module 1 - 7 point form 106

Upload: pz

Post on 02-Mar-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Module 1 - 7 Point Form 106

    1/106

    Project Management Module 1

    1.0 Introduction ......................................................................................................... 1

    1.1.2 Projects and other production systems .......................................................... 1

    1.1.3 Characteristics of a project ........................................................................... 1

    1.2. What is Project Management? ............................................................................ 2

    1.2.3 Basic Project Management Structures........................................................... 2

    1.2.3.1 Internal Project Management ................................................................. 2

    1.3.2 External Project Management .......................................................................... 3

    1.3 Characteristics of Project Management ............................................................... 3

    1.3.2 Multiple Objectives ....................................................................................... 3

    1.3.3 International Co-Operation and Standards ................................................... 3

    1.3.4 Multi Industry ............................................................................................... 3

    1.3.5 Generic Benchmarks ..................................................................................... 3

    1.3.6 Specific Provisions ........................................................................................ 41.3.7 Project Life Cycle ......................................................................................... 4

    1.4 Potential Benefits and Challenges of Project Management .................................. 4

    1.4.2 Potential Benefits .......................................................................................... 4

    1.4.3 Potential Challenges ..................................................................................... 4

    1.0 Introduction

    1.1.2 Projects and other production systems Production systems can be classified into three broad categories

    o Mass production e.g. cars

    o Batch production e.g. chemicals

    o Project (non-repetitive) production e.g. IT

    Mass production is capitally intensive, highly mechanistic & little

    management intervention once system running satisfactorily

    Batch production unlikely to be continual high demand, typically organised

    around functional groupings

    Project one off change e.g. improving batch or mass production efficiency

    Programme may contain many projects e.g. customer service improvement

    programme

    1.1.3 Characteristics of a project

    Single, definable purpose, product or result

    Usually has defined constraints or targets

    Uses skills & talents from multiple professions and organisations

    It is unique, unfamiliar and temporary

    It is part of a process to achieve a goal

  • 7/26/2019 Module 1 - 7 Point Form 106

    2/106

    It is part of an interlinked process

    It is generally of secondary importance to the company, exceptions are pure

    R&D

    It is relatively complex

    Skills required include:

    o

    Financial awarenesso Marketing appreciation

    o Technical knowledge

    o Planning skills

    o Strategic Awareness

    o Quality Management

    1.2. What is Project Management? It is about achieving time, cost and quality targets, within the general

    context of overall strategic and tactical client requirements, by using

    project resources Cost vs. Time vs. Quality, pick two

    Industrial Projects have become more complex and hence so has project

    management

    1.2.3 Basic Project Management Structures

    1.2.3.1 Internal Project Management

    Most common form, project team operates within the firm

    Most companies are organised around functional groupso Advantages specialisation

    o Disadvantages compartmentalised and rigid

    Project teams can operate across these functional groups

    Project team members then have project and functional responsibilities

    Characteristics

    o Single designated person (PM) acts independently and outside formal

    functional authority structure

    o PM has equal authority to functional managers over shared resources

    o PM acts as single leader

    o Projects normally require several functional specialists to work

    together

    o

    PM has to negotiate with functional heads for resourceso People can originate from any level with the organisation

    o Project structures generally require the assistance of standard support

    functions such as HR and IT

  • 7/26/2019 Module 1 - 7 Point Form 106

    3/106

    1.3.2 External Project Management

    External PM is appointed on a consultancy basis and acts as external agent on

    behalf of client, has external resources for project group

    Characteristics

    o External system is more flexible than the internal system

    o Communication has to be across organisational boundary, this may be

    a problem

    o Team allegiance is lower

    o PM has direct authority of his team, functional structure of firm does

    not matter

    o Greater requirement for risk transfer and contractual control

    o No built in knowledge of firm

    1.3 Characteristics of Project Management

    1.3.2 Multiple Objectives Typically these objectives fall into the categories of cost, quality and time

    Cost Quality curve shows how quality improves as cost improves (usually).

    Where you want to be on a curve can depend on factors like:

    o Market price of goods

    o Guaranties and warranties in place

    o Cost of replacement

    o True cost of defective workmanship

    Project Management is concerned with ensuring the project success criteria aremet within the changing constraints of the time,cost,quality continuum

    1.3.3 International Co-Operation and Standards

    PMs code of practice and body of knowledge are based on international rather

    than national practice, i.e. a project manager in one country should be able to

    practice his art in another

    The international body is the International Project Management Association(IPMA)

    1.3.4 Multi Industry

    PM not specific to one industry

    1.3.5 Generic Benchmarks

    There are standards that are not industry specific

    o British BS6079

    o International ISO10006

    and standards that are:

    o Prince2: controlled environment industries & government

  • 7/26/2019 Module 1 - 7 Point Form 106

    4/106

    1.3.6 Specific Provisions

    Traditionally PMs were selected from functional specialists within anorganisation

    Modern concept of project management includes the professional project

    manager

    1.3.7 Project Life Cycle

    Traditionally consultants have only advised on 1 or 2 sections of an overall

    project this leads to problems of lack of co-ordination

    Project managers now give advice to clients on all stages of the project

    Life cycles include:o Inception the basic proposal for work

    o Feasibility establish the validity of the proposal from all persepctives

    o Prototype

    o

    Full Design Development once protoype has been adjustedo Tendering and contractual arrangements can be a mixture of in house

    and external

    o Manufacturing

    o Commisionning all aspects of switching the system on

    o Operation actively used for the purpose for which it was designed

    o Decommisionning process by which it is switched off

    o Removal & Recycling

    1.4 Potential Benefits and Challenges of Project

    Management

    1.4.2 Potential Benefits

    Increased concentration on a specific objective

    More efficient use of resources

    Accountability

    Healthy competition between functional and project units

    Reduced disruption of functional operations

    Enhanced visibility of strategy implementation

    Improved team spirit and innovation

    Improved management skills

    1.4.3 Potential Challenges

    Key staff taken away from functional units

    Competition for resources

    Conflicting orders

    Powerful functional manager can deprive project of resources

  • 7/26/2019 Module 1 - 7 Point Form 106

    5/106

    Project sponsor is necessary go between for project manager and functionalmanager

    Staff need to be flexible

    Project staff may find it difficult to re-adjust to functional units

  • 7/26/2019 Module 1 - 7 Point Form 106

    6/106

    Module 2 Individual and Team issues

    2.2 The Project Manager ........................................................................................... 7

    2.2.2 Selecting the Project Manager ...................................................................... 7

    2.2.2.2 The concept of the PM ............................................................................ 7

    2.2.2.3 Central Position of the PM ..................................................................... 7

    2.2.2.4 Role of the PM ....................................................................................... 82.2.2.5 Selecting the Project Manager ............................................................... 9

    2.2.3 Some Essential PM requirements .................................................................. 9

    2.2.3.1 Introduction ........................................................................................... 9

    2.2.3.2 Planning ................................................................................................ 9

    2.2.3.3 Authorising .......................................................................................... 10

    2.2.3.4. Team organising ................................................................................. 10

    2.2.3.5 Controlling .......................................................................................... 11

    2.2.3.6 Directing .............................................................................................. 11

    2.2.3.7 Team Building ...................................................................................... 12

    2.2.3.8 Leadership ........................................................................................... 12

    2.2.3.9 Lifecycle Leadership ............................................................................ 13

    2.3 Project Team ..................................................................................................... 13

    2.3.2 Project teams within functional organisations ......................................... 13

    2.3.3 Team multi-disciplinary and heterogeneity Issues ....................................... 14

    2.3.4. Group and team processes ......................................................................... 14

    2.3.5 Project team performance ........................................................................... 14

    2.4 Project Team Staffing Profile and Operation ..................................................... 15

    2.4.2 Project Team Staffing ................................................................................. 15

    2.4.3 Project Team Profile ................................................................................... 15

    2.4.3.1 Project Team Mix ................................................................................. 15

    2.4.3.2 Uniqueness of project team .................................................................. 15

    2.4.4 Project Team Operation .............................................................................. 16

    2.5 Project Team Evaluation ................................................................................... 16

    2.5.2 Project Life Cycles ...................................................................................... 16

    2.5.3 Project Change control and management ................................................... 16

    2.5.4 Project Team evaluation ............................................................................. 16

    2.5.5. Groupthink ................................................................................................ 17

    2.6 Project team motivation ..................................................................................... 17

    2.6.2 McGregor and Maslow ............................................................................... 17

    2.6.3 Equity Theory and Expectancy Theory ........................................................ 17

    2.6.3.1 Equity Theory ....................................................................................... 172.6.3.2 Expectancy Theory ............................................................................... 18

