Performance Guarantee No.
01GR8999/6027356
19
March 2014
28 days from
the date of issue of the certificate
of completion,
foreseen on 30th
November 2015
Must follow
contract completion date
according to
contractors
current works
programme.
Advance Payment Guarantee
No.
01GR8999/6027562
4th
March 2011.
Bank Intesa Sanpaolo SpA
c/o Banca Infrastructtura Innovazione e Sviluppo
SpA, Via Montebello, 18
20121 Milano, Italy.
50,851,227.02 5,382,506.17 Until full
repayment
Until full
repayment to ANE
Contract Works and Contractors Public Liability Insurance
CAR Policy No.
12.000504
19th May
2011
EmpresaMoambicana de
Seguros
Contract
Value , etc
31st December
2015
Policy shall
remain in full
force and effect for additional
period
necessary.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 10 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
SECTION 2: PHYSICAL PROGRESS OF WORKS
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 11 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
2 PHYSICAL PROGRESS OF WORKS
2.1 OVERALL PROGRESS SUMMARY
Following suspension of the works in March 2014, partial works activities were resumed on 4th
May 2015. These activities included only layer works up to subbase level without stabilization.
Full resumption of the works was undertaken only in early July 2015. The cumulative progress
of the construction works is therefore generally as achieved by the Contractor in since early
July 2015 until end of October 2015 as shown in Table 2.1 below.
Table 2.1: Progress Summary
Works
Component Start End Total
(km) % Complete (*) and Remarks
Progress: Overall (All Works) 77.44%
Road Works
Subgrade 0+000 57+870 57.870 100.00
62+120 66+180 4.06 99.51
Total 61.930 99.97%
Cement Stab. S-
Base
0+000 47+860 47.860 72.30%
Cement Stabilized
Base
0+000 7+140 7.14 Completed but traffic and rain
damaged; both rhs and lhs shoulders
7+140 10+900 3.76
10+900 11+440 0.54 Base material spread, but not
completed due to railway line
crossing and associated levels issue.
11+440 23+350 11.91
23+350 25+860 2.510 Section rectified
25+860 44+620 18.760
Total completed 44.12 71.22%
Prime Coat 0+000 7+140 7.14
7+140 10+900 3.76
10+900 11+440 0.54 Base material spread, but not
completed due to railway line
crossing and associated levels issue.
11+440 23+350 11.91
23+350 25+860 2.51
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 12 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
25+860 35+720 9.86
35+720 44+620 8.90
Total Completed 44.08 71.15%
1st Seal 0+000 0+900 0.900
0+900 7+140 Work not yet done
66.2 7+140 10+900 3.760
10+900 11+440 Work not yet done
11+440 23+350 11.900
23+350 37+520 14.17
Total Completed 30.73 46.42%
2nd Seal 0+000 0+900 0.900
0+900 7+140 Work not yet done
66.2 7+140 10+900 3.760
10+900 11+440 Work not yet done
11+440 29+100 17.660
Total Completed 22.32 33.72%
Box and PIPE Culvert Works
Culvert works TBA Culvert construction works not yet
fully commenced exception being
one new culvert at km 45+038.
Bridge Works
Lugenda 94.00%
Uriate 91.00%
Necoleze 83.00%
Lureco 81.00%
Messenguele 74.00%
Material
Crushed Stone (m3) 20000
Crushed stone- (m3) 13000
9.5 mm (m3) 1800
9.5 mm precoated (m3) 285
19.0 mm (m3) 6000
(*) Note: Road subdivided in three sections
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 13 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
1. km 0+000 to km 7+140 (7.14 km), is an existing 6 m wide surfaced road that requires widening to 10.0 m with 1.0 m wide unsurfaced shoulder on each side and resealing.
2. From km 7+140 to km 57+870 and km 62+120 to km 66+200 (54.810 km) exists a 4 m to 4.5 m and 6 m wide road that requires pavement reconstruction and widening to
10.0 m with 1.0 m wide unsurfaced shoulder on each side.
3. From km 57+870 to km 62+120 (4.25 km) the existing road has a width of 6.1 m to 7.5m that in some places widens to 8 m, and requires also widening according to site
condition and resealing.
2.2 PROGRESS OF CULVERT CONSTRUCTION
Progress of culvert construction is as depicted in the culvert schedule presented under Appendix
2.1
2.3 PLANNED VS. ACTUAL PROGRESS BY WORKS COMPONENT
Table 2.2 Below gives current progress details.
Table 2.2: Planned vs. Actual Progress 31 October 2015 (**)
Activity Planned
%
Actual
%
Lead
/Delay
Comments
Clearing and Grubbing
100 100.00 Work was completed only
early October 2015; was to
be completed on 25/6/15
Earthworks (road widening / fill) 100 99.97 Work was completed only
delayed in early October
2015; was to be completed on
31/8/15
Cement Treated Sub-base 100 72.30 Delay Work was to be completed on
29/10/15
Cement treated crushed stone-gravel
mix base
100 71.15 Lead Work is to be completed on
3/12/15
Prime (MC 30) 100 71.15 Lead Work is to be completed on
26/12/15
First Seal (19mm ) 100 46.42 Lead Work is to be completed on
21/12/15
Second Seal (9.5mm) 100 33.72 Lead Work was to be completed on
22/12/15
Culvert/Rehabilitation/Replacement/
New works (structural only)
100 Culvert extension work not
yet commenced. One new
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 14 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
culvert completed
Bridge works
Lugenda Bridge 100 94.00 Delay Work was to be completed on
28/8/15
Uriate Bridge 100 91.00 Delay Work was to be completed on
21/10/15
Necoleze Bridge 100 83.00 Lead Work is to be completed on
18/2/16
Lureco Bridge 100 81.00 Delay Work was to be completed on
26/10/15
Messenguele Bridge 100 74.00 Lead Work is to be completed on
12/12/15
Quarry Production for Crushed
Stone Base.
