71281912 pgcil latest testing format

149

Upload: rajesh-kumar-pachigolla

Post on 14-Apr-2015

142 views

Category:

Documents


15 download

TRANSCRIPT

Page 1: 71281912 Pgcil Latest Testing Format
Page 2: 71281912 Pgcil Latest Testing Format
Page 3: 71281912 Pgcil Latest Testing Format

PRE-COMMISSIONING PROCEDURESAND

FORMATS FOR SUBSTATION BAY EQUIPMENT

FOR INTERNAL CIRCULATION ONLYDOC NO. D-2-01-03-01-02

पावरपावरपावरपावर िमडिमडिमडिमड कारपोरशनकारपोरशनकारपोरशनकारपोरशन ऑफऑफऑफऑफ इडयाइडयाइडयाइडया िलिमटडिलिमटडिलिमटडिलिमटडकियकियकियकिय चालनचालनचालनचालन सवाऐसवाऐसवाऐसवाऐ

POWER GRID CORPORATION OF INDIA LIMITEDCORPORATE OPERATION SERVICES

APRIL-2008

Page 4: 71281912 Pgcil Latest Testing Format
Page 5: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

CONTENTS

SR.

NO

PARTICULARS

PAGE

NOS

1.0 PRE-COMMISSIONING PROCEDURES FOR SUBSTATION BAY

EQUIPMENT

01-03

2.0 TRANSFORMER AND REACTOR 04-17

2.1 Checks after receipt of Transformer/ Reactor at site 04-06

2.2 Insulating oil 06-07

2.3 Oil filling 08-11

2.4 Hot Oil Circulation using High Vacuum Filter Machine 11-12

2.5 Procedure for Dry Out of Wet Winding of Transformer/ Reactor by

Vacuum Pulling, N2 filling and Heating

13-14

2.6 Relation between different units (conversion of units) 15

2.7 Check list for energization of Transformer/ Reactor 16-17

3.0 PRE-COMMISSIONING CHECKS/ TESTS FOR TRANSFORMERS &

REACTORS

18-32

3.1 Core Insulation Check 20

3.2 Operational checks on Protection System 20

3.3 Insulation Resistance (IR) Measurement 20-21

3.4 Capacitance & Tan Delta Measurement of Bushing 22

3.5 Capacitance and Tan δ measurement of windings 23-24

3.6 Turns ratio (Voltage ratio) measurement 24

3.7 Vector Group & Polarity 24-25

3.8 Winding resistance measurement 25-26

3.9 Magnetic Balance test 26-27

3.10 Floating Neutral point measurement 27

3.11 Measurement of Short Circuit Impedance 27

3.12 Exciting/Magnetising current measurement 28

Page 6: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

3.13 Vibration measurement of Oil-immersed Reactor 28

3.14 Operational checks on OLTCs 29-30

3.15 Stability of Differential, REF of Transformer/ Reactor 30-31

3.16 Tests/ Checks on Bushing Current Transformers (BCTs) 31

3.17 Frequency Response Analysis (FRA) measurement 31-32

3.18 Dissolved Gas Analysis (DGA) of oil sample 32

3.19 Thermovision Infra-red scanning (IR thermography) 32

4.0 PRE-COMMISSIONING CHECKS/ TESTS FOR OTHER SWITCHYARD

EQUIPMENTS

33-55

4.1 C & Tan δ measurement of CT, CVT, CB voltage grading capacitor &

Surge Arresters

36-39

4.2 Checks/ Tests applicable for CTs 39-43

4.3 Checks/ Tests applicable for Circuit Breakers 43-50

4.4 Checks/ Tests applicable for CVTs 50

4.5 Checks/ Tests applicable for Isolators 51

4.6 Checks/ Tests applicable for Surge Arrestors 51-52

4.7 Checks/ Tests for other areas/ equipments 52-55

5.0 PRE-COMMISSIONING FORMATS FOR SWITCHYARD EQUIPMENTS

5.1 No. CF/CT/01/R-2 DATED 31/12/07 - CURRENT TRANSFORMER 08 pages

5.2 No. CF/CVT/02/R-2 DATED 31/12/07 - CVT 05 pages

5.3 No. CF/BAY/03/R-2 DATED 31/12/07 - BAY/FEEDER 09 pages

5.4 No. CF/SA/04/ R-2 DATED 31/12/07 - SURGE ARRESTOR 03 pages

5.5 No. CF/CB/05/ R-2 DATED 31/12/07 - CIRCUIT BREAKER 14 pages

5.6 No. CF/ICT/06/ R-2 DATED 31/12/07 - ICT 25 pages

5.7 No. CF/SR/07/ R-2 DATED 31/12/07 - SHUNT REACTOR 16 pages

5.8 No. CF/ISO/08/ R-2 DATED 31/12/07 - ISOLATOR/GROUND SWITCH 05 pages

5.9 No. CF/WT/09/ R-2 DATED 31/12/07 - WAVE TRAP 02 pages

Page 7: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

1of 55

1.0 PRE-COMMISSIONING PROCEDURES FOR SUBSTATION BAY EQUIPMENTS

1.1 Introduction

Pre-commissioning checks/ tests are the activities carried out to ascertain the correctness, completeness of installation and healthiness of the equipment before its energization. These checks/ tests are to be carried out by Contractor’s representative in the presence of POWERGRID’s authorised representative.

1.2 Constitution of commissioning team 1.2.1 A Commissioning team should be constituted as per procedures laid down in Works &

Procurement Policy and Procedures (Clause C2.15.4.6 of WPPP Vol. II), which shall oversee/ coordinate with erection agency/ manufacturer for the pre-commissioning test and charging of the equipment. In case of Substation, commissioning team shall consist of following:

(i) I/C of Substation Construction (ii) O&M executive not below Manager (iii) T&C executive not below Sr. Engineer

1.2.2 The responsibilities of the commissioning team are to go through the storage history of each equipment, review the pre-commissioning test results and clear the equipment for energization (as described in section 1.2.3), go through statutory clearances and standing instructions before initial charging of new equipment, witness final commissioning tests and test charging, investigate failure of equipment during test charging, declare commencement of trial operation and evaluate guaranteed test results and recommend acceptance as may be provided in the contract, list out deviations/ exception/ incomplete work, for acceptance/ rejection (Clause C2.15.4.7 of WPPP Vol-II). Proper documentation also to be ensured by the commissioning team based upon the observations for the above for future reference.

1.2.3 The results of all pre-commissioning tests after erection of individual equipment as per requirement of guidelines issued by Corporate OS or in line with manufacturer’s recommendation, carried out jointly by the execution site in association with T&C executive and testing engineer of manufacturer/erection agency (including clearance for charging given by the manufacturer) shall be put up to the Commissioning Team for its acceptance and clearance for charging (Clause C2.15.4.8 (iv) of WPPP Vol-II).

1.2.4 The Commissioning Team shall examine the following statutory and other clearances obtained by Execution Site prior to clearance for test charging of the equipment/transmission line at rated voltage:

Statutory Clearances: a) Electrical Inspector’s Clearance (provisional or final) for charging transmission

line/bay equipment as per I.E. rules. b) P.T.C.C. clearance. c) Copy of notification informing public/administration regarding charging of the line.

d) Forest Clearance

Page 8: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

2of 55

Other Clearances:

a) Charging instruction from SEF Group of Corporate Engineering. b) Relay setting details from Corporate Engineering.

(Clause C2.15.4.8 (v) of WPPP Vol-II)

1.2.5 The Team shall also go through the factory test reports. If such tests have been repeated during pre -commissioning, the Team shall list out deviations, if any, in the results of pre-commissioning tests with respect to the factory tests.

(Clause C2.15.4.8 (vii) of WPPP Vol-II)

1.2.6 After all pre-commissioning checks and tests are found to be acceptable taking into account permissible deviation limits, the commissioning team, in consultation with regional O&M, shall give clearance for commissioning test.

(Clause C2.15.4.8 (viii) of WPPP Vol-II) 1.2.7 In case of deviation in commissioning test results beyond permissible limit as per

guidelines/standards in vogue, the commissioning team shall submit its report along with recommendations to the concerned DGM. In such an event, the test charging will be carried out only after obtaining approval of Head of O&M of the Region based on a proposal of execution site in consultation with regional OS.

(Clause C2.15.4.8 (ix) of WPPP Vol-II)

1.3 Safety

All measures and precautions should be undertaken to prevent occurrence of unsafe acts. All the personnel involved should be thoroughly apprised about the safe procedures to be adopted while performing various activities including carrying out tests in the switchyard. Warning signs and Safety barriers should be positioned in conformity to IE rules as amended from time to time.

1.4 General Procedures during Pre-commissioning of Substation Bay Equipment

All the equipment after erection/assembly at site, should be tested in order to check that it has not been damaged during transport, erection/assembly to such an extent that its future operation will be at risk. The significance of various tests with brief procedure has been elaborated in the subsequent sections of this document. Regarding the detailed testing methods / procedures for conducting various pre-commissioning tests refer to Doc. No. D-2-03-XX-01-01: Maintenance Procedures for Switchyard Equipments-Part 1: EHV Transformers & Reactors and Doc No. D-2-03-XX-01-01 –Part 2: Other Switchyard Equipments.

1.5 Documentation

The results of the test shall be documented on the test record formats as mentioned below, which are also part of this documentation:

Page 9: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

3of 55

Sl. No. FORMAT NO. EQUIPMENT 1. No. CF/CT/01/R-2 DATED 01/04/08 CURRENT TRANSFORMER 2. No. CF/CVT/02/R-2 DATED 01/04/08 CVT 3. No. CF/BAY/03/R-2 DATED 01/04/08 BAY/FEEDER 4. No. CF/SA/04/ R-2 DATED 01/04/08 SURGE ARRESTOR 5. No. CF/CB/05/ R-2 DATED 01/04/08 CIRCUIT BREAKER 6. No. CF/ICT/06/ R-2 DATED 01/04/08 ICT 7. No. CF/SR/07/ R-2 DATED 01/04/08 SHUNT REACTOR 8. No. CF/ISO/08/ R-2 DATED 01/04/08 ISOLATOR/GROUND SWITCH 9. No. CF/WT/09/ R-2 DATED 01/04/08 WAVE TRAP

These formats have all the possible test recordings to be performed at site before energization. Switching and operational activities will be recorded in regular manner in the operator’s log. Copies of this log, notes on special observations from inspections and other measurements will constitute the test records. The test records had to be signed by the responsible personnel from the OEM, the supplier, the erection agency and the POWERGRID representative. The test formats/records are to be distributed to Regional O&M office and Concerned Sub-Station library.

Page 10: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

4of 55

2.0 TRANSFORMER AND REACTOR 2.1 Following points to be checked After Receipt of transformer / reactor at Site:

2.1.1 N2 pressure and Dew point to be checked after receipt of transformer at Site. It should be within permissible band (as per graph provided by manufacturer & given below in Fig-1)

2.1.2 The data of impact recorder shall be analyzed jointly in association with the manufacturer. In case the impact recorder indicates some serious shocks during shipment, further course of action for internal inspection, if necessary shall be taken jointly. Impact Recorder should be detached from the Transformer/ Reactor preferably when the main unit has been placed on its foundation.

2.1.3 Oil Samples shall be taken from oil drums/ tanker received at site and sent to our Lab (CIOTL / IOTL) for oil parameter testing. The copy of test certificate of routine testing at oil refinery should be available at site for comparison of test results.

2.1.4 Unpacking and Inspection of Accessories to be carried out taking all precautions so that the tools used for opening do not cause damage to the contents. Fragile instruments like oil level gauge, temperature indicators, etc. are to be inspected for breakage or other damages. Any damaged or missing components should be reported to equipment manufacturer, so that the same can be investigated or shortage made up as per the terms/ conditions of the contract.

2.1.5 Core Insulation Test shall be carried out to check insulation between Core (CC&CL) and Ground. (Not applicable for Air Core Reactors)

A1

A2

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.5

0.05

0.05

1.0

1.52.0

2.5

3.0

3.5 4.0 4.5 5

Lb / in 2

-30 -20 -10 0 10 20 30 40 50

Temperature in ˚ C

Gau

ge P

ress

ure

–K

g/ C

m2

Graph showing variation of Pressure v/s Temperature of gas for gas filled unit during Transport or storage

Example: For 40 ˚C Temperature (Depending upon the pressure of gas at the time of filling), - minimum pressure of gas can be 0.185 Kg/ Cm2 at point A1- maximum pressure of gas can be 0.32 Kg/ Cm2 at point A2

A1

A2

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.5

0.05

0.05

1.0

1.52.0

2.5

3.0

3.5 4.0 4.5 5

Lb / in 2

-30 -20 -10 0 10 20 30 40 50

Temperature in ˚ C

Gau

ge P

ress

ure

–K

g/ C

m2

Graph showing variation of Pressure v/s Temperature of gas for gas filled unit during Transport or storage

Example: For 40 ˚C Temperature (Depending upon the pressure of gas at the time of filling), - minimum pressure of gas can be 0.185 Kg/ Cm2 at point A1- maximum pressure of gas can be 0.32 Kg/ Cm2 at point A2

Figure-1 : Graph depicting variation of N2 gas pressure w.r.t temperature

Page 11: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

5of 55

2.1.6 After receiving the accessories at site same should be inspected and kept ready for

immediate erection:

• If erection work can not start immediately due to some reasons, then accessories should be repacked into their own crates properly and packing list should be retained.

• All packings should be kept above ground by suitable supports so as to allow free air flow underneath. The storage space area should be such that it is accessible for inspection, water does not collect on or around the area and handling/transport would be easy. Proper drainage arrangement in storage areas to be ensured so that in no situation, any component get submerged in water due to rain, flooding etc.. Immediately after the receipt of main unit and also the accessories, same should be inspected and if found satisfactory, the unit should be erected completely and filled with dry transformer oil as per the instruction.

• It is preferable to store the main unit on its own location/foundation. If the foundation is not likely to be ready for more than three (3) months, then suitable action plan has to be taken from the manufacturer regarding proper storage of the Main Unit.

• If the transformer/ Reactor is to be stored up to three (3) months after arrival at site, it can be stored with N2 filled condition. N2 pressure to be monitored on daily basis so that chances of exposure of active part to atmosphere are avoided. In case of drop in N2 pressure, dew point of N2 has to be measured to check the dryness of the Transformer/ Reactor.

• In case of storage of transformer in oil-filled condition, the oil filled in the unit should be tested for BDV and moisture contents once in every three months. The oil sample should be taken from bottom valve. If BDV is less and moisture contents are more than as given for service condition then oil should be filtered.

2.1.7 During erection, the exposure of active part of transformers should be minimized. Further either dry air generator should be running all the time or dry air cylinders may be used to minimize ingress of moisture. The transformer should be sealed off after working hours. It is practical to apply a slight overpressure overnight with dry air or N2 inside – less than 300 mbar (30 kPa or 0.3 atmospheres). Next day the pressure is checked and suspected leaks may be detected with leak detection instruments , with soap water or with plastic bags tightened around valves (being inflated by leaking air)

For oil filled units whenever oil is drained out below the inspection covers, job will be treated as exposed. Other exposure activities are as below:

1) Bushing erections 2) Jumper connections of Bushings 4) Fixing bushing turrets on cover 5) Fixing bushing turrets on side 6) Core insulation checking 7) Buchholz relay pipe work fixing on cover. 8) Gas release pipes/equaliser pipe fixing. 9) Entering inside the tank for connections/inspection etc.

For oil filled units depending upon the level up to which the oil is drained decides the exposure time. All such exposure time should be recorded in a log sheet to decide the oil

Page 12: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

6of 55

processing (drying) and oil filling of transformer. For transformers with a gas pressure of 2.5- 3 PSI, the acceptable limits of dew point shall be as under: (Source: Courtesy BHEL, Bhopal)

Temperature of Insulation

in °F

Maximum Permissible dew

point in °F

Temperature of Insulation in °C

Maximum Permissible dew

point in °C 0 -78 -17.77 -61.11 5 -74 -15.0 -58.88 10 -70 -12.22 -56.66 15 -66 -9.44 -54.44 20 -62 -6.66 -52.22 25 -58 -3.33 -49.99 30 -53 -1.11 -47.22 35 -48 +1.66 -44.44 40 -44 +4.44 -42.22 45 -40 +7.44 -39.39 50 -35 +9.99 -37.22 55 -31 12.77 -34.99 60 -27 15.55 -32.77 65 -22 18.33 -29.99 70 -18 23.11 -27.77 75 -14 23.88 -25.55 80 -10 26.66 -23.33 85 -6 29.44 -21.11 90 -1 32.22 -18.33 95 +3 34.99 -16.11 100 +7 37.75 -13.88 110 +16 43.33 -8.88 120 +25 48.88 -3.88 130 +33 54.44 +0.55 140 +44 59.99 +5.55

TABLE 1- Variation of Dew Point of N2 Gas Filled in Transformer Tank w.r.t Temperature

2.2 Insulating Oil

When oil is dispatched to site separately it is usually in sealed steel drums. The oil to be used to filling and topping up must comply with oil specification given in POWERGRID Technical Specification for acceptance criteria. Before oil is accepted, samples have to be taken and checked with respect to dielectric strength and dielectric losses. The latter is important, since dirty transportation vessels can significantly contaminate the oil. High dielectric losses cannot be removed by filter treatment, such lots have to be rejected. If the oil is supplied in railroad or trailer tanks, one or two samples are sufficient. If the oil is delivered in 200 litres drums, the following scheme for checking is recommended.

Page 13: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

7of 55

Number of drums delivered No. of drums to be checked

2 to 5 2 6 to 20 3 21 to 50 4 51 to 100 7 101 to 200 10 201 to 400 15

However, before filling oil, each drum has to be physically checked for free moisture and appearance. In case any doubt arises, number of drums to be checked needs to be increased. A register needs to be maintained indicating the number of drums supplied in each lot as per LOA and number of drums of each lot used in filling a particular Transformer/ Reactor. The oil test results carried out as above should also be recorded.

2.2.1 Samples from Oil Drum Check the seals on the drums. The drum should first be allowed to stand with bung (lid) vertically upwards for at least 24 hours. The area around the bung should be cleaned & clean glass or brass tube long enough to reach to within 10mm of the lower most part of the drum should be inserted, keeping the uppermost end of the tube sealed with the thumb while doing so. Remove the Thumb thereby allowing oil to enter the bottom of the tube. Reseal the tube and withdraw an oil sample. The first two samples should be discarded. Thereafter, the sample should be released into a suitable receptacle.

2.2.2 Parameters of Transformer Oil The oil as received at site for filling and topping up in the transformer must comply with oil specification given in POWERGRID Technical Specification for acceptance criteria. The oil sample from the transformer tank, after filling in tank before commissioning should meet the following specifications as per IS: 1866 – 2000 (latest Revision) given in table-2 below:

Table-2 Highest Voltage of Equipment Sr.

No. Property <72.5 kV 72.5 – 170 kV >170 kV

1. Breakdown Voltage (BDV) (kV rms)-Min 40 50 60 2. Moisture content –(ppm) Max 20 15 10 3. Dielectric Dissipation Factor (Tan δ) at 90 ºC and

40-60Hz -Max 0.015 0.015 0.01

4. Resistivity at 90 ºC-Min ( x 1012 ohm-cm) 6 6 6 5. Interfacial Tension (mN/m) -Min 35 35 35 6. Viscosity at 27ºC-Max – cSt 27 27 27 7 Density at 29.5ºC gm/cm3 - Max 0.89 0.89 0.89 8. Flash point ºC – Min 140 140 140 9. Pour point ºC – Max -6 -6 -6

10. Neutralization Value mg KOH/gm of oil –Max 0.03 0.03 0.03 11. a. b.

Oxidation Stability of Uninhibited Oil Neutralization Value mg KOH/gm of oil –Max Sludge percent by mass – Max

0.4 0.1

0.4 0.1

0.4 0.1

12. Oxidation Stability for Inhibited Oil Similar values as before filling

Page 14: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

8of 55

2.3 Oil Filling (For detailed Oil filling procedure, please refer to Appendix-2 of Doc. No. D-2-03-XX-01-01: Maintenance Procedures for Switchyard Equipments-Part 1: EHV Transformers & Reactors)

Introduction: For transformer dispatched with gas filled from the works, the filling of oil inside the tank is done under vacuum. Transformer of high voltage ratings and their tanks are designed to withstand full vacuum. Manufacturer’s instructions should be followed regarding the creating of full vacuum during filling the oil in the tank.

Final tightness test with vacuum (i.e. leakage test or Vacuum Drop Test): Before the oil filling is started, a final check is made of the tightness of the transformer tank by applying vacuum. When any vacuum is applied to a transformer, empty of oil, a leakage test must be carried out to ensure that there are no leaks on the tank which would result in wet air being drawn into the transformer. The procedure is as follows:

• Connect the vacuum gauge to a suitable valve of the tank.(Vacuum application and measurement should perform only on top of the main tank)

• Connect the vacuum pump to another opening. • Evacuate the transformer/ reactor tank until the pressure is below 3 mbar ( 0.3 kPa or

about 2 mm of Hg) • Shut the vacuum valve and stop the pump. • Wait for an hour and take a first vacuum reading – say P1 • Take a second reading 30 minutes later- say P2 • Note the quantity of oil required, according to the rating plate, and express as a

volume, V, in m3 . • The maximum permitted leakage is 20 bar x litres/ second

Take the difference between P2 and P1, and multiply this with the oil quantity V. If the pressures are expressed in kPa, and the oil quantity in m3, then the product shall be less than 3.6. (P2 – P1) x V < 3.6 The transformer is then considered to be holding sufficient vacuum and is tight. Continued readings (at least 2 to 3) at successive 30 min intervals may be taken to confirm the result.

• If the leak test is successful, the pumping will be continued, until the pressure has come down to 0.13 kPa (1 Torr) or less. The vacuum shall then be held for the time given in Table-4 before the oil filling starts.

• If the specified vacuum cannot be reached, or if it does not hold, the leak in the transformer system shall be located and corrected.

Page 15: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

9of 55

This vacuum must be maintained for the time specified as per the voltage class in table-4 before and should also maintain during the subsequent oil filling operations by continuous running of the vacuum pumps. When filling a transformer with oil it is preferable that the oil be pumped into the bottom of the tank through a filter press or other reliable oil drying and cleaning device should be interposed between the pump and the tank. In case the transformer is provided with an On Load Tap Changer (OLTC), while evacuating the main transformer tank, the diverter switch compartment may also be evacuated simultaneously so that no undue pressure is allowed on the tap changer chamber. While releasing vacuum, the tap changer chamber vacuum should also be released simultaneously. For this one pressure equalizer pipe should be connected between main tank and tap changer. Manufacturer’s instruction manual should be referred to protect the air cell/diaphragm in the conservator during evacuation. The oil must pass from the oil tanker, or settling tanks, through an oil conditioning plant to the top oil filter valve (please refer Fig-2) and the oil must conform to the quality requirements as given in POWERGRID- Transformer Oil Specification. The oil flow at the entry valve must be controlled to maintain a positive pressure above atmospheric and to limit the flow rate if necessary to 5000 litres / hour, or a rise in oil level in the tank not exceeding one metre / hour (as measured on the oil level indicator) Continue oil filling until the level reaches approximately 200 mm above the ambient oil level indicated on the magnetic oil level gauge in the expansion vessel. Then, release the vacuum, with dry air of dew point -40deg C or better. The diverter tank can now be topped up at atmospheric pressure. Reconnect oil outlet hose to valve on flange on tap changer diverter head. Reinstate breather and very slowly top up the diverter switch such that the correct level is reached in the diverter expansion vessel. In the event the expansion vessel is overfull drain oil from flange into a suitable container until the correct level is reached. When the vacuum filling of the transformer and diverter tank is complete, the cooling system/ Radiator bank can be filled (WITHOUT VACUUM) at atmospheric pressure, via an oil processing plant. Oil must be admitted, very slowly, through the bottom cooler filter valve, with the cooler vented at the top and the top cooler filter valve unblanked and open to atmosphere. As the oil level reaches the vents and open valve, close off and shut down the processing plant. Note: Care must be taken not to pressurise the coolers/ radiators. Upon completion, open the top cooler isolating valve in order to equalise the pressure in the cooler with the transformer tank. This will also allow contraction or expansion of the oil as the ambient temperature changes.