    2.7 Project Team Communications .......................................................................... 18

    2.7.2 Project Communication .............................................................................. 18

    2.7.3 Formal and Informal communications ........................................................ 18

    2.7.4 Internal and External communications ......... .......... ......... .......... .......... ........ 18

    2.8 Project Team Stress ........................................................................................... 19

  • 7/26/2019 Module 1 - 7 Point Form 106

    7/106

    2.8.2 Origins and Symptoms of Team Member stress ........................................... 19

    2.8.3 Stress Management ..................................................................................... 19

    2.8.3.1 Individual Stress Management ............................................................. 19

    2.8.3.2 Project Team Stress ............................................................................. 19

    2.9 Conflict Identification and Resolution ................................................................ 20

    2.9.2 Sources of conflict ....................................................................................... 202.9.3 Conflict Characteristics .............................................................................. 20

    2.9.4 Approaches to Conflict ............................................................................... 20

    2.9.5 Conflict management .................................................................................. 20

    2.2 The Project Manager

    2.2.2 Selecting the Project Manager

    2.2.2.2 The concept of the PM

    PMs are sometime permanent specialists or external consultants

    The role is similar to CEO or General Manager

    PM usually responsible to Project Sponsor

    Different kind of projects call for different types of PM

    Projects tend to be run outside the traditional top down hierarchy of thecompany

    His role is temporary and without the power of functional managers

    They have the authority to make project decisions but dont have authority to

    order people to carry out the work which results from these decisions The PM must depend on other forms of influence to persuade functional

    managers to agree with them

    o Competency

    o Professionalism

    o Reputation

    o Skill

    o Inter personal skills

    o Alliances

    If these dont work, go to the Project Sponsor, so the PS needs to be senior

    2.2.2.3 Central Position of the PM Key ability is to be able to focus on issues in detail while not losing sight of

    the project as a whole

    PM occupies a central position relating to communications between the

    various people and organizations involved

    Needs both the intellect to devise the project strategy and the diligence toensure that the actions are taken, both to the required standards and on time

  • 7/26/2019 Module 1 - 7 Point Form 106

    8/106

    2.2.2.4 Role of the PM

    Primary requirements of the role are:

    o Planning project activities, schedules and budget

    o Organising and selecting project team

    o Interfacing with client, the organisation and all interested parties

    o Negotiating with suppliers and clients

    o

    Managing the project resourceso Monitoring and controlling the project status

    o Identifying issues and problems

    o Finding solutions

    o Resolving conflicts

    These requirements have to be carried out within the overall success criteria of

    the project, including:

    o Within agreed time limits

    o Within agreed cost limit

    o To at least minimum specified quality level

    o To the satisfaction of the client

    o

    In compliance with the strategic plano

    Within agreed scope

    Scope is what is and is not part of project

    Project scope creep is a killer, need to manager it using interface management

    managing the organisational interfaces

    Personal, Managerial and Leadership skills

    In terms of personal skills, the PM should:o Be flexible and adaptable

    o Be able to concentrate on more than one thing at a time

    o Demonstrate initiative

    o Be persuasive

    o

    Good communicatoro Balance multiple objectives

    o Be prepared to generalize rather than always specialise

    o Good planner and implementer

    o Good time manager

    o Good negotiator and influencer

    o Be diplomatic

    Technical and Business Skills

    Technical skills help a PM understand the detailed components of a project

    Harder characteristics include

    o Understanding how to setup a team and run it

    o

    The ability to develop complex time and cost plans and achieve them

    o Understanding of contracts, procurement and purchasing

    o Active interest in training and development

    o Understanding of the technology that is central to project success

    o Ability to translate business strategy into project objectives

  • 7/26/2019 Module 1 - 7 Point Form 106

    9/106

    2.2.2.5 Selecting the Project Manager

    Best person is a functional manager with project management skills

    knowledge of industry & organisation

    Problem is losing a good functional manager, should not do both PM and fnc

    management at same time

    Could use an external consultant, but they have learning curve

    Specialist project managers are best main issue is technical competence

    2.2.3 Some Essential PM requirements

    2.2.3.1 Introduction

    Primary functions

    o Project planning

    o Authorising

    o Team organising

    o

    Controllingo Directing

    o Team building

    o Leadership

    o Life cycle leadership

    2.2.3.2 Planning

    Most critical phase of project as mistakes made here are most expensive to

    rectify if they are not discovered until later phases

    Organisational and resourcing issues planning covers activities and their

    sequence Technical planning required for

    o Time planning & control

    o Cost planning & control

    o Quality management

    Also need to plan and establish individual/team authority and communication

    relationships

    Use Task Responsibility Matrix (TRM) to define authority linkages. TRMshows

    o Key milestones

    o Individual important activities

    o General responsibilities

    o

    Specific responsibilitieso Dates

    Responsibilities include:

    o Approval

    o Preparation

    o Checking

    o Making and input

    o Authorising

  • 7/26/2019 Module 1 - 7 Point Form 106

    10/106

    Typical TRM

    Person A Person B Person C

    Inception Report O,I C A

    Feasibility Report O,I I A

    Outline Proposals O,I I A

    Scheme Designreport

    I O,I O,C,A

    I = Input

    C= Checking report

    A = authorising contents before submission to client

    O = Organising reports

    2.2.3.3 Authorising

    Interested in authority from two perspectives:o Sufficient authority to get job done

    o How much authority to delegate

    Authority is not the same as power

    Authority is the type of ability to control and direct that is delegated from

    higher levels

    Power is given to an individual by subordinates at lower levels

    For example, PM and functional manager have the same authority, but

    functional leader has more power, given to him by subordinates

    PM has to enter authority negotiations with functional manager

    2.2.3.4. Team organizing PM responsible for organising how work is to be executed

    To create organisational structures, PM must understand politics of the

    organisation & the stakeholders

    Organisational structures fall into the following categories

    o Classic Theory: people involved are components of a production

    process, producing the goals of the org. Often used in large scale

    manufacturing

    o Empirical Theory: basic similarities between the systems and processes

    adopted by organisations. If enough observations and sample data are

    taken, the process can be identified & indeed predicted. E.g. train

    operating organisations tend towards the same systems and procedureso Behavioural Theory: two main schools

    Human relations school: suggests there are intrinsic links

    between the behaviour of individuals and the behaviour of the

    organisation, need to match the two e.g. total quality

    management

    Social system school: as social characteristics of the

    organisation change, so to must those of individuals. Changes

  • 7/26/2019 Module 1 - 7 Point Form 106

    11/106

    may go beyond attitudes and objectives they may involve

    working practices e.g. smoking ban in workplace

    o Decision theory: organisations can be observed and modelled and

    models can be used to predict organisational efficiency in other

    organisations

    o System management theory: break up an organisation into a series of

    linked systems, each with inputs, some form of processing and outputs Managers that subscribe to any of the above theories will be resistant to the

    imposition of any systems derived from any other theory e.g. using classical

    theory in an ad agency

    PMs tend to favor more analytical - decision and system theories

    PM needs to review available resources and pick appropriate org structure

    At the first meeting, the following are agreed:

    o Individual responsibilities

    o Project organisational breakdown structure (OBS)

    o Project Task responsibility matrix (TRM)

    o Communication links

    o Authority links

    o

    Information configuration management system

    o Project programme

    2.2.3.5 Controlling

    PM responsible for

    o Establishing desired targets for performance

    o Measuring actual performance against targets

    o Initiating corrective action where the actual performance deviates too

    far from that desired

    Controlling is a four stage process:

    o

    Targeting targets can be set for individuals or the group and shouldbe in line with overall success and failure criteria for project

    o Measuring can be formal (earned value analysis) or informal

    (appreciation or evaluation)

    o Evaluating identifying where progress is not being made in

    accordance with the overall project plan & consideration of corrective

    action. Variance analysis looks at difference between planned and

    actual events i.e. its retrospective. Should also use a forecasting

    system, telling the PM where planned actions are likely to result in

    poor performance

    o Correcting Evaluation identifies where problems are occurring,

    correcting phase identifies why problems are occurring, how to correct

    them and monitors if they are being corrected (second level varianceanalysis)

    2.2.3.6 Directing

    1 This is the process involved in converting organizational goals into reality

    using organizational and project resources

    2 Activities include:

  • 7/26/2019 Module 1 - 7 Point Form 106

    12/106

    o Setting up the project team

    o Team training and development

    o Supervision

    o Individual and team motivation

    o Co-ordination

    2.2.3.7 Team Building

    1 Process of taking a series of individuals from different functional groups andwelding them into a unified project team

    2 This is an ongoing thing, not just at start, although the start is most critical

    3 Ten sections to any good team building process:

    o Individual and team commitment: sharing aims and objectives of

    project. This is easier when its an internal rather than external team.

