monthly progress report january 2013

94
National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh THIRD PARTY QUALITY AUDIT (TPQA) in Joint Venture with

Upload: mys85

Post on 08-Feb-2016

42 views

Category:

Documents


11 download

DESCRIPTION

Report

TRANSCRIPT

Page 1: Monthly Progress Report January 2013

National Cyclone Risk Mitigation Project(NCRMP)

Revenue (DM) DepartmentGovernment of Andhra Pradesh

THIRD PARTY QUALITY AUDIT (TPQA)

in JointVenture with

Page 2: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

INDEX

1.0 Project Background 2

2.0 Third Party Quality Audit Consultant 3

3.0 Major Activities and Review Meetings of the Month 3

4.0 Status of TPQA Visits 4

5.0 Progress of NCRMP works 5

TPQA Status Report for NCRMP Works and NCRs Pending up to end ofJanuary-2013 6

6.0 District wise status of tests conducted by TPQA 28

7.0 Details of QC Audit Reports Submitted during this Month 29

8.0Statement Showing the Inspections and Site Visits of Districts during the Month

of January-2013 32

Photographs of Site Visits during the Month of January-2013 45

Page 1 of 93

Page 3: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.0 Project BackgroundAndhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state,

the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-

December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic

events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years

ranging from 1892 to 1989, there were as many as 67 cyclones within the State.

It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster

due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based

on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

existing facilities available in the project area in Andhra Pradesh.

The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

proceeds to payments for goods, works, related services and consulting services under this Project.

National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

Guntur, Prakasam and Nellore. The project “Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

Shelters, and Roads to habitations and Roads & Bridges under NCRMP” is funded by International Development

Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

implemented by various line departments working under PIU. The number of works under progress / for which

agreements are concluded in each district is shown in the table below.

District

No. of works(Under Concluded Agreements) No. of works under Progress No. ofworks

notstartedRHB RCS MPCS Bridges Roads

(R&B) Total RHB RCS MPCS Bridges Roads(R&B)

Srikakulam 6 8 2 4 1 21 6 8 2 4 1 0

Vizianagaram - - - 2 1 3 - - - 2 1 0

Visakhapatnam 8 6 7 - - 21 8 6 7 - - 0

East Godavari 2 8 3 - - 13 2 7 3 - - 1

West Godavari 10 - - - - 10 10 - - - - 0

Krishna 5 3 - - - 8 5 3 - - - 0

Guntur 3 12 - 2 - 17 3 12 - 2 - 0

Prakasham 14 7 2 1 - 24 14 7 2 1 - 0

Nellore 17 9 - - - 26 17 9 - - 0

Page 2 of 93

Page 4: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2.0 Third Party Quality Audit Consultant.

To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st May’2011, the Contract for Consultancy Service was signed

between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

3.0 Major Activities and Review Meetings of the Month

S.No. Place Date Activity

1 Hyderabad 07.01.2013 Attended Review meeting of TPQA at H Block in APSecretariat with Commissioner and PD

2 Hyderabad 08.01.2013 Attended Review meeting of EPTRI at H Block in APSecretariat with Commissioner and PD

3 Hyderabad 31.01.2013 Attended Review meeting at H Block in AP Secretariat withCommissioner and PD

Page 3 of 93

Page 5: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.0 Status of TPQA Visits:

The following table shows the details of TPQA visits to sites in respective districts.

DistrictTotal Number of Visits

Up to Dec.2012 In Jan.2013 Up toJanuary.2013

Srikakulam 452 31 483

Vizianagaram 72 1 73

Vishakhapatnam 361 53 414

East Godavari 612 16 628

West Godavari 436 26 462

Krishna 299 5 304

Guntur 373 19 392

Prakasam 407 31 438

Nellore 323 18 341

No. of Visits by TPQA

Page 4 of 93

Page 6: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5.0 Progress of NCRMP works:

The district wise progress of works is shown below. The works in the West Godavari are not started and the works inKrishna District has just started. At many places the first milestone is completed but works are not started. The linedepartments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per theagreement conditions should be imposed.

Third Party Quality Audit by Egis – India consulting services

Summary of Activities

S.No. District

Agreements for PackagesCommunicated Status of works

PR R&B Progress Not Started

1 Srikakulam 6 5 21 0

2 Vizianagaram - 3 3 0

3 Visakhapatnam 13 0 21 0

4 East Godavari 7 0 12 1

5 West Godavari 3 0 10 0

6 Krishna 4 0 8 0

7 Guntur 6 2 17 0

8 Prakasham 12 1 24 0

9 Nellore 16 0 26 0

Total 67 11 142 1

Total Packages for which Agreements are received 79

Total Number of works in the above packages 143

Page 5 of 93

Page 7: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF JANUARY 2013

S.No. District

Packages /Works

entrustedStatus of Works No. of

Visitsof

TPQA

TotalNo. of

QCtestsdone

NCRs AuditReportsIssued

Environmental& SocialReportsIssuedPR R&B Started Not

Started Issued closed Pending

1 Srikakulam 16 5 21 0 452 1475 54 54 0 78 57

2 Vizianagaram - 3 3 0 72 461 3 3 0 11 9

3 Visakhapatnam 21 - 21 0 361 2237 25 25 0 73 41

4 East Godavari 13 - 12 1 612 1128 28 28 0 58 31

5 West Godavari 10 - 10 0 436 349 20 20 0 62 37

6 Krishna 8 - 8 0 299 85 3 3 0 43 21

7 Guntur 15 2 17 0 373 606 14 14 0 61 32

8 Prakasam 23 1 24 0 407 1905 36 36 0 118 50

9 Nellore 26 - 26 0 323 1174 32 32 0 109 48

Total 132 11 142 1 3335 9420 215 215 0 613 326

Page 6 of 93

Page 8: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN SRIKAKULAM DISTRICT UP TO 31.01.2013

Category

Packages allottedunder Phase - 1

Names of works undereach package

AgreementNo. / Date

Milestone Completion DatesProgress

w.r.t.milestone up

to31.01.2013

RemarksFirst Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

Road from DPN R&B road toUddandapalem

/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete

Entire work completed

Road from K. UmiladaJunction to Koduru (Link

Road)

/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete

Entire work completed

Road from Borubhadra,Malagam to Kollipadu via

Seepuram, Gantapeta

/2010-11, Dt.30.04.2011 31.08.11 31.12.11 30.04.12 complete

Entire work completed

NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

Road from R&B roadMobagam to

Duubakavanipeta viaGajapathinagaram

/2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12

First Milestonei.e Earthwork& Cd works

&GSB

300 mts CC roadcompleted, GSB

laying is inprogress, roadformation width

vary from6.00mts to7.50mts

Road from Talasamudram toDola Regulator

/2010-11, Dt.30.04.2011 30.08.11 31.12.11 30.04.12

First Milestonei.e Earthwork& Cd works &

GSB

completed

NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

Road from R&B roadEdulavalasa - Killam to

Jonnam via Talasamudram

/2011-12, Dt.30.04.2011 31.07.11 31.10.11 31.01.12

First Milestonei.e Earthwork& Cd works

&GSB

BT layercompleted fromKm 5/670 to Km7/270, and WBM

Gr- III metal

Page 7 of 93

Page 9: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

collection is inprogress from

Km 5/000 to Km5/670

Bridges

NCRMP/B-W/AP/Br/R&B/01/Patnavanipeta/001

Construction of bridge at Km11/6-8 of NH-5 toPatnavanipeta ConnectingSundarapalem

46/2011, Dt.17.12.2010 17.08.11 17.01.12 17.06.12 Completion of

entire work

Slab A2-piercompleted andSlab A1-pier sisin progress,Approach roade/w, GSB,WMM, SDBCcompleted. CD,R/W workscompleted.

NCRMP/B-W/AP/Br/R&B/01/Surampeta/003

Construction of Minor Bridgeat Km 12/2-4 of NH-5 to

Surampeta Road via Naruva,mentada

45/2010-2011,Dt17.12.2010 17.05.11 17.10.11 17.03.12 Completion of

entire work Completed.

