monthly progress report january 2013
DESCRIPTION
ReportTRANSCRIPT
National Cyclone Risk Mitigation Project(NCRMP)
Revenue (DM) DepartmentGovernment of Andhra Pradesh
THIRD PARTY QUALITY AUDIT (TPQA)
in JointVenture with
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
INDEX
1.0 Project Background 2
2.0 Third Party Quality Audit Consultant 3
3.0 Major Activities and Review Meetings of the Month 3
4.0 Status of TPQA Visits 4
5.0 Progress of NCRMP works 5
TPQA Status Report for NCRMP Works and NCRs Pending up to end ofJanuary-2013 6
6.0 District wise status of tests conducted by TPQA 28
7.0 Details of QC Audit Reports Submitted during this Month 29
8.0Statement Showing the Inspections and Site Visits of Districts during the Month
of January-2013 32
Photographs of Site Visits during the Month of January-2013 45
Page 1 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.0 Project BackgroundAndhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state,
the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-
December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic
events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years
ranging from 1892 to 1989, there were as many as 67 cyclones within the State.
It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster
due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based
on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the
existing facilities available in the project area in Andhra Pradesh.
The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development
Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the
proceeds to payments for goods, works, related services and consulting services under this Project.
National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), Andhra Pradesh, headquartered at
Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality
Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,
Guntur, Prakasam and Nellore. The project “Construction of Multipurpose Cyclone Shelters, Roads to Cyclone
Shelters, and Roads to habitations and Roads & Bridges under NCRMP” is funded by International Development
Association and received through Government of India. This consultancy is envisaged to audit the quality of works being
implemented by various line departments working under PIU. The number of works under progress / for which
agreements are concluded in each district is shown in the table below.
District
No. of works(Under Concluded Agreements) No. of works under Progress No. ofworks
notstartedRHB RCS MPCS Bridges Roads
(R&B) Total RHB RCS MPCS Bridges Roads(R&B)
Srikakulam 6 8 2 4 1 21 6 8 2 4 1 0
Vizianagaram - - - 2 1 3 - - - 2 1 0
Visakhapatnam 8 6 7 - - 21 8 6 7 - - 0
East Godavari 2 8 3 - - 13 2 7 3 - - 1
West Godavari 10 - - - - 10 10 - - - - 0
Krishna 5 3 - - - 8 5 3 - - - 0
Guntur 3 12 - 2 - 17 3 12 - 2 - 0
Prakasham 14 7 2 1 - 24 14 7 2 1 - 0
Nellore 17 9 - - - 26 17 9 - - 0
Page 2 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2.0 Third Party Quality Audit Consultant.
To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to
Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for
Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV
with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st May’2011, the Contract for Consultancy Service was signed
between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and
the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.
3.0 Major Activities and Review Meetings of the Month
S.No. Place Date Activity
1 Hyderabad 07.01.2013 Attended Review meeting of TPQA at H Block in APSecretariat with Commissioner and PD
2 Hyderabad 08.01.2013 Attended Review meeting of EPTRI at H Block in APSecretariat with Commissioner and PD
3 Hyderabad 31.01.2013 Attended Review meeting at H Block in AP Secretariat withCommissioner and PD
Page 3 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4.0 Status of TPQA Visits:
The following table shows the details of TPQA visits to sites in respective districts.
DistrictTotal Number of Visits
Up to Dec.2012 In Jan.2013 Up toJanuary.2013
Srikakulam 452 31 483
Vizianagaram 72 1 73
Vishakhapatnam 361 53 414
East Godavari 612 16 628
West Godavari 436 26 462
Krishna 299 5 304
Guntur 373 19 392
Prakasam 407 31 438
Nellore 323 18 341
No. of Visits by TPQA
Page 4 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5.0 Progress of NCRMP works:
The district wise progress of works is shown below. The works in the West Godavari are not started and the works inKrishna District has just started. At many places the first milestone is completed but works are not started. The linedepartments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per theagreement conditions should be imposed.
Third Party Quality Audit by Egis – India consulting services
Summary of Activities
S.No. District
Agreements for PackagesCommunicated Status of works
PR R&B Progress Not Started
1 Srikakulam 6 5 21 0
2 Vizianagaram - 3 3 0
3 Visakhapatnam 13 0 21 0
4 East Godavari 7 0 12 1
5 West Godavari 3 0 10 0
6 Krishna 4 0 8 0
7 Guntur 6 2 17 0
8 Prakasham 12 1 24 0
9 Nellore 16 0 26 0
Total 67 11 142 1
Total Packages for which Agreements are received 79
Total Number of works in the above packages 143
Page 5 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF JANUARY 2013
S.No. District
Packages /Works
entrustedStatus of Works No. of
Visitsof
TPQA
TotalNo. of
QCtestsdone
NCRs AuditReportsIssued
Environmental& SocialReportsIssuedPR R&B Started Not
Started Issued closed Pending
1 Srikakulam 16 5 21 0 452 1475 54 54 0 78 57
2 Vizianagaram - 3 3 0 72 461 3 3 0 11 9
3 Visakhapatnam 21 - 21 0 361 2237 25 25 0 73 41
4 East Godavari 13 - 12 1 612 1128 28 28 0 58 31
5 West Godavari 10 - 10 0 436 349 20 20 0 62 37
6 Krishna 8 - 8 0 299 85 3 3 0 43 21
7 Guntur 15 2 17 0 373 606 14 14 0 61 32
8 Prakasam 23 1 24 0 407 1905 36 36 0 118 50
9 Nellore 26 - 26 0 323 1174 32 32 0 109 48
Total 132 11 142 1 3335 9420 215 215 0 613 326
Page 6 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SRIKAKULAM DISTRICT UP TO 31.01.2013
Category
Packages allottedunder Phase - 1
Names of works undereach package
AgreementNo. / Date
Milestone Completion DatesProgress
w.r.t.milestone up
to31.01.2013
RemarksFirst Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
Road from DPN R&B road toUddandapalem
/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete
Entire work completed
Road from K. UmiladaJunction to Koduru (Link
Road)
/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete
Entire work completed
Road from Borubhadra,Malagam to Kollipadu via
Seepuram, Gantapeta
/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete
Entire work completed
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006
Road from R&B roadMobagam to
Duubakavanipeta viaGajapathinagaram
/2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12
First Milestonei.e Earthwork& Cd works
&GSB
300 mts CC roadcompleted, GSB
laying is inprogress, roadformation width
vary from6.00mts to7.50mts
Road from Talasamudram toDola Regulator
/2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12
First Milestonei.e Earthwork& Cd works &
GSB
completed
NCRMP/B-W/AP/RHB/PRED/01/Polaki/005
Road from R&B roadEdulavalasa - Killam to
Jonnam via Talasamudram
/2011-12, Dt.30.04.2011 31.07.11 31.10.11 31.01.12
First Milestonei.e Earthwork& Cd works
&GSB
BT layercompleted fromKm 5/670 to Km7/270, and WBM
Gr- III metal
Page 7 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
collection is inprogress from
Km 5/000 to Km5/670
Bridges
NCRMP/B-W/AP/Br/R&B/01/Patnavanipeta/001
Construction of bridge at Km11/6-8 of NH-5 toPatnavanipeta ConnectingSundarapalem
46/2011, Dt.17.12.2010 17.08.11 17.01.12 17.06.12 Completion of
entire work
Slab A2-piercompleted andSlab A1-pier sisin progress,Approach roade/w, GSB,WMM, SDBCcompleted. CD,R/W workscompleted.
NCRMP/B-W/AP/Br/R&B/01/Surampeta/003
Construction of Minor Bridgeat Km 12/2-4 of NH-5 to
Surampeta Road via Naruva,mentada
45/2010-2011,Dt17.12.2010 17.05.11 17.10.11 17.03.12 Completion of
entire work Completed.