Crushed Stone Base 100 TBA 20000
Crushed stone-gravel mix 100 TBA 13000
(**) The contractor submitted a revised program on 4th October 2015 to replace the June
tentative Program. According to this current program and as can be observed from the above
the Contractor is behind schedule in construction of sub-base and in construction of Lugenda,
Uriate and Necoleze Bridges. During the review period production has been negiligible This
was mainly due to unavailability of cement for the sub-base. There was also shortage of diesel
internitently caused by cash flow problem. The Contractor needs to submit another revised
program to reflect the real progress.
2.3.1 Survey &Setting out
During the review period survey activities consisted mainly of checks on Subgrade, sub-base
and base for the purpose of compliance with the permissible level tolerance limits, setting out
works on abutment embankment slopes and concrete lined side drains. All survey works
concerning the road alignment and cross sections of the road have been completed.
2.3.2 Traffic Management
The status of Traffic Management is satisfactory with traffic management signs now being
erected as necessary despite the problem faced with vandalism.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 15 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
2.3.3 Materials Laboratory
The Materials Laboratory has been fully operational over the review period with all equipment
supplied to the contract specifications and being in satisfactory condition and having been
calibrated at project resumption. Further equipment calibration is being done as and when
necessary..
2.3.4 Engineers Facilities
The Engineers houses and offices are satisfactory. Occupation of the same has been effected
as necessary.
The following project vehicles are available to the Engineer
1 x 3000 diesel LWB Four by four double cab Toyota Raider.
2 x NP 300 Nissan double cab four by four.
2 x 3000 diesel LWB four by Four single cab Toyota Raider.
2 x NP 300 Nissan single cab four by four
2.3.5 Major Equipment Mobilization Status
Table 2.5 below summarises the Major equipment mobilisation status as at the end of October,
2015.
Table 2-5: Major Equipment Mobilization Status
Item
No
Type Minimum
Requirement
by the
Contract
Actual by
Contractor
Actual
cw(**)
Minimum
Requirement
Remarks
1 Motorised
grader
4 10 +6 1.5 BD; 1 ID;
1 Scrap;
2 Dozer 1 10 +9 3 BD
3 Excavator 3 11 +8 4 BD
5 Front end
loader
3 10 +7 4 BD
6 Tipper
>10m3
15 34 +19 6 BD
7 Water
bowser >
7Kl
6 14 +8
1 BD
8 Vibratory
Roller >20t
4 11 +7 1BD
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 16 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
Note:
(**) cw = compared with
BD = Breakdown
2.3.6 Drainage Structures & Erosion Protection Works
Due to the highly erodible nature of the soils encountered along the project, erosion
protection works are critical. The contractor is being instructed accordingly as the
works progress.
The need for subsoil drainage at varying locations of the road is being assessed and
instructions being issued as necessary.
9 Pneumatic
Roller
4 3 -1 1 BD
10 Crusher 1 1 +0 Consisting
primary,
secondary and
tertiary and
two screens.
BD for one
Week
11 Concrete
mixer
trucks
3 +3
Mobile
mixer 250
ltr and 350
ltr.
2 +2
12 Recycler 5 +5 All not capable
of spraying
water during
mixing. 2 BD
13 Chip
spreader
2 2 0 1 BD
14 Mechanical
Broom
2 +2
15 Bitumen
Distributor
2 3 +1 1 not in use
Total No.
of Items
45 121 76 168.9%
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status
Page 17 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
2.3.7 Railway Crossing
The stabilization works of the base layer and surfacing of the section km 10+900 to km 11+440
could not be completed due to issues concerning level differences between the finished road
level and the levels at which the railway lines were crossing. This had to be discussed with
Corridor de Desenvolvimento de Norte (CDN) and Vale. This discussion was concluded on
29th September 2015 and the two organizations have now given their concent that the road can
be constructed at the current design levels. The Contractor had been instructed to proceed with
the construction works in this section.
2.3.8 Clearing and Grubbing
This activity has been completed satisfactorily up to chainage 66+200.
2.3.9 Earthworks
Earthwork has progressed satisfactorily up to chainage 66+180
2.3.10 Cement Stabilized Sub base
The status of the progress on the construction of cement stabilized sub-base layer is at 47+860
2.3.11 Cement stabilized Base
Construction of the base layer consists of mechanical and chemical stabilization of natural
gravel with 50 % crushed stone material and generally stabilized by 2,5% cement. The progress
of construction works is at chainage 44+620.
2.3.12 Quarry Production
Production of crushed stone materials has been ongoing as necessary. Quantities are given
above.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 18 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
SECTION 3: FINANCIAL REPORT
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 19 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
3 FINANCIAL REPORT
3.1 ACCEPTED CONTRACT AMOUNT (ACA) BREAKDOWN
Table 3-1: Accepted Contract Amount Breakdown
Bill Description Amount (MZM) % of
ACA
A Road Works 766,214,271.59
70.81
B Bridges
Messenguele Bridge 43,438,311.37
4.014
Loreco Bridge 46,171,757.31
4.267
Necoleze Bridge 65,609,291.38
6.063
Uriate 57,102,058.95
5.277
Lugenda 91,623,152.16
8.467
C Daywork 8,676,699.12 0.802
D Social 3,289,650.06 0.304
Total (excluding IVA) 1,082,125,191.94 100%
3.2 ESTIMATED VALUE OF WORKS COMPLETED TO DATE
Table 3.2: Value of Works Achieved to Date (Engineers Estimate)
Bill Description Amount (ZMZ) Amountspent to
Date (ZMZ)
%
A Road Works 766,214,271.59 638,935,000.31 83.38%
B Bridges
Messenguele Bridge 43,438,311.37 28,165,285.97 64.84%
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 20 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
Loreco Bridge 46,171,757.31
33,654,327.92 73.20%
Necoleze Bridge 65,609,291.38 31,226,855.98 47.60%
Uriate 57,102,058.95 31,419,716.72 55.02%
Lugenda 91,623,152.16 74,929,225.33 81.78%
C Daywork 8,676,699.12 62,120.34 0.72%
D Social 3,289,650.06 3,289,650.06 100.00%
Total (excluding IVA) 1,082,125,191.94 841,825,045.25 77.8%
Total as % of Accepted Contract
Amount 77.8%
3.3 CONTRACTORS STATEMENTS
For the review period the Contractor submitted the following Statement by way letter reference
Prot.No.: 993-15-CMCAAJV-RL-AP-CPG dated 31st October 2015.
