MANAKAMANA ENGINEERING HYDROPOWER COMPANY (P) LTD.
Ghatte Khola Small Hydropower Project
Dolakha
CONSULTING SERVICES AND
CONSTRUCTION SUPERVISION
MONTHLY PROGRESS REPORT
September-2018
Submitted By:
TAC Hydro Engineers Pvt. Ltd. Kupandole, Lalitpur Tel No. +977 1 5522896 Fax No. +977 1 5522896 E-mail: [email protected]
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. i
TABLE OF CONTENT
TABLE OF CONTENT i
LIST OF ANNEXES ii
LIST OF ABBREVIATIONS iii
SALIENT FEATURES OF THE PROJECT iv
PROJECT LOCATION MAP viii
1 GENERAL a
1.1 Introduction a
1.2 Work Nature a
1.3 Report Setup b
2 PROJECT MANAGEMENT b
2.1 Organizational Set up b
2.2 Construction Management b
2.3 Visit to the Work Site c
3 PROJECT ENGINEERING c
3.1 Project Engineering c
3.2 Construction Works c
3.2.1 Civil Works c
3.2.2 Hydromechanical Works d
3.2.3 Electromechanical Works h
3.2.4 Transmission Line Works h
4 QUALITY CONTROL h
5 CLAIMS AND VARIATION h
6 AREAS OF CONCERN AND CORRECTIVE ACTIONS h
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. ii
LIST OF ANNEXES
Annex – A List of personnel of the Employer, the Consultant and the Contractor
Annex – B Progress Sheets
Annex – C Deviations in Time Schedule
Annex – D Photographs
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. iii
LIST OF ABBREVIATIONS
BOK
COD
-
‐
Bank of Kathmandu Limited
Commercial Operation Date
CMA ‐ Construction Management Advisor
DoED ‐ Department of Electricity Devlopment
Development DS
‐
Downstream
EM ‐ Electro‐mechanical
HW ‐ Headwork
HM ‐ Hydro‐mechanical
HR ‐ Headrace
NEA ‐ Nepal Electricity Authority
PC ‐ Penstock
PH ‐ Powerhouse
PPA ‐ Power Purchase Agreement
JV ‐ Joint Venture
RCOD ‐ Required Commercial Operation Date
SHEP ‐ Small Hydroelectric Project
SS ‐ Substation
TAC Hydro ‐ TAC Hydro Engineers Pvt. Ltd.
TR ‐ Tailrace
TL ‐ Transmission Line
US ‐ Upstream
VCB ‐ Vacuum Circuit Breaker
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. iv
SALIENT FEATURES OF THE PROJECT
Project Location : Marbu VDC of Dolakha District,
Central Development Region,
Nepal
Longitude : 27o46′25″ N to 27
o47′14″ N
Latitude : 86o17′00″ N to 86o
18′35″ N.
Type : ROR Small Hydro
Hydrology
Catchment Area (Intake Site) : 30 km 2
(Total) Average Flow : 3.20 m3/s
Design Flow : 1.78 m3/s (Q40)
1:100 years flood : 90.70 m3/s
Weir
Type : Concrete diversion weir with controlled
spillway
Crest Elevation : 1906.00 masl
Crest Length : 15.00 m
Maximum Height : 5.00 m (From Foundation)
Intake
Type : Orifice Intake
Invert Level : 1904.5 masl
Normal Water Level : 1906.00 masl
Width x Height : 3.0 m x 0.40 m
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. v
Undersluice
Invert Level : 1901.5 masl
Normal Water Level : 1906.00 masl
Width x Height : 2.0 m x 2.5 m
Desander
Type : Dufour
Length : 38.00 m
Width : 3.00 m
Depth : 4.20 m
Flushing : Simple head cutting (In the monsoon)
Water Conveyance System (Headrace Pipe)
Length : 2085 m
Diameter : 1.3 m
Thickness : 6 mm
Surge Tank Dimensions
Height : 17 m
Diameter : 3.5m
Normal Water Level : 1904.44 msl
Static Water Level : 1906.44 msl
Minimum Downsurge level : 1894.23 msl
Maximum upsurge level : 1912.44 msl
Invert Level of Penstock Intake : 1892.94 msl
Surface Penstock / Manifold
Penstock Length : 1015. m
Diameter (Internal) : 0.90m
Thickness (Steel) : 6mm to15mm
Number of Anchor Blocks : 20
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. vi
Manifold Length : 8.0m
Diameter (Internal) : 0.64 m
Thickness (Steel) : 15 mm
Power Facilities
Powerhouse Type : Surface
Dimensions (L x B x H) : 24.00 m x 10.00 m x
14.00 m Gross Head : 345.20 m
Net Head : 338.47 m
Installed Capacity (Q40) : 5000
KW Average Annual Energy Output : 29.87
GWh Energy Output (Dry Season) : 4.4
GWh Energy Output (Wet Season) : 25.4