NCRMP/B-W/AP/Br/R&B/01/Bendigedda/004
Construction of High levelbridge across Bendigedda atKM 4/10 of Pundi-Parlakimidiroad in Srikakulam Dt, A.P.
1/2010,Dt.11.11.2010 11.08.11 11.01.12 11.06.12 Completion of
entire work Completed.
RoadsNCRMP/B-W/AP/RD/R&B/01/Nowpada/006)
Improvesments Naupada-Venkatapuram road from0/0to15/0km
43/2010-11,17.12.2010
17.05.11 17.10.11 17.03.12 Completion ofentire work work completed
RCSNCRMP/B-W/AP/RCS/PRED/01/V.KOTTURU/002
Road from NP road toURKpuram
G.o rt No 451dt 06.04.2010 29.01.12 29.05.12 29.09.12 WBM GR-II
&III complete work completed
Road from Deppuru,Bahadapalli road to onkuluru& to cyclone shelter
G.o rt No 451dt 06.04.2011 29.01.12 29.05.12 29.09.12 WBM GR-II
&III complete work completed
Road from R&B road toDevunthalada
G.o rt No 451dt 06.04.2012 29.01.12 29.05.12 29.09.12 WBM GR-II
&III complete work completed
Page 8 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from pollada toKomarthalada & to cycloneshelter
G.o rt No 451dt 06.04.2013 29.01.12 29.05.12 29.09.12 WBM GR-II
&III complete work completed
NCRMP/B-W/AP/RCS/PRED/01/ETCHERLA/005
Road from Koyyam R&BRoad to Moosavanipeta
G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of
entire work work completed
Road from Mentada toDovupeta
G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of
entire work work completed
Road from Kotcherela road toKollibhemavaram & cycloneshelter
G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of
entire work work completed
Road from Kotcherla road toPathasundarapalem
G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of
entire work work completed
MPCSNCRMP/B_W/AP/MPCS/PRED/01/Santhabommalli/005
Construction of Cycloneshelter at Kollipadu
G.o rt No 451dt 06.04.2010 07.03.12 07.08.12 07.01.13
Completion ofstilt floor &first floor
Silt floor levelslab completed.
Construction of CycloneShelter at Runku
G.o rt No 451dt 06.04.2010 07.03.12 07.08.12 07.01.13
Completion ofstilt floor &first floor
Upto plinthbeam
completed, andcolumns above
plinth beam is inprogress
Page 9 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN VIZIANAGARAM DISTRICT UP TO 31.01.2013
Category
Packagesallotted under
Phase - 1
Names of works under eachpackage
AgreementNo./ Date
Milestone Completion Dates Progress w.r.t.milestone upto 31.01.2013
RemarksFirst Second Third
Bridges
NCRMP/B-W/ AP/Br/ R&B/
02/Puligadda/ 007
Construction of Minor Bridge atKm. 7/2 near Puligedda of
Konada – Ramatheertham R&BRoad to Konathalapalem via
Yerukonda, Pasupam,Kollayavalsa (Z.P. Road)
31/2010-2011Dt.
01.12.201030.06.11 31.01.12 31.05.12 100% of work
completed
As against of100 % in the 3rd
Milestone
NCRMP/B-W/ AP/Br/ R&B/ 02/
Chakaligadda /008
Construction of Minor Bridge atKm 15/2 near Chakaligadda ofKonada Ramatheertham R&Broad to Konathalapalem (via)
Yerukonda, Pasupam,Kollayavalsa (ZP Road)
34/2010-2011Dt.
08.12.201007.07.11 07.02.12 07.06.12 90% of work
completed
Minor deviationapproval is
awaited. It takes15 days time tocomplete thework afterdeviationapproval
RoadNCRMP/B-
W/AP/RD/R&B/ 02/Konada/009
Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)
Pasupam, Yerukonda,Kollayavalsa from Km 12/0 to16/5 (Km 0/0 to 4/0 i.e. up to
NH-5 crossing)
33/2010-2011Dt.
08.12.201007.06.11 07.12.11 07.03.12 100% of work
completed -
Page 10 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT UP TO 31.01.2013
Category
Packagesallotted under
Phase - 1
Names of worksunder each package
AgreementNo. / Date
Milestone Completion Dates Progress w.r.t.milestone up to
31.01.2013Remarks
First Second Third
MPCS
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopet
a/003
Construction of cycloneshelter at
Gajapathinagaram
/2011-12, Dt.03.10.2011 05.06.12 05.10.12 05.02.13
Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOAT submittedon 24.08.12
likely to becompleted
beforeMarch.2013
Construction of cycloneshelter at Ratnayampeta
/2011-12, Dt.03.10.2011 02.02.12 02.06.12 02.10.12
All Slabs are completed.Inside and outside wallplastering work completed.White cement applications,wood joinery and Electricalworks are to be progress.
likely to becompleted
before15.02.2013
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/00
2
Construction of cycloneshelter at Patimeeda
/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13
Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOATsubmitted on 24.08.12
likely to becompleted
beforeMarch.2013
Construction of cycloneshelter at Mullaparra
/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13
Stilt Slab & stilt floor, Firstfloor and head room slabsare completed. Ceilingplastering work and firstfloor brick work are inprogress.
likely to becompleted
beforeMarch.2013
Page 11 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Construction of cycloneshelter at Bangarampeta
/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13
Stilt floor, First floor,second floor, Head roomslabs are completed. Istfloor and second floor brickmasonry work is inprogress.
likely to becompleted
beforeMarch.2013
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of cycloneshelter at
Venkayyapalem
/2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12
Plinth beam completed andfilling under floor is inprogress. EOAT proposalssubmitted on 29.06.12.
likely to becompleted
beforeJune.2013
NCRMP/B-W/AP/MPCS/PRED/03/Parawada/00
1
Construction of cycloneshelter at
Thikkavanipalem
/2011-12, Dt.07.10.2011 06.01.12 06.04.12 06.07.12 Work not started due to
site problemProgress is
Slow
RCS
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/
001
Road from NH-5 toRamarayadupalem
/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 Road Furniture & B.T is
completed. completed
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Road from R & B road toRajakoduru
/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD works are completed &
B.T work is Completed completed
Road from R & B road toKattubolu to Marripalem
/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD works are completed &
B.T work is Completed completed
Road from R & B road toKrishnampalem
/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD Work is completed &
B.T work is completed completed
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R&B road toPedatheernala toChinatheernala
/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 B.T & C.C road works are
Completed. completed
Page 12 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from UpmakaRajayyapeta R&B road
to Janakayyapeta
/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 CD works are Completed &
B.T work is completed completed
RHB
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001
Road from Vempudi toPatimeeda
/2010-11, Dt.11.01.2011 10.05.11 10.09.11 10.01.12 Work is completed -
Road from R&B road toMullaparra up to Beach
end
/2010-11, Dt.27.01.2011 26.04.11 26.07.11 26.10.11 Work is completed -
NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/
003
Road from R&B B.PKallalu to
Matchvanipalem
/2010-11, Dt.10.03.2011 09.06.11 09.09.11 09.12.11 Work is completed -
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R & B road toPothurajanapalem
/2010-11, Dt.28.03.2011 27.06.11 27.09.11 27.12.11 Work is completed -
Road from R & B road toJalaripeta
/2010-11, Dt.28.03.2011 27.06.11 27.09.11 27.12.11 Work is completed -
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006
Road from R & B road toVenkayyapalem
/2010-11, Dt.11.01.2011 10.04.11 10.07.11 10.10.11 Work is completed -
NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/
007
Road from R&B road toAva- Somavaram
/2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -
Road from R&B Road toAvarajam
/2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -
Page 13 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT UP TO 31.01.2013.
