minutes of 457 - wrpcwrpc.gov.in/occ/457occ_minute.pdfhe requested to amend the shifting of load of...

148

Upload: others

Post on 31-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • MINUTES OF 457TH MEETING OF OPERATION & COORDINATION SUB-COMMITTEE OF WRPC HELD ON 11th MARH 2014

    AT NTPC MUMBAI

    The 457th meeting of Operation & Co-ordination Sub-Committee of WRPC was held on 11th March 2014 at NTPC, Mumbai. The list of participants is enclosed at Annexure-I.

    Shri, G J Despande, RED, NTPC WRHQ-I, Mumbai welcomed all esteemed delegates to 457th OCC meeting of Western Region Power Committee at NTPC Mumbai.

    He wished for qualitative and fruitful discussion during the meeting. Shri P B Behere, GM, NTPC, WRHQ-I, welcomed all the participants & highlighted some of the following important aspects of Grid,facing presently

    1. Synchronization of 765 kV Solapur-Raichur single line, one nation one grid formed and consequent.

    2. Problems for load dispatchers, Generators and Discom’s. 3. Narrow band frequency operation and implementation of DSM. 4. Implementation of RGMO & FGMO in generating units. 5. Over voltage problems. 6. New NTPC units (Mauda-2 (500 MW) & Vindhyachal-12 (500 MW))

    synchronized in grid. He wished for smooth conduct of meeting. Shri S D Taksande, Member Secretary, WRPC extended warm welcome to the

    members and participants of the 457th OCCM. He expressed his gratitude to Shri, G J

    Despande, RED NTPC WRHQ-I, Mumbai, for willingly agreeing to host 457th OCCM at

    NTPC Mumbai. He also thanked to Shri P B Behere GM, NTPC and his team for

    making excellent arrangement for meeting. He intimated that on 10.3.14 there was a

    seminar on “Smart Grid Initiative in India : The Way Forward” organized by IEEE with

    the assistance of WRPC wherein topics like LVDC with focus on DC in Micro grids,

    IEEE Smart Grid Initiatives and IEEE Conformity Assessment Program were

    presented by prominent speakers from Crompton Greaves Ltd. and IEEE.

    He further intimated that :

    1. New IEGC frequency band (49.90 Hz to 50.05 Hz) has been implemented w.e.f. 17.02.2014.

    2. DSM has been implemented w.e.f. 17.02.2014.

    3. 28.02.2014 was typical date of minimum as well as maximum frequency day which is to be discussed in detail.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    4. MPPMCL filed a petition in High Court of Jabalpur challenging implementation of DSM.

    5. He welcomed GM, WRLDC Shri P Mukhopadhyay in his first OCC of WR. He also highlighted the immense contribution in making important decisions in various OCC forums by Shri P. Pentayya, Ex. GM, WRLDC.

    There after he requested to SE(O) to take regular agenda items in seriatim.

    ITEM No. 1: CONFIRMATION OF THE MINUTES

    Superintending Engineer(Opn), WRPC stated that the Minutes of 456TH meeting

    of Operation & Coordination Sub-Committee of WRPC held on 13th February 2014 at

    GETCO, Vadodara, were forwarded vide letter No. WRPC/OPN/OCC-Minutes/2013-

    14/1741 dated 25.02.2014.

    1. GM(OS & Comml), NTPC Mumbai vide letter dated 05.03.2014 commented on Item

    no 1A(6) of minutes regarding Technical minimum scheduling of NTPC stations wrt to

    following paragraph :

    Quote:

    “In view of above discussions, OCC recommended that in case of schedule is less

    than 30% of MCR even after final review by WRLDC as indicated above, then NTPC

    either run the NTPC units above 30% of MCR as recommended by CEA to CERC,

    even after review the requisition doesn’t match TM, otherwise NTPC is at liberty to

    either shut down the units or run the units more than schedule to the extent possible

    without oil support, thus over injecting into the grid.”

    Unquote:

    He requested that the above recorded paragraph of OCC is discordant with 24th

    WRPC decision as CEA vide letter dated 12.09.2013 have just sent the

    recommendations to Hon’ble CERC which states that the operating capability for coal

    fired units can operate at any load without any limits; and minimum load without oil

    support is taken as about 30% MCR and operation below this limit need oil support

    and it cannot be implemented unless approved by Hon’ble CERC. In addition, higher

    forum(WRPC) decision can’t be changed in lower forum(OCC) and therefore

    requested for deletion of the paragraph.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Member Secretary, WRPC intimated WRPC agrees with observation of NTPC and

    WRPC decision taken in 24th WRPC meeting shall stand till it further reviewed in the

    same or any guidelines/regulation issued by appropriate authorities. Therefore parawill

    be deleted from 456th OCC minutes.

    2. Representative from DNH made following comment on item of MOM regarding

    shifting of DD/DNH load from GETCO to PGCIL networks:

    Quote:

    DNH representative informed that:

    • 66 kV Vapi-Dabhel feeder will be ready by May 2014.

    • 220 kV Bhilad- Silvassa Ckt-I will be ready by March 2014.

    • 220 kV Bhilad- Silvassa Ckt-II will be ready by April 2014.

    • Magarwada S/S(supply of GIS delayed) will be ready by May 2014.

    Unquote:

    He requested to amend the shifting of load of DNH from GETCO network to PGCIL

    network will be in above time frame subjected to commissioning of Kala S/s.

    OCC members agreed on the same. Minutes of 455th OCCM were confirmed with above modification.

    ITEM No.2: REVIEW OF SYSTEM OPERATION DURING THE MONTH OF FEBRUARY 2014

    SE(Operation), WRPC requested WRLDC to brief the Committee on Grid Operation

    experiences during February 2014.

    Chief Manager, WRLDC in the presentation ( copy attached at Annexure – 2 in soft copy) concentrated broadly on the performance of the grid for month of February 2014 as below:

    Frequency Particulars WRLDC presented the following highlights of grid operation during the month of

    February 2014.

    During February 2014 the system frequency profile was as below:

    The average frequency during the month of February was 50.06 Hz. The maximum

    instantaneous frequency was 50.71 Hz on 28th February 2014 while minimum

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    instantaneous frequency was 49.37 Hz on 28th February 2014. The frequency profile

    during February 2014 was as under:

    01-Feb 2014 to 16-Feb 2014

    17-Feb 2014 to 28-Feb 2014

    After IEGC 2nd Amendment

    % time % time

    < 49.7 Hz 0.39 % 50.2 Hz 9.88 % >50.05 Hz 48.76 %

    The detailed frequency particulars are enclosed at Annex- 2.1.

    Member Secretary, WRPC intimated that 28.02.2014 was a special date of minimum as

    well as max frequency day and asked any specific reason thereof.

    WRLDC representative intimated that there was heavy rainfall on 27th Feb, 2014 and in

    the evening of 28th February, 2014, Chandrapur unit -5 was out and overdrawal by

    some of the WR constituents.

    MSETCL representative intimated that load dispatcher were not prepared for such a

    drastic low demand situation due to sudden heavy rains and storm. MSETCL during

    this low demand period all possible measures such as technical minimum on all

    generating units, immediate lifting of load shedding, withdrawal of central sector shares

    were implied. As regards to evening frequency dip it was attributed to combined

    problems such as tripping of Chandrapur Unit-5, SSP units not generating, overdrawal

    by other States etc.

    SE(Opn), WRPC stated that schedule vs drawal of all the States including States from

    other regions as well to be seen for over drawal by other regions at the time of

    frequency dip.

    The Sub-Committee noted.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Inter-regional exchanges status:

    There was a net inter-regional export of 3020.00 MUs by WR against net export

    schedule of 2867.00 MUs.

    The Sub-Committee noted as above. 2.3 Voltage Profile

    Voltage profile at some of 765/400 kV sub-stations during the month of

    February 2014 furnished by WRLDC is enclosed at Annex-2.3. The Sub-Committee noted as above. 2.4 U/F Relay Operations

    As per WRLDC records during February 2014 the system frequency didn’t touch

    49.2 Hz. The details of UFR operation received from constituents for the month of

    February 2014 is enclosed at Annexure 2.4.

    The Sub-Committee noted as above. 2.5 Power Cuts / Load Restrictions

    The committee noted the details of Power Cuts and Regulatory Measures during

    February 2014 as furnished by the state utilities as per the enclosed Annexure-2.5.

    The Sub-Committee noted the above. 2.6 Details of Generating Units under Forced outages

    Details of generating units under forced outages during February 2014 were discussed. The modified details of force outages programme of Generating units are given in Annexure-2.6.

    The Sub-Committee noted the above. 2.7 Details of Generating Units under Planned outages The status of planned outage is modified as per intimation by concern members. The modified details of generating units under Planned Outages during February 2014 are given in Annexure-2.7.

    The Sub-Committee discussed and finalized the planned outages.

     

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM No.3: OPERATIONAL PLANNING 3.1 Proposed outage programme of generating units

    The maintenance programme of generating units for March 2014 & April 2014 was discussed. The Sub-Committee finalized the outage schedule of generating units for the above period and the modified outages plan is placed at Annexure-3.1.

    3.2 A. Outage Programme of Transmission Lines/elements

    SE(Opn), WRPC informed that for the 457th OCC transmission elements outages planning data, must be submitted on or before 03.04.2014. Inter-regional outages proposal must be submitted on 03.04.2014 so that it can be take up with the counterpart of other region as well as NLDC. The Committee discussed the maintenance Programme for transmission lines/elements for the months of March 2014 & April 2014.

    The Sub-Committee discussed and finalized the planned outages(enclosed at Annexure-3.2 A & Annexure-3.2 B).

    B. Line outages planned vs. implemented:

    In 453rd OCC it was decided that the status of lines planned vs. lines availed and any

    deviation from planning or emergency outages for the concerned month shall be

    submitted by WRLDC for discussion in respective OCC. Accordingly in the next OCC,

    WRLDC would furnish the status of complete list of line outages during the month of

    March 2014 planned vis-à-vis implemented.

    WRLDC had submitted the list of emergency outages (Attached at Annexure-

    3.2-C1).

    WRLDC submitted the status of planned transmission element outages vs.

    actual availed or emergency outages during the February 2014(Attached at Annexure-

    3.2-C2).

    SE(Operation), WRPC pointed out that out of approved transmission outages large

    quantum of outages are not availed by constituents even when there is no real time

    constraints in the grid. He also pointed out that specific satisfactory reasons to be

    furnished by all the constituents who have not availed the approved outages w.e.f

    Month of Jan-2014. WRPC Secretariat is also in process of preparing basic software

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    for tracking such issues relating to outage, outage planning, standardization of line

    name, codification of lines etc. For this necessary details were requested by SE(O)

    from all the constituents.

    The Sub-Committee noted as above. 3.3 ANTICIPATED POWER SUPPLY POSITION FOR THE MONTHS – MARCH -

    2014 & APRIL- 2014 Anticipated Power Supply Position for the months of March 2014 & April 2014 were discussed. The details of anticipated regional deficit are given below:

    All figures in MW) State/ Region

    March 2014 April 2014 Anticipated Availability

    Anticipated Peak Demand

    Shortage AnticipatedAvailability

    Anticipated Peak Demand

    Shortage

    GETCO 11625 11740 115 12005 12140 135

    MPPTCL 8150 8340 190 8890 9050 160

    CSEB 3150 3225 75 3015 3105 90

    MSETCL 17500 19150 1650 18000 19250 1250

    GOA 400 425 25 410 415 5

    DD 330 345 15 340 350 10

    DNH 620 635 15 620 640 20

    WR 39860 42172 2312 40570 43221 2651

    Details of anticipated restricted & un-restricted demands for the months of March 2014

    & April 2014 are given in Annex 3.3 (A).