GWh
Transmission Line and Sustation
Transmission Line : 14.0 km (33 kV Single Circuit)
Sub station : Singati
Cost
Total Cost with Financing : Rs. 87.63 Crore
Loan Amount : Rs. 61.00 Crore
Promoter Equity : Rs. 26.63 Crore
Cost per MW : Rs. 17.53 Crore
Revenue per MW : Rs. 2.90 Crore
Financial Indicators
Financial Cost : Rs. 87.63 Crore
IDC : Rs. 6.13 Crore
IRR : 13.84 %
Return on Equity : 18.52 %
NPV : Rs. 24,705 thousand
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. vii
Benefit Cost Ratio (B/C) : 1.33
Debt Service Capacity Ratio : 1.62
Payback Period - Simple : 6.47 years
Payback Period - Discounted : 10.81 years
Construction Period : 1.5 Years
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. viii
PROJECT LOCATION MAP
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. a
1 GENERAL
1.1 Introduction
Ghatte Khola Small Hydroelectric Project with installed capacity of 5000 kW, being
constructed by MANAKAMANA ENGINEERING HYDROPOWER COMPANY (P) LTD.,
is in the preliminary phase of construction. Construction site of this project is at the Ghatte
Khola, Marbu‐VDC, Dolakha, which is a tributary of Khare River. This is a run‐off‐river
scheme with orifice side intake. The proposed headworks site is located on the left bank of Ghatte
Khola about 100 m downstream from the confluence of Thado Khola and Ghatte Khola at an
elevation of 1906 masl in Marbu VDC-7. Similarly, the powerhouse site is on the left bank of
Ghatte Khola around 125m upstream of the confluence of Khare Khola and Ghatte Khola in the
same VDC at an elevation of about 1585 masl. Geographically, the project is located in between
86°17′00″ N to 86°18′35″ N Latitudes and 27°46′25″ N to 27°47′14″ N Longitudes.
Water will enter into the system through orifice side intake on the left bank of the river.
Diversion weir is of non‐regulated type, with Orifice type intake & one under‐sluice on the
left bank. Water will be carried to the 32m. long double chamber desanding basin through
30 m long power canal having 7m long spillway. Water is conveyed through a 2234m long
steel headrace pipe having 1300mm diameter and 1015m long steel penstock pipe. Circular
Steel Surge Tank of diameter 5m is used to regulate the surge. There are two numbers of pelton
tur bine s each of installed capacity 2500 kW. A 14.5 km long 33kV transmission line will
feed generated power from the Powerhouse (switchyard) to Singati substation.
1.2 Work Nature
Construction work comprises of construction of access road to Headworks and Powerhouse, civil
works at headworks, headrace alignment, penstock and powerhouse area, fabrication and
erection of steel pipe for headrace and penstock pipe, installation and commissioning of
electromechanical equipment in powerhouse, switchyard and Singati substation, erection of
transmission line and other related works.
Sakurapower/Biruwa/Divyajyoti J.V. has been selected for the construction of all civil works.
North Hydro and Engineering Pvt. Ltd. is responsible for all Hydromechanical works and Hydro
Equipment Services Pvt. Ltd. is awarded electromechanical installation work. Consulting and
construction supervision has been awarded to TAC Hydro Engineers Pvt. Ltd.
17 km. of Motorable track goes from Singati to Marbu (Powerhouse site). Singati is connected
to Charikot (District Headquater) by 47 km. good gravel road. 450 m access road to Powerhouse
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. b
has been constructed to reach the Powerhouse and 500 m to reach Headworks along Ghatte khola.
The overall length of track opening for waterway alignment is around 2234 m. At present full
loaded truck can reach to the Surge Tank area and access road towards Powerhouse and
Headworks.
