module ii soil stabilization (ss) and sediment control (sc) bmps module ii soil stabilization (ss)...

63
Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Modul e Topic 0 Overview I Introduction II Soil Stabilization (SS) and Sediment Control (SC) BMPs III Tracking, Wind Erosion, and Construction Site Management BMPs IV Incorporation of Construction Site BMPs into the Design Process V Final Wrap-Up

Upload: gwendolyn-short

Post on 28-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Module IISoil Stabilization (SS)

and Sediment Control (SC) BMPs

Module IISoil Stabilization (SS)

and Sediment Control (SC) BMPs

Module

Topic

0 Overview

I Introduction

IISoil Stabilization (SS) and Sediment Control (SC) BMPs

IIITracking, Wind Erosion, and Construction Site Management BMPs

IVIncorporation of Construction Site BMPs into the Design Process

V Final Wrap-Up

Page 2: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Module II ObjectivesModule II Objectives

Upon completion, the student will be able to

• Understand potential erosion and sediment problems

• Understand water pollution control strategies behind the selection of soil stabilization (SS) and sediment control (SC) practices

• Select BMPs using the Caltrans-developed process (PS&E level detail)

• Identify Standard Special Provisions (SSPs) for selected bid line items 2

Page 3: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Construction Activities

and Storm Water

Construction Activities

and Storm WaterConstruction projects tend to

• Disrupt the existing area by exposing soils and changing drainage patterns

• Store and use materials that contain or are themselves pollutants

• Require ancillary activities that are potential sources of pollutants

3

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 4: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

4

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 5: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

5

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 6: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

• Clear and grub• Roadway clearing• Roadway/structure excavation• Channel excavation• Utility trenching• Dirt hauling• Grading• Soil/aggregate base stockpiling• Irrigation and planting

What potential storm water pollutants can these activities

yield?

Typical Construction Activities

Typical Construction Activities

6

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 7: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Sediment

Potential Construction Site Pollutants

Potential Construction Site Pollutants

The most common pollutant washed from construction sites, sediment clogs the gills of fish, blocks light transmission, and increases water temperature, harming aquatic life and disturbing the food chain.

7

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 8: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

• Failure to install BMPs

• Inappropriate BMP selection

• Failure to use a combination of BMPs

• Improper BMP installation

• Inadequate maintenance during construction

Problems with Soil Stabilization and Sediment Control BMP

Implementation

Problems with Soil Stabilization and Sediment Control BMP

Implementation

8

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 9: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Since sediment is the major pollutant from construction sites, the timely installation of BMPs is imperative.

Failure to Install BMPsFailure to Install BMPs

9

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 10: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

There are limitations for each Soil Stabilization and Sediment Control BMP. Selecting the appropriate BMP for each application ensures success.

Inappropriate BMP Selection

Inappropriate BMP Selection

10

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 11: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

The lack of soil stabilization resulted in severe slope erosion. A combination of BMPs is required.

Failure to Usea Combination of BMPs

Failure to Usea Combination of BMPs

11

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 12: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Types of ErosionTypes of Erosion

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

12

Page 13: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Water Pollution Control Strategies during

Construction

Water Pollution Control Strategies during

Construction• Prevent storm water contact with disturbed soil areas (DSAs)

• Protect DSAs from erosion• Minimize sediment in storm water

before discharge• Control discharges of sediment from

other sources• Prevent non–storm water discharges• Prevent storm water contact with

other potential construction site pollutants

13

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 14: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Prevent Storm Water Contact with Disturbed Soil Areas

Prevent Storm Water Contact with Disturbed Soil Areas

The BMP used to protect

DSAs from rainfall is this one:

• Scheduling

14

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 15: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Protect Disturbed Soil Areas from Splash and Sheet

Erosion

Protect Disturbed Soil Areas from Splash and Sheet

Erosion This is the BMP used to protect DSAs from these types of erosion:

• Temporary soil stabilization

15

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 16: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Protect Disturbed Soil Areas from Rill ErosionProtect Disturbed Soil Areas from Rill Erosion

BMPs to protect DSAs from rill erosion are slope interrupter devices:

• Gravel Bag Berms• Fiber Rolls

16

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 17: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

BMPs used to protect DSAs from concentrated storm water flows are as follows:• Check Dams• Earth Berms and Dikes• Slope Drains• Outlet Protection Devices

Protect Disturbed Soil Areas from Gully and Channel Erosion

Protect Disturbed Soil Areas from Gully and Channel Erosion

17

These BMPs are important for storm water run-on controls from off-site sources.