Statement No.23 over an amount of MZM 368,544,824.12 and Euro 28,892,
286.59 for the period 21st September to 20th October 2015.
3.4 INTERIM PAYMENT CERTIFICATES
For the review period the Engineer issued Interim Payment Certificate:
1. IPC No.18 for an amount of MZM 57,416,571.65 on Statement No.23 for the period
between 21st September to 20th October 2015.
Details of IPCs issued to date are given in Table 3.6 at the end of this section of the report.
3.5 PAYMENTS TO CONTRACTOR
All interim payment certufificates issued to date are listed in Table 3.6 presented at the end of
this section. All payments are done up to and including IPC 15. The last date for payment of IPC
16 was 27th October 2015 and therefore expired. It is likely IPC 16 will attract interest charges.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 21 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
3.6 PROVISIONAL SUMS EXPENDED
Table 3.3: Provisional Sums Expended to Date
Bill Item Prov. Sum
Amount
(MZM)
Expenditure
to Date
(MZM)
Balance ($)
B13.03: Compensation for material
damage suffered by the local
population
625,000.00 227,025.00 397,975.00
B13.05: Payment to DRB 750,000.00 976,582.80 -226,582.80
B14.07: Rented and hotel
accommodation
1,770,000.00 1,905,920.04 -135,920.04
B14.15:The provision of furniture,
appliances and additional appliances
212,400.00 509,693.04 -297,293.04
B14.17: Uninterrupted power supply
(UPS)
129,800.00 136,408.00 -6,608.00
15.08:Repairs, alterations and/or
additions to existing roads used as
diversions
200,000.00 80,000.00 120,000.00
61.01: Additional Foundation
Investigation: Messenguele Bridge
354,000.00 729,609.95 -375,609.95
61.01: Additional Foundation
Investigation: Loreco Bridge
354,000.00 689,118.58 -335,118.58
61.01: Additional Foundation
Investigation: Necoleze Bridge
354,000.00 669,116.40 -315,116.40
61.01: Additional Foundation
Investigation: Uriate Bridge
354,000.00 629,946.92 -275,946.92
61.01: Additional Foundation
Investigation: Lugenda Bridge
354,000.00 655,201.84 -301,201.84
100.3: HIV/AIDS Training 1,180,000.00 1,180,000.00 -
Total 6,637,200.17 8,388,622.90 -1,751,422.73
DW: Daywork 8,676,699.12 62,120.34 8,614,578.78
Social 2,109,650.06 2,712,407.22 -602,757.16
Total 10,786,349.18 2,774,527.56 8,011,821.62
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 22 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
3.7 PRIME COST SUMS EXPENDED
Table 3.4: Prime Cost Amounts Expended to Date
Bill Item Prov. Sum
Amount
(MZM)
Expenditure
to Date
(MZM)
Balance
(MZM)
B14.03: Telephone and radios for
Engineer
1,416,000.00 1,449,117.51 -33,117.51
B14.16:Supply of Office Stationary 76,700.00 675,425.75 -598,725.75
25.06:Provision of vegetation destroyer
and ant poison
4720.08 0.00 4,720.08
71.02: Special tests requested by
Engineer
118,000.00 0.00 118,000.00
Total 1,615,420.08 2,124,543.26 -509,123.18
3.8 RETENTION MONEY
An amount of MZM 105, 956, 577. 30 has been retained until the end of the review period; this
represents the amount withheld up to IPC No.18.
Details of retentions made to date are given in Table 3.6 in this section of the report.
3.9 ACCEPTED CONTRACT AMOUNT ADJUSTMENT
The following table gives a breakdown of the anticipated Final Contract Sum following review
of the Accepted Contract Amount (inclusive of provisional sums, prime cost items,
contingencies and IVA) accounting for variations, claims, Contract Price Adjustment and cost of
time extension.
Table 3.5: Estimated Final Contract Sum
Item Accepted
Contract
Amt. ()
Final Contract
Sum Amt. ()
Difference
Accepted Contract BoQ Value 33,640,663.54 33,640,663.54 NIL
Variation Orders No. 1 TBA -
Approved Claims TBA -
Extension of Time Costs TBA -
Contract Price Adjustment 5,761,861.000 -
Totals 33,640,663.54 39,402,252.54 -
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 23 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
3.10 CLAIMS REVIEW
3.10.1 Employer Claims
There were no Claims from the Employer that were known to the CPG Team at the time of
reporting.
3.10.2 Contractor Claims and Notices
To date the Contractor has submitted a total of 6 notices and has 6 Claims. Engineers opinion
concerning claims 2 and 5 is presented under Appendix 3.2. An Extension of Time resulting
from Claims 2 and 5 in a number of 166 days had been included in Certificate No. 18 following
an Authorization by Administrao Nacional de Estradas.