1.3 Report Setup
TAC Hydro was responsible for carrying out the detailed design of the project. In addition, it has
been awarded the consulting services for the engineering supervision of all the construction works
going on at site including managerial activities at Kathmandu office.
This is Monthly Progress Report for the month of September 2018, which consists of an account
of construction activities of civil structures, hydro mechanical components, electromechanical
equipment, transmission line and project infrastructures carried out in the past month, major
problems arisen, deviations from the original working schedule and the catch‐up plans,
photographs of progresses made in the last months and other relevant details as per the activities
being carried out.
This report includes the following Annexes:
List of personnel of the Employer, the Consultant and the Contractor are given in Annex–
A. Progress Sheets are given in Annex–B. Deviations in Time Schedule is presented in
Annex–C and photographs are presented in Annex‐D.
2 PROJECT MANAGEMENT
2.1 Organizational Set up
This project is under direct supervision of Company’s Directors. TAC Hydro assists the
Management by looking after all the technical matters of the Project. All other issues are
directly taken over by the Management.
2.2 Construction Management
One PRO is stationed at site to resolve social issue. Technical matters are all handled by the
engineers deputed at site from the Consultant, TAC Hydro. There is one Resident Engineer,
one Civil Engineer, one Mechanical Engineer and three Civil Sub‐ Engineers / surveyor
including four Sub-overseer stationed at site. Considering work progress few more engineer and
supervisors shall be deputed at site. Other kinds of engineering professionals handle the
technical matters from Kathmandu, and they visit site every now and then. During
electromechanical installation works, one electrical engineer along with supervisor shall be
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. c
deputed at site.
2.3 Visit to the Work Site
Project officials, Consultants and bank’s representatives frequently visit the work site to apprise
themselves of latest situation.
Name Organization Designation
1. Tek Prasad Chaulagain Manakamana Engineering
Hydropower Pvt. Ltd.
Director
3 PROJECT ENGINEERING
An Agreement was signed between Manakamana and TAC Hydro Engineers Pvt. Ltd.
(hereafter, referred as TAC Hydro) for Construction Supervision and management of site
works of the Project. As per the provisions and scope of consulting services, the Consultant
makes a constant control and monitoring of Contractor’s works within the frame work of the
Technical Specifications and reports timely to the Project, with suggestions and
recommendations for further actions. The Consultant also makes observations of overall
progress at site and checks it against the time schedule of the Project. The Consultant also
indicates those activities which are lagging and need special attention and efforts to complete
the activities in order to catch up the schedule.
3.1 Project Engineering
i. Inspection, measurement and quality control of civil construction works .
ii. Identification of interferences and dependencies with preceding, concurrent and follow-on
Contractors and utilities.
iii. Internal Discussion and planning of construction works.
iv. Discussion and planning of daily construction works with the contractor
v. Suggestions and recommendations for improving the speed of construction works.
3.2 Construction Works
3.2.1 Civil Works
3.2.1.1 Intake, Undersluice and Settling Basin
I. Concreting (About 8 m3) is carried out at inlet gate of settling basin along deck slab .
II. Concreting (about 150 m3) of Settling basin panel 6, panel 7, panel 8 and panel 5 base slab is
completed
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. d
III. Concreting of headpond (20 m3) has been carried out upto 1908 msl.
IV. Stone masonry work about 15 m3 has been carried out settling basin panel 1
3.2.1.2 Waterway Alignment.
I. Excavation has been carried out in between AB 10-11 of headrace alignment.
3.2.1.2.1 Power House
I. Concreting of MIV is completed
II. Concreting of control room upto beam level is completed
III. Concreting for the base for transformer, Isolator is carried out at switch yard.
3.2.1.2.2 Penstock
I. Concreting (about 60 m3) of AB 17 has been carried out
II. Stone masonry for 5 saddle support has been completed in between AB 9-10.
III. 2 numbers of saddle support has been constructed in between AB 18-19.
IV. The saddle cap concreting (10 m3) in between AB 9-10 and AB 13-14 has been completed.
V. Concreting of Reducer block in between AB 15-16 of penstock alignment has been completed
3.2.1.2.3 Construction Material Stock
Item Description Previous Month Stock Added This Month Used This Month Current Stock
Cement (50 kg bag) 2500.00 1500.00 2000.00 2000.00
Reinforcement (ton) 15.00 0.00 5.00 10.00
Sand (m3) 200.00 150.00 150.00 200.00
Aggregate (m3) 125.00 250.00 225.00 150.00
Equipment’s Mobilized by Civil Contractor at Site
S.N Name
1 Excavator (PC 225, Doosan) 2
2 Breaker 1
3 Back Loader (JCB) 1
4 Dumper (Tipper) 2
5 Bolero 1
6 Tractor 1
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. e
3.2.2 Hydromechanical Works
• AB 16-17 Pipe Erection
30m length of pipe has been installed in between AB 16-17 of penstock alignment.