NCRMP/B-W/AP/Br/R&B/01/Bendigedda/004

Construction of High levelbridge across Bendigedda atKM 4/10 of Pundi-Parlakimidiroad in Srikakulam Dt, A.P.

1/2010,Dt.11.11.2010 11.08.11 11.01.12 11.06.12 Completion of

entire work Completed.

RoadsNCRMP/B-W/AP/RD/R&B/01/Nowpada/006)

Improvesments Naupada-Venkatapuram road from0/0to15/0km

43/2010-11,17.12.2010

17.05.11 17.10.11 17.03.12 Completion ofentire work work completed

RCSNCRMP/B-W/AP/RCS/PRED/01/V.KOTTURU/002

Road from NP road toURKpuram

G.o rt No 451dt 06.04.2010 29.01.12 29.05.12 29.09.12 WBM GR-II

&III complete work completed

Road from Deppuru,Bahadapalli road to onkuluru& to cyclone shelter

G.o rt No 451dt 06.04.2011 29.01.12 29.05.12 29.09.12 WBM GR-II

&III complete work completed

Road from R&B road toDevunthalada

G.o rt No 451dt 06.04.2012 29.01.12 29.05.12 29.09.12 WBM GR-II

&III complete work completed

Page 8 of 93

Page 10: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from pollada toKomarthalada & to cycloneshelter

G.o rt No 451dt 06.04.2013 29.01.12 29.05.12 29.09.12 WBM GR-II

&III complete work completed

NCRMP/B-W/AP/RCS/PRED/01/ETCHERLA/005

Road from Koyyam R&BRoad to Moosavanipeta

G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of

entire work work completed

Road from Mentada toDovupeta

G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of

entire work work completed

Road from Kotcherela road toKollibhemavaram & cycloneshelter

G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of

entire work work completed

Road from Kotcherla road toPathasundarapalem

G.o rt No 451dt 06.04.2010 07.11.11 07.02.12 07.06.12 Completion of

entire work work completed

MPCSNCRMP/B_W/AP/MPCS/PRED/01/Santhabommalli/005

Construction of Cycloneshelter at Kollipadu

G.o rt No 451dt 06.04.2010 07.03.12 07.08.12 07.01.13

Completion ofstilt floor &first floor

Silt floor levelslab completed.

Construction of CycloneShelter at Runku

G.o rt No 451dt 06.04.2010 07.03.12 07.08.12 07.01.13

Completion ofstilt floor &first floor

Upto plinthbeam

completed, andcolumns above

plinth beam is inprogress

Page 9 of 93

Page 11: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN VIZIANAGARAM DISTRICT UP TO 31.01.2013

Category

Packagesallotted under

Phase - 1

Names of works under eachpackage

AgreementNo./ Date

Milestone Completion Dates Progress w.r.t.milestone upto 31.01.2013

RemarksFirst Second Third

Bridges

NCRMP/B-W/ AP/Br/ R&B/

02/Puligadda/ 007

Construction of Minor Bridge atKm. 7/2 near Puligedda of

Konada – Ramatheertham R&BRoad to Konathalapalem via

Yerukonda, Pasupam,Kollayavalsa (Z.P. Road)

31/2010-2011Dt.

01.12.201030.06.11 31.01.12 31.05.12 100% of work

completed

As against of100 % in the 3rd

Milestone

NCRMP/B-W/ AP/Br/ R&B/ 02/

Chakaligadda /008

Construction of Minor Bridge atKm 15/2 near Chakaligadda ofKonada Ramatheertham R&Broad to Konathalapalem (via)

Yerukonda, Pasupam,Kollayavalsa (ZP Road)

34/2010-2011Dt.

08.12.201007.07.11 07.02.12 07.06.12 90% of work

completed

Minor deviationapproval is

awaited. It takes15 days time tocomplete thework afterdeviationapproval

RoadNCRMP/B-

W/AP/RD/R&B/ 02/Konada/009

Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

Pasupam, Yerukonda,Kollayavalsa from Km 12/0 to16/5 (Km 0/0 to 4/0 i.e. up to

NH-5 crossing)

33/2010-2011Dt.

08.12.201007.06.11 07.12.11 07.03.12 100% of work

completed -

Page 10 of 93

Page 12: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT UP TO 31.01.2013

Category

Packagesallotted under

Phase - 1

Names of worksunder each package

AgreementNo. / Date

Milestone Completion Dates Progress w.r.t.milestone up to

31.01.2013Remarks

First Second Third

MPCS

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopet

a/003

Construction of cycloneshelter at

Gajapathinagaram

/2011-12, Dt.03.10.2011 05.06.12 05.10.12 05.02.13

Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOAT submittedon 24.08.12

likely to becompleted

beforeMarch.2013

Construction of cycloneshelter at Ratnayampeta

/2011-12, Dt.03.10.2011 02.02.12 02.06.12 02.10.12

All Slabs are completed.Inside and outside wallplastering work completed.White cement applications,wood joinery and Electricalworks are to be progress.

likely to becompleted

before15.02.2013

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/00

2

Construction of cycloneshelter at Patimeeda

/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOATsubmitted on 24.08.12

likely to becompleted

beforeMarch.2013

Construction of cycloneshelter at Mullaparra

/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

Stilt Slab & stilt floor, Firstfloor and head room slabsare completed. Ceilingplastering work and firstfloor brick work are inprogress.

likely to becompleted

beforeMarch.2013

Page 11 of 93

Page 13: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Construction of cycloneshelter at Bangarampeta

/2011-12, Dt.03.10.2011 02.03.12 02.08.12 02.01.13

Stilt floor, First floor,second floor, Head roomslabs are completed. Istfloor and second floor brickmasonry work is inprogress.

likely to becompleted

beforeMarch.2013

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of cycloneshelter at

Venkayyapalem

/2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12

Plinth beam completed andfilling under floor is inprogress. EOAT proposalssubmitted on 29.06.12.

likely to becompleted

beforeJune.2013

NCRMP/B-W/AP/MPCS/PRED/03/Parawada/00

1

Construction of cycloneshelter at

Thikkavanipalem

/2011-12, Dt.07.10.2011 06.01.12 06.04.12 06.07.12 Work not started due to

site problemProgress is

Slow

RCS

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/

001

Road from NH-5 toRamarayadupalem

/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 Road Furniture & B.T is

completed. completed

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

Road from R & B road toRajakoduru

/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD works are completed &

B.T work is Completed completed

Road from R & B road toKattubolu to Marripalem

/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD works are completed &

B.T work is Completed completed

Road from R & B road toKrishnampalem

/2011-12, Dt.15.09.2011 14.01.12 14.05.12 14.09.12 CD Work is completed &

B.T work is completed completed

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from R&B road toPedatheernala toChinatheernala

/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 B.T & C.C road works are

Completed. completed

Page 12 of 93

Page 14: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from UpmakaRajayyapeta R&B road

to Janakayyapeta

/2011-12, Dt.15.09.2011 14.12.11 14.03.12 14.06.12 CD works are Completed &

B.T work is completed completed

RHB

NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

Road from Vempudi toPatimeeda

/2010-11, Dt.11.01.2011 10.05.11 10.09.11 10.01.12 Work is completed -

Road from R&B road toMullaparra up to Beach

end

/2010-11, Dt.27.01.2011 26.04.11 26.07.11 26.10.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/

003

Road from R&B B.PKallalu to

Matchvanipalem

/2010-11, Dt.10.03.2011 09.06.11 09.09.11 09.12.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

Road from R & B road toPothurajanapalem

/2010-11, Dt.28.03.2011 27.06.11 27.09.11 27.12.11 Work is completed -

Road from R & B road toJalaripeta

/2010-11, Dt.28.03.2011 27.06.11 27.09.11 27.12.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006

Road from R & B road toVenkayyapalem

/2010-11, Dt.11.01.2011 10.04.11 10.07.11 10.10.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/

007

Road from R&B road toAva- Somavaram

/2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -

Road from R&B Road toAvarajam

/2011-12, Dt.27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -

Page 13 of 93

Page 15: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT UP TO 31.01.2013.