    The Sub-Committee noted as above. ITEM No. 4: OPERATIONAL STATISTICS FOR THE MONTH OF FEBRUARY 2014 The details of schedule Vs actual generation, demand, drawl of power from

    grid; exchanges etc. are given in the following Annexure:

    Annex 4.1 - Actual Generation and Requirement for February 2014

    Annex 4.2 - Peak Demand: Schedule Vs Actual for February 2014

    Annex 4.5- Details of Declared Capacity, Schedules and Injections from Central sector

    stations, Drawl Schedules and Entitlements of constituents during February 2014

    Annex 4.6 - Inter System Exchanges for February 2014

    Annex 4.7- Details of level of Major Reservoirs in Western Region for February 2014

    The sub-Committee noted as above.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM No. 5: SYSTEM DISTURBANCE IN WESTERN REGION

    There was no major grid disturbance in the Western Region during the month.

    however the consolidated list of grid disturbances of lesser magnitude as furnished by

    WRLDC is attached at Annexure- 5.

    The tripping details and Voltage profiles have to be furnished by WRLDC to WRPC on

    first working day of the month. The same has to be reported to MOP via GM division

    of CEA. Accordingly, WRLDC were requested to furnish the tripping details to WRPC

    along with details immediately in the event of tripping.

    The Sub-Committee noted as above.

    ITEM No. 6. Confirmation of Healthiness status of SERs/DRs equipment in the system.

    Constituents have furnished the status of healthiness of SER/DRs in their

    systems on the dates below:-

    Sl No. Name of constituents

    Date of Receipt

    1 PGCIL,WRTS-I 06.03.2014 2 PGCIL,WRTS-II 08.03.2014 3 MPPTCL 11.03.2014 4 NTPC 05.03.2014 5 CSPTCL 05.03.2014 6 GETCO 11.03.2014 7 MSETCL 11.03.2014

    Constituents of WR were requested to continue sending the information as per the

    recommendation of enquiry committee of Grid disturbances on 25.02.2007 and

    28.02.2007.

    The Sub-Committee noted as above. ITEM No. 7: STATUS OF COMPLETION OF ONGOING SCHEMES FOR

    COMMISSIONING OF REACTORS, TRANSMISSION LINES AND GENERATING UNITS IN WR.

    7.1 Status of completion of ongoing Schemes for Commissioning of reactors.

    As discussed in 457th OCCM and as per the present status available on the work for

    providing additional reactors at the various locations in WR.

    Accordingly the information regarding the commissioning schedule is as below:

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    S. No.

    400 kV Sub/stn.

    Size (MVAR)

    Implementing agency

    Expected commissioning date

    1 Ranchodpura 125 MVAR GETCO Commd. On 8th July 2013 2 Varsana 125 MVAR GETCO Commd. On 25th July 2013 3 Rajkot 125 MVAR GETCO Commd. On 5th August 2013 4 Amreli 125 MVAR GETCO Commd. On 12.07.2013 5 Jetpur 63 MVAR GETCO Commd. on 11.07.2013 6 Zerda 125 MVAR GETCO Commd. in July 2013 7 Kosmba 80 MVAR GETCO Commissioned on 29.11.2013 8 Limbdi (Chornia) 125 MVAR GETCO 25th July 2013 9 Jabalpur 125 MVAR PGCIL June 2014 10 Khandwa 125 MVAR PGCIL June 2014 11 Shujalpur 125 MVAR PGCIL June 2014 12 Bhatapara 125 MVAR PGCIL June 2014 13 Raigarh 125 MVAR PGCIL June 2014 14 Aurangabad 125 MVAR PGCIL June 2014 15 Nanded 125 MVAR MSETCL 2014 16 Sholapur 125 MVAR MSETCL 2014 17 Kolhapur 125 MVAR MSETCL 2014 18 Akola 125 MVAR MSETCL 2014 19 India bull 80mvar BR MSETCL Commissioned 26.11.2013 20 Nagda 125 MVAR MPPTCL September 2014 21 Bhopal 80 MVAR MPPTCL March 2014 22 Damoh 125 MVAR PGCIL August 2014 23 Bachau 125 MVAR PGCIL August 2014 24 Pirana 125 MVAR PGCIL August 2014 25 Itarsi 2X125

    MVAR PGCIL August 2014

    26 Seoni 125 MVAR PGCIL August 2014 27 Parli 125 MVAR PGCIL August 2014 28 Raipur 125 MVAR PGCIL August 2014 29 Gwalior 125 MVAR PGCIL August 2014 30 Nagda 50 MVAR MPPTCL 2014 31 ISP 125 MVAR NHDC 2015 32 Satpura 50 MVAR MPPGCL March-2015 33 Sasan Line

    reactor-1 240 MVAR RELIANCE Commissioned on 16.02.2014

    34 Sasan Line reactor-2

    240 MVAR RELIANCE May -2014

    35 Sasan Bus reactor

    240 MVAR RELIANCE June-2014

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    The respective utilities were requested to ensure that reactors are installed and commissioned according to the schedule agreed as above. 7.2 Status of completion of ongoing Transmission Schemes being executed/implemented by POWERGRID/ Other Agencies The updated status on various ongoing transmission schemes for the current year as per the current information available is as follows: - S. No.

    Name of the Line Target Completion Date

    Remarks

    POWERGRID 1 400 kV Vapi(PG)-Navsari Commissioned on

    16.03.2013 2 400 kV Navsari - Navi Mumbai D/C

    Line June- 2014 ROW problem

    3 765kV S/C Satna-Gwalior line (Ckt.-I) Commissioned on 1.02.2014

    4 765kV S/C Satna-Gwalior line (359Km + 60Km D/C Portion) Ckt.-II

    March.- 2014

    5 765 kV Sasan-Satna-II Commissioned on 01.06.13

    GUJARAT 1 400 kV D/C Kosamba-Chorania line

    (Package I)(From Chorania S/S to AP-54)

    March -2014

    2 400 kV D/C Kosamba-Chorania line (Package II)(From Kosamba S/S to AP-54)

    March -2014

    3 400 kV D/C Mundra-Zerda line No. 1 August -2014 4 400 kV D/C Mundra-Zerda line No. 2 April -2014 5 400 kV D/C Vadinar-Amreli line April -2014 6 400kV Mundra-Hadala LILO to

    Halvad April -2014

    7 400 kV D/C Amreli-Kasor line(Part-1) April -2014 8 315 MVA IInd ICT at Kosamba S/S Charged on 15.11.2013 9 ICT at 400/220kV Jetpur Charged on

    27.02.2014 loaded on 05.03.2014

    MADHYA PRADESH 1 Malwa-TPH-Pithampur 400KV

    DCDS Line 23,24.10.2013

    2 Malwa TPH-Chhegaon 400 KV DCDS Line

    Ckt –I on 22.03.2013 Ckt-II on 11.07.2013

    3 Chhegaon-Julwania 400 KV DCDS Line

    March - 2014

    4 Pithampur- Indore 400KV DCDS Line March- 2014

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    5 Satpura TPH-Ashta 400KV DCDS Line

    December – 2014

    CSPTCL 1 400 kV Korba (W)-Khedamara

    DCDS Ckt II LILOed at Marwa August 2013 Test charged on

    20.08.2013

    2 400 kV Khedamara- Raita -II Commissioned on 20.02.2014

    3 400kV DCDS Marwa-Raipur(Raita) January -2014

    Test charge from Raipur end in August 2013

    4 LILOof 400kV K(W)-Khedamara line at Marwa (one ckt.)

    April -2014

    5 50MVAR LR at Khedamara Charged on 28.02.2014 MAHARASHTRA(STU)

    1 400KV D/C line from Koradi-II to Wardha S/S(PG) D/C

    March - 2014

    2 400 kV Chandrapur-II-Warora-II Commissioned on 16.01.2014 3 400 kV Bableshwar-Sinner Ckt-II Commissioned on 27.12.2013 4 400 kV Chandrapur-Parli-II LILO at

    Chandrapur-II S/S Commissioned on

    16.01.2014 5 765kV Tiroda – Akola(Adani) Commissioned on 23.02.2014 MAHARASHTRA (IPTC route) by WR Transmission (Mah) Pvt. Ltd

    1 400 kV Parli(PG)-Pune D/C Commissioned Ckt - 1 on 08.11.2013 Commissioned Ckt - 2 on 10.11.2013

    2 400 kV Pune (PG)-Aurangabad (MSETCL) D/C

    November-13 Commissioned Ckt - 1 on 05.12.2013 Commissioned Ckt - 2 on 04.12.2013

    3 LILO Lonikhand –Kalwa at Pune(PG) Lonikhand-Pune charged on 21:30 on 09.07.2013 and Kalwa –Pune at 21:45 on 09.07.2013.

    GUJARAT (IPTC route) by WR Transmission (Guj) Pvt. Ltd

    1 400 kV Rajgarh(PG)-Karamsad (GETCO) D/C

    February -2014

    The Sub-Committee noted as above.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    7.3 Commissioning of new Generating units in Western Region and the capacity expected to be commissioned during the year 2013-14 The status regarding Generating units, commissioned /expected to be

    commissioned during the current year 2013-14 according the available information is

    as below:

    Name of the Power Projects Unit No. Capacity (MW)

    Date of Commissioning /Schedule Date

    GUJARAT Ukai 6 500 COD on 08.06.2013

    Pipavav CCPP- GPCL & GSPC joint venture Block-1 350

    March- 2014 Made in synchronized on 10.10.2013.

    Bhavnagar Lignite TPP-JV I 250 August 2014 II 250 August 2014 UNO SUGEN 1 382.5 COD on 04.04.2013 CHHATTISGARH Marwa TPS I 500 25.12.2013 Korba (w) Ext-5 500 COD on 05.09.2013 KSK Mahanadi 3 600 COD on 14.08.2013

    VEDANTA VIDYUT 1 135 Synchronized on 11.08.2013

    MAHARASHTRA

    INDIABULLS (Amaravati) 1 270

    Synchronized on 03.06.2013

    COD on 01.02.2014

    INDIABULLS (Amaravati) 2 270 Synchronized on 1.02.2014

    INDIABULLS (Sinnar) 1 270 Synchronized on 24.02.2014

    VIPL(Butibori) 1 300 COD on 05.04.2013

    VIPL (Butibori) 2 300

    First synchronized on 02.01.2013

    Full load on 19.03.2013

    GMR EMCO 2 300 COD on 27.08.2013

    Dhariwal 1 300

    Synd. On 2.9.13

    COD on 11.02.2014

    Bhusawal 5 500/400 COD on 03.01.2014

    MADHYA PRADESH

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    SINGAJI TPP 1 600

    Synchronized on 31.08.2013

    Coal fired on 30.09.2013

    COD on 01.02.2014

    2 600 June-2014 M/s Jhabua Power, Seoni

    1 300 JANUARY – 2014 MB Power, Anuppur

    1 300 JANUARY – 2014 Satpura

    11 250 Synchronized on 02.10.2013 SATPURA

    10 250 COD on 18.08.2013

    CENTRAL SECTOR Vindhyachal TPP IV 12 500 March-14

    MAUDA 2 500 March -14

    The Sub-Committee noted as above. ITEM NO. 8: MISCELLANEOUS OPERATIONAL ITEMS

    (A) FOLLOW-UP

    8.1 QUARTERLY REVIEW OF CRISIS MANAGEMENT PLAN

    All the constituents are requested to submit the CMP report for the Third quarter

    (October 2013 to December 2013) for the year 2013-14.