Page 16: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

10of 55

Figure-2 : Arrangement for Evacuation and Oil filling upto tank Oil gauge & Conservator Before oil filling into conservator inflate the air cell to 0.5 PSIG i.e. 0.035kg/cm2 max. slightly by applying pressure (N2/Compressed dry air) so that it can take shape. Release pressure. Fit breather pips but do not fit breather in position, instead put wire mesh guard over and flange of the pipe. This will ensure free air movement from the air cell to the atmosphere. Use flow meter / indicator on outlet of filter machine and regulate the flow using the valve to limit oil filling rate to 2000 litres per hour max. in case filter capacity is more. Push oil slowly into conservator through the transformer via valve No. 5 (valve 2,3 & 4 to remain open) till the oil comes out first through valve Nos.2 & 3 (close these valves) and then through valve No. 4. Allow some oil to come out through valve No.4. Oil should come out freely into the atmosphere. This will ensure that air inside the conservator is expelled out and the space surrounding the air cell is full of oil. (Close valve No. 4). During all these operations valve No.1 to remain closed. Drain oil from the conservator by gravity only through valve No. 1 or through drain valve of the transformer via valve No. 5. Do not use filter machine for draining oil from the conservator. Also do not remove buchholz relay and its associated pipe work, fitted between the conservator and the transformer tank while draining oil. Stop draining oil till indicator of magnetic oil level gauge reaches position-2 on the dial, which is corresponding to 30°C reading on the oil temperature indicator.

TRANSFORMER TANK

FILTERMACHINEOIL

STORAGE TANK

VACUUM PUMP

SUMP

D.O.F. Filter Valve If not, then BTM Filter Valve

B A C

B.R.

Top FilterValve

Compound Pressure & Vacuum gauge Filter on any 1” Sampling or 2” Filter Valve

Valve near B. RELAYtowards Conservator

Tank Oil Gauge/ Transparent hose forLevel monitoring

Page 17: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

11of 55

Figure-3 : General Arrangement For Oil Conservator

After Oil filling, Hot Oil Circulation has to be applied to all the Transformers/ Reactors expect under the circumstances when active part of Transformer/ Reactor gets wet. Following conditions can be considered to define the Transformer/ Reactor wet:

1. If Transformer/ Reactor received at site without positive N2 pressure. 2. If Dry air not used during exposure while doing erection activities 3. Overexposure of active part of Transformer/ Reactor during erection

(Overexposure when exposure > 12 Hrs) Under above mentioned conditions, Manufacturer shall take necessary action for effective dry out of the Transformer/ Reactor. However general guidelines for dry out in such cases is given in section 1.4.2 2.4 HOT OIL CIRCULATION USING HIGH VACUUM OIL FILTER MACHINE To ensure total impregnation and absorption of possible trapped gas bubbles, the oil in the tank is to be circulated through the vacuum filter and with circulation direction as shown in Fig.-4. The circulation procedure for the main tank is as follows: 2.4.1 The Transformer/ Reactor is connected to the filter in a loop through the upper and

lower filter valves. The direction of circulation shall be from the filter to the transformer at the top and from the bottom of the transformer to the filter.

2.4.2 The temperature of the oil from the filter to the Transformer should be around 60 ˚ C and in no case it should go beyond 70 ˚ C otherwise this may cause oxidation of oil.

Page 18: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

12of 55

2.4.3 The circulation shall proceed until a volume of oil has passed through the loop corresponding to 2 times the total oil volume in the tank. (At freezing ambient temperature the circulation time is increased: circulate 3 times the volume at temperature down to minus 20 ˚ C, increase to 4 times below that temperature).

The oil will be circulated through a vacuum filtration machine till the parameters are attained as per IS 1866 - 2000, Table-3 below:

KV CLASS B.D.V ( Min )*

(KV)

Moisture ( Max ) *

(ppm)

Tan Delta ( MAX ) * (90 Deg C)

Resistivity ( Min ) *

(Ohm-Cm)

IFT at 27 Deg. ( Min )*

N/m

> 170 KV 60 10 0.01 6 x 10 12 0.035

< 170 KV But > 72.5 KV 50 15 0.015 6 x 10 12 0.035

< 72.5 kV 40 20 0.015 6 x 10 12 0.035

Table-3

* The limiting values given in the above table-3 to be revised as per revision in IS 1866 in future

Figure-4: Arrangement for Hot Oil Circulation and Filteration

TRANSFORMER TANK

Top Filter Valve

Bottom Filter Valve

Filter Machine Outlet

Vacuum Filter

Filter Machine Inlet

Page 19: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

13of 55

2.5 PROCEDURE FOR DRY OUT OF WET WINDING OF TRANSFORMER/ REACTOR BY VACUUM PULLING, N2 FILLING AND HEATING The drying of a new Transformer/ Reactor required when the moisture get absorbed by the solid insulation used in Transformers/ Reactors due to various reasons. The process of drying out a transformer is one requiring care and good judgment. If the drying out process is carelessly or improperly performed, a great damage may result to the transformer insulation through over heating, etc. In no case shall a transformer be left unattended during any part of the dry out period. The transformer should be carefully watched through out the dry-out process and also observations shall be carefully recorded. When the transformer is dried out it is necessary to ensure that fire fighting equipment is available near the transformer.

2.5.1 Isolation Required: All the openings of transformer main tank like openings for coolers/radiators, conservator, OLTC etc. is to be properly isolated and totally blanked.

2.5.2 Procedure:

a. Fill the main transformer/ reactor tank with Nitrogen (Use only Dry N2 gas as per IS: 1747 with 50 ppm moisture and 1% oxygen by volume) until it comes to a positive pressure of 0.15 Kg/cm2. It is kept at least 48 hrs. At the end of 48 hrs, dew point of N2 at outlet is measured. If the dew point is not within acceptable limits as per Table-I, dry out method should be continued.

b. Heating from outside: While N2 circulation is in progress, the heaters are to be installed around the transformer tank as shown in the Annexure. The heaters are to be kept ON until we achieve a temperature of about 75–80 deg C of the core & winding of transformer.

c. Vacuum Pulling: After ascertaining that there is no leakage, pull out vacuum and keep the transformer/reactor under near absolute vacuum (1-5 torr) for about 96 hours running the vacuum pump continuously. The duration of vacuum can vary between 48 to 96 hrs depending upon the dew point being achieved. Keep Vacuum machine ON and collect condensate for measurement. Observe the rate of condensate collection on hourly basis. Depending on the value of rate of condensate, continuation of further vacuum shall be decided.

d. Nitrogen Circulation: Then the vacuum is broken with dry nitrogen. The dew point of nitrogen at the inlet is to be measured and should be of the order of - 50 °C or better. When the nitrogen comes to the positive pressure of 0.15 kg/cm2, it is stopped and kept for 24 hours. Heating from outside is to be continued while N2 circulation is in progress. Then the nitrogen pressure is released and the outlet nitrogen dew point is measured. If the dew point is within acceptable limits as per Table-I then the dryness of transformer is achieved. If not again the transformer is taken for vacuum treatment and then nitrogen is admitted as mentioned above and tested. The cycle to be continued till desired dew point as per Table-I is achieved.

e. Periodicity: Periodicity of vacuum cycle may vary between 48-96 hrs. Initially two N2 cycles may be kept for 24 hrs. After that it may be kept for 48 hrs depending upon dew point being achieved.

Page 20: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

14of 55

After completion of drying process, oil filling and hot oil circulation to be carried out before commissioning. Please ensure standing time as per table-4 given below before charging.

Transformer HV

Rated Voltage (in kV)

Application of Vacuum & holding for (before oil filling )

(in Hours)

STANDING TIME After Oil circulation and before energising

(in Hours) Up to 145kV 12 HRS 12 HRS

145 kV and up to 420kV

24 HRS 48 HRS

Above 420 kV 36 HRS 120 HRS

Table-4 After the expiry of this time, air release operation to be carried out in Buchholz relays and other release points given by the manufacturers before charging. For subsequent activities, proceed to format no. CF/ICT/06/ R-2 DATED 31/12/07 for ICT & format No. CF/SR/07/ R-2 DATED 31/12/07 for Reactor.

Page 21: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

15of 55

2.6 RELATION BETWEEN DIFFERENT UNITS (CONVERSION OF UNITS):

Pressure: 1 bar = 105 Pa = 750 Torr = 14.5 psi = 1.02kg/cm2 1 Torr = 1.33 mbar = 0.133 kPa 1 kPa(kilo-Pascal) = 103 Pa = 10 mbar = 7.501 Torr(mm of mercury) 1 MPa = 106 Pa 1 atmosphere=0.1 MPa=1.02kg/cm2= 14.5 psi Force: 1 kp = 9.807 N Weight: 1 ton=1000 kg=2200 lbs Temperature: ° C = 5

9* (° F - 32)

° F = 95

* (° C )+ 32

Volume: 1m3= 1000 litres=260 US gallons=220 Imp gallons 1 litre =0.26 US Gallons 1 US Gallons = 3.78 litres 1 litre =0.22 Imp Gallons 1 Imp Gallons

Benchmarks: 1-mm mercury (Torr) is about 1 millibar or 0.1 kPa 1 m3 of oil weights 0.9 tons –say 1 ton 1000 US gallons of oil weights 3.5 tons

Page 22: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

16of 55

2.7 CHECK LIST FOR ENERGISATION OF TRANSFORMER/ REACTOR 2.7.1 PRELIMINARY CHECKS 1. Release air at the high points, like oil communicating bushings, buchholz petcock, tank

cover and the cooling devices including headers, radiators, pumps, expansion joints etc. of the transformer. Air release should be resorted from low points to high points.

2. Check the whole assembly for tightness and rectify where necessary. 3. Check the general appearance and retouch the paint work if need be. 4. Check that the valves are in the correct position :

• Tank : valves closed and blanked • Cooling circuit : valves open • Conservator connection : valves open • By-pass: valves open or closed as the case may be. • On-load tap changer : valves open

5. Check that the silica gel in the breather is blue and that there is oil in the breather cup ( oil

seal ) 6. Check that CC-CL-G are shorted 7. Check the oil level in the main conservator and the conservator of on-load tap changer,

bushing caps, flanges, turrets, expansion bellows as per manufacturer’s recommendation. Level should correspond to 35º C mark on oil level gauges for BHEL transformers

8. Check the bushings :

• Oil level ( bushings fitted with sight-glasses) • Adjustment of spark-gaps /arcing horn –gaps, if provided • Conformity of connection to the lines ( no tensile stress on the terminal heads) • Bushing CT secondary terminals must be shorted and earthed, if not in use. • Neutral bushing effectively earthed

9. Check the on-load tap changer : • Conformity of the positions between the tap changer control cubicle and the tap changer

head • Adjustment of the tap-changer control cubicle coupling • Electric and mechanical limit switches and protective relays • Step by step operation- local and remote electrical operation as well as manual operation

and parallel operation, if any • Signalling of positions

10. Check the quality of the oil: • Draw off a sample from the bottom of the tank • Carry out DGA and oil parameters test ( i.e. BDV, Moisture content, resistivity & tan δ

at 90°C and IFT ) before energisation

Page 23: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

17of 55

11. Check the oil of OLTC chamber, if not good, drain and fill with filtered oil upto desired level.

12 Check that equalising link between OLTC tank and Main tank is removed

13 Extraneous materials like tools, earthing rods, pieces of clothes, waste etc. should be

removed before energisation 2.7.2 CHECKING OF AUXILIARY AND PROTECTIVE CIRCUITS 1. Check temperature indicator readings and their calibrations 2. Check the setting and working of the mercury switches of winding and oil temperature

indicators and presence of oil in the thermometer pockets • Follow the same procedure for the thermal replicas

3. Check the direction of installation of buchholtz relay. 4. Check the operation of the buchholz relay and the surge protective relay of the tap-changer :

• Alarm and tripping • Protections and signals interlocked with these relays

5. Check the insulation of the auxiliary circuits in relation to the ground by 2 kV megger for 1 min.

6. Check the earthing of the tank and auxiliaries like cooler banks at two places. 7. Measure the supply voltages of the auxiliary circuits 8. Check the cooling system :

• Check the direction of installation of oil pumps • Check the direction of rotation of the pumps and fans • Check the working of the oil flow indicators • Check the setting of the thermal overload relays • Go through the starting up sequences, control and adjust, if necessary, the relay time

delays 9. Check that there is efficient protection on the electric circuit supplying the accessories and

tightness of all electrical connections 10. Check the heating and lighting in the cubicles 11. Check the differential protection, over-current protection, restricted earth fault protection,

over-fluxing protection etc. are in service and settings are as per CC/Engg recommendations. After the inspection / tests are completed, the transformer may be energised from the incoming side on NO LOAD. The initial magnetising current at the time of switching will be very high, depending upon the particular moment in the cycle. The transformer should always be soaked for few hours under constant care i.e. keep it energised for twelve hours. Excessive vibrations of radiator parts etc. should be located and corrected. The transformer hum should be observed for any abnormality. After that it may be checked for gas collection. Should the gas prove to be inflammable, try to detect the cause which may probably be an internal fault? If the breaker trips on differential /REF, buchholz or any other protective device, the cause must be investigated thoroughly before re-energizing the transformer/ reactor. After successful charging, performance of transformer / rector should be checked under loading; OTI/WTI readings should be monitored for 24 hours and ensured that they are as per loading. DGA samples may be sent as per Standard practice (after 24 hrs of energisation, one week, 15 days, one month and three months after charging, thereafter as per normal frequency of 6 months). Loading data may be forwarded to CC/OS and manufacturer (if requested by them).

Page 24: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

18of 55

3.0 PRE-COMMISSIONING CHECKS /TESTS FOR TRANSFORMERS & REACTORS

Once oil filling is completed, various pre-commissioning checks/ tests are performed to ensure the healthiness of the Transformer/ Reactor prior to its energisation. Various electrical tests to be performed and their significance are given below.

Sr. No.

Name of Test / Check point

Purpose of test/ check

3.1 Core insulation tests To check the insulation between Core (CC&CL) and Ground

3.2 Operational Checks on protection System

Operational Checks on cooler bank (pumps & Fans), Breathers (silica gel or drycol), MOG, temperature gauges (WTI/OTI), gas actuated relays (Buchholz, PRD, SPR etc.) and simulation test of protection system

3.3 Insulation Resistance (IR) measurement

Test reveals the condition of insulation (i.e. degree of dryness of paper insulation), presence of any foreign contaminants in oil and also any gross defect inside the transformer (e.g. Failure to remove the temporary transportation bracket on the live portion of tap-changer part)

3.4 Capacitance and Tan δ measurement of bushings

Measurement of C1 & C2 Capacitance and Tanδ in UST mode. Changes in the normal capacitance of an insulator indicate abnormal conditions such as the presence of moisture layer, short -circuits or open circuits in the capacitance network.

3.5 Capacitance and Tan δ measurement of windings

Dissipation factor/Loss factor and capacitance measurement of winding is carried out to ascertain the general condition of the ground and inter-winding insulation

3.6 Turns ratio (Voltage ratio) measurement

To determine the turns ratio of transformers to identify any abnormality in tap changers/ shorted or open turns etc

3.7 Vector Group & Polarity

To determine the phase relationship and polarity of transformers

3.8 Winding resistance measurement

To check for any abnormalities due to loose connections, broken strands and high contact resistance in tap changers

3.9 Magnetic Balance test

This test is conducted only in three phase transformers to check the imbalance in the magnetic circuit

3.10 Floating Neutral point measurement

This test is conducted to ascertain possibility of short circuit in a winding.

3.11 Measurement of Short Circuit Impedance

This test is used to detect winding movement that usually occurs due to heavy fault current or mechanical damage during transportation or installation since dispatch from the factory.

3.12 Exciting/Magnetising current measurement

To locate defect in magnetic core structure, shifting of windings, failures in turn to turn insulation or problems in tap changers. These conditions change the effective reluctance of the magnetic circuit thus affecting the current required to establish flux in the

Page 25: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

19of 55

core

3.13 Vibration measurement of Oil-immersed Reactor

To measure the vibrations of core /coil assembly in the tank of the reactor. Movement of the core-coil assembly and shielding structure caused by the time–varying magnetic forces results in vibration of the tank and ancilliary equipment. These vibrations have detrimental effects such as excessive stress on the core-coil assembly

3.14 Operational checks on OLTCs

To ensure smooth & trouble free operation of OLTC during operation.

3.15 Stability of Differential, REF of Transformer/ Reactor

This test is performed to check the proper operation of Differential & REF protection of Transformer & Reactor by simulating actual conditions. Any problem in CT connection, wrong cabling, relay setting can be detected by this test.

3.16 Tests/ Checks on Bushing Current Transformers (BCTs)

To ascertain the healthiness of bushing current transformer at the time of erection

3.17 Frequency Response Analysis (FRA) measurement

To assess the mechanical integrity of the transformer. Transformers while experiencing severity of short circuit current looses its mechanical property by way of deformation of the winding or core. During pre-commissioning this test is required to ascertain that Transformer active part has not suffered any severe impact/ jerk during transportation.

3.18 Dissolved Gas Analysis (DGA) of oil sample

Oil sample for DGA to be drawn from transformer main tank before commissioning for having a base data and after 24 hrs. of charging subsequently to ensure no fault gas developed after first charging. DGA analysis helps the user to identify the reason for gas formation & materials involved and indicate urgency of corrective action to be taken

3.19 Thermovision Infra-red scanning (IR thermography)

A thermo vision Camera determines the temperature distribution on the surface of the tank as well as in the vicinity of the Jumper connection to the bushing. The information obtained is useful in predicting the temperature profile within the inner surface of tank and is likely to provide approximate details of heating mechanism. Thermovision scanning of transformer to be done at least after 24 hrs. of loading and repeated after one week.

Page 26: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

20of 55

3.1 CORE INSULATION TEST

This test is recommended before the unit is placed in service after receipt at site or following modifications to the transformer that could affect the integrity of its core insulation and at other times, when indicated by DGA (key gases being ethane and/or ethylene and possibly methane) or usually during a major inspection. For core-insulation to ground test, remove the cover of the terminal block, Disconnect the closing link that connects the two terminals CL-G. Apply 2.0 kV direct voltage between CL and CC + G (core grounding strap). The tank shall be grounded during the test. The insulation value after 1min. test-time should be minimum 10 MΩ for new transformer at the time of commissioning. Core insulation resistance is generally more than 100 MΩ for new assembled transformer when tested at factory.

3.2 OPERATIONAL CHECKS ON PROTECTION SYSTEM

• Operational Checks on Breathers (Conventional Silcagel or Drycol as supplied with the transformers)

• Visual check of MOG of Main Conservator • Marshalling Box & Kiosk Checks • Valve Operational Checks • Checks on Cooling System

Checks on cooling fans-rotation, speed & Control (Manual /temp /load) setting checks

Checks on Cooling pumps- rotation, vibration/noise, oil flow direction • Checks on temperature Gauges (OTI/WTI-Calibration and Cooler Control , alarm & trip

setting tests • Checks on gas actuated (SPRs/ PRDs/ Buchholz) relays –Operational checks by

simulation as well as shorting the respective contacts as applicable • Checks on tightness of Terminal connectors - micro-ohm measurement of each

connection • Checks on Transformer/ Reactor protection (differential, REF, Over-current & stability

tests etc.)

3.3 INSULATION RESISTANCE (IR) MEASUREMENT

IR measurements shall be taken between the windings collectively (i.e. with all the windings being connected together) and the earthed tank (earth) and between each winding and the tank, the rest of the windings being earthed. Before taking measurements the neutral should be disconnected from earth. Following table gives combinations of IR measurements for auto-transformer, three -winding transformer & Shunt Reactor.

For Auto-transformer For 3 winding transformer

For Shunt Reactor

HV + IV to LV HV + IV to LV HV to E HV + IV to E HV + LV to IV

LV to E HV + IV +LV to E Where HV-High voltage, IV-Intermediate voltage, LV-Low voltage/Tertiary voltage windings, E- Earth

Page 27: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

21of 55

Unless otherwise recommended by the manufacturer the following IR values as a thumb rule may be considered as the minimum satisfactory values at 30°C (one minute measurements) at the time of commissioning.

Rated Voltage class of

winding Minimum desired IR value at 1 minute

(Meg ohm) 11kV 300 MΩ 33kV 400 MΩ

66kV & above 500 MΩ Insulation resistance varies inversely with temperature and is generally corrected to a standard temperature (usually 20 °C) using table (Source: BHEL instruction Manual) as given below.

Difference in temperatures ( °C)

Correction Factor (k)

10 1.65 20 2.6 30 4.2 40 6.6 50 10.5

The ratio of 60 second insulation resistance to 15 second insulation resistance value is called dielectric absorption coefficient or Index (DAI). For oil filled transformers with class A insulation, in reasonably dried condition the absorption coefficient at 30°C will be more than 1.3. Polarization Index Test is ratiometric test, insensitive to temperature variation and may be used to predict insulation system performance. The polarization index test is performed generally by taking mega ohm readings at the following intervals at a constant dc voltage: 1 min and then every minute up to 10 min. The polarization index is the ratio of the 10 min to the 1 min mega ohm readings.

PI= R10 / R1 (dimensionless), Where PI is Polarisation Index and R is resistance

The following are guidelines for evaluating transformer insulation using polarization index values:

Polarization Index Insulation Condition Less than 1 Dangerous 1.0-1.1 Poor 1.1-1.25 Questionable 1.25-2.0 Fair 2.0 – 4.0 Good Above 4.0 Excellent

A PI of more than 1.25 and DAI of more than 1.3 are generally considered satisfactory for a transformer when the results of other low voltage tests are found in order. PI less than 1 calls for immediate corrective action. For bushings, an IR value of above 10,000 MΩ is considered satisfactory.

Page 28: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

22of 55

3.4 CAPACITANCE AND TAN δ MEASUREMENT OF BUSHINGS

C& Tan δ measurement of bushings shall be done at 10kV with fully automatic test kit so as to have reliable test result.

• For 3-Ph auto-transformer, short together all 400kV, 220kV and Neutral (isolated from

earth) Bushings. Also short all 33kV Bushings and earth the same. Measurement of C1 Capacitance and Tanδ: Connect the crocodile clip of the HV cable to the top terminal of the shorted HV/IV bushings. Unscrew the test tap cover, Insert a pin in the hole of the central test tap stud by pressing the surrounding contact plug in case of 245 kV OIP Bushing and remove the earthing strip from the flange by unscrewing the screw (holding earth strip to the flange body) in case of 420 kV OIP Bushing. Connect the LV cable to the test tap (strip/central stud) of the bushing under test to the C & TAN δ KIT through a screened cable and earth the flange body. Repeat the test for all Bushings by changing only LV lead connection of the kit to test tap of the Bushing which is to be tested Measurement of C2 Capacitance and Tanδ : HV lead to be connected to the test tap of the bushing under test (if required additional crocodile type clip may be used) and LV of the kit to be connected to the ground. HV of the bushing is to be connected to the Guard terminal of the test kit. Test to be carried out in GSTg mode at 1.0kV.

• For measurement of 33kV Bushing Tan Delta, earth HV/IV Bushings (already shorted). Apply HV lead of the Test kit to shorted 33kV Bushings and connect LV lead of the test kit to Test tap of the Bushing under test.

• Measurements shall be made at similar conditions as that of a previous measurement.

The oil-paper insulation combination of bushings exhibit fairly constant tan delta over a wide range of operating temperature. Hence, effort is to be made for testing at temperature near to previous test and Correction factor need not be applied.

• Do not test a bushing (new or spare) while it is in its wood shipping crate, or while it is

lying on wood. Wood is not as good an insulator as porcelain and will cause the readings to be inaccurate. Keep the test results as a baseline record to compare with future tests.

• It is to be ensured that C& Tan δ measurement of bushings and testing of turrets carried out before installation. This will prevent installation of bushings having C& Tan δ values beyond permissible limits.

• It is to be ensured that Test Tap points are earthed immediately after carrying out the measurements for that particular Bushing and earthing of test tap to be ensured by carrying out continuity test.

Page 29: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

23of 55

3.5 CAPACITANCE AND TAN δ MEASUREMENT OF WINDINGS

The combination for C & tanδ measurement of winding is same as that of measurement of IR value. The summery of probable combination is given below:

Auto-

Transformer (Two winding)

Test Mode

Shunt Reactor

Test Mode

3 winding Transformer

Test Mode

V HV + IV to LV UST V HV to E GST HV to LV1 UST V HV + IV to E GSTg HV to LV2 UST

LV to E GSTg LV1 to LV2 UST HV to Ground GSTg LV1 to Ground GSTg LV2 to Ground GSTg

Table 5: Combination for C & tanδ measurement of winding for various transformers/ Shunt Reactor

• Ensure that test specimen is isolated from other equipments. Removal of Jumpers from Bushings is Pre-Requisite for C & Tan δ Measurement of Windings.

• For ICTs (Auto-Transformers): Shorting of all three phase Bushings (400kV&220kV) and neutral to be done. In case of single phase, 400kV, 220kV and neutral Bushings to be shorted Capacitance and Tan δ measurement of windings should be done in following combinations:

Test No.

Winding Combination

Test mode

Cap Symbol

Test lead Connection Remarks

1. HV-IV/LV UST CHL HV lead of test kit to HV/IV bushings of transformer LV lead of test kit to LV bushing of transformer

2. HV-IV/ LV+G GST CHL +C HG -do- 3. HV-IV / LV

with Guard GSTg C HG - do- LV to be

Guarded 4 HV-IV/LV UST CHL LV lead of test kit to

HV/IV bushings of transformer HV lead of test kit to LV bushing of transformer

5 LV/ HV-IV +G

GST CHL +C LG -do-

6. LV/ HV-IV with Guard

GSTg C LG -do- HV to be Guarded

Table 6:.Winding combination for C & tan δ measurement for auto transformer

• Measurement inter-check can be done by calculating C1= C2-C3 & C4= C5- C6 & DF1=C2DF2-C3DF3 / C2-C3= C4DF4-C5DF5 / C4-C5 Where C stands for capacitance

and DF for dissipation factor or tan δ and attached suffix (1…6) denotes the sr. no. of test in above table.

