mississippi river long distance sediment pipeline project louisiana office of coastal protection and...

15
Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority Meeting August 19 th , 2009

Upload: aron-melton

Post on 04-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Mississippi River Long Distance Sediment Pipeline Project

Louisiana Office of Coastal Protection and Restoration

Coastal Protection and Restoration Authority Meeting

August 19th, 2009

Page 2: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Presentation Overview

• Goals and Funding

• Project Implementation

• Potential Alternatives

• Crossover Site Selection

• Interaction with other Projects

• Current Activities

• Schedule

Page 3: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Project Goal

Design and construct an efficient sediment

delivery pipeline system from a renewable

resource in the Mississippi River to

strategic locations in Barataria Basin.

Page 4: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Project Funding

• This project is funded by the Coastal Impact Assistance Program (CIAP) and Surplus Funds.

• Current project budget is approximately $66.5M – CIAP $34M

– Surplus $32.5M

• CIAP funds contributed by the State of Louisiana and Plaquemines, Jefferson, and Lafourche Parishes

Page 5: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Phased Implementation

• Expedited Phase 1:– Perform comprehensive planning– Select the “crossover” location– Design and construct the “crossover”

infrastructure (construction advertisement planned for December 2009)

• Later Phases: Design and construction of pipeline extensions into “Area of Need” placement sites in the Barataria Basin

Page 6: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Potential “Crossover” Sites

• Criteria for selection:– Proximity to Area of Need

– Land Rights and Development Constraints

– Constructability

– Sediment Sources

– Oyster Leases

Page 7: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Potential Crossover Sites

Page 8: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority
Page 9: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Potential Sediment Sources

Areas shallower than -70ft

Page 10: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Screening Criteria of Crossover Site• Sediment Supply:

– Renewable borrow sources– Proximity to beneficial use

opportunities

• River Navigation & Existing River Bank Facilities

• Land rights• Environmental & Permitting:

– Impacts to oyster leases– Environmental impacts– Permitting constraints

• Restoration Objectives:– Proximity and access to

restoration opportunities– Restoration benefits

• Costs:– Distances to Areas of Need– Distance to Lafourche Parish– Crossings– Use of existing infrastructure– Synergistic opportunities with

other projects– Connection to natural corridor

(e.g., waterway)

Page 11: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

West Point a la Hache Location • Straightforward land rights• Nearby renewable borrow sites with no navigation issues• Proximity to beneficial sediment reuse opportunities• Greater indirect benefits by reducing storm and salinity

impacts to large areas to the north• Proximity to an existing corridor that provides access to

large portions of the Barataria Basin• Potential to combine permitting efforts with Lake

Hermitage project and reduce schedule• Potential to link on-going marsh creation projects

Page 12: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Interaction with other Projects• Lake Hermitage and West Point a la Hache can “piggy-

back” on the Crossover project– Cost savings– Streamline permitting schedule (permit modification only)– Multiple existing projects can use same pipeline and

infrastructure crossing– Maximum use of existing data collection efforts– Previously designed marsh creation project with permitted

borrow source to begin using Long Distance Sediment Pipeline infrastructure immediately

Page 13: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Current Activities• Land Rights Acquisition• Field-data collection• Preliminary Design• Cost Estimating• Stakeholder Presentations• Over-all project planning (Phase I & II)

– Detailed modeling of borrow source re-fill rates– Geomorphic analysis of regional sediment budgets– Corridor alignments and placement sites– Pipeline construction methodology– Scheduling

Page 14: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Schedule

• 30% Design: August 2009

• Crossover Permit Modification Application:

– “Pre-Application” Meeting June 2009

– Permit Modification Request September 2009

• Final (95%) Design: October 2009

• Bid Documents: November 2009

• Advertise for Construction: December 2009

Page 15: Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority

Laura Belden, P.E.

[email protected]

(225) 342-4592