Category
Packages allottedunder Phase - 1
Names of worksunder each package
AgreementNo. / Date
Milestone Completion DatesProgress
w.r.t.milestone upto 31.01.2013
Remarks
First Second Third
RCS
NCRMP/B-W/RCS/PRED/04/Karapa/001
Approach Road tocyclone Shelter atAdivipudi
32/2011-12Dt:20.05.2011 30-11-2011 31-10-2011 31-01-2012 100% Completed.
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto P.Chodipallipeta CS
73/2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 100% Completed.
NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto K.Chodipallipeta CS
73/2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 100% Completed
NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Hukumpeta CS
73/2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 100% Completed
NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003
Road from R&B Roadto ChinaraghavulapetaCyclone Shelter
74/2011-12Dt: 23.09.2011
3 months22.11.2011
3 months22.06.2011 ----------- 100% Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Gaddipeta CS
73 /2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 100% Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Danavaipeta CS
73 /2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 100% Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto G.Musalayyapeta CS
73/2011-12Dt:07.09.2011
3 months06.12.2011
3 months06.03.2012
3 months06.06.2012 Nil Not yet
Started
RHB NCRMP/B-W/AP/RHB/PRED/04/Karapa/001
Road from Gurjanapallito Bandulavaripalem
24/2011-12Dt:27.04.2011 30-09-2011 31-10-2011 31-01-2012 100% Completed
Page 14 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/0
03
Road from PR roads toDasarivanipeta and toCyclone Shelter
18/2011-12Dt:27.04.2011 30-11-2011 30-11-2011 20-01-2012 100% Completed.
MPCS
NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction ofCyclone Shelter atPedaraghavulapeta ofUppalaguptam MandalE.G.Dt.
78/2011-12Dt:17.10.2011
3 months16.01.2012
3 months16.04.2012
3 months16.07.2012 45%
Likely to becompleted byJune 2013
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction ofCyclone Shelter atLakshmanudipeta inThondangi
77/2011-12Dt:07.09.2011
4 months16.02.2012
4 months16.06.2012
4 months16.10.2012 80%
Likely to becompleted byMarch 2013
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction ofCyclone Shelter atAvulamanda
77/2011-12Dt:07.09.2011
4 months16.02.2012
4 months16.06.2012
4 months16.10.2012 80%
Likely to becompleted byMarch 2013
Page 15 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN WEST GODAVARI DISTRICT UP TO 31.01.2013
Category
Packagesallotted under
Phase – 1
Names of works under eachpackage
Agreement No. /Date
Milestone Completion Dates Progressw.r.t.
milestoneup to
31.01.13
RemarksFirst Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001
Road from NH 214 A at Ranga Statuecenter to Harijanawada of Kalipatnam
(E) (Mogalthuru Mandal
16 /2011-12Dt.27.04.2011
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012
100% Completed
R&B road at Panchayat Office toPulaparthivarithota via Badava(Mogalthuru Mandal W.G.Dist.)
100% Completed
Mogalthuru Vempa R&B Road atUchintha Kalava Bridge to Gogulamma
Harijanapeta (Mogalthuru Mandal)100% Completed
From Narsapur Mogalthuru R&B road toDayadaldaspeta via Venkateshwara
Swamy temple (Mogalthuru Mandal )100% Completed
Road from NH 214 A road toHarijanapeta of Kothota
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012100% Completed
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002
R&B road to Indira Nagar (via)Pochamma temple (Narsapur Mandal) 21 /2011-
12Dt.09.05.2011
09/05/2011to
04/09/2011
05/09/2011to
06/01/2012
07/01/2011to
08/5/2012
100% Completed
Road from R&B road to Pedalanka(Narsapur Mandal W.G.Dist.) 100% Completed
Road from LB Cheria CC road toChillapalem of LB Cheria. 100% Completed
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road toSatyanarayanapuram (Kalla Mandal) 25 /2011-
12Dt.26.05.2011
26/5/2011To
20/8/2011
20/8/2011to
21/11/2011
22/11/2011To
23/2/2012
100% Completed
From A-U R&B Road to Mekaladibba(Kalla Mandal W.G.Dist.) 100% Completed
Page 16 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN KRISHNA DISTRICT UP TO 31.01.2013
Category
Packages allotted underPhase - 1
Names of works undereach package
AgreementNo. / Date
Milestone Completion DatesRemarks
First Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001
Road connecting R&B roadthrough Gantlammapalem
8/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from R & B Road to B.VThota
7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed
Road from Potalapalem Z.Proad to Chikativanipalem
7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Intheru R&B Roadto Rangaraopet
9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed
Road from R&B road toCyclone Shelter at Chandala
9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed
RCS NCRMP/B-W /AP/RCS/PRED/06/Machilipatnam/001
Road from BhogireddypalliR&B Road to Ramakhandam
32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012 Completed
Road from R&B RoadChinnapuram to Gundupalem
32/2011-12/27.04.2011 01.12.2011 01.03.2012 01.06.2012 Completed
Road from Potlapalem Z.P roadto Pothepalli.
32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012 Completed
Page 17 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN GUNTUR DISTRICT UP TO 31.01.2013
Category
Packages allottedunder Phase - 1
Names of works undereach package
Agreement No./Date
Milestone completion dates Progressw.r.t.
milestoneup to
31.01.2013
RemarksFirst Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/
07/KARLAPALEM/001
R/f Ganapavaram R&BRoad to Kesavapuri ST colony
7/2011-2012
27.04.2011
26.7.2011 26.10.2011 26.01.2012 -Completed
NCRMP/B-W/AP/PRED/07/Nagaram/002
R/f R&B Road to MohammadAlipalem
8/2011-2012
27.04.2011
26.8.2011 26.12.2011 26.4.2012 -Completed
R/f R&B Road toKaturivaripalem.
-Completed
Bridges
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of High-levelBridge @Km5/2 of Bapatla-Suryalanka Road across peralidrain in Guntur Dt.
79/2010-2011
1.12.2010
31.5.2011 30.11.2011 31.5.2012
- Completed
NCRMP/B-W/AP/Br/R&B/07/Bapatla/011
Reconstruction of High-levelBridge @Km2/4 of Bapatla-Pandurangapuram Road acrossperali drain in Guntur Dt.
78/2010-2011
1.12.2010
31.5.2011 30.11.2011 31.5.2012
90%
Likely to becompleted
beforeMarch 2013
RCS
NCRMP/B-W/AP/RCS/PRED/ 07/PV
Palem/001
Road from R&B road toMandevaripalem
2011-20121.11.2011
31.01.2012 30.04.2012 31.07.2012- Completed.
Road from R&B Road Alluru toYadavapalem
31.01.2012 30.04.2012 31.07.2012
45%
Likely to becompletedbefore Feb
2013
NCRMP/B-W/AP/RCS/PRED/
07/Karlapalem/002
Road from Ganapavaram R&BRoad to Pedamarpuvaripalem
2011-20121.11.2011
29.02.2012 30.06.2012 31.10.2012
20%
Likely to becompletedbefore Feb
2013
Page 18 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B Road toChinapuluguvaripalem
29.02.2012 30.06.2012 31.10.2012
25%
Likely to becompletedbefore Feb
2013From R&B road toYaramvaripalem
29.02.2012 30.06.2012 31.10.2012- Completed.
Road from R&B Road toPedagollapalem CycloneShelter
29.02.2012 30.06.2012 31.10.2012- Completed.
Pedagollapalem P.R road toBonthagoralapalem
29.02.2012 30.06.2012 31.10.2012-
Shouldersare in
progress.