3.11 INSTRUCTIONS AND ORDERS
3.11.1 Site Instructions
Register of Site Instructions issued by CPG is presented under Appendix 3.3
3.11.2 Provisional Sum Orders
Provisional Sum expended to date is as shown in Table 3.3 above.
3.11.3 Variation Orders
There is a Variation Order issued before suspension of the works. Details of this Variation
Order will be given after thorough study and a register shall be set up.
3.12 MATERIAL ON SITE
The status of materials on site for the review period ending on 31 October 2015 is as shown
here below.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
Page 24 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
,
MONTHLY STATEMENT N 23 MATERIALS ON SITE (MOS) PERIOD: 21 Sept to 20 October 2015
Unit Rate Previous This Month To Date Previous This Month To Date
1 Cimpor Cement (Cimentos de Mozambique) bags 501.54 13,875.00 -13,875.00 0.00 6,958,867.50 -6,958,867.50 0.00
2 Rapid Setting Cement bags 550.01 0.00 0.00 0.00 0.00 0.00 0.00
3 Pre-cast Kerbs Fig. 7 No 283.95 1,246.00 0.00 1,246.00 353,797.95 0.00 353,797.95
4 Pre-cast Kerbs Fig. 8 No 283.95 314.00 0.00 314.00 89,159.36 0.00 89,159.36
5 Pre-cast Kilometer Posts No 1,528.59 66.00 0.00 66.00 100,887.00 0.00 100,887.00
6 Pre-cast 5 Kilometer Posts No 1,528.59 15.00 0.00 15.00 22,928.86 0.00 22,928.86
7 Crushed Stone base m3 383.59 10,190.38 6,514.58 16,704.96 3,908,903.63 2,498,912.25 6,407,815.88
8 19mm stone m3 1,225.64 2,857.26 293.33 3,150.59 3,501,964.51 359,516.20 3,861,480.70
9 9.5mm stone m3 1,225.64 2,341.75 164.32 2,506.07 2,870,136.21 201,396.73 3,071,532.93
10 Bitumen 80/100 Ton 27,606.90 160.014 0.00 160.01 4,453,528.39 0.00 4,453,528.39
11 m2 10.17 2,790.00 0.00 2,790.00 112,814.72 0.00 112,814.72
12 No 1,943.70 1,284.81 -968.81 316.00 2,497,289.51 -1,883,080.31 614,209.20
13 Timber Posts 1,8X150-175mm No 297.83 0.00 426.00 426.00 0.00 126,873.45 126,873.45
14 No 67.29 0.00 426.00 426.00 0.00 28,664.90 28,664.90
15 No 88.29 0.00 426.00 426.00 0.00 37,612.82 37,612.82
13 Geotextile Kaymat U24 (150mx5m) No 17,784.00 9.09 2.91 12.00 161,728.59 51,679.41 213,408.00
14 No 485.93 1,471.56 -698.56 773.00 715,067.97 -339,447.95 375,620.03
16 Gabions Boxes 2,0X1X1 Long Mesh No 956.18 119.28 325.72 445.00 114,052.12 311,445.76 425,497.88
17 Gabions Boxes 3,0X1X1 Long Mesh No 564.30 0.00 102.00 102.00 0.00 57,558.60 57,558.60
18 No Fines units 500 x 500 x 150mm in class No 165.30 6,440.00 -1,456.00 4,984.00 1,064,530.52 -240,676.47 823,854.06
19 Ton 17,791.53 65.84 -8.14 57.70 1,171,394.47 -144,823.07 1,026,571.40
18 Welded Mesh ref.395 (6mx2.5) No 2,000.00 234.00 -126.00 108.00 468,000.00 -252,000.00 216,000.00
19 Welded Mesh ref.245 (6mx2.5) No 1,240.00 0.00 400.00 400.00 0.00 496,000.00 496,000.00
20 Modified Bittumen Ton 34,497.30 109.18 -109.18 0.00 4,224,546.23 -3,766,415.57 458,130.67
21 Colocote in Drums Ton 43,441.43 26.00 0.00 26.00 1,129,477.18 0.00 1,129,477.18
22 Chryso Aditivs (1000 litre Containers) No 25,108.50 1.00 1.00 2.00 258,916.80 25,108.50 284,025.30
23 Armco galvanized Pipe No 4,335.71 41.13 -21.13 20.00 178,339.25 -91,625.15 86,714.10
TOTAL VALUE OF MATERIALS ON SITE (MOS) 34,356,330.77 -9,482,167.41 24,874,163.37
DEDUCT : 25% OF VALUE OF MATERIALS ON SITE 8,589,082.69 -2,370,541.85 6,218,540.84
TOTAL VALUE OF EXTRA WORK TO CARRY FORWARD TO SUMMARY STATEMENT 25,767,248.08 -7,111,625.56 18,655,622.53
Item No DescriptionRates Quantities Amounts (Mzm)
MATERIALS ON SITE (MOS)
Polyethlene Sheeting 30mX3m
Guard-Rails 3,81mx2.6mm
Spacer Block for guardrails
Bolt-Post 350 INCL WASHER
Gabions Matresses 2X1X0,30
Reinforcing Steel Bars
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report
CPG-Civil & Planning Group 25 Monthly Progress Report No 19: October 2015
Table 3.6: Interim Payment Certificates
Certificates Date Work done Claims Psums CPA Local CPA Euro MoS RetentionAdvance Payment
RepaymentVAT Total
Cert. 00 11-Mar-11 238,067,542.87 16,188,592.92 254,256,135.79
Cert. 01C R3 6-Feb-13 56,032,074.65 3,177,420.90 5,628,197.77 13,331,778.76 (7,816,947.21) 0.00 5,315,524.10 75,668,048.97
Cert. 02B R1 31-May-13 63,911,826.73 525,244.86 7,064,292.25 14,836,228.53 985,959.00 (8,732,355.14) 0.00 5,938,001.49 84,529,197.73