• AB 15-16 Pipe Installation
About 30 m of total lenth of pipe has been installed in between AB 15-16 of penstock alignment
this month.
• Pipe Installation in between AB 15-16
About 70m of pipe length has been installed in between AB15-16 during the month
• Pipe Installation in between AB 7-8-9
24 m length of pipe has been installed in between AB 7-8-9 of penstock alignment
• De coiling and Shifting
De coiling and shifting of pipe is ongoing from camp yard to site.
H.M contractors material Stock at site:
S.N. Items Name Specifications Units Quantity
1 Electrode 4.00 ESAB Kg 60
2 Electrode 3.15 ESAB Kg 100
3 Electrode 3.15 D&H kg 70
4 Electrode 3.20 D&H kg 150
5 Electrode 2.50 D&H Kg 255
6 Electrode 3.15 ADOR Kg 10
7 Grinding Wheel 7" Nos 56
8 Grinding Wheel 5" Nos 45
9 Grinding Wheel 4" Nos 53
10 Cutting Wheel 7" Nos 53
11 Cutting Wheel 5" Nos 77
12 Cutting Wheel 4" Nos 53
13 Black Goggles Nos 20
14 White Goggles Nos 19
15 Bulb 100 W Nos 8
16 Welding Holder Nos 3
17 Gas cutting Nozzle Nos 4
18 Chalk Pks 7
19 Insulation tape Nos 15
20 Thread Seal Tape Nos 2
21 L.P.G. Regulator Nos 1
22 Bulb Holder Nos 9
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. f
23 Power Socket Set 11
24 Jute Nos 18
25 Buffing Wheel 3" Nos 4
26 Cleaner Nos 7
27 Developer Nos 1
28 Penetrant Nos 5
29 Welding Helmet Nos 1
30 Bulb 100 W Nos 3
31 Cable Shoe Nos 4
32 Hose Clip Nos 6
33 Gas Cutting Torch Nos 1
34 Painting Roller Nos 17
35 safety Shoe Nos 2
36 Oven Nos 1
37 7/22 wire m 70
38 Industrial Fan Nos 1
39 Blower Fan Nos 1
40 Safety Helmet Nos 7
41 Screw Driver Set Nos 1
42 ABC Connector Nos 15
43 Carbon Brush Nos 4
H.M Contractors Equipment and Tools at site
S.N. Tools and Equipment Brand Name Quantity
1 Welding Machine 10
2 Chain Block(3 T) 7
3 Cutting Torch 5
4 Oven 300C 6
5 Max Puller 8 Ton 2
6 V- Lever 3 Ton 4
7 Hydraulic Jack 35 T 2
8 Drilling Machine Dongcheng 1
9 Angle Grinder(7") Dongcheng 5
10 Angle Grinder(5") Dongcheng 4
11 Angle Grinder(4") Dongcheng 3
12 Angle Grinder(4") Hitachi 3
13 Industrial Fan Gemtek 1
14 Abrasive Cutting Machine Star 1
15 Hydraulic Pump 1
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report September2018
TAC Hydro Engineers Pvt. Ltd. g
3.2.3 Transmission Line Works
186 numbers of poles has been erected till date.
3.2.4 Electro Mechanical Works
I. Shifting of equipment and material has been carried out to power house
II. Installation of board of control panel has been carried out at control room.
QUALITY CONTROL
➢ NDT test has been carried out at all joint of penstock pipes.
➢ Compressive strength test of concrete cubes has been carried out on regular basis.
4 CLAIMS/VARIATIONS, ACCIDENTS AND DAMAGES
➢ No claim has been made in this month.
5 AREAS OF CONCERN AND CORRECTIVE ACTIONS
• H.M work progress was lagging behind this month. Hence, number of manpower has been
increases to catch up with the work schedule.
