monitoring report-goyal mg gases
TRANSCRIPT
-
8/3/2019 Monitoring Report-Goyal MG Gases
1/12
14.85 MW Grid connected Wind farm project
in Tamil Nadu, India by M/s Goyal MG
Gases Private Limited
MONITORING REPORT
From 25/03/2004 to 10/04/2007
Version 01
Dated 14-06-2007
-
8/3/2019 Monitoring Report-Goyal MG Gases
2/12
1. Title of the project activity:
14.85 MW Grid connected Wind farm project, at various locations in Tamil Nadu, by M/s
Goyal MG Gases Private Limited
Version: III
Date: 15/01/2007
Date of registration of project: 29th April 2007
UNFCCC registration reference number: 0992
2. Introduction:
The proposed self-financed project activity is an initiative by Goyal Group towards clean
electricity generation using wind energy resources in the state of Tamil Nadu. The project activity
leads to the installation of 66 Wind Electric Generators (WEGs) of individual capacity 225 kW at
various locations in Tamil Nadu totaling to an installed capacity of 14.85 MW. Out of the total 66
WEGs, 47 WEGs are owned by the group companies Goyal MG gases Pvt. Ltd. and the rest 19
are owned by Morgan Ventures Ltd.
Goyal group is a renowned group since 1973 in the field of Industrial Gases and other allied
services. Since last 10 years, it has grown rapidly with its diversities. To fulfil the companys
commitment towards better environment, they have set up a series of wind farms in Tamil Nadu
in the name of Kanyakumari wind farm, Cochin wind farm, Salem wind farm and Erode wind
farm.
Names of Investor of WEGs:
M/s Goyal MG Gases Private Limited
M/s Morgan Ventures Limited
The project activity has sought a 10 year fixed crediting period starting from 25/03/2004.
3. Reference:
Appendix B of the simplified M&P for small scale CDM project activities (UNFCCC, 2003b)
Project Type: I Renewable energy project
Project Category: I D Renewable electricity generation for a grid
Version: 10 (23rd December, 2006)
The installed capacity of the project is 14.85 MW, which is less than the limiting capacity of 15
MW and is thus eligible to use small-scale simplified methodologies. Further, the project activity
is generation of electricity for sale to state electricity utility utilizing the regional grid system
using wind potential. Hence, the type and category of the project activity matches with I.D. as
specified in Appendix B of the indicative simplified baseline and monitoring methodologies for
small-scale CDM project activities.
Project Design Document: 14.85 MW Grid connected Wind farm project, at various locations
in Tamil Nadu, by M/s Goyal MG Gases Private Limited
-
8/3/2019 Monitoring Report-Goyal MG Gases
3/12
4. Definitions in the report:
CDM Clean Development Mechanism
PDD Project Design Document
GHG Green House Gas / Gases
IPCC Intergovernmental Panel on Climate Change
SEB State Electricity BoardTNEB Tamil Nadu Electricity Board
JMR Joint Meter Reading
5. General description of the project:
5.1 Project Activity:
The candidate CDM project will generate electricity from WEGs in the Goyal MG Gases Pvt. Ltd.
Wind Park. The project activity has been essentially conceived for the sale of generated
electricity to state electricity utility (Tamil Nadu Electricity Board). The wind power will be
wheeled utilizing the regional grid (Southern Region Electricity Grid), and will be supplied to the
local consumers drawing electricity from the grid. Since wind based electricity generation is
GHG emissions free, the electrical power generated will save the anthropogenic Green House Gas
(GHG) emissions generated by the fossil fuel based thermal power stations comprising coal,
diesel, furnace oil and gas.
The project activity started in March 2004 and was estimated to generate approximately 30
million kWh per year, contributing an estimated reduction of 279630 tCO2e over the ten year
crediting period of the project from 2004-2014. This reduction is the result of displacement of
fossil fuel fired power plants that would otherwise have delivered the electricity to Southern
Region Grid in the absence of the project activity.
5.2 Technical description of the project:
Location of project activity: The project activity is spread across three locations in Tamil Nadu
with the following geographical positioning:
Coimbatore: 11 N (Latitude) and 77 E (Longitude)
Erode: 11 20 N (Latitude) and 77 46 E (Longitude)
Tirunelveli: 8 44 N (Latitude) and 77 44 E (Longitude)
Technology employed by the project activity:
The project activity envisages installation of small sized WEGs of individual capacity 225 kW
supplied by NEPC. The salient features of the technology are furnished below.
Details Type 225/40 KW
Over all Data
Cut in windspeed
Cut out Windspeed
Rated windspeed
Survival Windspeed
Tip Speed
Approx. 4m/s
Approx. 25m/s
15m/s
60m/s at 2 sec gust
58/39 m/s
-
8/3/2019 Monitoring Report-Goyal MG Gases
4/12
-
8/3/2019 Monitoring Report-Goyal MG Gases
5/12
The project activity leads to the promotion of small sized Wind Electric Generators (WEGs) into
the region, demonstrating the success of wind based renewable energy generation, which is fed
into the nearest sub-station (part of the Southern Regional Grid), thus increasing energy
availability and improving quality of power under the service area of the substation. Hence, the
project leads to technological well being.
