modeling the relationship between mcphee dam selective

39
Modeling the Relationship Between McPhee Dam Selective Level Outlet Operations, Downstream Algal Biomass, Dissolved Oxygen and Temperature: Phase 1, Background Data and Model Development. Chester Anderson Watershed llc dba B.U.G.S. Consulting www.bugsconsulting.com [email protected] 970-764-7581

Upload: others

Post on 03-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Modeling the Relationship Between McPhee Dam Selective

Modeling the Relationship Between McPhee Dam Selective Level

Outlet Operations, Downstream Algal Biomass, Dissolved Oxygen and

Temperature:

Phase 1,

Background Data and Model Development.

Chester Anderson

Watershed llc dba B.U.G.S. Consulting www.bugsconsulting.com

[email protected]

970-764-7581

Page 2: Modeling the Relationship Between McPhee Dam Selective

1

Table of Contents

Executive Summary........................................................................................................................ 5

Background data and information................................................................................................... 6

McPhee Dam Outlet Works ........................................................................................................ 6

Discharge from McPhee Reservoir............................................................................................. 7

Water Temperature in the Dolores.............................................................................................. 8

Reservoir Dynamics Water Quality and Fish Distribution ......................................................... 9

Dissolved Oxygen in the Dolores ............................................................................................... 9

Conductivity and pH in the Dolores ......................................................................................... 10

Limiting Nutrient Analysis in the Dolores................................................................................ 10

Discussion ................................................................................................................................. 10

Water temperature models ............................................................................................................ 11

Purpose of models and baseline:............................................................................................... 11

SELECT Reservoir model .................................................................................................... 11

River Water Quality Model .................................................................................................. 12

Methods................................................................................................................................. 12

Conclusions........................................................................................................................... 13

Next Steps ............................................................................................................................. 13

References..................................................................................................................................... 13

Appendix 1. History of Dolores River Diversions and the Dolores Project (from the DRD

Hydrology Report) ........................................................................................................................ 15

Appendix 2. Dolores River temperature data compiled from data provided by the Colorado

Division of Wildlife and the Dolores Water Conservancy District. ............................................. 17

Appendix 3. Reservoir data compiled from data provided by the Colorado Division of Wildlife

and the Bureau of Reclamation..................................................................................................... 17

Appendix 4. Existing McPhee Dam Operational Constraints ...................................................... 17

Figures........................................................................................................................................... 19

Page 3: Modeling the Relationship Between McPhee Dam Selective

2

Table of Figures

Figure 1. Selective Level Outlet Works showing the 2nd and 3rd inlets. The 1rst inlet faces the

dam. The sills of the inlets are located at elevations 6,892 (SLOW 1), 6,896 (SLOW 2) and

6,840 feet (SLOW 3). Full reservoir elevation is 6,924 ft. Note the proximity of the 3rd

SLOW to the benthos, habitat for white suckers. ................................................................. 19

Figure 2. Copy of blue prints cross section of Selective Level Outlet Works (SLOWs) ............. 20

Figure 3. Quantity of organic matter (median ± 75th

and 25th

percentile) measured as ash-free dry

mass in relation to other streams in the region. Note, the Dolores sites (@ dam, Ferris Creek

Campground and Bradfield Bridge) are at the high end of concentrations. The Colorado

Department of Public Health and Environment is in the process of setting nutrient criteria.

The New Mexico Environment Department has established a regional criterion of 5mg/m2.

............................................................................................................................................... 21

Figure 4. Median (±25th

percentiles) discharge at the USGS Gage located above the MVIC

diversion. Because there are few diversions above this site this graph is a close illustration

of the native hydrograph. ...................................................................................................... 22

Figure 5. Median (±25th

percentiles) discharges at the old town site of McPhee, CO (now buried

by McPhee Reservoir) below the MVIC diversion during dates prior to the construction of

McPhee Dam and after construction of the Great Cut Diversion. During the months of

August through November, flows were less than 10 cfs 50% of the time............................ 22

Figure 6. Median discharge at the USGS Bedrock Gage. Median flows prior to the construction

of McPhee Dam were less than after the construction of McPhee Dam July through

November and greater April through June............................................................................ 23

Figure 7. Median discharge (±25th

percentiles) from McPhee Dam. Median flows were 30 cfs or

greater for each month of the year. Note the 10 fold decrease in post-dam median flows for

the months of April and June (see Figure 5)......................................................................... 23

Figure 8. Discharge at the Ciscoe, Utah USGS gage. Median flows were less prior to the

construction of McPhee dam for the months of August through March. Median flows were

greater in the Dolores prior to the construction of McPhee Dam for the months of May and

June. ...................................................................................................................................... 24

Figure 9. Discharge data from McPhee Reservoir illustrating the low summer/fall flows in 1990,

2002, and 2003...................................................................................................................... 25

Figure 10. Pre and post dam differences in mean (± SE) daily water temperature (oC) collected at

the USGS Gage at Bedrock, CO (grab samples). Note differences in April and June during

the spawning period for native fish....................................................................................... 26

Figure 11. Mean (± SE) daily temperatures at the Ciscoe USGS Gage. Mean temperatures were

less prior to the construction of McPhee Dam January through July. Data set includes data

from 1986, 87, 88, 90, 02 and 05 through 09........................................................................ 26

Figure 12. Mean ± standard deviation of daily maximum temperature at 7 sites, McPhee dam

downstream to Slick Rock. Ambient temperature is reached near Disappointment Creek

where temperature of the water discharged from the dam has little influence on

temperatures found in the river. ............................................................................................ 27

Figure 13. Average of daily maximum temperature at 7 sites, McPhee Dam downstream to

Slickrock. Winter temperature upstream of Bradfield Bridge is greater than winter water

temperature Bradfield Bridge downstream showing the influence of the dam in DRD Reach

1 (McPhee to Bradfield Bridge)............................................................................................ 27

Page 4: Modeling the Relationship Between McPhee Dam Selective

3

Figure 14. May 1rst

through September 30th

daily maximum and minimum temperature and

discharge data during the 1990 drought, measured at Bradfield Bridge. Note that the chronic

temperature threshold for trout was exceeded twice for periods greater than 24 hours and the

acute temperature threshold was exceeded on 5 dates at discharges of both 20 and 50 cfs. 28

Figure 15. May through September daily maximum and minimum temperature and discharge

data during the 2002 drought, measured at Bradfield Bridge. Note that the chronic

temperature threshold for trout was exceeded several times for periods greater than 24 hours

and the acute temperature threshold was exceeded on numerous occasions. Discharge from

McPhee less than 20cfs. No temperature data available for 2003 also a period of very low

discharge from McPhee. ....................................................................................................... 28

Figure 16. Discharge from McPhee and daily maximum and minimum temperature at Bradfield

Bridge in 2009. The chronic temperature threshold for trout (64.9o

F) was never exceeded

for more than 24 hours and the acute temperature threshold for trout (74.9o

F) was never

exceeded at flows of 70 cfs during the summer months. ...................................................... 29

Figure 17. Overall (1987-2009) and summer (July through September) average of maximum

daily air temperature. Data collected at Great Cut operations center. .................................. 29

Figure 18. Reservoir Elevation in relationship to the SLOWs. The 3rd SLOW was less than 20

feet below the water surface from July 15th

2002 to February 24th

2003. ............................ 30

Figure 19. Thermoclines for McPhee Reservoir measured at the dam in 1987 in relation to the

SLOWs. Note that the top of the thermocline was between SLOW 1 & 2 for the September

and November sample dates and at or above the SLOW 1 for May, June, July and August

sample dates and non-existent for April. .............................................................................. 31

Figure 20. Dissolved oxygen-clines for McPhee Reservoir measured at the Dam in 1987 in

relation to the SLOWs. Note that the top of the oxygen-cline was between SLOW 2 & 3 for

September and November and between SLOW 1 and 2 for August and at or above the

SLOW 1 for July and non-existent for April and May. ........................................................ 32

Figure 21. Fish, thermocline and oxygen-cline data collected August 2003. The 3rd

Selective

Outlet Work was just below the clines 8-5-03. Sonar data indicates fish living below the

clines. Vertical gill nets set for 24 hours caught 20 fish of which 1 was a small mouth bass.

The others were Kokanee Salmon, Rainbow and Brown Trout. Reservoir elevation August

5-8, 2003 averaged 15-17.5 meters below full. July 21rst, 2004 it was 9m below full and 8-

24-1994 it was 6m below full. All catch depths are in relationship to elevation of the

SLOWs.................................................................................................................................. 33

Figure 22. Mean concentration of dissolved oxygen at the Bedrock USGS Gage (grab samples).