• Use of safety accessories has been made compulsory while working as accident is likely to
happen in rainy season
Consulting Services and Annex-A Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. a
LIST OF PERSONNEL
EMPLOYER: Manakamana Engineering Hydropower Pvt. Ltd.
Name of Project staff deputed in the Project
S.N Name Designation
Staffs deputed at site / Frequent site visit
1 Tek Prasad Chaulagain Managing Director
2 Tilak Aral PRO / Management Officer
Staffs deputed at KTM office
1 Sushma Chaulagain Accountant
CONSULTANT: TAC Hydro Engineers Pvt. Ltd.
Name of staffs involved in Ghatte Khola SHP
S.N Name Designation Remarks
1 Prahlad Chaudhary Technical Coordinator Frequent visit to site
2 Dipesh Thapa Project Manager Frequent visit to site
3 Balkrishna Pangeni Resident Engineer Site Stationed
4 Milan Adhikari Mechanical Engineer Frequent visit to site
5 Bibek Pandey Civil Engineer Frequent visit to site
6 Uspal Ghimire Civil Engineer Site Stationed
7 Navaraj Gaire Mechanical Engineer Site Stationed
8 Bishnu Shiwakoti Geologist Frequent visit to site
9 Ghanshyam Rana Sub-Engineer Site Stationed
10 Chandra Thapa Sub-Engineer / Surveyor Site Stationed
11 Rohit Gurung Sub Engineer Site Stationed
CONTRACTOR: Sakurapower/Biruwa/Divyajyoti J.V.
Name of staffs involved in Ghatte Khola SHP
S.N Name
1 Dipendra Poudel Site In-charge
2 Manish Kandel Assistant Site In-charge
3 Ghanshyam Basnet Civil Engineer
4 Gopal Gurung Technician
5 Operator/Driver/Helper 1/1/1 Nos.
Consulting Services and Annex-A Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. b
CONTRACTOR: North Hydro & Engineering Pvt. Ltd
Human Resources
S.N. Designation No
1 Project Manager 1
2 Project Engineer 1
3 Supervisor 1
4 Floor Supervisor 2
5 Fitter 5
6 Welder 4
7 Grinder Man 2
8 Helper 10
Total 26
Consulting Services and Annex B Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. c
PROGRESS SHEET NO. 1
Components Sub-Components Excavation
Foundation
Preparation
Bar Bending / Form
Work / Concreating
Stone Masonry /
Protection work
Filling /
Finishing Work
Sub-
Components
Progress
Progress
Till Last
Month
Progress
Till This
Month
A1. To Headworks 100% 100% 100%
A2. To Power House 100% 100% 100%
B1. Weir 100% 100% 100% 100% 95% 98.50%
B2. Undersluice and Intake 100% 100% 95% 97.50%
B4. Approach Canal 100% 100% 100% 100% 100.00%
B5. Settling Basin 80% 70% 50% 52.50%
B6. Filling Work 0% 0.00%
C1. Track and/or Trench 73% 70% 12% 56.89%
C2. Anchor Block 83% 73% 50% 57.50%
C3. Saddle Support 90% 90% 90% 90% 90.00%
C3. Saddle Pad 60% 60% 60% 60.00%
D. Surge Tank D1. Surge Tank 5% 0% 0% 0% 1.00% 0.00% 0.03%
E1. Track and/or Trench 80% 0% 0% 40.00%
E2. Anchor Block 73% 73% 36% 52.73%
E3. Saddle Support 90% 90% 80% 70% 75.50%
F1. Power House 100% 100% 96% 100% 60% 96.60%
F2. Tailrace 100% 75% 58% 50% 75.46%
70.10%
2.21%
F. Power House 21.56% 21.73%
Overall Civil Progress
This Months Progress
C. Headrace Alignment 19.01% 19.18%
E. Penstock Alignment 8.99% 10.33%
Civil Construction Work ProgressSep-18
A. Access Road 2.00% 2.00%
B. Headworks 16.32% 16.83%
Consulting Services and Annex B Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. d
PROGRESS SHEET NO. 2
Sep-18
Frame LeafHoisting
System
A1. Intake Orifice Stoplogs 100% 100% 100% 0% 85%
A2. Undersluice Stoplogs 90% 80% 30% 0% 65%
A3. Undersluice Gate 100% 50% 25% 0% 59%
A4. Intake Gate 95% 95% 0% 0% 67%