    The Sub-Committee noted as above.

    8.2 STATUS OF PHYSICAL & CYBER SECURITY IN POWER SECTOR REGARDING

    Status of physical & cyber security in Power Sector for the Third quarter (October 2013 to December 2013) have not been received from some of the constituents. Constituents were requested to furnish the latest status.

    Shri Samual C. Sciacca, from SCS consulting, LLC USA who was present in IEEE seminar at Mumbai held on 10.3.2014 was specially invited by Member Secretary for giving a brief presentation on cyber security to OCC Members & participants. Shri Samual C. Sciacca expert shared his knowledge with members of OCC.

    The sub-committee appreciated the exposure given by Shri Samual C. Sciacca and thanked him for his willful participation.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM NO. 8.3 ADMS IMPLEMENTATION STEP BY GETCO

    A pilot project in respect of ADMS have been successfully implemented by GETCO in

    11 kV Sadhi feeder (MGVCL ) on 19.02.2014.

    SLDC, GETCO submitted a presentation on the same, which is enclosed at annexure-8.3.

    ITEMS FROM WRLDC:

    ITEM NO. 9.1 : PERFORMANCE OF WR CONSTITUENTS POST THE IMPLEMENTATION OF DEVIATION SETTLEMENT MECHANISM ON 17.02.2014

    The IEGC second amendment as well as the Deviation Settlement Mechanism is in

    force w.e.f. 17.02.2014. The performance of WR constituents during first 10 days i.e.

    from 17th to 28th Feb 2014 comprising of 960 time blocks is illustrated below. Members

    may like to analyze and devise suitable measures to ensure compliance to the above

    CERC regulations.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Since the decisions in real-time are based on the SCADA data it is now important to

    monitor and ensure correctness of drawal / injection as seen in SCADA. The chart

    below indicates the difference between the drawal of constituents as seen in SCADA

    and as recorded in SEM for the period of 01st Feb 2014 to 16th February 2014. It may

    be seen that the significant difference between SCADA and SEM needs to be

    addressed by ensuring healthiness of telemetry and periodic validation by the SCADA

    team at the respective SLDCs and WRLDC.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Following points were highlighted by the constituents regarding sticking to DSM for

    curtailing over/under drawal within limits as specified in IEGC/DSM :

    • SLDC are doing their best to manage load/generation as per schedule but as

    the margins is very less and due to SCADA data errors, deviations would be

    there.

    • Persistant underdrawal by Chhattisgarh is a big problem

    • In Gujarat, schedules are revised in real time but the the generation is not

    controlled within time. CGPL representative expressed that many revisions are

    issued to them (as good as 15 revisions a day) and it becomes difficult for them

    to achieve technical minimun to full load(wet to dry mode) as per schedule.

    • NTPC representative indicated that Mounda unit is under reserve shutdown but

    at the same time schedule from Chhattisgarh is there.

    After hearing the views of the constituents Member Secretary, WRPC stated that all

    efforts for maintaining the drawal as per schedule should be made. Regarding CGPL

    problem for ramping generation from wet to dry mode he requested CGPL for submit

    an agenda item in ensuing OCC after getting OEM recommendations for ramping

    rates.

    Committee noted as above.

    ITEM NO. 9.2: UNDER DRAWAL BY MAHARASHTRA AND INSECURE OPERATION IN THE GRID ON 27-28 FEB 2014

    During late night of 27th Feb and early morning hours of 28th Feb-14, the grid

    frequency remained above 50.2 Hz continuously for five hours from 22:52 hrs of 27-

    02-2014 to 04:07 hrs of 28-02-2014. The situation was caused due to demand

    reduction across the WR and NR on account of widespread rains and persistent under

    drawal by Maharashtra during the above period as illustrated in figure-1 below.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    50.67

    49

    49.2

    49.4

    49.6

    49.8

    50

    50.2

    50.4

    50.6

    50.8

    ‐1000

    ‐850

    ‐700

    ‐550

    ‐400

    ‐250

    ‐100

    50

    200

    350

    500

    650

    800

    21:00

    21:15

    21:30

    21:45

    22:00

    22:15

    22:30

    22:45

    23:00

    23:15

    23:30

    23:45

    0:00

    0:15

    0:30

    0:45

    1:00

    1:15

    1:30

    1:45

    2:00

    2:15

    2:30

    2:45

    3:00

    3:15

    3:30

    3:45

    4:00

    4:15

    4:30

    4:45

    5:00

    5:15

    5:30

    5:45

    6:00

    6:15

    6:30

    6:45

    7:00

    7:16

    7:31

    7:46

    Maharashtra Deviation from schedule vis‐a‐vis grid frequency21:00 hrs of 27‐02‐2014 to 08:00 hrs of 28‐02‐2014

    MSEBUI FREQ

    Deviation from Schedule

    Frequency

    MW Hz

    Several messages were sent from WRLDC control room to SLDC Kalwa directing them to control their under drawal from the grid. Details of these messages is tabulated below.

    Sl. No. Message sent to Ref No. Message date and

    time

    1 SLDC Maharashtra

    56/079 27.02.2014, 22:10 hrs.

    2 SLDC Maharashtra

    3070 27.02.2014, 22:30 hrs.

    3 SLDC Maharashtra

    3078 28.02.2014, 01:25 hrs.

    4 SLDC Maharashtra

    3079 28.02.2014, 01:50 hrs.

    Despite the above messages, the response from SLDC Kalwa was inadequate in

    controlling the under drawal of Maharashtra. Consequently the frequency touched

    50.69 Hz at 02:11 hrs. of 28-Feb 2014; the voltage across the grid increased sharply

    and there was over injection from WR to other regions. Subsequently as a

    contingency measure the drawal schedule of Maharashtra was reduced by 600 MW

    by suo motu revision in the requisition of Maharashtra in Korba, Vindhyachal, Sipat

    and Vidhyachal STPS w.e.f. 02:30 hrs to 05:00 hrs of 28.02.2014. This was later

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    extended up to 07:00 hrs of 28.02.2014. It was a near miss situation that could have

    been avoided by adequate planning and commensurate actions in real-time. It is

    requested that the matter may be taken up at the highest level in MSETCL and a

    separate meeting may be convened on the above subject to avoid reoccurrence of

    such event in future.

    As indicated in opening remarks this incidence need to be studied. Hence SE(O),

    WRPC requested to furnish schedule vs drawl figures for all the constituent for 27 and

    28th Feb 2014.

    The sub committee noted the same.

    ITEM NO. 9.3: NON AVAILABILITY OF REAL-TIME TELEMETRY FROM LARGE NUMBER OF STATIONS IN MAHARASHTRA

    There are 224 nodes in Maharashtra that comprising of 32 Generating stations and

    192 substations. Out of these 224 nodes, 47 locations are yet to be integrated in the

    System. Out of the balance 177, the data from nearly 50% nodes are not coming since

    last 6 months. Thus in totality data is not available from more than 135 out of 224

    stations .i.e. 60 % which is highly alarming. The extremely poor status of telemetry in

    the state of Maharashtra has become a security threat. Maharashtra load is touching

    17500 MW and there are large number of construction related outages that have to be

    facilitated. Further with the formation of the synchronous All India grid there is a need

    for close monitoring of system parameters such as the line flows, voltage and grid

    frequency. Inadequate telemetry is resulting in severe constraints in real time

    operation as well as outage coordination. There have been several instances of line

    tripping on high voltage, and SPS operation due to sudden increase in line flows

    during hour boundary, or during facilitating planned outage. These events could be

    minimized with better supervision if the telemetry is available.

    The telemetry issue in Maharashtra has been discussed in the various WRPC forums

    wherein it was informed by MSETCL that the problem is due to failure of M/s Tulip

    who was the service provider for the communication network. During the month of

    August 2013 representative from MSETCL had assured that a new contract was being

    awarded and the situation would improve within one month.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    SE(O), WRPC requested MSETCL to provide the statistics of progress of provision of

    telemetry in various nodes to WRPC/WRLDC on regular basis till its final

    implementation.

    SE(Tel), MSETCL intimated that work is under final stage & assured that Telemetry

    data from Maharashtra stations would be available regularly by end of April 2014.

    The sub committee noted the same.

    ITEM NO. 9.4: STATUS OF LINE AND BUS REACTORS AT 765 KV SASAN

    The line reactor of 765 kV Sasan-Satna ckt-2 as well as the Bus reactors of 765 kV Sasan bus are yet to be commissioned at Sasan end. In the absence of these reactors, high voltage is experienced at Sasan and nearby stations. Often one circuit of 765 kV Sasan-Satna is required to be opened for voltage regulation. Consequently the reliability of evacuation of generation from two units of Sasan is affected. During 456th OCC meeting, the revised schedule of the above elements as informed by M/s Reliance was as under:

    Schedule in formed in meetings

    451st OCC 455th OCC 454th OCC

    1 Line reactor of 765 kV Sasan-Satna ckt-2

    By Dec 2013 By April 2014 By May 2014

    2 765 kV Bus-1 Reactor

    Jan 2014 By Mar 2014 By June 2014

    CE(LD) MPPTCL intimated that visit to SASAN site to check readiness of Line and Bus reactors would be made 2nd or 3rd week of March-14 alongwith representative from NTPC.

    The sub committee noted the same.

    ITEM NO. 9.5: CHARGING OF NEW TRANSMISSION ASSET IN THE GRID In order to have better coordination of the transmission utilities with RLDC/NLDC during charging / synchronization of new elements into the grid a communication has been received from NLDC (ref: POSOSCO/NLDC/System Operation/Outage Planning/1239) on 10.02.2014. It has been proposed that

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    a. Owner of the asset shall submit the request for expected charging/commissioning of new element for the calendar month latest by 5th day of the month to the respective RLDC & NLDC along with status of activities mentioned in the check-list.

    b. RLDC shall study the impact of the new element commissioning and based on its assessment of the preparedness of the utility may recommend to NLDC who in turn would examine the issue independently considering pan India grid scenario.

    c. After the above, the owner of the new asset shall give its readiness to charge the new element at least three days in advance with current status of activities mentioned in the check list.

    Check list is as under

    1. List of elements to be charged along with the details of approval of the transmission scheme from the Standing Committee/CTU/STU

    2. Single Line Diagram of the concerned substations, along with status of completion of each dia/bus/breakers

    3. Availability of real-time data and communication to the designated SLDC/RLDC

    4. Installation of Special Energy Meter complying with CEA’s Regulations (Serial number / Meter number, CT/PT ratio to be indicated)

    5. Charging Instructions by CTU/STU 6. Schedule and sequence of charging of elements 7. Availability of line / bus reactors as per planning. In case the transmission

    system is planned to be charged without the planned line reactor, requisite authorization from CTU/STU by studies

    8. Connection Agreement (along with all annexure) with CTU or STU 9. Copy of Long term Access (LTA) or MTOA granted by CTU or STU as the

    case may be 10. Copy of Power Purchase Agreement (PPA) 11. A signed undertaking with name and designation of the officer clearly

    indicating the following: a. All Disturbance recorders (DR) and Event Loggers (ELs) with time

    synchronization are commissioned b. All protective systems have been commissioned c. All statutory clearances have been obtained

    12. Output of EL and DR after charging Each document mentioned in check list from Sl. No. 1 to 10 must be attached for sake of completeness and emailed as a consolidated document to the nodal RLDC well before the new element charging date.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Member Secretary, WRPC suggested members (particularly ISTS licensees) to go through the proposal submitted by NLDC, and discuss & revert with suggestions in next OCCM.