Dissolved oxygen was less in the Dolores after the construction of McPhee Dam for the

months of March, May, June and August despite lower, post-dam temperatures (see Figure

10) indicating the possible effects of respiration of organic matter on dissolved oxygen.... 34

Figure 23. Temperature and dissolved oxygen data obtained with a YSI sonde at 3 sample

stations: Below McPhee Dam, Ferris Creek Campground and Bradfield Bridge, September

17-19th

2008. Note the low DO concentrations (5.99mg/l @ Bradfield Bridge and 6.06mg/l

@ Ferris Creek Campground and 6.55mg/l @ the Dam measured in the early morning due

to decomposition of organic matter. The State standard for Trout Fisheries is 6mg/l. The

chronic temperature threshold for trout (18.22C) was not exceeded during the time period.

Discharge from McPhee Reservoir was 40cfs. ..................................................................... 35

Page 5: Modeling the Relationship Between McPhee Dam Selective

4

Figure 24. Mean conductivity at the Bedrock USGS Gage (grab samples) prior to the

construction of McPhee Dam. The conductivity was greater for the months of July through

November and less for the month of June. ........................................................................... 36

Figure 25. Mean daily conductivity at the Ciscoe, Utah USGS Gage prior to the construction of

the McPhee Dam. Conductivity was greater for each month of the year except June prior to

the construction of McPhee Dam.......................................................................................... 36

Figure 26. Mean pH at the USGS Bedrock Gage (grab samples) prior to the construction of

McPhee Dam. The pH was less for each month of the year and had much greater variability

prior to the construction of McPhee Dam............................................................................. 37

Figure 27. Actual compared to predicted maximum water temperature @ Bradfield Bridge based

on a multiple regression equation using maximum air temperature at Bradfield Bridge,

average air temperature at Bradfield Bridge, discharge (Q) from McPhee Reservoir,

maximum temperature of water discharged from McPhee Reservoir, and angle of the sun .

The model tends to over predict water temperatures at actual temperatures greater than 65 oF. Data collected at Bradfield Bridge in 2008 and 2009. .................................................... 37

Figure 28. Predicted maximum water temperature at Bradfield Bridge given the 75th percentile

of average air temperature at Bradfield Bridge, the 75th

percentile of water temperature

discharged from McPhee Dam from the 3rd SLOW, and 75 cfs, June to September 15th

and

35 cfs after September 15th

from McPhee Reservoir. ........................................................... 38

Figure 29. Algal bioassay data. Mean ± S.E. at 3 Dolores River sites: below McPhee Dam, at

Ferris Creek Campground and at Bradfield Bridge. The addition of nitrogen and phosphorus

to tiles at Bradfield Bridge resulted in significantly greater amounts of algal growth

measured as concentration of chlorophyll-a. No significant differences at the upstream sites.

............................................................................................................................................... 38

Page 6: Modeling the Relationship Between McPhee Dam Selective

5

Executive Summary The Dolores River has changed considerably since McPhee Dam was constructed. The Selective

Level Outlet Works (SLOWs), a million dollar structure built with McPhee Dam, were designed

to help Stakeholders meet downstream water quality goals but have never been used as they were

designed. Water has only been released from the 3rd

SLOW and the bottom of the reservoir.

Releases from the bottom of the reservoir discharge highly reactive forms of nutrients

downstream, increasing algal biomass and its negative impacts on dissolved oxygen. Limiting

releases to the 3rd SLOW and the bottom of the reservoir also restricts opportunities to manage

for downstream water temperature goals.

This report illustrates water quality changes to the Dolores River since construction of McPhee

Dam and outlines a couple of models developed to predict downstream changes in water

temperature and other water quality parameters given full use of the SLOW’s. The models

predict the effect of various release levels through the outlet works on temperature, algal biomass

and dissolved oxygen of receiving waters below McPhee. One model, developed by the U.S.

Army Corps of Engineers, has been applied to McPhee reservoir data to predict water

temperature discharge from McPhee given various discharge scenarios through the outlet works,

reservoir elevation and time of year. The other model, developed by B.U.G.S. Consulting ,

was constructed to predict daily maximum water temperature in the Dolores River between the

dam and the confluence with the San Miguel given various release scenarios and time of year,

Preliminary testing of the models indicates that a discharge of 75 cfs exclusively from the 3rd

selective level outlet (no releases from the bottom of the reservoir) under normal reservoir

elevations (i.e. the 3rd

SLOW being at or near the bottom of the thermocline) will result in

downstream temperatures that do not exceed Colorado temperature standards for cold-water

fisheries. This strategy may facilitate the Colorado Division of Wildlife’s goal of a gold medal

fishery. Other release scenarios may help improve non-native fish populations.

The models will be refined with data collected summer 2010 and operational and experimental

recommendations will be developed for full use of the SLOWs to meet downstream water quality

goals. Further use of the SLOWs and their impacts could then be experimentally completed

utilizing baseline data collected on fish biomass, algal biomass, dissolved oxygen and

temperature as response variables.

It is recommended that the thermometers that were originally installed at each SLOW inlet be

repaired prior to expanding use of the SLOWs to SLOW 1 and SLOW 2. This will ensure up-to-

date and accurate temperature data for model input. Also, it would be prudent to take the

Biology Committees recommendation and complete a thorough investigation of fish entrainment

through the outlet works to determine the probability of non-native fish (primarily white suckers

and small mouth bass) making it to and into the SLOWs, surviving a trip through the SLOWs

and the turbines and surviving and reproducing in the reaches below the reservoir given various

temperature regimes.

Page 7: Modeling the Relationship Between McPhee Dam Selective

6

Background data and information

McPhee Dam Outlet Works

Selective Level Outlet Works (SLOWs) were constructed with McPhee Dam in 1984 to

minimize releases of highly reactive forms of nitrogen and phosphorus from the bottom of the

reservoir and to facilitate downstream water temperature objectives. The SLOWs have never

been fully utilized for either of these purposes.

The U.S. Army Corps of Engineers and the Bureau of Reclamation have been using selective

withdrawal from reservoirs to manage downstream water quality since the 1970s (Vermelyen et.

al. 2003). Selective withdrawal is a method of withdrawing water from a particular level within a

reservoir that has ambient stratification. Typically, decisions regarding selective withdrawal

operations are tied to established downstream water quality goals (in most cases temperature).

Meeting a daily release-quality target involves selecting an outlet or outlets for which the

predicted, flow-weighted release approaches the release objective.

A problem faced by reservoir managers is the daily or short-term operational decisions required

for a selective withdrawal structure to meet specific water quality management objectives. An

operational decision model should identify which outlets to open when and how much to open

the outlets to meet downstream water quality and discharge goals of the project.

The SLOWs for McPhee Dam consist of 3 inlets with sills at elevations 6,892 (SLOW 1), 6,896

(SLOW 2) and 6,840 feet (SLOW 3) opening into a tower sitting on a shelf near the dam (Figure

1, full reservoir elevation is 6,924 ft). Each inlet empties into a shaft that takes water through the

bedrock and the dam (Figure 2). The original design of the SLOWs allowed for a maximum

discharge of 205 cfs. Temperature recorders were placed at each SLOW inlet to facilitate

downstream temperature goals. Since construction of McPhee Dam, little if any water has ever

been released through SLOW 1 or SLOW 2 and the temperature recorders are no longer

operable.

A power plant was added to the selective level outlet works in 1993. This altered the flow outlet

equation so that only a maximum of 144cfs can now be discharged through the SLOW tower. To

discharge more than 75 cfs through the SLOW tower the power plant would have to be taken

offline. Power can only be generated at discharge increments of 25, 50 and 75 cfs. If demands for

downstream water are other than 25, 50 or 75 cfs, the additional water is run through a bypass

gate located at the bottom of the reservoir. Maximum discharge through the bypass gate at the

bottom of the reservoir is 55 cfs. Power has been generated since 1993, except from September

1994 to January 1997 due to a turbine problem and from May 2002 to January 2003 due to low

reservoir elevations and during short periods of maintenance. In addition to the SLOWs and the

bypass gate, two 4 by 4ft gates located at the bottom of the reservoir allow for discharges up to

4,500 cfs.

Algal biomass

Algal biomass data indicates that nutrient releases from the bottom of McPhee reservoir through

the bypass gate at the bottom of McPhee Dam creates high levels of algae in the Dolores River

Page 8: Modeling the Relationship Between McPhee Dam Selective

7

below McPhee Dam (Figure 3). A consequence to the fisheries is that, as the algae accumulates,

and decays, the dissolved oxygen in the river falls below critical thresholds for trout and possibly

for native fish. The over enrichment of the river associated with releases from the bottom of

McPhee Dam may also cause toxicity issues associated with de-nitrification from the benthos

(Cheslak and Carpenter, 1990).