Page 30: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

24of 55

(a)

1.1

1.2 2.2

2.1

• For Reactors: All 400kV and neutral Bushings to be shorted. HV of the test kit to be connected to shorted Bushings and LV of the test kit to be connected to Earth connection. Measure the Capacitance and tan Delta in GST mode. Neutral connection with earth/ NGR to be isolated before the test.

3.6 TURNS RATIO (VOLTAGE RATIO) MEASUREMENT

Ratio measurements must be made on all taps to confirm the proper alignment and operation of the tap changers. The test should preferably be performed by automatic Transformer turns ratio (TTR) meter. Open turns in the excited winding will be indicated by very low exciting current and no output voltage. Open turns in the output winding will be indicated by normal levels of exciting current, but no or very low levels of unstable output voltage. The turns ratio test also detects high-resistance connections in the lead circuitry or high contact resistance in tap changers by higher excitation current and a difficulty in balancing the bridge. Results of the transformation turns or voltage ratio are absolute, and may be compared with the specified values measured during factory testing. The turns ratio tolerance should be within 0.5 % of the nameplate specifications. For three phase Y connected winding this tolerance applies to phase to neutral voltage. If the phase-to-neutral voltage is not explicitly indicated in the nameplate, then the rated phase-to-neutral voltage should be calculated by dividing the phase-to-phase voltage by √3.

3.7 VECTOR GROUP & POLARITY

Polarity and phase-relation tests are of interest primarily because of their bearing on paralleling or banking two or more transformers. Phase-relation tests are made to determine angular displacement and relative phase sequence. Phase-relation or vector group verification test is performed on a three phase transformer or on a bank of three single-phase transformers. The details of Additive and Subtractive polarity are given in IS: 2026-Part 1 and IEC 60076-1. For a single-phase transformer having a ratio of transformation of 30 to 1 or less, the polarity test shall be done as following. The line terminal of high voltage winding (1.1) shall be connected to the adjacent line terminal low-voltage winding (2.1) as shown in figure below

Page 31: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

25of 55

Any convenient value of alternating voltage shall be applied to the full high-voltage winding and readings shall be taken of the applied voltage and the voltage between the right-hand adjacent high-voltage and low-voltage leads. When the later reading is greater than the former, the polarity is additive. When the later reading is less than the former (indicating the approximate difference in voltage between that of the high-voltage and low-voltage windings), the polarity is subtractive. The test shall be conducted with 3 phase, 415V supply. By the measured voltage data, it should be verified that the desired conditions of vector group and polarity are fulfilled

Example for Y D11

1R13R1

3B13Y1

2R1

2B1 2Y1

1B1 1Y1

1R13R1

3B13Y1

2R1

2B1 2Y1

1B1 1Y1

Fig 5: For HV-Star / LV-Delta Transformer

Please Note: Most of the auto transformers in POWERGRID are of YD11configuration. 3.8 WINDING RESISTANCE MEASUREMENT

Preferably to be carried out using Automatic kit or V/I method. To reduce the high inductive effect it is advisable to use a sufficiently high current to saturate the core. This will reduce the time required to get a stabilized reading. It is essential that temperatures of the windings are accurately measured. Care shall be taken that self inductive effects are minimized. Care also must be taken to ensure that direct current circulating in the windings has settled down before the measurement is done. In some cases this may take several minutes depending upon the winding inductance. The winding resistance shall be preferably done when the difference in the top and bottom temperature of the winding (temperature of oil in steady-state condition) is equal to or less than 5°C.

- Connect neutral point and LV phase with Earth

- Join 1R1 & 3R1 Terminals - Apply 415 , 3-φ supply to HV - Ensure 2R1-N=2Y1-N=2B1-N=Constant - If 3R1-N>3Y1-N>3B1-N, and 3Y1-

1B1>3Y1-1Y1 Vector group Yna0d11 is confirmed and polarity verified.

N

Page 32: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

26of 55

The winding resistance should preferable be carried out last after completion of all other LV tests, as after this test core gets saturated and tests like magnetizing current, magnetic balance etc. carried out after winding test may be affected and indicate a misleading results, if the core is not de-magnetized before carrying out these tests. For star connected auto-transformers the resistance of the HV side is measured between HV terminal and IV terminal, then between IV terminal and the neutral AT ALL TAPS. The tap changer should be changed from contact to contact so that contact resistance can also be checked. Measurement of winding resistance to be carried out from tap position 1 to 17 and again from 17 to 9. While doing measurements in reverse order, 2 to 3 steps shall be enough. During tap changing operation, continuity check between HV to neutral to be carried out by analog multimeter while changing tap. For delta connected windings, such as tertiary winding of auto-transformers, measurement shall be done between pairs of line terminals and resistance per winding shall be calculated as per the following formula: Resistance per winding = 1.5 x Measured value Take the winding temperature reading while doing the resistance measurement. Calculate the resistance at 75°C as per the following formula R75 = Rt (235+75)/(235+t ), Where Rt = Resistance measured at winding temperature t The resistance value obtained should be compared with the factory test value. Results are compared to other phases in Star-connected transformers or between pairs of terminals on a Delta–connected winding to determine if a resistance is too high or low. Because field measurements make it unlikely that precise temperature measurements of the winding can be made, the expected deviation for this test in the field is 5.0 % of the factory test value.

3.9 MAGNETIC BALANCE TEST

This test is a low voltage test conducted at factory and site by applying single phase voltage between phase and neutral of a winding and measuring voltage induced in other two phases of the same winding. Keep the tap in nominal tap position. Disconnect transformer neutral from ground. Apply single phase 230 V across one phase of Highest Voltage (HV) winding terminal and neutral (call it v1) then measure voltage in other two HV terminals across neutral (call them v2 and v3 respectively). Repeat the test for each of the three phases. Repeat the above test for Intermediate Voltage (IV) winding also. The identical results confirm no damage due to transportation. The following points may be noted. Transformer neutral should be disconnected from ground (i) No winding terminal should be grounded, otherwise results would be erratic and confusing. (ii) Zero voltage or very negligible voltage induced in any of the other two phases shall be investigated.

Page 33: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

27of 55

(iii) It is proposed that a set of readings should be taken for information and comparison later during service of the transformer.

Also the applied voltage may be expressed as 100% voltage and the induced voltage may be expressed as percentage of the applied voltage. This will help in comparison of the two results when the applied voltages are different. The voltage induced in the centre phase shall be 50 to 90% of the applied voltage. However, when the centre phase is excited then the voltage induced in the outer phases shall be 30 to 70% of the applied voltage. Zero voltage or very negligible voltage induced in the other two windings should be investigated.

3.10 FLOATING NEUTRAL POINT MEASUREMENT

This test is conducted by applying 3 phase 415 volt supply across HV windings or IV winding as the case may be after disconnecting the transformer neutral from the ground. For a healthy transformer, when 3 phase balance voltage is applied, the voltage between neutral and ground is zero or otherwise a negligible voltage will appear. But in case there is a short circuited winding, the voltage between the neutral and the ground is appreciable. This test will also help in detecting the gradual deterioration or development of fault in the winding during service.

3.11 MEASUREMENT OF SHORT CIRCUIT IMPEDANCE

This test is used to detect winding movement that usually occurs due to heavy fault current or mechanical damage during transportation or installation since dispatch from the factory. Ensure the isolation of Transformer from High Voltage & Low voltage side with physical inspection of open condition of the concerned isolators/disconnectors. In case tertiary is also connected, ensure the isolation of the same prior to commencement of testing The measurement is performed in single phase mode. This test is performed for the combination of two winding. The one of the winding is short circuited and voltage is applied to other winding. The voltage and current reading are noted. The test shall be conducted with variac of 0-280 V, 10 A, precision RMS voltmeter and ammeter. The conductors used for short-circuiting one of the transformer windings should have low impedance (less than 1m-ohm) and short length. The contacts should be clean and tight. The acceptable criteria should be the measured impedance voltage having agreement to within 3 percent of impedance specified in rating and diagram nameplate of the transformer. Variation in impedance voltage of more than 3% should be considered significant and further investigated.

Page 34: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

28of 55

3.12 EXCITING/ MAGNETISING CURRENT MEASUREMENT

This test should be done before DC measurements of winding resistance to reduce the effect of residual magnetism. Magnetising current readings may be effected by residual magnetism in the core. Therefore, transformer under test may be demagnetised before commencement of magnetising current test. Three-phase transformers are tested by applying Single-phase 10 kV voltage to one phase (HV terminals) and keeping other winding open circuited and measuring the current at normal, minimum and max. tap positions. Keep the tap position in normal position and keep HV and LV terminals open. Apply 1phase 10kV supply on IV terminals. Measure phase to phase voltage between the IV terminals and current on each of the IV terminals. The set of reading for current measurement in each of the tap position should be equal. Unequal currents shall indicate possible short circuits in winding. Results between similar single-phase units should not vary more than 10 % .The test values on the outside legs should be within 15 % of each other, and values for the centre leg should not be more than either outside for a three-phase transformers. Results compared to previous tests made under the same conditions should not vary more than 25%. If the measured exciting current value is 50 times higher than the value measured during pre-commissioning checks, then there is likelihood of a fault in the winding which needs further analysis. The identical results confirm no damage due to transportation. The availability of test data of normal condition and faulty condition results help us to analyze the problem in future.

3.13 VIBRATION MEASUREMENT OF OIL-IMMERSED REACTOR

Movement of the core-coil assembly and shielding structure caused by the time –varying magnetic forces results in vibration of the tank and ancillary equipment. These vibrations have detrimental effects such as excessive stress on the core-coil assembly. The shunt reactor under test shall be completely assembled in normal operating condition with cooling equipments, gauges and accessories. The shunt reactor shall be energised at rated voltage and frequency. Three phase excitation for 3-ph units. The shunt reactor should be mounted on a level surface that will provide proper bearing for the base, in order to eliminate the generation of abnormal tank stresses. The vibration of shunt reactor shall be measured by transducers, optical detectors or equivalent measuring devices. The measuring equipment should be accurate within +/- 10 % at 2nd harmonic of the exciting frequency. The peak-to-peak amplitude shall be determined by direct measurement or calculated from acceleration or velocity measurement. The average amplitude of all local maximum points shall not exceed 60 µm (2.36 mils) peak to peak. The maximum amplitude within any individual reading shall not exceed 200 µm (7.87 mils) peak to peak.

.

Page 35: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

29of 55

3.14 OPERATIONAL CHECKS ON OLTC

Following checks should be carried out during pre-commissioning: Before applying voltage to the Transformer, the mechanical operation of tap changer and motor drive for step by step operation to be checked as follows:

Manual Operation: The tap changer has to be run manually by the hand crank through the total operating cycle. In each operating position, the position indicators of motor drive and tap changer (On TC head) show the same position.

Motor drive for step by step tap changing operation: Push button to be kept pressed till the motor stops i.e. driving motor should be automatically switched off when the tap changer has performed one switching operation.

(Note: At the time of change over selector operation (i.e. 9b to 10 & vice-versa), higher torque is required. Tap changer end position should be checked that the same is not overrun to avoid any failure during operation. Same can be seen through the inspection glass in the tap changer head cover. With the tap-changer fully assembled on the transformer the following sequence of operations shall be performed: a. With the transformer un-energised, one complete cycles of operations (a cycle of

operation goes from one end of the tapping range to the other, and back again). Check continuity of winding during this test. Ensure that the voltmeter needle does not deflect to zero.

b. With the transformer un-energised, and with the auxiliary voltage reduced to 85% of its rated value, one complete cycle of operation. c. With the transformer energized at rated voltage and frequency at no load, one complete cycle of operation. The following additional check points /guide lines for OLTC is recommended in consultation with OLTC manufacturer to ensure the absence of problems and proper operation: a) Function of control switches b) OLTC stopping on position c) Fastener tightness d) Signs of moisture such as rusting, oxidation or free standing water and leakages e) Mechanical clearances as specified by manufacturer’s instruction booklet f) Operation and condition of tap selector, changeover selector and arcing transfer switches g) Drive mechanism operation h) Counter operation, Position indicator operation and its co-ordination with mechanism

and tap selector positions i) Limit switch operation j) Mechanical block integrity k) Proper operation of hand-crank and its interlock switch l) Physical condition of tap selector m) Freedom of movement of external shaft assembly n) Extent of arc erosion on stationary and movable arcing contacts o) Inspect barrier board for tracking and cracking

Page 36: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

30of 55

p) After filling with oil, manually crank throughout entire range q) Oil BDV and Moisture content (PPM) to be measured and recorded (Min BDV should be

60 KV and Moisture content should be less than 10 PPM)

3.15 STABILITY OF DIFFERENTIAL, REF OF TRANSFORMER/ REACTOR

This test is performed to check the correctness of CT polarity, CT secondary core connections, connections at relay terminals and operation of relay under fault conditions.

3.15.1 REF STABILITY TEST FOR TRANSFORMER

1) After opening the C.B. and isolators at both side (H.V. and L.V. side) of transformer, use “Primary Test Tap (M point or PI1/PI2)” provided in the BUSHING TURRET CTs to bypass the Transformer with the help of Primary current injection leads. Now, after ensuring completion of all CT wiring & normal polarity, inject Current with the help of Primary Injection kits in the relevant Turret CTs of R phase & Neutral, subject to the maximum rating of Primary Test Tap.

2) Measure the spill current in REF relay which should be nearly zero. 3) Switch off Current Injection. 4) Reverse the polarity of R phase Bushing CT and again start Current Injection.

Appreciable spill current will appear in REF relay. 5) Normalize the CT circuit which was reversed in step no. (4), after switching off Current

injection. 6) Repeat the same procedure for Y and B phases and note down the results in formats. 7) Normalise the connections of CT. 8) This test has to be performed from both HV side & LV side w.r.t. Neutral.

However, if Primary Test Tap is not available in the Turret CTs, adopt following procedure; 1) After opening the C.B. and isolators at both side (H.V. and L.V. side) of transformer

apply 440V three phase voltage at three phase bushing of H.V. side with the help of three phase variac.

2) Earth the R phase of the LV side (through isolator earth switch or discharge rod). 3) Measure the spill voltage (in mV)/ spill current (in mA) to REF relay which should be

nearly zero. 4) Switch off 440V supply. 5) Reverse the polarity of R phase Bushing CT and again switch on 440V supply.

Appreciable spill voltage/ current will appear in REF relay. 6) Normalize the CT circuit which was reversed in step no. (5), after switching off 440V

supply. 7) Repeat the same procedure for Y and B phases and note down the results in formats. 8) Normalise the connections of CT and remove feeding of three phase supply.

3.15.2 REF STABILITY TEST FOR REACTOR

1) After opening the C.B. and isolators of Reactor, use “Primary Test Tap (M point or PI1/PI2)” provided in the BUSHING TURRET CTs to bypass the Reactor with the help of Primary current injection leads. Now, after ensuring completion of all CT wiring & normal polarity, inject Current with the help of Primary Injection kits in the relevant

Page 37: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

31of 55

Turret CTs of R phase of Reactor & earth side CT of NGR, subject to the maximum rating of Primary Test Tap.

2) Measure the spill current in REF relay which should be nearly zero. 3) Switch off Current Injection. 4) Reverse the polarity of R phase Bushing CT and again start Current Injection.

Appreciable spill current will appear in REF relay. 5) Normalize the CT circuit which was reversed in step no. (4), after switching off Current

injection. 6) Repeat the same procedure for Y and B phases and note down the results in formats. 7) Normalise the connections of CT.

However, if Primary Test Tap is not available in the Turret CTs, adopt following procedure;

1) After opening the C.B. and isolators of Reactor, remove the jumpers of three phase

bushings. Reactor Neutral will remain connected to NGR, however Earth connection of NGR Bushing will be opened.

2) Apply 415 volts, phase to phase voltage across R phase bushing of Reactor & earth side Bushing of NGR, after ensuring completion of all CT wiring & normal polarity.

3) Measure the spill voltage (in mV)/ spill current (in mA) in REF relay which should be nearly zero.

4) Switch off 415V supply to Reactor / NGR Bushing. 5) Reverse the polarity of R phase bushing CT. 6) Switch on 415V supply to Reactor / NGR Bushing. 7) Appreciable spill voltage/ current will appear in REF relay. 8) Now normalize the polarity of the Bushing CT which was reversed in step (5). 9) Repeat the same procedure for Y and B phase and note down the results in formats. 10) After completing the test for all three phases normalize the reactor CT connection and

jumpers & Earth connection of NGR Bushing.

3.16 TESTS/ CHECKS ON BUSHING CURRENT TRANSFORMERS (BCTS)

Continuity, Polarity and secondary winding resistance tests of individual cores of Bushing CTs

3.17 FREQUENCY RESPONSE ANALYSIS (FRA) MEASUREMENT

Frequency Response Analysis (FRA) is conducted to assess the mechanical integrity of the transformer which may get disturbed due to transportation shocks or Short Circuit forces experienced in service. FRA signatures will be taken after assembly and oil filling and compared with factory testing to ensure the healthiness of core /coil assembly during transportation. These signatures will be benchmark for future reference. The FRA signatures should be analysed in conjunction with Impact Recorder readings. Report of Impact recorder readings is to be obtained from manufacturer. It is recommended to follow the standard procedure for the SFRA measurement as per the Table-7. It should be done on maximum, normal and minimum tap.

Page 38: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

32of 55

Auto Transformer

Test Type Test 3 Ф 1 Ф Test 1 H1-X1 Test 2 H2-X2 Series Winding (OC)

All Other Terminals Floating Test 3 H3-X3 H1-X1

Test 4 X1-H0X0 Test 5 X2-H0X0 Common Winding (OC)

All Other Terminals Floating Test 6 X3-H0X0 X1-H0X0

Test 7 Y1-Y3 Test 8 Y2-Y1 Tertiary Winding (OC)

All Other Terminals Floating Test 9 Y3-Y2

Y1-Y2 (Y1-Y0)

Test 10 H1-H0X0 Test 11 H2-H0X0

Short Circuit (SC) High (H) to Low (L) Short (X1-X2-X3) Test 12 H3-H0X0

H1-H0X0 Short (X1-H0X0)

Test 13 H1-H0X0 Test 14 H2-H0X0

Short Circuit (SC) High (H) to Tertiary (Y) Short (Y1-Y2-Y3) Test 15 H3-H0X0

H1-H0X0 Short (Y1-Y2)

Test 16 X1-H0X0 Test 17 X2-H0X0

Short Circuit (SC) Low (L) to Tertiary (Y) Short (Y1-Y2-Y3) Test 18 X3-H0X0

X1-H0X0 Short (Y1-Y2)

Table-7: Various combinations for FRA measurement in Auto Transformer

Shunt Reactor: In case of Shunt Reactor, FRA to be done in following combinations:

H1-H0 H2-H0 H3-H0

3.18 DISSOLVED GAS ANALYSIS (DGA) OF OIL SAMPLE

Dissolved Gas Analysis (DGA) is a powerful diagnostic tool to detect any incipient fault developing inside the oil-filled equipment. The oil sample is to be taken after oil filling (before commissioning ) as a benchmark and there after 24hrs of charging, 7 days, 15 days, one month and three months after charging to monitor the gas build up if any. The oil samples are to be sent to CIOTL/IOTL/STL for DGA and first two samples for oil parameter testing also.

3.19 THERMOVISION SCANNING (IR THERMOGRAPHY)

Once the transformer/ reactor is charged and loaded, Thermovision scanning is to be carried out to see any hotspots. For detailed procedure for each test, please refer Transformer and Reactor Maintenance manual (Doc No. D-2-03-XX-01-01)-First Revision, Part B, C & D.

Page 39: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

33of 55

4.0 PRE-COMMISSIONING CHECKS /TESTS FOR OTHER SWITCHYARD EQUIPMENTS

Once erection is completed, various pre-commissioning checks/ tests are performed to ensure the healthiness of the switchyard equipments prior to their energisation. Various major electrical tests to be performed and their significance are given below.

Sr. No.

Name of Test / Check point

Purpose of test/ check

4.1 Tan δ & Capacitance measurement of CT, each stack of CVT & total capacitance, CB voltage grading capacitor & each stack of Surge Arresters

The purpose of the dissipation factor measurement of high voltage insulation is to detect incipient weaknesses in HV insulation. The most important benefit to be gained from this measurement is to obtain a “benchmark reference reading” on costly and high voltage equipment when the equipment is new and insulation is clean, dry and free from impurities. Tan delta & Capacitance values shall be comparable with factory test results and in no case shall be more than 0.5 %.

4.2 Checks/ Tests applicable for CTs

4.2.1 Polarity test for CT To ascertain whether the polarity markings are correct or not as per drawing.

4.2.2 Magnetization characteristics of CT

To prove that the turns of CTs secondary windings are not short circuited and to check healthiness of CT cores. The magnetizing currents at KPV (Knee point voltage) shall be less than the specified value. The ratio of secondary and primary voltage shall also be measured.

4.2.3 Ratio test for CT The ratio errors of the primary to the secondary currents should within specified ratio errors.

4.2.4 IR measurement of CT (Primary & Secondary windings)

Changes in the normal IR value of CT indicate abnormal conditions such as presence of moisture, dirt, dust, crack in insulator of CT and degradation of insulation.

4.2.5 DGA test of CT oil This test shall be conducted after 30 days of commissioning. The purpose is to identify evolving faults in the CT and DGA values shall be comparable with factory values (if available)

4.3 Checks/ Tests applicable for Circuit Breakers 4.3.1 Dew point measurement

of SF6 gas Dew point of SF6 gas is to measure moisture content in SF6 gas which shall indicate whether CB evacuation is done properly or not. This test shall be carried out preferably at rated pressure of SF6 gas.

4.3.2 Measurement of Circuit Breaker Operating Timings including PIR Timings

To measure closing/ tripping/ CO timings. These timings should be within permissible limits and shall be comparable with factory values. Pole discrepancies and Break to Break discrepancies shall be less than specified values.

Page 40: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

34of 55

4.3.3 DCRM Contact Travel Measurement / DC injected currents and trip/ close coil currents.

DCRM is the technique for measuring Contact Resistance during operation (Close/ Trip) of a circuit breaker with a delay Tco of 300ms. A DC current of at least 100 Amp is injected through the circuit breaker. The current and voltage drop are measured and resistance is calculated. The resistance and travel versus time data provides useful information on the condition of the circuit breaker contacts and is used as a diagnostic tool. DCRM test signatures shall be approved by Corporate OS.

4.3.4 Operational lockout checking for EHV Circuit Breakers

To ensure various lockout operation of CB by simulating the actual conditions at the specified pressure of oil/ air/ operating medium.

4.3.5 Measurement of static contact resistance

This test is conducted to evaluate healthiness of Main contacts. 100 Amp DC is injected and voltage drop is measured across each CB contact to compute contact resistance.

4.3.6 Checking the Anti-Pumping feature

By giving simultaneous close/ trip commands, CB hunting shall not take place by operation of Mechanical/ Electrical anti pumping feature.

4.3.7 Checking the Anti-Condensation Heaters

To check correct operation of Thermostat provided for anti condensation heaters.

4.3.8 Pole discrepancy relay testing

To test tripping of CB in case of pole discrepancy more than 2.5 seconds or specified value.

4.3.9 Checking the N2 priming pressure

This test is to check healthiness of N2 accumulators provided in Hydraulic drive mechanisms. N2 priming pressure shall be as per the rated pressure.

4.4 Checks/ Tests applicable for CVTs

4.4.1 CVT polarity, Ratio test This test is conducted in the same manner as for CT to determine correct CVT polarity, ratio and phasor group.

4.4.2 Insulation resistance measurement of Primary & secondary winding

Changes in the normal IR value of CVT indicate abnormal conditions such as presence of moisture, dirt, dust, crack in insulator of CVT and degradation of insulation.

4.5 Checks/ Tests applicable for Isolators

4.5.1 MILLIVOLT Drop test The voltage drop gives a measure of resistance of current carrying part and contacts by injecting minimum 100 A DC current.

4.5.2 50 operation tests To test operation of contacts etc with jumpers connected and contact resistance to be measured after 50 operations. There shall not be any change from the previous value.

4.6 Checks/ Tests applicable for Surge Arrestors

4.6.1 Third Harmonic Resistive Current

To monitor healthiness of Surge arrestors by monitoring third harmonic resistive current from the leakage current.

Page 41: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

35of 55

(THRC) for surge arrestors

This test is to be conducted after charging of Las. The value of THRC shall be less than 30 µA.

4.6.2 IR measurement of each stack of LA

Changes in the normal IR value of LA indicate abnormal conditions such as presence of moisture, dirt, dust, crack in insulator of LA and degradation of insulation.