    Use reward system or external factors

    o Developing team spirit: this is a measure of motivation

    o Obtaining project resources: often a problem when the success of a

    team means it grows. Mix of skills also criticalo Establishment of clear goalsand successes and failure criteria: stops

    people moving the goalposts, strategic changes must be relayed to

    team and project objectives re-established. Criteria must be

    quantifiable

    o Formalisation of visible senior management support

    o Demonstration of effective program leadership

    o Development of open formal and informal communications. Good

    communications is a motivator. People take ownership

    o Application of reward and retribution systems: good performers are

    recognised and rewarded

    o Identification and management of conflict: not just between people

    but between incompatible design and cost information. Some conflict

    is necessary

    o Development of heterogeneity control and cohesiveness

    2.2.3.8 Leadership

    Traits include:

    1 Decision making capability

    2 Problem solving

    3 Ability to integrate new team members

    4 Inter personal skills

    5

    Ability to identify and manage conflict6 Communications skills

    7 Interface management skills: with upper management, functional heads and

    project team

    8 Factor balancing skill: constant tradeoffs

  • 7/26/2019 Module 1 - 7 Point Form 106

    13/106

    2.2.3.9 Lifecycle Leadership

    Project leadership is unique because requirements vary over time

    1 Project teams last only until project is completed and hence there is little time

    to gain knowledge of the project and team

    2 Project manager concerned with complete lifecycle rather than just the

    individual stage. So he must apply different leadership skills and styles

    depending on the stage3 Lifecycle leadership is only relevant when one person leads team(s) through

    entire lifecycle

    4 Task oriented leadership relates to tasks themselves and the mechanics of the

    process

    5 People oriented leadership relates to leadership of individuals and how they

    work as a team

    Phase Characteristic Task People Effect

    1 Inception Hi Lo Telling2 Development Hi Hi Persuading

    3 Stablisation Lo Hi Participating

    4 Maturity Lo Lo Delegating

    1

    Phase 1: similar to new employees joining a company, they want to be told

    what to do as there is much confusion

    2

    Phase 2: system not yet evolved, so high task leadership. Growing trust

    and so growing people leadership

    3

    Phase 3: Stabilised team and output secure. Manager moves to higher level

    motivational factors (e.g. Maslows hierarchy)

    4

    Phase 4: team can be left alone to do project

    2.3 Project Team

    2.3.2 Project teams within functional organisations

    1 Most projects are carried out within traditional organisations designed along

    functional lines e.g. repackaging product is a marketing project

    2 Some projects are run across functional areas e.g. installing a new finance

    system

    3 Some pure project organizations may be setup external to a parent company

    4 Advantage of running projects with operating project teams within functional

    organizations:o Structure provides flexibility

    o Employees given new skills and experiences

    o Team and cross functional attitude is improved

    o Experts can share expertise across organisation

    o Experts working together produce new synergies

    o Employees in project can still follow primary career path

    o New career paths open

  • 7/26/2019 Module 1 - 7 Point Form 106

    14/106

    o Less costly than using external consultants

    5 Disadvantages

    o Function has to continue to operate as normal despite resource

    depletion

    o Functional managers sometimes put weak people on projects

    o May be difficult to adapt

    o Project manager has difficulty making his project the priority

    o Communications problems between projects and functional

    organizations

    o Motivation may be a problem

    2.3.3 Team multi-disciplinary and heterogeneity Issues

    1 The Project manager must blend functional specialists together

    2 Sentience is the tendency for individuals to identify with their own

    professional background3 Interdependency is when teams depend on inputs from more than one person

    4 Specilaism adds to sentience which can lead to a communications problem

    5 Integration is the process of defining responsibilities and control

    6 The greater the range of team members characteristics and background, the

    less the chance of overall bias or sentience, but higher conflict

    7 Homogenous = one type

    8 Heterogeneous = many types

    2.3.4. Group and team processes1 Groups are collection of individuals who work together in pursuance of a

    common objective

    2

    Teams are a collection of individuals who work under direction of a team

    leader in pursuance of a common objective

    3

    Team = subset of Group

    4 An organisation has many groups, formal and informal

    5

    Informal groups meet because of social reasons

    6 Project Managers must be aware of all types of groups in an organisation

    7

    Groups are better than individuals at problem solving because

    o they brainstorm more effectively

    o consider a wide range of factors

    o develop an enhanced logic flow

    o generate more original ideaso consider a wider range of consequences

    o solve problems quicker and more accurately

    2.3.5 Project team performance

    8 Factors which effect team performance the most are:

    o Heterogeneity - the more, the better problem sovling but the more

  • 7/26/2019 Module 1 - 7 Point Form 106

    15/106

    conflict

    o Cohesiveness - how much team members want to be members and how

    well personal goals are aligned to team goals

    2.4 Project Team Staffing Profile and Operation

    2.4.2 Project Team Staffing

    A balance of skills and experience is sought

    Normally project manager will assemble a schedule of resources requiredand submit to senior management

    Factors taken into account include

    o Availability of resources - short and long term, internal vs.

    external

    o Ability

    o Continuity requirements

    o team working skills

    o

    special skills Successfully staffing means:

    o Staffing is voluntary

    o Staffing is in relation to value of project

    o Less formal than functional teams

    o PMs lead by example

    o Teams are flexible and responsive

    o Teams interface across all boundaries

    o Teams innovate and evolve

    o Functional managers receive recognition

    o Conflict can be good during staffing

    2.4.3 Project Team Profile

    2.4.3.1 Project Team Mix

    Think about team in the widest terms, including clients, subcontractors,stakeholders

    The Project Office provides a focus

    2.4.3.2 Uniqueness of project team

    No set skills profile for an effective project team There are three project management positions that need to be filled: Project

    Manager (acts as MD), Project Planner (acts as Operations Manager) and

    Project Controller (CFO)

  • 7/26/2019 Module 1 - 7 Point Form 106

    16/106

    2.4.4 Project Team OperationKey areas are:

    Establish measurable objectives: identify which stakeholders will decide ifproject is a success and work with them to define success

    Stakeholder management: perception by them is critical, develop mentors and

    get quality resources

    Establish & plan for SMART targets at different levels with different people,

    plan for risk and use milestones

    Plan and establish processes: the environment and relationships should be

    planned for (morale). Clear but flexible rules applied

    Leadership: constant improving of team & rewards

    Membership and identity: credibility, active membership

    Communication systems: meetings are important, formal and informal,

    actionable

    Team separation: rely on the ability of other member to keep in regular contact

    Teams in general: regular face to face meetings, performance measures,

    completion criteria, commitments and responsibility

    2.5 Project Team Evaluation

    2.5.2 Project Life Cycles

    Inception

    Feasibility

    Preliminary R&D

    Manufacture of prototype

    Development and testing of prototype

    Second stage R&D Final trials

    Production

    Commissioning

    Use

    Decommissioning

    Recycling

    2.5.3 Project Change control and management

    Very important

    2.5.4 Project Team evaluation

    Forming: team meets, objectives set, rules established, everyone knows their

    responsibilities and objectives

    Storming: establish cohesiveness, maybe conflict at this stage

    Norming: establishing team standards

    Performing

  • 7/26/2019 Module 1 - 7 Point Form 106

    17/106

    2.5.5. Groupthink

    Happens when group of individuals become highly motivated towards a set ofbeliefs