Category

Packages allottedunder Phase - 1

Names of worksunder each package

AgreementNo. / Date

Milestone Completion DatesProgress

w.r.t.milestone upto 31.01.2013

Remarks

First Second Third

RCS

NCRMP/B-W/RCS/PRED/04/Karapa/001

Approach Road tocyclone Shelter atAdivipudi

32/2011-12Dt:20.05.2011 30-11-2011 31-10-2011 31-01-2012 100% Completed.

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto P.Chodipallipeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 100% Completed.

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto K.Chodipallipeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 100% Completed

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Hukumpeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

Road from R&B Roadto ChinaraghavulapetaCyclone Shelter

74/2011-12Dt: 23.09.2011

3 months22.11.2011

3 months22.06.2011 ----------- 100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Gaddipeta CS

73 /2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Danavaipeta CS

73 /2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto G.Musalayyapeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012 Nil Not yet

Started

RHB NCRMP/B-W/AP/RHB/PRED/04/Karapa/001

Road from Gurjanapallito Bandulavaripalem

24/2011-12Dt:27.04.2011 30-09-2011 31-10-2011 31-01-2012 100% Completed

Page 14 of 93

Page 16: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/0

03

Road from PR roads toDasarivanipeta and toCyclone Shelter

18/2011-12Dt:27.04.2011 30-11-2011 30-11-2011 20-01-2012 100% Completed.

MPCS

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction ofCyclone Shelter atPedaraghavulapeta ofUppalaguptam MandalE.G.Dt.

78/2011-12Dt:17.10.2011

3 months16.01.2012

3 months16.04.2012

3 months16.07.2012 45%

Likely to becompleted byJune 2013

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction ofCyclone Shelter atLakshmanudipeta inThondangi

77/2011-12Dt:07.09.2011

4 months16.02.2012

4 months16.06.2012

4 months16.10.2012 80%

Likely to becompleted byMarch 2013

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction ofCyclone Shelter atAvulamanda

77/2011-12Dt:07.09.2011

4 months16.02.2012

4 months16.06.2012

4 months16.10.2012 80%

Likely to becompleted byMarch 2013

Page 15 of 93

Page 17: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN WEST GODAVARI DISTRICT UP TO 31.01.2013

Category

Packagesallotted under

Phase – 1

Names of works under eachpackage

Agreement No. /Date

Milestone Completion Dates Progressw.r.t.

milestoneup to

31.01.13

RemarksFirst Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001

Road from NH 214 A at Ranga Statuecenter to Harijanawada of Kalipatnam

(E) (Mogalthuru Mandal

16 /2011-12Dt.27.04.2011

27/4/2011to

22/9/2011

23/9/2011to

24/2/2012

25/2/2012to

26/7/2012

100% Completed

R&B road at Panchayat Office toPulaparthivarithota via Badava(Mogalthuru Mandal W.G.Dist.)

100% Completed

Mogalthuru Vempa R&B Road atUchintha Kalava Bridge to Gogulamma

Harijanapeta (Mogalthuru Mandal)100% Completed

From Narsapur Mogalthuru R&B road toDayadaldaspeta via Venkateshwara

Swamy temple (Mogalthuru Mandal )100% Completed

Road from NH 214 A road toHarijanapeta of Kothota

27/4/2011to

22/9/2011

23/9/2011to

24/2/2012

25/2/2012to

26/7/2012100% Completed

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

R&B road to Indira Nagar (via)Pochamma temple (Narsapur Mandal) 21 /2011-

12Dt.09.05.2011

09/05/2011to

04/09/2011

05/09/2011to

06/01/2012

07/01/2011to

08/5/2012

100% Completed

Road from R&B road to Pedalanka(Narsapur Mandal W.G.Dist.) 100% Completed

Road from LB Cheria CC road toChillapalem of LB Cheria. 100% Completed

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road toSatyanarayanapuram (Kalla Mandal) 25 /2011-

12Dt.26.05.2011

26/5/2011To

20/8/2011

20/8/2011to

21/11/2011

22/11/2011To

23/2/2012

100% Completed

From A-U R&B Road to Mekaladibba(Kalla Mandal W.G.Dist.) 100% Completed

Page 16 of 93

Page 18: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN KRISHNA DISTRICT UP TO 31.01.2013

Category

Packages allotted underPhase - 1

Names of works undereach package

AgreementNo. / Date

Milestone Completion DatesRemarks

First Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001

Road connecting R&B roadthrough Gantlammapalem

8/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from R & B Road to B.VThota

7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

Road from Potalapalem Z.Proad to Chikativanipalem

7/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from Intheru R&B Roadto Rangaraopet

9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

Road from R&B road toCyclone Shelter at Chandala

9/2011-12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

RCS NCRMP/B-W /AP/RCS/PRED/06/Machilipatnam/001

Road from BhogireddypalliR&B Road to Ramakhandam

32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012 Completed

Road from R&B RoadChinnapuram to Gundupalem

32/2011-12/27.04.2011 01.12.2011 01.03.2012 01.06.2012 Completed

Road from Potlapalem Z.P roadto Pothepalli.

32/2011-12/Dt.02.09.2011 01.12.2011 01.03.2012 01.06.2012 Completed

Page 17 of 93

Page 19: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN GUNTUR DISTRICT UP TO 31.01.2013

Category

Packages allottedunder Phase - 1

Names of works undereach package

Agreement No./Date

Milestone completion dates Progressw.r.t.

milestoneup to

31.01.2013

RemarksFirst Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/

07/KARLAPALEM/001

R/f Ganapavaram R&BRoad to Kesavapuri ST colony

7/2011-2012

27.04.2011

26.7.2011 26.10.2011 26.01.2012 -Completed

NCRMP/B-W/AP/PRED/07/Nagaram/002

R/f R&B Road to MohammadAlipalem

8/2011-2012

27.04.2011

26.8.2011 26.12.2011 26.4.2012 -Completed

R/f R&B Road toKaturivaripalem.

-Completed

Bridges

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of High-levelBridge @Km5/2 of Bapatla-Suryalanka Road across peralidrain in Guntur Dt.

79/2010-2011

1.12.2010

31.5.2011 30.11.2011 31.5.2012

- Completed

NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

Reconstruction of High-levelBridge @Km2/4 of Bapatla-Pandurangapuram Road acrossperali drain in Guntur Dt.

78/2010-2011

1.12.2010

31.5.2011 30.11.2011 31.5.2012

90%

Likely to becompleted

beforeMarch 2013

RCS

NCRMP/B-W/AP/RCS/PRED/ 07/PV

Palem/001

Road from R&B road toMandevaripalem

2011-20121.11.2011

31.01.2012 30.04.2012 31.07.2012- Completed.

Road from R&B Road Alluru toYadavapalem

31.01.2012 30.04.2012 31.07.2012

45%

Likely to becompletedbefore Feb

2013

NCRMP/B-W/AP/RCS/PRED/

07/Karlapalem/002

Road from Ganapavaram R&BRoad to Pedamarpuvaripalem

2011-20121.11.2011

29.02.2012 30.06.2012 31.10.2012

20%

Likely to becompletedbefore Feb

2013

Page 18 of 93

Page 20: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R&B Road toChinapuluguvaripalem

29.02.2012 30.06.2012 31.10.2012

25%

Likely to becompletedbefore Feb

2013From R&B road toYaramvaripalem

29.02.2012 30.06.2012 31.10.2012- Completed.

Road from R&B Road toPedagollapalem CycloneShelter

29.02.2012 30.06.2012 31.10.2012- Completed.

Pedagollapalem P.R road toBonthagoralapalem

29.02.2012 30.06.2012 31.10.2012-

Shouldersare in

progress.