Cert. 03A 19-Jul-13 44,424,859.24 261,602.90 5,927,450.99 9,669,055.74 9,036,587.89 (6,931,955.68) 0.00 4,713,729.86 67,101,330.94
Cert. 04 3-Sep-13 35,679,710.62 262,603.55 4,206,645.01 8,141,544.22 3,145,719.89 (5,143,622.33) 0.00 3,497,663.18 49,790,264.14
Cert. 05 3-Oct-13 33,062,921.78 193,105.41 3,615,313.28 6,468,664.81 1,058,498.60 (4,439,850.39) 0.00 3,019,098.26 42,977,751.76
Cert. 06 A 25-Nov-13 19,242,671.53 16,340.64 1,755,309.07 2,682,797.83 (1,921,319.27) (2,177,579.98) 0.00 1,480,754.39 21,078,974.21
Cert. 07 15-Jan-14 26,713,619.29 2,344,813.28 2,847,198.21 4,304,508.56 277,656.24 (2,390,469.32) (4,358,764.89) 2,184,774.09 31,923,335.46
Cert. 08 8-Mar-14 24,260,591.90 199,901.93 4,385,099.61 5,566,782.91 13,866,877.78 (3,441,237.64) (7,724,017.82) 2,757,756.07 39,871,754.74
Cert. 09 8-Apr-14 21,123,008.47 2,942,598.75 3,882,872.41 5,869,453.37 (2,794,847.96) (6,670,122.65) 1,846,051.10 26,199,013.49
Cert. 10 30-May-14 25,653,761.99 3,063,995.72 4,253,191.31 3,071,967.13 (3,297,094.90) (12,917,990.38) 1,572,494.95 21,400,325.82
Cert. 11A 7-Jul-14 29,044,691.62 3,827,816.58 5,555,667.77 5,978,526.05 (3,842,817.60) (9,171,593.89) 2,395,987.35 33,788,277.89
Cert. 12 2-Sep-14 72,897,305.98 8,094,732.89 10,989,786.63 (2,113,508.96) (9,198,182.55) (23,019,162.83) 4,545,742.45 62,196,713.61
Cert. 13 2-Oct-14 44,160,462.80 4,355,307.12 6,790,779.06 (3,779,139.62) (5,530,654.90) (13,944,779.85) 2,555,618.81 34,607,593.42
Cert. 14 4-Mar-15 121,561,415.16 12,136,526.21 18,890,003.73 (7,872,951.75) (15,258,794.51) (44,839,526.90) 6,791,531.72 91,408,203.66
Cert. 15 28-Jul-15 30,769,004.74 3,807,439.66 1,499,357.79 (285,329.89) (3,607,580.22) (10,257,461.90) 1,736,244.71 23,661,674.89
Cert. 16 26-Aug-15 48,218,247.75 6,377,799.35 2,826,104.98 917,975.43 (5,742,215.21) (16,074,515.37) 2,874,061.63 39,397,458.56
Cert. 17 3-Oct-15 80,671,266.34 9,985,438.40 1,593,483.59 (2,469,723.82) (9,225,018.83) (26,893,376.90) 4,276,321.96 57,938,390.73
Cert. 18 31-Oct-15 57,416,571.65 6,116,433.25 320,524.61 (7,111,625.56) (6,385,352.95) (19,140,960.24) 2,556,864.17 33,772,454.93
Cert. 19
834,844,012.24 6,981,033.47 96,137,594.11 121,603,133.25 18,655,622.51 (105,956,577.30) 43,055,269.24 76,246,813.21 1,091,566,900.73
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration
Page 26 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 4: CONTRACT ADMINISTRATION
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration
Page 27 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
4 CONTRACT ADMINISTRATION
4.1 CONTRACT SUPERINTENDENCE AND CHANGES
The Contractors key staff in attendance on the site during the reporting period are as presented
here below in Table 4-1.
Table 4-1: Contractors Key Staff
Ord. Name Function Nacionalidade
1 Alberto Piras Contractor Representative Italian
2 Anteneh Mamo Wolde Mechanic Ethiopian
3 Antonio Oliveira Fernando Ferreira Quantity Surveyor Portuguese
4 Domingos Costa Workshop Manager Moz./Portuguese
5 Fernando Alves Rajado Eletrician Portuguese
6 Jay Bernardo Administrative Manager Philippine
7 Marlon Estrada Fuel Controller Philippine
8 Taib Hbabou Earthmoving Supervisor Moroccan
9 Tamirat Chekol Mechanic Ethiopian
10 Twaibu Kamsuli Laboratory Assistant Manager Malawian
11 Luigi Fumagalli Production Manager Italian
12 Gabriele Lazzari Administrative Manager Italian
13 Kouka Mananga Concrete Foreman Congolese
14 Gianluca de Lorenzo Warehouse Manager Italian
15 Bana Abderrahman Earthmoving Supervisor Moroccan
16 Roseller Roxas Surveyor Manager Philippine
17 Gianni Baldisser Concrete Foreman Italian
18 Martins Gonalo Workshop Manager Portuguese
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration
Page 28 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
4.2 CONTRACTORS ORGANIZATIONAL CHART
The Contractors organizational Charts will be presented as and when compilation of the same is
completed and submitted by the contractor and will be included as Appendix 4.1.
4.3 CONTRACT RECORDS
4.3.1 Daily Returns
The Daily Returns signed by both the Contractor and the Engineer has been compiled during
the review period.
4.3.2 Mobilization of Equipment
The Contractor has satisfactorily mobilized all equipment to site as per contract requirements.