    Inconsistencies can cause problems

    Groups emerging beliefs and aims replace their own

    Symptoms include

    o Absolute commitment to project

    o Lack of respect for competitors

    o Intolerance of dissenters

    o Fear that something is wrong but censor themselves

    o Self delusion, positive filter

    o Selective reporting

    2.6 Project team motivation

    2.6.2 McGregor and Maslow

    McGregor:

    Theory X: operatives are lazy and need to be led

    Theory Y: operatives want to work and find work stimulating

    Most operational systems fall between the two

    Functional managers are more X, Project managers are more Y

    Maslow hierarchy of needs

    Self actualisation (freedom to make the best of one's talents)

    Esteem

    Belongingness Safety

    Physiology (Food/Water)

    Hierarchy should be considered from the following perspectives:

    Relative importance of needs, varies from project to project

    Time based requirements, higher the level, the more time it takes to achieve it

    Unsatisfied needs can cause resentment

    Complex needs: higher level are more subjective and so more complex

    Anticipation: fulfilled needs are no longer a motivation

    2.6.3 Equity Theory and Expectancy Theory

    2.6.3.1 Equity Theory

    Based on the perceptions of individuals in relation to what they do and who

    they are

    Employees compare these and the level of effort to achieve them and that

    defines level of motivation

    If you perceive inequality you can:

  • 7/26/2019 Module 1 - 7 Point Form 106

    18/106

    o seek promotion

    o seek increased reward level

    o make a lesser contribution

    o increase other inputs (shift work to colleagues)

    2.6.3.2 Expectancy Theory People are motivated to achieve goals they believe will give them the rewards

    they desire

    People can be motivated provided the successful completion of the project can

    be linked to their own personal goals

    2.7 Project Team Communications

    2.7.2 Project Communication

    Process by which the Project Manager sends out information, directives and

    objectives and monitors actual performance Depends partly on quantity and quality of face to face meetings

    2.7.3 Formal and Informal communications

    Organisations naturally develop barriers to communication

    Various section of the organisation that are defined by functional and power

    boundaries are called operation boundaries

    Formal lines of communication are setup so project stakeholders get whatever

    information they need and vice versa

    A good communications system monitors and records the flow of information

    Danger that formal communications become choked with volumes ofrelatively low value information, problem made worse by email and MS

    Project

    Formal communications include

    o frequently distributed reports to predefined list

    o regular project meetings

    o project memos

    o project noticeboard, newsletter and project away days

    Informal communications revolve around the grapevine: hard to control but

    can be influenced by

    o lunch and dinner appointments

    o telephone conversations

    o

    coffee breakso evening in bar

    o social events

    2.7.4 Internal and External communications

    Project communication is either internal to project members or external to allother people

  • 7/26/2019 Module 1 - 7 Point Form 106

    19/106

    Good internal communication relies on people's willingness to communicateand disseminate openly

    Good external communications is the opposite: requires absolute control overdissemination of information

    One person should be responsible for all external communication

    2.8 Project Team Stress

    2.8.2 Origins and Symptoms of Team Member stressTypical reasons for stress

    o Conflict between project and functional duties

    o Working to strict time, cost and quality limits

    o Team's short life span

    o Projects tend to be relatively complex

    o Operating within a changing environment

    Stress leads to a loss in productivity and efficiency Stress types

    o personal - from within the team member

    o work - from work environment, usually linked to workload

    o environmental stress - originates from outside both individual and

    workplace e.g. fear of unemployment

    Symptoms

    Physiological - blood pressure

    Phychological - sleep problems

    Behavioural - loss of energy

    2.8.3 Stress Management

    2.8.3.1 Individual Stress Management

    Poor diet

    Lack of exercise

    Physiological awareness and control

    communication

    Holidays

    2.8.3.2 Project Team Stress Deregulation e.g. flexi time

    Reasonableness

    Fairness - balancing the workload

    Open mindedness

    Flexibility

    Approachableness

  • 7/26/2019 Module 1 - 7 Point Form 106

    20/106

    2.9 Conflict Identification and Resolution

    2.9.2 Sources of conflict

    Onerous resource constraints

    Pressure to increase speed / reduce costs

    pressure to meet deadlines

    personality clashes

    functional vs project

    misunderstanding requirements

    incorrect or late communications

    perception of inequalities

    underlying resentment

    2.9.3 Conflict Characteristics

    more multi disciplined the team, the more the conflict

    positive conflict is good

    the lower the project managers power and authority, the higher the conflict

    the lower the degree of specified and quantifiable objectives, the greater the

    conflict

    lower communications and accountability means more conflict

    more change means more conflict

    lower prestige of project means more conflict

    2.9.4 Approaches to Conflict

    must monitor and manage divergences of opinion

    conflict highest during active phases of project, reduces at the beginning andend

    Questions to ask

    o why is conflict occurring

    o what is the source of conflict e.g. are objective inconsistent?

    o what is the potential impact to project

    o can conflict be reduced or eliminated

    o could conflict be foreseen and can we avoid it in future

    2.9.5 Conflict management conflict avoidance: used if matter is not important enough or there is no

    acceptable solution

    conflict absorption: accept it and try to minimize

    conflict resolution imposition: where there is no alternative, no consultation or

    negotiation e.g. unemployment

    negotiated conflict resolution

  • 7/26/2019 Module 1 - 7 Point Form 106

    21/106

  • 7/26/2019 Module 1 - 7 Point Form 106

    22/106

    Module 3 - Risk

    3.2 Background to risk .................................................................................................. 23

    3.2.2 Concept of Risk ................................................................................................. 23

    3.2.3 The Human Cognitive Process .......................................................................... 24

    3.2.3.1 Pattern Recognition and Attention.............................................................. 243.2.3.2 Bounded Rationality ................................................................................... 24

    3.2.3.4 Intuition and bias ....................................................................................... 24

    3.2.3.5 The Decision Model ................................................................................... 24

    3.3 Risk Handling .......................................................................................................... 25

    3.3.2 Approaches to risk handling ............................................................................. 25

    3.3.3 Risk Assessment and Control ............................................................................ 25

    3.3.3.1 Elements of Risk assessment ....................................................................... 25

    3.3.3.2 Elements of Risk Control ............................................................................ 25

    3.3.3.3 Risk Identification ...................................................................................... 26

    3.3.4 Project and Strategic Risks ............................................................................... 26

    3.4 Types of Risk ........................................................................................................... 26

    3.4.1 Generic Risk Headings ..................................................................................... 26

    3.4.2 Market and Static Risk ...................................................................................... 26

    3.4.3 External and Internal Risk ................................................................................ 26

    3.4.3.1 External Risk (cannot be controlled) .......................................................... 26

    3.4.3.2 Internal Risk (can be controlled) ................................................................ 27

    3.4.4 Predictable and Unpredictable risks ................................................................. 27

    3.5. Risk conditions and decision making....................................................................... 27

    3.5.1 Conditions of Certainty ..................................................................................... 27

    3.5.2 Decisions made under conditions of risk ........................................................... 27

    3.5.3 Decision made under conditions of uncertainty ................................................. 27

    3.5.3.1 Hurwicz Criteria ........................................................................................ 28

    3.2.3.2 Wald Criterion ........................................................................................... 28

    3.5.3.3 Savage Criterion ........................................................................................ 28

    3.5.4.3.4 Laplace Criterion .................................................................................... 28

    3.5.4 Rules for risk taking based on certainty risk and uncertainty ........... ........... ....... 29

    3.5.5 Need for risk management strategy ................................................................... 29

    3.6 The concept of Risk Management ............................................................................. 29

    3.6.2 Risk Identification ............................................................................................. 30

    3.6.2.1 Brainstorming ............................................................................................ 30

    3.6.3 Risk Classification ............................................................................................ 303.6.4. Risk Analysis .................................................................................................... 30

    3.6.4.1 Risk Analysis table ..................................................................................... 31

    3.6.4.3 Risk Drivers Map ....................................................................................... 31

    3.6.4.4 Risk Map .................................................................................................... 31

    3.6.4.5 Risk grid .................................................................................................... 31