NCRMP/B-W/AP/RCS/PRED/
07/Nizampatnam/003
Road from R&B Road toGurunadhanagar
2011-201217.10.2011
16.01.2012 16.04.2012 16.07.2012- Completed.
Road from R & B Road toAdavala H/O Bavaji palem
16.01.2012 16.04.2012 16.07.2012- Completed.
Road from R & B Road toAtlavaripalem
16.01.2012 16.04.2012 16.07.2012- Completed.
NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004
Road from R & B Road toHanumathanagar
2011-201227.10.2011
26.01.2012 26.04.2012 26.07.2012- Completed.
Road from R & B Road toAdarsh nagar
26.01.2012 26.04.2012 26.07.2012- Completed.
Page 19 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN PRAKASAM DISTRICT UP TO 31.01.2013
Category
Packages allottedunder Phase - 1
Names of worksunder eachpackage
Agreement No. /Date
Milestone completion dates Progress of workfor the month –January 2013
RemarksFirst Second Third
BRIDGES
NCRMP/B-W/AP/Br/R&B/08/ Kanaparthy/012
Construction of Highlevel Bridge at Km16/10 ofNaguluppapadu –Kanaparthy road
76/2010-11Dated1/12/2010
5/31/2011Completionup to silllevel
12/31/2011Completionup to belowdeck slab
5/31/2012Completionof entireworkincludingapproaches
Bridge work iscompleted. completed
RHB
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from Pakala ZPRoad toAulavaripalemCyclone shelter
Dated25.04.2011
8/24/2011Earth work,CD work,
GSB
12/24/2011WBM,
Grade II &III
4/24/2012BT,
Shoulders& road
furniture
CC Road & Shoulderswork is Completed. completed
Road from R&B Roadto Somarajupalli
Dated25.04.2011
BT, CC road & culvertsare completed fromKM 0/0 to 2/146.
completed
Road from R&B roadto Narravaripalem
Dated25.04.2011
BT, & culverts areCompleted from KM0/0 to 0/900. work iscompleted
completed
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from NH5 toMulaguntapadu
dated10/02/2011 6/9/2011
Earth work,CD work,
GSB
10/9/2011WBM,
Grade II &III
2/9/2012BT,
Shoulders& road
furniture
WBM-Grade-III LayerCompleted. OGPC +Seal Coat To be takenup
work is notgoing on
Road from R&B roadto Chalivendradibba
dated -10/02/2011
WBM-Grade-III LayerCompleted. OGPC +Seal Coat To be takenup
work is notgoing on
Page 20 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from PakalaR&B road toMosanaladinne
dated10/02/2011
6/9/2011Earth work,CD work,
GSB
10/9/2011WBM,
Grade II &III
2/9/2012BT,
Shoulders& road
furniture
WBM-Grade-IIImaterial laying work isin progress
98%
Road from R&B roadto BinginapalliHarijanawada CycloneShelter
dated10/02/2011
CC road work iscompleted from KM0/0 to KM 0/220.Shoulders work is tobe taken up.
98%
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Road from R&B RoadAllur to M T Rajucolony
Dated27/04/2011
8/26/2011Earth work,CD work,GSB
12/26/2011WBM,Grade II &III
4/26/2012BT,Shoulders& roadfurniture
BT, CC road, shoulders& culverts arecompleted from km0/0 to km 3/8.work iscompleted
completed
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Road from KEM R&BRoad toSankuvarigunta
Dated27/04/2011
9/26/2011Earth work,CD work,
GSB
2/26/2012WBM,
Grade II &III
7/26/2012BT,
Shoulders& road
furniture
BT completed.CD workcompleted.CC roadwork completed fromkm 0/0 to km 1/430and CC dip work iscompleted
completed
Road from KEM R & BRoad toPullareddypalem
Dated27/04/2011
BT completed.CD workcompleted.CC roadand shoulders workcompleted from km0/0 to km 3/900.
completed
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07
Road from MC Roadto SubbarayuduSatram
dated27/04/2011
8/26/2011Earth work,CD work,GSB
12/26/2011WBM,Grade II &III
4/26/2012BT,Shoulders& roadfurniture
BT completed.CD workcompleted andshoulders workcompleted from km0/0 to km 3/4. work iscompleted
completed
Page 21 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08
Road from R&B roadTettu toRamayapatnam
dated27/04/2011
8/26/2011Earth work,CD work,GSB
12/26/2011WBM,Grade II &III
4/26/2012BT,Shoulders& roadfurniture
BT completed.CD workcompleted.CC roadand shoulders workcompleted from km0/0 to km 5/086. workis completed
completed
NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09
Road from R&B roadPellur toVasepallipadu
dated16/03/2011
7/15/2011Earth work,CD work,GSB
11/15/2011WBM,Grade II &III
3/15/2012BT,Shoulders& roadfurniture
BT completed. CDwork completed.CCroad and shoulderswork completed fromkm 0/0 to km 4/5.work is completed
completed
NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10
Road from R&B roadto Kesupalem
dated19/04/2011
7/18/2011Earth work,CD work,GSB
10/18/2011WBM,Grade II &II
1/18/2012BT,Shoulders& roadfurniture
BT completed. CDwork completed.CCroad and shoulderswork completed fromkm 0/0 to km 2/103.work is completed
completed
RCS NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B roadto Vijayanagar colonycyclone shelter
dated30.09.2011
1/29/2012Earth work,GSB
5/29/2012shoulders,Gr-III
9/29/2012BT, CCpavementand roadfurniture
cc road completed, BTroad completed&shoulders completed.Road from km 0/0 tokm 0/525. work iscompleted
completed
Road from NH road toChallareddypalem
cc road completed, BTroad completed&shoulders completed.Road from km 0/0 tokm 1/735. work iscompleted
completed
Road from R&B roadto jeevaraksh nagarcolony cyclone shelter
C.C.road andShoulders arecompleted Road fromkm 0/0 to km 0/500.
completed
Page 22 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B roadto Ramnagar colonycyclone shelter
C.C.completed Roadfrom km 0/0 to km0/475.Shoulders to betaken up.
completed
Road from R&B roadto cyclone shelter atMankenavaripalem
CC road completed.Shoulders work is tobe taken up.
completed
NCRMP/B-W/AP/RCS/PRED/08/Chirala/002
Road from R&B Roadto Keerthivaripalemcyclone shelter
dated27.08.2011
C.C road andShoulders arecompleted from km0/0 to km 0/265. workis completed
completed
Road from R&B Roadto Devinuthulacyclone shelter ofChirala Mandal
C.C road andShoulders arecompleted from km0/0 to km 0/800. workis completed
completed
MPCS NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001
Chakicharla cycloneshelter in UlavapaduMandal
24.11.2011All items upto stilt floorslabincludingramp, staircasefoundations, columns,beams, pccflooringetc.,
24.02.2012All items upto secondfloor slabincludingfirst floor,and in 2ndfloorincludingstair case,columnsetc.,
24.05.2012Head room,plastering,flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compoundwall, ccpavement.Earthenmounds(raised
Stilt floor, G.F , &Terrace floor- roof slabcompleted. Brick workcompleted, Plasteringwork completed, Cattleplatform completedrevetment workcompleted, flooringwork is completed,compound wall 120meters lengthcompleted, Electricalwork is completed.work is completed
completed
Page 23 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
portion),waterharvesting,septic tank,slump andsoak pit.etc.,
NCRMP/B-W/APMPCS/PRED/08/NG Padu/003
Kanaparthy cycloneshelter inNaguluppapaduMandal prakasamdistrict
23.11.2011All items upto stilt floorslabincludingramp, staircasefoundations, columns,beams, pccflooringetc.,
23.02.2012All items upto first floorslab andhead roomslb in 2 ndfloorincludingstair case,columnsetc.,
23.05.2012plastering,flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compoundwall, ccpavement.Earthenmounds(raisedportion),waterharvesting,septic tank,slump andsoak pit.etc.,
Internal & ExternalPlastering completed.Flooring WorkCompleted. CompoundWall PaintingCompleted. CC RoadCompleted. Shoulderwork in Completed.Painting work inCompleted. ElectricalFittings in progress.Tiles in bathroomswork in Completed.Water harvest & Soakpit work in completed.