    The sub-committee noted the same.

    ITEM NO. 9.6: OPENING FEEDERS WITHOUT PRIOR INTIMATION TO WRLDC

    It was gathered based on the observation from WRLDC SCADA data and subsequent

    discussion with MPPTCL that 220 kV Bina (MP)-Gwalior(MP) D/C were taken under

    shut down for LILO works at Datia at 09:10hrs on 23/02/2014 for 4 days. The outage

    of these lines was neither discussed in OCC and neither was there any intimation to

    WRLDC before availing the outage. These lines are included in the important grid

    elements list of Western region and prior concurrence of WRLDC is required for

    switching these lines. Further these lines form the parallel path to 765 kV Bina-Gwalior

    D/C and with the shutdown of these lines the network upstream of WR-NR inter

    regional corridor was depleted.

    OCC suggested that WRLDC shall circulate list of important STU lines for which

    WRLDC concurrence required. WRLDC agreed.

    The sub-committee noted the same.

    ITEM NO. 9.7 TRIPPING OF 765 KV LINES ON OVER VOLTAGE

    Recently several tripping of 765 kV lines have been reported on over voltage. These are indicated below:

    1) 765 kV Bina-Gwalior I at 23:58 hrs of 16.02.2014 2) 765 kV Bina-Gwalior I at 20:11 hrs of 14.02.2014 3) 765 kV Satna-Gwalior at 13:00 hrs of 06.02.2014 4) 765 kV Sasan-Satna II at 00:13 hrs of 18.01.2014 5) 765 kV Jabalpur-Bina I at 23:50 hrs of 10.01.2014 6) 765 kV Jabalpur-Bina II at 04:05 hrs of 06.01.2014

    PGCIL intimated that as the equipments for 765 kV are rated for 108 %, adopted Stage-I O/V setting for the above lines vary from 106 % to 108 %. As per SCADA data the bus voltage at any of the substations mentioned above had not reached 826 kV during the above incidents.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    POWERGRID may examine the above tripping in detail and apprise the OCC regarding the above. In case of issues related with protective relays /field equipment are detected, these may be addressed at the earliest.

    Member Secretary WRPC directed WRTS-II(PGCIL), to submit the DR status & complete report including settings to WRPC/WRLDC for further analysis.

    PGCIL, WRTS-II representative agreed for the same.

    The sub-committee noted as above.

    ITEM NO. 9.8: RGMO / FGMO OF MANDATED GENERATORS IN WESTERN REGION

    As per the latest information available at WRLDC, there are 251 number of units with a total capacity of 57517 MW in Western Region that are mandated to operate in Restricted / Free Governor Mode. The need for compliance to the IEGC regulations w.r.t RGMO/FGMO was emphasized in the 455th and 456th OCC meeting as well as during the 25th TCC/WRPC meeting. Subsequently it was communicated by email to all entities in WR to provide the latest status of RGMO/FGMO implementation. We have received updated status from MPPTCL, LANCO, CGPL, DB Power and JPL Tamnar in Feb 2014. The latest state wise RGMO/FGMO summary is given below.

    Name of Entity No of

    mandated units

    RGMO / FGMO available at

    RGMO/FGMO

    Not available at

    Maharashtra 90 35 55

    Madhya Pradesh 58 36 22

    Gujarat 35 19 16

    Chhattisgarh 10 3 7

    CGPL 5 5 0

    NCA 11 6 5

    SASAN 2 1 1

    NTPC 24 10 14

    ESSAR_Mahan 1 1 0

    NSPCL 2 2 0

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    KSK 1 1 0

    KWPCL 1 0 1

    DB POWER 1 1 0

    JPL 5 4 1

    LANCO 2 2 0

    IEPL 1 0 1

    EMCO 2 0 2

    WR_Total 251 126 125

    WRLDC vide its letter ref WRLDC/RGMO-FGMO/1-2014 dated 23.01.2014 has issued directions under Section 29 of the Electricity Act to ensure compliance of IEGC regulations 5.2 (f), (g), (h) and (i). All utilities are requested to furnish the status of compliance in respect of generating units under their jurisdiction.

    DTPS Dahanu representative expressed his experience of technical difficulties during implementation of RGMO/FGMO at technical minimum loading at DTPS Dahanu. Other generators in WR endorsed the views expressed by DTPS representative.

    Members expressed that RGMO/FGMO to be disabled at technical minimum loading but as the issue of technical minimum itself is pending since long therefore agreed to continuing the existing practice.

    The sub-committee noted as above.

    ITEM NO. 9.9 STATUS OF TELEMETRY IN WESTERN REGION

    The status of telemetry related issues in respect of WR constituents is as under:

    a) Chhattisgarh Data (except MW) from 500 MW Korba West extension generating station is not available.

    Status points from 400 kV Raita pending

    b) Madhya Pradesh Telemetry of following bus reactors is not available at WRLDC. MP representative intimated that in ULDC there is no provision for relemetry from reactors and therefore telemetry from reactor is being implemented separately.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    S. No.

    Station Name Bus Reactor

    Nunber x Capacity

    Total MVAR

    Rated voltage

    Status of Telemetry at WRLDC

    1 Nagda 2*50 100 420Not

    available

    2 Indore 2*25 50 33Not

    available

    3 Bhopal 2*25 50 33Not

    available

    4 Birsinghpur 1*50 50 420Not

    available

    c) Gujarat Data is not-available/intermittent from following stations in Gujarat

    a. 220 kV Nano of Tata—(not available) b. Kansari 400 kV s/s and Navsari 220 kV…Intermittent (PLCC Problem)

    d) Goa Due to non-availability of SCADA data from Goa the difference between drawal as seen in SCADA and as recorded in SEM is as high as 5.72 % during the period 1st Feb to 16th Feb 2014. Data from the following stations in Goa is not available at WRLDC:

    S No. Station Status

    1 Amona 220 kV Not available. Line not charged.

    2 Cuncolin 220 kV Not available. Line not charged.

    3 Kadamba 110 kV Intermittent

    4 Tivim 220 kV Intermittent

    5 Ponda 220 kV Intermittent

    6 Xeldam-220 kV Intermittent

    7 Verna-110 kV Intermittent

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    e) DD & DNH Due to non-availability of SCADA data from Daman & Diu the difference between drawal as seen in SCADA and as recorded in SEM is as high as 5.71 % during the period 1st Feb to 16th Feb 2014. Data from The error is mainly due to non-availability of data from 220 kV Magarwada. Telemetry from 220 kV Kharadpara and Khadoli station is not available.

    DNH representative intimated that there are not RTU in their UT. RTU implementation to be covered under SCADA upgradation programme.

    f) POWERGRID The data from the following stations is not available at WRLDC

    1) 765 kV Tamnar (Communication problem, GPRS link is not stable)

    Telemetry from following stations is Intermittent at WRLDC

    1) 765 kV Durg (PLCC frequent problems)

    2) 765 kV Kotra (communication intermittency)

    3) 765 kV Gwalior (PLCC link established , but still there is some

    issue(Delay) in data updation at WRLDC, Rectification work under

    progress by Site Engineer.

    4) 765 kV Solapur - Redundant link established through Reliance but the

    gateway connected to above link is not configured for 765 KV data.

    Hence when BSNL link is down 765 KV data is not updating at

    WRLDC.

    PGCIL Representative from Raipur assured that 765 kV Durg & 765 kV Kotra

    telemetry link will be available by the end of May 2014.

    The sub-committee noted the same.

    ITEM NO. 9.10: COMPARISON OF DRAWAL AS SEEN IN SCADA VS SEM

    The IEGC second amendment and the Deviation Settlement Mechanism is in force since the 17.02.2014. The IEGC stipulates maintaining injection / drawal within the limits prescribed in the Deviation Settlement Mechanism.

    The sub-committee noted the same.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM NO. 9.11: MOCK BLACK START EXERCISE

    As per sec 5.8(b) of IEGC the users/STUs etc. need to conduct Black start mock

    exercises in their respective systems once in every six month under intimation to

    RLDC. Also the all the black start Diesel Generator (DG) sets are [as per sec 5.8(b)

    of IEGC] required to be tested weekly and the test report needs to be sent to RLDC

    on quarterly basis.

    The following table summarizes the status of mock exercises in respect of black start

    facilities in Western Region.

    Sl No Power Station Installed Cap. (MW) Unit Type

    Black Start Source

    Capacity of Black start source

    Last BS Capabili

    ty demonstrated

    on

    Receipt of DG set testing

    report at RLDC

    GUJARAT

    1 Ukai (H) 4 x 75 Hydro Diesel 500 kVA 22.12.13 Y

    2 Mini Hydro 2 x 2.5 Hydro Diesel 50 KW ?? N

    3 Kadana 4 x 60 Hydro Diesel 500 KVA 2.4.13 Y

    (2.4.13)

    4

    Dhuvaran

    1 x 107 (68+39)

    + 1 x 112 (72+40)

    Gas

    Details to be furnished by Gujarat

    Details to be furnished by Gujarat.

    ??

    N

    5 GIPCL-I 3 x 32

    + 1 x49

    Gas /

    Steam Diesel

    141 KW

    07.09.12

    Y

    6 GIPCL-II 1x104+1x56 Gas /

    Steam Diesel 500 kVA ??

    N

    7

    Torrent Power

    Stn. C

    Stn.- D,E,F,CCPP

    StnC:2x30

    StnD:120

    Stn.E,F(110MW each)CCPP:100MW

    Thermal

    (Units-C,D,E,F)/

    Gas(CCPP)

    Stn-C islands

    Diesel

    Stn.C:15kVA;

    Stn.D,E ,F and CCPP(500 kVA each)

    28.11.12

    Y

    8 GPEC 3x138+1x241 Thermal Natural Gas 3000 kVA ?? N

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Sl No Power Station Installed Cap. (MW) Unit Type

    Black Start Source

    Capacity of Black start source

    Last BS Capabili

    ty demonstrated

    on

    Receipt of DG set testing

    report at RLDC

    9 Sugen 3x382.5 MW Gas Diesel 2x6MVA ?? N

    Madhya Pradesh

    10 Gandhisagar 5 x 23 Hydro DG set 100 kVA ?? N

    11 Birsinghpur 1 x 20 Hydro Battery 220 Volt Battery ??

    N

    12 Pench 2 x 80 Hydro DG set 250 kVA 12.10.12 Y

    13 Bargi 2 x 45 Hydro DG set 250 kVA 10.02.12 Y

    14 Bansagar Stage-I 3 x 105 Hydro DG set 250 kVA ?? N

    15 Indira Sagar 8x125 Hydro DG set 2x1000 KVA 22.5.11 Y

    Chhattisgarh

    16

    Hasdeo Bango 3 x 40 Hydro DG Set 250 kVA 25.08.12

    N

    17

    Korba(E)-phse-I

    Power plant retired but Black start DG set available and on- load trial is reported to be carried out regularly

    DG Set 1500 kW(3.3kV) ??