NCRMP/B-W/AP/RCS/PRED/

07/Nizampatnam/003

Road from R&B Road toGurunadhanagar

2011-201217.10.2011

16.01.2012 16.04.2012 16.07.2012- Completed.

Road from R & B Road toAdavala H/O Bavaji palem

16.01.2012 16.04.2012 16.07.2012- Completed.

Road from R & B Road toAtlavaripalem

16.01.2012 16.04.2012 16.07.2012- Completed.

NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004

Road from R & B Road toHanumathanagar

2011-201227.10.2011

26.01.2012 26.04.2012 26.07.2012- Completed.

Road from R & B Road toAdarsh nagar

26.01.2012 26.04.2012 26.07.2012- Completed.

Page 19 of 93

Page 21: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN PRAKASAM DISTRICT UP TO 31.01.2013

Category

Packages allottedunder Phase - 1

Names of worksunder eachpackage

Agreement No. /Date

Milestone completion dates Progress of workfor the month –January 2013

RemarksFirst Second Third

BRIDGES

NCRMP/B-W/AP/Br/R&B/08/ Kanaparthy/012

Construction of Highlevel Bridge at Km16/10 ofNaguluppapadu –Kanaparthy road

76/2010-11Dated1/12/2010

5/31/2011Completionup to silllevel

12/31/2011Completionup to belowdeck slab

5/31/2012Completionof entireworkincludingapproaches

Bridge work iscompleted. completed

RHB

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from Pakala ZPRoad toAulavaripalemCyclone shelter

Dated25.04.2011

8/24/2011Earth work,CD work,

GSB

12/24/2011WBM,

Grade II &III

4/24/2012BT,

Shoulders& road

furniture

CC Road & Shoulderswork is Completed. completed

Road from R&B Roadto Somarajupalli

Dated25.04.2011

BT, CC road & culvertsare completed fromKM 0/0 to 2/146.

completed

Road from R&B roadto Narravaripalem

Dated25.04.2011

BT, & culverts areCompleted from KM0/0 to 0/900. work iscompleted

completed

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from NH5 toMulaguntapadu

dated10/02/2011 6/9/2011

Earth work,CD work,

GSB

10/9/2011WBM,

Grade II &III

2/9/2012BT,

Shoulders& road

furniture

WBM-Grade-III LayerCompleted. OGPC +Seal Coat To be takenup

work is notgoing on

Road from R&B roadto Chalivendradibba

dated -10/02/2011

WBM-Grade-III LayerCompleted. OGPC +Seal Coat To be takenup

work is notgoing on

Page 20 of 93

Page 22: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from PakalaR&B road toMosanaladinne

dated10/02/2011

6/9/2011Earth work,CD work,

GSB

10/9/2011WBM,

Grade II &III

2/9/2012BT,

Shoulders& road

furniture

WBM-Grade-IIImaterial laying work isin progress

98%

Road from R&B roadto BinginapalliHarijanawada CycloneShelter

dated10/02/2011

CC road work iscompleted from KM0/0 to KM 0/220.Shoulders work is tobe taken up.

98%

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

Road from R&B RoadAllur to M T Rajucolony

Dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II &III

4/26/2012BT,Shoulders& roadfurniture

BT, CC road, shoulders& culverts arecompleted from km0/0 to km 3/8.work iscompleted

completed

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R&BRoad toSankuvarigunta

Dated27/04/2011

9/26/2011Earth work,CD work,

GSB

2/26/2012WBM,

Grade II &III

7/26/2012BT,

Shoulders& road

furniture

BT completed.CD workcompleted.CC roadwork completed fromkm 0/0 to km 1/430and CC dip work iscompleted

completed

Road from KEM R & BRoad toPullareddypalem

Dated27/04/2011

BT completed.CD workcompleted.CC roadand shoulders workcompleted from km0/0 to km 3/900.

completed

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

Road from MC Roadto SubbarayuduSatram

dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II &III

4/26/2012BT,Shoulders& roadfurniture

BT completed.CD workcompleted andshoulders workcompleted from km0/0 to km 3/4. work iscompleted

completed

Page 21 of 93

Page 23: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

Road from R&B roadTettu toRamayapatnam

dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II &III

4/26/2012BT,Shoulders& roadfurniture

BT completed.CD workcompleted.CC roadand shoulders workcompleted from km0/0 to km 5/086. workis completed

completed

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

Road from R&B roadPellur toVasepallipadu

dated16/03/2011

7/15/2011Earth work,CD work,GSB

11/15/2011WBM,Grade II &III

3/15/2012BT,Shoulders& roadfurniture

BT completed. CDwork completed.CCroad and shoulderswork completed fromkm 0/0 to km 4/5.work is completed

completed

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

Road from R&B roadto Kesupalem

dated19/04/2011

7/18/2011Earth work,CD work,GSB

10/18/2011WBM,Grade II &II

1/18/2012BT,Shoulders& roadfurniture

BT completed. CDwork completed.CCroad and shoulderswork completed fromkm 0/0 to km 2/103.work is completed

completed

RCS NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B roadto Vijayanagar colonycyclone shelter

dated30.09.2011

1/29/2012Earth work,GSB

5/29/2012shoulders,Gr-III

9/29/2012BT, CCpavementand roadfurniture

cc road completed, BTroad completed&shoulders completed.Road from km 0/0 tokm 0/525. work iscompleted

completed

Road from NH road toChallareddypalem

cc road completed, BTroad completed&shoulders completed.Road from km 0/0 tokm 1/735. work iscompleted

completed

Road from R&B roadto jeevaraksh nagarcolony cyclone shelter

C.C.road andShoulders arecompleted Road fromkm 0/0 to km 0/500.

completed

Page 22 of 93

Page 24: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R&B roadto Ramnagar colonycyclone shelter

C.C.completed Roadfrom km 0/0 to km0/475.Shoulders to betaken up.

completed

Road from R&B roadto cyclone shelter atMankenavaripalem

CC road completed.Shoulders work is tobe taken up.

completed

NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

Road from R&B Roadto Keerthivaripalemcyclone shelter

dated27.08.2011

C.C road andShoulders arecompleted from km0/0 to km 0/265. workis completed

completed

Road from R&B Roadto Devinuthulacyclone shelter ofChirala Mandal

C.C road andShoulders arecompleted from km0/0 to km 0/800. workis completed

completed

MPCS NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001

Chakicharla cycloneshelter in UlavapaduMandal

24.11.2011All items upto stilt floorslabincludingramp, staircasefoundations, columns,beams, pccflooringetc.,

24.02.2012All items upto secondfloor slabincludingfirst floor,and in 2ndfloorincludingstair case,columnsetc.,

24.05.2012Head room,plastering,flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compoundwall, ccpavement.Earthenmounds(raised

Stilt floor, G.F , &Terrace floor- roof slabcompleted. Brick workcompleted, Plasteringwork completed, Cattleplatform completedrevetment workcompleted, flooringwork is completed,compound wall 120meters lengthcompleted, Electricalwork is completed.work is completed

completed

Page 23 of 93

Page 25: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

portion),waterharvesting,septic tank,slump andsoak pit.etc.,

NCRMP/B-W/APMPCS/PRED/08/NG Padu/003

Kanaparthy cycloneshelter inNaguluppapaduMandal prakasamdistrict

23.11.2011All items upto stilt floorslabincludingramp, staircasefoundations, columns,beams, pccflooringetc.,

23.02.2012All items upto first floorslab andhead roomslb in 2 ndfloorincludingstair case,columnsetc.,

23.05.2012plastering,flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compoundwall, ccpavement.Earthenmounds(raisedportion),waterharvesting,septic tank,slump andsoak pit.etc.,

Internal & ExternalPlastering completed.Flooring WorkCompleted. CompoundWall PaintingCompleted. CC RoadCompleted. Shoulderwork in Completed.Painting work inCompleted. ElectricalFittings in progress.Tiles in bathroomswork in Completed.Water harvest & Soakpit work in completed.

completed

Page 24 of 93

Page 26: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN SPSR NELLORE DISTRICT UP TO 31.01.2013