    3.6.5 Risk Attitude ..................................................................................................... 31

    3.6.6 Risk Response ................................................................................................... 32

    3.6.6.1 Response Considerations ........................................................................... 32

  • 7/26/2019 Module 1 - 7 Point Form 106

    23/106

    3.6.6.2 Response Options ....................................................................................... 32

    3.6.7 Risk control, policy and reporting ..................................................................... 33

    3.7 Risk, Contracts and Procurement ............................................................................ 33

    3.7.2 Basic Contract theory ....................................................................................... 33

    3.7.3 Procurement ..................................................................................................... 34

    3.7.4 Characteristics of Contracts ............................................................................. 343.7.4.1 Controllable and uncontrollable costs ........................................................ 34

    3.7.4.2 Express and implied terms.......................................................................... 34

    3.7.5 Transfer of risk in contracts .............................................................................. 35

    3.7.6 Variation orders and change notices ................................................................. 35

    3.7.7. Claims risk ....................................................................................................... 35

    3.2 Background to risk

    3.2.2 Concept of Risk1 Risk management evolved in the 50s with the design of nuclear reactors2 Risk is a measurement of the probability and consequence of not achieving a

    specific project goal

    3 First level equation for risk:

    o Risk = function (event, uncertainty, consequences)

    4 Two different events may carry the same risk, depending upon theiruncertainty and consequences

    5 Second level equation is used when uncertainty is difficult to measure

    o Risk = function (event, hazard, safeguard)

    6 Something or lack of something = event. An event causes a risky situation7 Hazard = source of danger8 Safeguard = mitigation or defence against hazard9 Risk acts as a barrier to the development of an effective strategy10Risk management means that risk can be controlled and a certain strategy can

    be pursued

    11Exposure is a measure of the vulnerability of parts of the organisation to riskimpacts

    12An organisations sensitivity to risk is a function ofo Significance (severity) of enterprises exposure

    o Likelihood of different events occurring

    o

    Firms ability to manage implications13 Sensitivity = function(significance, likelihood, manageability)14Effective Risk Exploitation (EFE) is when an organisation makes use of assets

    not normally measured on its P&L e.g. IP

    15 Positive or negative changes in key variables are a source of risk16 General facts about risks

    o World is uncertain

    o Sometimes risks can be eliminated

    o Risk is a function of opportunity

  • 7/26/2019 Module 1 - 7 Point Form 106

    24/106

    o Risk is an ally, if seized can lead to competitive advantage

    o Risk management providers a range of analytical tools

    17Risk management operates at all levels within an organisation18 Companies have to take risks19No risk management system is infallible

    3.2.3 The Human Cognitive Process

    3.2.3.1 Pattern Recognition and Attention

    1 The decision making process is largely dependant on perceived risks andrewards

    2 The human cognitive process involveso Pattern recognition: have I seen this before?

    o Attention: this filters out unwanted information so only info relevant to

    the decision remains

    o Memory: short term memory stores the basic pattern recognition

    information. Once filtered, its stored in long term memory to be usedagain

    3.2.3.2 Bounded Rationality

    1) A person will generally opt for rational behaviour within constraints2) Risk forecasting is

    o Built on experience

    o As much subjective as objective

    o Possible to model it in complex maths

    o Best evaluated using a combination of modelling and subject

    approaches

    o Extrapolate from past data to predict future events

    3) Important to accurate forecasting:

    o Accurate data

    o Time limit, longer the time the more inaccurate

    o Cost

    o Vision, trying to envisage what the future will look like

    3.2.3.4 Intuition and bias

    1 Intuition is a combination of experience and extrapolations forward2 Bias is the tendency to misinterpret data because of a person's aims or

    outcome preferences

    3.2.3.5 The Decision Model

    The analysis and synthesis of a problem from a four stage process:

    Framing: avoid working on the wrong problem, the various

    components of the problem are evaluated

    Formulation: provides the formal model based on the problem

  • 7/26/2019 Module 1 - 7 Point Form 106

    25/106

    o alternatives available

    o relationship between possible decisions and outcome

    o preferences of decision maker

    Evaluation: establish a ranking order of options

    Appraisal: sensitivity of decision and effects on risk

    3.3 Risk Handling

    3.3.2 Approaches to risk handling

    Bunker approach : try to be ready for anything.

    o very expensive initial estimate

    o only applicable to high tech, high significance work

    Ostrich approach: opposite to bunker

    Gut reaction: should be last resort

    Aggressive

    3.3.3 Risk Assessment and Control

    Risk Assessment is part of risk analysis

    Risk Analysis = determining the probability of risky events occurring and

    their potential consequences and a monitoring and control process

    Risk handling = how we deal with the risks

    Risk control = risk analysis + risk handling + feedback to future strategies

    Risk Management = Risk Assessment + Risk control

    3.3.3.1 Elements of Risk assessment Risk assessment = Identify, analyse, classify and prioritise risk

    process is iterative

    steps are

    o Identify risk

    o Analyse risk

    o Classify risk

    o Prioritise risk

    Likelihood of occurrence: Rabbits Lions

    Mice Shark

    Potential of occurring->

    3.3.3.2 Elements of Risk Control

    Risk control is a process by which actual and planned risk are measured andvariances between them acts as a basis for corrective action

    must consider project constraints

    activities on critical path are especially scrutinised

  • 7/26/2019 Module 1 - 7 Point Form 106

    26/106

    3.3.3.3 Risk Identification

    Risk will have a source and an effect

    Control requirements will vary according to the relative importance of an

    activity

    'Project could overrun' is not a risk

    'Task A is underestimated' is a risk

    3.3.4 Project and Strategic Risks

    Project Risks are limited to Project

    Strategic risks are more difficult to manage because they're more long term

    and more complex & difficult to model

    Most strategies allow for a variance envelope, up to which no action is taken.

    Margin must diminish as project nears completion

    3.4 Types of Risk

    3.4.1 Generic Risk Headings

    Strategic risk e.g. market, economic environment

    Operational risk : the process, people in project teams

    Financial risk : market, credit and capital structure

    Knowledge risk: IT and KM issues

    Catastrophic risk: cannot be predicted

    All of the above are linked

    3.4.2 Market and Static Risk

    Some risks can have positive or negative outcomes and are dynamic e.g.

    shares

    Others are only negative e.g. insurance

    Market risk is dynamic and concerned with potential losses and gains to the

    organisation.

    Market Business Risk (MBR) is when the company trades with its assets:

    spreads risks throughout all of the company

    Market Financial Risks arise from gearing ration and effects equity holders

    only

    Static Risk e.g. insurance, can be controlled or reduced whereas market risks

    are always there

    3.4.3 External and Internal Risk

    3.4.3.1 External Risk (cannot be controlled)

    Competition Risk

    Market demand

    Innovation

  • 7/26/2019 Module 1 - 7 Point Form 106

    27/106

    Exposure e.g. gearing

    Shareholder risk eg. if shareholder confidence declines, may be difficult to

    raise capital

    Political risk

    Statute risk

    Impact - some companies can handle big hits

    3.4.3.2 Internal Risk (can be controlled)

    Operational

    Financial

    Management e.g. outsourcing

    IT

    3.4.4 Predictable and Unpredictable risks

    Predictable are 'known unknown'

    Unpredictable are 'unknown unknown'

    change in project priority is an example of a dynamic internal unpredictable

    risk

    3.5. Risk conditions and decision making Risk assessment and control are tools for decision making

    Three main conditions under which decisions can be made

    o conditions of certainty

    o conditions of risk: reasonable probability of a event occurring &

    assessment can be made (predictable risk)

    o

    condition of uncertainty (unpredictable risk)

    3.5.1 Conditions of Certainty

    you know exactly what the outcome is for a range of strategies under a range

    of different conditions

    3.5.2 Decisions made under conditions of risk

    In general, higher profits mean high risk

    in the absence of a dominant strategy a probability is assigned to each state of

    nature

    3.5.3 Decision made under conditions of uncertainty

    essential in this case to identify sources of uncertainty that relate to each of

    the firms exposures (risk assessment)

    source of uncertainty

    o external

  • 7/26/2019 Module 1 - 7 Point Form 106

    28/106

    o internal

    o decision drive (information) e.g. new market analysis

    Its not possible to predict what will happen i.e. what state of nature will apply