completed
Page 24 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SPSR NELLORE DISTRICT UP TO 31.01.2013
Name of package Name of work date ofagreement mile stone -I mile stone -II mile stone -III
PresentStatues of
workRemarks
RHB
NCRMP/B-W/AP/RHB/PRED/09/
BOGOLO/RHB/001
1. Road from NH5 toSambasiva Puram
1/19/20115Months: Earth
Work, PipeCulverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months: BTand RoadFurniture
OGPC+ SCcompleted
completed
Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem
OGPC+ SCcompleted
completed
NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002
Road from 1/6 ofZuvvaladinne R&B Road to
Tellagunta KM to 2/72007.02.2011
6.5,20113Months: Earth
Work, PipeCulverts, GSB
6.8.2011 6Months: WBMGrII, GrII and
Shoulders
6.11.20119Months: BTand RoadFurniture
OGPC+ SCcompleted
completed
NCRMP/B-W/AP/RHB/PRED/09/
CHITTAMURU/003
Road from R&B Road toMuttambeka Via
Pittuvanipalla 18.01.2011
17.6.20115Months: Earth
Work, PipeCulverts, GSB
17.11.2011 10Months: WBMGrII, GrII and
Shoulders
17.4.2012 15Months: BTand RoadFurniture
OGPC+ SCcompleted
completed
Road from R&B Chittamurto Soma Samudram
OGPC+ SCcompleted
completed
NCRMP/B-W/AP/RHB/PRED/09/RHB/
KAVALI/004
Road from5/8 ofChennayapalem Road to
Gummadi bandla
17.01.2011
16.6.20115Months: Earthwork,CD Works, ccpavement and
GSB
16.11.2011 10Months: WBM
GrII, GrIi I andShoulders
16.4.2012 15Months: BTand RoadFurniture
OGPC+ SCcompleted
completed
Road from pedattapupalemR&B road to
Chennayapalem H.wada
OGPC+ SCcompleted
completed
Road from K.T R&B Road toAlliguntapalem
OGPC+ SCcompleted
completed
NCRMP/B-W/AP/RHB/PRED/09/
VIDAVALURU/005
1)Road from KT R&Broad to Alaganipadu to
Vavilla27.04.2011
26.9.20115Months: Earth
Work, PipeCulverts, GSB
26.2.201210Months: WBMGrII, GrII and
Shoulders
26.7.2012 15Months: BTand RoadFurniture
OGPC+SCcompleted
completed
Road from R&B roadKancharapalem HW to
Alaganipadu.
WBM Gr-II isin progress &
CD Workscompleted.
98%
Page 25 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/PRED/09/
MUTHUKUR/RHB/006
Road from R&B road toPatuvari Kandriga 25.4.11
24.7.20113Months: Earth
Work, PipeCulverts, GSB
24.10.2011 6Months: WBMGrII, GrII, CCPavement and
Shoulders
24.1.2012 9Months: BTand RoadFurniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/RHB/PRED/09/
V.CHALEM/RHB/007
Road from Survepalli-Pudiparthi road to Srikanth
Colony27.04.2011
26.8.20114Months: Earth
Work, PipeCulverts, GSB
26.12.2011 8Months: WBMGrII, GrII and
Shoulders
26.4.2012 12Months: BTand RoadFurniture
OGPC+ SCcompleted completed
providing BT Surface tothe road from R&B road to
Edagali Kandriga
OGPC+ SCcompleted completed
NCRMP/B-W/AP/RHB/PRED/09/Allur
/009
Road from R&B road Alluruto Galidibbalu (via)Chukavani dibba
24.01.2011
23.6.20115Months: Earth
Work, PipeCulverts, GSB
23.11.2011 10Months: WBMGrII, GrII and
Shoulders
23.4.2012 15Months: BTand RoadFurniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur-Salipeta R & B Road via CSPuram and Mandapam Vill. 19.05.2011
18.8.20113Months: Earth
Work, PipeCulverts, GSB
18.11.2011 6Months: WBMGrII,GrII, CC
Pavement andShoulders
18.2.2012 9Months: BTand RoadFurniture
OGPC+ SCcompleted completed
Road from R & B Road C SPuram to Sivaramapuram
OGPC+ SCcompleted completed
RCS
NCRMP/B-W/AP/PRED/09/kota/RCS
/001
Road from R&B road to A.SPURAM
10.05.2011
9.8.20113Months: Earth
Work, PipeCulverts, GSB
9.11.11 6Months: WBMGrII,GrII and
Shoulders
9.2.2012 9Months: BT,CC Pavement
and RoadFurniture
OGPC+ SCcompleted completed
Road from GD Road toVavilla Palem
OGPC+ SCcompleted completed
NCRMP/B-W/AP/PRED/09/
MUTHUKUR/RCS/002
Road from R&B Roadkappaladoruvu to bandla
Palem H.wada21.04.2011
20.7.20113Months: Earth
Work, PipeCulverts, GSB
20.10.2011 6Months: WBMGrII,GrII,CC
Pavement andShoulders
20.1.2012 9Months: BT CCroad and Road
Furniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/PRED/09/Chillakur/
RCS/004
Road from KakuvaripalemR&B road to Vellapalem 23.05.2011
22.8.20113Months: Earth
Work, CDWorks, GSB
22.11.2011 6Months: WBMGrII,GrII and
Shoulders
22.2.2012 9Months: BT,CC Pavement
and RoadFurniture
OGPC+ SCcompleted completed
Page 26 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/09/
T.P.GUDUR/005
Road from7/2 M.C Road toVenkannapalem
Pattuapalem17.05.2011
16.8.20113Months: EarthWork, PipeCulverts, GSB
16.11.2011 6Months: WBMGrII,GrIIShoulders andCC Pavement
16.2.2012 9Months: BT,CC Pavementand RoadFurniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006
Road Connecting R&B Roadthrough Voturu Village in
SPSR Nellore District.21.09.2011
20.1.2012 4Months: Earth
Work, PipeCulverts,
GSB
20.5.2012 4Months: WBM
GrII,GrII ,Shoulders andCC Pavement
20.9.2012 4Months: BT,CC Pavement
and RoadFurniture
GSB. From0.00 to 5.320(Bits), WBMGr-II, Gr-IIIfrom 0.00 to5.320 and
OGPC+SC 0/6to 5/1 is
completed
completed
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007
Road from Kotha satramR&B to Indrsanagar (via)
Thumalapenta palam,Patharavadu palam,
Ramudu palam, Karaduvaripalam & Sreeramapuram
29.08.2011
28.12.20114Months: Earth
Work, PipeCulverts, GSB
28.4.2012 4Months: WBM
GrII,GrII ,Shoulders andCC Pavement
28.8.2012 4Months: BT,CC Pavement
and RoadFurniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/PRED/09/
D.V.SATRAM/RCS/008
Road from R&B road toSullurpeta Mallam to
Berijengalapalli cycloneshelter
09.05.2011
8.8.20113Months: EarthWork, PipeCulverts, GSB
8.11.2011 6Months: WBMGrII, GrIIShoulders andCC Pavement
8.2.2012 9Months: BT,CC Pavementand RoadFurniture
OGPC+ SCcompleted completed
NCRMP/B-W/AP/RCS/PRED/
09/TADA/009
Providing BT road toPedapannamgadu in Tada
Mandal
14.09.2012
14.02.2013(5Months) EarthWork, PipeCulverts, GSB &CC road
13.06.2013 (4Months): WBMGrII, GrIIShoulders
13.09.2013Months) BTand RoadFurniture
GSB work is inprogress 67%
Road from @ 56/8 to C.Kroad to Periyavettu kuppamcyclone shelter
14.02.2013(5Months) EarthWork, PipeCulverts, GSB &CC road
13.06.2013 (4Months): WBMGrII, GrIIShoulders
13.09.2012Months) BTand RoadFurniture
Sub grade is inprogress 9.41%
Page 27 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6.0 District wise status of tests conducted by TPQA:
Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various
stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are
carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of
tests conducted in the field till end of December 2012 are presented.