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 18: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Minimize Sediment in Storm Water before Discharge

Minimize Sediment in Storm Water before Discharge

Linear Sediment Barriers• Silt Fence• Sandbag Barrier• Straw Bale Barrier• Fiber Rolls• Gravel Bag Berm

Sediment Removal Devices• Storm Drain Inlet

Protection• Sediment/Desilting

Basins

1818

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 19: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

Example Project

Roadway WideningCentral Expressway• Widen from two to four

lanes• Elevate roadway• Construct wall and bridge

structures• Grade embankments

Purpose• Assess impacts and

problem conditions• Select and deploy BMPs• Identify SSPs for separate

bid line items

19

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

PS&E PhaseSee Exercise Page 1

Page 20: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Embankment SlopeAccess Road

Additional Right of WayBridge Structure

Retaining WallDrainage System

20

Page 21: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Project Information

Project Information

Construction Activities• Clearing and

grubbing• Structure

excavation• Roadway

excavation• Roadway grading• Cuts and fills

21

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Example

Project

Page 22: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

More Project Information

More Project Information

Construction Activities• 27 acres of DSA• Four construction

stages• Slopes from flat to

1:1.5• Slope lengths to 125

ft• Discharges to an

urban channel – Adobe Creek an ESA (not on 303[d] list)

Designate appropriate soil stabilization and sediment control BMPs

22

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Example

Project

Page 23: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

What’s the first thing

we want to do

What’s the first thing

we want to do

Example Project

23

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 24: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Has Caltrans developed any aids to assist the Designer with selecting appropriate Soil Stabilization and Sediment Control BMPs?

24

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Example

Project

Page 25: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

Construction Site BMP

Consideration Form

Construction Site BMP

Consideration Form

25

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 1

Page 26: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Checklist CS-1, Part 1

Checklist CS-1, Part 1

27.1 ac (11 ha)

7.4 ac (3 ha)

17.3 ac (7 ha)

2.5 ac (1 ha)

12.4 ac (5 ha)

3

Example Project

26

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 2

Page 27: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

27

(Refer to Table 2-1 of theConstruction Site Best Management Practices

Manual.)

(Refer to Table 2-2, and2-3 of the Construction Site Best Management

Practices Manual

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Checklist CS-1, Part

1Checklist CS-1, Part

1

Page 28: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

28

Example Project

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 12

Page 29: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

29

Example Project

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 13

Page 30: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

30

NON-ACTIVE DISTURBED SOIL AREAS

SOIL STABILIZATION (5)

SEDIMENT BARRIER

DESILTING BASIN

(5)

Example Project

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

4

NON-RAINY

4

See ReferenceMaterial TabPage 14

Page 31: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

ACTIVE DISTURBED SOIL AREAS (3)

SOIL STABILIZATION

SEDIMENT BARRIER

DESILTING BASIN (2)RAINY

NON-RAINY

31

Example Project

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

4

4

See Reference Material TabPage 15

Page 32: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Combination of Soil Stabilization and Sediment Controls and

Barriers

Combination of Soil Stabilization and Sediment Controls and

BarriersSeason BMP Non-Active DSAs Active DSAs

RainyRainyRainyRainy

October 1 - October 1 - May 1May 1October 1 - October 1 - May 1May 1

Non-Non-RainyRainyNon-Non-RainyRainy

May 2 - May 2 - September 30September 30May 2 - May 2 - September 30September 30

Soil Soil StabilizationStabilization

Soil Soil StabilizationStabilization

Sediment Sediment BarrierBarrier

Sediment Sediment BarrierBarrier

Desilting Desilting BasinBasin

Desilting Desilting BasinBasin

Soil Soil StabilizationStabilization

Soil Soil StabilizationStabilization

Sediment Sediment BarrierBarrier

Sediment Sediment BarrierBarrier

Desilting Desilting BasinBasin

Desilting Desilting BasinBasin

Slope LengthsSlope Lengths All AllSlope InclinationsSlope Inclinations All AllSlope LengthsSlope Lengths All AllSlope InclinationsSlope Inclinations All All

Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1

None *None *None *None *

NoneNoneNoneNone

NoneNoneNoneNone

NoneNoneNoneNone

NoneNoneNoneNone

NoneNoneNoneNone

NoneNoneNoneNoneNoneNoneNoneNone

Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1

Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1Slope Lengths > 10’Slope Lengths > 10’Slope Inclinations > 2:1Slope Inclinations > 2:1

* Except prior to predicted rain (Footnote 3)

Page 33: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

33

4

Checklist CS-1, Part 1

Checklist CS-1, Part 1

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 34: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

34

Checklist CS-1, Part 1

Checklist CS-1, Part 1

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 35: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

The following contract items of work, as shown on the plans or specified elsewhere in these special provisions shall be incorporated into the SWPPP and identified as permanent water pollution control practices: 

A. _____________________B. _____________________C. _____________________

The Contractor shall construct permanent water pollution control items identified in the SWPPP as specified in "Order of Work" of these special provisions. The Contractor shall maintain the permanent water pollution control items in the locations and condition shown on the plans throughout the duration of the project.

07-345 – Water Pollution Control07-345 – Water Pollution Control

Example Project

35

Standard Special

Provisions

Standard Special

Provisions

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 36: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Rainy Season Implementation Requirements

The Contractor shall provide soil stabilization and sediment control practices during the rainy season between……..

During the defined rainy season, the active disturbed soil area of the project shall not be more than 5 acres. The Engineer may approve, on a case-by-case basis, expansions of the active disturbed soil area limit.

07-345 – Water Pollution Control07-345 – Water Pollution Control

Example Project

36

Standard Special

Provisions

Standard Special

Provisions

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 37: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Scheduling Type BMPs• 07-485 Move In/Move Out (Temp. Erosion

Control)• 20-020 Move In/Move Out (Erosion Control)• 05-020 Order of Work (refs 07-345, 07-446, S5-

760)

Example Project

37

Standard Special

Provisions

Standard Special

Provisions

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Preservation of Existing Vegetation Type BMPs• 07-446 Temporary Fence (Type ESA)

See Reference Material TabPage 18

Page 38: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

38

Page 39: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

39

Checklist CS-1, Part 1

Checklist CS-1, Part 1

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 40: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Do all soil stabilization methods work the same?

• 07-371 Temporary Soil Binder• 07-380 Temporary Mulch• 07-381 Temporary Hydraulic Mulch

(Bonded Fiber Matrix)• 07-382 Temporary Hydraulic Mulch

(Polymer Stabilized Fiber Matrix)• 07-390 Temporary Erosion Control

Blanket• 07-395 Temporary Cover

Example Project

40

Disturbed Soil Area (DSA) Protection BMPs

Disturbed Soil Area (DSA) Protection BMPs

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 18

Page 41: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Temporary Stabilization

Selection Criteria Matrix

Temporary Stabilization

Selection Criteria Matrix

TEMPORARY SOIL STABILIZATION CONTROL CRITERIA

CLASS TYPE Ante

cede

nt M

oist

ure

Avai

labi

lity

Ease

of C

lean

-Up

Inst

alle

d Co

st P

er H

a

EC E

ffect

ivene

ss (%

)

Degr

adab

ility

Leng

th o

f Dry

ing

Tim

e(h

rs)

Tim

e to

Effe

ctive

ness

(day

s)

Long

evity

Mod

e of

App

licat

ion

Resid

ual I

mpa

ct

Nativ

e

Runo

ff Ef

fect

Wat

er Q

uality

Impa

ct

CATEGORY: STANDARD BIODEGRADABLE MULCHES (SBM)Straw Mulch Wheat Straw D S H $5,200 90-95 B 0 1 M L/M M + M

Rice Straw D S H $5,200 90-95 B 0 1 M L/M M + LWood Fiber Mulch Wood Fiber D S H $2,200 50-60 B 0-4 1 M H L + MRecycled Paper MulchCellulose Fiber D S H $2,100 50-60 B 0-4 1 S H L + LBonded Fiber Matrix Biodegradable D S H $13,600 90-95 B 12-18 1 M H M + HCATEGORY: ROLLED EROSION CONTROL PRODUCTS (RECP)Biodegradable Jute Mesh D S H $16,000 65-70 B 1 M L M + UNK