    3.5.3.1 Hurwicz Criteria

    Also known as the Maximax criterion: decision maker seeks to maximizeprofits

    N1 (probability= 25%) N2 (prob=25%) N3(prob=50%)

    S1 100M 80M 60M

    S2 150M 100M 80M

    S3 200M 160M -100M

    S= Strategies, N = events

    Decision maker here would go for strategy S3 becuase it gives the maximum

    profit (200)

    He would ignore the fact that S3 is risky : max loss -100M

    3.2.3.2 Wald Criterion

    Also known as Maximin

    Only considers minimum profits (not losses)

    He would go for S2, as its worst case still yields 80M

    3.5.3.3 Savage Criterion

    Also known as Minimax

    Minimise maximum regret for each strategy

    For N1:

    S1 regret = 200 -100 = 100

    S2 regret = 200 -150 = 50

    S3 regret = 200 -200 = 0

    Regret table

    N1 (probability= 25%) N2 (prob=25%) N3(prob=50%)

    TOTAL

    S1 100M 80M 20M 200

    S2 50M 20M 0M 110

    S3 0M 0M 180M 180

    S2 has least regret and hence S2 is chosen

    3.5.4.3.4 Laplace Criterion

    Tries to convert uncertainty decision making to risk decision making using

    subjective possibilities

    objective possibilities are based on long term frequencies of occurrence

    subject possibilities are based on degree of belief of decision maker

  • 7/26/2019 Module 1 - 7 Point Form 106

    29/106

    usually you compare the uncertain risk to a hypothetical risk and compare up

    with an approximate possibilities

    in the example, he just averages the payoffs for each strategy

    3.5.4 Rules for risk taking based on certainty risk and

    uncertainty Uncertainty

    o how much money can we afford to lose

    o what level of risk are we willing to take

    o what level of risk outcome can we absorb

    General

    o analyse risks carefully

    o plan as much as possible

    o always have a plan B

    o Dont accept risks for spurious reasons

    o never risk more than you can afford to lose

    o

    allow for bias and groupthink Hazard and safeguard

    o take risks in non critical areas

    o reduce risk profile where possible

    o dont confuse risk taking with boldness

    Philosophical

    o cannot avoid risk so accept

    o risk = opportunity

    o use risk to make money

    3.5.5 Need for risk management strategy

    Every area for outsourcing and risk transfer has been explored

    Risk management should be seen as a collective corporate strategy

    Total Strategic Risk Management (TRSM) is better suited to strategic planning

    rather than tactical response

    3.6 The concept of Risk Management Most risk management systems consist of 5 distinct areas

    o risk identification

    o risk classification

    o risk analysis

    o

    risk attitude

    o risk response

    A Risk Management system should be

    o practical

    o realistic

    o compliant

    o cost effective

  • 7/26/2019 Module 1 - 7 Point Form 106

    30/106

    3.6.2 Risk Identification

    This is about finding out all risks likely to impact on a given project and

    exploring linkages between them, risks like:

    Project risk: time & cost limits

    Technical risk: R&D risk

    Production risk: downtime Engineering risk: maintenance

    Classifications of risk

    Internal: these can be identified by breaking the project down into separate

    work packages using Work Breakdown Structure (WBS)

    External

    Project: overlap internal and external, they are a feature of this specific

    project e.g. the specific project team

    It is important that identification process is concerned with risk source rather

    than effect

    Objective risk = based on experience Subjective risk = based on current knowledge e.g. Pert analysis

    3.6.2.1 Brainstorming

    Primary method for risk identification

    Two phases: creative & evaluation

    3.6.3 Risk Classification

    Portfolio theory considers risk classification from a financial point of view

    Three level classificationo risk type: static (insurable) or market (business)

    o risk extent: environment, sector, company, project

    o risk impact: hi, lo or medium

    3.6.4. Risk Analysis

    Identification of all feasible options and data relating to various risks and

    analysis of outcomes of any decision

    Step 1: evaluate all options: look deeper into identified risks

    Step 2: consider the risk attitude of decision maker

    Step 3: consider the characteristics of the risks eg. controllable?outcomes?

    Step 4: establish measurement system e.g. qualitative or quantitative

    Step 5: interpret results of measurement system

    Step 6: make decision as to which risks to retain, which to transfer to

    other parties and what risk profile is acceptable

  • 7/26/2019 Module 1 - 7 Point Form 106

    31/106

    3.6.4.1 Risk Analysis table

    A risk analysis should comprise of a simple numerical analysis

    Soil Type Probability Cost Probable Cost Time Probable

    Time

    Dry 0.2 1 0.20 2 0.4

    Average 0.3 3 0.90 10 3Wet 0.5 5 2.50 20 10

    TOTALS 3.60 13.4

    3.6.4.2 Risk Factor Checklists

    1=High, 5 = Low

    Risk Description Probability Impact

    ---------------- ----------- --------

    Design Problems 3 5Project Team gets VD 2 2

    3.6.4.3 Risk Drivers Map

    Usually derived from the SWOT analysis

    3.6.4.4 Risk Map

    Put isolated risks on an axis of impact vs. probability of occurrence

    Risks can move within the risk map over time

    you can have an 'actual' and a 'target' risk map

    may be zones rather points that mark a risk where either impact and/or

    probability is not exactly known

    3.6.4.5 Risk grid

    Alternative to risk map

    Severity

    Probability LO Medium High

    Lo Retain Retain Insure

    Medium Retain Insure Insure

    High Insure Cease Cease

    3.6.5 Risk Attitude

    Risk evaluation is subjective and hence perceived level of risk depends upon

    attitude of risk taker

    Depends on company and personality of risk taker

    Professions can be plotted

  • 7/26/2019 Module 1 - 7 Point Form 106

    32/106

    Plot of jobs on graph of Creativity vs. Risk

    FACT: Teams take riskier decisions the longer they are together

    3.6.6 Risk Response

    3.6.6.1 Response Considerations Response depends upon

    o nature of risk

    o detail of the risk analysis

    o attitude of risk taker

    Risk response centres on risk distribution

    The contract is the tool by which risk is allocated and distributed

    The distribution of risk depends on

    o is the outcome of project worth the risk?

    o who has greatest risk control? e.g. suppliers controls delivery risk

    o who has the greatest risk liability? Usually in legal systems the onus is

    on the party who would be least effected by it occurring e.g. employerliable for employee

    o what incentive does each party have? Usually both parties share at

    least some risk

    3.6.6.2 Response Options

    Risk retention eg. not insuring household contents and hoping nothing goes

    wrong. Perhaps you can retain some risk and transfer other e.g. 5% defect

    rate on widgets

    Risk reduction by:

    o education/training

    o

    physical protection to reduce likelihood of loss [design to be robust]o systems for contingency

    o physical protection to people and property

    Risk reduction matrix:

    Risk How to reduce probability How to reduce impact

    -------------- --------------------------- --------------------------

    ......