    N

    Maharashtra

    18

    Koyna I & II

    4 x 65

    4 x 75 Hydro

    House generator

    2 MVA 23.10.13 N

    19 KDPH 2 x20 Hydro DG set 310 KW ??

    N

    20 Eldari 3 x 7.5 Hydro DG set 6 KW ??

    N

    21

    Uran (Gas)

    4 x 60 (GT)

    + 4x108 (GT)+ 2x120 WHR

    Gas DG set

    4 MW

    PH1:412kVA PH2:450kVA

    WH:520kVA

    16.10.12

    N

    22 RGPPL

    Block 1: 640MW+Block 2: 663.54MW+Block 3: 663.54MW

    Gas

    Gas Turbine (Frame-6)

    35 MW (Under testing): Details to be provided by

    ??

    N

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Sl No Power Station Installed Cap. (MW) Unit Type

    Black Start Source

    Capacity of Black start source

    Last BS Capabili

    ty demonstrated

    on

    Receipt of DG set testing

    report at RLDC

    RGPPL.

    23 Ghatghar 2x125 Hydro DG set 1x1250 kVA 5.10.12

    N

    24 Khopoli 3x24+2x12 Hydro

    DC Governor & bearing oil pumps

    DC power (self start)

    27.10.13

    (detailed report awaited)

    N

    25 Bhivpuri

    3 x 24 +

    2 x 1.5 +2x12 Hydro

    DC Governor & bearing

    -do- ??

    N

    26 Bhira 6 x 25 Hydro

    1 No.of 500 KVA house generator with water turbine

    500 kVA

    20.10.13

    (detailed report

    awaited)

    N

    27

    Bhira PSS 1 x 150 Hydro DG set 500 kVA ??

    N

    28 Trombay 1 x 120

    Gas Turbine DG Set 2.5 MW ??

    N

    1 x 60 Steam Turbine

    NTPC

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Sl No Power Station Installed Cap. (MW) Unit Type

    Black Start Source

    Capacity of Black start source

    Last BS Capabili

    ty demonstrated

    on

    Receipt of DG set testing

    report at RLDC

    29 Kawas 4 x 106

    2 x 116 Gas Diesel 2850 KW 15.10.13

    N

    30 Gandhar 3 x 144

    + 1x225 Gas Diesel 2975 KW ??

    N

    NCA

    31 SSP(RBPH & CHPH) 6x200+5*50 Hydro Diesel 2x1000kVA 08.04.12

    N

    Accordingly the Black start capable stations may forward their tentative plan for conducting Black start exercises in compliance to sec 5.8(b) of IEGC.

    • As per the communication for MPPTCL the tentative plan of Black start in Madhya Pradesh system is given under SL No Name of the Station Tentative Date Remarks

    1 Pench March, 2014 DG set at Pench & are Bargi under outage

    2 ISP Apr-May, 2014 -

    3 TONS June, 2014 Governor Problem being attended

    4 Birsinghpur June, 2014 -do-

    5 Medikheda June, 2014 -do-

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    6 Rjghat June, 2014 -do-

    Member Secretary, WRPC suggested that WRLDC shall prepare a list for next six months and concern generator/agency shall be adhered on schedule.

    The sub-committee noted the same.

    ITEM NO. 9.12: HEALTHINESS OF MAIN CIRCUIT BREAKER OF 400 KV BIRSINGPUR-KATNI-I AT KATNI END

    The main CB of Birsingpur-Katni-I was under shut down since 23:50 hrs of 14th February 2013. Representatives from MPPTCL informed that of restoration of the Main CB of 400 kV Birsingpur-Katni-I at Katni end has already been carried out.

    The sub-committee noted the same.

    ITEM NO. 9.13: TESTING OF SPS RELATED TO TRIPPING OF BINA-GWALIOR-

    AGRA AT CGPL, VINDHYACHAL AND KORBA In 25th WRPC/TCC the matter of testing of the SPS for 765 kV Gwalior-Agra D/C discussed & recommended that signals simulating the trip of the above line shall be sent and successful receipt of the signal shall be sufficient to ensure that SPS is working. It was decided that WRLDC shall co-ordinate and witness and the SPS may be taken into service subsequently OCC suggested that WRLDC shall fixed up a date for testing in consultation with NLDC.

    A team comprising officers from WRPC, WRLDC, NTPC, PGCIL & CGPL to perform test on 21.03.2014. Test result will be discussed in next OCC meeting.

    The sub-committee noted the same.

    ITEM NO. 9.14: SPS AT SIPAT

    WRLDC vide letter No. WRLDC/MO-I/1719/2013 dt 21.6.13 requested to take up this matter with the concerned for early implementation of the SPS.

    OCC suggested that WRPC, WRLDC & NTPC would discuss the scheme and suggest implementation of SPS with any modification required at the earliest.

    The sub-committee noted the same.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM NO. 9.15 :SPS AT 4X300 MW BALCO IPP

    The SPS at 2010 MW Balco (4x67.5MW + 4x135 MW + 4x300 MW) was to be commissioned by Nov 2013 before commissioning of first unit of 4x300 MW Balco IPP. For the new SPS scheme envisaged for the Balco CTU connection, namely the Grid Islanding and Load Management Scheme (GILMS), Balco had reported to have placed an order with M/s SEL. As discussed earlier, the scheme suggested by WRLDC may be implemented before commissioning of first unit of 300 MW. It was intimated during the 456th OCCM by the Balco representatives that the SPS shall be commissioned by March 2014.

    The sub-committee noted the same.

    ITEM NO. 9.16 :ACTIONS TAKEN FOR REVIVAL OF TRANSMISSION ELEMENTS

    UNDER LONG OUTAGE As per the information available at WRLDC following elements are out for a long period.

    Sl. No Date of outage Reason

    ISTS/IPP

    1 80 MVAR BR at ESSAR(Mahan) 23.12.13 Oil leakage

    2 125 MVAR BR at JPL 12.05.13

    Expected by March 2014 end

    Hydrogen formation

    3 50 MVAR LR of Indore-Asoj-II at Indore 19.06.13

    Charged on 04.03.2014

    R phase bushing burst

    4 50 MVAR LR of Birsingpur-Damoh at Damoh(PG)

    13.10.2014

    Expected by June 2014

    Oil Leakage

    & Internal problem

    5 765 kV Durg-Kotra-I 24.02.2014

    Ready for charging

    Sparking in Isolator

    6 400 kV Raipur-Raigarh-IV 18.01.2014

    Already Charged

    Voltage Regulation

    MSETCL

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Concerned were requested to furnish the actions being taken for expediting revival of

    the above elements.

    The sub-committee noted as above.

    ITEM NO. 9.17: STATUS OF 220 KV KOLHAPUR-MUDSINGHI-CHIKODI- BELGAM LINE

    Consent for trial operation of 220 kV Kolhapur-Mudsinghi-Chikodi- Belgam line in radial mode for supply of Karnataka load from Maharashtra side was granted after discussion in the 455th OCC meeting. WRLDC is in receipt of letter from SRLDC regarding concurrence for the above arrangement. MSETCL representative intimated that it is under consideration to settle down the commercial issues due to SMP mechanism of deviation settlement by embedded generators.

    WRPC OCC Sub-committee reiterated that not withstanding the commercial mechanism. It agrees with transfer of power to the tune of 100 MW in radial mode to Karnataka as decided in earlier OCC.

    The sub-committee noted as above.

    ITEM NO. 9.18 :CONTRIBUTION OF GENERATORS IN VOLTAGE CONTROL The contribution of generators in WR in voltage control was analyzed during 456th OCC meeting. It was noted that following units were injecting reactive power even during high voltage

    1. 210 MW units of Khaparkheda, Koradi and Chandrapur (Maharashtra) 2. 210 MW units of Satpura and Birsinghpur (Madhya Pradesh) 3. 210 MW unit # 2,3 of Korba West (Chattisgarh) 4. 200 MW unit # 3,4 of Ukai (T) in (Gujarat)

    1 400 kV RGPPL-N’Koyna-I 22.01.2014 Voltage Regulation

    2 400 kV Sholapur-Sholapur(PG) 26.02.2014 Tower Collapse

    MPPTCL

    1 400 kV Birsingpur-Katni-I 28.01.2014 Voltage Regulation

    CSPTCL

    1 400/220 kV ICT at Bhilai-II 28.02.2014

    Expected by April 2014

    Bushing failure

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    Utilities were requested to check the setting of AVR/GT tap and revert back with findings.

    The sub-committee noted as above.

    ITEM NO. 9.19: REAL-TIME MONITORING OF FEEDERS / SUBSTATIONS THAT

    ARE COVERED UNDER THE AUFLS Telemetry of feeders / substations covered under the AUFLS is desirable for real-time assessment of the anticipated relief that would be available from the AUFLS scheme at any given instant of time. CERC has also directed all the constituents to for mapping of these feeders in the SCDA of SLDCs/RLDC. Member Secretary, WRPC suggested that if both measurands and CT indication is not possible to telemeter, at least indication can be telemetered with existing facilities and load shed can be derived at higher leveled S/S by deference in total drawl by particular S/S and request for early implementations. The sub-committee noted as above.

    ITEM NO. 9.20: LOAD FORECASTING As per the amended Indian Electricity Grid Code that is effective from 17th February 2013 the SLDCs, SEB, distribution licensees shall always restrict the net drawal of the State from the grid within the drawal schedule keeping the deviations from the schedule within the limits specified in the Deviation settlement mechanism regulations. Therefore it is imperative that adequate attention may be paid towards load forecasting. The matter was discussed in the 455th and 456th OCC as well as in the 25th TCC/WRPC board meeting wherein it was decided to create a task force for exploring development of a software for load forecasting. Members may like to deliberate further. SLDC, GETCO made a presentation(enclosed at Annexure-9.20) on the factors to be considered for correct load forecasting. OCC suggested for a separate meeting between WRPC, WRLDC, SLDC’s & Discom’s. Subsequently it was decided that meeting would be held on 03.04.2014 at Mumbai. The outcome of the meeting will be intimated in ensuing OCC meeting.

    The sub-committee noted as above.

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ITEM NO. 9.21: IMPLEMENTATION OF THE REVISED AUFLS IN GOA, DD AND DNH

    It was decided during the 455th and 456th OCC meeting as well as during 25th WRPC meeting that Goa, DD and DNH shall complete the implementation of the revised AUFLS in Goa, DD and DNH at the earliest. Goa representative intimated that AUFLS in Goa has been already implemented for 25 MW.

    DNH representative intimated that tendering process in under process but because of election code of conduct process is slow. DD representative intimated that they have written a letter to GETCO and PGCIL for implementation of the same.

    The sub-committee noted as above.

    ANY OTHER ITEMS

    9.22 RESTORATION OF COLLAPSED 1 NO. OF TOWER OF 400KV D/C LILO SOLAPUR KARAD LINE & COLLAPSED 2 NOS. OF TOWER OF 400KV SOLAPUR KOLHAPUR LINE

    AGM WRLDC intimated that the Significance incidences in Maharashtra have taken place i.e. One no. of tower of 400kV d/c LILO Solapur-Karad line & collapsed & 2 nos. of tower of 400kV Solapur- Kolhapur line. Subsequent to that power flow pattern in Maharashtra has been totally changed. He requested Reliance transmission for restoration progress.

    VP, Reliance (WRTML) intimated latest status vide email as below:

    A. Restoration of collapsed 1 no. of tower of 400kV D/C LILO Solapur Karad line:

    Erection gang mobilized on site

    Tower material has reached at site

    Tower erection will start immediately

    Restoration of LILO Solapur Karad line by 16.03.2014

    B. Restoration of collapsed 2 nos. of tower of 400kV Solapur Kolhapur Transmission line:

    Dismantling of failed tower is in progress in full swing.

