monthly progress report - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime...

5
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08 MONTHLY PROGRESS REPORT Proposed Apartments Building at No.410/115, Bauddhaloka Mawatha Colombo - 07 Month/ Year - January/ 2017 Document Number - PLR-MPR-BD2-2017-01

Upload: doanhuong

Post on 31-Aug-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MONTHLY PROGRESS REPORT - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 2. work done

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

MONTHLY PROGRESS REPORT Proposed Apartments Building at No.410/115, Bauddhaloka Mawatha

Colombo - 07

Month/ Year - January/ 2017

Document Number - PLR-MPR-BD2-2017-01

Page 2: MONTHLY PROGRESS REPORT - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 2. work done

MONTHLY PROGRESS REPORT January 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

1. PROJECT DETAILS

Project Name & Address : PROPOSED APARTMENTS BUILDING AT NO 410/115,

BAUDDHALOKA MAWATHA, COLOMBO - 07 Commenced Date : August 2016 Project Duration : 540 days

Consultants

Project Architect : Architect. Anil Kumarage Structural Eng. : Eng. Laksiri Cooray MEP Engineer : Eng. K. P. A. Weerasinghe

Contactors Civil Contractor : Nikko Construction (PVT) Ltd

PROPOSED APARTMENTS BUILDING AT NO 410/115, BAUDDHALOKA2, COLOMBO - 07

Page 3: MONTHLY PROGRESS REPORT - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 2. work done

MONTHLY PROGRESS REPORT January 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

2. WORK DONE DURING THE MONTH OF JANUARY

1. GFL Column Concreting from Grid 3 to 6 -100%

2. Concreting of Lift wall Up to MFL slab Level -100%

3. Concreting of 1st flight on Stair Case 01 -100%

4. Concreting of 1st flight on Stair Case 02 -100%

5. Brick work Along Grid A up to MFL slab Level -100%

6. Back filling under Ground Floor Slab -100%

7. From work on MFL Slab -50%

8. Re Bar Work on MFL Slab and Beams -20%

9. External wall along Grid A Plastering up to MFL Slab level -75%

Page 4: MONTHLY PROGRESS REPORT - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 2. work done

MONTHLY PROGRESS REPORT January 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

3. SITE PHOTOS

Figure 1 - Lift wall Concreting Figure 2 –Stair Case Concreting

Figure 3– Brick work along Grid A Figure 4 – Back Filling under Ground floor

Page 5: MONTHLY PROGRESS REPORT - primeresidencies.lk 2.pdf · monthly progress report january 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 2. work done

MONTHLY PROGRESS REPORT January 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

Figure 5-MFL Slab form work Figure 6-Rafter Beams Concreting