monitoring report-goyal mg gases

Upload: sriram

Post on 06-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    1/12

    14.85 MW Grid connected Wind farm project

    in Tamil Nadu, India by M/s Goyal MG

    Gases Private Limited

    MONITORING REPORT

    From 25/03/2004 to 10/04/2007

    Version 01

    Dated 14-06-2007

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    2/12

    1. Title of the project activity:

    14.85 MW Grid connected Wind farm project, at various locations in Tamil Nadu, by M/s

    Goyal MG Gases Private Limited

    Version: III

    Date: 15/01/2007

    Date of registration of project: 29th April 2007

    UNFCCC registration reference number: 0992

    2. Introduction:

    The proposed self-financed project activity is an initiative by Goyal Group towards clean

    electricity generation using wind energy resources in the state of Tamil Nadu. The project activity

    leads to the installation of 66 Wind Electric Generators (WEGs) of individual capacity 225 kW at

    various locations in Tamil Nadu totaling to an installed capacity of 14.85 MW. Out of the total 66

    WEGs, 47 WEGs are owned by the group companies Goyal MG gases Pvt. Ltd. and the rest 19

    are owned by Morgan Ventures Ltd.

    Goyal group is a renowned group since 1973 in the field of Industrial Gases and other allied

    services. Since last 10 years, it has grown rapidly with its diversities. To fulfil the companys

    commitment towards better environment, they have set up a series of wind farms in Tamil Nadu

    in the name of Kanyakumari wind farm, Cochin wind farm, Salem wind farm and Erode wind

    farm.

    Names of Investor of WEGs:

    M/s Goyal MG Gases Private Limited

    M/s Morgan Ventures Limited

    The project activity has sought a 10 year fixed crediting period starting from 25/03/2004.

    3. Reference:

    Appendix B of the simplified M&P for small scale CDM project activities (UNFCCC, 2003b)

    Project Type: I Renewable energy project

    Project Category: I D Renewable electricity generation for a grid

    Version: 10 (23rd December, 2006)

    The installed capacity of the project is 14.85 MW, which is less than the limiting capacity of 15

    MW and is thus eligible to use small-scale simplified methodologies. Further, the project activity

    is generation of electricity for sale to state electricity utility utilizing the regional grid system

    using wind potential. Hence, the type and category of the project activity matches with I.D. as

    specified in Appendix B of the indicative simplified baseline and monitoring methodologies for

    small-scale CDM project activities.

    Project Design Document: 14.85 MW Grid connected Wind farm project, at various locations

    in Tamil Nadu, by M/s Goyal MG Gases Private Limited

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    3/12

    4. Definitions in the report:

    CDM Clean Development Mechanism

    PDD Project Design Document

    GHG Green House Gas / Gases

    IPCC Intergovernmental Panel on Climate Change

    SEB State Electricity BoardTNEB Tamil Nadu Electricity Board

    JMR Joint Meter Reading

    5. General description of the project:

    5.1 Project Activity:

    The candidate CDM project will generate electricity from WEGs in the Goyal MG Gases Pvt. Ltd.

    Wind Park. The project activity has been essentially conceived for the sale of generated

    electricity to state electricity utility (Tamil Nadu Electricity Board). The wind power will be

    wheeled utilizing the regional grid (Southern Region Electricity Grid), and will be supplied to the

    local consumers drawing electricity from the grid. Since wind based electricity generation is

    GHG emissions free, the electrical power generated will save the anthropogenic Green House Gas

    (GHG) emissions generated by the fossil fuel based thermal power stations comprising coal,

    diesel, furnace oil and gas.

    The project activity started in March 2004 and was estimated to generate approximately 30

    million kWh per year, contributing an estimated reduction of 279630 tCO2e over the ten year

    crediting period of the project from 2004-2014. This reduction is the result of displacement of

    fossil fuel fired power plants that would otherwise have delivered the electricity to Southern

    Region Grid in the absence of the project activity.

    5.2 Technical description of the project:

    Location of project activity: The project activity is spread across three locations in Tamil Nadu

    with the following geographical positioning:

    Coimbatore: 11 N (Latitude) and 77 E (Longitude)

    Erode: 11 20 N (Latitude) and 77 46 E (Longitude)

    Tirunelveli: 8 44 N (Latitude) and 77 44 E (Longitude)

    Technology employed by the project activity:

    The project activity envisages installation of small sized WEGs of individual capacity 225 kW

    supplied by NEPC. The salient features of the technology are furnished below.

    Details Type 225/40 KW

    Over all Data

    Cut in windspeed

    Cut out Windspeed

    Rated windspeed

    Survival Windspeed

    Tip Speed

    Approx. 4m/s

    Approx. 25m/s

    15m/s

    60m/s at 2 sec gust

    58/39 m/s

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    4/12

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    5/12

    The project activity leads to the promotion of small sized Wind Electric Generators (WEGs) into

    the region, demonstrating the success of wind based renewable energy generation, which is fed

    into the nearest sub-station (part of the Southern Regional Grid), thus increasing energy

    availability and improving quality of power under the service area of the substation. Hence, the

    project leads to technological well being.