Name of package Name of work date ofagreement mile stone -I mile stone -II mile stone -III

PresentStatues of

workRemarks

RHB

NCRMP/B-W/AP/RHB/PRED/09/

BOGOLO/RHB/001

1. Road from NH5 toSambasiva Puram

1/19/20115Months: Earth

Work, PipeCulverts, GSB

10 Months:WBM GrII, GrIIand Shoulders

15 Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002

Road from 1/6 ofZuvvaladinne R&B Road to

Tellagunta KM to 2/72007.02.2011

6.5,20113Months: Earth

Work, PipeCulverts, GSB

6.8.2011 6Months: WBMGrII, GrII and

Shoulders

6.11.20119Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/

CHITTAMURU/003

Road from R&B Road toMuttambeka Via

Pittuvanipalla 18.01.2011

17.6.20115Months: Earth

Work, PipeCulverts, GSB

17.11.2011 10Months: WBMGrII, GrII and

Shoulders

17.4.2012 15Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

Road from R&B Chittamurto Soma Samudram

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/RHB/

KAVALI/004

Road from5/8 ofChennayapalem Road to

Gummadi bandla

17.01.2011

16.6.20115Months: Earthwork,CD Works, ccpavement and

GSB

16.11.2011 10Months: WBM

GrII, GrIi I andShoulders

16.4.2012 15Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

Road from pedattapupalemR&B road to

Chennayapalem H.wada

OGPC+ SCcompleted

completed

Road from K.T R&B Road toAlliguntapalem

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/

VIDAVALURU/005

1)Road from KT R&Broad to Alaganipadu to

Vavilla27.04.2011

26.9.20115Months: Earth

Work, PipeCulverts, GSB

26.2.201210Months: WBMGrII, GrII and

Shoulders

26.7.2012 15Months: BTand RoadFurniture

OGPC+SCcompleted

completed

Road from R&B roadKancharapalem HW to

Alaganipadu.

WBM Gr-II isin progress &

CD Workscompleted.

98%

Page 25 of 93

Page 27: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/PRED/09/

MUTHUKUR/RHB/006

Road from R&B road toPatuvari Kandriga 25.4.11

24.7.20113Months: Earth

Work, PipeCulverts, GSB

24.10.2011 6Months: WBMGrII, GrII, CCPavement and

Shoulders

24.1.2012 9Months: BTand RoadFurniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/RHB/PRED/09/

V.CHALEM/RHB/007

Road from Survepalli-Pudiparthi road to Srikanth

Colony27.04.2011

26.8.20114Months: Earth

Work, PipeCulverts, GSB

26.12.2011 8Months: WBMGrII, GrII and

Shoulders

26.4.2012 12Months: BTand RoadFurniture

OGPC+ SCcompleted completed

providing BT Surface tothe road from R&B road to

Edagali Kandriga

OGPC+ SCcompleted completed

NCRMP/B-W/AP/RHB/PRED/09/Allur

/009

Road from R&B road Alluruto Galidibbalu (via)Chukavani dibba

24.01.2011

23.6.20115Months: Earth

Work, PipeCulverts, GSB

23.11.2011 10Months: WBMGrII, GrII and

Shoulders

23.4.2012 15Months: BTand RoadFurniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

Ring Road to TP Gudur-Salipeta R & B Road via CSPuram and Mandapam Vill. 19.05.2011

18.8.20113Months: Earth

Work, PipeCulverts, GSB

18.11.2011 6Months: WBMGrII,GrII, CC

Pavement andShoulders

18.2.2012 9Months: BTand RoadFurniture

OGPC+ SCcompleted completed

Road from R & B Road C SPuram to Sivaramapuram

OGPC+ SCcompleted completed

RCS

NCRMP/B-W/AP/PRED/09/kota/RCS

/001

Road from R&B road to A.SPURAM

10.05.2011

9.8.20113Months: Earth

Work, PipeCulverts, GSB

9.11.11 6Months: WBMGrII,GrII and

Shoulders

9.2.2012 9Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted completed

Road from GD Road toVavilla Palem

OGPC+ SCcompleted completed

NCRMP/B-W/AP/PRED/09/

MUTHUKUR/RCS/002

Road from R&B Roadkappaladoruvu to bandla

Palem H.wada21.04.2011

20.7.20113Months: Earth

Work, PipeCulverts, GSB

20.10.2011 6Months: WBMGrII,GrII,CC

Pavement andShoulders

20.1.2012 9Months: BT CCroad and Road

Furniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/PRED/09/Chillakur/

RCS/004

Road from KakuvaripalemR&B road to Vellapalem 23.05.2011

22.8.20113Months: Earth

Work, CDWorks, GSB

22.11.2011 6Months: WBMGrII,GrII and

Shoulders

22.2.2012 9Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted completed

Page 26 of 93

Page 28: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/09/

T.P.GUDUR/005

Road from7/2 M.C Road toVenkannapalem

Pattuapalem17.05.2011

16.8.20113Months: EarthWork, PipeCulverts, GSB

16.11.2011 6Months: WBMGrII,GrIIShoulders andCC Pavement

16.2.2012 9Months: BT,CC Pavementand RoadFurniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

Road Connecting R&B Roadthrough Voturu Village in

SPSR Nellore District.21.09.2011

20.1.2012 4Months: Earth

Work, PipeCulverts,

GSB

20.5.2012 4Months: WBM

GrII,GrII ,Shoulders andCC Pavement

20.9.2012 4Months: BT,CC Pavement

and RoadFurniture

GSB. From0.00 to 5.320(Bits), WBMGr-II, Gr-IIIfrom 0.00 to5.320 and

OGPC+SC 0/6to 5/1 is

completed

completed

NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007

Road from Kotha satramR&B to Indrsanagar (via)

Thumalapenta palam,Patharavadu palam,

Ramudu palam, Karaduvaripalam & Sreeramapuram

29.08.2011

28.12.20114Months: Earth

Work, PipeCulverts, GSB

28.4.2012 4Months: WBM

GrII,GrII ,Shoulders andCC Pavement

28.8.2012 4Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/PRED/09/

D.V.SATRAM/RCS/008

Road from R&B road toSullurpeta Mallam to

Berijengalapalli cycloneshelter

09.05.2011

8.8.20113Months: EarthWork, PipeCulverts, GSB

8.11.2011 6Months: WBMGrII, GrIIShoulders andCC Pavement

8.2.2012 9Months: BT,CC Pavementand RoadFurniture

OGPC+ SCcompleted completed

NCRMP/B-W/AP/RCS/PRED/

09/TADA/009

Providing BT road toPedapannamgadu in Tada

Mandal

14.09.2012

14.02.2013(5Months) EarthWork, PipeCulverts, GSB &CC road

13.06.2013 (4Months): WBMGrII, GrIIShoulders

13.09.2013Months) BTand RoadFurniture

GSB work is inprogress 67%

Road from @ 56/8 to C.Kroad to Periyavettu kuppamcyclone shelter

14.02.2013(5Months) EarthWork, PipeCulverts, GSB &CC road

13.06.2013 (4Months): WBMGrII, GrIIShoulders

13.09.2012Months) BTand RoadFurniture

Sub grade is inprogress 9.41%

Page 27 of 93

Page 29: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.0 District wise status of tests conducted by TPQA:

Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of

tests conducted in the field till end of December 2012 are presented.

Summary of QC Tests - Up to 31.01.2013

S.No. District

No. TestsConductedduring the

Month

Total no. of TestsCumulativeTests Done

Total no. of Tests up to31.01.2013

Passed Failed Passed Failed

1 Srikakulam 30 30 0 1505 1499 6

2 Vizianagaram 0 0 0 461 461 0

3 Visakhapatnam 89 89 0 2326 2280 46

4 East Godavari 42 42 0 1170 1170 0

5 West Godavari 0 0 0 349 349 0

6 Krishna 3 3 0 88 88 0

7 Guntur 50 50 0 656 645 11

8 Prakasham 50 50 0 1955 1951 4

9 Nellore 32 32 0 1206 1185 21

Total 296 296 0 9716 9628 88

Page 28 of 93

Page 30: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.0 Details of Quality Control Audit Reports Submitted During this Month:

Package Number Name of Work District

NCRMP/BW/AP/RHB/PRED/09/vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore

NCRMP/B-W/AP/RCS/PRED/08/VETAPALEM/001

Road from NH to Challareddypalem InPrakasam District Prakasam

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.