No technology transfer from other countries is involved in this project activity.
6. Monitoring methodology & Plan:
The project activity meets the eligibility criteria to use simplified modalities and procedure for
small-scale CDM project activities as set out in paragraph 6 (c) of decision 17/CP.7.
Data to be monitored during project activity (As per D3 of the PDD of the registered project activity)
ID
number
Data
type
Data
variable
Data
unit
Measured
(m),
calculated
(c) or
estimated
(e)
Recording
frequency
Proportion of
data to be
monitored
How will
the data be
archived?
(electronic/
paper)
For how
long is
archived
data to be
kept?
Comment
1 et
Electricity
supplied
o theegional
electricity
grid
Electricity kWh M Monthly 100% Electronic
& Paper
Two
years
beyond
Creditingperiod
7. Quality Control (QC) and Quality Assurance (QA)
QA and QC procedures undertaken during project activity
ID number Uncertainty level of
data
(High/Medium/Low)
Explain QA/QC procedures planned for these data, or
why such procedures are not necessary.
1 Low The data can be very accurately measured. The meters
installed on sub stations (grid interconnection point)
will be used to measure mentioned variables on a
continuous basis. Every month these meter readings
will be recorded by plant personnel, these records will
be archived for crosschecking yearly figures. The
meters at the sub station will be two-way meters and
will be in custody of State Electricity Utility. SEB
officials will take the readings in these meters and the
same reading may be used to determine the net power
supplied to the grid and determine the extent of
mitigation of GHG over a period of time.
-
8/3/2019 Monitoring Report-Goyal MG Gases
6/12
7.1 Calibration / Maintenance of Measuring and Analytical Equipments
Training
All incoming new incumbents are given formal class room type structured training at windfarm
sites. Various topics covered are as follows:
- Import knowledge about technical details of various components and parts of windmills- Teach the importance and functional details of each component of the windmill.
- Impart training regarding normal starting procedure, normal stopping procedure, emergency
stopping procedure and procedure for handling windmill and its switchyard, emergency etc.
- Impart knowledge about mechanical, electrical and electronics / instrumentation related
preventive and predictive maintenance schedule, procedure for undertaking routine
maintenance and keeping up to date maintenance records, thereto.
- Procedure for diagnostic approach for analyzing defects and the procedure for undertaking
break down repairs.
- Keeping close watch and control reactive power import / export from/to TNEB grid.
Commensurate with the wind speed and wind power generated there from.
- Monitoring and record keeping of windfarm performance parameters through Centralized
Monitoring System (CMS)- Imbibe safety procedures.
- Ensuring study of technical literature of various parts and components of the windfarms.
- Preparation of daily generation report for the wind energy generated, record defects or
reasons for low generation, if any instituting corrective measures to improve generation,
where feasible.
- Procedure for drawal and use of spares, consumables and other materials for repairs and
maintenance of windmills.- Imparting training on various associated aspects for smooth operation & maintenance of
windmills so as to ensure minimum down time and enhance their MTBF.
Energy Meter
The measurement of electricity is carried out as per the prevailing guidelines of the stateelectricity regulatory commission, which mandates implementation of 0.5 accuracy class meters
at grid interconnection point for measurement of generated electricity. The transmission loss
incurred till the metering point is to be absorbed by the project proponent and the payment is
made on the basis of electricity fed into the grid.
- The primary recording of the electricity fed to the state utility grid will be carried out jointly
at the incoming feeder of the state electricity utility (TNEB). Machines for sale to utility will
be connected to the feeder.
- The joint measurement will be carried out once in a month in presence of both parties (the
developers representative and officials of the state power utility). Both parties will sign the
recorded reading.
- In exceptional circumstances of failure of metering system, immediate replacement is carried
on 24 * 7 basis.- The meter is calibrated every 6 months as per the TNEB statutory laid down periodicity.
- As per TNEB laid down procedure, the defective main energy meter is always replaced by
the TNEB accredited representative in presence of the Companys personnel by a spare
energy meter.
- The defective energy meter is taken away by the accredited TNEB representative to their
laboratory for retrieval of recorded data and issue of certificate for the last recorded readings
thereto.
-
8/3/2019 Monitoring Report-Goyal MG Gases
7/12
- The measurement is thus always on the lower side, and is therefore conservative with respect
to generation of electricity as well as GHG abetment.
Other Maintenance and upkeep practices include:
- Regular calibration of the energy meters
- Calibration of other monitoring equipment, in all the wind farms.
7.2 Environmental Impact
1. The electricity from wind electricity generator has no negative environmental impacts.
2. As per the Schedule 1 of Ministry of Environment and Forests (Government of India)
notification dated January 27, 1994, - 30 activities are required to undertake environmental
impact assessment studies. The details of these activities are available at:
http://envfor.nic.in/divisions/iass/notif/eia.htm
3. The proposed project doesnt fall under the list of activities requiring EIA as it will not
involve any negative environmental impacts, because the WEGs installed for generation of
power use wind (cleanest possible source of renewable energy).