4.6.3 Checking of operation of LA counter

This test is done to check the healthiness of LA counter.

4.7 Checks/ Tests for other areas/ equipments

4.7.1 Earth resistance measurement

To ensure value of earth resistance is below 1 ohm.

4.7.2 Secondary current injection test

Conducted for testing of protecting devices, circuit breakers, trip coils, motor overloads etc.

4.7.3 Contact Tightness check of Bay contacts by Primary injection method

Since complete bay contact resistance measurement is practically not possible because DC current may not be injected in CT primary, hence contact tightness check by primary injection method has been introduced to check overall contact tightness.

4.7.4 Stability check for Bus Bar

This test is performed to check the proper operation of Bus Bar protection by simulating actual conditions. Any problem in CT connection, wrong cabling, relay setting can be detected by this test.

Page 42: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

36of 55

4.1 TAN DELTA & CAPACITANCE MEASUREMENT OF CT, CVT, CB VOLTAGE GRADING CAPACITORS AND LA STACKS

To measure dissipation factor/loss factor (Tan delta) and Capacitance measurement of EHV class CTs, CVTs, CB Voltage Grading Capacitors & LA stacks by applying test voltages upto 10kV. Dissipation Factor Dissipation factor/loss factor (Tan delta)is defined as the ratio of resistive component(Ir) of current to that of capacitive current (Ic) flowing in an insulating material. Power Factor Power factor is the ratio of resistive current to that of total current. For very low value of resistive currents, values of dissipation factor and power factor are same (upto 2%). UST Test set connected for Ungrounded Specimen Test mode. This is used when specimen is isolated from earth e.g. Transformer bushing, CTs with test tap, CVTs and CB voltage grading capacitors. The test mode is often used to reduce the effect of stray capacitance losses to ground, and to reduce the effect of interference pickup from energized apparatus. GST Test set connected for grounded specimen test mode. This is used when specimen do not have two specific points (isolated from ground) for Tan delta measurement e.g. Transformer/Reactor winding, CTs without test tap etc. GSTg This test is used to separate the total values of a GST test into separate parts for better analysis. Often this test is used with GST test to confirm the test readings made using the UST mode. TEST EQUIPMENT 10 KV or 12 KV fully automatic Capacitance and Tan delta test kit to be used for accurate measurement and repeatability of test results. PRECAUTIONS a) There should be no joints in testing cables. b) HV lead should be screened with double shield and shields should not have internal

shorting otherwise tests in GST/GSTg modes, shall not be possible. Check the same by Insulation Tester(100V)

c) Test leads should not touch any live part. d) Never connect the test set to energised equipment e) The ground cable must be connected first and removed at last f) High voltage plugs should be free from moisture during installation and operation. g) It should be ensured that whole testing equipment alongwith Operation Manual of the kit

testing procedures are available at testing site. Testing must be carried out by testing personnel only.

h) After testing with high voltage (10 kV), test terminals must be grounded before being touched by any personnel.

TESTING PROCEDURE: Typical arrangement for Tan δ measurement is given below in Figure 6, 7 & 8:

Page 43: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

37of 55

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

UST Mode of Measurement

N1 N2

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

UST Mode of Measurement

N1 N2

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

GST Mode of Measurement

N1 N2

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

GST Mode of Measurement

N1 N2

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

GSTg Mode of Measurement

N1 N2

~PowerSupplyCs

StandardCapacitor

CHg

CHL

CLg

UnknownSpecimen

Null Detector

GSTg Mode of Measurement

N1 N2

Page 44: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

38of 55

A) CURRENT TRANSFORMERS

CTs with test taps: 1. Tan delta tap to be disconnected from ground. 2. High voltage lead from tan delta kit to be connected to primary(HV) Terminal and

LV lead to be connected to the Tan delta test tap. 3. P1 and P2 to be shorted 4. Porcelain surface to be thoroughly cleaned. 5. Measurements have to be taken in UST mode with fully automatic test kit. 6. Standard procedure(as specified by kit supplier) for measuring capacitance and tan

delta in charged switchyard/induced voltage conditions should be followed for measurement of capacitance and tan delta values.

7. It is to be ensured to connect the test tap to ground terminal after carrying out the test.

B) CB VOLTAGE GRADING CAPACITOR

1. Connect LV cable to the middle of the double interrupter. 2. Connect HV cable to the other end of the Grading capacitor to be tested. 3. The opposite end of the grading capacitor has to be grounded using earth switch. 4. Measurements have to be taken in UST Mode with fully automatic test kit. 5. Disconnect the HV cable and connect the same to the other grading capacitor and

ground the previous grading capacitor. Now the second grading capacitor is ready for testing.

6. Standard procedure (as specified by kit supplier) for measuring capacitance and tan delta in charged switchyard/induced voltage conditions should be followed

7. Measurements are to be carried out at 10 kV/ 12 KV. C) CAPACITOR VOLTAGE TRANSFORMES

1. Testing procedure for Top and Middle Stacks:

(a) Apply 10 KV between flanges of Top/Middle stacks (whichever is being tested) (b) Carry out measurements in UST mode at 10.0 KV (c) While measuring Middle/ Bottom stacks, Top/ middle stacks to be shorted.

2. Testing procedure for Bottom Stack connected to EMU PT. (a) Connect HV of the test kit at the top flange of bottom stack. HF point to be

grounded. Earth connection of the neutral of the PT to be opened/ isolated from ground.

(b) Top of CVT to be guarded. LV lead of the kit to be connected at the top of the CVT for guarding.

(c) Carry out measurements in GSTg mode at 10.0 KV (d) Repeat the Test with neutral of PT connected to ground. (e) In case Tan delta value is negative or erratic, only capacitance values are to be

monitored. (f) Measurement to be carried out using fully automatic kit.

Page 45: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

39of 55

3. Standard procedure (as specified by kit supplier) for measuring capacitance and tan delta in charged switchyard/ induced voltage conditions should be followed.

D) SURGE ARRESTORS

1. Testing procedure for Top, Middle and Bottom Stacks:

(a) Apply 10 KV between flanges of Top/Middle/ Bottom stacks (whichever is being tested)

(b) Carry out measurements in UST mode at 10.0 KV with fully automatic test kit. (c) While measuring Middle/ Bottom stacks, the stacks above the HV lead to be

shorted.

2. Standard procedure (as specified by kit supplier) for measuring capacitance and tan delta in charged switchyard/ induced voltage conditions should be followed.

3. While doing measurement of bottom stack the earth connection to be removed.

4.2 CHECKS/ TESTS APPLICABLE FOR CTs

4.2.1 POLARITY TEST FOR CT

A centre zero voltmeter is connected across CT secondary. A 1.5 Volt battery is touched to primary of CT. The deflection of pointer should be similar in case of each CT core.

At any instant current entering the primary from P1 the current should leave secondary from the terminal marked S1. A setup shown in the Figure 9 can show whether the polarity markings are correct or not.

When the key is pressed, current enters the primary through terminal P1, the voltmeter connected as shown, should read positive. A general arrangement of polarity test setup is indicated in Fig. 10.

+

-KEY

P2 S2

S1P1

-

+V

1.5 V

-

+V

+-

R Y B

S2

S1

P1 P1 P1

Figure – 9

Figure - 10

Page 46: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

40of 55

4.2.2 MAGNETIZATION CHARACTERISTICS OF CTs

PRECAUTIONS a) There should be no joints in testing leads/cables. b) It should be ensured that whole testing equipment along with testing procedures are

available at testing site. Testing must be carried out in presence of testing personnel only.

Test Equipment: Voltage source of 5 kV, Voltmeter of range 0 to 5 kV, Ammeter, of range 0 to 500 Amps, testing leads/cables etc. Test Procedure: Make connections as per diagram shown below (Fig- 11). After making proper connections, applied voltage is increased from zero to rated Knee Point Voltage in steps of 25%, 50%, 75% and 100%. Measure the current drawn by the CT secondary core at respective applied voltages and record the test results

Figure - 11

Knee Point Voltage is normally defined as the voltage at which 10% increase in the applied

voltage causes 30 to 50% increase in secondary current. The magnetization current at rated Knee Point Voltage should not be more than the specified/designed value. A curve can be drawn between applied voltage and magnetizing current. Typically, the curve drawn should be like the one given below in Fig.-12:-

Page 47: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

41of 55

100

200

300

400

500

600

MAGNETIZINGCURRENT

30 %

10 %

TYPICAL MAGNETIZATION CURVE

VO

LTA

GE

Figure - 12

From the curve it can be implied that up to rated KPV (Knee Point Voltage), the VI curve should be almost a straight line. However, if this line is not linear, this indicates that the magnetizing characteristics are not desirable. If the slop of the curve starts increasing, it indicates that magnetizing induction becomes low and total primary current is utilized in exciting the core alone. Consequently, out put of CT secondary disappears.

4.2.3 RATIO TEST FOR CURRENT TRANSFORMER

The ratio check has to be carried out as indicated in Fig-13 below.

PRIMARYCURRENTINJECTION

SET

A1

A2A1 : PRIMARY CURRENT

A2 : SECONDARY CURRENT Figure - 13

It is customary to conduct this in conjunction with the primary injection test. Current is passed through the primary circuit with the secondary winding circuit to its normal circuit load. The ratio of the primary to the secondary currents should approximate closely to that stamped under CT identification plate.

Alternatively, ratio test is to be conducted as per the following method (Fig-14).

Page 48: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

42of 55

Figure - 14

Apply voltage from secondary of the CT and measure voltage in primary winding. Increase voltage in secondary up to rated KPV/ ISF and by recording Primary Voltage, compute ratio of V1/ V2. The ratio should match with the specified value.

4.2.4 INSULATION RESISTANCE MEASUREMENT OF CURRENT

TRANSFORMER PRECAUTIONS

a) There should be no joints in testing cables. b) Test leads should not touch any live part. c) Megger body should be earthed (if separate terminal is provided). d) Surface/terminals should be cleaned. e) IR measurement should be carried out preferably in dry and sunny weather. f) Never connect the test set to energised equipment. g) The ground terminal must be connected first and removed at last. h) High voltage plugs should be free from moisture during installation and operation. i) If oil traces are found on the surface of CT, the same should be cleaned by Methyl

Alcohol only. Petrol or diesel should never be used. j) It should be ensured that whole testing equipment along with testing procedures are

available at testing site. Testing must be carried out in presence of testing engineer only.

k) After testing with high voltage, test terminals must be grounded before being touched by any personnel.

l) Test leads should be properly screened/ shielded.

Connect the Megger as per figure-15 given below. Connect the HV terminal to the Primary terminal of CT by using crocodile clip for firm grip.

Page 49: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

43of 55

Figure-15 Typical Arrangement for IR measurement

Carry out the measurement as per standard procedure given by the kit supplier. A test voltage as specified is applied as per the above connections and successive readings are taken. Values of IR should be recorded after 15 seconds, 60 seconds and 600 seconds. Ambient temperature and weather conditions are to be recorded. 4.2.5 DGA Test of CT Oil: Oil samples to be collected in 300ml bottles and to be sent to

CIOTL Hyderabad for testing. Test results should be comparable to factory values. In case of any deviation, test results may be forwarded to CC-OS for approval.

4.3 CHECKS/ TESTS APPLICABLE FOR CIRCUIT BREAKERS

4.3.1 DEW POINT MEASUREMENT OF SF6 GAS FOR CIRCUIT BREAKER Dew Point is the temperature at which moisture content in SF6 gas starts condensing. Dew Point at rated pressure of CB: Dew Point when measured keeping regulating valve in service at the outlet of dew point kit to allow required flow rate of gas, is called at rated pressure of CB. Inlet valve is opened completely. Dew Point at atmospheric pressure : Dew Point when measured by regulating the gas flow at the inlet of dew point kit and keeping outlet regulating valve ( if provided) in fully open condition so that flow rate of gas is maintained as required, is called at atmospheric pressure.

TESTING PROCEDURE

a) Make the connections to the kit from CB pole ensuring that regulating valve is fully closed at the time of connections of the Dew Point kit.

b) By regulating the flow rate of SF6 gas (0.2 liter/min to 0.5 liter/min - ref. IEC 60480), the

value of dew point is observed till it becomes stable.

Page 50: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

44of 55

c) If the regulating valve is provided at outlet of the dew point kit then values as given in Doc. no. for rated pressures are to be monitored.

Dew Point of SF6 gas varies with pressure at which measurement is being carried out. This is due to the fact that Saturation Vapour Pressure decreases with increase in Pressure of the SF6 gas. Hence, dew point of SF6 gas at higher pressure is lower than dew point at atmospheric pressure Therefore, it is to be ensured that if measurement has been done at a pressure other than the atmospheric pressure, same is to be converted to the atmospheric pressure as given in the table below used at the time of commissioning for various CB manufacturers: Method for converting dew point at different gas pressures, is given/described in IEC-60480.

Sl. No. Make of CB

Dew point at rated pressure

Dew point at Atmospheric Pressure ( Limit )

1 BHEL (-) 15° C - 36° C 2 M & G - - 39° C 3 CGL (-) 15° C - 35° C 4 ABB (-) 15° C - 35° C 5 NGEF (-) 15° C - 36° C

4.3.2 MEASUREMENT OF CIRCUIT BREAKER OPERATING TIMINGS INCLUDING PRE INSERTION RESISTOR TIMINGS

PRECAUTIONS a) There should not be any joint in testing cables. b) Test leads should not touch any live part. c) Never connect the test set to energised equipment. d) The ground cable must be connected first and removed at last. e) High voltage plugs should be free from moisture during installation and operation. f) Circuit Breaker Analyser body should be earthed (if separate earth is provided). g) It should be ensured that whole testing equipment along with testing procedures are

available at testing site. Testing must be carried out in presence of testing personnel only. h) Surface/terminals should be cleaned where the connections for testing are to be made. i) Clean earth point with sand paper/wire brush where earth terminal is to be provided. j) Ensure that all the poles trip simultaneously through single close/trip command. TESTING PROCEDURE a) Make connections as shown in the figure-16 below. It is to be ensured that R, Y, B

phase marking cables are connected with the proper place in the CB analyser and colour codes are to be maintained for all the three poles of CB.

b) Make connections for recording operating timings of Auxiliary contacts. c) Extend power supply to Circuit Breaker Analyzer. d) Give closing command to closing coil of CB and note down the PIR and main contact

closing time. Take the print out from the analyser.

Page 51: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

45of 55

e) Give tripping command to trip coil-I of CB & note down the main contact tripping time. f) Give tripping command to trip coil-II of CB & note down the main contact closing time. g) Note down the timings for `CO', and `OCO' by giving respective commands. CO

command to be given without time delay but 300ms time delay to be given between O and CO operation in testing for OCO.

h) To find out opening time of PIR contacts, PIR assembly has to be electrically isolated from Main contacts and then PIR contacts are to be connected to separate digital channels of the Analyzer.

EVALUATION OF TEST RESULTS

A) CLOSING TIMINGS Closing timings and Discrepancy in operating times of PIR and main contacts should not exceed the permissible limits as specified in the DOC NO: D-5-02-XX-01-03. In any case, main contacts should not close prior to closing of PIR contacts and PIR contacts should not open prior to closing of main contacts. In case, contact bouncing is observed in operating timings for PIR and main contacts, same should be rectified by tightening the cable connections.

Figure-16 B) TRIPPING TIMINGS

Trip time and pole discrepancy in operating timings should not exceed beyond permissible value given in Doc. No. D-5-02-XX-01-03. In case of ABB, NGEF and CGL make CBs, while tripping, PIR contacts should not open after opening of main contacts.

Page 52: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

46of 55

C) ‘CO' TIMINGS CO timings should be within permissible limits as specified by different manufacturers. If operating timings of CB poles are not within limits, same may be corrected by: 1. Equalizing the SF6 gas pressure in all the poles 2. Adjusting plunger movement of trip/ close coils 3. Adjustment in operating mechanism 4. Changing of trip/ close coils (if required) It is also important to measure timings of auxiliary contacts from the point of view of

variations w.r.t. the main contacts.

4.3.3 DYNAMIC CONTACT RESISTANCE MEASUREMENT (DCRM) AND CONTACT TRAVEL MEASUREMENT OF EHV CIRCUIT BREAKERS

Test Equipment: 100 Amp. DCRM kit with CB operational analyzer with 10k Hz sampling

frequency. Isolation Required a) CB should be in open position. b) Isolator of both sides of CB should be in open position.

c) Earth switch of one side of CB should be in open position. Precautions

a) There should be no joints in testing leads/cables. b) It should be ensured that whole testing equipment along with testing procedures are

available at testing site. Testing must be carried out in presence of testing personnel only.

c) Current leads should be connected such that voltage leads are not outside area of current flow.

Testing Procedure

1. Follow the standard procedure as given in instruction manual of DCRM kit. 2. The tightness of connections at CB flanges is most important to ensure error free

measurement. CB during CO operation generates lot of vibrations and failure of connections during this period can dramatically change the dynamic signature of CB resistance.

3. DCRM signatures should be recorded for CO operation. Open command should be extended after 300 ms from the close command.

4. Clean portions of incoming and outgoing flanges of CB with polish paper to remove paint, oxidation etc, at points where Current clamps are mounted.

5. Select this point of connection, as close as possible to the end of porcelain insulator to ensure that minimum resistance is offered by flanges, bolts, terminal connectors etc.

6. It should be ensured that Travel Transducers are properly fitted. 7. Sampling frequency during measurement should be 10 KHz. 8. Resistance, travel, injected current and Trip/ Close coil currents are to be recorded.

Page 53: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

47of 55

The variations in the measured resistance versus time will be seen as a finger print for the breaker contacts and can be used as a bench mark for comparing with future measurements on the same breaker. This provides information on the condition of the breaker contacts, driving mechanism, operating levers etc.

Dynamic Contact Resistance Measurement for CB healthiness By application of Dynamic Contact Resistance Measurement, condition of arcing contact, main contact, operating levers, driving mechanism can be predicted. If DCRM signature shows vide variations and also there is change in arcing contact insertion time, it indicates erosion of the arcing contacts to main contacts and subsequent failure.

Contact Travel Measurement Transducers are attached to the operating rod or interrupting chamber in order to record the contact travel. When CB closes, contact travel is recorded. Contact bounces or any other abnormality is also clearly indicated by the Contact Travel Measurement.

If contact travel, contact speed and contact acceleration signature are compared with the original signatures, then it may indicate problems related with the operating mechanism, operating levers, main/ arcing contacts, alignments etc. DCRM along with Contact Travel measurement is useful in monitoring length of Arcing contacts. Erosion of Arcing contacts may lead to commutation failures and current may get transferred to Main contacts. Due to heat of arc, main contacts may get damaged.

4.3.4 OPERATIONAL LOCKOUT CHECKING FOR EHV CIRCUIT BREAKERS

4.3.4.1 TESTING PROCEDURE:

A. SF6 GAS PRESSURE LOCKOUT a) LOW PRESSURE ALARM

Close Isolation Valve between CB Pole(s) and density monitor. Start releasing SF6 gas from density monitor till the low pressure gas alarm contacts are actuated which is detected by Multimeter. Note down the pressure and temperature at which the contacts get actuated. b) OPERATIONAL LOCKOUT: Continue releasing SF6 gas from isolated zone till the operational lockout Alarm Contacts are actuated which are detected by Multimeter. Note down the pressure and temperature at which the contacts get actuated. This is called operational lockout pressure. B. PNEUMATIC OPERATING SYSTEM LOCKOUT a) COMPRESSOR START/STOP SWITCH Close the isolating valve of CB. Release air into atmosphere from the compressor. Note down the value of pressure at which Compressor starts building up air pressure and

Page 54: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

48of 55

pressure at which Compressor stops. b) CB AUTO RECLOSE LOCKOUT Close Isolation valve between pneumatic system and pressure switches. Release air from the isolated zone to atmosphere. Note down pressure at which A/R L/O contacts of pres-sure switch get actuated which are detected by Multimeter. The leads of the Multimeter should be connected to the contactor where the AR L/O of CB are made. c) CB CLOSING LOCKOUT Release air from the isolated zone to atmosphere. Note down pressure at which CB Closing L/O contacts of pressure switch get actuated which are detected by Multimeter. d) CB OPERATIONAL LOCKOUT Release air from the isolated zone to atmosphere. Note down pressure at which CB Operational L/O contacts of pressure switch get actuated which are detected by Multimeter. e) MECHANICAL CLOSING INTERLOCK (FOR ABB & BHEL CBs ONLY) CB should be in closed position. Release air from pneumatic system of CB to atmosphere and observe whether CB poles start opening, if so, note down the pressure at which tie rod starts coming down. In such case the closing interlock is to be opened for inspection and if required, replace the closing interlock. C. HYDRAULIC OPERATING SYSTEM LOCKOUT a) Pump START/STOP By opening pressure release valve, note down the pressure at which Pump starts building up oil pressure and pressure at which pump stops. b) CB AUTO RECLOSE LOCKOUT Close Isolation valve between hydraulic system and pressure switches. Release oil from the isolated zone to oil tank. Note down pressure at which A/R L/O contacts of pressure switch get actuated which are detected by Multimeter. c) CB CLOSING LOCKOUT Release oil from the isolated zone to oil tank. Note down pressure at which CB Closing L/O contacts of pressure switch get actuated which are detected by Multimeter. d) CB OPERATIONAL LOCKOUT Release oil from the isolated zone to container. Note down pressure at which CB Opera-tional L/O contacts of pressure switch get actuated which are detected by Multimeter. D. OPERATING PRESSURE DROP TEST: For Pneumatic/ Hydraulic operating system, operating pressure drop test to be performed during OCO operation of CB, keeping AC supply of Hydraulic pump/ Compressor in off condition. Hydraulic/ Pneumatic pressure drop should be within limits (as recommended by Manufacturer)

Page 55: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

49of 55

4.3.4.2 EVALUATION OF TEST RESULTS A. SF6 GAS PRESSURE LOCKOUT All the SF6 gas pressure switches settings should be checked and corrected with ambient temperature. Settings of SF6 gas pressure switches should be within ± 0.1 bar/ Kg/cm2 of the set value ( after taking into account the temperature correction factor). B. AIR PRESSURE LOCKOUT All the air pressure switches settings should be checked and corrected and should be within ± 0.3 bar/ Kg/cm2 of the set value. C. OIL PRESSURE LOCKOUT All the oil pressure switches settings should be checked and corrected and should be within ± 0.3 bar/ Kg/cm2 of the set value.

4.3.5 MEASUREMENT OF STATIC CONTACT RESISTANCE

The Static contact resistance of main circuit of each pole of a circuit breaker is of the order of a few tens of micro ohms. 100 A DC is injected and milli volt drop is measured across each CB contact to compute contact resistance. The values should be within specified limits as given in Doc No. D-5-02-XX-01-01.

4.3.6 CHECKING THE ANTI-PUMPING FEATURE

When the breaker is in open position and closing and opening commands are given simultaneously the breaker first closes and then opens, but does not reclose even though the closing command is maintained.

4.3.7 CHECKING THE ANTI-CONDENSATION HEATERS

Check the supervisory circuit of the anti-condensation heaters for correct functioning. With the heaters switched ON, measure their current output.

4.3.8 POLE DISCREPANCY RELAY TESTING

Pole Discrepancy is defined as the difference in closing & opening timings of different poles of CB.

A. WHEN CB IN OPEN POSITION Closing Command is extended to close one pole, say R-Pole, of CB. After closing R-Pole of CB, this Pole should automatically open after 2.5 seconds (as per pole discrepancy timer settings). Repeat the test for remaining two poles of CB. B. WHEN CB IN CLOSED POSITION Tripping Command is extended to trip one pole, say R-Pole, of CB. Remaining Y and B- Poles of CB should automatically open after 2.5 seconds. Repeat the same test for remaining two poles of CB.

Page 56: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

50of 55

C. EVALUATION OF TEST RESULTS Permissible value of pole discrepancy between two poles of CB is 3.33 msec. from system point of view and it should not be confused with the setting of pole discrepancy timer which is generally 1.0 or 2.5 sec. depending on Auto-reclose scheme.

4.3.9 CHECKING THE NITROGEN PRIMING PRESSURE

Close the pressure release valve. Shortly after the oil pump starts, the priming pressure (200 bar at 20°C) in the accumulator can be read. The relationship between the pressure and temperature is indicated in Fig. 17.

150

16

0

170

1

80

190

2

00

210

2

20

230

P rim ing p ressure as a function o f the tem pera tu reN om ina l ra ting a t 20 deg .C : 200 .1 ba r

bar

Figure - 17

4.4 CHECKS/ TESTS APPLICABLE FOR CVTs

4.4.1 CVT POLARITY, RATIO TEST

CVT polarity is checked in the same manner as for CT, taking care to ensure that the battery is connected to the primary winding. In case of star/star winding configuration care has to be taken to ensure that the primary and secondary neutral points are not connected together. It is necessary to verify that the phase rotation sequence of the 3 phase CVT is correct. The secondary voltage between phases and neutral are measured and then phase rotation meter is connected across the three phase terminal.