Road from Pedagollapalem PR Road toBonthagorlapalem Prakasam

NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001

Road from R&B Road Alluru to Yadavapalemin Guntur DT. Guntur

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT Road to Peda Pannam Gadu inTada Mandal of Nellore Dt. Nellore

NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

Providing Road from R&B B.P Kallalu toMatchvanipalem in Visakhapatnam Dt. Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001

Providing B.T to the Road from NH-5 toRamaraidupalem in Visakhapatnam Dt. Visakhapatnam

Page 29 of 93

Page 31: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/BW/AP/RHB/PRED/09/vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of cyclone shelter at Kollipadu inSanthabommali Mandal in Srikakulam Dt. Srikakulam

Final QCR’s submitted in this month

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from Interu ZP road to Rangaraopeta inKrishna Dt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Bhogireddypalli R&B road toRamakhandam in Krishna Dt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Potlapalem ZP road to Potepalli inKrishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from R&B road to B.V.Thota in KrishnaDt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Chinnapuram R&B road toGundupalem in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001

Road connecting R&B road throughGantalammapalem in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from R&B road to Cyclone shelter atChandala in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from Potlapalem Z.P road toChikativanipalem in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

R&B Road at Panchayat office toPulaparthivarithota via Badava of Mogalthuru

Mandal in West Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from R&B road to Pedalanka of NarsapurMandal in West Godavari District. West Godavari

NCRMP/B-W/AP/RHB/ PRED/05/Narasapur/002

R&B road to Indira Nagar (via) Pochammatemple of Narsapur Mandal in West Godavari

Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Road from NH 214 A road to Harjanawada ofkothota of Mogalthuru Mandal in West

Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Road from NH 214 A at Ranga statue centerto Harijanawada of Kalipatnam (E) of

Mogalthuru MandalWest Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from LB Cherla CC road to Chillapalemof LB Cherla of Narsapur Mandal in West

Godavari Dt.West Godavari

Page 30 of 93

Page 32: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Mogaltur Vempa R&B Road at Uchintha kalavaBridge to Gogulamma Harijanapeta of

Mogalthuru Mandal in West Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

From Narsapur Mogaltur R&B road toDayaldaspeta via Venkateshwara SwamyTemple of Mogalthuru Mandal in West

Godavari Dt.

West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuramof Kalla Mandal in West Godavari Dt. West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Mekaladibba of KallaMandal in West Godavari Dt. West Godavari

Page 31 of 93

Page 33: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.0 Statement Showing the Inspections and Site Visits of Districts during the Month of January -2013

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF DECEMBER2012

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Runku inSanthabommali Mandal. 19.01.13,26.01.13 2

2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Road from Deppuru, bhadapalli road to Onkuluru &cyclone shelter. 8.01.13 1

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 8.01.13 1

4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 8.01.13 1

5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 8.01.13 1

6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal. 3.01.13, 19.01.13, 24.01.13 3

7 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004

Construction of High level Bridge acrossBendigedda at km 4/10 of Pundi-Parlkimidi road inSrikakulam Dist.

12.01.13 1

8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 24.01.13 1

9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006

Road from Mabagam R&B road to Dubbakavanipetavia gajapathinagaram. 24.01.13 1

Page 32 of 93

Page 34: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005

Road from R&B road Edullavalasa-Killam to jonnamvia talasamudram 24.01.13 1

11 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 11.01.13 1

12 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 11.01.13 1

13 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from mentada to Dovupeta 11.01.13 1

14 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 11.01.13 1

15 NCRMP/B_W/BR/R&B/01/uppigedda/002 Construction of HLB across uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 3.01.13, 5.01.13, 10.01.13, 24.01.13 4

16 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001

Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.

4.01.13, 10.01.13, 18.01.13,21.01.13, 22.01.13, 26.01.13,

27.01.137

17 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 9.01.13 1

18 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 9.01.13 1

19 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

Road from Borubadra, Malagam road to Kollipaduvia Seepuram, Ghantapeta 9.01.13 1

TOTAL 31

Page 33 of 93

Page 35: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OFDECEMBER 2012

S

NO.PACKAGE NO NAME OF WORK

TPQA INSPECTIONSDURING THIS MONTH

DATES OFVISIT

NO. OFVISITS

1 NCRMP/B-W/ AP/ Br/ R&B/ 02/ Chakaligadda /008

Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) in VizianagaramDistrict.

29.02.2013 1

Total 1

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DURING THIS MONTH OF JANUARY - 2013

SNO

.PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem inRambilli Mandal

03.01.13, 05.01.1308.01.13, 19.01.1322.01.13, 30.01.13

6

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda inNakkapalli Mandal

03.01.13, 09.01.1310.01.13, 17.01.1323.01.13, 30.01.13

6

3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra inNakkapalli Mandal

03.01.13, 17.01.1323.01.13, 30.01.13 4

Page 34 of 93

Page 36: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarrampeta inNakkapalli Mandal 03.01.13, 30.01.13 2

5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 04.01.13, 12.01.13 2

6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Gajapathinagaramin Payakaraopeta Mandal

04.01.13, 09.01.1312.01.13 3

7 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 Road from R&B road to B.P Kallalu toMatchavanipalem 18.01.13 1

8 NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayyadupalem 19.01.13 1

9 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Rajakoduru 19.01.13, 22.01.13 2

10 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 19.01.13 1

11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 B.T to the road from R & B road to Venkayyapalem 19.01.13, 22.01.13 2

12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 11.01.13 1

13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla toChinateenarla 23.01.13 1

14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road toJanakayyapeta 23.01.13 1

15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi toPatimeeda 23.01.13 1

16 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002 B.T to the road from R&B to Mullaparra up to beachend 23.01.13 1

Page 35 of 93

Page 37: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

17 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cycloneshelter . 31.01.13 1

18 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009 Construction of Cyclone shelter at BangarampalemI&II H/O Vakadu. 31.01.13 1

19 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 08.01.13, 19.01.1322.01.13 3

20 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 09.01.13, 17.01.13 2

21 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 09.01.13, 17.01.13 2

22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 09.01.13, 17.01.13 2

23 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Kadapalem 08.01.13 1

24 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Vadapalem 08.01.13 1

25 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 08.01.13 1

26 NCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007 Road from R&B road to Kothapatnam 08.01.13 1

27 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 08.01.13 1

28 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Jalaripeta 11.01.13 1

29 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Mutyalammpalem 11.01.13 1

TOTAL 53

Page 36 of 93

Page 38: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DURING THIS MONTH OF JANUARY 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/ AP/RCS/ PRED/04/ KARAPA/001 Road from approach road to cyclone shelter atadavipudi in e.g.dt. Nil Nil

2 NCRMP/B-W/ AP/RHB/ PRED/04/ KARAPA/001 Road from gurajanapalli to bandulavaripalem Nil Nil

3 NCRMP/B-W/AP/RHB/ PRED/04/ Katrenikona/003 Road from PR road to Dasarivanipeta and to CycloneShelter 16.012.2013 1

4

NCRMP/B-W /AP/RCS/PRED/04/ Thondangi/004

Road from R&B Road to G.Musalayyapeta CS Nil Nil

5 Road from R&B Road to P.Chodipallipeta CS Nil Nil

6 Road from R&B Road to K.Chodipallipeta CS Nil Nil

7 Road from R&B Road to Hukumpeta CS Nil Nil

8 Road from R&B Road to Gaddipeta CS Nil Nil

9 Road from R&B Road to Danavaipeta CS Nil Nil

10

NCRMP/B-W/ AP/MPCS/ PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of ThondangiMandal , E.G.Dt.