Reactive forms of nitrogen and phosphorus form during the summer/fall stratification of

reservoirs and within the deeper, denser, anaerobic layers of the reservoir (Correl, 1998). When

water is released from near the bottom of the reservoir, the reactive forms of nitrogen and

phosphorus essentially act as fertilizer, resulting in high concentrations of algae in downstream

reaches (Figure 3). During the oxygen consuming phases of algal respiration and decomposition

and when large amounts of oxygen producing photosynthesis is not occurring, the negative

balance of oxygen can result in low concentrations of dissolved oxygen in the reaches

downstream of the dam. These periods of low concentrations of oxygen occur at night, during

cloudy periods, when the water is turbid and in the winter. This negative balance can overwhelm

the positive effects of cold water and the rate of atmospheric exchange on dissolved oxygen

concentrations.

I hypothesize that by eliminating releases from the bottom of McPhee reservoir (e.g. through the

bypass gate) and utilizing only water from the Selective Level Outlet Works (SLOWs) during the

base-flow period, water quality, primarily dissolved oxygen, can be improved in both the cold-

water and warm water reaches below McPhee Dam.

Discharge from McPhee Reservoir

Diversions out of the Dolores basin began in the late 1880s when the majority of the river was

diverted during late summer months at the Great Cut Diversion that took water out of the

Dolores River and discharged it into the Montezuma Valley which lies in the watershed of the

San Juan River. Flows prior to the Great Cut Diversion were most likely similar to flows at the

Town of Dolores, just upstream of the Diversion (Figure 4).

After diversions began in the late 1880s, a USGS gage at the old town site of McPhee, CO (now

buried by McPhee Reservoir) shows that flows were most likely intermittent (surface water

limited to pools and no surface flows connecting the pools) during late summer months (flows <

10 cfs, Figure 5) from McPhee Dam to Bedrock (DRD Reaches 1 through 5). The Great Cut

Diversion could take almost 1,400 cfs from the river at a site just below the town of Dolores,

CO. Since McPhee dam was completed in 1985, median April flows decreased from 850 cfs to

50 cfs and median June flows decreased from 900 to 85 cfs and median base-flows for July,

August and September increased from less than 10 cfs to 70, 60 and 50 cfs respectively (Figure

7).

Discharge data from the USGS Bedrock Gage shows that median flows prior to the construction

of McPhee Dam were less than after the construction of McPhee Dam July through November

(Figure 6). Discharge data from the USGS Ciscoe, Utah gage show that median flows were less

prior to the construction of McPhee dam for the months of August through March. Median flows

were much greater in the Dolores prior to the construction of McPhee Dam for the months of

May and June (Figure 8).

Page 9: Modeling the Relationship Between McPhee Dam Selective

8

Post dam discharge changed as projects came on line and affected the amount of water available

to discharge downstream (Figure 9). During the period from 1985 to 1996, when the downstream

release from McPhee were determined on an “indexed” basis ((i.e., 78cfs in “wet” years, 50cfs

in “average” years, 20cfs in “dry” years, (Appendix 1), base flows below McPhee Dam ranged

from 30 cfs during the winter months to 78 cfs during the summer months (Figure 9). When

flows changed from being an ‘indexed’ flow regime to a ‘managed pool’ flow regime with the

1996 Environmental Assessment. Pre 1996 McPhee Dam discharge resulted in a baseflow of at

least 50 cfs, and more, often well over 78 cfs. The change to the managed pool in 1996 reduced

baseflows significantly. There was a brief period in 1990 where the index went to 20 cfs but was

quickly changed to 50 cfs due to the recognition that 20 cfs would not sustain the fishery.

In the summer of 2002, under the “managed pool,” established releases from McPhee Dam were

as low as 15 cfs due to drought and shared shortage among project allocations. Releases from

the dam were less than 20 cfs from April 28, 2002 to May 4, 2003. Peak flow in 2003 was 41 cfs

and hovered around 40 cfs for a few weeks and then below 20 cfs until May 4th, when slight

improvements in base-flow occurred. Peak flow in 2004 was 92 cfs and lasted for only 1 day.

Water Temperature in the Dolores

Temperature, pH, conductivity and dissolved oxygen data in the Dolores was obtained from the

USGS. Other temperature data in the river was compiled from data collected by the Colorado

Division of Wildlife and the Dolores Water Conservancy District (Appendix 2). Means and

standard deviations of maximum daily temperatures were calculated and graphed to determine

the effect McPhee Dam had on downstream water temperatures. The data set is incomplete and

below is a summary of the data available.

Mean daily water temperature in the Dolores River prior to the construction of McPhee Dam was

significantly less than post McPhee water temperature for the months of April, June and

September at the USGS Bedrock gage (Figure 10). At the Cisco USGS gage near the confluence

with the Colorado River, mean daily temperatures were less prior to the construction of McPhee

Dam for each month of the year except August through December compared to post construction

mean daily temperatures (Figure 11).

Summer ambient daily maximum water temperature is reached near Disappointment Creek

(Figure 12). Winter daily maximum water temperatures are greater upstream of Bradfield Bridge

than are winter daily maximum temperatures recorded downstream of Bradfield Bridge (Figure

13) due to the influence of deep releases from the reservoir.

The acute temperature threshold for trout (74.9○ F) was not exceeded in 1986, 1987 or 1988

(Appendix 2, Colorado Department of Public Health and Environment. 2007). The chronic

temperature threshold for trout (64.9○ F) was exceeded twice for periods greater than 24 hours

and the acute temperature threshold was exceeded on 5 dates in 1990 at Bradfield Bridge (Figure

14). The chronic temperature threshold for trout was exceeded several times for periods greater

than 24 hours and the acute temperature threshold was exceeded on numerous occasions in 2002

at Bradfield Bridge (Figure 15). The chronic temperature threshold for trout was never exceeded

for a period of 24 hours and the acute temperature threshold was never exceeded on any date in

Page 10: Modeling the Relationship Between McPhee Dam Selective

9

2005, 2006, 2007, and 2009 at Bradfield Bridge (only late summer and fall data collected in

2008, Figure 16).

In 2009, daily maximum water temperature exceeded the chronic threshold of 64.9○ F but never

for more than 24 hours. Daily minimum water temperature was always below the chronic

threshold in part because air temperatures for 2009 were less than the overall average (Figure

17). When flows were ramped up from 40 cfs on 9/30/09 to 196 cfs on 10/1/09, minimum water

temperature at Bradfield Bridge went from 54○ to 40

○ F and maximum water temperature went

from 60○ to 50

○ F, a decline of 20

○ F in less than 36 hours.

Reservoir Dynamics Water Quality and Fish Distribution

Reservoir discharge data and elevation data was obtained from the Dolores Water Conservancy

District and reservoir water quality data and fish data was obtained from the Bureau of

Reclamation and the Colorado Division of Wildlife (Appendix 3).

Since first reaching its maximum elevation of 6,924 ft in June of 1987, reservoir elevation has

varied with a low of 6,806 ft occurring in October 2002 (Figure 18). Data collected each month

(April – November) in 1987 by the Colorado Division of Wildlife shows that McPhee Reservoir

began stratifying in April and the stratification lasted into October (Figure 19, Appendix 3).

Dissolved oxygen in 1987 began stratifying in July, peaking in September with stratification

continuing to be present into November (Figure 20). Data collected fall 2004 and summer 2005

by the Bureau of Reclamation shows similar stratification patterns.

Data collected by the CDOW in 2003 and 2004 near the outlet works show that fish are

distributed from near the surface, through the thermocline down to 10 meters above the bottom

gates (sonar data). Gill net data from near the outlet works captured 1 small mouth bass 4 meters

below the level of the SLOW, several Kokanee salmon and rainbow trout. No white suckers

were captured in the gill nets which is expected given that white suckers are benthic foragers and

avoid predators in open waters (Figure 21).

Dissolved Oxygen in the Dolores

Mean concentration of dissolved oxygen (grab samples) at the USGS Bedrock Gage (data

obtained from the USGS) was greater prior to the construction (1965-1984) of McPhee Dam for

the months of March, May, June and August when compared to the post dam dissolved oxygen

data (1984-2007, Figure 22).

Temperature and dissolved oxygen data was also collected with a YSI sonde at three sample

stations: below McPhee Dam, Ferris Creek Campground and Bradfield Bridge, September 17-

19th

, 2008. The data show low dissolved oxygen concentrations (5.99mg/l @ Bradfield Bridge

and 6.06mg/l @ Ferris Creek Campground and 6.55mg/l @ the Dam) measured in the early

morning due to biological respiration and decomposition of organic matter (discharge from

McPhee was 40 cfs). The Colorado State dissolved oxygen standard for cold water trout fisheries

is 6mg/l. The chronic temperature threshold for trout (64.9○ F) was not exceeded during the

sample period (Figure 23). Dissolved oxygen was also less than the 6mg/l at several locations in

DRD Reach 1 (McPhee Dam to Bradfield Bridge) measured June 25, 1990.