Curled Wood Fiber D S H $26,000 85-90 P/B 1 M L M + LStraw D S H $22,000 85-90 P/B 1 M L M + HWood Fiber D S H $22,000 85-90 P/B 1 M L M + LCoconut Fiber D S H $32,000 90-95 P/B 1 L L M + LCoconut Fiber Mesh D S H $77,000 85-90 B 1 L L M + UNKStraw Coconut Fiber D S H $27,000 90-95 P/B 1 L L M + M

Non-Biodegradable Plastic Netting D M H $5,000 <50 P 1 L L H + UNKPlastic Mesh D M H $8,000 75-80 P 1 L L H + UNKSynthetic Fiber with Netting D M H $86,000 90-95 P 1 L L H + UNKBonded Synthetic Fibers D M H $121,000 90-95 P 1 L L H + UNKCombination with Biodegradable D M H $79,000 85-90 P 1 L L H + UNK

CATEGORY: TEMPORARY SEEDING (TS)High-Density Ornamentals S-M H $1000 - $4000 50-60 28 M-L H L-M N/E + UNK

Turf species S H $900 50-60 28 L H M-H N/E + UNKBunch grasses S-M H $750 - $3200 50-60 28 L H L-M N + UNK

Fast-Growing Annual S H $900 - $1,600 50-60 28 L H L-H N/E + UNKPerennial S H $800 - $2000 50-60 28 L H M N/E + UNK

Non-Competing Native S-M H $700 - $4000 50-60 28 L H L-M N + UNKNon-Native S-M H $1000 - $1200 50-60 28 L H L-H E + UNK

Sterile Cereal Grain S H $1,200 50-60 28 L H L E + UNKCATEGORY: IMPERVIOUS COVERS (IC)Plastic Rolled Plastic Sheeting S $17,000 100 P 1 M L H - UNK

Geotextile (Woven) S $14,800 90-95 P 1 M L H - UNKCATEGORY: HYDRAULIC SOIL STABILIZERS (HSS)(PBS) Plant Material Guar D S H $1,000 80-85 B 12-18 S B L 0/+ M/LBased- Short Lived Psyllium P S H $1,000 25-35 B 12-18 M B L 0 L/H

Starches D S H $1,000 25-30 B 9-12 S H L 0 L(PBL) Plant MaterialBased- Long Lived

Pitch/ Rosin Emulsion D S M $3,000 60-75 B 19-24 M B M - H

(PEB) Polymeric Acrylic polymers and copolymers D S M $3,000 35-70 P/C 19-24 L B M +/- L/MEmulsion Blends Methacrylates and acrylates D M M $1,000 35-40 P/C 12-18 S W L 0/+ L

Sodium acrylates and acrylamides D M M $1,000 20-70 P/C 12-18 S H L +/- L/MPolyacrylamide D M M $1,000 55-65 P/C 4-8 M H L 0/+ LHydro-colloid polymers D M H $1,000 25-40 P/C 0-4 M H L 0/+ L/M

(PRB) Petroleum/Resin-Based Emulsions

Emulsified Petroleum Resin D M L $3,000 10-50 P/C 0-4 M B M 0/- H

(CBB) CementitiousBased Binders

Gypsum D S M $2,000 75-85 P/C 4-8

Sam

e as

Len

gth

of D

ryin

g Ti

me.

M H L - M/H

= not applicable for category, class or typeUNK = unknown

A variety of soil stabilization BMPs are compared using several selection criteria. These include installed cost, longevity of effectiveness, availability, mode of application, and water quality impact.

41

Table C-2 can be found in Appendix C of the PPDG.

See Reference Material TabPage 16

Page 42: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Specify Soil Stabilization Type

Protect DSAs from splash and sheet erosion by applying soil stabilization BMPs

42

Adobe Creek

Page 43: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

What’s next?What’s next?

Is there any help

out there?

