PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
MONTHLY PROGRESS REPORT Proposed Apartments Building at No.410/115, Bauddhaloka Mawatha
Colombo - 07
Month/ Year - January/ 2017
Document Number - PLR-MPR-BD2-2017-01
MONTHLY PROGRESS REPORT January 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
1. PROJECT DETAILS
Project Name & Address : PROPOSED APARTMENTS BUILDING AT NO 410/115,
BAUDDHALOKA MAWATHA, COLOMBO - 07 Commenced Date : August 2016 Project Duration : 540 days
Consultants
Project Architect : Architect. Anil Kumarage Structural Eng. : Eng. Laksiri Cooray MEP Engineer : Eng. K. P. A. Weerasinghe
Contactors Civil Contractor : Nikko Construction (PVT) Ltd
PROPOSED APARTMENTS BUILDING AT NO 410/115, BAUDDHALOKA2, COLOMBO - 07
MONTHLY PROGRESS REPORT January 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
2. WORK DONE DURING THE MONTH OF JANUARY
1. GFL Column Concreting from Grid 3 to 6 -100%
2. Concreting of Lift wall Up to MFL slab Level -100%
3. Concreting of 1st flight on Stair Case 01 -100%
4. Concreting of 1st flight on Stair Case 02 -100%
5. Brick work Along Grid A up to MFL slab Level -100%
6. Back filling under Ground Floor Slab -100%
7. From work on MFL Slab -50%
8. Re Bar Work on MFL Slab and Beams -20%
9. External wall along Grid A Plastering up to MFL Slab level -75%
MONTHLY PROGRESS REPORT January 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
3. SITE PHOTOS
Figure 1 - Lift wall Concreting Figure 2 –Stair Case Concreting
Figure 3– Brick work along Grid A Figure 4 – Back Filling under Ground floor
MONTHLY PROGRESS REPORT January 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
Figure 5-MFL Slab form work Figure 6-Rafter Beams Concreting