    2 trucks of ERS has reached site

  • Minutes of 457TH OCC meeting held on 11th March 2014 at NTPC Mumbai

    ERS unloading & erection shall start today

    Site will be cleared by today evening.

    Tower material on its way to site

    The sub-committee noted as above.

    ITEM NO. 10: DATE AND VENUE OF NEXT OCC MEETING As per meeting roaster circulated during 452nd OCC meeting, the 458th OCC Meeting

    will be hosted by Maharashtra and scheduled on 16th April 2014 at Prakashgad,

    Bandra(E), Mumbai.

    *****************

  • Sl.No. Organisation, Name & Designation E-mail

    I WRPC1 Shri S.D. Taksande, M.S. [email protected] Shri M.M. Dhakate, S.E. [email protected] Shri L.K.S. Rathore, DD(Opn) [email protected]

    II MSETCL / MSEDCL/MahaGenco4 Shri D.K. Rokade, S.E. [email protected] Shri H.M. Sahare, S.E. [email protected] Shri B.P. Singh, E.E. [email protected] Shri Ajit V. Pachori, E.E. [email protected] Shri A.V. Patel, E.E. [email protected] Shri D.J.Kolhe, E.E. [email protected] Miss. S.P. Mahajan, A.E. [email protected]

    III MPPTCL / MPPGCL11 Shri P.A.R. Bende CE [email protected]

    IV CSPTCL / CSPGCL12 Shri R. K. Bhagwat, ACE [email protected] Shri A.K. Khanna, E.E. [email protected]

    V GETCO / GSLDC/ GSECL14 Shri B.B. Mehta, C.E. [email protected] Shri B.M. Shah, D.E. [email protected]

    VI D D / DNH ELE.DEPT. 16 Shri H.C. Surma, A.E. [email protected] Shri Jay Solanki, J.E. ld-aesldc-dd.nic.in

    VII GOA ELE. DEPT. 18 Shri Sudan Kuncolienkar, Asst. Mgr. [email protected]

    VIII WRLDC / POWERGRID19 Shri P. Mukhopadhyay, G.M. [email protected] Shri V.K. Shrivastav, A.G.M. [email protected] Shri P.R. Wankhede, D.G.M. [email protected] 22 Shri K.Y. Deone, C.M. [email protected] Miss. Pushpa.S., C.M. [email protected] Shri Anand Dubey, C.M. [email protected] Shri Abhishek Kr. Gupta, Dy. Mgr. abhishek_all @yahoo.com26 Shri Kuleshwar Sahu, C.M. [email protected] Miss.Sumegha Katiyar, Sr. Eng. [email protected] 28 Shri Ankur Gulati, Sr. Eng. [email protected] Shri Aditya P. Das, Dy. Mgr. [email protected]

    IX NTPC30 Shri Pradeep B. Behere, G.M. pbbehere @ntpc.co.in31 Shri S.K. Shrivastava, A.G.M. [email protected] Shri E.P. Rao, A.G.M. [email protected] Shri Hari Nath, A.G.M. [email protected] Shri Tusar Bhattacharjee, A.G.M. [email protected] Shri H.D. Vaidya, A.G.M. [email protected]

    LIST OF PARTICIPANTS OF 457th OCC MEETING OF WRPC HELD ON 11.03.2014

  • 36 Shri S. Paul, A.G.M. [email protected] Shri D.B. Adhikary, A.G.M. [email protected] Shri D. Mukharjee, A.G.M. [email protected] Shri D.K. Pramal, A.G.M. [email protected] 41 Shri M.K. Jain, D.G.M. [email protected] Shri A.K.Chandelia, D.G.M. [email protected]

    X TATA POWER43 Shri R.M.Sankhe, G.M. [email protected] Shri P.R. Gadave, A.G.M. [email protected] Shri Bijan Biswas, Exe. [email protected]

    XI CENTRAL RAILWAY46 Shri Milind Pakha [email protected]

    XII APL 47 Shri C.S. Bobade, G.M. [email protected]

    XIII RINFRA48 Shri Pinal Desai, A.V.P. [email protected] Shri G.N. Kameshwaran, D.G.M. [email protected]

    XIV KSK Mahanadi50 Shri B.V. Rao, Mgr. [email protected]

    XV JPL 51 Shri Ajeet Kumar, Mgr. [email protected]

    XVI NPCIL52 Shri S.K. Maiti, S.C.E. [email protected] Shri P. Mohanty, S.C.E. [email protected] 54 Shri A. Sheopure, A.S.C.E. [email protected] Shri S.S. Gadre, Sr. Op. Eng. [email protected]

    XVII ESSAR 56 Shri O.J. Saxena, Sr. Mgr. [email protected] Shri Khilendra Pant, Asst. Mgr. [email protected]

    XVIII TORRENT POWER LTD.58 Shri M.H.Kshatriya, G.M. [email protected] Shri B.V. Patel, Mgr. babubhaipatel@torrent power.com

    XIX STERLITE GRID LTD60 Shri Sachin Deshpande, G.M. [email protected]

  • Anaulagnak 2.1

    maah frvarI 2014

    1. INTEGRATED OVER AN-HOURek GaMTo maoM samaakilat

    1.1 MAXIMUM FREQUENCY 50.51 Hz. BETWEEN 0200 Hrs & 0300 Hrs Hrs. ON 28.02.2014AiQaktma AavaRi%t

    1.2 MINIMUM FREQUENCY 49.70 Hz. BETWEEN 1800 Hrs & 1900 Hrs Hrs. ON 28.02.2014nyaUnatma AavaRi%t

    1.3 AVERAGE FREQUENCY 50.06 Hz.AaOsat AavaRi%t

    2. INSTANTANEOUS ta%kailak

    2.1 MAXIMUM FREQUENCY 50.71 Hz. AT 02:10 Hrs. ON 28.02.2014AiQaktma AavaRi%t

    2.2 MINIMUM FREQUENCY 49.37 Hz. AT 18:50:00 Hrs. ON 28.02.2014nyaUnatma AavaRi%t

    3. %AGE OF TIME WHEN FREQUENCY WAS FEBRUARY 2014 JANUARY 2014 DECEMBER 2013

    AavaRi%t ka samaya p`itSat maoM

    3.1 BELOW 48.5 Hz. 0.00 0.00 0.00 48.5 hT\ja ko naIcao3.2 BETWEEN 48.5 Hz. AND 48.8 Hz. 0.00 0.00 0.00 48.5 hT\ja AaOr 48.8 hT\ja ko baIca3.3 BETWEEN 48.8 Hz. AND 49.2 Hz. 0.00 0.00 0.00 48.8 hT\ja AaOr 49.2 hT\ja ko baIca3.4 BETWEEN 49.2 Hz. AND 49.5 Hz. 0.00 0.01 0.05

    49.2 hT\ja AaOr 49.5 hT\ja ko baIca3.5 BETWEEN 49.5 Hz. AND 49.7 Hz. 0.41 0.61 1.88 49.5 hT\ja AaOr 49.7 hT\ja ko baIca3.6 BETWEEN 49.7 Hz. AND 49.9 Hz. 10.69 54.23 48.64 49.7 hT\ja AaOr 50.2 hT\ja ko baIca3.7 BETWEEN 49.9 Hz. AND 50.05 Hz. 40.14 35.69 39.87

    49.9 hT\ja AaOr 50.05 hT\ja ko baIca3.8 BETWEEN 50.05 Hz. AND 51.5 Hz. 48.76 9.46 9.56

    50.05 hT\ja AaOr 51.5 hT\ja ko baIca3.9 ABOVE 51.5 Hz. 0.00 0.00 0.00

    51.5 hT\ja ko }pr

    4.1 NO. OF TIMES FREQUENCY 0 0 0 TOUCHED 48.80 Hz. AavaRi%t 48.80 hT\ja kao CUhI

    4.2 NO. OF TIMES FREQUENCY 0 0 0 TOUCHED 48.60 Hz. AavaRi%t 48.60 hT\ja kao CUhI

    4.3 NO. OF TIMES FREQUENCY 0 0 0 TOUCHED 51.00 Hz. AavaRi%t 51.00 hT\ja kao CUhI

    maoM AavaRi%t ko AaMkD,aoM ka ivavarNa

    FREQUENCY PARTICULARS DURING FEBRUARY 2014

    (AS PER FREQUENCY REPORT OF WRLDC)

    (piScama xao~ Baar p`oYaNa kond` kI AavaRi%t irpaoT- ko AaQaar pr)

  • Voltage Profile during the month of Feb. 2014

    दनांकDate

    अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतमMax. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv

    1 421 401 426 403 409 409 408 408 415 399 414 402 424 413 417 3922 420 402 423 404 409 409 408 408 417 402 418 404 425 415 420 3993 421 399 426 400 429 405 425 402 412 399 419 408 423 410 413 3964 422 402 426 404 430 406 428 401 414 400 414 404 424 412 414 3965 420 396 423 400 409 409 408 408 413 396 415 401 424 411 415 3996 420 396 426 400 428 405 426 402 415 398 416 402 423 411 412 4007 420 394 424 399 430 402 427 401 416 399 417 402 423 409 416 3968 418 393 422 397 409 409 408 408 416 399 416 402 422 409 418 3989 418 399 423 404 409 409 408 408 417 402 417 407 419 409 419 400

    व तूदाब परेखा फरवर 2014 सं नक Annex-2.3

    इंदौर इटारसी कराड धलुे असोज कासोर िभलाई जेतपुरIndore Itarsi Karad Dhule Asoj Kasor Bhilai Jetpur

    10 419 394 423 399 409 409 408 408 416 400 415 401 420 408 417 39511 421 393 426 397 429 405 427 401 44 399 419 404 423 407 414 39912 419 395 422 400 409 409 408 408 416 401 419 407 421 410 418 39813 420 396 424 401 409 409 408 408 417 400 416 401 421 409 418 40114 421 399 424 403 430 419 428 414 417 402 415 402 421 409 417 40015 423 397 424 399 428 414 429 412 417 398 406 406 421 407 418 40016 423 397 424 400 431 404 424 401 416 401 422 409 421 409 418 40317 421 402 424 403 432 414 420 404 416 402 412 405 422 410 417 39818 420 397 423 399 409 409 408 408 416 400 414 401 422 414 416 40019 420 396 423 399 409 409 408 408 411 398 418 405 421 413 413 39920 417 397 420 402 429 406 426 401 413 399 416 404 421 413 410 39821 419 399 422 402 430 407 421 401 415 401 418 406 422 411 414 39722 419 397 422 402 432 409 423 401 416 400 413 402 423 413 414 40023 420 396 423 397 430 412 428 404 414 404 415 402 427 414 416 40324 421 399 423 401 433 411 425 400 416 398 414 402 427 415 418 40225 421 399 423 401 433 411 425 400 416 398 414 402 427 415 418 40226 420 397 423 404 431 411 428 409 411 397 415 404 424 414 412 39327 418 398 426 403 409 409 408 408 417 399 418 402 429 415 419 39128 421 400 427 406 409 409 408 408 414 400 416 403 430 415 418 401

    423 393 427 397 433 402 429 400 417 396 422 401 430 407 420 391

  • दनांकDate

    अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतम अिधकतम युनतमMax. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv Max. Kv Min. Kv