Summary of QC Tests - Up to 31.01.2013
S.No. District
No. TestsConductedduring the
Month
Total no. of TestsCumulativeTests Done
Total no. of Tests up to31.01.2013
Passed Failed Passed Failed
1 Srikakulam 30 30 0 1505 1499 6
2 Vizianagaram 0 0 0 461 461 0
3 Visakhapatnam 89 89 0 2326 2280 46
4 East Godavari 42 42 0 1170 1170 0
5 West Godavari 0 0 0 349 349 0
6 Krishna 3 3 0 88 88 0
7 Guntur 50 50 0 656 645 11
8 Prakasham 50 50 0 1955 1951 4
9 Nellore 32 32 0 1206 1185 21
Total 296 296 0 9716 9628 88
Page 28 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7.0 Details of Quality Control Audit Reports Submitted During this Month:
Package Number Name of Work District
NCRMP/BW/AP/RHB/PRED/09/vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore
NCRMP/B-W/AP/RCS/PRED/08/VETAPALEM/001
Road from NH to Challareddypalem InPrakasam District Prakasam
NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.
Road from Pedagollapalem PR Road toBonthagorlapalem Prakasam
NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001
Road from R&B Road Alluru to Yadavapalemin Guntur DT. Guntur
NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT Road to Peda Pannam Gadu inTada Mandal of Nellore Dt. Nellore
NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003
Providing Road from R&B B.P Kallalu toMatchvanipalem in Visakhapatnam Dt. Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001
Providing B.T to the Road from NH-5 toRamaraidupalem in Visakhapatnam Dt. Visakhapatnam
Page 29 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/BW/AP/RHB/PRED/09/vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of cyclone shelter at Kollipadu inSanthabommali Mandal in Srikakulam Dt. Srikakulam
Final QCR’s submitted in this month
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Interu ZP road to Rangaraopeta inKrishna Dt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Bhogireddypalli R&B road toRamakhandam in Krishna Dt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Potlapalem ZP road to Potepalli inKrishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from R&B road to B.V.Thota in KrishnaDt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Chinnapuram R&B road toGundupalem in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001
Road connecting R&B road throughGantalammapalem in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from R&B road to Cyclone shelter atChandala in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from Potlapalem Z.P road toChikativanipalem in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
R&B Road at Panchayat office toPulaparthivarithota via Badava of Mogalthuru
Mandal in West Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002
Road from R&B road to Pedalanka of NarsapurMandal in West Godavari District. West Godavari
NCRMP/B-W/AP/RHB/ PRED/05/Narasapur/002
R&B road to Indira Nagar (via) Pochammatemple of Narsapur Mandal in West Godavari
Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Road from NH 214 A road to Harjanawada ofkothota of Mogalthuru Mandal in West
Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Road from NH 214 A at Ranga statue centerto Harijanawada of Kalipatnam (E) of
Mogalthuru MandalWest Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002
Road from LB Cherla CC road to Chillapalemof LB Cherla of Narsapur Mandal in West
Godavari Dt.West Godavari
Page 30 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Mogaltur Vempa R&B Road at Uchintha kalavaBridge to Gogulamma Harijanapeta of
Mogalthuru Mandal in West Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
From Narsapur Mogaltur R&B road toDayaldaspeta via Venkateshwara SwamyTemple of Mogalthuru Mandal in West
Godavari Dt.
West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road to Satyanarayanapuramof Kalla Mandal in West Godavari Dt. West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road to Mekaladibba of KallaMandal in West Godavari Dt. West Godavari
Page 31 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8.0 Statement Showing the Inspections and Site Visits of Districts during the Month of January -2013
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF DECEMBER2012
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Runku inSanthabommali Mandal. 19.01.13,26.01.13 2
2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Road from Deppuru, bhadapalli road to Onkuluru &cyclone shelter. 8.01.13 1
3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 8.01.13 1
4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 8.01.13 1
5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 8.01.13 1
6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal. 3.01.13, 19.01.13, 24.01.13 3
7 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004
Construction of High level Bridge acrossBendigedda at km 4/10 of Pundi-Parlkimidi road inSrikakulam Dist.
12.01.13 1
8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 24.01.13 1
9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006
Road from Mabagam R&B road to Dubbakavanipetavia gajapathinagaram. 24.01.13 1
Page 32 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005
Road from R&B road Edullavalasa-Killam to jonnamvia talasamudram 24.01.13 1
11 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 11.01.13 1
12 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 11.01.13 1
13 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from mentada to Dovupeta 11.01.13 1
14 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 11.01.13 1
15 NCRMP/B_W/BR/R&B/01/uppigedda/002 Construction of HLB across uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 3.01.13, 5.01.13, 10.01.13, 24.01.13 4
16 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001
Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.
4.01.13, 10.01.13, 18.01.13,21.01.13, 22.01.13, 26.01.13,
27.01.137
17 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 9.01.13 1
18 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 9.01.13 1
19 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
Road from Borubadra, Malagam road to Kollipaduvia Seepuram, Ghantapeta 9.01.13 1
TOTAL 31
Page 33 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OFDECEMBER 2012
S
NO.PACKAGE NO NAME OF WORK
TPQA INSPECTIONSDURING THIS MONTH
DATES OFVISIT
NO. OFVISITS
1 NCRMP/B-W/ AP/ Br/ R&B/ 02/ Chakaligadda /008
Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) in VizianagaramDistrict.