    Risk Transfer

    o insurance is an option

    o contractual clauses

    Factors when considering insuranceo insurability of risk (eg. is data available)

    o cost of premium

    o maximum probable loss

    o likely cost of loss (including replacement)

    o likely cost of paying for loss if uninsured

    Risks can be transferred through damage clauses within contracts

    Non insurable risks can be transferred to contractors

    Risk avoidance = refusal to take risks

  • 7/26/2019 Module 1 - 7 Point Form 106

    33/106

    Further information can be gathered

    3.6.7 Risk control, policy and reporting

    Risk Control = using information learnt now on a project at a later stage of

    project

    Risk impact + probabilities change over time and so need to be monitored

    A risk handbook documents risk experiences

    Risk reports could include

    o risk maps with variances

    o listing of risk drivers

    o risks and KPIs

    o progress reports

    A risk policy doc contains

    o risk holders and risk strategies for high probability and high impact

    risks

    o overall aims and objectives of risk management strategy

    o

    accountability e.g. task responsibility matrix (TRM)o formalised reporting channels

    o risk tolerances

    o authorisation

    3.7 Risk, Contracts and Procurement Contract defines rights, dues, obligations and liabilities of each party

    3.7.2 Basic Contract theory Companies compete for work using bids or tenders

    These bids and tenders depend upon wording of the contract

    Contract normally include

    o signature block and project title

    o definition of contract terms and scope

    o information and facilities provided by client

    o project approvals e.g. milestones

    o payment systems e.g. when and how much

    o specification of product/service being provided

    o general conditions

    o specific conditions

    o

    provision for changeso form of tender

    o dispute resolution e.g. bad contract, insolvency

    o bonds and warranties

    For a contract to exist there must be

    o offer and acceptance

    o consideration i.e. exchange of something, usually money

    o Capacity ie. ability to perform obligations

  • 7/26/2019 Module 1 - 7 Point Form 106

    34/106

    o legal relations - contract must be legal

    o communication - offeror must be aware

    Alternatives to successfully performing the contract are

    o breach

    o frustration - contract cannot be performed even though both parties

    want to

    o

    recission - error or misunderstanding in original contracto rectification - badly worded contract

    o void e.g. legal goods

    o termination

    o determination - one party seeks reimbursement from the other

    3.7.3 Procurement

    process by which goods and services are acquired

    good procurement -> good suppliers -> good performance

    procurement can be strategic or project procurement can have lifecycle phases:

    o objective: establishing objectives of procurement process and contract

    terms

    o exposure: sourcing vendors

    o alternatives: comparing vendors

    o documentation: preparation of contracts and definition

    o tendering : vendors invited to bid

    o award: bids scrutinised

    o contract administration: monitor T&C's to ensure they are satisfied

    3.7.4 Characteristics of Contracts

    3.7.4.1 Controllable and uncontrollable costs

    these effect overall level of risk in contract

    fundamental contract risks are

    o adequacy of design: latent (hidden) and patent (obvious) defects

    o project eventual cost: cost overrun risk could be born by client and/or

    contractor

    o safety and indemnification for accidents

    o third party insurance

    o fire/flood etc.

    o completion deadlines

    3.7.4.2 Express and implied terms

    Fundamental risks are expressed by express terms

    Liabilities (eg. reasonable duty of care) are generally covered by implied

    terms

    There are contractual situations (e.g. professional services) where you cannot

    cover everything in express terms

  • 7/26/2019 Module 1 - 7 Point Form 106

    35/106

    most consultants/professional have professional indemnity insurance

    3.7.5 Transfer of risk in contracts

    The greater transfer of risk, the greater the cost of the contract

    Indemnity clauses transfer specific risk for specific events onto a named party

    3.7.6 Variation orders and change notices

    There allow for changes in a contract without invalidating it

    Must be fair to both parties

    3.7.7. Claims risk

    If a delay or change occurs a party might seek reimbursement from the party

    that caused it

    Contracts will often list items that are classified as client risk e.g. feature

    creep

    Contractor could claim direct loss and expense and/or more time

    client usually liable for fire/flood/acts of God

    contractor usually liable for his employees/harmful chemicals etc.

  • 7/26/2019 Module 1 - 7 Point Form 106

    36/106

    Module 4: Project Management

    Organisation Structures and Standards

    4.1 Introduction ............................................................................................................. 364.2. Organisation Theory and structures ....................................................................... 37

    4.2.2 The Project within an existing organisation ...................................................... 37

    4.2.2.1 Introduction ............................................................................................... 37

    4.2.2.2 Functional structure ................................................................................... 37

    4.2.2.3 Pure Project Structure ............................................................................... 37

    4.2.2.4 Matrix Structure ......................................................................................... 38

    4.2.2.5 Mixed or hybrid structure ........................................................................... 39

    4.2.3 The Project external to the existing organisation .............................................. 39

    4.2.3.1 Introduction ............................................................................................... 39

    4.2.3.2 External (executive) project management structure .................................... 39

    4.2.4 Criterion for selecting organisation structure ................................................... 41

    4.2.4.1 Broad Considerations ................................................................................ 414.2.4.2 Project Objectives and choice of organisational structure .......................... 41

    4.3 Examples of Organisation Structure ........................................................................ 41

    4.3.2 Example of an internal project management structure ...................................... 42

    4.4 Project Management Standards ............................................................................... 42

    4.4.2 The APM and the APM body of knowledge ....................................................... 42

    4.4.2.1 Aims ........................................................................................................... 42

    4.4.2.2 The APM body of knowledge profile ........................................................... 42

    4.4.3 BS6079 ............................................................................................................. 43

    4.4.4. Prince 2 ........................................................................................................... 43

    4.4.4.1 Introduction ................................................................................................... 43

    4.4.4.2 PRINCE2 Methodology .................................................................................. 43

    4.1 Introduction The org structure defines the arrangement of resources within the

    organisation

    An org breakdown structure (OBS) is a map showing main components or

    organisation and how they relate to each other

    A project managers task is to look at existing org structures, look at the

    required project structure and modifying both to produce the optimal project

    structure

    Project teams can beo wholly internal to organisation

    o wholly external to organisation

    o partly internal but with external specialist support

    Organisation structures can be

    functional based

    pure project based e.g. R&D

  • 7/26/2019 Module 1 - 7 Point Form 106

    37/106

    matrix structure - functional group exist but project teams are formed

    across functional boundaries

    internal project teams eg. local govt

    external project teams e.g. ad agencies

    4.2. Organisation Theory and structures

    4.2.2 The Project within an existing organisation

    4.2.2.1 Introduction

    The decision of internal vs. external depends on

    size of project relative to organisation

    relative status and importance of project

    resources available

    strategic fit with strategic objectives of company

    4.2.2.2 Functional structure

    In larger organisations self contained non matrixed projects can exist within

    a particular functional group

    These are usually incremental improvement projects

    Advantages

    clear reporting

    clear authority

    simpler

    uses specialist knowledge

    Disadvantages

    inflexible

    projects within functional group tend to be viewed as of secondary

    importance

    cross functional activities are discouraged

    career is tied to functional rather than project

    projects become islands in group

    only OK for continuous programs of work

    greater degree of central support required

    main problem is operational islands = semi independent sub groups

    project and matrix structures remove these islands by forming horizontal and

    vertical lines of authority and communication

    4.2.2.3 Pure Project Structure

    Could be a self contained project within a group

    used when project are difficult to plan and resources required are uncertain

    at its simplest, project manager picks from a pool of specialist resources that

    get returned to the pool when project is complete (e.g. consultancy company)

    pure project structure differs from functional organisation projects in that the

    latter are internal for benefit of organisation itself whereas former are more

    visible e.g. new drug development

  • 7/26/2019 Module 1 - 7 Point Form 106

    38/106

    pure project structures may be completely separate from parent company e.g.

    joint venture

    Advantages

    flexibility

    encourages innovation

    operational: can be dynamically adjusted

    project manager has total control of project, not sharing resource withthe functional manager

    clear reporting

    communications lines shorter

    authority contained within project

    team members have no functional loyalties

    support requirements are smaller

    easier to use external consultants in this structure

    can have a series of projects forming a program-> more efficiencies

    Disadvantages

    several projects at same time => duplication of work

    initial operating costs can be high

    central authority required

    may be a padding of resources

    unhealthy competition e.g. cutting corners

    lack of long term commitment

    difficult to compare project performance due to different nature

    prolonged absence from their functional group may blunt a team

    members specialist knowledge

    4.2.2.4 Matrix Structure

    pure functional and pure project structures represent different ends of the

    spectrum matrix is a compromise, also known as internal or non-executive project

    management structure

    usually technical decisions on the project are responsibility of functional

    group

    Resourcing, scheduling and cost decisions made by project manager

    matrix structures can be strong e.g. long-term projects that veer more

    towards pure project structures

    Internal project management systems have the following key characteristics:

    functional boundaries - vertical

    organisationl islands - same horizontal level but different functions and

    so dont communicate

    project sponsor - conflict resolving and monitors project

    Project management chair: PS

  • 7/26/2019 Module 1 - 7 Point Form 106

    39/106

    Time recording and cost centre charging

    Good points of matrix project management system

    self contained unit

    access to functional units

    flexible and adaptable

    links with functional groups means project remains in sync with corporate

    and functonal objectivesgood innovation

    Weaknesses

    difficulties balancing project vs functional

    confused reporting to two bosses

    project management job is more complex

    project sponsor requirements adds complexity

    4.2.2.5 Mixed or hybrid structure

    combination of functional and project structures e.g. new product project

    based in marketing but requires R&D input

    4.2.3 The Project external to the existing organisation

    4.2.3.1 Introduction

    Surrogacy is the extent to which clients want to delegate control/authority to

    running a project

    Risk transfer is also an important issue in external project management

    4.2.3.2 External (executive) project management structure

    'Executive' because project management has total control, no negotiation

    with functional managers

    Suits smaller organisations

    Formal interface body acts as gateway between organisation and external

    organisation project manager

    A legal contract might be drawn up and monitored

    Characteristics

    o multidisplinarian/shared loyalty group characteristics -> sentience

    and differentiation

    o fee structure - consultants bid to be part of an external project team.