A list of all equipment on site and their status is as presented under Appendix 4.2
4.3.3 Labour Return
The status of labour returns during the reporting period is as presented in Appendix 4.3.
.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control
Page 29 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 5: QUALITY CONTROL
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control
Page 30 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
5 QUALITY ASSURANCE
5.1 PROJECT QUALITY ASSURANCE PLAN (PQAP)
The status of the project quality assurance plan will be given once adequate information has been
received.
5.2 IMPLEMENTATION OF CONTRACTORS QAP
5.2.1 Quality Control Plan
There are some forms/work sheets in the quality control plan that is being used currently for
the day to day activities in the laboratory, site testing and reporting in general. The Quality
Control Plan is a live document that can be continuously updated during the progress of work.
5.3 GENERAL QUALITY CONTROL
5.3.1 Pre works Compliance Checks
The following are considered to be amongst the pre-work compliance checks
Health and safety compliance checks
Environment and social compliance checks
Labour law compliance checks
Traffic Management compliance checks
Material testing facilities and calibration
Material sources and suitability of materials
Availability of resources; i.e., office equipment, personnel and office supplies
Measurement and Survey equipment availability
Measurements check
Office facilities
The Contractor and the Engineer will have to work towards fulfilling all the above throughout
the time remaining.
Currently Contractors request for inspection for any relevant activity is preceded by the
compliance checks as applicable.
5.3.2 Contractors Supervision
The status of most of the components of the Contractors Quality Assurance Plan are not yet
known to the current Engineer. The status concerning the Contractors Health and Safety
Officer, Environmental Site Officer has not been obvious since recommencement of the works
after suspension. However, laboratory personnel have been engaged in the implementation of
the Quality Control Plan.
5.3.3 Engineers Supervision
The current Engineer, Civil and Planning Group (CPG), has been attending to Requests for
Inspection and Approval submitted by the Contractor following completed works activities
carried out on mainly fills, Subgrade, cement stabilized sub-base and base layers, earth and
layerworks on bridge approaches construction works on concrete lined drains and gabion
gravity wall and sampling and testing of materials during the review period.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control
Page 31 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
Schedule of Requests for Inspection received from the Contractor and Approvals given by the
Engineer`s representative for the review period is presented under Appendix 5-1.
5.4 MATERIAL SAMPLING AND TESTING
The material sampling and the various types of tests conducted during the review period are
described under the relevant sub-sections here below and summaries of tests and approval status
are shown in the schedules presented under Appendix 5-2.
5.4.1 Materials from Borrow pits
Sampling and testing for confirmatory tests on CBR, UCS, ITS, durability, Atterberg Limits
and Linear Shrinkage were carried out for the material that was used for construction of all
layer works. The results submitted have been compliant and written approvals have been given
to the contractor as necessary.
5.4.2 Material from Sub-base and Base Layers
Samples of materials from cement stabilized sub base and base layers worked on during the
report period were tested for Indicators,field and laboratory Density, Optimum Moisture
Content (OMC), Unconfined Compressive Strength (UCS) and Indirect Tensile Strength (ITS)
tests and all test results are compliant.
5.4.3 Aggregates for Surface Dressing
Quality control tests were carried out during the month and all results were acceptable.
5.4.4 Crushed Stone Base Aggregates from Stockpiles and the road
Quality control tests were carried out during the month and all results were acceptable.
5.4.5 Concrete Samples from Construction Site
Concrete sampled from structural members of bridges as shown in Appendix 5.2 were tested
for workability and strength and results were acceptable.
5.4.6 Bitumen Quality
No biumen was received on site over the report period. However previous supplies of Colflex
SE1 bitumen last received in September 2015 and used on site were found acceptable as per
Quality test results submitted by the Contractor and provided by the supplier.
5.4.7 Prime Coat
This activity was was not carried out this month.
5.4.8 Construction of 1st Seal
This activity was satisfactorily carried out for the section from km 23+500 to km 25+860
5.4.9 Construction of 2nd Seal.
This activity was satisfactorily carried out for the section from km 23+500 to km 29+100
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control
Page 32 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
5.5 SOURCES OF MATERIALS
The sources of materials that have been identified and approved to date are as shown in the table
included under Appendix 5.3.
5.6 DESIGN MODIFICATION
The Contractor proposed that the modified binder Colflex SE1 specified in the Lichinga Litunde
Road Rehabilitation and Upgrading project to be replaced by the penetration grade bitumen
70/100 of which 330 tons are available at their Montepois Works Yard. The proposal is done
mainly due to the non availability of the SE1 binder at the Lichinga Site because of sever cash
flow problem the Contractor is facing at this point in time. The contractors proposal is passed to
the ANE with the Engineers recommendation for their consideration.
5.7 ISSUES, PROBLEMS AND SOLUTIONS
5.7.1 Damaged base layer
The following two sections were rejected due to damage during the works suspension period
caused by vehicular traffic and surface run-off during rains.
The Base sections of the shoulders from chainage 0+900 to 7+140
The full width base within chainages 23+350 to 25+860
Instructions were issued to the contractor for rectification of both sections following which
the section km 23+350 to km 25+860 had already been rectified during the month of
September 2015.
5.7.2 Railway Crossing
The stabilization works of the base layer and surfacing of the section km 10+150 to km
11+450 could not be completed due to issues concerning level differences between the
finished road level and the levels at which the railway lines were crossing. This had to be
discussed with Corridor de Desenvolvimento de Norte (CDN) and Vale. This discussion was
concluded on 29th September 2015 and the two organizations have now given their consent
that the road can be constructed at the current design levels. Instructions to proceed with the
construction works had been issued to the Contractor early October 2015.
5.7.3 Non-Conformances
The following non-conformances, all caused by the Contractor, were discovered during the
review period.