    1 424 404 415 392 424 404 431 407 766 746 797 765 800 756 804 7692 422 406 417 398 426 404 434 407 769 754 798 774 801 769 804 7773 423 405 416 402 426 401 432 410 767 750 796 768 802 773 805 7764 426 407 417 402 423 403 430 408 768 751 797 779 801 776 808 7785 422 403 415 398 423 397 430 400 768 749 797 767 798 763 797 7586 425 404 417 401 423 399 432 404 768 750 797 767 802 773 807 7707 427 401 419 397 423 396 431 404 770 741 800 763 807 769 809 7698 422 403 416 403 424 395 427 399 756 737 788 756 801 765 802 7679 422 405 416 401 424 402 427 404 755 738 786 758 804 773 804 775

    10 421 400 414 396 423 398 429 403 3 88 6 98 6 801 60

    वािलयर बनाBina Gwalior Nagda Khandwa Sipat seoni Gwalior Bina

    बना वािलयर नागदा खंडवा िसपत िसविन

    10 421 400 414 396 423 398 429 403 755 737 788 765 798 765 801 76011 423 397 414 390 426 396 433 399 758 736 794 750 800 752 802 75612 420 403 414 395 423 397 428 403 757 739 787 759 801 763 798 77013 424 405 417 400 427 397 430 402 759 740 794 760 804 773 803 77214 426 410 420 406 424 400 431 405 761 740 794 766 810 780 808 78215 425 404 417 399 426 399 430 401 762 738 794 962 808 768 806 76816 426 406 422 400 427 402 429 400 759 739 792 760 815 774 811 77617 429 407 417 398 427 404 427 406 761 742 792 762 805 765 810 77418 426 404 418 395 423 399 427 404 763 748 793 768 805 759 806 76819 423 409 415 394 422 399 428 403 759 737 795 765 804 758 806 76720 421 406 410 397 420 398 426 406 765 749 795 771 791 766 799 77421 423 407 424 399 423 403 428 405 759 744 792 760 795 761 800 76722 425 406 414 398 423 400 425 404 760 743 790 762 794 762 800 76823 425 402 412 392 424 400 428 405 758 740 790 759 796 755 799 76124 425 401 411 393 423 401 427 403 760 744 796 764 792 757 798 75625 421 408 412 395 423 401 427 403 756 742 793 766 795 764 795 76926 422 405 413 390 421 399 426 402 757 739 789 760 796 750 798 76127 426 407 416 393 421 401 431 403 760 741 795 762 803 755 804 76228 428 409 414 392 423 403 432 405 762 740 795 753 809 775 803 771

    429 397 424 390 427 395 434 399 770 736 800 750 815 750 811 756

  • No. of Occasions

    Max Load Relief at 49.2 Hz

    No. of Occasions

    Max Load Relief at 49.2 Hz

    No. of Occasions

    Max Load Relief at 49.2 Hz

    No. of Occasions

    Max Load Relief at 49.2 Hz

    1 01-Feb-14 0 0 0 0 0 0 0 02 02-Feb-14 0 0 0 0 0 0 0 03 03-Feb-14 0 0 0 0 0 0 0 04 04-Feb-14 0 0 0 0 0 0 0 05 05-Feb-14 0 0 0 0 0 0 0 06 06-Feb-14 0 0 0 0 0 0 0 07 07-Feb-14 0 0 0 0 0 0 0 08 08-Feb-14 0 0 0 0 0 0 0 09 09-Feb-14 0 0 0 0 0 0 0 0

    10 10-Feb-14 0 0 0 0 0 0 0 011 11-Feb-14 0 0 0 0 0 0 0 012 12-Feb-14 0 0 0 0 0 0 0 013 13-Feb-14 0 0 0 0 0 0 0 014 14-Feb-14 0 0 0 0 0 0 0 015 15-Feb-14 0 0 0 0 0 0 016 16-Feb-14 0 0 NIL NIL NIL 017 17-Feb-14 0 0 0 0 0 0 0 018 18-Feb-14 0 0 0 0 0 0 0 019 19-Feb-14 0 0 0 0 0 0 0 020 20-Feb-14 0 0 0 0 0 0 0 021 21-Feb-14 0 0 0 0 0 0 0 022 22-Feb-14 0 0 0 0 0 0 0 023 23-Feb-14 0 0 0 0 0 0 0 024 24-Feb-14 0 0 0 0 0 0 0 025 25-Feb-14 1 17 0 0 0 0 0 026 26-Feb-14 0 0 0 0 0 0 0 027 27-Feb-14 0 0 0 0 0 0 0 028 28-Feb-14 0 0 0 0 0 0 0 0

    Max 1 17 0 0 0 0.0 0 0Total 1 17 0 0 0 0 0 0

    1025 91 490 851

    ANNEX -2.4

    DateSl. No Madhya Pradesh( Compiled from the data received from the constituents)

    Chhattisgarh

    Under Frequency Operation in various Constituent System of Western Region during the month FEBRUARY 2014

    Recommonded Load relief at 49.2 Hz / 49.0/48.8/48.6 Hz

    Gujarat Maharashtra

  • ANNEXURE-2.5

    Power Cut/Restrictions in Western Region for the month of February-2014 k : gaujarat Gujarat

    1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM 1 Power Cut/ Restriction on Industries a) All industries are allowed to run their units on all days of week & if they want to avail staggered holiday,

    then they will have to staggered on notified day only & cannot avail as per their choice. b) All industries are required to keep their recess timings staggered. 2 kRiYa va ga`amaINa xao~aoM kao ivaVut AapUit- 2. Power supply to Agricultural & Rural Sectors

    a) Only 8 Hrs. Power supply in staggered form in rotation of day & night is given to Ag. Single Phase supply during rest of 16 Hrs by providing LSTC.

    b) Jyotigram Yojana 24 hrs. 3 Anya jaanakarI 3. Any other information: NIL. K : maQya p`doSa Madhya Pradesh 1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid 1 Power Cut/ Restriction on Industries, Load Shedding in the state etc

    ivavarNa Details ivaVut kTaOtI kI maa~aQuantum of

    power cut (MW)

    pabandI ka samayaRestriction Timing

    p`it idna kula }jaa- kTaOtITotal Energy Cut

    (MUs /day sao From tk To (a) Power Restrictions(Evening peak Hour) on non continuous process HT/LT IndustriesM (b) Baar inayamana Load Shedding

    SaUnya Nil SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    (c) Anya jaanakarI Other information 1.Weekly Off 2.Staggering of power supply

    SaUnya Nil SaUnya Nil

    SaUnya Nil SaUnya Nil

    SaUnya Nil SaUnya Nil

    SaUnya Nil SaUnya Nil

    2 kRiYa xao~ kao ivaVut AapUit- 2. Power supply to Agricultural Sector: -

    ivavarNa Details sao From idnaaMk Date

    tk To idnaaMk Date

    p`it idna AapUit- GaMTo Supply Hours per day Max. (Hrs) Min. (Hrs) Average (Hrs)

    2.1 Three-Phase Supply(DLF)

    01.02.2014 28.02.2014 23:44 22:40 23:32

    2.1 Three-Phase Supply(Irrigation)

    01.02.2014 28.02.2014 09:56 09:05 09:46

    2.1 Three-Phase Supply(Mixed)

    01.02.2014 28.02.2014 23:43 22:27 23:30

  • 3 Anya jaanakarI 3. Any other information

    SahrI xao~aoM maoM inayamana ivaVut kTaOityaaM Scheduled Power cuts in Urban Areas ivavarNa Details sao From

    idnaaMk Date tk To idnaaMk

    Date Aaosat p`itidna Average Supply AapUit- GaMTo Hours per day

    Max. (Hrs)

    Min. (Hrs) Average (Hrs)

    3.1 Commissionary H. Qtrs. 01.02.2014 28.02.2014 23:53 23:37 23:47 3.2 District Head Qtrs. 01.02.2014 28.02.2014 23:55 23:40 23:51 3.3 Tehsil Head Qtrs. 01.02.2014 28.02.2014 23:49 23:09 23:41

    ga : maharaYT/ Maharashtra 1 ]QyaaogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid

    1. Power Cut/ Restriction on Industries, Load Shedding in the state etc

    ivavarNa Details ivaVut kTaOtI kI maa~aQuantum of

    power cut (MW)

    pabandI ka samayaRestriction Timing

    p`it idna kula }jaa- kTaOtITotal Energy Cut

    (MUs /day From To (a) Power Cuts/Restriction on HT/ LT Industries (b) Load Shedding From 01.02.14 to 28.02.14

    SaUnya Nil

    @ 0-1655MW

    SaUnya Nil

    00.00

    SaUnya Nil 24.00

    SaUnya Nil

    @ 9.5 MUs/day

    (c) Any other information 1.Weekly Off 2. Staggering of power supply Industrial Staggering LS withdrawn from 03/02/2012

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    2 kRiYa xao~ kao ivaVut AapUit-

    2. Power supply to Agricultural Sector ivavarNa Details sao From

    idnaaMk Date tk To

    idnaaMk Date p`it idna AapUit- GaMTo Supply Hours per day

    Max. (Hrs) Min. (Hrs) Average (Hrs) 2.1 Three-Phase Supply 01.02.2014 28.02.2014 10:00 08:00 09:00

    2.2 Single-Phase Supply 01.02.2014 28.02.2014 18:00 18:00 18:00 3 Anya jaanakarI Any other information:

    There is no load shedding on industrial feeders in Maharashtra

  • Ga : C%tIsagaZ, Chhattisgarh: 1 ]QyaaogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid 1 Power Cut/ Restriction on Industries, Load Shedding in the state etc

    ivavarNa Details ivaVut kTaOtI kI maa~aQuantum of power cut (MW)

    pabandI ka samaya Restriction Time

    p`it idna kula }jaa- kTaOtI

    Total Energy Cut (MUs /day)

    sao From tk To

    (A) Scheduled (a) (i) Power Cuts/ Restriction on HT Industries (ii) Power Cuts/Restriction on LT Industries (iii) Power Cuts/Restriction on Rural (iv) Agriculture pump* (v)Urban/ Sub-Urban (iv)Town feeders(C-1to C-6) (B) Un-Scheduled (a) Load Shedding

    00.00(Av)

    00.00(Av)

    00.00 (Av)

    111.07 (Av) of 23 days 00.00(Av) 00.00 (Av)

    1.Rural 90.31(Av) for 34.86 Hrs. 2.Town Feeders (C-1to C-6 & X) : 0.00(Av)

    - - -

    17.00 - - -

    - - -

    23.00 - - - -

    - - -

    0.666 - -

    0.105 -

    3. HT Industries 0.00 (Av) for 00 Hrs. 0.00 Total Energy Cut/day 0.771 ( b) Any other information 1.Weekly Off/staggering of power supply

    1day (In a week as per consumer’s option) 50MW(Av.)