    The timing could be at

    completion of pre contract work (e.g. analysis) completion of post contract work (e.g. implementation)

    completion of final account (e.g. completion)

    o fees could be per hour or % of work to be done

    External contractual linkages

    o risk increases with more external dependency

    o contract take these forms

    completion contract - one off payments on completion

    term contracts : long term

  • 7/26/2019 Module 1 - 7 Point Form 106

    40/106

    service level agreements

    o contracts are priced by

    completion contracts

    negotiated contracts

    o contracts can be

    fixed price

    cost or cost plus: profit fixedreimbursement: expenses plus fees

    target price: target + fee+ incentive

    o contract types:

    standard: reasonable risk allocation, recourse cover all eventualities

    professional services contract: mostly implied terms, fees and dates

    covered, related to professional standards

    supply contract: specify goods and delivery dates

    pro forma contracts: monopoly situation, onus on the client e.g. ESB

    Contractual links include

    o Client to PM and other team members

    o Client to main contractor

    o Client to service authorities i.e. supply agreements

    o Client to nominated sub contractors and suppliers: sub contractor

    nominated to main contractor

    o Client to local authority e.g. safety & regulatory issues

    External non contractual linkages

    o Authority links: client = head of authority

    o Communication links: change control procedures

    o Having client bypass project manger and communicate directly with team

    is a bad idea: scope creep

    Advantages of external project management

    o Flexibleo Dynamic

    o External specialist bring in new ideas

    o If there is no internal knowledge you can use external

    o Quick to setup

    o Quick to disband

    o Internal risks avoided e.g. having key people missing

    Disadavantages:

    o Expensive

    o No loyalty

    o Recourse can be difficult

    o New control structures necessaryo Rigid and controlled communications required

    o Legal people get involved

    o Risk profile changes

    o Complex project management

  • 7/26/2019 Module 1 - 7 Point Form 106

    41/106

    4.2.4 Criterion for selecting organisation structure

    4.2.4.1 Broad Considerations

    o Authority

    o Communication

    o

    Knowledge transfer

    o Loyalty

    o Technology e.g. matrix use IT to innovate

    o Cost: functional is high cost and inflexible

    o Co-ordination: functional has a low degree of co-ordination required

    o Support functions: functional require lots of support

    4.2.4.2 Project Objectives and choice of organisational structure

    A Functional organisation structure is suitable when

    o Workload is constant and doesnt vary mucho Projects are required infrequently

    o Well developed support structure exist

    o Informal communications not required

    o Where functional objectives are the main concern

    A Matrix structure is suitable when

    o Dynamic workload

    o Project frequently required

    o R&D frequently required

    o Centralised support present or outsourced

    o Split authority ok

    o Informal communications oko Projects are of secondary importance but still significant

    o Projects are small to medium sized

    o Fast response not required

    Pure project structure is suitable when

    o Workload varies a lot

    o Projects are frequent

    o Lots of R&D

    o Little centralised support

    o Authority can be devolved to project managers

    o Projects are primary concern

    o Projects are largeo Fast response time required

    4.3 Examples of Organisation Structure

  • 7/26/2019 Module 1 - 7 Point Form 106

    42/106

    4.3.2 Example of an internal project management structureSetting up a new engineering project management course

    Step 1: Appoint a project manager and team. The choice depends on

    o Priority of new course

    o General availability and workload

    o Existing commitments

    o University policy

    Step 2: structure: maybe matrix across engineering, management and science?

    Step 3: external consultants? Yes, if its a highly specialised subject area. It may

    involve the setting up an interface via the Legal Services group within the

    university

    Step 4: setup formal and informal links within the internal project team, university

    admin, external consultant and project sponsor

    4.3.3 Example of an external project management structureManaging external training courses

    Step 1 : the clients legal services setup contracts with external service providersStep 2: Draw up pro-forma professional services agreements describing syllabus

    and details, fees and expenses

    4.4 Project Management StandardsAPM is the Association for Project Management: body of knowledge

    BS 6079: standards for practice based on APM approaches

    Prince 2: stand alone methodology (Project management ina Controlled

    Envrionment), its an alternative to BS 6079

    Numerous industry specific adaptations of these generic standards

    4.4.2 The APM and the APM body of knowledge

    4.4.2.1 Aims

    o Act as the first point of contact

    o Lead the development of professionalism

    o Champion interest representation: lobby govts etc.

    o Establish standards of qualifications

    o Establish national branches

    o Establish practices and procedures for training

    4.4.2.2 The APM body of knowledge profile

    Lists five areas project managers must have academic qualifications and

    experience in:

    o Project management e.,g. project lifecycle and environment

    o Organisation and people e.g. leadership and communications

    o Techniques and procedures e.g. scheduling and estimating

    o General management e.g. finance and law

  • 7/26/2019 Module 1 - 7 Point Form 106

    43/106

    o Value management i.e. aims and objectives of client

    Project manager should be concerned about the long term use of the system

    being built

    4.4.3 BS6079 British guide to Project management

    Strategic Project Plan (SPP) is the most important part of BS6079

    Establishes a generic project plan that is applied to all projects

    Main sections of SPP defined in BS 6079 include:

    o Preliminaries: title page, description of project, contents list, defines who

    has access to what

    o Project aims and objectives: objectives relate to time, cost, quality and a

    range of other objectives. may also be sub objectives e.g. health and

    safety, environment

    o Subject specific sections: information presented in standard format.

    scheduling and cost control, project history Contributors to the SPP include:

    o design engineers

    o cost consultants

    o legal consultants

    o client (aims and objectives)

    o project manager (communication and co-ordination systems)

    o external statutory bodies

    4.4.4. Prince 2

    4.4.4.1 Introduction

    Its an alternative to BS 6079

    Originally used for government IT projects

    4.4.4.2 PRINCE2 Methodology

    Based on the process model of a project - breaking project down into

    component processes

    Each process is then defined in terms of its key inputs and outputs and in

    terms of the aims and objectives of each process

    Prince 2 is driven by the project business case Main advantages

    o offers a standardized project structure with a clear start, middle and

    end

    o allows regular and detailed reviews of actual vs. planned progress

    o allows regular and detailed reviews of actual vs. business case

    o identifies and makes use of flexible decision points

  • 7/26/2019 Module 1 - 7 Point Form 106

    44/106

    o identifies and allows automatic control of any deviations from project

    plan

    o ensures timing and involvement of all stakeholders and management is

    optimized

    o encourages good communication channels

  • 7/26/2019 Module 1 - 7 Point Form 106

    45/106

    Module 5 : Project Time Planning and Control

    5.1 The Concept of Project Time Planning and Control ................................................................. 46

    5.1.1 Introduction ...................................................................................................................... 46

    5.1.2 Aim and Objectives of the planning process ...................................................................... 46

    5.1.3 Project Time Planning and control and the Generic Project Plan ..................................... 47

    5.1.4 Project Time Planning and the Project Life Cycle ............................................................. 47

    5.2 The Process of Project Time Planning ..................................................................................... 48

    5.2.1 Factors Affecting the Time Planning Process .................................................................... 48

    5.2.1.2 Sources of Time Planning Data .................................................................................. 48

    5.2.1.3 Project Uniqueness .................................................................................................... 48

    5.2.1.4 People Issues ............................................................................................................. 48

    5.2.1.5 Complexity ................................................................................................................. 48

    5.2.1.6 Uncerta