Is there any help

out there? 43

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Example

Project

Page 44: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

44

Checklist CS-1, Part 1

Checklist CS-1, Part 1

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 45: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

45

Checklist CS-1, Part 1

Checklist CS-1, Part 1

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 46: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Slope Interrupter Type BMPs

• 07-420 Temporary Fiber Roll

• 07-470 Temporary Gravel Bag Berm

Example Project

46

Slope Interrupter and Channelized

Flow BMPs

Slope Interrupter and Channelized

Flow BMPs

Channelized Flow Type BMPs• 07-390 Temporary Erosion Control Blanket• 07-415 Temporary Check Dam• SS-9 Earth Dikes/Swales and Ditches• SS-10 Outlet Protection/Velocity Dissipation

Devices• SS-11 Slope Drains

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 47: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Apply appropriate devices to create slope breaks

Disturbed Soil Area (DSA) Protection by Slope Interrupter Devices

47

Page 48: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

48

Protect DSAs from concentrated flows by applying• Dikes and berms• Slope drains• Check dams

DSA Protection by Controlling Concentrated Flows

Page 49: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

We’ve done what we can to keep sediment in its place . . . Are we done selecting appropriate Construction Site BMPs for the erosion process?

49

Page 50: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

No!!! We need an effective combination of soil stabilization and sediment control measures.

50

Let’s select the appropriate sediment controls for our example project

Page 51: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Okay, where should the prudent

Designer start?

Okay, where should the prudent

Designer start?

51

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs Example

Project

Page 52: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Construction Site BMP

Consideration Form

Construction Site BMP

Consideration Form

Example Project

52

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 1

Page 53: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

53

Checklist CS-1, Part 2

Checklist CS-1, Part 2

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Ref TabPage 5

Page 54: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

54

Checklist CS-1, Part 2

Checklist CS-1, Part 2

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 55: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Example Project

55

(Refer to Tables 2-1, 2-2, and 2-3 of the Construction Site Best Management Practices Manual for rainfall area requirements.)

Checklist CS-1, Part 2

Checklist CS-1, Part 2

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 56: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Sediment Control BMPs

Sediment Control BMPs

Example Project

56

Linear Barrier (Perimeter/Run-off Controls)

• 07-420 Temporary Fiber Roll

• 07-430 Temporary Silt Fence

• 07-460 Temporary Straw Bale Barrier

• 07-420 Temporary Gravel Bag Berm

• 07-XXX Temporary Sand Bag Barrier

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

See Reference Material TabPage 18

Page 57: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

More Sediment Control BMPs

More Sediment Control BMPs

Example Project

57

Storm Drain Inlet Protection BMPs

• 07-490 Temporary Drain Inlet Protection

Perimeter/Run-On Controls• SS-9 Earth Dikes/Swales and

Ditches• SC-5 Fiber Roll• SC-6 Gravel Bag Berm• SC-8 Sandbag Barrier• SC-9 Straw Bale Barrier

Potential Erosion and Sediment Problems

Water Pollution Control Strategies

Selecting Appropriate SS & SC BMPs

Page 58: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Perimeter Controls – Run-off Control

Consider the trapping ability of• Linear sediment barriers• Perimeter controls

Perimeter Controls – Run-off Control

Consider the trapping ability of• Linear sediment barriers• Perimeter controls

58

Page 59: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Perimeter Control – Run-on Controls

Route storm water around or through the construction site

59

Page 60: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Storm Drain Inlets

• Identify existing drain inlets• Identify proposed drain inlets• Protect drain inlets

60

Page 61: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Module II SummaryModule II Summary

We have just covered the following topics:

• The potential erosion and sediment problems on construction sites

• The water pollution control strategies behind the selection of soil stabilization and sediment control practices

• The selection of appropriate soil stabilization and sediment control BMPs using the Caltrans-developed process

• Identifying SSPs that will be included in the PS&E process

61

Page 62: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Questions

62

Page 63: Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs ModuleTopic 0Overview

Can you believe it? A few more questions

Can you believe it? A few more questions

Permanent Erosion Control (e.g. Erosion Control (Type D)) is not intended to be used as a Construction Site BMP?

63

Name a few sediment barriers (as intended in Tables 2-2 & 2-3).

What are the Water Pollution Control Strategies for sediment?