03.01.2013, 11.01.2013,15.01.2013 and 31.01.2013 4

11 Cyclone Shelter at Lakshmanudipeta of ThondangiMandal, E.G.Dt.

03.01.2013, 11.01.2013,15.01.2013 and 31.01.2013 4

12 NCRMP/B-W/ AP/RCS/PRED/04/Uppalaguptam/003

Road from R&B Road to Chinaraghavulapeta CycloneShelter NIL NIL

Page 37 of 93

Page 39: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

13 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002

Cyclone Shelter at Pedaraghavulapeta ofUppalaguptam Mandal, E.G.Dt.

04.01.2013, 10.01.2013,12.01.2013, 18.01.2013,22.01.2013, 24.01.2013

and 30.01.2013.

7

TOTAL 16

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF YEAR-II WORKS DURING THIS MONTH JANUARY 2013

SNO

.PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OFVISITS

1. NCRMP/B-W/AP/RCS/PRED/05/Achanta/002 Road from R&B road to Ayodya lanka Marrimulacyclone shelter. 19.01.2013 –

2.NCRMP/B-W/AP/RCS/PRED/05/Kalla/003

Road from R&B road to Modi Cyclone Shelter 10.01.2013 –

3. Road from R&B road to S.C Bose Colony CycloneShleter 10.01.2013 –

4. NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004 Construction of approach road to cyclone shelter inLosari of Bhimavaram Mandal. 02.01.2013 –

5.

NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/005

Road from R&B road to Kothakayalathippa cycloneshelter – 1

6.Road from Narsapur Perupalem R&B road toMandavarithota – 1

7. Road from Mollaparru R & B road to Mollaparru PathaColony – 1

8.Road from K.P Palem (N) Panchayat office toMetturevu Palli palem – 1

Page 38 of 93

Page 40: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.

NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006

R&B road to Chinamynavanilanka – 1

10. P.R road to Ramanujapuram – 1

11. Road from P.R road to Prakasapuram – 1

12. NCRMP/B-W/AP/RHB/PRED/05/Kalla/004 K.G. R&B Road to Mamidipudi of Kalawapudi. 10.01.2013 –

13.NCRMP/B-W/AP/RHB/PRED/05/Bhimavaram/005

Road from Dongapindi R & B Road to Revu(Pallipalem) in Dongapindi of Bhimavaram Mandal. 02.01.2013 –

14. Road from R & B Road to Sarvodhyanagar(Garivelladibba) H/o Losari of Bhimavaram Mandal. 02.01.2013 –

15. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006 Khalipatnam R&B Road to Khalipatnam ferry – 1

16.

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/007

Road from R & B Road at Metturevu to Parasavarimeraka via Kandulapativari meraka – –

17.Road from Narasapur Perupalem R &B Road to

Janakiram Colony in Andevarimeraka of K.P.Palem(S)

– –

18. Road from Narsapur Perupalem R & B road toDondaparthivari meraka – –

19.

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/008

Road from Narsapur PerupalemR & B Road to Melamvaripalem Perupalem(S) – 1

20. Road from Perupalem Mollaparru R & B road viaSattinenivarimeraka to K.D.Pallavapalem – 1

21. Road from Perupalem Dibbalapallipalem R & B roadto Mellapallavapalem – 1

22. Road from Perupalem beach R & B Road toChallavarimeraka via Mucherlavarimeraka – 1

23.

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/009

Road from Perupalem R&B road to Dindla – –

24. Road from Narsapur Perupalem R & B road toNellipallipalem via Ambedkar colony Harijanapeta – –

25. Road from Perupalem R & B Road to Kouruvaripalem – –26. NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010 Road from SP R&B road to Pasaladeevi – 1

Page 39 of 93

Page 41: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

27. LT R&B road to Modi – 1

28. SP R&B road to Gannabathulavari palem ofChamakuripalem – 1

29.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012

Road from R&B road to SC Colony of Pedalanka – 1

30. R&B road to Rajeev Nagar of Darbharevu – 131. SP R&B road to Pedathota of Turputallu – 132. R&B road to Peta of Turputallu – 133. R&B road to Pedathota of Turputallu – 134.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

R&B road to Guttulavarimeraka – 135. Road from R & B Road to Pulaparthivaripalem – 136. R&B road to Pedaedigapalem – 137. R&B road to Evanivarimeraka – 1

38.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014

Road from PR Road to Prakashpuram SC colony ofVemuladeevi(E) – 1

39. Road from PR road to Vemuladeevi (E) colony (Via)Ralla cheruvu of Vemuladeevi (E) – 1

40. Road from PR road to Addalavarimeraka ofVemuladeevi(E) – –

41.NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/001

Sardupalli Palem of Vemuladeevi 23.01.2013 –42. Pedamynavani lanka 23.01.2013 –43.

NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/003Chinamynavani lanka 23.01.2013 –

44. Vemuladeevi East 23.01.2013 –45.

NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002Yetimondi of Perupalem 24.01.2013 –

46. Bellamkondavarimeraka 24.01.2013 –

Total 26

Page 40 of 93

Page 42: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH JANUARY 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/006

Road from China Zinkapalem to Gollamanda via pedaZinkapalem 09.01.13 1

Road from R&B road to Cyclone Shelter at Gollamanda 09.01.13 1

Road from ZP Road to Cyclone shelter at Natchugunta 09.01.13 1

Road from Krishna river to Elechetla Dibba Cycloneshelter 09.01.13 1

2 NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/009 Road from R&B Road Dananjaya Colony toKrishnapuram 09.01.13 1

TOTAL 5

Page 41 of 93

Page 43: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF JANUARY- 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1

NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002

Road from Ganapavaram R&B Road toPedamarpuvaripalem.

7.1.2013, 8.1.203,17.1.2013, 26.1.2013,27.1.2013, 30.1.2013,

31.1.2013.

7

2 Road from R&B road to chinapuluguvaripalem 5.1.2013, 30.1.2013,31.1.2013. 3

3 Road from Ganapavaram PR Road toBonthagorlapalem. 5.1.2013 1

4 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010 Reconstruction of HLB @ km 5/2 of Bapatla -Suryalanka road across perali drain in Guntur District. 8.1.2013, 10.1.2013. 2

5NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001

Road from R & B Road to Hanumanth Nagar. 31.1.2013. 1

6 Road from R & B Road to Adarshnagar. 31.1.2013. 1

7 NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001 Road from R & B Road Allur to Yadavapalem 4.1.2013, 5.1.2013,7.1.2013, 8.1.2013. 4

TOTAL 19

Page 42 of 93

Page 44: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF JANUARY-13

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/APMPCS/PRED/08/NG Padu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 04.01.2013 1

2 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

Construction of High level Bridge at Km 16/10 ofNaguluppalapadu – Kanaparthi road in Prakasam District 03.01.2013 1

3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 05.01.2013, 10.01.2013, 15.01.2013

29.01.2013, 30.01.2013, 31.01.2013 6

4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne

05.01.2013, 10.01.2013, 15.01.201326.01.2013, 28.01.2013, 29.01.2013

31.01.20137

5 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from R&B road to Binginapalli Harijanawada CycloneShelter 10.01.2013 1

6 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 10.01.2013, 15.01.2013, 23.01.2013

25.01.2013, 28.01.2013 5

7 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from Pakala ZP Road to Aulavaripalem Cycloneshelter 10.01.2013 1

8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli 10.01.2013 1

9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B road to Narravaripalem 10.01.2013 1

10 NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07 Road from MC Road to Subbarayudu Satram 11.01.2013 1

11 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu 10.01.2013, 23.01.2013

24.01.2013, 28.01.2013 4

12 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem 10.01.2013 1

13 NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001

Chakicherla cyclone shelter in Ulavapadu mandalprakasam district 11.01.2013 1

TOTAL 31

Page 43 of 93

Page 45: Monthly Progress Report January 2013

MONTHLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF JANUARY 2013

SLNO Package Number Name of work

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007

Providing BT Surface to the road from R&B road toEdagali kandriga 01.01.2013, 02.01.2013 2

2 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007

Road from Suvepalli-Pudiparthi road to SrikanthColony 01.01.2013, 02.01.2013 2

3 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/006 Road from R&B road to Patuvarikandriga 01.01.2013 1

4 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/002

Road from R&B Road kappaladoruvu to bandla palemH.wada 01.01.2013 1

5 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 11.01.2013 1

6 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

Road from R&B road Kancharlapalam HW toAlaganipadu.