Page 11: Modeling the Relationship Between McPhee Dam Selective

10

Conductivity and pH in the Dolores

Mean conductivity (grab samples) at the USGS Bedrock Gage prior to the construction of

McPhee Dam 1965-1984 data) was greater for the months of July through November and less for

the month of June compared to post McPhee data (1984 – 2007, Figure 24). Mean daily

conductivity at the USGS Ciscoe, Utah gage prior to the construction of the McPhee Dam (1951-

1984) was greater for each month of the year except June compared to post McPhee data (1984 –

2004, Figure 25). Mean pH at the USGS Bedrock Gage prior to the construction of McPhee Dam

was less for each month of the year with greater variability (Figure 26).

Limiting Nutrient Analysis in the Dolores

Quantitative limiting nutrient analysis for algae using artificial nutrient diffusing substrates

(NDS) took place in September of 2007 along the Dolores River at three sites: Dolores below

McPhee dam, Dolores at Ferris Canyon Campground and Dolores at Bradfield Bridge.

Twenty clay saucers containing a 2% agar solution with four different treatments were deployed

on the Dolores River at each station to determine whether nitrogen or phosphorus were limiting.

The four treatments were: Control (i.e., ambient nutrient chemistry) (C); nitrogen-supplemented

(N); phosphorus-supplemented (P); and nitrogen and phosphorus-supplemented (NP).

Nutrient concentrations for the phosphorus treatments were 0.1 M K2H2PO4; for the nitrogen

treatment was 0.5 M NaNO3 and for the NP treatment was a combination of the two. Control

saucers (C) were placed upstream of NDS saucers, and all saucers were deployed at the same

depth. Five replicates of each treatment at each site were deployed. Saucers were deployed on

September 18th

, 2008 and retrieved after 2 weeks of incubation time.

The periphyton was scrubbed off with a brush and rinsed with de-ionized water to capture the

periphyton grown on the tiles. The periphyton was transferred to label Whirl-Pak bags. Samples

were processed at the B.U.G.S. lab according to state and EPA approved Standard Operating

Procedures to measure quantity of periphyton growing on the tiles.

The addition of nitrogen and phosphorus to tiles at Bradfield Bridge resulted in significantly

greater amounts of algal growth measured as concentration of chlorophyll-a (Figure 29). It does

not appear there is a specific limiting nutrient discharged from McPhee Reservoir but rather both

highly reactive forms of nitrogen and phosphorus are being discharged from the bottom of the

reservoir resulting in the high amounts of periphyton biomass found below the dam.

Periphyton biomass data was also collected from cobble substrate in riffles at the same sample

sites and during the same sample period as the NDS study and biomass was measured using

chlorophyll-a and ash-free dry mass (AFDM) analyses. Data was incorporated into the

periphyton biomass database (Figure 3).

Discussion

Clearly McPhee Dam has altered downstream hydrology, temperature, pH, conductivity and

dissolved oxygen. The Selective Level Outlet Works were designed to minimize the deleterious

effects of many of the water quality impacts and to meet downstream water quality goals.

Page 12: Modeling the Relationship Between McPhee Dam Selective

11

Existing goals and constraints are many and varied (Appendix 4) and, although there exists the

Selective Level Outlet Works at McPhee (unlike most dams), the opportunities to meet a large

number of goals are still limited.

Utilizing the SLOWs fully may benefit either or both the trout and the native fish. Further

refinement of the models and better understanding of life history needs of native fish may

identify such opportunities to benefit the native fisheries – i.e. through better cueing and timing

of reproduction by manipulating water temperatures with the SLOWs. Also, ther may be an

opportunity to expand native fisheries habitat upstream with warmer baseflows.

Because white suckers are benthic, utilizing the upper SLOWs with the powerplant on line will

not increase the probability of white suckers being entrained and surviving a journey into and

through the turbines. Utilizing the upper SLOWs, however, may increase the probability of small

mouth bass being entrained into the SLOWs and with warmer water temperatures downstream

the probability of survival of white suckers and small mouth bass may increase if they do make it

through the SLOWs and the turbines. Warmer downstream temperatures due to use of the upper

SLOWs may also increase habitat of small mouth bass upstream of Dove Creek Pumps. There

may, however, be opportunity to reduce populations of small mouth bass by mis-cueing them to

reproduce at the wrong time of year. Further understanding of the impacts that the SLOWs

could have on downstream water temperatures and of the life-history characteristics of both

native and non-native fish is important.

Water temperature models A model has been employed to predict discharge temperature from McPhee Reservoir given

various release scenarios through the SLOWs at various reservoir elevations, discharge rates and

dates. Another model has been developed to predict the effects of water temperature released

from McPhee Reservoir on downstream water temperatures. In addition to these models, baseline

data has been collected to determine the effect of different release scenarios on downstream algal

biomass and consequent impacts to dissolved oxygen.

Purpose of models and baseline:

1. Evaluate the degree that periphyton biomass can be reduced in downstream reaches;

2. Understanding the response of the concentrations of dissolved oxygen to decreasing

levels of algal biomass;

3. Predict changes in water temperature in the Dolores River below McPhee Dam if the

SLOWs were to be fully utilized;

4. Create operational recommendations for the SLOWs for McPhee Dam Managers and

Operators to meet particular downstream goals.

SELECT Reservoir model

SELECT is a numerical, one-dimensional model of selective withdrawal developed at the U.S.

Army Engineer Research and Development Center to compute withdrawal characteristics and

release water quality for various operational alternatives. The spreadsheet implementation of the

SELECT model provides an interactive environment for the application of the model. Input

parameters include release elevation (s) and discharge at each release point; output is water

Page 13: Modeling the Relationship Between McPhee Dam Selective

12

quality parameters – temperatures, dissolved oxygen, pH and specific conductivity. The Bureau

of Reclamation has provided the DRD with guidance regarding the SELECT model and will be

collecting input data for the model May, July and September 2010. Data collected by the CDOW

will also be input into the SELECT model further refine discharge values through the SLOWs.

River Water Quality Model

B.U.G.S. Consulting created a multiple regression equation to predict maximum water

temperature at Bradfield Bridge for the purpose of determining the degree that eliminating

releases from the bottom of the reservoir during summer/fall months and utilizing SLOW 1 and

SLOW 2 would affect maximum temperature in downstream reaches. To develop the regression,

input parameters were: daily maximum temperature of water discharged from McPhee (from the

SELECT Model), discharge (Q) from McPhee, average air temperature at Bradfield Bridge,

angle of sun, and maximum water temperature at Bradfield Bridge.

If the River Model developed for predicting water temperature downstream of McPhee Reservoir

suggests that full operation of the SLOW (including SLOW 1 and SLOW 2) would be effective

at improving water quality, operational changes of McPhee Dam to further refine a water quality

operations model and improve water quality below McPhee Dam would be worth considering. If

serious consideration is given to use of SLOW 1 and SLOW 2, in addition to SLOW 3 which is

currently used on a regular basis, then it would be important to further evaluate whether the

probability of live escapement of non –native fish increases and the potential that warming of the

downstream environment results in an expansion of the area currently occupied by small mouth

bass (Dolores Project Biology Committee 2010).

Methods

The predictive model was developed using 2008 and 2009 discharge and temperature data

collected by the Dolores Water Conservancy District.

Input parameters for the model development (See Appendix 2):

• Maximum water temperature at Bradfield Bridge;

• Flow from McPhee Dam;

• Maximum water temperature in the stilling basin below McPhee Dam;

• Average air temperature collected at Bradfield Bridge; and,

• Angle of the sun.

Utilizing an Excel based multiple regression equation generator and analysis tool, the resulting

model equation (linear multiple regression equation) is:

Predicted maximum water temperature @ Bradfield Bridge = 0.27 X

Angle of Sun + 0.51 X Average Air Temp - 0.03 X Flow Below McPhee

Dam + 0.43 X Water Temp. Below McPhee Dam + 1.3

This equation was applied to the existing data set and graphically analyzed showing that the

model slightly over-predicts water temperature at the upper end of actual water temperature

ranges (Figure 27). Because the model is linear and input flow data was limited (i.e. low flow

Page 14: Modeling the Relationship Between McPhee Dam Selective

13

data was incremental and not continuous) the model only works well at flows between 30 and

100 cfs, tending to over-predict water temperature at flows greater than 100 cfs.