29.02.2013 1
Total 1
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DURING THIS MONTH OF JANUARY - 2013
SNO
.PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem inRambilli Mandal
03.01.13, 05.01.1308.01.13, 19.01.1322.01.13, 30.01.13
6
2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda inNakkapalli Mandal
03.01.13, 09.01.1310.01.13, 17.01.1323.01.13, 30.01.13
6
3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra inNakkapalli Mandal
03.01.13, 17.01.1323.01.13, 30.01.13 4
Page 34 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarrampeta inNakkapalli Mandal 03.01.13, 30.01.13 2
5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 04.01.13, 12.01.13 2
6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Gajapathinagaramin Payakaraopeta Mandal
04.01.13, 09.01.1312.01.13 3
7 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 Road from R&B road to B.P Kallalu toMatchavanipalem 18.01.13 1
8 NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayyadupalem 19.01.13 1
9 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Rajakoduru 19.01.13, 22.01.13 2
10 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 19.01.13 1
11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 B.T to the road from R & B road to Venkayyapalem 19.01.13, 22.01.13 2
12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 11.01.13 1
13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla toChinateenarla 23.01.13 1
14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road toJanakayyapeta 23.01.13 1
15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi toPatimeeda 23.01.13 1
16 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002 B.T to the road from R&B to Mullaparra up to beachend 23.01.13 1
Page 35 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
17 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cycloneshelter . 31.01.13 1
18 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009 Construction of Cyclone shelter at BangarampalemI&II H/O Vakadu. 31.01.13 1
19 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 08.01.13, 19.01.1322.01.13 3
20 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 09.01.13, 17.01.13 2
21 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 09.01.13, 17.01.13 2
22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 09.01.13, 17.01.13 2
23 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Kadapalem 08.01.13 1
24 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Vadapalem 08.01.13 1
25 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 08.01.13 1
26 NCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007 Road from R&B road to Kothapatnam 08.01.13 1
27 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 08.01.13 1
28 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Jalaripeta 11.01.13 1
29 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Mutyalammpalem 11.01.13 1
TOTAL 53
Page 36 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DURING THIS MONTH OF JANUARY 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/ AP/RCS/ PRED/04/ KARAPA/001 Road from approach road to cyclone shelter atadavipudi in e.g.dt. Nil Nil
2 NCRMP/B-W/ AP/RHB/ PRED/04/ KARAPA/001 Road from gurajanapalli to bandulavaripalem Nil Nil
3 NCRMP/B-W/AP/RHB/ PRED/04/ Katrenikona/003 Road from PR road to Dasarivanipeta and to CycloneShelter 16.012.2013 1
4
NCRMP/B-W /AP/RCS/PRED/04/ Thondangi/004
Road from R&B Road to G.Musalayyapeta CS Nil Nil
5 Road from R&B Road to P.Chodipallipeta CS Nil Nil
6 Road from R&B Road to K.Chodipallipeta CS Nil Nil
7 Road from R&B Road to Hukumpeta CS Nil Nil
8 Road from R&B Road to Gaddipeta CS Nil Nil
9 Road from R&B Road to Danavaipeta CS Nil Nil
10
NCRMP/B-W/ AP/MPCS/ PRED/04/Thondangi/001
Cyclone Shelter at Avulamanda and of ThondangiMandal , E.G.Dt.
03.01.2013, 11.01.2013,15.01.2013 and 31.01.2013 4
11 Cyclone Shelter at Lakshmanudipeta of ThondangiMandal, E.G.Dt.
03.01.2013, 11.01.2013,15.01.2013 and 31.01.2013 4
12 NCRMP/B-W/ AP/RCS/PRED/04/Uppalaguptam/003
Road from R&B Road to Chinaraghavulapeta CycloneShelter NIL NIL
Page 37 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
13 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002
Cyclone Shelter at Pedaraghavulapeta ofUppalaguptam Mandal, E.G.Dt.
04.01.2013, 10.01.2013,12.01.2013, 18.01.2013,22.01.2013, 24.01.2013
and 30.01.2013.
7
TOTAL 16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF YEAR-II WORKS DURING THIS MONTH JANUARY 2013
SNO
.PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISITS NO. OFVISITS
1. NCRMP/B-W/AP/RCS/PRED/05/Achanta/002 Road from R&B road to Ayodya lanka Marrimulacyclone shelter. 19.01.2013 –
2.NCRMP/B-W/AP/RCS/PRED/05/Kalla/003
Road from R&B road to Modi Cyclone Shelter 10.01.2013 –
3. Road from R&B road to S.C Bose Colony CycloneShleter 10.01.2013 –
4. NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004 Construction of approach road to cyclone shelter inLosari of Bhimavaram Mandal. 02.01.2013 –
5.
NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/005
Road from R&B road to Kothakayalathippa cycloneshelter – 1
6.Road from Narsapur Perupalem R&B road toMandavarithota – 1
7. Road from Mollaparru R & B road to Mollaparru PathaColony – 1
8.Road from K.P Palem (N) Panchayat office toMetturevu Palli palem – 1
Page 38 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9.
NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006
R&B road to Chinamynavanilanka – 1
10. P.R road to Ramanujapuram – 1
11. Road from P.R road to Prakasapuram – 1
12. NCRMP/B-W/AP/RHB/PRED/05/Kalla/004 K.G. R&B Road to Mamidipudi of Kalawapudi. 10.01.2013 –
13.NCRMP/B-W/AP/RHB/PRED/05/Bhimavaram/005
Road from Dongapindi R & B Road to Revu(Pallipalem) in Dongapindi of Bhimavaram Mandal. 02.01.2013 –
14. Road from R & B Road to Sarvodhyanagar(Garivelladibba) H/o Losari of Bhimavaram Mandal. 02.01.2013 –
15. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006 Khalipatnam R&B Road to Khalipatnam ferry – 1
16.
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/007
Road from R & B Road at Metturevu to Parasavarimeraka via Kandulapativari meraka – –
17.Road from Narasapur Perupalem R &B Road to
Janakiram Colony in Andevarimeraka of K.P.Palem(S)
– –
18. Road from Narsapur Perupalem R & B road toDondaparthivari meraka – –
19.
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/008
Road from Narsapur PerupalemR & B Road to Melamvaripalem Perupalem(S) – 1
20. Road from Perupalem Mollaparru R & B road viaSattinenivarimeraka to K.D.Pallavapalem – 1
21. Road from Perupalem Dibbalapallipalem R & B roadto Mellapallavapalem – 1
22. Road from Perupalem beach R & B Road toChallavarimeraka via Mucherlavarimeraka – 1
23.
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/009
Road from Perupalem R&B road to Dindla – –
24. Road from Narsapur Perupalem R & B road toNellipallipalem via Ambedkar colony Harijanapeta – –
25. Road from Perupalem R & B Road to Kouruvaripalem – –26. NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010 Road from SP R&B road to Pasaladeevi – 1
Page 39 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
27. LT R&B road to Modi – 1
28. SP R&B road to Gannabathulavari palem ofChamakuripalem – 1
29.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012
Road from R&B road to SC Colony of Pedalanka – 1
30. R&B road to Rajeev Nagar of Darbharevu – 131. SP R&B road to Pedathota of Turputallu – 132. R&B road to Peta of Turputallu – 133. R&B road to Pedathota of Turputallu – 134.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013
R&B road to Guttulavarimeraka – 135. Road from R & B Road to Pulaparthivaripalem – 136. R&B road to Pedaedigapalem – 137. R&B road to Evanivarimeraka – 1
38.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014
Road from PR Road to Prakashpuram SC colony ofVemuladeevi(E) – 1
39. Road from PR road to Vemuladeevi (E) colony (Via)Ralla cheruvu of Vemuladeevi (E) – 1
40. Road from PR road to Addalavarimeraka ofVemuladeevi(E) – –
41.NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/001
Sardupalli Palem of Vemuladeevi 23.01.2013 –42. Pedamynavani lanka 23.01.2013 –43.
NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/003Chinamynavani lanka 23.01.2013 –
44. Vemuladeevi East 23.01.2013 –45.
NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002Yetimondi of Perupalem 24.01.2013 –
46. Bellamkondavarimeraka 24.01.2013 –
Total 26
Page 40 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH JANUARY 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/006
Road from China Zinkapalem to Gollamanda via pedaZinkapalem 09.01.13 1
Road from R&B road to Cyclone Shelter at Gollamanda 09.01.13 1
Road from ZP Road to Cyclone shelter at Natchugunta 09.01.13 1
Road from Krishna river to Elechetla Dibba Cycloneshelter 09.01.13 1
2 NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/009 Road from R&B Road Dananjaya Colony toKrishnapuram 09.01.13 1
TOTAL 5
Page 41 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF JANUARY- 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1
NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002
Road from Ganapavaram R&B Road toPedamarpuvaripalem.
7.1.2013, 8.1.203,17.1.2013, 26.1.2013,27.1.2013, 30.1.2013,
31.1.2013.