A5.Settling Basin Inlet Gate 100% 50% 0% 0% 55%
A6.Settling Basin Outlet Gate 75% 10% 0% 0% 33%
A7.Sand Flushing Gate 75% 30% 0% 0% 39%
A8.Coarse Trashrack 100% 40%
A9.Fine Trash Rack 100% 40%
A10.Bell Mouth 100% 40%
B1.Headrace Pipe 100% 78%
B2. Bends 69% 60%
B3. Saddle Plate 90% 84%
B4.Expansion Joints 5% 2%
B5.Manholes 5% 2%
B6.Crossing Bridge 5% 2%
C. Surge Tank C1.Surge Tank 0% 0% 0% 0%
D1.Penstock Pipe 100% 51%
D2. Bifurcation 100% 88%
D3.Branch Pipe ,Reducer &
Short piece pipe 100% 100%
D4.Bends 81% 72%
D5.Saddle Plate 70% 67%
D6.Expansion Joints 5% 2%
D7.Manholes 5% 2%
54.73%
2.49%
0%
Overall HM Progress
Progress This Month
0%
D. Penstock Alignment
19%
56% 58%
80%
100%
67%
65%
0%
B. Headrace Alignment
63%
60% 62%
54%
80%
0%
0%
0%
A. Headworks 47% 50%
0%
0%
0%
HM Work Progress
Components Sub-ComponentsFabrication,
Inspection
and
Delivery
Erection and Inspection Sub
Component
Progress
Progress Till
last Month
Progress Till This
Month
Consulting Services and Annex B Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. e
PROGRESS SHEET NO. 3
Transmission Line Works:
186 poles has been erected till date.
PROGRESS SHEET NO. 4
Electro Mechanical Works:
60% of the total electro-mechanical work has been completed
Consulting Services and Annex C Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. a
DEVIATIONS IN TIME SCHEDULE
Schedule for October 2018 of H.M
Headrace Alignment Date of
S.N
. Activities Start
Complete
/Handove
r
Durations
(Days) Remarks
1 AB#10-11 10/10/201
8
2 AB#22 8/9/018 13/10/201
8 6
3
Bridge Installation along with
AB#15 17/09/218
16/10/201
8 30
4 AB#6-7 17/09/218 1/10/2018 18
5 AB#18-19,19 26/10/201
8
Penstock Alignment Date of
S.N
. Activities Start
Complete/
Handover
Durations
(Days) Remarks
1 AB#9-7 1/10/2018
2 AB#9-10 Saddle Plate installation 17/09/018 20/10/2018 4
3 AB#9-10 Pipe Erection 26/10/018 15/10/2018 20
4 AB#10-11 Pipe Erection 15/10/2018
5 AB#12-13 Saddle Plate installation 21/10/2018
6 AB#13-11 Pipe Installation 16/10/2018
7 AB#16-18 Pipe Installation 11/9/2018 22/10/2018 12
8 Y Test 1/10/2018
Schedule for October 2018 of Civil
S.No. Activities Date
Days Remarks Start Finish
A: HEADWORKS
1 Headpond area up to bottom of
desander outlet gate 9-oct 15 oct
2 Bellmouth base and other 10/22/2018 11/11/2018
B: HEADRACE
Consulting Services and Annex C Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. b
1 AB 8 10/17/2018 21-Oct
2 AB 10 15
3 AB16 20
4 AB 15 20
5 AB 19 12
6 AB21 10/26/2018 6-Oct
7 AB 22 6-Oct 16-Oct
8 Surge tank excavation 10/17/2018 -
C: Penstock
1 AB 8 concreting 15
2 AB 9 concreting 20
3 AB 17 concreting 10/10/2018 - 12
4 Saddle works in PAB 9-PAB10 10/17/2018
5 Saddle cap in PAB 9-10 12
5 AB 10 concreting 16
D: POWER HOUSE
1 control room base - 10/10/2018
2 Control room up to truss level for em 10/10/2018
Consulting Services and Annex D Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. c
PHOTOGRAPHS
PCC at settling basin panel 4
Power Generator Installation
Consulting Services and Annex D Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. d
Pipe installation in between AB 15-16 of penstock
Concreting at heapond area
Consulting Services and Annex D Construction Supervision of Ghatte Khola SHP Progress Report September 2018
TAC Hydro Engineers Pvt. Ltd. e
Pipe installation at AB 14 -15 during night
PCC and Stone masonry work at control room