Using the 75th

percentile of the water temperature data found at the level of the 3rd

SLOW in the

reservoir, the 75th

percentile of average air temperature at Bradfield Bridge and a flow of 75 cfs

below McPhee Dam, the model predicts a maximum daily water temperature of 72.24O

F in June,

74.97O

F in July and 72.57 O

F in August at Bradfield Bridge (Figure 28). These values are just

above or below the acute maximum daily temperature for trout (74.9 O

F). Daily maximum water

temperatures between Bradfield and McPhee Dam would be less.

Conclusions

Given reservoir temperature and a release of 75 cfs in June and July the river model predicts that

by eliminating releases from the bottom of the reservoir and only using SLOW 3 the probability

of exceeding the acute temperature threshold for trout in DRD Reach 1 (McPhee Dam to

Bradfield Bridge) is low.

Because the water quality model tends to over predict maximum water temperatures at Bradfield

Bridge during the critical time frames (June – September) and a conservative use of the 75th

percentile of water temperature at the 3rd

SLOW and 75th

percentile of average air temperature

were used as input parameters and the acute temperature for cold water fisheries was just reached

at Bradfield Bridge by model predictions, I conclude that the use of the SLOWs should be

further studied to determine the degree that they can be utilized to improve downstream water

quality conditions (primarily algal biomass, dissolved oxygen, temperature and other parameters

associated with over-enrichment of rivers – i.e. ammonia toxicity). Further use of the SLOWs

and their impacts can be experimentally completed utilizing baseline data collected on fish

biomass, algal biomass, dissolved oxygen and temperature as response variables. It would be

prudent to take the Biology Committees recommendation (Spring 2010) and complete a thorough

investigation of fish entrainment through the outlet works as well and to repair the thermometers

that were originally installed at each SLOW outlet.

Next Steps

The following next steps will be completed 2010:

1. Collecting data on temperature, pH, dissolved oxygen and nutrients at various levels in

the reservoir near the SLOWs

2. Collecting diurnal data monthly, at 6 sample sites (Bradfield Bridge to Bedrock) on

temperature, pH, and dissolved oxygen; and,

3. Creating a predictive, more accurate, non-linear multiple regression model that includes

the interaction between date and reservoir elevation to be utilized by dam managers for

management of the SLOWs through the summer months year.

References Correl, David L. 1998 The Role of Phosphorus in the Eutrophication of Receiving Waters, A

Review. Journal of Environmental Quality. 27: 261-268.

Page 15: Modeling the Relationship Between McPhee Dam Selective

14

Cheslak, Edward, and Jeannette Carpenter. 1990. Compilation report on the effects of reservoir

releases on downstream ecosystems. U.S. Department of the Interior, Bureau of

Reclamation, Rec-Erc-90-1.

Colorado Department of Public Health and Environment. 2007. Water Quality Control

Commission Temperature Criteria Methodology, Policy Statement 06-1.

Graf, David and John Porter, Dolores River Dialogue Hydrology Report. 2004.

Schneider, Michael L., Steven C. Wilhelms, and Laurin I. Yates. 2004. SELECT Version 1.0

Beta: A One-Dimensional, Reservoir Selective Withdrawal Model, Spreadsheet. US

Army Corps of Engineers, Coastal and Hydraulics Laboratory, Engineer Research and

Development Center Water Operations Technical Support Program, ERDC/EL SR-04-1

Vermelyen, Tracy, B., and Connie DeMoyer, Wayne Delzer, and Dennis Kubly. 2003. A survey

of Selective Withdrawal Systems. U. S. Department of Interior, Bureau of Reclamation.

Denver Technical Service Center, Water Resources Services, Water Resources Research

Laboratory. Report R-O3-02.

Page 16: Modeling the Relationship Between McPhee Dam Selective

15

APPENDICES

Appendix 1. History of Dolores River Diversions and the Dolores Project (from the DRD Hydrology Report)

The first diversions from the Dolores River, except for domestic purposes, were in 1875. These

diversions were for agricultural purposes stretching from Rico and Dunton at the high end of the

basin to Paradox Valley at the lower end of the basin. The amount of water diverted was

negligible – less than 10,000 acre-feet per year. In 1883 the Cortez Canal Companies No1 &

No2 were privately incorporated and funded. The purpose of those two companies was to

develop the infrastructure to trans-basin divert up to 1,400 cubic feet per second from the

Dolores Basin to irrigable lands in the upper areas of McElmo Creek, tributary to the San Juan

River. Two physical diversions were constructed. One was a 1 ½ mile long tunnel and the other

was 6 mile long canal. Diversion of water first began in 1886. From that day forward, until

McPhee Dam was constructed, Montezuma Valley Irrigation Company, successor to the original

two Canal Companies, diverted the entire Dolores River from the conclusion of the spring runoff

until the end of the irrigation season, in late October.

During the 1970s planning for the needs of the multi-purpose Dolores Project, the BOR, not only

planned for the traditional uses of a project, but planned for two unique / non-traditional needs.

First, the Dolores Project would be the means for satisfying Ute Mountain Ute Indian Tribe’s

(“UMUT”) Winters Doctrine claims to the Mancos River; and second, a year-round by-pass flow

for a trout fishery below McPhee Dam.

To get the water for what was considered up until then, non-traditional needs, the BOR

converted the design of non-Indian Full Service irrigation features of Project from an open ditch

surface delivery system to an "underground pipeline / pressurized" system. Doing so saves

enough water to meet the needs of the two purposes described above. One, it provided 23,200

AF of water for the UMUT to irrigate 7,500 acres of land. It also provided 25,400 AF of water

for a trout fishery below McPhee Dam.

The BOR realized that without being able to develop all of the flow of the Dolores River (to do

so meant flooding the town of Dolores) the downstream fishery would have to share water

supply shortage commensurate with other users, specifically irrigators. The method the BOR

chose to administer such a shortage was to incorporate into the Final Environmental Impact

Statement (“EIS”) a mechanism whereby the release below McPhee would be 20, 50, or 78 cfs,

depending on whether it was a dry, normal or wet year. The type of year was to be determined

on March 1st of each year based on the content of the reservoir and the relative amount of snow

pack. If those two criteria established a "dry" year then 20 cfs would be released for the next 365

days. If the formula determined a "normal" year then 50 cfs would be the next years release and

if it was a "wet" year, then 78 cfs was the annual release.

Construction of McPhee Dam was completed in the fall of 1983. Filling began in the spring of

1984. The Division of Wildlife (“DOW”) began a fish-stocking program below the dam in the

Page 17: Modeling the Relationship Between McPhee Dam Selective

16

fall 1983 and continued throughout the filling of the reservoir and beyond. A quality fishery was

established. Filling of the reservoir was completed in 1987. Very few irrigators were on line, so

there was plenty of water for the downstream fishery during filling. The release was set at 150

cfs until the drought of 1988 through 1992.

In accordance with the Project's EIS, the March 1st 1990 content of the reservoir and the snow

pack dictated a "dry" year, meaning a 20 cfs downstream release. Contrary to the Environmental

Impact Statement (“EIS”) guidelines, the District & the BOR agreed to re-evaluate the criteria on

May 1st. As a result of April precipitation, the calculation was much nearer being a "normal”

year, which would have designated a 50 cfs release, but the absolute criteria still indicated “dry”,

so the District and the BOR abided by the EIS guidelines and set the release at 20 cfs. Had the

calculation been redone on May 5th it would have clearly been a normal year.

In May, the Five Rivers Chapter of Trout Unlimited (“TU”) wrote "arbitrary selection of water

use and management by DWCD is offensive and wrong”. Naturally, the District responded with

a defensive retort as follows: “More water for the fishery hurts all the other users”. By June 10th

the 20 cfs was clearly having a negative effect on the fishery. The word on the street and in the

State's newspapers was, “Dolores means river of sorrow” - “The River will die” – “lawsuit in

works”. On June 12th the BOR in Washington - ordered the gates below McPhee be opened -

that the flow be increased back to 78 cfs. The District's response was, “the EIS is being abided

by”, and “By what authority do you make such a request”. I gather, somewhat uniquely, the

DWCD owns the projects water rights, rather than the Federal Government.

The stage was set for a confrontation. In many cases the better way to manage water is obvious.

In this case it was clear that if a way could be found to manage the fishery release in such a

manner that water could be saved during the winter season for higher flows during the summer (a

pool concept) the fishery would benefit. However, the irrigators would suffer greater shortages

during consecutive drought years.