7
2 Road from R&B road to chinapuluguvaripalem 5.1.2013, 30.1.2013,31.1.2013. 3
3 Road from Ganapavaram PR Road toBonthagorlapalem. 5.1.2013 1
4 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010 Reconstruction of HLB @ km 5/2 of Bapatla -Suryalanka road across perali drain in Guntur District. 8.1.2013, 10.1.2013. 2
5NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001
Road from R & B Road to Hanumanth Nagar. 31.1.2013. 1
6 Road from R & B Road to Adarshnagar. 31.1.2013. 1
7 NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001 Road from R & B Road Allur to Yadavapalem 4.1.2013, 5.1.2013,7.1.2013, 8.1.2013. 4
TOTAL 19
Page 42 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF JANUARY-13
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/APMPCS/PRED/08/NG Padu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 04.01.2013 1
2 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012
Construction of High level Bridge at Km 16/10 ofNaguluppalapadu – Kanaparthi road in Prakasam District 03.01.2013 1
3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 05.01.2013, 10.01.2013, 15.01.2013
29.01.2013, 30.01.2013, 31.01.2013 6
4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne
05.01.2013, 10.01.2013, 15.01.201326.01.2013, 28.01.2013, 29.01.2013
31.01.20137
5 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from R&B road to Binginapalli Harijanawada CycloneShelter 10.01.2013 1
6 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 10.01.2013, 15.01.2013, 23.01.2013
25.01.2013, 28.01.2013 5
7 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from Pakala ZP Road to Aulavaripalem Cycloneshelter 10.01.2013 1
8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli 10.01.2013 1
9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B road to Narravaripalem 10.01.2013 1
10 NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07 Road from MC Road to Subbarayudu Satram 11.01.2013 1
11 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu 10.01.2013, 23.01.2013
24.01.2013, 28.01.2013 4
12 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem 10.01.2013 1
13 NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001
Chakicherla cyclone shelter in Ulavapadu mandalprakasam district 11.01.2013 1
TOTAL 31
Page 43 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF JANUARY 2013
SLNO Package Number Name of work
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007
Providing BT Surface to the road from R&B road toEdagali kandriga 01.01.2013, 02.01.2013 2
2 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007
Road from Suvepalli-Pudiparthi road to SrikanthColony 01.01.2013, 02.01.2013 2
3 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/006 Road from R&B road to Patuvarikandriga 01.01.2013 1
4 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/002
Road from R&B Road kappaladoruvu to bandla palemH.wada 01.01.2013 1
5 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 11.01.2013 1
6 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005
Road from R&B road Kancharlapalam HW toAlaganipadu.
09.01.2013, 11.01.2013,21.01.2013, 24.01.2013 4
7 NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006
Road Connecting R&B Road through Voturu Villagein SPSR Nellore District 21.01.2013 1
8 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt. 09.01.2013, 31.01.2013 2
9 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter 09.01.2013, 31.01.2013 2
10 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Village 16.01.2013 1
11 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012 Road from R & B Road C S Puram to Sivaramapuram 16.01.2013 1
Total 18
Page 44 of 93
In Joint Venture
Photo Presentation by Third
Party Quality Audit
Consultant of AP NCRMP
Works during January 2013
Page 45 of 93
Page 46 of 93
Page 47 of 93
Page 48 of 93
Page 49 of 93
Page 50 of 93
Page 51 of 93
Providing B.T to the Road from NH-5 to Ramaraidupalem
Measurement verification
Measurement verification Measurement verification
Page 52 of 93
Providing B.T to the Road from NH-5 to Ramaraidupalem
Measurement verification
Site View
Site View
Page 53 of 93
Page 54 of 93
Page 55 of 93
Page 56 of 93
Page 57 of 93
Page 58 of 93
Page 59 of 93
Page 60 of 93
Page 61 of 93
Page 62 of 93
Page 63 of 93
Name Board Site View
Site View Measurement verification
Page 64 of 93
Name Board Site View
Cc road completed
Measurement verification Measurement verification
Page 65 of 93
Name Board
Site view
Site view
Site view
Page 66 of 93
Village name board fixed
Measurement verification Site View
Name Board
Page 67 of 93
Name Board
Measurement verification
Name Board
Site view
Page 68 of 93
Village board Name board
Site View Site View
Page 69 of 93
Site View
Name board Site View
Site View
Page 70 of 93
Site View
Km stone and Name board
Measurement verification
Name board
Page 71 of 93
Page 72 of 93
Page 73 of 93
Page 74 of 93
Page 75 of 93
Page 76 of 93
Page 77 of 93
Page 78 of 93
Page 79 of 93
Page 80 of 93
Page 81 of 93
NCRMP TPQA inspection of Road from R&B road
Kancharapalem HW to Alaganipadu of Nellore Dt.
On 20.12.12 –Collection of WBM Gr-II aggregates
Gradation for WBM Gr-II aggregates
Wearing coat on vented road dam is in progress
Gradation for WBM Gr-II aggregates
Page 82 of 93
Thickness checking for WBM Gr-II layer
Volumetric analysis for WBM Gr-II layer NCRMP TPQA inspection of Road from R&B road
Kancharapalem HW to Alaganipadu of Nellore Dt.
On 20.12.12 –Wearing coat is in progress
Thickness checking for WBM Gr-II layer and
volumetric analysis
Page 83 of 93
NCRMP TPQA inspection of Road from R&B road
Kancharapalem HW to Alaganipadu of Nellore Dt.
On 29.12.12 Volumetric analysis for WBM Gr-II
layer
Collection of gravel for shoulder , WBM Gr-II layer
Wearing coat curing by ponding. Both side of Road Dam,Guard stones.
Page 84 of 93
NCRMP TPQA inspection of Road from
R&BroadKancharapalem HW to Alaganipadu of Nellore Dt
o29.12.12-Carriage way width checking
Carriage way width checking at curve location
View of WBMGr-II layer View of WBMGr-II layer
Page 85 of 93
NCRMP TPQA inspection of Providing BT road to Peda Pannam Gadu in Tada Mandal of Nellore Dt on 18.12.2012-Collection of WBM Gr-II aggregates
Gradation for WBM Gr-II aggregates
Gradation for WBM Gr-II aggregates Gradation for WBM Gr-II aggregates
Page 86 of 93
Gradation for WBM Gr-II aggregates Gradation for WBM Gr-II aggregates
Gradation for WBM Gr-II aggregates View of CC road
Page 87 of 93
Gradation for WBM Gr-II aggregates Camber checking for WBM Gr-II layer
Watering for WBM Gr-II layer CC road thickness checking
Page 88 of 93
View of CC road
Checking of formation width
CC road width checking
Checking of carriage way width
Page 89 of 93
NCRMP TPQA inspection of Road from R&B
road Kancharapalem HW to Alaganipadu on
11.01.13-Collection of WBM Gr-III aggregates
Gradation for WBM Gr-III aggregates
Gradation for WBM Gr-III aggregates Gradation for WBM Gr-III aggregates
Page 90 of 93
Gradation for WBM Gr-III aggregates
Gradation for WBM Gr-III aggregates
Gradation for WBM Gr-III aggregates
Gradation for WBM Gr-III aggregates
Page 91 of 93
NCRMP TPQA inspection of Road from R&B
road Kancharapalem HW to Alaganipadu on
21.01.13- WBM Gr-III layer thickness checking
WBM Gr-III layer thickness checking
Volumetric analysis for WBM Gr-III layer Camber checking for WBM Gr-IIII layer
Page 92 of 93
WBM Gr-III layer thickness checking WBM Gr-III layer thickness checking
WBM Gr-III layer undulations checking View of WBM Gr-III layer
Page 93 of 93