4.4.2 INSULATION RESISTANCE MEASUREMENT OF PRIMARY & SECONDARY WINDING

Page 57: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

51of 55

4.5 CHECKS/ TESTS APPLICABLE FOR ISOLATORS

4.5.1 MILLI VOLT DROP TESTS

The milli volt drop across the isolator is measured using DC current. The voltage drop gives a measure of resistance of current carrying part and contacts.

The DC current should be equal to or more than 100 A. The resistance of isolator should be measured at ambient air temperature. The temperature of specimen/environmental temperature should be recorded. The value of measured resistance should be converted to the value of temperature at which factory test results are taken. Temperature corrected value of resistance should be comparable to the factory value.

4.5.2 50 OPERATION TESTS

4.6 CHECKS/ TESTS APPLICABLE FOR SURGE ARRESTORS

4.6.1 MEASUREMENT OF THIRD HARMONIC RESISTIVE CURRENT FOR SURGE ARRESTERS

Testing Procedure a. Make the connections as per the diagram given below (Fig.18) b. The kit should be properly earthed. c. Clamp On type CT should be placed above the surge monitor to pick up the total leakage

current. d. Carryout the measurements as per standard procedure supplied by the test kit

manufacturer. e. Note down the system voltage and ambient temperature along with the test current value. f. Avoid measurement during monsoon.

Figure- 18 Typical arrangement for THRCM Test EVALUATION OF TEST RESULTS

A. ZnO Surge Arrester continuously conducts a small leakage current (Fig.19). The resistive

component of this leakage current may increase with time due to different stresses causing ageing and finally cause arrester failure.

Page 58: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

52of 55

B. If Harmonics are present in the system voltage, it affects the value of measured third harmonic current. Compensating device provided to be used to nullify the effect. The value of Third Harmonic Resistive current shall be less than 30 µA.

Figure-19 Arrester equivalent circuit

4.7 CHECKS/ TESTS FOR OTHER AREAS/ EQUIPMENTS

4.7.1 EARTH RESISTANCE MEASUREMENT

Normally Earth tester is used for measuring

(a) Soil resistivity

(b) Earth resistance

a. Prior to the testing of soil resistivity and earth resistance the operation manual of the testing instrument available at site may be referred for procedures to be adopted for measurement of soil resistivity and earth resistance.

A typical earth tester has 4 terminals. C1, P1, C2, P2 and 4 similar electrodes are driven in the ground at equal distances and connected to the instruments in the order of C1, P1 and P2, C2. Then the handle is rotated or button is pressed and the reading of the resistance is read on the scale of the instrument. If R is the resistance measured then

Specific Resistivity = 2 π a R

Where ‘a’ is the distance between the electrode

And R is the resistance in ohms measured on the earth tester.

b. In order to measure earth resistance of the electrode of the substation, it could be connected to C1 and the value of R could be read in the scale with the rotation of the handle of the Insulation tester. This will give the earth resistance. The value as far as possible should be around 1 ohm. To improve the value, water should be spread at the earth pit.

Page 59: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

53of 55

4.7.2 SECONDARY CURRENT INJECTION TEST SETS

The primary test is essential when commissioning and new installation as a test the whole protection system and will detect current transformers connected with incorrect polarity or relays that have been set in the wrong sequence in differential system. Secondary current injection sets are very useful for conducting these tests. The standard secondary current injection test equipment consists of a 1/5 A current injection set, separate wave form filter unit and a digital counter. The equipment is designed in a portable kit for on site testing of protecting devices, circuit breakers, trip coils, motor overloads, and similar apparatus. The filter unit should be used when testing saturating core type relays to ensure that the test current has a substantially sinusoidal waveform. The typical test setup is shown in the figure 20. Details of the testing will be elaborated in the relay testing.

S2

S1

P1 P1 P1

LOAD

INSULATING TESTPLUGS

INJECTCURRENT

HERE

A1

A2

Figure - 20

4.7.3 CONTACT TIGHTNESS TEST OF BAY CONTACTS:

a. Isolate the Bay from Bus –Side and line side as shown in Fig.-21. b. Ensure that all the secondary cores are connected or short if not in use. c. Inject the Current at Point 1 (200A) from primary injection kit (w r t earth) and return

current via earth point at 2 as shown in Fig.-21. d. Check that we are able to inject current at point 1 and measure the current at point 2. e. Injection of current is the indication of contact tightness. f. Repeat the procedure for point 1 & 3 g. Repeat the procedure for point 1 & 4

Note: Above tests can be aborted if individual contact resistances are within satisfactory limit and physical phase checking is satisfactory.

Page 60: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

54of 55

POINT 4 POINT 3

POINT 2POINT 1

CB

CB

I

LINE

LINE

POINT 4 POINT 3

POINT 2POINT 1

CB

CB

I

LINE

LINE

Figure-21 : Primary injection test to check contact tightness of Bay/ feeders

4.7.4 STABILITY TEST FOR BUSBAR: Procedure given below is to be adopted phase wise

1) Isolate all the bays connected to the bus bar from line side and close bus CBs and bus isolators as shown in the Fig. 22

BUS EARTHSWITCH

BUSBAR1 2 3

4 5BUS EARTHSWITCH

BUSBAR1 2 3

4 5

BUSBAR1 2 3

4 5

Figure-22: Status of switches for performing Stability Test

2) Inject the Primary current of 200A from point 1 to point 4 with bus earth switch open

as shown in Fig 23 and check the spill current in check zone / bus zone in bus bar protection panel, measured value is to be near zero (for 2000/1 CT ratio secondary current is 100 mA and spill current may be 1 mA or below) .If spill current is more than 10% check CT bus bar wiring and correct it.

Page 61: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LTD. PRE-COMMISSIONING PROCEDURES / ी किमशिनग ि याए DOC NO: D-2-01-03-01-02- SECOND REVISION / ि तीय सशोधन

55of 55

BUSBAR

1 2 3

4 5

BUS EARTHSWITCH OPEN

I

BUSBAR

1 2 3

4 5

BUS EARTHSWITCH OPEN

BUSBAR

1 2 3

4 5

BUSBAR

1 2 3

4 5

BUS EARTHSWITCH OPEN

I

Figure-23: Primary injection with Bus Earth Switch Open

3) Inject the Primary current of 200A from point 1 to point 4 with bus earth switch close

as shown in Fig. 24 and check the spill current in check zone / bus zone in bus bar protection panel, measured value is to be around full secondary current (for 2000/1 CT ratio secondary current is 100 mA and spill current may be near 100 mA ) .If no spill current found check the CT bus bar wiring and correct it.

BUSBAR

1 2 3

4 5

BUS EARTHSWITCH CLOSE

I

BUSBAR

1 2 3

4 5

BUS EARTHSWITCH CLOSE

I

Figure-24: Primary injection with Bus Earth Switch Closed

4) Repeat the above test for all remaining CT combination i.e 1-3 , 1-5 , 1-2 etc

5) If a new bay is added to the BUS, check only new CT with any Old CT of that BUS.

Page 62: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II DATE OF III DATE OFERECTION : ENERGISATION :

IV DETAILS OF EQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. : R - PHASE : Y - PHASE : B - PHASE :

YEAR OFMANUFACTURE :

FEEDER NAME :

V RATED DATA AND DUTY

CORE RATIO CLASS BURDEN KVP PROTECTION / METERING

WINDING I

WINDING II

WINDING III

WINDING IV

WINDING V

KVp : KNEE POINT VOLTAGE IN VOLTSVI DETAILS :

SL. DESCRIPTION STATUSNO YES NO 1 EQUPIMENT IS CLEANED AND FREE FROM

DUST / DIRT FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLE

DEFECTS ON PHYSICAL INSPECTION

3 CHECK CT TANK HAS BEEN PROVIDED

WITH DOUBLE EARTHING(DEAD TANK CT's)

4 CHECK THAT CT JUNCTION BOX IS EARTHED.

5 ALL NUTS AND BOLTS ARE TIGHTENED

CORRECTLY AS PER SPECIFIED TORQUE

6 CHECK TIGHTNESS OF TERMINAL CONNECTOR

7 ALL FITTINGS AS PER OUT LINE

GENERAL ARRANGEMENT DRAWING.

8 LEVELLING AND ALIGNMENT OF STRUCTURE

AND BASE FRAME IS CHECKED

9 ERECTION COMPLETION CERTIFICATE ALONG

WITH LIST OF OUTSTANDING ACTIVITIES

REVIEWED

10 ANY PAINT REMOVED / SCRATCHED IN

TRANSIT HAS BEEN TOUCHED UP

11 CHECK PRIMARY POLARITY OF CT,S

ERECTED AS PER RELEVANT DRAWING.

RECORD DEFICIENCIES, IF ANYREMARK

PAGE 1 OF 8 CURRENT TRANSFORMER

Page 63: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

12 CHECK HERMETICALLLY SEALING IS INTACT

13 CHECK THE OIL LEVEL AND LEAKAGE

THROUGH ANY JOINTS / SEC. TERMINALS

14 CHECK OIL DRAIN VALVE IS PROPERLY

CLOSED AND LOCKED.

15 OIL LEVEL & OIL SAMPLING

16 N2 PRESSURE CHECKED (WHEREVER APPLICABLE)

17 OIL LEVEL ON TOP CHAMBER GAUGE GLASS

18 BDV OF OIL SAMPLE TAKEN FROM TANKBOTTOM DRAIN VALVE ( ONLY IF NITROGEN

PRESSURE IS MEASURED ZERO )

19 ALL THE CABLE IDENTIFICATION TAGSPROVIDED AND ALL CORES ARE PROVIDED

WITH IDENTIFICATION FERRULES AT M.B.

20 CHECK SECONDARY CABLE END BOX IS PROPERLY FIXED AND ENSURE CABLE ENTRY

AT THE BOTTOM AND UNUSED HOLES SEALED

21 ENSURE INTERPOLE CABLING IS COMPLETED

AND CHECK THE CONTINUTY.

22 CHECK THE IR VALUE OF SECONDARY CABLE

23 CHECK EXTERNAL CABLING FROM JUNCTION-

BOX TO RELAY / CONTROL PANEL COMPLETED

24 ENSURE UNUSED SECONDARY CORES,

IF ANY, HAS BEEN SHORTED

25 CHECK STAR POINT HAS BEEN FORMED

PROPERLY AND GROUNDED AT ONE END ONLY

26

27

28

29

30

IX INSULATION RESISTANCE MEASUREMENT : ( USING 5KV MEGGER)

DETAILS OF TEST KIT:

NOTE : A) REMOVE THE CONNECTED EARTHING TO SYSTEM INVOLVING CT UNDER TEST

B) DISCONNECT THE CONNECTED TERMINALS OF CT M.BOX

C) PERMISSIBLE VALUES IS 1000 MOHMS

CORE PHASE R Y B

PRIMARY - CORE I MOHM

PRIMARY - CORE II MOHM

PRIMARY - CORE III MOHM

CHECK THAT LUGS USED IN SECONDARY CIRCUIT ARE OF RING TYPE

CHECK DIRECTION OF PRIMARY (P1/ P2) w.r.t. BUS/ LINE ON ERECTION

PERMANENT POLE LAVELLING AND IDENTIFICATION MARKINGS MADE

CHECK TAN DELTA TEST TAP IS PROPERLY EARTHED

CHECK SPARK GAP SETTING IN P1 TERMINAL (WHEREVER PROVIDED/ POSSIBLE)

PROVISION OF BIMETALLIC STRIPS (Cu +Al) ENSURED WHEREVER APPLICABLE

PAGE 2 OF 8 CURRENT TRANSFORMER

Page 64: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

PRIMARY - CORE IV MOHM

PRIMARY - CORE V MOHM

PRIMARY - EARTH MOHM

X INSULATION RESISTANCE MEASUREMENT : (USING 500 V MEGGER)

DETAILS OF TEST KIT: PERMISSIBLE VALUES IS 50 MOHMS

A PHASE R Y B

SECONDARY CORE I - EARTH MOHM

SECONDARY CORE II - EARTH MOHM

SECONDARY CORE III - EARTH MOHM

SECONDARY CORE IV - EARTH MOHM

SECONDARY CORE V - EARTH MOHM

B PHASE R Y B

CORE I - CORE II MOHM

CORE I - CORE III MOHM

CORE I - CORE IV MOHM

CORE I - CORE V MOHM

CORE II - CORE III MOHM

CORE II - CORE IV MOHM

CORE II - CORE V MOHM

CORE III - CORE IV MOHM

CORE III- CORE V MOHM

CORE IV - CORE V MOHM

XII R -PHASE Y -PHASE B -PHASE

XIII SECONDARY WINDING RESISTANCE (IN OHM)( BY DIGITAL MULTIMETER )

CORE TERMINALFACTORY SITE FACTORY SITE FACTORY SITE

CORE I 1S1 - 1S2 OHM

1S1 - 1S3 OHM

1S1 - 1S4 OHM

CORE II 2S1 - 2S2 OHM

2S1 - 2S3 OHM

2S1 - 2S4 OHM

CORE III 3S1 - 3S2 OHM

3S1 - 3S3 OHM

3S1 - 3S4 OHM

CORE IV 4S1 - 4S2 OHM

4S1 - 4S3 OHM

4S1 - 4S4 OHM

CORE V 5S1 - 5S2 OHM

5S1 - 5S3 OHM

5S1 - 5S4 OHM

FACTORY TEST REPORT REF. NO :

B -PHASEY -PHASER -PHASE

CHECK IR VALUE BETWEEN TAN DELTA POINT AND EARTH AT 1 KV IN SECONDARY BOX

BETWEEN

BETWEEN

PAGE 3 OF 8 CURRENT TRANSFORMER

Page 65: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

XIV POLARITY TEST : WITH 1.5 VOLT DC SUPPLY (CONNECT +VE AT P1 AND - VE AT P2 )

CORE BETWEEN PHASE R -PHASE Y -PHASE B -PHASE

CORE I 1S1 (+VE) 1S2 (-VE)

1S1 (+VE) 1S3 (-VE)

1S1 (+VE) 1S4 (-VE)

CORE II 2S1 (+VE) 2S2 (-VE)

2S1 (+VE) 2S3(-VE)

2S1 (+VE) 2S4 (-VE)

CORE III 3S1 (+VE) 3S2(-VE)

3S1 (+VE) 3S3(-VE)

3S1 (+VE) 3S4(-VE)

CORE IV 4S1 (+VE) 4S2(-VE)

4S1 (+VE) 4S3(-VE)

4S1 (+VE) 4S4(-VE)

CORE V 5S1 (+VE) 5S2(-VE)

5S1 (+VE) 5S3(-VE)

5S1 (+VE) 5S4(-VE)

XV TAN DELTA AND CAPACITANCE MEASUREMENT (BY AUTOMATIC TAN DELTA KIT)

DETAILS OF TEST KIT:

AVOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

BVOLTAGE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KVFACTORY TEST REPORT REF. NO :

XVI CURRENT RATIO TEST

PRIMARY INJECTION THROUGH PRIMARY INJECTION KIT AT PRIMARY TERMINAL P1 - P2MEASURE CURRENT ON THE SECONDARY TERMINALS

DETAILS OF TEST KIT: A R - PHASE

CORE PRIMARY CURRENT SECONDARY THEORET- ACTUAL % OFS1 - S2 % ACTUAL CURRENT ICAL RATIO RATIO ERROR

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

CORE V 20 %

(5S1 - 5S2) 40 %

80 %

CORE I 20 %

(1S1 - 1S3) 40 %

B PHASE

CAPACITANCE ( MEASURED VALUE )

TAN DELTA ( MEASURED VALUE )R PHASE Y PHASE

PAGE 4 OF 8 CURRENT TRANSFORMER

Page 66: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

80 %

CORE II 20 %

(2S1 - 2S3) 40 %

80 %

CORE III 20 %

(3S1 - 3S3) 40 %

80 %

CORE IV 20 %

(4S1 - 4S3) 40 %

80 %

CORE V 20 %

(5S1 - 5S3) 40 %

80 %

CORE I 20 %

(1S1 - 1S4) 40 %

80 %

CORE II 20 %

(2S1 - 2S4) 40 %

80 %

CORE III 20 %

(3S1 - 3S4) 40 %

80 %

CORE IV 20 %

(4S1 - 4S4) 40 %

80 %

CORE V 20 %

(5S1 - 5S4) 40 %

80 %

B Y - PHASE

CORE PRIMARY CURRENT SECONDARY THEORET- ACTUAL % OF

S1 - S2 % ACTUAL CURRENT ICAL RATIO RATIO ERROR

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

CORE V 20 %

(5S1 - 5S2) 40 %

80 %

CORE I 20 %

(1S1 - 1S3) 40 %

80 %

PAGE 5 OF 8 CURRENT TRANSFORMER

Page 67: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

CORE II 20 %

(2S1 - 2S3) 40 %

80 %

CORE III 20 %

(3S1 - 3S3) 40 %

80 %

CORE IV 20 %

(4S1 - 4S3) 40 %

80 %

CORE V 20 %

(5S1 - 5S3) 40 %

80 %

CORE I 20 %

(1S1 - 1S4) 40 %

80 %

CORE II 20 %

(2S1 - 2S4) 40 %

80 %

CORE III 20 %

(3S1 - 3S4) 40 %

80 %

CORE IV 20 %

(4S1 - 4S4) 40 %

80 %

CORE V 20 %

(5S1 - 5S4) 40 %

80 %

C B - PHASECORE PRIMARY CURRENT SECONDARY THEORET- ACTUAL % OFS1 - S2 % ACTUAL CURRENT ICAL RATIO RATIO ERROR

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

CORE V 20 %

(5S1 - 5S2) 40 %

80 %

CORE I 20 %

(1S1 - 1S3) 40 %

80 %

CORE II 20 %

(2S1 - 2S3) 40 %

80 %

CORE III 20 %

PAGE 6 OF 8 CURRENT TRANSFORMER

Page 68: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

(3S1 - 3S3) 40 %

80 %

CORE IV 20 %

(4S1 - 4S3) 40 %

80 %

CORE V 20 %

(5S1 - 5S3) 40 %

80 %

CORE I 20 %

(1S1 - 1S4) 40 %

80 %

CORE II 20 %

(2S1 - 2S4) 40 %

80 %

CORE III 20 %

(3S1 - 3S4) 40 %

80 %

CORE IV 20 %

(4S1 - 4S4) 40 %

80 %

CORE V 20 %

(5S1 - 5S4) 40 %

80 %

NOTE: DURING RATIO TEST OF CT , THE CURRENT LEVEL ATTAINED SHOULD NOT BE LESS THAN 500 A

XVII MAGNETISING CURVES PERFORMANCEKNEE POINT VOLTAGE ( KVp ) _______________ VOLT

DETAILS OF TEST KIT:

A R - PHASE VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - IV CORE - VAPPLIED VALUE 1S1-1S2 2S1 - 2S2 4S1 - 4S2 5S1 - 5S2 mA

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

B Y - PHASE VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - IV CORE - VAPPLIED VALUE 1S1-1S2 2S1 - 2S2 4S1 - 4S2 5S1 - 5S2

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

C B - PHASE VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - IV CORE - VAPPLIED VALUE 1S1-1S2 2S1 - 2S2 4S1 - 4S2 5S1 - 5S2

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

PAGE 7 OF 8 CURRENT TRANSFORMER

Page 69: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CT/01/R-02 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CURRENT TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

NOTE : 1.0 CT SHOULD NOT SATURATE AT 110 % OF KNEEPOINT VOLTAGE ( KVp ) 2.0 IF KNEEPOINT VOLTAGE IS NOT MENTIONED THEN KNEE POINT CURRENT MAY BE TAKEN INTO CONSIDERATION 3.0 MAGNETISATION OF CORE III IS NOT DONE SINCE IT IS USED FOR METERING PURPOSE.

XVIII CONTACT RESISTANCE MEASUREMENT (WHEREVER POSSIBLE/ ACCESIBLE)

DETAILS OF TEST KIT:

R-PHASE Y-PHASE B-PHASE

MICRO OHM

MICRO OHM

NOTE : THE VALUE OF CONTACT RESISTANCE SHOULD NOT BE MORE THAN10 MICRO-OHMS PER JOINT / CONNECTOR

XIX TESTS FOR SF6 FILLED 765 KV CTs

DETAILS OF TEST KIT:

R Y B

XX DGA TEST OF CT OIL (AFTER ONE MONTH OF COMMISSIONING)

TO BE TAKEN IN 250 ml BOTTLES

R PHASE Y PHASE B PHASE

XXI FINAL DOCUMENTATION REVIEW :

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & MPURPOSE YES NO

C AFTER MODIFICATION, IF ANY, " AS BUILT DRAWINGS "ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

DISSOLVE GASES

SF6 LOSS ALARM (KG)SF6 LOCK OUT (KG)

PARTICULARS PHASE

DEW POINT (DEG C)

TOTAL GAS (%)REMARKS

H2CH4C2H4C2H6C2H2COCO2O2N2

CONTACT RESISTANCE

ACROSS TERMINAL P1

ACROSS TERMINAL P2

PAGE 8 OF 8 CURRENT TRANSFORMER

Page 70: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CVT/02/R-2 DATED:01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II DATE OF III DATE OFERECTION : ENERGIZATION :

IV DETAILS OF EQUIPMENT : R-PHASE Y-PHASE B-PHASE

LOA NO :

MAKE :

TYPE :

SL NO. :

YEAR OF :MANUFACTURE

V FEEDER NAME :

VI PRIMARY VOLTAGE : Kv

VII SECONDARY DETAILS :

WINDING 1 WINDING 2 WINDING 3

VOLTAGE : VOLTS

VA BURDEN : VA

CLASS

PURPOSE

VIII DETAILS OF CHECKLIST :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY1 EQUPIMENT IS CLEANED AND FREE FROM

DUST / DIRT FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLE DEFECTS ON PHYSICAL INSPECTION

3 CHECK CVT TANK HAS BEEN PROVIDEDWITH DOUBLE EARTHING

4 CHECK THAT CVT MARSHALLING BOX ISEARTHED

5 ALL NUTS AND BOLTS ARE TIGHTENEDCORRECTLY AS PER SPECIFIED TORQUE

6 CHECK TIGHTNESS OF TERMINAL CONNECTOR

7 ALL FITTINGS AS PER OUT LINE

GENERAL ARRANGEMENT DRAWING.