Changing from a “flow release” to a “managed pool” was a process which took 6 years. In 1996

an Environmental Assessment was issued, with a FONSI (Finding of No Significant Impact)

which officially changed the release below McPhee Dam from an "annual flow" to a "managed

pool". In addition the parties agreed to work together to create a pool of 36,500 AF of water for

the fishery. As of 2010, the pool of water available for downstream uses includes 29,300 AF of

Project water allocated to fisheries, 1274 AF of non-project downstream senior water ( although

this quantity is subject to river administration and downstream ‘beneficial uses’), and 700AF of

Project water to meet augmentation needs at the Paradox Salinity Unit (this amount does not

share shortages). Therefore, on a year when all Project allocations can be met, the water

available for downstream uses is 31,274AF. In years when all project allocations cannot be met

(e.g., 2002) all except the Paradox Augmentation shares the shortage with other project

allocations. Trout Unlimited and DWCD cooperatively provided the leadership in forming an ad

hoc group, in 1997, called the Dolores River In-stream-flow Partnership (DRIP). The purpose of

the group was to “work together to create a pool of 36,500 AF” for the downstream fishery. The

focus of the DRIP effort was for more water. Many options were explored. A consensus could

not be reached and because of the 2000 - 2004 drought the DRIP process was suspended.

Page 18: Modeling the Relationship Between McPhee Dam Selective

17

In the fall of 2003, San Juan Citizen’s Alliance, guided by Chuck Wanner (SJCA staff) and

DWCD, guided by Steve Arveshough, (DWCD Gen. Manager) resurrected talks. That

collaborative effort resulted in the formation of the Dolores River Dialogue.

Appendix 2. Dolores River temperature data compiled from data provided by the Colorado Division of Wildlife and the Dolores Water Conservancy District (see separate document).

Appendix 3. Reservoir data compiled from data provided by the Colorado Division of Wildlife and the Bureau of Reclamation (see separate document).

Appendix 4. Existing McPhee Dam Operational Constraints

There are 2 distinct operational discharges from McPhee Dam – 1) spill-discharge and base-

discharge. Spill-discharge usually occurs in the spring when predicted inflow from snowmelt

exceeds the available storage capacity in the reservoir and the excess water is discharged through

the 2 large gates at the bottom of the reservoir. To the degree possible this water is managed for

recreational and commercial boating. Spill discharge occurred once in the fall 1999 due to low

demand for irrigation water that left a relatively full reservoir and high inflow from a large

rainfall event.

Base-discharge begins when demand for water from the reservoir exceeds inflow and water for

downstream purposes is discharged through the 3rd

SLOW, the turbines and the bottom by-pass

gate. Beginning April 1rst, 31,978 acre feet of water known as the fish pool water and managed

by the Biology Committee begins to be used. The clock for the fish pool ends October 1rst.

The amount of water that can be stored each year in the reservoir depends on reservoir elevation

at the beginning of the spring-runoff period which in turn depends on the level that the reservoir

was filled the previous spring, the amount of inflow and demand for water since the reservoir

was filled. Spill water cannot be used to enhance base-flows.

Dam operations since the construction of the power-plant in 1993 for spill-discharge has

consisted of discharges up to 4,500 cfs through the large gates at the bottom of the reservoir plus

75 cfs through the turbines to generate power. Dam operation to date for base-discharge has been

through the 3rd

Selective Level Outlet Work (SLOW) and the turbines plus additional flows

through the bypass gate at the bottom of the reservoir to meet downstream priority water rights

and base-flow recommendations from the Biology Committee.

Other constraints include:

Page 19: Modeling the Relationship Between McPhee Dam Selective

18

• If at all possible, no water is to ever be released over the spillway to avoid introduction of

non-native fish and damage to the spillway;

• To satisfy water supply contracts the reservoir must be filled to capacity each year and

carry-over to the next year must be maximized;

• If the reservoir cannot be filled to capacity, then shared shortage is required by law for all

water supply contracts including non-priority water for downstream uses such as the

fisheries.

• Spill-discharges are required to be managed for rafting, meaning flows near 1000 cfs for

as long as possible.

• The Bureau of Reclamation desires to continue use of and maximize use of the turbines

to generate power.

Page 20: Modeling the Relationship Between McPhee Dam Selective

19

Figures

Figure 1. Selective Level Outlet Works showing the 2nd and 3rd inlets. The 1rst inlet faces the dam. The sills

of the inlets are located at elevations 6,892 (SLOW 1), 6,896 (SLOW 2) and 6,840 feet (SLOW 3). Full

reservoir elevation is 6,924 ft. Note the proximity of the 3rd SLOW to the benthos, habitat for white suckers.

SLOW 3

SLOW 2

SLOW 1

Dam Face

Full Pool

Shaft House

Dam

Face

Benthos

Page 21: Modeling the Relationship Between McPhee Dam Selective

20

Figure 2. Copy of blue prints cross section of Selective Level Outlet Works (SLOWs)

Page 22: Modeling the Relationship Between McPhee Dam Selective

21

0

2

4

6

8

10

12

14

Do

lore

s @

Da

m

Flo

rida

@ D

am

An

ima

s @

Flo

ra V

ista

An

ima

s @

32

nd

Flo

rid

a 2

@ S

alt C

reek

Sam

bri

to

An

ima

s @

We

ase

lskin

Do

lore

s @

Bri

dg

e

Flo

rida

@ R

ed

Cre

ek

Do

lore

s @

Ca

mp

gro

un

d

Flo

rid

a 1

@ 1

60

Pin

e 1

Lo

ng

Ho

llow

An

ima

s @

Fa

rmin

gto

n

An

imas @

Hig

h B

rid

ge

An

ima

s @

Tw

in C

rossin

gs

Dry

Cre

ek

An

imas a

bv W

WT

P

Ute

Cre

ek

Pin

e 2

@ L

a B

oca

Sa

n J

ua

n B

el C

on

fl

An

ima

s @

An

idu

rco

Anim

as @

Basin

Cre

ek

An

ima

s @

Azte

c

Sto

llste

ime

r

Ign

acio

Cre

ek

Pie

dra

2

Rock C

reek

Pin

e B

elo

w D

am

Ch

err

y C

ree

k

Sa

n J

ua

n 2

Sa

n J

ua

n 1

Ca

sca

de

Cre

ek

Na

va

jo R

ive

r

Casca

de B

elo

w L

ime

Salt C

ree

k

Be

ave

r C

reek

Pin

e @

Lla

ma R

an

ch

Pie

dra

1

Do

wn C

asca

de

Ck

Lim

e C

reek

La

Pla

ta 2

Anim

as @

Tri

mb

le

Sp

rin

g C

reek

An

ima

s @

Ja

me

s R

an

ch

La

Pla

ta 1

AF

DM

(m

g/m

2)

F

e

r

r

i

s

B

r

a

d

D

a

m

NMED Criteria = 5

mg/cm2

Figure 3. Quantity of organic matter (median ± 75th

and 25th

percentile) measured as ash-free dry mass in relation to other streams in the region. Note,

the Dolores sites (@ dam, Ferris Creek Campground and Bradfield Bridge) are at the high end of concentrations. The Colorado Department of Public

Health and Environment is in the process of setting nutrient criteria. The New Mexico Environment Department has established a regional criterion of

5mg/m2.

Page 23: Modeling the Relationship Between McPhee Dam Selective

22

Dolores @ Dolores, 1896-2009

1

10

100

1000

10000

1 2 3 4 5 6 7 8 9 10 11 12

Month

CF

S -

Med

ian

± 2

5th

Perc

en

tile

Figure 4. Median (±25th

percentiles) discharge at the USGS Gage located above the MVIC diversion. Because

there are few diversions above this site this graph is a close illustration of the native hydrograph.

Dolores Near McPhee, 1939-1952

1

10

100

1000

10000

1 2 3 4 5 6 7 8 9 10 11 12

Month

CF

S -

Me

dia

n ±

25

th P

erc

en

tile

Figure 5. Median (±25th

percentiles) discharges at the old town site of McPhee, CO (now buried by McPhee

Reservoir) below the MVIC diversion during dates prior to the construction of McPhee Dam and after

construction of the Great Cut Diversion. During the months of August through November, flows were less

than 10 cfs 50% of the time.

Page 24: Modeling the Relationship Between McPhee Dam Selective

23

Dolores @ Bedrock

1

10

100

1000

10000

1 2 3 4 5 6 7 8 9 10 11 12

Month

Me

dia

n c

fs

Median cfs Predam Median cfs Postdam

Figure 6. Median discharge at the USGS Bedrock Gage. Median flows prior to the construction of McPhee

Dam were less than after the construction of McPhee Dam July through November and greater April through

June.