    No technology transfer from other countries is involved in this project activity.

    6. Monitoring methodology & Plan:

    The project activity meets the eligibility criteria to use simplified modalities and procedure for

    small-scale CDM project activities as set out in paragraph 6 (c) of decision 17/CP.7.

    Data to be monitored during project activity (As per D3 of the PDD of the registered project activity)

    ID

    number

    Data

    type

    Data

    variable

    Data

    unit

    Measured

    (m),

    calculated

    (c) or

    estimated

    (e)

    Recording

    frequency

    Proportion of

    data to be

    monitored

    How will

    the data be

    archived?

    (electronic/

    paper)

    For how

    long is

    archived

    data to be

    kept?

    Comment

    1 et

    Electricity

    supplied

    o theegional

    electricity

    grid

    Electricity kWh M Monthly 100% Electronic

    & Paper

    Two

    years

    beyond

    Creditingperiod

    7. Quality Control (QC) and Quality Assurance (QA)

    QA and QC procedures undertaken during project activity

    ID number Uncertainty level of

    data

    (High/Medium/Low)

    Explain QA/QC procedures planned for these data, or

    why such procedures are not necessary.

    1 Low The data can be very accurately measured. The meters

    installed on sub stations (grid interconnection point)

    will be used to measure mentioned variables on a

    continuous basis. Every month these meter readings

    will be recorded by plant personnel, these records will

    be archived for crosschecking yearly figures. The

    meters at the sub station will be two-way meters and

    will be in custody of State Electricity Utility. SEB

    officials will take the readings in these meters and the

    same reading may be used to determine the net power

    supplied to the grid and determine the extent of

    mitigation of GHG over a period of time.

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    6/12

    7.1 Calibration / Maintenance of Measuring and Analytical Equipments

    Training

    All incoming new incumbents are given formal class room type structured training at windfarm

    sites. Various topics covered are as follows:

    - Import knowledge about technical details of various components and parts of windmills- Teach the importance and functional details of each component of the windmill.

    - Impart training regarding normal starting procedure, normal stopping procedure, emergency

    stopping procedure and procedure for handling windmill and its switchyard, emergency etc.

    - Impart knowledge about mechanical, electrical and electronics / instrumentation related

    preventive and predictive maintenance schedule, procedure for undertaking routine

    maintenance and keeping up to date maintenance records, thereto.

    - Procedure for diagnostic approach for analyzing defects and the procedure for undertaking

    break down repairs.

    - Keeping close watch and control reactive power import / export from/to TNEB grid.

    Commensurate with the wind speed and wind power generated there from.

    - Monitoring and record keeping of windfarm performance parameters through Centralized

    Monitoring System (CMS)- Imbibe safety procedures.

    - Ensuring study of technical literature of various parts and components of the windfarms.

    - Preparation of daily generation report for the wind energy generated, record defects or

    reasons for low generation, if any instituting corrective measures to improve generation,

    where feasible.

    - Procedure for drawal and use of spares, consumables and other materials for repairs and

    maintenance of windmills.- Imparting training on various associated aspects for smooth operation & maintenance of

    windmills so as to ensure minimum down time and enhance their MTBF.

    Energy Meter

    The measurement of electricity is carried out as per the prevailing guidelines of the stateelectricity regulatory commission, which mandates implementation of 0.5 accuracy class meters

    at grid interconnection point for measurement of generated electricity. The transmission loss

    incurred till the metering point is to be absorbed by the project proponent and the payment is

    made on the basis of electricity fed into the grid.

    - The primary recording of the electricity fed to the state utility grid will be carried out jointly

    at the incoming feeder of the state electricity utility (TNEB). Machines for sale to utility will

    be connected to the feeder.

    - The joint measurement will be carried out once in a month in presence of both parties (the

    developers representative and officials of the state power utility). Both parties will sign the

    recorded reading.

    - In exceptional circumstances of failure of metering system, immediate replacement is carried

    on 24 * 7 basis.- The meter is calibrated every 6 months as per the TNEB statutory laid down periodicity.

    - As per TNEB laid down procedure, the defective main energy meter is always replaced by

    the TNEB accredited representative in presence of the Companys personnel by a spare

    energy meter.

    - The defective energy meter is taken away by the accredited TNEB representative to their

    laboratory for retrieval of recorded data and issue of certificate for the last recorded readings

    thereto.

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    7/12

    - The measurement is thus always on the lower side, and is therefore conservative with respect

    to generation of electricity as well as GHG abetment.

    Other Maintenance and upkeep practices include:

    - Regular calibration of the energy meters

    - Calibration of other monitoring equipment, in all the wind farms.

    7.2 Environmental Impact

    1. The electricity from wind electricity generator has no negative environmental impacts.

    2. As per the Schedule 1 of Ministry of Environment and Forests (Government of India)

    notification dated January 27, 1994, - 30 activities are required to undertake environmental

    impact assessment studies. The details of these activities are available at:

    http://envfor.nic.in/divisions/iass/notif/eia.htm

    3. The proposed project doesnt fall under the list of activities requiring EIA as it will not

    involve any negative environmental impacts, because the WEGs installed for generation of

    power use wind (cleanest possible source of renewable energy).