Wrong alignment setting out on the Lichinga side approach of Uriate Bridge.
Following the wrong setting out a wrong work was done which now needs
rectification.
Abutment embankment slope, left hand side on the Lichinga side, was set out
wrongly and the slope is cut to the wrong inclination.
Wrong design of inserting a left curve between two right curves instead of joining
them with a tangent. Alignment looks aukward. Needs to be changed. But requires
only minimal rectification.
Wrong alignment setting out on Lichinga side of Lureco bridge approach. Work
commenced on the wrong premise and therefore needs rectification by the Contractor.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety
Page 33 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 6: ENVIRONMENT, HEALTH AND SAFETY
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety
Page 34 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
6 ENVIRONMENTAL MONITORING, HEALTH AND SAFETY
6.1 QUALITY ASSURANCE DOCUMENTS
The status of the Project Quality Assurance documents up to end of reporting period will be
reported on as information becomes available:
6.2 ESMP IMPLEMENTATION
6.2.1 EHS Meeting/ Audit/ Inspection
Will be reported on as and when information becomes available
6.2.2 Induction/ Training/ Toolbox Talk/Inspection Monitoring
Will be reported on as and when information becomes available.
6.2.3 Monthly Environmental, Health and Safety Training Session
Will be reported on as and when information becomes available..
6.3 ENVIRONMENT MONITORING
6.3.1 Environmental Baseline Survey Report (EBSR)
Will be reported on as and when information becomes available
6.3.2 Road Reserve
Anthills
Site Instructions were issued to the Contractor for removal of anthills within the realignment
to Lugenda, Uriate , Nicoleze and Lureco bridge approaches as well as for the main road works
section 23+350 to 66+200 as detailed in Appendix 3.3
6.3.3 Camp site
Hazardous Substance Management
Will be reported on as information becomes available.
Waste Management
Will be reported on as information becomes available.
6.3.4 Borrow Pits
The status of the borrow pits during the reporting period is as shown in the table below.
Borrow pits Station Side Status
25+700 RHS In use for Base material
29+960 LHS Not opened due to excessive haul distance
36+640 LHS Not opened, Not required for subgrade
38+400 LHS Used up; Pending rehabilitation
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety
Page 35 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
47+400 LHS Used up; Pending rehabilitation
47+800 LHS In Use for subbase
74+800 LHS Stock piling in progress for subbase and base
154+000 RHS Stock piling in progress for base blending with
crushed stone.
154+000 LHS Pending rehabilitation
171+900 RHS Pending rehabilitation
176+300 LHS Stock piling in progress for subbase and base
186+300 L and In use for fill and preparation for Subbase stock
187+200 LHS No Longer Required
242+200 RHS Not yet opened for sub-base and base
242+200 LHS Not yet opened for fill
276+700 RHS Not yet opened for fill
277+700 LHS Not yet opened for sub-base and base
6.4 SAFETY MONITORING
6.4.1 Accident/ Incident Records
Will be reported on as information becomes available under Appedix 6.1.
6.4.2 Road Safety Campaign
Will be reported on as information becomes available.
6.4.3 Personnel Protective Equipment
All the Contractors employees were provided with basic safety equipment. But currently it is
observed that some workers do not use PPE
6.4.4 Fire Extinguisher
Fire extinguishers have been distributed within the Campsite, Engineers facilities and the
Quarry including the second camp site at Lugenda and efforts are being made to improve the
current situation.
6.4.5 Traffic Accommodation
The deviation has been satisfactorily constructed between km 23+400 and km 66+200 and is
currently open to traffic. The Contractor is currently working towards making the main road
trafficable during the rainy season.
6.5 HEALTH MONITORING
6.5.1 Site Clinic
A Clinic and an ambulance have been available to the workers and fully functional.
6.5.2 Illness/ Injuries
No Reports of injuries and illnesses have been recorded in this period.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety
Page 36 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
6.5.3 Water for Human Consumption ( Laboratory Results)
Reports will be made when more information is available.
6.5.4 Toilets
Reports will be made on portable toilets for field use when more information is received
concerning this matter.
6.5.5 First Aid Kits
Reports will be made when more information is received concerning this matter.
6.6 HIV/AIDS AWARENESS CAMPAIGN
The Contractor held HIV/AIDS awareness and prevention campaign, the first after resumption
of the works, using own trained staff. A report was also generated and submitted to the Engineer
for review. This work is conducted at the Contractors own cost and will continue to be this way
until the Environment, Health and Safety Officer and the HIV/AIDS awareness campaigner
subcontractor have been remobilized. In addition, the Contractor has also submitted HIV/AIDS
Awareness and Prevention Campaign Program covering the period from 20th October 2015 to
17th December 2015. Copies of the above report and campaign program are presented under
Appendix Appedix 6.2.
6.7 TRAFFICKING IN PERSONS (TIP)
Can only be reported as and when information is received.
6.8 SOCIAL ISSUES
6.8.1 Project Liaison Committee (PLC)
Reports will be prepared once more information has been received.
6.8.2 Employment and gender issues
Statistics of number workers subdivided into gender during the life of the project to date will
be given once it is made available.
6.8.3 Non-conformances Monitoring
This will be reported once the record has been made available or received under.