Dolores Below McPhee Reservoir, 1986 - 2009

1

10

100

1000

10000

1 2 3 4 5 6 7 8 9 10 11 12

Month

CF

S -

Me

dia

n ±

25th

Pe

rcen

tile

Figure 7. Median discharge (±25th

percentiles) from McPhee Dam. Median flows were 30 cfs or greater for

each month of the year. Note the 10 fold decrease in post-dam median flows for the months of April and June

(see Figure 5).

Page 25: Modeling the Relationship Between McPhee Dam Selective

24

Dolores @ Confluence w/Colorado River

100

1000

10000

1 2 3 4 5 6 7 8 9 10 11 12

Month

Med

ian

cfs

Median cfs Predam Median cfs Postdam

Figure 8. Discharge at the Ciscoe, Utah USGS gage. Median flows were less prior to the construction of

McPhee dam for the months of August through March. Median flows were greater in the Dolores prior to the

construction of McPhee Dam for the months of May and June.

Page 26: Modeling the Relationship Between McPhee Dam Selective

25

Mean Daily McPhee Release

DWR - Dol District Data

10

100

1000

10000

1/1

/86

1/1

/87

1/1

/88

1/1

/89

1/1

/90

1/1

/91

1/1

/92

1/1

/93

1/1

/94

1/1

/95

1/1

/96

1/1

/97

1/1

/98

1/1

/99

1/1

/00

1/1

/01

1/1

/02

1/1

/03

1/1

/04

1/1

/05

1/1

/06

1/1

/07

1/1

/08

1/1

/09

Q (

cfs

)

Figure 9. Discharge data from McPhee Reservoir illustrating the low summer/fall flows in 1990, 2002, and 2003.

Page 27: Modeling the Relationship Between McPhee Dam Selective

26

0

5

10

15

20

25

1 2 3 4 5 6 7 8 9 10 11 12

Month

Mea

n T

em

p (

c)

± S

E

Predam Postdam

Predam Data, 1965-1984Postdam Data, 1984-2007

Figure 10. Pre and post dam differences in mean (± SE) daily water temperature (oC) collected at the USGS

Gage at Bedrock, CO (grab samples). Note differences in April and June during the spawning period for

native fish.

0

5

10

15

20

25

1 2 3 4 5 6 7 8 9 10 11 12

Month

Me

an

Tem

p (

c)

± S

E

Predam Postdam

Predam data = 5/1/1949 - 2/29/1984

Postdam data = 3/1/1984 - 8/17/2004

Figure 11. Mean (± SE) daily temperatures at the Ciscoe USGS Gage. Mean temperatures were less prior to

the construction of McPhee Dam January through July. Data set includes data from 1986, 87, 88, 90, 02 and

05 through 09.

Page 28: Modeling the Relationship Between McPhee Dam Selective

27

45

50

55

60

65

70

75

80

Sti

ll P

on

d

Me

tas

ka

Lo

ne

Do

me

Brd

fld

Bri

dg

e

Do

ve

Crk

Pu

mp

s

Up

.

Dis

sa

po

intm

en

t

Sli

ck

Ro

ck

Me

an

SD

) o

f D

ail

y M

ax

imu

m T

em

pe

ratu

re (

F)

Figure 12. Mean ± standard deviation of daily maximum temperature at 7 sites, McPhee dam downstream to

Slick Rock. Ambient temperature is reached near Disappointment Creek where temperature of the water

discharged from the dam has little influence on temperatures found in the river.

30

35

40

45

50

55

60

65

70

75

80

1 2 3 4 5 6 7 8 9 10 11 12

Month

Avera

ge o

f D

ail

y M

axim

um

Tem

pera

ture

(F

)

McPhee Stilling Pond

Metaska

Lone Dome

Slickrock

Bradfield

Up. Dissapointment

Dove Creek Pumps

Figure 13. Average of daily maximum temperature at 7 sites, McPhee Dam downstream to Slickrock. Winter

temperature upstream of Bradfield Bridge is greater than winter water temperature Bradfield Bridge

downstream showing the influence of the dam in DRD Reach 1 (McPhee to Bradfield Bridge).

Page 29: Modeling the Relationship Between McPhee Dam Selective

28

10

20

30

40

50

60

70

80

90

5/2/

1990

5/9/

1990

5/16

/199

0

5/23

/199

0

5/30

/199

0

6/6/

1990

6/13

/199

0

6/20

/199

0

6/27

/199

0

7/4/

1990

7/11

/199

0

7/18

/199

0

7/25

/199

0

8/1/

1990

8/8/

1990

8/15

/199

0

8/22

/199

0

8/29

/199

0

9/5/

1990

9/12

/199

0

9/19

/199

0

9/26

/199

0

Dis

ch

arg

e (

cfs

)

50

55

60

65

70

75

80

85

Tem

p (F

)

Discharge Max Daily Temp Acute Thrshold Chronic Thrshld Min Daily Temp

Figure 14. May 1rst

through September 30th

daily maximum and minimum temperature and discharge data

during the 1990 drought, measured at Bradfield Bridge. Note that the chronic temperature threshold for

trout was exceeded twice for periods greater than 24 hours and the acute temperature threshold was

exceeded on 5 dates at discharges of both 20 and 50 cfs.

10

20

30

40

50

60

70

80

90

5/15

/200

2

5/22

/200

2

5/29

/200

2

6/5/

2002

6/12

/200

2

6/19

/200

2

6/26

/200

2

7/3/

2002

7/10

/200

2

7/17

/200

2

7/24

/200

2

7/31

/200

2

8/7/

2002

8/14

/200

2

8/21

/200

2

8/28

/200

2

9/4/

2002

9/11

/200

2

9/18

/200

2

Dis

ch

arg

e (

cfs

)

50

55

60

65

70

75

80

85

Tem

p (F

)

Discharge Max Daily Temp Chronic Thrshld Acute Thrshld Min Daily Temp

Figure 15. May through September daily maximum and minimum temperature and discharge data during

the 2002 drought, measured at Bradfield Bridge. Note that the chronic temperature threshold for trout was

exceeded several times for periods greater than 24 hours and the acute temperature threshold was exceeded

Page 30: Modeling the Relationship Between McPhee Dam Selective

29

on numerous occasions. Discharge from McPhee less than 20cfs. No temperature data available for 2003 also

a period of very low discharge from McPhee.

30

40

50

60

70

80

90

100

6/25

/200

9

7/2/

2009

7/9/

2009

7/16

/200

9

7/23

/200

9

7/30

/200

9

8/6/

2009

8/13

/200

9

8/20

/200

9

8/27

/200

9

9/3/

2009

9/10

/200

9

9/17

/200

9

9/24

/200

9

10/1

/200

9

10/8

/200

9

Dis

ch

arg

e (

cfs

)

40

45

50

55

60

65

70

75

80

Tem

pera

ture

(F)

Ave CFS Bel McPh Max Wat Tmp Brad Chronic Wat Tmp

Acute Wat Tmp MinWatTempBrad

Figure 16. Discharge from McPhee and daily maximum and minimum temperature at Bradfield Bridge in

2009. The chronic temperature threshold for trout (64.9o F) was never exceeded for more than 24 hours and

the acute temperature threshold for trout (74.9o F) was never exceeded at flows of 70 cfs during the summer

months.

76

77

78

79

80

81

82

83

84

85

86

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

Year

Tem

pera

ture

(F

)

Yearly Average Overall Average

Figure 17. Overall (1987-2009) and summer (July through September) average of maximum daily air

temperature. Data collected at Great Cut operations center.

Page 31: Modeling the Relationship Between McPhee Dam Selective

30

6830

6840

6850

6860

6870

6880

6890

6900

6910

6920

6930

3/2

0/1

984

3/2

0/1

985

3/2

0/1

986

3/2

0/1

987

3/2

0/1

988

3/2

0/1

989

3/2

0/1

990

3/2

0/1

991

3/2

0/1

992

3/2

0/1

993

3/2

0/1

994

3/2

0/1

995

3/2

0/1

996

3/2

0/1

997

3/2

0/1

998

3/2

0/1

999

3/2

0/2

000

3/2

0/2

001

3/2

0/2

002

3/2

0/2

003

3/2

0/2

004

3/2

0/2

005

3/2

0/2

006

3/2

0/2

007

3/2

0/2

008

3/2

0/2

009

Re

se

rvo

ir E

lev

ati

on

SLOW 3

SLOW 1

SLOW 2

Reservoir Elevation

Figure 18. Reservoir Elevation in relationship to the SLOWs. The 3rd SLOW was less than 20 feet below the water surface from July 15th

2002 to

February 24th

2003.