PAGE 1 OF 5 CAPACITIVE VOLTAGE TRANSFORMER

Page 71: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CVT/02/R-2 DATED:01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES,IF ANY

8 LAVELLING AND IDENTIFICATION MARKINGIS CARRIED OUT

9 LEVELLING AND ALIGNMENT OF STRUCTUREAND BASE FRAME IS CHECKED

10 ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIESREVIEWED

11 ANY PAINT REMOVED / SCRATCHED IN TRANSIT HAS BEEN TOUCHED UP

12 SL. NO OF HV CAPACITOR IDENTICAL TO THESL.NO MENTIONED ON RATING & DIG. PLATE

13 ENSURE BRASS VENT PLUG BETWEENSTACKS OF CVT'S IS REMOVED

14 CHECK THE OIL LEVEL AND LEAKAGE THROUGH ANY JOINTS / SEC. TERMINALS

15 CHECK OIL DRAIN VALVE IS PROPERLYCLOSED AND LOCKED.

16 OIL LEVEL ON TANK GAUGE GLASS

17 BDV OF OIL SAMPLE TAKEN FROM TANKBOTTOM DRAIN VALVE

18 CHECK SECONDARY CABLE END BOX IS PROPERLY FIXED AND ENSURE CABLE ENTRY AT THE BOTTOM.

19 ENSURE H.F TERMINAL OF UNUSED PHASES HAS BEEN EARTHED AND NO LOAD ON H.F TERMINAL BUSHING

20 CHECK RATING / HEALTHINESS OF FUSESAT CVT M.B AND CVT TERMINAL BOX.

21 CHECK THAT THE NEUTRAL POINT IS EARTHED

PAGE 2 OF 5 CAPACITIVE VOLTAGE TRANSFORMER

Page 72: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CVT/02/R-2 DATED:01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY

22 ENSURE INTERPOLE CABLING IS COMPLETEDAND CHECK THE CONTINUTY.

23 CHECK THE IR VALUE OF SECONDARY CABLE( > 50 M OHMS FOR CONTROL CABLES)

24 CHECK EXTERNAL CABLING FROM M.BTO RELAY / CONTROL PANEL COMPLETED

25 ALL THE CABLE IDENTIFICATION TAGSPROVIDED AND ALL CORES ARE PROVIDEDWITH IDENTIFICATION FERRULES AT M.B.

IX CONTINUITY OF WINDING : (After removing Earth Link 1,2 & 3)

A BETWEEN TERMINALS 1a - 1n OK NOT OK

B BETWEEN TERMINALS 2a - 1n OK NOT OK

C BETWEEN TERMINALS 3a - 1n OK NOT OK

X INSULATION RESISTANCE MEASUREMENT :USING A MEGGER OF 5KV/ 10 KV MIN : 1000 M OHMS

BETWEEN MEASURED VALUER-PHASE Y-PHASE B-PHASE

PRIMARY - SECONDARY CORE 1 MOHM

PRIMARY - SECONDARY CORE 2 MOHM

PRIMARY - SECONDARY CORE 3 MOHM

PRIMARY - EARTH MOHM

XI SECONDARY WINDING RESISTANCE IN OHMS

PHASE CORE 1 CORE 2 CORE 3 REMARK

FACTORY SITE FACTORY SITE FACTORY SITE

R

Y

B

FACTORY TEST REPORT REF. NO :

PAGE 3 OF 5 CAPACITIVE VOLTAGE TRANSFORMER

Page 73: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CVT/02/R-2 DATED:01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

XII INSULATION RESISTANCE MEASUREMENT :USING A MEGGER OF 500 VOLT MIN : 50 M OHMS

BETWEEN MEASURED VALUER-PHASE Y-PHASE B-PHASE

SECONDARY CORE 1 - EARTH MOHMSECONDARY CORE 2 - EARTH MOHMSECONDARY CORE 3 - EARTH MOHMCORE 1 - CORE 2 MOHMCORE 1 - CORE 3 MOHMCORE 2 - CORE 3 MOHM

XIII VOLTAGE RATIO TEST

PHASE PRIMARY %VOLTAGE BETWEEN VALUE FACTORY SITE ERROR

R 1a - 1 n

R 2a - 2 n

R 3a - 3 n

Y 1a - 1 n

Y 2a - 2 n

Y 3a - 3 n

B 1a - 1 n

B 2a - 2 n

B 3a - 3 n

NOTE : 1. APPLY VOLTAGE OF THE ORDER OF 500V OR MORE ACROSS LINE CAPACITOR ( TOP FLANGE ) TO EARTH LIN 2. ENSURE ALL EARTH LINKS CONNECTED

XIV ALL TERMINAL BLOCKS CLOSED IN THE SECONDARY AFTER ALL TESTING

XV PHASING ( PHASE RELATIONSHIP ) OF CVT BY MEASURING VOLTAGE BETWEEN R-PHASE,Y-PHASE AND B-PHASE AT INCOMING TERMINAL IN CONTROL CUBICLE,FOR ONECIRCUIT OF THE CHECKED CVT AND OUTPUT TERNINALS R-PHASE, Y-PHASEAND B-PH OF A REFERENCE CIRCUIT (EXISTING CVT) WITH KNOWN PHASING

REFERENCE MEASURED VALUECIRCUIT R-PHASE Y-PHASE B-PHASE

R-PHASE

Y-PHASE

B-PHASE

SECONDARY VOLTAGE ACTUAL RATIOTHEORATICAL RATIO

PAGE 4 OF 5 CAPACITIVE VOLTAGE TRANSFORMER

Page 74: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CVT/02/R-2 DATED:01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF CAPACITOR VOLTAGE TRANSFORMER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

XVI TAN DELTA AND CAPACITANCE MEASUREMENT

DETAILS OF TEST KIT:

ACROSS STACK

R PH Y PH B PH R PH Y PH B PHTOPMIDDLEBOTTOMTOTAL

R PH Y PH B PH R PH Y PH B PHTOPMIDDLEBOTTOMTOTAL

FACTORY TEST REPORT REF. NO :

XVII FINAL DOCUMENTATION REVIEW :

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED

B DOCUMENTS REGARDING SPARES,EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & MPURPOSE

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

PRE COMMISSIONING VALUES

FACTORY VALUESCAPACITANCE TAN DELTA

CAPACITANCE TAN DELTA

PAGE 5 OF 5 CAPACITIVE VOLTAGE TRANSFORMER

Page 75: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II ERECTION START DATE : III ERECTION COMPLETION DATE :

IV DATE OF ENERGIZATION :

V FEEDER NAME :

VI VOLTAGE LEVEL :

VII DETAILS OF EQUIPMENTS INVOLVED :

EQUIPMENT R - PHASE Y - PHASE B - PHASEID NO SL NO ID NO SL NO ID NO SL NO

CT

CVT

LA

BREAKER

TRANSFORMER

REACTOR

ISOLATOR

EARTH

SWITCH

LINE TRAP

MAKE

PAGE 1 OF 9 BAY/ FEEDER

Page 76: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

VIII DETAILS OF CR PANEL AND PLCC

PANEL IDENTIFICATION IDENTIFICATION IDENTIFICATIONDETAILS NAME NUMBER NAME NUMBER NAME NUMBER

CONTROLPANELRELAYPANEL

PLCC PANEL

RTU PANEL

RECORDING IDENTIFICATION INSTRUMENTS NAME NUMBER

FAULT LOCATOR

EVENT LOGGER

DISTURBANCE RECORDER

TIME SYNCRONISATION

STRIP CHART RECORDER

IX PROTOCOL DOCUMENTATION

CT

CVT

LABREAKER

TRANSFORMERREACTORISOLATOR

REMARKSEQUIPMENT IDENTIFICATION NO

ALL PRE-COMM TESTS CARRIED OUT AS PER FQP

YES/ NO

ALL TEST RESULTS ARE WITHIN THE LIMIT OF

TOLERANCE YES/ NO

JOINT PROTOCOLS OF THE EQUIPMENT INVOLVED IN CHARGING ARE DOCUMENTED AND SIGNED BY ALL CONCERNED YES/NO

MAKE

PAGE 2 OF 9 BAY/ FEEDER

Page 77: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

EARTHSWITCH

LINE TRAP

CONTROLPANEL

RELAYPANEL

PLCC

RTUPANEL

EQUIPMENT IDENTIFICATION NO

ALL PRE-COMM TESTS CARRIED OUT AS PER FQP

YES/ NO

ALL TEST RESULTS ARE WITHIN THE LIMIT OF

TOLERANCE YES/ NO

JOINT PROTOCOLS OF THE EQUIPMENT INVOLVED IN CHARGING ARE DOCUMENTED AND SIGNED BY ALL CONCERNED YES/NO

REMARKS

PAGE 3 OF 9 BAY/ FEEDER

Page 78: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

X CHECK OF BAY MARSHALLING KIOSK

DETAILS IDENTIFICATION NUMBER REMARKS , IF ANY

ILLUMINATION AND HEATER OK/NOT OK OK/NOT OK OK/NOT OK 5 /15 AMP SOCKET ALL SPECIFIED FUSES IN POSITION EARTHING AT 2 LOCATION ALL CABLES TIGHTNESS ALL CABLES ARE PROPERLY GLANDED ALL CABLES HAVE IDENTIFICATION NO ALL CORES HAVE IDENTIFICATION NO SHIELDING WIRES ARE EARTHED FREE FROM DUST AND DAMAGE DOOR HINGES AND LOCKING PAINTS UNUSED HOLES ARE SEALED

XI AVAILABILITY OF THE FOLLOWING

DETAILS STATUS REMARKSYES/NO TEMPORARY ARRANGEMENT,IF ANY

1 FIRE FIGHTING SYSTEM COMMISSIONED

A FIRE PROTECTION INCLUDING ALARMS YES/NO

B FIRE HYDRANT SYSTEM YES/NO

C FIRE DELUGE (SPINKLER) SYSTEM YES/NO

2 PORTABLE FIRE EXTINGUSHERS ARE

IN POSITION YES/NO

3 FIRE TENDERS CAN BE MADE AVAILABLE FOR ANY

EVENTUALITY YES/NO TEL NO:

4 ALL EQUIPMENT ERECTION AS PER GENERAL

ARRANGEMENT DRAWING ISSUED BY ENGG. YES / NO

5 EQUIPMENT IDENTIFICATION NAME PLATEARE PROPERLY FIXED YES / NO

6 ALL BUSPOST INSULATORS ARE CLEANED AND

FREE FROM DUST / DIRT FOREIGN MATERIALS ETC. YES / NO

7 ALL EARTHING POINTS HAVE BEEN EARTHED YES / NO

PAGE 4 OF 9 BAY/ FEEDER

Page 79: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

DETAILS STATUS REMARKSYES/NO TEMPORARY ARRANGEMENT,IF ANY

8 ALL NUTS AND BOLTS OF BUS BAR ARE TIGHTENED

CORRECTLY AS PER SPECIFIED TORQUE YES / NO

9 ALL CLAMPS AND CONNECTORS ARE AS PER THE

DRAWINGS ISSUES BY ENGG. DEPT AND

CORRECTLY TIGHTENED AS PER SPECIFIED TORQUE YES / NO

10 ANY PAINT REMOVED / SCRATCHED IN

YARD EQUIPMENTS HAVE BEEN TOUCHED UP YES / NO

11 BAY IDENTIFICATION AND DESIGNATION PLATE

ARE ON POSITION WITH R,Y, B PHASE MARKING YES / NO

12 GRAVEL FILLING IN THE YARD (IF DESIGNED)

HAS BEEN DONE YES / NO

13 THE LADDERS / TOOLS / VEHICLES / WORKBENCH

/ TEMPORARY EARTHING ETC. REMOVED FROM

THE AREA WHICH IS TO BE ENERGIZED YES / NO

14 DC EMERGENCY LIGHT IN OPERATION AND IN AUTO YES / NO

15 DG SET IS AVAILABLE AND IN OPERATION YES / NO

16 SWITCHING SEQUENSES WITH PROCEDURES ARE

DOCUMENTED AND AVAILABLE IN THE CONTROL

ROOM YES / NO

17 REGULAR OPERATION IN THE CONTROL ROOM IS

MANNED ROUND THE CLOCK WITH REGULAR

OPERATION STAFF YES / NO

18 ALL PTW ISSUED EARLIER ARE CANCELLED AND

NOTHING ARE PENDING YES / NO

19 OPERATION DATA LOG SHEETS, PTW AND OTHER

STANDARD FORMATS OF POWERGRID ARE

AVAILABLE FOR REGULAR OPERATION YES / NO

20 YES / NO

21 YES / NO

22 YES / NO

23 YES / NO

24 YES / NO

CHECK THAT TREATED EARTH PITS ARE COVERED AND NUMBERED

CHECK THE TIGHTNESS OF THE CONNECTING LINKS OF TREATED EARTH PITS

CORE WISE SECONDARY INJECTION TEST FOR BOTH CTs AND PTs INPUTS FROM SECONDARY TERMINAL BOX OF CT/ PT DONE TO DETECT ANY MIXING/ INTERCHANGING OF CORES/ PHASES

CHECK STAR POINTS OF CT & CVT SECONDARY AND ASSOCIATED LINKS IF ANY

CONFIRM COLOR CODING OF ALL EQUIPMENTS AND PHASE MARKING

PAGE 5 OF 9 BAY/ FEEDER

Page 80: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

25 YES / NO

26 YES / NO

27 CHARGING CLEARANCE IS RECEIVED FROM GRIDOPERATION CPCC / IOCC / REB VIDE MSG NO : ___________ TIME :___________ DATED

XII MEASUREMENT OF EARTH RESISTANCE HAS BEEN

CARRIED OUT AND THE EARTH RESISTANCE ARE

TABULATED

SL. LOCATION DISTANCE BETWEEN RESISTANCE NO DESCRIPTION ELECTRODE

LOCATION - 1

LOCATION - 2

LOCATION - 3

LOCATION - 4

LOCATION - 5

LOCATION - 6

XIII CONTACT TIGHTNESS CHECK BY PRIMARY CURRENT INJECTION

XIV A MEASUREMENT OF SOIL RESISTIVITY DONE EARLIER PRIOR TO COMMISSIONINGMAY BE TABULATED

DATE : DISTANCE BETWEEN SOIL REMARK ELECTRODE RESISTIVITY

B CHECK THE MINIMUM CLEARANCE BETWEEN LIVE PARTS W.R.T GROUNG AND BETWEEN LIVE PARTS .

VOLTAGE PHASE TO PHASE TO REMARK , IF ANYGROUND PHASE

132 kV 1270 mm 1473 mm

220 kV 2082 mm 2368 mm

400 kV 3065 mm 5750 mm765 KV 6400 mm 9400 mm

NOTE : ALL THE CLEARANCE BETWEEN PHASES & PHASE TO GROUND ARE CHECKED AS PER THE DRGS. ISSUES BY ENGG. DEPT.

NECESSARY CLEARANCES AS APPLICABLE HAVE BEEN OBTAINED

FUSE FAIL PROTECTION CHECKED FOR M1, M2, BACKUP IMPEDANCE ETC

CURRENT INJECTED

CURRENT MEASURED

REMARKS ON CONTACT HEALTHINESS

CURRENT INJECTION AT CURRENT MEASURED AT

PAGE 6 OF 9 BAY/ FEEDER

Page 81: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

XV CHECKING OF INTERLOCKS :

PLEASE REFER THE RELEVENT PLANT CIRCUIT DIADRAM FOR CHECKINGTHE INTERLOCKS OF VARIOUS EQUIPMENTS TO BE ENERGIZED.

ALL ISOLATORS AND GROUND SWITCHESINTERLOCKINGS ARE CHECKED AS PER THE

DOCUMENT NO CF/ISO/08 YES NO PLEASE GIVE REASONS IF NO

IF NOT REPEAT THE TESTING ON INTERLOCKS YES NO

XVI TRIP TESTALL BREAKERS ARE TESTED AND ALL THE TRIPTESTAS PER THE REQUIRED PLANT CIRCUIT DIAGRAMSARE CARRIED OUT AS PER THE DOCUMENT

NO CF/CB/05 YES NO

XVII STABILITY TEST FOR BUSBAR

TO BE DONE IN LINE WITH APPROVED SCHEME

DETAILS OF KIT USED:

CONDITION 1: BUS EARTH SWITCH OPEN

PHASECURRENT

VALUERYBRYBRYB

CONDITION 2: BUS EARTH SWITCH CLOSED

PHASECURRENT

VALUERYBRYBRYB

SPILL CURRENT VALUE REMARKSPRIMARY INJECTION

BETWEEN CTs

SPILL CURRENT VALUE REMARKSPRIMARY INJECTION

BETWEEN CTs

PAGE 7 OF 9 BAY/ FEEDER

Page 82: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

XVIII FINAL TRIP TESTTHE TRIP TEST MUST BE REPEATED PRIOR TO ENERGIZATION AS PER APPROVED SCHEME.

TRIPPING OPERATION TO BE CHECKED FOR BOTH THE TRIP COILS FROM LOCAL/ REMOTE/ PROTECTION

A DC SOURCE 1 OFF

SL. PROTECTION SIMULATION METHOD CB TRIP RESPONCE REMARKNO TYPE MAIN TIE

I MAIN - III MAIN - IIIII OVER VOLTAGEIV CARRIER INTER

TRIPPINGV LBBVI BUS BARVII TEE DIFFERENTIALVIII DIFFERENTIALIX RESTRICTED EARTH

FAULTX BACK UP O/C & E/FXI OVERFLUXINGXII OTI TRIPXIII WTI TRIPXIV BUCHHOLZ TRIP (MAIN )XV BUCHHOLZ TRIP (OLTC)XVI PRD

XVII AUTO-RECLOSE - R ØXVIII AUTO-RECLOSE - Y ØXIX AUTO-RECLOSE - B Ø

B DC SOURCE 2 OFF

SL. PROTECTION SIMULATION METHOD CB TRIP RESPONCE REMARKNO TYPE MAIN TIE

I MAIN - III MAIN - IIIII OVER VOLTAGEIV CARRIER INTER

TRIPPINGV LBBVI BUS BARVII TEE DIFFERENTIALVIII DIFFERENTIALIX RESTRICTED EARTH

FAULTX BACK UP O/C & E/F

PAGE 8 OF 9 BAY/ FEEDER

Page 83: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/BAY/03/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF BAY / FEEDER FEEDER / BAY IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. PROTECTION SIMULATION METHOD CB TRIP RESPONCE REMARKNO TYPE MAIN TIEXI OVERFLUXINGXII OTI TRIPXIII WTI TRIPXIV BUCHHOLZ TRIP (MAIN )XV BUCHHOLZ TRIP (OLTC)XVI PRD

XVII AUTO-RECLOSE - R ØXVIII AUTO-RECLOSE - Y ØXIX AUTO-RECLOSE - B Ø

OPERATIONAL CONSTRAINTS IF ANY

1

2

3

4

5

XIX FINAL DOCUMENTATION REVIEW :

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES,EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & M YES NOPURPOSE

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE YES NO

D THE ABOVE BAY / FEEDER IS CLEARED FOR HIGH VOLTAGE ENERGIZATION YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

PAGE 9 OF 9 BAY/ FEEDER

Page 84: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. MR/CF/SA/04/R-2 DATED: 01/04/08CORPORATE OPERATION SERVICES

PRE-COMMISSIONING OF SURGE ARRESTERCOMMISSIONING FORMATS

I REGION :

II DATE OF III DATE OFERECTION : ENERGISATION :

IV DETAILS OF EQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. : R - PHASE : Y - PHASE : B - PHASE :

YEAR OFMANUFACTURE :

FEEDER NAME :

V RATING :

VOLTAGE RATING :

VI DETAILS : CHECKLIST / TESTING

SL. DESCRIPTION STATUSNO YES NO

1 EQUIPMENT IS FREE FROM DIRT / DUSTFOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLEDEFECTS ON PHYSICAL INSPECTION

3

4 ALL NUTS AND BOLTS ARE TIGHTENEDCORRECTLY AS PER SPECIFIED TORQUE

5 EQUPIMENT ERECTION IS COMPLETE INALL RESPECT(ATTACH REMAINING ACTIVITIES,IF ANY)

6 PERMANENT LA LAVELLING ANDIDENTIFICATION IS DONE

SUB STATION : BAY NO : EQUIPMENT IDENTIFICATION NO : DATE OF TESTING :

REMARK RECORD DEFICIENCIES, IF ANY

SUPPORT STRUCTURES HAVE BEEN PROVIDED WITH DOUBLE EARTH

1 OF 3 SURGE ARRESTOR

Page 85: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. MR/CF/SA/04/R-2 DATED: 01/04/08CORPORATE OPERATION SERVICES

PRE-COMMISSIONING OF SURGE ARRESTERCOMMISSIONING FORMATS

SUB STATION : BAY NO : EQUIPMENT IDENTIFICATION NO : DATE OF TESTING :

SL. DESCRIPTION STATUSNO YES NO7 LEVELLING AND ALIGNMENT OF STRUCTURE

AND BASE FRAME IS CHECKED

8 ALL INSULATORS & SURGE COUNTER AREFREE FROM ANY PHYSICAL DEFECTS

9 TIGHTNESS OF NUTS BOLTS OF TERMINALCONNECTORS ARE CHECKED

10 ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIESREVIEWED

11 CHECK ONE END OF SURGE COUNTER IS CONNECTED TO THE BOTTOM OF LA STACK ANDONE END OF SURGE COUNTER HAS BEEN EART

12 THE DIRECTION OF THE EXHAUST VENT PORTSAWAY FROM THE PROTECTED EQUIPMENT ANDOTHER ARRESTER POLES

13 CREARANCE FROM THE ARRESTER TO EARTHEDOBJECTS AND FROM THE ARRESTER POLE TOANOTHER ARRESTER POLE MAINTAINED AS PEROUTLINE DRAWING AND ALL ERECTION HAS BEEN DONE AS PER DRAWING ISSUED BY ENGG. DEPT.

14

15

16

17

VII INSULATION RESISTANCE MEASUREMENT : ( USING 5KV MEGGER)

SL. NO BETWEEN PHASE MIN VALUE > 1000 M OHMSR-PHASE Y-PHASE B-PHASE

1 1ST STACK & EARTH MOHM

2 2ND STACK & EARTH MOHM

3 3RD STACK & EARTH MOHM

4 4TH STACK & EARTH MOHM

5 5TH STACK & EARTH MOHM

6 6TH STACK & EARTH MOHM

OPERATION OF LA COUNTER CHECKED BY APPLYING APPROPRIATE VOLTAGE

CHECK THE SERIAL NO. AND SEQUENCE OF LA PARTS FOR ERECTION IN MULTI STACK LA

RECORD DEFICIENCIES, IF ANYREMARK

CHECK THE ALIGNMENT OF CORONA RING

CHECK ON CHARGING, THE SURGE COUNTER POINTER IS IN GREEN ZONE

2 OF 3 SURGE ARRESTOR

Page 86: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. MR/CF/SA/04/R-2 DATED: 01/04/08CORPORATE OPERATION SERVICES

PRE-COMMISSIONING OF SURGE ARRESTERCOMMISSIONING FORMATS

SUB STATION : BAY NO : EQUIPMENT IDENTIFICATION NO : DATE OF TESTING :

VIII SURGE COUNTER READING

SL. NO READING PHASER-PHASE Y-PHASE B-PHASE

1 COUNTER SR. NO.

2 COUNTER MAKE3 COUNTER READING

IX CAPACITANCE & TAN DELTA MEASUREMENT

X CHECKING OF HEALTHINESS OF SURGE MONITOR : OKREFER MANUFACTURER'S CATALOGUE FOR DETAIL CHECKING OF SURGE MONITOR

XI THIRD HARMONIC RESISTIVE CURRENT MEASUREMENT

AMBIENT TEMPERATURE :SYSTEM VOLTAGE :

PH TOTAL CURRENT

RYB

XII

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & MPURPOSE YES NO

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

MIDDLE 1

FINAL DOCUMENTATION REVIEW

3RD HARMONIC RESISTIVE CURRENT (I3 R) in µ A

REMARKS

TOP

TAN DELTA

THE VALUE OF THIRD HARMONIC CURRENT AFTER COMPENSATION SHALL BE LESS THAN 30 µA. IN CASE OF DISCREPANCY, TEST RESULTS TO BE FORWARDED TO CC/OS.

REMARKS

BOTTOMMIDDLE 2

NOT OK

CAPACITANCESTACK

3 OF 3 SURGE ARRESTOR

Page 87: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II DATE OF III DATE OFERECTION : ENERGIZATION :

IV DETAILS OFEQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. :

YEAR OF MANUFACTURE :

FEEDER NAME :

OPERATING VOLTAGE : kV

RATED BREAKING CAPACITY : kA

CONTROL VOLTAGE : VOLT DC

V DETAIL CHECKLIST :

SL. DESCRIPTION STATUS REMARKNO YES NO1 EQUIPMENT IS FREE FROM DIRT/DUST

FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLEDEFECTS ON PHYSICAL INSPECTION

3 SUPPORT STRUCTURES, MARSHALLING BOXHAS BEEN PROVIDED WITH DOUBLE EARTH

4 ALL NUTS AND BOLTS ARE TIGHTENEDCORRECTLY AS PER SPECIFIED TORQUE

5

(ATTACH REMAINING ACTIVITIES,IF ANY)

6 PERMANENT POLE LAVELLING ANDIDENTIFICATION IS DONE

RECORD DEFICIENCIES, IF ANY

EQUPIMENT ERECTION IS COMPLETE IN ALL RESPECT & ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIES REVIEWED

PAGE 1 OF 14 CIRCUIT BREAKER

Page 88: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY7 LEVELLING AND ALIGNMENT OF STRUCTURE

AND BASE FRAME IS CHECKED

8 CONTROL BOX / MARSHALLING KIOSK ISFREE FROM ANY PHYSICAL DEFECTS

9 TIGHTNESS OF NUTS BOLTS OF TERMINALCONNECTORS ARE CHECKED

10 i) AUXILLARY CONTACTS AND RELAYS HAVEBEEN CLEANED AND FREE FROM RUST /DAMAGE

iii) CHECK ALL THE VALVES IN THE SF6 PIPELINE ARE TIGHTENED, DILO COUPLINGARE TIGHTENED.