09.01.2013, 11.01.2013,21.01.2013, 24.01.2013 4

7 NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

Road Connecting R&B Road through Voturu Villagein SPSR Nellore District 21.01.2013 1

8 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt. 09.01.2013, 31.01.2013 2

9 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter 09.01.2013, 31.01.2013 2

10 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Village 16.01.2013 1

11 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012 Road from R & B Road C S Puram to Sivaramapuram 16.01.2013 1

Total 18

Page 44 of 93

Page 46: Monthly Progress Report January 2013

In Joint Venture

Photo Presentation by Third

Party Quality Audit

Consultant of AP NCRMP

Works during January 2013

Page 45 of 93

Page 47: Monthly Progress Report January 2013

Page 46 of 93

Page 48: Monthly Progress Report January 2013

Page 47 of 93

Page 49: Monthly Progress Report January 2013

Page 48 of 93

Page 50: Monthly Progress Report January 2013

Page 49 of 93

Page 51: Monthly Progress Report January 2013

Page 50 of 93

Page 52: Monthly Progress Report January 2013

Page 51 of 93

Page 53: Monthly Progress Report January 2013

Providing B.T to the Road from NH-5 to Ramaraidupalem

Measurement verification

Measurement verification Measurement verification

Page 52 of 93

Page 54: Monthly Progress Report January 2013

Providing B.T to the Road from NH-5 to Ramaraidupalem

Measurement verification

Site View

Site View

Page 53 of 93

Page 55: Monthly Progress Report January 2013

Page 54 of 93

Page 56: Monthly Progress Report January 2013

Page 55 of 93

Page 57: Monthly Progress Report January 2013

Page 56 of 93

Page 58: Monthly Progress Report January 2013

Page 57 of 93

Page 59: Monthly Progress Report January 2013

Page 58 of 93

Page 60: Monthly Progress Report January 2013

Page 59 of 93

Page 61: Monthly Progress Report January 2013

Page 60 of 93

Page 62: Monthly Progress Report January 2013

Page 61 of 93

Page 63: Monthly Progress Report January 2013

Page 62 of 93

Page 64: Monthly Progress Report January 2013

Page 63 of 93

Page 65: Monthly Progress Report January 2013

Name Board Site View

Site View Measurement verification

Page 64 of 93

Page 66: Monthly Progress Report January 2013

Name Board Site View

Cc road completed

Measurement verification Measurement verification

Page 65 of 93

Page 67: Monthly Progress Report January 2013

Name Board

Site view

Site view

Site view

Page 66 of 93

Page 68: Monthly Progress Report January 2013

Village name board fixed

Measurement verification Site View

Name Board

Page 67 of 93

Page 69: Monthly Progress Report January 2013

Name Board

Measurement verification

Name Board

Site view

Page 68 of 93

Page 70: Monthly Progress Report January 2013

Village board Name board

Site View Site View

Page 69 of 93

Page 71: Monthly Progress Report January 2013

Site View

Name board Site View

Site View

Page 70 of 93

Page 72: Monthly Progress Report January 2013

Site View

Km stone and Name board

Measurement verification

Name board

Page 71 of 93

Page 73: Monthly Progress Report January 2013

Page 72 of 93

Page 74: Monthly Progress Report January 2013

Page 73 of 93

Page 75: Monthly Progress Report January 2013

Page 74 of 93

Page 76: Monthly Progress Report January 2013

Page 75 of 93

Page 77: Monthly Progress Report January 2013

Page 76 of 93

Page 78: Monthly Progress Report January 2013

Page 77 of 93

Page 79: Monthly Progress Report January 2013

Page 78 of 93

Page 80: Monthly Progress Report January 2013

Page 79 of 93

Page 81: Monthly Progress Report January 2013

Page 80 of 93

Page 82: Monthly Progress Report January 2013

Page 81 of 93

Page 83: Monthly Progress Report January 2013

NCRMP TPQA inspection of Road from R&B road

Kancharapalem HW to Alaganipadu of Nellore Dt.

On 20.12.12 –Collection of WBM Gr-II aggregates

Gradation for WBM Gr-II aggregates

Wearing coat on vented road dam is in progress

Gradation for WBM Gr-II aggregates

Page 82 of 93

Page 84: Monthly Progress Report January 2013

Thickness checking for WBM Gr-II layer

Volumetric analysis for WBM Gr-II layer NCRMP TPQA inspection of Road from R&B road

Kancharapalem HW to Alaganipadu of Nellore Dt.

On 20.12.12 –Wearing coat is in progress

Thickness checking for WBM Gr-II layer and

volumetric analysis

Page 83 of 93

Page 85: Monthly Progress Report January 2013

NCRMP TPQA inspection of Road from R&B road

Kancharapalem HW to Alaganipadu of Nellore Dt.

On 29.12.12 Volumetric analysis for WBM Gr-II

layer

Collection of gravel for shoulder , WBM Gr-II layer

Wearing coat curing by ponding. Both side of Road Dam,Guard stones.

Page 84 of 93

Page 86: Monthly Progress Report January 2013

NCRMP TPQA inspection of Road from

R&BroadKancharapalem HW to Alaganipadu of Nellore Dt

o29.12.12-Carriage way width checking

Carriage way width checking at curve location

View of WBMGr-II layer View of WBMGr-II layer

Page 85 of 93

Page 87: Monthly Progress Report January 2013

NCRMP TPQA inspection of Providing BT road to Peda Pannam Gadu in Tada Mandal of Nellore Dt on 18.12.2012-Collection of WBM Gr-II aggregates

Gradation for WBM Gr-II aggregates

Gradation for WBM Gr-II aggregates Gradation for WBM Gr-II aggregates

Page 86 of 93

Page 88: Monthly Progress Report January 2013

Gradation for WBM Gr-II aggregates Gradation for WBM Gr-II aggregates

Gradation for WBM Gr-II aggregates View of CC road

Page 87 of 93

Page 89: Monthly Progress Report January 2013

Gradation for WBM Gr-II aggregates Camber checking for WBM Gr-II layer

Watering for WBM Gr-II layer CC road thickness checking

Page 88 of 93

Page 90: Monthly Progress Report January 2013

View of CC road

Checking of formation width

CC road width checking

Checking of carriage way width

Page 89 of 93

Page 91: Monthly Progress Report January 2013

NCRMP TPQA inspection of Road from R&B

road Kancharapalem HW to Alaganipadu on

11.01.13-Collection of WBM Gr-III aggregates

Gradation for WBM Gr-III aggregates

Gradation for WBM Gr-III aggregates Gradation for WBM Gr-III aggregates

Page 90 of 93

Page 92: Monthly Progress Report January 2013

Gradation for WBM Gr-III aggregates

Gradation for WBM Gr-III aggregates

Gradation for WBM Gr-III aggregates

Gradation for WBM Gr-III aggregates

Page 91 of 93

Page 93: Monthly Progress Report January 2013

NCRMP TPQA inspection of Road from R&B

road Kancharapalem HW to Alaganipadu on

21.01.13- WBM Gr-III layer thickness checking

WBM Gr-III layer thickness checking

Volumetric analysis for WBM Gr-III layer Camber checking for WBM Gr-IIII layer

Page 92 of 93

Page 94: Monthly Progress Report January 2013

WBM Gr-III layer thickness checking WBM Gr-III layer thickness checking

WBM Gr-III layer undulations checking View of WBM Gr-III layer

Page 93 of 93