6.9 PROJECT TECHNICAL ISSUES
All the documents in the table below needed to have been submitted by the Contractor and
checked and approved by the Engineer. Whether this had been done before the period of
suspension of the works can only be reported when the information is received.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety
Page 37 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
Description Date Submitted By Contractor
Current Status Version 00 Version 01
Waste Management Plan TBA
HSE Awareness Training
Plan TBA
Environmental Method
Statement (EMS) Camp
Site Clearing and
Grubbing
TBA
EMS Camp Site
Establishment TBA
EMS Road Maintenance TBA
EMS Road Reserve
Clearing and Grubbing TBA
EMS Treatment of Ant
hills TBA
EMS Borrow pits TBA
EMS Opening of
Dumping Site TBA
EMS Concrete Batching
Plant localization TBA
EMS for Quarry TBA
EMS Quarry Rock
Blasting TBA
EMS Waste Management TBA
EMS Chemical Products TBA
EMS Deviations TBA
EMS Rehabilitation of
Borrow Pits TBA
Road Awareness Plan TBA
EMS Application of MC
30 and Bitumen Products TBA
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity
Page 38 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 7: ANCILLARY ACTIVITIES
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity
Page 39 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
7 ANCILLARY ACTIVITIES
7.1 CLIMATIC & WEATHER CONDITIONS AND CHARTS
Rain gauge readings for the month of October 2015 and a table showing the possible effects of
the rains on the works are presented under Appendix 7.1.
7.2 LAND ACQUISITION AND UTILITIES RELOCATION
These two activities were not done during the review period.
7.3 RESETTLEMENT ACTION PLAN (RAP) IMPLEMENTATION
The work of RAP Implementation has been completed. There were some properties identified
for compensation at Uriate and Lugenda Bridges. A list of names of property owners eligible for
compensation will be presented under Appendix 7.2 as and when information is available.
7.4 OUTSTANDING RESETTLEMENT ACTION PLAN (RAP) ISSUES
There are no outstanding resettlement action plan issues.
7.5 SUBCONTRACTING AND COMPLIANCE WITH ESMP IMPLEMENTATION PLAN
There is no Subcontractor on the project site currently.
7.6 CORRESPONDENCE
The summary list of correspondence as well as some key correspondence for the review period
is presented under Appendix 7.3.
7.7 STATUS OF AS-BUILT DRAWINGS
Preparation of as built drawings has not yet commenced.
7.8 RECORD AND MINUTES OF MEETINGS
7.8.1 Minutes of Monthly Site Meeting
The monthly Progress Site Meeting was held on 27th and 28th October 2015. On 27th October
2015 a site visit in connection with road works was conducted following which a Progress Site
Meeting was held at the Engineers Office. On 28th October 2015 site vist was conducted in
connection with the five bridges being constructed in the Litunde to Marrupa section. The
minutes are presented under Appendix 7.4.
7.8.2 Minutes of Technical Meeting
Technical Meetings was held on 21st October 2015 minutes of which are presented under
Appendix 7.4.
7.8.3 Minutes of EHS
No EHS meeting had been held during the review period.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity
Page 40 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
7.9 VISITS
Details if any will be presented under Appendix 7.5.
7.10 PHOTOGRAPHIC RECORD
Project photographic records are presented under Appendix 7.6.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services
Page 41 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 8: RISKS AND MITIGATION MEASURES
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services
Page 42 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
8 RISKS AND MITIGATION MEASURES
8.1 RISKS TO SUCCESSFUL PROJECT IMPLEMENTATION
The tentative programme of works issued by the contractor in June 2015 had been replaced by a
revised one on 4th October 2015. According to this program the work could be expected to be
completed only in February 2016. But this is only possible if the following issues were resolved
urgently.
a) Settlement of all issues pertaining to Claims, certificates and extension of tim b) Revision of the tentative Program of Works and strict adherence to it by the
Contractor.
c) Urgent decision by Adiministraa Nacional de Estradas concerning the issue pertaining to replacement of SE-1 (SBR) bitumen currently in use by a common
70/100 penetration grade bitumen.
d) Resolving the problem faced by the Contractor in connection with cash flow and the resulting problem in purchasing cement, binder and diesel.
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services
Page 43 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
SECTION 9: SUPERVISION SERVICES
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services
Page 44 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
9 SUPERVISION SERVICES
9.1 CONSULTANCY CONTRACT DETAIL
Contract Name : Rehabilitation of Road N14 between Lichinga
and Litunde
Funding : AfDB
Employer : Administrao Nacional de Estradas (ANE)
Contract No. : TBA
Contract Amount for Phase 3 : TBA
Date of Contract Signing : TBA
Commencement Date : TBA
Completion Date : TBA
Percentage Time Elapsed : TBA
Revised Completion Date : TBA
Revised Contract Amount : TBA
9.2 ENGINEERS ORGANIZATIONAL STRUCTURE
9.2.1 Organizational Structure and Staffing
The Engineers organizational structure is as given in tabular form below.
Table 9.1: Record of CPG Staffing
Position Name Effective Base Work Permit Status
Management
Project Manager Rick Correia Maputo
Engineer JP DAguiar Maputo
Site Supervision Staff Lot C: Lichinga Litunde Road
Resident Engineer Elias Ibrahim Lichinga, 5th April
2015
Issued
Measurements D.R.
Engineer
Simon Nderi Lichinga,
September,2015
Issued
Materials/A.R. Engineer Peter
Mzarabani
Lichinga, 15th March
2015
Issued
Materials/D.R. Engineer Charles
Munetsi
Lichinga August,2015 Issued
Inspector of Works Carlos
Lourenzo
Lichinga August,2015 Local
Surveyor Salvadore
Tamele
Lichinga August,2015 Local
-
The Rehabilitation of Road N14 between Litunde to Lichinga and Construction
of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services
Page 45 of 48
CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015
EHS Supervisor TBA
9.3 ENGINEERS REPORTING PERIOD ACTIVITY
9.3.1 General Supervision Activities
Table 9.4: Supervision Activities Summary
9.4 FINANCIAL DATA, INVOICING, ESTIMATE TO COMPLETION
9.4.1 Invoices to Date
The Status of invoices for the Supervision Services is as shown in the table below.
Ac