    8. GHG Calculations

    8.1 Project Activity Emissions: Nil

    Emissions by sources of GHGs due to the project activity within the project boundary are zero

    since wind power is a GHG emission free source of energy.

    8.2 Leakage: Nil

    This is not applicable as the renewable energy technology used is not equipment transferred

    from another activity. Therefore, as per the simplified procedures for SSC project activities, no

    leakage calculation is required.

    There is no alternate fuel which can generate electricity from the installed plant and machinery

    in absence of wind.

    8.3 Baseline Emissions

    The wind power project uses the Combined Margin methodology as suggested in the Appendix

    B of the simplified modalities and procedures for small-scale CDM project activities.

    The total baseline emissions BEy (tCO2/yr) = EGy * EFy

    Where

    BEy = Baseline emissions in year y (tCO2).

    EGy (MWh/yr) = Electricity generated by the project in year y;

    EFy

    = Combined margin emissions factor (Baseline emission factor) for the year y

    (tCO2/MWh).

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    8/12

    The emission factor EFy of the Western Region Grid is a fixed value over the projects crediting

    period and is calculated as the weighted average of the Operating Margin emission factor

    (EFOM, y) and the Build Margin emission factor (EFBM,y):

    EFy = wOM EFOM,y + wBM .EFBM,y

    Where the weights wOM and wBM, are 75% and 25%, and EFOM, y and EFBM, y are the OperatingMargin and Build Margin emission factors respectively calculated in the following paragraph.

    The emission factor EFy is estimated to be0.9321 tCO2/MWh.

    The Operating Margin is the weighted average emissions of all generating sources serving the

    Northern Grid excluding hydro, geothermal, wind, low-cost biomass, nuclear and solar

    generation. It is derived from the following equation:

    EFOM, simple, y = Fi, j, y COEFi, jGENj, y

    where,Fi, j, y is the amount of fuel i (in a mass or volume unit) consumed by relevant power sources j

    in year(s) y,

    j refers to the power sources delivering electricity to the grid, not including low-operating cost

    and must-run power plants, and including imports to the grid.

    COEFi,j y is the CO2 emission coefficient of fuel i (tCO2 / mass or volume unit of the fuel),taking into account the carbon content of the fuels used by relevant power sources j and the

    percent oxidation of the fuel in year(s) y, and

    GEN j, y is the electricity (MWh) delivered to the grid by source j.

    The CO2 emission coefficient COEFi is obtained as

    COEFi = NCVi * EFCO2, i * OXIDiwhere:

    NCVi is the net calorific value (energy content) per mass or volume unit of a fuel i,

    OXIDi is the oxidation factor of the fuel (see page 1.29 in the 1996 Revised IPCC Guidelines

    for default values),

    EFCO2,i is the CO2 emission factor per unit of energy of the fuel i.

    The EFOM,Y is estimated to be 1.00349 tCO2/MWh (based on three years average).

    The Build Margin emission factor (EFBM,y) is calculated as the generation weighted average

    emission factor (tCO2/MWh) of a sample of power plants m, as follows:

    EFBM,y = Fi, m, y .COEFi, mGENm,y

    WhereFi, m,y = quantity of fuel i used in plant m (kt/yr) in year y

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    9/12

    COEFi, m = carbon emissions factor for fuel i in plant m (tCO2/kt), taking into account the

    carbon content of the fuels by power sources and the percent oxidation of the fuel

    GENm, y = annual generation from plant j (MWh/yr) in year y

    The EFBM,y is estimated as 0.7179 tCO2/MWh (with sample group m constituting most recent

    capacity additions to the grid comprising 20% of the system generation).

    The baseline emissions are estimated as the product of the electricity generated by the projectactivity and the Emission factor of the regional electricity grid as calculated above.

    Name of Item GEN

    Description Electricity Quantity Electricity fed into the southern grid

    Crediting Period 25/03/2004 24/03/2014

    Method of monitoring Measured using energy meter

    Recording frequency Continuous

    Reporting frequency Monthly (Jointly by SEB and representative of the investor)

    Background data Joint meter reading available at the site

    Archiving mode Electronic & paper

    The project started on 25/03/2004 and the crediting period starts from 25/03/2004.

    Report has been prepared by:

    SenergyGlobal Private Limited

    9th Floor, Eros Corporate Tower

    Nehru Place

    New Delhi 110 019

    Monthly Emission Reductions:

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    10/12

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    11/12

  • 8/3/2019 Monitoring Report-Goyal MG Gases

    12/12

    Thus, total emission reductions in 3 years, starting from 25th March 2004 to 10th April 2007, are:

    Total 1 + Total 2 = 21205.3 + 32832.7

    = 53925.7 kWh

    Yearly Emission Reductions

    S.No Crediting periodEmissionsreductions

    1 25/03/2004 - 10/04/2005 8035.5

    2 11/04/2005 - 10/04/2006 22272.8

    3 11/04/2006 -10/04/2007 23617.4

    TOTAL 53925.7