Page 32: Modeling the Relationship Between McPhee Dam Selective

31

Figure 19. Thermoclines for McPhee Reservoir measured at the dam in 1987 in relation to the SLOWs. Note that the top

of the thermocline was between SLOW 1 & 2 for the September and November sample dates and at or above the SLOW

1 for May, June, July and August sample dates and non-existent for April.

4 6 8

10

12

14

16

18

20

22

0

-3

-6

-9

-12

-15

-18

-21

-24

-27

-30

-33

-36

-39

-42

-45

-48

-51

-54

-57

-60

-63

-66

-69

-72

-75

-78

(Depth (m

Temp (c)

Ap

ril

May

Jun

e

July

Au

gu

st

Se

pte

mb

er

No

ve

mb

er

SLOW 1

SLOW 3

SLOW 2

Bypass

Gates

Page 33: Modeling the Relationship Between McPhee Dam Selective

32

Figure 20. Dissolved oxygen-clines for McPhee Reservoir measured at the Dam in 1987 in relation to the SLOWs. Note

that the top of the oxygen-cline was between SLOW 2 & 3 for September and November and between SLOW 1 and 2 for

August and at or above the SLOW 1 for July and non-existent for April and May.

3 4 5 6 7 8 9

10

0

-3

-6

-9

-12

-15

-18

-21

-24

-27

-30

-33

-36

-39

-42

-45

-48

-51

-54

-57

-60

-63

-66

-69

-72

-75

-78

Depth (m)

DO (mg/l)

Ap

ril

May

Jun

e

July

Au

gu

st

Se

pte

mbe

r

Novem

ber

SLOW 1

SLOW 2

SLOW 3

BypassGates

Page 34: Modeling the Relationship Between McPhee Dam Selective

33

Figure 21. Fish, thermocline and oxygen-cline data collected August 2003. The 3rd

Selective Outlet Work was just below

the clines 8-5-03. Sonar data indicates fish living below the clines. Vertical gill nets set for 24 hours caught 20 fish of

which 1 was a small mouth bass. The others were Kokanee Salmon, Rainbow and Brown Trout. Reservoir elevation

August 5-8, 2003 averaged 15-17.5 meters below full. July 21rst, 2004 it was 9m below full and 8-24-1994 it was 6m

below full. All catch depths are in relationship to elevation of the SLOWs.

6 11 16 21 26

0

-4

-8

-12

-16

-20

-24

-28

-32

-36

-40

-44

-48

-52

-56

-60

-64

-68

-72

-76

Temp (c)

3.5 4.5 5.5 6.5

DO (mg/l)

Max o

f Tem

p. ©

Max o

f DO

(mg

/l)

0 50 100 150

0

-4

-8

-12

-16

-20

-24

-28

-32

-36

-40

-44

-48

-52

-56

-60

-64

-68

-72

-76

Dep

th (M

)

No .Fish

7- 2

1- 2

004

8- 8

- 2003

8- 7

- 2003

8- 5

- 2003

Benthos

1rst SLOW

Bypass

Gates

3rd SLOW

2nd SLOW

Small Mth Bass

Page 35: Modeling the Relationship Between McPhee Dam Selective

34

6

7

8

9

10

11

12

13

1 2 3 4 5 6 7 8 9 10 11 12

Month

Mea

n D

O (

mg

/l)

± S

E

Predam Postdam

Predam Data, 1965-1984Postdam Data, 1984-2007

Figure 22. Mean concentration of dissolved oxygen at the Bedrock USGS Gage (grab samples). Dissolved oxygen was

less in the Dolores after the construction of McPhee Dam for the months of March, May, June and August despite

lower, post-dam temperatures (see Figure 10) indicating the possible effects of respiration of organic matter on

dissolved oxygen.

Page 36: Modeling the Relationship Between McPhee Dam Selective

35

10

11

12

13

14

15

16

17

18

19

8:3

5

11

:10

1:4

5

4:2

0

6:5

5

9:3

0

12

:05

2:4

0

5:1

5

7:5

0

10

:25

1:0

0

3:3

5

6:1

0

8:4

5

11

:20

1:5

5

4:3

0

7:0

5

9:4

0

12

:15

2:5

0

5:2

5

8:0

0

10

:35

1:1

0

Time

(Tem

p)

5.5

6.0

6.5

7.0

7.5

8.0

8.5

DO

Temp

DO mg/l

CO Criteria (6mg/l)

5.5

6.0

6.5

7.0

7.5

8.0

8.5

DO

(m

g/l

)

Min D.O. Criteria = 6mg/l

6

8

10

12

14

16

18

20T

em

p (

c)

Bradfield Ferris Dam

Bradfield

Min D.O. Criteria = 6mg/l

Figure 23. Temperature and dissolved oxygen data obtained with a YSI sonde at 3 sample stations: Below McPhee

Dam, Ferris Creek Campground and Bradfield Bridge, September 17-19th

2008. Note the low DO concentrations

(5.99mg/l @ Bradfield Bridge and 6.06mg/l @ Ferris Creek Campground and 6.55mg/l @ the Dam measured in the

early morning due to decomposition of organic matter. The State standard for Trout Fisheries is 6mg/l. The chronic

temperature threshold for trout (18.22C) was not exceeded during the time period. Discharge from McPhee

Reservoir was 40cfs.

Page 37: Modeling the Relationship Between McPhee Dam Selective

36

300

500

700

900

1100

1300

1500

1 2 3 4 5 6 7 8 9 10 11 12

Month

Mea

n C

on

du

cti

vit

y (

us

/cm

) ± S

E Predam Postdam

Predam Data, 1965-1984Postdam Data, 1984-2007

Figure 24. Mean conductivity at the Bedrock USGS Gage (grab samples) prior to the construction of McPhee Dam.

The conductivity was greater for the months of July through November and less for the month of June.

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

1 2 3 4 5 6 7 8 9 10 11 12

Month

Me

an

Co

nd

ucti

vit

y (

us/c

m)

± S

E

Predam Postdam

Predam data = 5/1/1951 - 2/29/1984

Postdam data = 3/1/1984 - 8/17/2004

Figure 25. Mean daily conductivity at the Ciscoe, Utah USGS Gage prior to the construction of the McPhee Dam.

Conductivity was greater for each month of the year except June prior to the construction of McPhee Dam.

Page 38: Modeling the Relationship Between McPhee Dam Selective

37

6.5

6.7

6.9

7.1

7.3

7.5

7.7

7.9

8.1

8.3

8.5

1 2 3 4 5 6 7 8 9 10 11 12

Month

Mean

pH

± S

E

Predam Postdam

Predam Data, 1965-1984Postdam Data, 1984-2007

Figure 26. Mean pH at the USGS Bedrock Gage (grab samples) prior to the construction of McPhee Dam. The pH

was less for each month of the year and had much greater variability prior to the construction of McPhee Dam.

40

45

50

55

60

65

70

75

Date

Tem

p (

F)

Actual Predicted

Figure 27. Actual compared to predicted maximum water temperature @ Bradfield Bridge based on a multiple

regression equation using maximum air temperature at Bradfield Bridge, average air temperature at Bradfield

Bridge, discharge (Q) from McPhee Reservoir, maximum temperature of water discharged from McPhee Reservoir,

and angle of the sun . The model tends to over predict water temperatures at actual temperatures greater than 65 oF.

Data collected at Bradfield Bridge in 2008 and 2009.

Page 39: Modeling the Relationship Between McPhee Dam Selective

38

45

50

55

60

65

70

75

80

6/2

5/2

00

9

7/9

/200

9

7/2

3/2

00

9

8/6

/200

9

8/2

0/2

00

9

9/3

/200

9

9/1

7/2

00

9

10/1

/200

9

Te

mp

era

ture

(F

)

20

30

40

50

60

70

80

Dis

ch

arg

e (c

fs)

Pred max wat tmp Brdfield Brdg 75th percentile ave air temp Brdfield Brdg

75th percentile wat tmp @ 3rd SLOW cfs from McPhee

Figure 28. Predicted maximum water temperature at Bradfield Bridge given the 75th percentile of average air

temperature at Bradfield Bridge, the 75th

percentile of water temperature discharged from McPhee Dam from the

3rd SLOW, and 75 cfs, June to September 15th

and 35 cfs after September 15th

from McPhee Reservoir.

0

500

1000

1500

2000

2500

3000

Dam Ferris Bridge

Ch

loro

ph

yll

-a

Nitrogen Phosphorus Nitro/Phos Control

Figure 29. Algal bioassay data. Mean ± S.E. at 3 Dolores River sites: below McPhee Dam, at Ferris Creek

Campground and at Bradfield Bridge. The addition of nitrogen and phosphorus to tiles at Bradfield Bridge resulted

in significantly greater amounts of algal growth measured as concentration of chlorophyll-a. No significant

differences at the upstream sites.