8. GHG Calculations
8.1 Project Activity Emissions: Nil
Emissions by sources of GHGs due to the project activity within the project boundary are zero
since wind power is a GHG emission free source of energy.
8.2 Leakage: Nil
This is not applicable as the renewable energy technology used is not equipment transferred
from another activity. Therefore, as per the simplified procedures for SSC project activities, no
leakage calculation is required.
There is no alternate fuel which can generate electricity from the installed plant and machinery
in absence of wind.
8.3 Baseline Emissions
The wind power project uses the Combined Margin methodology as suggested in the Appendix
B of the simplified modalities and procedures for small-scale CDM project activities.
The total baseline emissions BEy (tCO2/yr) = EGy * EFy
Where
BEy = Baseline emissions in year y (tCO2).
EGy (MWh/yr) = Electricity generated by the project in year y;
EFy
= Combined margin emissions factor (Baseline emission factor) for the year y
(tCO2/MWh).
-
8/3/2019 Monitoring Report-Goyal MG Gases
8/12
The emission factor EFy of the Western Region Grid is a fixed value over the projects crediting
period and is calculated as the weighted average of the Operating Margin emission factor
(EFOM, y) and the Build Margin emission factor (EFBM,y):
EFy = wOM EFOM,y + wBM .EFBM,y
Where the weights wOM and wBM, are 75% and 25%, and EFOM, y and EFBM, y are the OperatingMargin and Build Margin emission factors respectively calculated in the following paragraph.
The emission factor EFy is estimated to be0.9321 tCO2/MWh.
The Operating Margin is the weighted average emissions of all generating sources serving the
Northern Grid excluding hydro, geothermal, wind, low-cost biomass, nuclear and solar
generation. It is derived from the following equation:
EFOM, simple, y = Fi, j, y COEFi, jGENj, y
where,Fi, j, y is the amount of fuel i (in a mass or volume unit) consumed by relevant power sources j
in year(s) y,
j refers to the power sources delivering electricity to the grid, not including low-operating cost
and must-run power plants, and including imports to the grid.
COEFi,j y is the CO2 emission coefficient of fuel i (tCO2 / mass or volume unit of the fuel),taking into account the carbon content of the fuels used by relevant power sources j and the
percent oxidation of the fuel in year(s) y, and
GEN j, y is the electricity (MWh) delivered to the grid by source j.
The CO2 emission coefficient COEFi is obtained as
COEFi = NCVi * EFCO2, i * OXIDiwhere:
NCVi is the net calorific value (energy content) per mass or volume unit of a fuel i,
OXIDi is the oxidation factor of the fuel (see page 1.29 in the 1996 Revised IPCC Guidelines
for default values),
EFCO2,i is the CO2 emission factor per unit of energy of the fuel i.
The EFOM,Y is estimated to be 1.00349 tCO2/MWh (based on three years average).
The Build Margin emission factor (EFBM,y) is calculated as the generation weighted average
emission factor (tCO2/MWh) of a sample of power plants m, as follows:
EFBM,y = Fi, m, y .COEFi, mGENm,y
WhereFi, m,y = quantity of fuel i used in plant m (kt/yr) in year y
-
8/3/2019 Monitoring Report-Goyal MG Gases
9/12
COEFi, m = carbon emissions factor for fuel i in plant m (tCO2/kt), taking into account the
carbon content of the fuels by power sources and the percent oxidation of the fuel
GENm, y = annual generation from plant j (MWh/yr) in year y
The EFBM,y is estimated as 0.7179 tCO2/MWh (with sample group m constituting most recent
capacity additions to the grid comprising 20% of the system generation).
The baseline emissions are estimated as the product of the electricity generated by the projectactivity and the Emission factor of the regional electricity grid as calculated above.
Name of Item GEN
Description Electricity Quantity Electricity fed into the southern grid
Crediting Period 25/03/2004 24/03/2014
Method of monitoring Measured using energy meter
Recording frequency Continuous
Reporting frequency Monthly (Jointly by SEB and representative of the investor)
Background data Joint meter reading available at the site
Archiving mode Electronic & paper
The project started on 25/03/2004 and the crediting period starts from 25/03/2004.
Report has been prepared by:
SenergyGlobal Private Limited
9th Floor, Eros Corporate Tower
Nehru Place
New Delhi 110 019
Monthly Emission Reductions:
-
8/3/2019 Monitoring Report-Goyal MG Gases
10/12
-
8/3/2019 Monitoring Report-Goyal MG Gases
11/12
-
8/3/2019 Monitoring Report-Goyal MG Gases
12/12
Thus, total emission reductions in 3 years, starting from 25th March 2004 to 10th April 2007, are:
Total 1 + Total 2 = 21205.3 + 32832.7
= 53925.7 kWh
Yearly Emission Reductions
S.No Crediting periodEmissionsreductions
1 25/03/2004 - 10/04/2005 8035.5
2 11/04/2005 - 10/04/2006 22272.8
3 11/04/2006 -10/04/2007 23617.4
TOTAL 53925.7