    -

    -

    0.039

    2 kRiYa xao~ kao ivaVut AapUit- 2. Power supply to Agricultural Sector

    ivavarNa Details sao From idnaaMk Date

    tk To idnaaMk Date

    p`it idna AapUit- GaMTo Supply Hours per day Max. (Hrs) Min. (Hrs) Average (Hrs)

    2.1 Three-Phase Supply 01.02.2014 to 28.02.14, 6.00 Hrs (Power cut)

    18.00

    2.2 Single-Phase Supply - - - - - 2.3 Remarks/Note/ - - - - -

    *-up till 23/2/2014, as conveyed to SLDC, CSPTCL for power cut under Atal Jyoti scheme by Raipur & Durg region, CSPDCL 3 Anya jaanakarI / Any other information: SaUnya Nil ca : gaaovaa Goa: SaUnya Nil

  • प म े ऽय भार ूेषण कि, मु बई ूणाली ूचालन-ISO-I

    संल नकAnnex-2.6 पावर िसःटम ऑपरेशन कारपोरेशन िलिमटेड

    (पावरिमड क एक पूण ःवािम व वाली कंपनी)

    प म े ऽय भार ूेषण के ि,मु बई Power System Operation Corporation Ltd. (A wholly owned subsidiary company of POWERGRID)

    Western Regional Load DespatchCentre,Mumbai

    अिनवाय युिनट आऊटेज का फरवर 2014का वःता रत यौरा Details of forced unit outages during the month ofFeb.2014

    अन ुबमांक Sl.No

    यिुनट Unit

    सघंटक Constituent/IPP

    मता मेगावॉटCap.MW

    स o From

    समय दनांक

    स o From

    समय दनांक

    कारण Reason

    Time Date Date

    1. एःसार वा डनर

    ESSAR VADINAR-I

    गुरा विनिल GSECL

    660 21:56 20-Jan-14 20:18 10-Feb-14 Coal shortage

    2. एःसार Essar-2

    गुरा विनिल GSECL

    172 12:12 22-Feb-13 अनपुल ध Still out

    अनपुल ध Still out

    Shortage of gas

    3. एसएलपीपी SLPP-1

    गुरा विनिल GSECL

    125 14:45 23-Feb-14 12:37 27-Feb-14 BTL

    4. एकेएलट पीएसAKLTPS-1

    गुरा विनिल GSECL

    125 11:47 26-Feb-14 अनपुल ध Still out

    अनपुल ध Still out

    DCS FAIL

    5. एपीएल APL - 2

    अदानी ADANI

    330 0:56 3-Feb-14 अनपुल ध Still out

    अनपुल ध Still out

    Turbine vibration bearing probl em

    6. एपीएल APL-5

    अदानी ADANI

    660 17:32 15-Feb-14 4:56 27-Feb-14 Turbine vibration

    7. एपीएल APL - 6

    अदानी ADANI

    660 20:49 25-Feb-14 19:47 3-Mar-14 Coal mill problem

    8. टाटा TATA-6

    मारा वउकंिल MSPGCL

    500 23:52 19-Jul-13 अनपुल ध Still out

    अनपुल ध Still out

    For Economy S/D

    9. वीआईपीएल VIPL-I

    मारा वउकंिल MSPGCL

    300 1:05 2-Oct-13 अनपुल ध Still out

    अनपुल ध Still out

    Turbine bearing vibration probl em

    10. टाटा TATA-8

    मारा वउकंिल MSPGCL

    250 22:55 9-Jan-14 अनपुल ध Still out

    अनपुल ध Still out

    H/T due to fire near turbine generator desk

    11. चंिपुर Chandrapur-2

    मारा वउकंिल MSPGCL

    210 12:38 14-Jan-14 13:10 23-Feb-14 ID fan problem

    12. कोराड KORADI-6

    मारा वउकंिल MSPGCL

    210 6:51 24-Jan-14 14:56 14-Feb-14 Coal bunkering problem

    13. डब यूपीसीएल WPCL-1

    मारा वउकंिल MSPGCL

    135 12:45 30-Jan-14 अनपुल ध Still out

    अनपुल ध Still out

    Furnace press high

    14. डब यूपीसीएल WPCL-3

    मारा वउकंिल MSPGCL

    135 4:21 7-Feb-14 13.02.14 Less requisition

  • प म े ऽय भार ूेषण कि, मु बई ूणाली ूचालन-ISO-I

    15. चंिपुर C'PUR - 6

    मारा वउकंिल MSPGCL

    500 15:23 11-Feb-14 20:33 13-Feb-14 BTL

    16. नािसक NASIK-3

    मारा वउकंिल MSPGCL

    250 3:00 11-Feb-14 1:00 19-Feb-14 UAT problem

    17. कोराड KORADI-5

    मारा वउकंिल MSPGCL

    210 1:53 14-Feb-14

    21.02.14

    ID fan problem

    18. ितरोडा Tiroda-I

    मारा वउकंिल MSPGCL

    660 20:59 15-Feb-14 20:54 26-Feb-14 Turbine bearing problem

    19. ितरोडा Tiroda-2

    मारा वउकंिल MSPGCL

    660 11:25 17-Feb-14 1:52 22-Feb-14 BTL

    20. कोराड KORADI-6

    मारा वउकंिल MSPGCL

    210 23:57 19-Feb-14 2:50 23-Feb-14 BTL

    21. भुसावल BHUSWAL-2

    मारा वउकंिल MSPGCL

    210 3:01 22-Feb-14 17:06 25-Feb-14 PA fan temp. High

    22. खापरखेड़ा KHAPERKHEDA-3

    मारा वउकंिल MSPGCL

    250 14:48 22-Feb-14 1:30 25-Feb-14 BTL

    23. जयगड Jaigad-4

    मारा वउकंिल MSPGCL

    300 19:30 22-Feb-14 11:07 4-Mar-14 Low schedule

    24. कोराड Koradi-5

    मारा वउकंिल MSPGCL

    300 4:04 23-Feb-14 अनपुल ध Still out

    अनपुल ध Still out

    Electrical fault

    25. पल PARLI-4

    मारा वउकंिल MSPGCL

    210 18:36 28-Jan-14 19:56 3-Feb-14 Air preheater problem

    26. भुसावल BHUSAWAL-4

    मारा वउकंिल MSPGCL

    250 14:32 28-Feb-14 18:02 3-Mar-14 Ash hopper problem

    27. आरजीपीपीएल RGPPL-1B

    आरजीपीपीएल RGPPL

    320 0:00 16-Jan-14 Ready Ready Less requisition

    28. आरजीपीपीएल RGPPL-2B

    आरजीपीपीएल RGPPL

    320 0:00 16-Jan-14 Ready Ready Less requisition

    29. आरजीपीपीएल RGPPL 3A

    आरजीपीपीएल RGPPL

    320 0:00 16-Jan-14 Ready Ready Less requisition

    30. आरजीपीपीएल RGPPL-1A

    आरजीपीपीएल RGPPL

    320 15:00 18-Jan-14 अनपुल ध Still out

    अनपुल ध Still out

    SRV problem

    31. आरजीपीपीएल RGPPL 3B

    आरजीपीपीएल RGPPL

    320 12:30 8-Feb-14 Ready Ready Less requisition

    32. िसंगाजी SINGAJI - I

    मू वउकंिल MPPGCL

    600 4:22 12-Feb-14 17.03.14 Coal shortage

    33. सातपुरा SATPURA-11

    मू वउकंिल MPPGCL

    250 19:13 15-Feb-14 21:49 19-Feb-14 Main stream temperature low

    34. सातपुरा SATPURA-11

    मू वउकंिल MPPGCL

    250 5:42 26-Feb-14 16:42 2-Mar-14 BTL

    35. एःसार महान Essar-Mahan-1

    एःसार ESSAR

    600 0:00 29-Jan-14 0:15 18-Feb-14 Less requisi tion

    36. लॅ को Lanco-2

    लॅ को Lanco

    300 12:20 21-Aug-13 अनपुल ध Still out

    अनपुल ध Still out

    Coal shortage

    37. वंदना Vandana-1

    वंदना Vandana

    135 1:49 12-Jan-14 अनपुल ध Still out

    अनपुल ध Still out

    BTL

  • प म े ऽय भार ूेषण कि, मु बई ूणाली ूचालन-ISO-I

    38. ससान Sasan-2

    आरईएल REL

    660 2:05 16-Feb-14 16:50 23-Feb-14 Problem in ash handling

    39. कावास Kawas 2A

    एनट पीसीNTPC 164 20:18 23-Dec-13 Ready Ready Less requisition

    40. गांधार Gandhar-3

    एनट पीसीNTPC 144 20:37 28-Dec-13 Ready Ready Less requisition

    41. गांधार Gandhar-I

    एनट पीसीNTPC 144 20:11 1-Jan-14 Ready Ready Less requisition

    42. कावास Kawas 2B

    एनट पीसीNTPC 164 9:00 13-Jan-14 4:21 5-Mar-14 Maintenance

    43. गांधार Gandhar-2

    एनट पीसीNTPC 219 0:23 30-Jan-14 अनपुल ध Still out

    अनपुल ध Still out

    Less requisition

    44. कावास Kawas-1A

    एनट पीसीNTPC 164 20:55 4-Feb-14 7:12 20-Feb-14 Less requisition

    45. कावास

    Kawas-1B एनट पीसीNTPC 164 19:51 13-Feb-14 5:03 20-Feb-14 Less requisition

    46. कावास Kawas 1A

    एनट पीसीNTPC 164 12:10 21-Feb-14 Ready Ready Less requisition

    47. कावास Kawas 1B

    एनट पीसीNTPC 164 0:12 22-Feb-14 11:44 26-Feb-14 Less requisition Note: Units out for more than 72 hrs are only included.

  • प म े ऽय भार ूेषण कि, मु बई ूणाली ूचालन-ISO-I

    संल नकAnnex-2.7 पावर िसःटम ऑपरेशन कारपोरेशन िलिमटेड

    (पावरिमड क एक पूण ःवािम व वाली कंपनी)

    प म े ऽय भार ूेषण के ि,मु बई Power System Operation Corporation Ltd. (A wholly owned subsidiary company of POWERGRID)

    Western Regional Load DespatchCentre,Mumbai

    िनयो जत युिनट आऊटेज का फरवर 2014 का वःता रत यौरा Details of planned unit outages during the month of Feb.2014

    अन ुबमांक Sl.No

    यिुनट Unit

    सघंटक Constituent/IPP

    मता मेगावॉटCap.MW

    सo From

    समय दनांक

    स o From

    समय दनांक

    कारण Reason

    Time Date Time Date

    1. डब यूट पीएस WTPS-3

    गुरा विनिल GSECL

    210 2:12 12-Feb-14 अनपुल ध Still out

    अनपुल ध Still out

    AOH

    2. पल ParlI-3

    मारा वउकंिल MSPGCL

    210 23:51 13-Feb-13 अनपुल ध Still out

    अनपुल ध Still out

    Water Shortage

    3. चंिपुर Chandrapur-5

    मारा वउकंिल MSPGCL

    500 1:01 14-Jul-13 8:41 19-Feb-14 AOH

    4. कोरबा प म KORBA-(W)-4

    छरा वउकंिल CSPGCL

    210 22:26 7-Feb-14 24.03.14 GT Tap changer problem

  • Annex- 3.1

    (MW) sao From tk To1 gau}ivainaila GUVNL

    NIL2

    NIL

    3 Craiva]kMila CSPGCL

    NIL

    4

    NIL

    5 koMd``Iya xao~ Central Sector5.1 VSTPS 4 210 01.04.14 07.04.14 AOH5.2 VSTPS 2 210 08.04.14 27.04.14 AOH5.3 VSTPS 1 210 30.04.14 19.05.14 AOH5.4 CGPL 10 800 26.03.14 13.05.14 COH5.5 KSTPS 5 500 15.04.14 09.05.14 AOH5.6 SASAN UMPP 3 660 03.04.14 22.04.14 PG TEST

    5.7KAPS-2 2 220 07.04.14 05.05.14

    BIANNUAL SHUTDOWN

    maraiva]kMila MSPGCL

    map`iva]kMila MPPGCL

    ReasonS. No. Unit No.