11 SLOW AND POWER CLOSING OPERATION AND OPENING DONE YES NO (WHEREVER APPLICABLE)

(OPENING)12 OPERATING SYSTEM : HYDRAULIC : HYDRAULIC

(CLOSING) PNEUMATIC: PNEUMATIC SPRING : SPRING OTHERS : OTHERS

12.1 HYDRAULIC SYSTEMR PHASE Y PHASE B PHASE

12.1.1 ACCUMULATOR MAKE

SL NO

TYPE

YR. OF MANUFACTURE

12.1.2 PUMP DETAILS MAKE : VOLT

SL NO : AMPERES

TYPE : HP/KW

YEAR OF : O/L SETTING

MANUFACTURE (THERMAL OVERLOAD)

ii) ALL SPARE WIRES TO BE KEPT WITH FERRULES BUT NOT TERMINATED AT THE TERMINAL BLOCKS

PAGE 2 OF 14 CIRCUIT BREAKER

Page 89: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

12.1.3 DETAILS OF RELAYS/CONTACTORS USED : SCHEMATIC DRAWING NO :

MAKE SERIAL NO. TYPE NO+NCOIL PRESSURE MONITOR

CLOSING LOCKOUT

AUTO RECLOSING LOCKOUT

GENERAL LOCKOUT

ANTI PUMPING CONTACTOR

POLE DESCREPANCY TIMER

AUXILLARY

POWER CONTACTOR

OTHERS

12.1.4 OPERATION CHECKS :

DATE OF FILLING HYDRAULIC OILTYPE OF HYDRAULIC OIL

AERO SHELL FLUID 4

OTHER (TYPE :__________)VENTING OF HYDRAULIC SYSTEM IS DONE

(i) PUMP(ii) PILOT VALVE(iii) ACCUMULATOR(iv) HYDRAULIC MECHANISM

PRESSURISING HYDRAULIC SYSTEMFACTORY TEST SITE TEST

VALUE VALUEPRE-FILLING PRESSURE OF N2IN ACCUMULATOR ( BAR / BAR AT BAR AT

DEG. C)DEG. C DEG. C

PUMP RUNNING TIME FOR CHARGINGHYDRAULIC SYSTEM FROM INITIAL PRESSURE

TO WORKING PRESSURE MIN

CHECKING SAFETY VALVE (OPEN/CLOSE) BAR /

HYDRAULIC PRESSURE DROP FOR 1 HR

BREAKER ON POSITION BAR

BREAKER OFF POSITION BAR

CIRCUIT REFERENCE

PAGE 3 OF 14 CIRCUIT BREAKER

Page 90: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

FACTORY TEST SITE TESTVALUE VALUE

OIL PRESSURE MONITORPUMP ON / OFF BAR BARPUMP RUNNING TIME SEC

AUTO RECLOSING LOCKOUT (OIL)PRESSURE CONTACT __________MAKE/BREAK BAR

CLOSING LOCKOUT (OIL)PRESSURE CONTACT __________MAKE/BREAK BAR

GENERAL LOCKOUT (OIL)PRESSURE CONTACT __________MAKE/BREAK BAR

CHECKING ANTI PUMPING CONTACTORPRESSURE CONTACT __________MAKE/BREAK OK/NOTOK

CHECKING LOSS OF NITROGENPRESSURE CONTACT __________MAKE/BREAK OK/NOTOK

FACTORY TEST REPORT REF NO:

12.1.5 OIL PRESSURE DROP DURING OPERATIONS AND PUMPRUNNING TIME IN SECONDS FACTORY TEST SITE TEST

VALUE VALUE(i) PRESSURE BEFORE OPERATION BAR

PRESSURE AFTER CLOSING OPERATION BAR

PUMP RUNNING TIME SEC

(ii) PRESSURE BEFORE OPERATION BAR

PRESSURE AFTER OPENING OPERATION BAR

PUMP RUNNING TIME SEC

(iii) PRESSURE BEFORE OPERATION BAR

PRESSURE AFTER CLOSE/OPEN OPERATION BAR

PUMP RUNNING TIME SEC

(iv) PRESSURE BEFORE OPERATION BAR

PRESSURE AFTER OPEN-CLOSE-OPEN OPER. BAR

PUMP RUNNING TIME SEC

FACTORY TEST REPORT REF NO:

PAGE 4 OF 14 CIRCUIT BREAKER

Page 91: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

12.2 PNEUMATIC SYSTEM

12.2.1 OPERATING SYSTEM DETAILS

R PHASE Y PHASE B PHASE

AIR RECEIVER NO :

CONTROL BLOCK NO :

PNEUMATIC DRIVE NO :

MAGNETIC VENTIL NO :

12.2.2 MOTOR DETAILS MAKE : VOLT

SL NO : AMPERES

TYPE : HP/KW

YEAR OF : SETTING AMPMANUFACTURE (THERMAL OVERLOAD)

12.2.3 ICU DETAILS MAKE :

SL NO :

TYPE :

DISCHARGE :

CAPACITY :

YEAR OF :MANUFACTURE

12.2.4 DETAILS OF RELAYS/ CONTACTORS USED : SCHEMATIC DRAWING NO :

CIRCUIT REFERENCE MAKE SERIAL NO. TYPE NO+NC

AIR PRESSURE MONITOR

CLOSING LOCKOUT

AUTO RECLOSING LOCKOUT

GENERAL LOCKOUT

POLE DESCREPANCY TIMER

AUXILLARY

POWER CONTACTOR IN ICU

OTHERS

PAGE 5 OF 14 CIRCUIT BREAKER

Page 92: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

12.2.5 PRESSURE SWITCH SETTING

MAKE REMARKS

BLOCK DEBLOCK BLOCK DEBLOCK

AUTO RECLOSING CKTLOW/HIGH PRESSURE ALARM CIRCUIT

ICU AUTO SETTINGICU SAFETY VALVEOPERATIONS

FACTORY TEST REPORT REF NO :

12.2.6 PRESSURE DROP DURING OPERATION : ( IN KG/SQ.CM -BAR )

SL NO DESCRIPTION FACTORY SETTING SITE SETTING VALUE VALUE

A TRIPPING THROUGH TC - I

B TRIPPING THROUGH TC - II

C CLOSING CIRCUIT

D CLOSE-OPEN OPERATION

E OPEN - CLOSE - OPEN

FACTORY TEST REPORT REF NO :

12.2.7 NUMBER OF OPERATION FROM LOCAL.TANK PRESSURE ___________ KG/SQ.CM OR BAR

BREAKER INITIALLY CLOSE :

FACTORY TEST : O-C- | PLEASE KEEP INLET PNEUMATIC VALVE

SITE TEST : O-C- | CLOSED IN THESE OPERATION

BREAKER INITIALLY OPEN :

FACTORY TEST : C-O- | PLEASE KEEP INLET PNEUMATIC VALVE

SITE TEST : C-O- | CLOSED IN THESE OPERATION

12.2.8 LEAKAGE CHECK :AIR PRESSURE DROP IN 24 HRS :

BREAKER ON DROP IN PRESSURE : KG/SQ.CM OR BAR

BREAKER OFF DROP IN PRESSURE : KG/SQ.CM OR BAR

OPERATION LOCKOUT -1

OPERATION LOCKOUT -2

CLOSING LOCKOUT

SITE SETTING VALUE CIRCUIT REFERENCE

FACTORY SETTING VALUE

PAGE 6 OF 14 CIRCUIT BREAKER

Page 93: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

12.3 SPRING OPERATING SYSTEM

12.3.1 MOTOR DETAILS MAKE : VOLT

SL NO : AMPERES

TYPE : HP/KW

YEAR OF : SETTINGMANUFACTURE (THERMAL OVERLOAD)

DC CURRENT TAKEN BY MOTOR FOR CHARGING THE SPRING

12.3.2 DETAILS OF RELAYS/CONTACTORS USED : SCHEMATIC DRAWING NO :

CIRCUIT REFERENCE MAKE SERIAL NO. TYPE NO+NC

CLOSING LOCKOUT

AUTO RECLOSING LOCKOUT

GENERAL LOCKOUT

POLE DESCREPANCY TIMER

AUXILLARY

POWER CONTACTOR

OTHERS

12.3.3 SPRING OPERATING TIME :

TIME TAKEN BY THE SPRING TO CHARGE FULLY AFTER CLOSING OF BREAKER.

DETAILS R-PHASE Y-PHASE B-PHASEFACTORY SITE FACTORY SITE FACTORY SITE

CHARGING TIME

FACTORY TEST REPORT REF NO :

13.0 SF6 DENSITY MONITOR DETAILSR-PHASE Y-PHASE B-PHASE

MAKE : QUANTITY OF SF6 GAS FILLED

MODEL : ACTUAL AS PER SPEC

SL.NO : R:

YEAR OF : Y:MANUFACTURE B:

13.1 SF6 DENSITY MONITOR SETTINGS

PHASE DETAILS BLOCKING DEBLOCKING SF6 GAS FILLED ATFACTORY SITE FACTORY SITE ________ BAR ____

R - PHASE REFILL ALARM AT _____ DEG. C ON

OPERATION BLOCK ___/___/___

Y - PHASE REFILL ALARM

OPERATION BLOCK

B - PHASE REFILL ALARM

OPERATION BLOCK

FACTORY TEST REPORT REF NO :

____________AMP

PAGE 7 OF 14 CIRCUIT BREAKER

Page 94: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

13.2 MEASUREMENT OF DEW POINT OF SF6 GAS :

SL. NO DESCRIPTION

NOTE: DEW POINT MEASUREMENT OF SF6 GAS NEEDS TO BE DONE POLE WISE IN CLOSE LOOP METHOD WITHOUT ANY WASTAGE OF SF6 GAS

13.3 LEAKAGE CHECK :

A INITIAL FILLING OF SF6 GAS AT ____DEG C : BAR

(AS PER TEMP. CORRECTION CHART )

B DROP IN SF6 GAS PRESSURE IN 24 HRS : BAR

C FINAL SF6 PRESSURE AT ________DEG. C BARAFTER ALL TESTING

D ADDITIONAL LEAKAGE TEST BY COVERING YES NOINDIVIDUAL JOINT WITH POLYTHENE

14.0 COIL RESISTANCE MEASUREMENT :

SL NO PHASE COIL MEASURED SERIES TOTALVALUE RESISTOR

TRIP COIL - I OHMS

A R TRIP COIL - II OHMS

CLOSE COIL OHMS

TRIP COIL - I OHMS

B Y TRIP COIL - II OHMS

CLOSE COIL OHMS

TRIP COIL - I OHMS

C B TRIP COIL - II OHMS

CLOSE COIL OHMS

MEASURED VALUEMIN. VALUE OF DEW POINT TO BE AS PER DOC. NO. D-5-02-XX-01-03 ANNEXURE-1

PAGE 8 OF 14 CIRCUIT BREAKER

Page 95: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

15.0 CIRCUITARY / OPEARTIONAL CHECKS :

SL NO CIRCUIT REFERENCE CIRCUITARY CHECK OPERATIONAL CHECKLOCAL REMOTE LOCAL REMOTE

A TRIPPING THROUGH TC-IB TRIPPING THROUGH TC-IIC CLOSING CIRCUITD ANTI-HUNTING FEATURE

(CLOSE OPEN OPERATION )E POLE DISCREPANCY FEATUREF BREAKER POSITION INDICATION G HEATER IN SWITCH CUBICLEH HEATER IN CONTROL CUBICLEI ILLUM. IN SWITCH CUBICLEJ ILLUM. IN CONTROL CUBICLE

NOTE : IN CASE WIRING FOR REMOTE OPERATION IS NOT READY, PLEASE INDICATETERMINAL NUMBER ALONG WITH WIRE FERRULE NUMBER IN SWITCH CUBICLE WHEREREMOTE CABLES SHALL BE TERMINATED. REMOTE OPERATION CAN BE CHECKED FROMTHESE TERMINALS.

16.0 OPERATING TIME ( IN MILLI-SECONDS )

PHASE BREAK CLOSE T R I PTRIP - I TRIP -II TRIP - I TRIP - II

R - PH MAIN CONTACT BREAK 1

R - PH PIR

AUXILIARY CONTACT

R - PH MAIN CONTACT BREAK 2

R - PH PIR

AUXILIARY CONTACT

Y - PH MAIN CONTACT BREAK 1

Y - PH PIR

AUXILIARY CONTACT

Y - PH MAIN CONTACT BREAK 2

Y - PH PIR

AUXILIARY CONTACT

B - PH MAIN CONTACT BREAK 1

B - PH PIR

AUXILIARY CONTACT

B - PH MAIN CONTACT

B - PH PIRAUXILIARY CONTACTNOTE: FOR 765 KV, TAKE MEASUREMENTS FOR FOUR BREAKS

CLOSE TRIP USING

BREAK 2

PAGE 9 OF 14 CIRCUIT BREAKER

Page 96: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

17.0 IR VALUE OF CONTROL CIRCUIT :USING 500 VOLT MEGGERMINIMUM VALUE 2 MOHM

CAUTION : ISOLATE NECESSARY DC FOR TRIP COIL I AND TRIP COIL II ,CLOSINGCOIL BEFORE MEGGARING.

COIL DETAILS MEASUREMENT VALUER - PHASE TRIP COIL - I MOHM

R - PHASE TRIP COIL - II MOHM

R - PHASE CLOSE COIL MOHM

Y - PHASE TRIP COIL - I MOHM

Y - PHASE TRIP COIL - II MOHM

Y - PHASE CLOSE COIL MOHM

B - PHASE TRIP COIL - I MOHM

B - PHASE TRIP COIL - II MOHM

B - PHASE CLOSE COIL MOHM

18.0 IR VALUE WITH BREAKER OPEN :USING 5000 VOLT MEGGERMINIMUM VALUE 1000 MOHM MEASUREMENT VALUE

MOHM

MOHM

MOHM

MOHM

MOHM

MOHM

19.0 IR VALUE WITH RESPECT TO EARTH WITH BREAKERCLOSED, EARTH SWITCH AND ISOLATOR OPEN :USING 5000 VOLT MEGGER MINIMUM VALUE 1000 MOHM

BETWEEN

R - PHASE AND EARTH MOHM

Y - PHASE AND EARTH MOHM

B - PHASE AND EARTH MOHM

MEASUREMENT VALUE

Y - PHASE BREAK-2

R - PHASE BREAK-2

R - PHASE BREAK 1

Y - PHASE BREAK 1

B - PHASE BREAK-2

B - PHASE BREAK 1

ACROSS OPEN CONTACT

PAGE 10 OF 14 CIRCUIT BREAKER

Page 97: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

20.0 MINIMUM PICKUP VOLTAGE OF COILS

COIL DETAILSR - PHASE TRIP COIL - I VR - PHASE TRIP COIL - II VR - PHASE CLOSE COIL VY - PHASE TRIP COIL - I VY - PHASE TRIP COIL - II VY - PHASE CLOSE COIL VB - PHASE TRIP COIL - I VB - PHASE TRIP COIL - II VB - PHASE CLOSE COIL V

21.0 GRADING CAPACITOR :

21.1 DETAILS : DETAILS INTERRUPTER 1 INTERRUPTER 2

R Y B R Y BMAKE

SERIAL NO.

CAPACITANCE VALUE

FACTORY VALUE

YEAR OF MANUFAC.

21.2 CAPACITANCE AND TAN DELTA MEASUREMENT :

TO BE DONE IN UST MODE DESCRIPTION INTERRUPTER 1 INTERRUPTER 2

R Y B R Y BCAPACITANCE - SITE

- FACTORY

TAN DELTA - SITE

- FACTORY

FACTORY TEST REPORT REF NO :

22 CONTACT RESISTANCE MEASUREMENT :

SL.NO PHASE ACROSS EACH POLE ACROSS INTERRUPTR 1 ACROSS INTERRUPTR 2FACTORY SITE FACTORY SITE FACTORY SITE

A R-PHASE

B Y-PHASE

C B-PHASE

FACTORY TEST REPORT REF NO :

MEASUREMENT VALUE

PAGE 11 OF 14 CIRCUIT BREAKER

Page 98: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

23 BREAKER OPERATION COUNTER READING :

COUNTER TYPE : SL.NO PHASE READING DATE

ELECTRICAL : A R-PHASE

MECHANICAL : B Y-PHASE

C B-PHASE

24 CHECK FOR ANNUNCIATION IN CONTROL ROOM AS PER THEFOLLOWING FORMATS AND RECORD THE READING :

SL DESCRIPTION SOURCE OF WINDOW RESULT REMARKNO OF TEST INITIATION DESCRIPTION OK/NOTOKA SWITCH OFF THE DC CONTROL CUBICLE DC SOURCE I/II DC

SWITCH IN CONTROL SWITCH ON/OFF FAIL / AC FAILCUBICLE

B SWITCH OFF THE AC CONTROL CUBICLE AC SOURCE I/II DCSWITCH IN CONTROL SWITCH ON/OFF FAIL / AC FAILCUBICLE

C SHORT THE ALARM DENSITY MONITOR SF6 GAS DENSITYCONTACTS OF SF6 LOWGAS DENSITYMONITOR (R-PHASE)

D SHORT THE ALARM DENSITY MONITOR SF6 GAS DENSITYCONTACTS OF SF6 LOWGAS DENSITYMONITOR (Y-PHASE)

E SHORT THE ALARM DENSITY MONITOR SF6 GAS DENSITYCONTACTS OF SF6 LOWGAS DENSITYMONITOR (B-PHASE)

F REMOVE THE CABLE DENSITY MONITOR OPERATION/CLOSINGCONNECTED TO LOCKOUTDENSITY MONITOR(R-PHASE)

G REMOVE THE CABLE DENSITY MONITOR OPERATION/CLOSINGCONNECTED TO LOCKOUTDENSITY MONITOR(Y-PHASE)

H REMOVE THE CABLE DENSITY MONITOR OPERATION/CLOSINGCONNECTED TO LOCKOUTDENSITY MONITOR(B-PHASE)

PAGE 12 OF 14 CIRCUIT BREAKER

Page 99: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION SOURCE OF WINDOW RESULT REMARKNO OF TEST INITIATION DESCRIPTION OK/NOTOK

I GIVE TRIPPING POLE DESCRIPANCY BREAKER POLECOMMAND TO R-PH RELAY AT BREAKER DESCRIPANCYONLY AND CHECK THE CUBICLEOPERATION OF POLEDISCRIPANCY RELAY

J GIVE TRIPPING POLE DESCRIPANCY BREAKER POLECOMMAND TO Y-PH RELAY AT BREAKER DESCRIPANCYONLY AND CHECK THE CUBICLEOPERATION OF POLEDISCRIPANCY RELAY

K GIVE TRIPPING POLE DESCRIPANCY BREAKER POLECOMMAND TO B-PH RELAY AT BREAKER DESCRIPANCYONLY AND CHECK THE CUBICLEOPERATION OF POLEDISCRIPANCY RELAY

L CHECK OTHER ALARMSAS PER PLANTCIRCUIT DIAGRAM

M CLOSE THE BREAKER PROTECTION RELAY BREAKER AUTO TRIPAND TRIP THROUGH AS PER SCHEMEPROTECTION WHICHARE APPLICABLE

NOTE : THE TRIPPING DETAILS ARE TO BE CHECKED AS PER THE SCHEME APPROVED BY ENGINEERING.

PAGE 13 OF 14 CIRCUIT BREAKER

Page 100: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/CB/05/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :

BAY NO :PRE-COMMISSIONING OF SF6 CIRCUIT BREAKER EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

25.0 DYNAMIC CONTACT RESISTANCE & TRAVEL MEASUREMENT

PHASE FACTORY

RYB

26.0

27.0 MECHANICAL CLOSE INTERLOCK CHECKED (WHEREVER APPLICABLE) YES NO

28.0

a FACTORY TEST RESULTS ARE AVAILABLE YES NO

b FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

c DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & MPURPOSE YES NO

d AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE YES NO

e CC-OS APPROVED DCRM SIGNATURES AVAILABLE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

APPROVAL FROM CC/OS OBTAINEDSITE REMARKS

FINAL DOCUMENTATION REVIEW

OPERATION TIME MEASUREMENT OF POLE DISCREPANCY RELAY

PAGE 14 OF 14 CIRCUIT BREAKER

Page 101: 71281912 Pgcil Latest Testing Format

1 REGION :

2 DATE OFRECEIPT AT SITE :

3

ERECTION & OIL FILLING :

4 DATE OFENERGISATION :

5 DETAILS OF EQUIPMENT

a LOA NO :

b MAKE :

c TYPE :

d RATING :

e SL NO. :

f VOLTAGE RATIO :

g COOLING TYPE :

h :

i :

j OIL QUANTITY :

Quantity of Main Tank: :Quantity of Radiator :

k OIL MAKE & TYPE :Specify oil type Inhibited/ Uninhibited/ Standard

DATE OF TESTING :

YEAR OF MANUFACTURE

TRANSFORMERS

TYPE OF NEUTRAL GROUNDING

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

DATE OF COMPLETION OF

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

GENERAL INFORMATION

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

Page 1 of 25 TRANSFORMER

Page 102: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

1

S.N

a

b

c

d

e

f

g

h

i

j

k

l

m

n

o

p

q

r

s

t

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :

NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

CONTINUITY TEST OF BUSHING CTs

POLARITY TEST OF BUSHING CTs

VECTOR GROUP TEST & POLARITY CHECK

NAME OF TEST

MEASUREMENT OF WINDING RESISTANCE

SECONDARY WINDING RESISTANCE OF BUSHING CTs

TAN DELTA & CAPACITANCE MEASUREMENT OF BUSHING

PROTECTION AND ALARM TESTS

PERFORMED (YES/NO)

CURRENT RATIO TEST

TEST RESULTS (OK/ NOT OK)

MAGNETIC BALANCE TEST

INSULATION RESISTANCE MEASUREMENTS OF BUSHING CTs

VOLTAGE RATIO TEST

INSULATION RESISTANCE MEASUREMENT

MAGNETISING CURVES PERFORMANCE

FREQUENCY RESPONSE ANALYSIS

STABILITY TEST OF DIFFERENTIAL AND REF PROTECTION

MAGNETISATION CURRENT TEST

FLOATING NEUTRAL VOLTAGE MEASUREMENT

SHORT CIRCUIT IMPEDANCE TEST

CHECK LIST OF ELECTRICAL TESTS CARRIED OUT FOR TRANSFORMER

TAN DELTA & CAPACITANCE MEASUREMENT OF WINDINGS

CONTACT RESISTANCE MEASUREMENT

Page 2 of 25 TRANSFORMER

Page 103: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

2

a

b

YES NO

Note: Impact Recorder should be detached from the Transformer/ Reactor preferably when the main unit has been placed on its foundation.

c

APPLY 1.0 KV DC BETWEEN CL & CC+G

( RECOMMENDED VALUE > 10 M Ohms)'

3

a ACTIVE PART OF TRANSFORMER SHOULD MINIMUM EXPOSED TO ATMOSPHERE

b DURING EXPOSURE OF ACTIVE PART OF TRANSFORMER TO ATMOSPHERE :

YES NO

DRY AIR GENERATOR/ DRY AIR CYLINDERS USED :

c

YES NO

d

BETWEEN CL-G

BETWEEN CC-CL

* Please write 'NIL' in case of No Remarks

AMBIENT TEMP.

IMPACT RECORER ANALYSIS

Remarks*

REMARKS

CORE INSULATION CHECK

WHILE ENTERING IN TRANSFORMER TANK, CHECK AVAILABILITY OF PROPER OXYGEN

TRANSFORMER KEPT SEALED WITH N2 IN BETWEEN DIFFERENT ERECTION ACTIVITIES

REMARKS

NO

CHECKS/ PRECAUTIONS DURING ERECTION

INSULATION VALUE

Note: SHORTING LINK BETWEEN CC, CL & G TO BE REMOVED AND IR VALUE TO BE TAKEN BETWEEN CC-G, CL-G & CC-CL

BETWEEN CC-G

RECEIVED IN HEALTHY CONDITION AT SITE

ANALYSIS REPORT RECEIVED FROM MANUFACTURER BEFORE CHARGING

YES

STATUS

N2 PRESSURE & DEW POINT RECORD

DURING DISPATCH AT FACTORY

AFTER RECEIPT AT SITE

N2 PRESSURE DEW POINT

DURING STORAGE AT SITE BEFORE COMM.

BRIEF ANALYSIS

NOTE: N2 PRESSURE AND DEW POINT SHOULD BE WITHIN PERMISSIBLE RANGE AS PER GRAPH PROVIDED BY MANUFACTURER AND ALSO GIVEN IN OS DOC NO D-2-03-XX-01-01 REV-01. DURING STORAGE AT SITE, DEW POINT HAS TO BE MEASURED WHENEVER ANY DROP IN N2 PRESSURE IS OBSERVED. DURING STORAGE AT SITE BEFORE COMMISSIONING, N2 PRESSURE HAS TO BE MEASURED DAILY AND RECORD TO BE MAINTAINED IN A SEPARATE SHEET.

CHECKS AFTER RECEIPT OF TRANSFORMER AT SITE:

Page 3 of 25 TRANSFORMER

Page 104: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

4

DETAILS :

SL.

NO YES NO

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

PRE-COMMISSIONING CHECKS:

ANY PAINT REMOVED / SCRATCHED IN TRANSIT HAS BEEN TOUCHED UP

CHECK MAIN TANK HAS BEEN PROVIDED WITH DOUBLE EARTHING

REMARK

RECORD DEFICIENCIES, IF ANY

STATUS

ICT AND ITS AUXILIARIES ARE FREE FROM VISIBLE DEFECTS ON PHYSICAL INSPECTION

DESCRIPTION

CHECK THAT MASHALLING BOX, T/C DRIVING GEAR, DIVERTER, RADIATOR BANK PUMP & FAN MOTOR ETC HAS BEEN EARTHED

1

CHECK NEUTRAL IS GROUNDED THROUGH SEPARATE CONNECTIONS. ENSURE METALLIC REQUIREMENTS AS PER SPECIFICATION (e.g. Cu) IN EARTHING STRIPS USED

ALL FITTINGS AS PER OUT LINE GENERAL ARRANGEMENT DRAWING .

ALL NUTS AND BOLTS ARE TIGHTENED CORRECTLY AS PER SPECIFIED TORQUE (AS PER MANUFACTURERS RECOMMENDATION)

CHECK OIL DRAIN VALVES ARE PROPERLY CLOSED AND LOCKED.

ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIES REVIEWED

CHECK TIGHTNESS OF TERMINAL CONNECTORS

CHECK LEVELLING OF TRANSFORMER AND ITS ACCESSORIES

OIL LEVEL IS CORRECT ON ALL BUSHINGS

BUSHINGS ARE CLEAN AND FREE FROM PHYSICAL DAMAGES

CHECK HERMETICALLLY SEALING IS INTACT IN ALL BUSHINGS

CHECK OIL LEAKAGE THROUGH ANY JOINTS / VALVES ETC.

CHECK OIL LEVEL IN MAIN / OLTC CONSERVATOR TANK

Page 4 of 25 TRANSFORMER

Page 105: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

CKECK ALL VALVES FOR THEIR OPENING & CLOSING SEQUENCE

CHECK CABLES ARE PROPERLY FIXED AND ENSURE CABLE ENTRY AT THE BOTTOM.

ENSURE ALL POWER AND CONTROL CABLE TERMINALS ARE TIGHTENED

CHECK OIL LEVEL AT CONSERVATOR MATCHES WITH OIL TEMPERATURE OF TRANSFORMER

CHECK THAT LABELLING AND IDENTIFICATION IS PERMANENT AND SATISFACTORY

CHECK OTI AND WTI POCKETS AND REPLENISH THE OIL , IF REQUIRED

CHECK THAT BUCHHOLZ RELAY IS CORRECLY MOUNTED WITH ARROW POINTING TOWARDS CONSERVATOR

CHECK GEAR BOX OIL LEVEL IN OLTC

CHECK AVAILABILITY OF OIL IN THE BREATHER CUP

CHECK ALL ROLLERS ARE LOCKED AND TACK WELDED WITH RAILS ( WHEREEVER APPLICABLE )

CHECK DOOR SEALS OF MARSHALLING BOX IS INTACT AND ALL CABLE GLAND PLATES UNUSED HOLES ARE SEALED

CHECK STAR POINT HAS BEEN FORMED PROPERLY AND GROUNDED AT ONE END ONLY AS PER SCHEME

CHECK BUSHING TEST TAP IS GROUNDED

CHECK NO DEBRIS , LOOSE T & P AND OIL STRAINS ON AND AROUND THE TRANSFORMER

ENSURE UNUSED SECONDARY CORES OF BUSHING CT's, IF ANY, HAS BEEN SHORTED

CKECK THAT PERMANENT AND ADEQUATE LIGHITING ARRANGEMENTS ARE READY

CHECK THAT PRESSURE RELIEF VALVE IS CORRECTLY MOUNTED

CHECK THE COLOUR OF BREATHER SILICA GEL ( BLUE WHEN DRY )

Page 5 of 25 TRANSFORMER

Page 106: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

35

36

37

38

39

40

41

42

43

44 CHECK VARIOUS INTERLOCKS PROVIDED WITH FIRE FIGHTING

AS PER THE SCHEMATIC REF. DRG NO :

5

6 YES NO

7

MAKE

DETAILS OF RELAYS/ CONTACTORS USED : SCHEMATIC DRAWING NO.:

CHECK THAT AIR HAS BEEN RELEASED FROM THE RADIATORS AND THEIR HEADERS / OLTC BUCHHOLZ RELAY / MAIN TANK / TANK/ BUSHING TURRETS ETC.

CHECK FIRE PROTECTION SYSTEM & EMULSIFIRE SYSTEM IS ADEQUATE & READY

DESCRIPTION OF INTERLOCKS CHECKED

CHECK THAT CC-CL&G ARE SHORTED

CHANGE OVER OPERATION OF AC SUPPLY FROM SOURCE-I TO SOURCE-II CHECKED

CHECK THAT ALL RADIATOR BANK VALVES ON TOP AND BOTTOM HEADERS ARE OPEN

CHECK THE FLANGES OF BUSHING & OLTC FOR ANY CRACK AFTER FIXING

CALIBRATION OF OTI & WTI PERFORMED AS PER PROCEDURE

MEASUREMENT OF EARTH RESISTANCE OF ELECTRODE

SERIAL NO.

CHECK THAT ALL CABLES ARE CORRECTLY GLANDED

CHECK EXTERNAL CABLING FROM JUNCTION BOX TO RELAY / CONTROL PANEL COMPLETED

CHECK ALL CABLES AND FERRULS ARE PROVIDED WITH NUMBER AS PER CABLE SCHEDULE (CROSS FERULING TO BE CHECKED)

NO+NCCIRCUIT REFERENCE TYPE

NOTE: VALUE OF EARTH RESISTANCE< 1.0 OHM

LOCATION

VALUE (Before connection to grid)

VALUE (After connection to grid)

Page 6 of 25 TRANSFORMER

Page 107: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

8

8.1 BEFORE FILLING OIL, EACH DRUM HAS BEEN PHYSICALLY CHECKED FOR FREE MOISTURE AND APPEARANCE YES NO

8.2

a) CAPACITY :

b) MAKE :

c) LUBRICATING OIL OF VACUUM PUMP CHANGED OR NOT :

d) FILTER PACKS CLEANED OR NOT :

e) WHOLE FILTER MACHINE FLUSHED WITH FRESH OIL OR NOT :

f) VACUUM OBTAINED WITHOUT LOAD (milli bar) :

8.3

a) LUBRICATING OIL CHANGED OR NOT :

b) VACUUM OBTAINED WITHOUT LOAD (milli bar) :

c) DIAMETER OF VACUUM HOSE (50 mm) :

d) DRY ICE CHAMBER EMPLOYED OR NOT :

8.4

a) INSIDE PAINTED OR NOT :

b) SILICA GEL BREATHER PROVIDED OR NOT :

c) ANY OPENING LEFT UNCOVERED :

d) CAPACITY & QUANTITY :

e) CLEANLINESS OF INSIDE OF PIPES/ HOSES TO THE STORAGE TANK :

8.5 EXPOSURE DURING ERECTION Transformer to be kept sealed with N2 in between

a) First day Hrs :

b) Second day Hrs :

c) Third Day Hrs :

d) N2 pressure applied after each days erection work PSI :

e) Ambient Temperature DegC :

f) Average Relative Humidity :

g) Weather Condition rainy/ stormy/ cloudy/sunny :

8.6

a) No. of Cylinders used for displacing the air inside the tank :

b) N2 admitted from bottom valave :

c) Valve at diametriccaly opposite end at top kept open :

d) No. of Cylinders used for building up 2 PSI :

DATE TIME

c. PRESSURE P1 ..... kPa

b. STOP EVACUATING AT 0.3 kPa (3 mbar)

INSPECTION ACTIONS

I. TIGHTNESS TEST

0.5 HOUR AFTER READING PRESSURE P1

1 HOUR AFTER STOP EVACUATING

d. PRESSURE P2 ..... kPa

OIL FILTER MACHINE :

EVACUATING AND OIL FILLING

OIL STORAGE TANK :

V=Oil quantity in Cu mtr

N2 SEALING IN CASE OF DELAY IN OIL FILLING

VACUUM PUMP FOR EVACUATION OF TRANSFORMER :

REMARKS

e. LEAKAGE = (P2-P1)xV=

a. START EVACUATING ON COMPLETE UNIT

CHECKED

Page 7 of 25 TRANSFORMER

Page 108: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

8.7

DATE :

TIME :

(HOURLY READING TO BE TAKEN)

DATE TIME OTI OF TANK

Record of filteration and Dry out shall be kept in a register and shall be made a part of the Pre-commissioning document.

DRYING OUT STARTED ON

6. STANDING TIME

4. OIL CONSERVATOR

a. PRESSURE 0.13 kPa (1.3 mbar) REACHED

CONDENSATE COLLECTED TOTAL /

RATE

3 OIL FILLING

b. VACUUM IS KEPT FOR

2 VACCUM

IF LEAKAGE >3.6, CONTINUE EVACUATING

a. OIL FILLING IS MADE

Above 420 KV, 36 HRS

Upto 145 KV , 12 HRS

Upto 145 KV , 12 HRS

145 & upto 420 KV, 24 HRS

145 & upto 420 KV, 48 HRS

5. DIVERTER SWITCH HOUSING

VACUUM READING IN TRANSFORMER

TANK

OIL CONSERVATOR WITH AIR CELL

diverter switch housing filled and has an

air cushion

Above 420 KV, 120 HRS

VACUUM READING IN FILTRATION MACHINE

RECORD OF DRYING OUT PROCESS (IF CARRIED OUT)

REMARKS & SIGN OF Mtc ENGINEER

AMBIENT TEMP :

Page 8 of 25 TRANSFORMER

Page 109: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

9 a

:

:

SL.NO

YES NO

A CONTROL WIRING

B TAP CHANGER

a) MOTOR

b) CONTROL

C COOLING SYSTEM

a) MOTOR FAN

b) MOTOR PUMP

c) CONTROL WIRING

NOTE : IR VALUES SHOULD BE > 50 MOHMS FOR CABLES

b

TESTING INSTRUMENT DETAILS: :

:

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

15 SEC. 60 SEC. 600 SEC.

10

CONNECT NEUTRAL POINT WITH EARTH

JOIN 1RI AND 3 RI TERMINALS

-APPLY 415V, 3-PHASE SUPPLY TO HV TERMINALS

3Y1- 1B1

3Y1- N1R1- N

HV+IV to LV (For 3 Wdg Tr)

HV+IV Tto E (For 3 Wdg Tr)

VECTOR GROUP TEST & POLARITY CKECKING

IN CASE THERE IS ANY TEMPERATURE DIFFERENCE BETWEEN MANUFACTURERS TEST CERTIFICATE VALUE AND SITE VALUE, USE TEMPERATURE CORRECTION FACTOR PROVIDED IN OS MANUAL DOC. NO. D-2-03-XX-01-01-Rev01

1B1- 1R1

INSULATION RESISTANCE MEASUREMENT : (USING 500 V MEGGER)

REMARK, IF ANY

HV+IV + LV to E (For 3 Wdg Tr)

TESTING INSTRUMENT DETAILS:

STATUS

TESTING EQUIPMENT CALIBRATION VALID OR NOT

TESTING EQUIPMENT CALIBRATION VALID OR NOT

DESCRIPTION

3Y1- 1Y1

HV+IV to LV (For auto Tr)

HV+IV Tto E (For auto Tr)

LV to E (For auto Tr)

3R1- N

1Y1- 1B1

IR VALUE

1R1 -1Y1TERMINALS REMARKS

MAIN WINDING

2Y1- N2B1-N

INSULATION RESISTANCE MEASUREMENT : (USING 5000 V MEGGER)

Dielectric Absorption Index (60s/15s)

Polarization Index (600s/ 60s)

VOLTAGE MEASURED

Temperature

2R1- N

Page 9 of 25 TRANSFORMER

Page 110: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

ENSURE 2R1 -N = 2Y1 -N = 2B1 - N = CONSTANT

AS 3R1 -N > 3Y1 - N > 3B1 - N, AND 3Y1 - 1B1 > 3Y1 - 1Y1

VECTOR GROUP Ynaod11 IS CONFIRMED AND POLARITY VERIFIED

11

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

:

a

1R1 - 2R1 1Y1 - 2Y1 1B1 - 2B1 R Y B R Y B

FACTORY TEST REPORT REF NO :

b

:

SITE VALUE

3

1

2

REMARKRESISTANCE AT 75 ºC

FACTORY

9b

10

WINDING

14

15

16

TAP NO……………….

REVERSE ORDER

INTERMEDIATE VOLTAGE SIDE

FACTORY VALUE RESISTANCE AT 75 ºC

2Y1 - N

2B1 - N

WTI READING

2R1 - N

BETWEEN

SITE

RESISTANCE

11

7

8

12

17

TAP NO……………….

13

TAP NO……………….

TAP NO……………….

MEASUREMENT OF WINDING RESISTANCE (IN OHM)

HIGH VOLTAGE SIDE

REMARKS WINDING RESISTANCE (HV-

N)TAP POSITION

4

5

TESTING INSTRUMENT DETAILS

6

Page 10 of 25 TRANSFORMER

Page 111: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

c

:

12 a

2R1 - N V 2Y1 - N V 2B1 - N V

2Y1 - N V 2R1 - N V 2B1 - N V

2B1 - N V 2Y1 - N V 2R1 - N V

NOTE : 1 = ( 2 + 3 ) APPROX.

b

DISCONNENT THE TRANSFORMER NEUTRAL FROM THE GROUND

APPLY 3 PHASE 415 VOLTS TO THE HIGH VOLTAGE WINDING AND MAKE THE MEASUREMENT IN THE

IV WINDING WITH RESPECT TO NEUTRAL AND NEUTRAL POINT TO GROUND.

APPLY 3 PHASE 415 VOLTS TO THE INTERMEDIATE VOLTAGE WINDING AND MAKE THE MEASUREMENT

IN THE TERTIARY WINDING WITH RESPECT TO NEUTRAL AND NEUTRAL POINT TO GROUND.

YES NO

VOLTAGE MEASURED

Check: After the test, neutral reconnected to Ground

3R - N

3Y - N

2 Y - N

IV

WINDING

REMARK

2 B - N

REMARKS, IF ANY

REMARKS, IF ANYAPPLIED

VOLTAGE MEASURED

VOLTAGE MEASURED IN VOLTS

BETWEEN

2Y - N

RESISTANCE

MAGNETIC BALANCE TEST

NOTE: LV WINDING RESISTANCE AT FACTORY MEASURED WITHOUT FORMATION OF DELTA. HOWEVER MEASUREMENTS CARRIED OUT AT SITE ARE AFTER FORMATION OF DELTA. HENCE A CORRECTION FACTOR OF 1.5 TIMES TO BE APPLIED IN SITE RESULTS

BETWEEN (3)

APPLY SINGLE PHASE 230 V ACROSS ONE PHASE OF HV WINDING TERMINAL AND NEUTRAL THEN MEASURE VOLTAGE IN OTHER TWO HV TERMINALS ACROSS NEUTRAL. REPEAT THE TEST FOR EACH OF THE THREE PHASES.

RESISTANCE AT 75 ºC

IV WINDINGVOLTAGE LV

WINDING

2R - N

N - EARTH

3R1 - 3B1

3Y1 - 3R1

NORMAL ( )

Apply 1-PH 230 V AC across (1)

SITE VALUE FACTORY

NORMAL ( )

TAP

POSITION

NORMAL ( )

WINDING

LOW VOLTAGE SIDE

BETWEEN (2)

REMARKS

FLOATING NEUTRAL VOLTAGE MEASUREMENT

1 Y - N

VOLTAGE

1 B - N

APPLIED

3B1 - 3Y1

PRIMARY WINDING

2 R - N1 R - N

SITE

2B - N 3B - N

N - EARTH

Page 11 of 25 TRANSFORMER

Page 112: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

13

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

a APPLY 1-PHASE AC SUPPLY ON HV TERMINALS AND KEEP IV & LV OPEN

R - N V

LOWEST ( ) Y - N V

B - N V

R - N V

NORMAL ( ) Y - N V

B - N V

R - N V

HIGHEST ( ) Y - N V

B - N V

b APPLY 1-PHASE AC SUPPLY ON IV TERMINALS AND KEEP HV & LV OPEN

VOLTS

2R -N VOLTS R - PH mAMPS

2Y -N VOLTS Y - PH mAMPS

2B -N VOLTS B - PH mAMPS

Compare with factory test results if carried out at factory

14

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

a RATIO : HV / IV

1R-N 1Y-N 1B-N 2R-N 2Y-N 2B-N R Y B R Y B

1

2

3

4

5

6

7

8

TAP POSITION REMARK

TESTING INSTRUMENT DETAILS

VOLTAGE APPLIED

VOLTAGE RATIO TEST :

NORMAL

TESTING INSTRUMENT DETAILS

VOLTAGE APPLIED

Remarks: To be done by Automatic Turns ratio meter

BETWEENTAP POSITION

B - PH m AMPS

R - PH m AMPS

Y - PH m AMPS

R - PH m AMPS

CURRENT MEASURED (IN LV SIDE)

R - PH m AMPS

Y - PH m AMPS

B - PH m AMPS

Y - PH m AMPS

VOLTAGE APPLIED CURRENT MEASURED

RATIO FACTORY RATIO

MAGNETISATION CURRENT TEST :

B - PH m AMPS

TAP POS. VOLTAGE MEASURED

Page 12 of 25 TRANSFORMER

Page 113: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

9

10

11

12

13

14

15

16

17

TAP NO…….

TAP NO…….

TAP NO…….

TAP NO…….

REMARKS (IF ANY) :

b

1R-N 1Y-N 1B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B

LOWEST

NORMAL

HIGHEST

REMARKS (IF ANY) :

c

2R-N 2Y-N 2B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B

LOWEST

REMARKS (IF ANY) :

15

(SAMPLE TO BE TAKEN PRIOR TO CHARGING OF TRANSFORMER AND IT SHOULD FULFILL THE

RECOMMENDATIONS AS PER IS 1866 - 2000, Table-I )

B.D.V * MOISTURE TAN DELTA RESISTIVITY INTERFACIAL REMARKS

( MIN ) ( MAX ) * ( MAX ) * ( MIN ) * TENSION AT 27 DEG.

(KV) (PPM) (90 Deg C) (OHM-CM) ( MIN ) N/m * FOR kV CLASS

12

IS-1866 60 10 0.01 6 x 10 O,O35 > 170 KV

12

IS-1866 50 15 0.015 6 x 10 O,O35

12

IS-1866 40 20 0.015 6 x 10 O,O35 < 72.5 kV

MAIN TANK SAMP. DATE :

OLTC SAMP. DATE :

VOLTAGE MEASURED

REVERSE SIDE

RATIO : IV / LV

<170 KV BUT>72.5 k

RATIO

RATIO : HV / LV

VOLTAGE APPLIEDTAP POS.

FACTORY RATIO

* The limiting values given in the above table to be revised as per revision in IS 1866 in future

OIL SAMPLE

TAP POS.

OIL CHARACTERISTICS :

VOLTAGE APPLIED VOLTAGE MEASURED

FACTORY RATIORATIO

Page 13 of 25 TRANSFORMER

Page 114: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

16

TOTAL GAS (%)

H2

CH4

C2H4

C2H6

C2H2

CO

CO2

O2

N2

17

SL.NO STATUS

1 OK NOT OK

2

3

4

5

6

7

8

9

10

11

18

a CHECKING OF COOLING EQUIPMENTS :

i. ROTATION DIRECTION OF PUMPS

ii. ROTATION DIRECTION OF FANS

OK NOT OK

OK

CHARGINGCHARGING

VISUAL INSPECTION OF EQUIPMENT

DESCRIPTION

CHARGING CHARGING

OVER LOAD DEVICE OF DRIVING MOTOR

LOCAL OPERATION (ELECTRICAL)

STEP BY STEP CONTACTOR

MANUAL OPERATION ON ALL TAPS ( LOCAL ) WITH CONFIRMATION OF THE NO. OF REVOLUTIONS AND LOCKING AT EXTREME TAPS

WINDING RESISTANCE AT ALL TAPS

REMOTE OPERATION (ELECTRICAL)

TAP POSITION INDICATOR

CHECK OPERATION WITH MASTER FOLLOWER

SCHEME ( PARALLEL OPERATION )

OUT OF STEP RELAY

NOT OK

TEST ON OLTC

REMARKS

BEFORE

CHARGING

24 HRS

CHARGING

15 DAYS

AFTER

LIMIT SWITCH

OIL SAMPLE SCHEDULE DISSOLVE GASES

JUST

DISSOLVE GAS ANALYSIS

OPERATIONAL TEST OF OTHER EQUIPMENTS

AFTER

01 MONTH

AFTER

03 MONTH

AFTER AFTER

7 DAYS

12 CONTINUITY TEST OF WINDING DURING ONE COMPLETE CYCLE OF OPERATION

Page 14 of 25 TRANSFORMER

Page 115: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

b PROTECTION CHECKS

EQPMT

FAN NO.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

c PUMP NO.

1

2

3

4

19

BETWEEN HV IV

R-PH Y-PH B-PH R-PH Y-PH B-PHMOHMMOHMMOHMMOHM

BETWEEN LV NEUTRAL

R-PH Y-PH B-PH MOHM IR VALUE SHOULD MOHM BE AT LEAST MOHM 2000 M OHMS MOHM

BETWEEN HV IV USING 500 V

R-PH Y-PH B-PH R-PH Y-PH B-PH MEGGERMOHMMOHMMOHMMOHMMOHMMOHM

BETWEEN LV USING 500 V

R-PH Y-PH B-PH MEGGERMOHMMOHMMOHMMOHMMOHMMOHM

SETTING VALUE PICKUP VALUE

INSULATION RESISTANCE MEASUREMENT OF BUSHING CT's : ( USING 500V MEGGER)

EARTH - CORE I

EARTH - CORE IV

EARTH - CORE IIEARTH - CORE III

EARTH - CORE IIEARTH - CORE IIIEARTH - CORE IV

SINGLE PHASING PREVENTION CHECK

EARTH - CORE I

CORE I - CORE II CORE I - CORE III CORE I - CORE IV

CORE II - CORE III CORE II - CORE IV CORE III - CORE IV

CORE II - CORE III CORE II - CORE IV CORE III - CORE IV

CORE I - CORE IV

CORE I - CORE II CORE I - CORE III

Page 15 of 25 TRANSFORMER

Page 116: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

20

CONTINUTY, CHECK BETWEEN TERMINAL: OK / NOT OK

a CORE BETWEEN HV IV

TERMINAL R-PH Y-PH B-PH R-PH Y-PH B-PHCORE I 1S1 - 1S2CORE II 2S1 - 2S2CORE III 3S1 - 3S2CORE IV 4S1 - 4S2

b CORE BETWEEN LV NEUTRAL

TERMINAL R-PH Y-PH B-PHCORE I 1S1 - 1S2CORE II 2S1 - 2S2CORE III 3S1 - 3S2CORE IV 4S1 - 4S2

21

a HV SIDE

CORE BETWEEN R -PHASE Y -PHASE

TERMINAL FACTORY SITE FACTORY SITE FACTORY SITE

CORE I 1S1 - 1S2 OHM

CORE II 2S1 - 2S2 OHM

CORE III 3S1 - 3S2 OHM

CORE IV 4S1 - 4S2 OHM

b IV SIDE

CORE BETWEEN R -PHASE Y -PHASE

TERMINAL FACTORY SITE FACTORY SITE FACTORY SITE

CORE I 1S1 - 1S2 OHM

CORE II 2S1 - 2S2 OHM

CORE III 3S1 - 3S2 OHM

CORE IV 4S1 - 4S2 OHM

FACTORY TEST REPORT REF NO :

c LV SIDE

CORE BETWEEN R -PHASE Y -PHASE

TERMINAL FACTORY SITE FACTORY SITE FACTORY SITE

CORE I 1S1 - 1S2 OHM

CORE II 2S1 - 2S2 OHM

CORE III 3S1 - 3S2 OHM

CORE IV 4S1 - 4S2 OHM

d NEUTRAL SIDE

CORE BETWEEN NEUTRAL

TERMINAL FACTORY SITE

CORE I 1S1 - 1S2

SECONDARY WINDING RESISTANCE OF BUSHING CT's (IN OHM)

CONTINUITY TEST OF BUSHING CT's :

B -PHASE

B -PHASE

B -PHASE

Page 16 of 25 TRANSFORMER

Page 117: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

22

(CONNECT +VE AT P1 AND - VE AT P2 )

a CORE BETWEEN HV IV

R-PH Y-PH B-PH R-PH Y-PH B-PHCORE I 1S1 (+VE) 1S2 (-VE)

CORE II 2S1 (+VE) 2S2 (-VE)

CORE III 3S1 (+VE) 3S2(-VE)

CORE IV 4S1 (+VE) 4S2 (-VE)

b CORE BETWEEN LV NEUTRAL

R-PH Y-PH B-PHCORE I 1S1 (+VE) 1S2 (-VE)

CORE II 2S1 (+VE) 2S2 (-VE)

CORE III 3S1 (+VE) 3S2(-VE)

CORE IV 4S1 (+VE) 4S2 (-VE)

23

MEASURE CURRENT ON THE SECONDARY TERMINALS

a R - PHASE HV SIDE

CORE PRIMARY CURRENT SECONDARY THEORET- ACTUAL % OF

S1 - S2 % ACTUAL CURRENT ICAL RATIO RATIO ERROR

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

b Y - PHASECORE I 20 %(1S1 - 1S2) 40 %

80 %CORE II 20 %(2S1 - 2S2) 40 %

80 %CORE III 20 %(3S1 - 3S2) 40 %

80 %CORE IV 20 %(4S1 - 4S2) 40 %

80 %

POLARITY TEST OF BUSHING CT's : WITH 1.5 V DC SUPPLY

CURRENT RATIO TEST

Page 17 of 25 TRANSFORMER

Page 118: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

c B - PHASECORE I 20 %

(1S1 - 1S2) 40 %80 %

CORE II 20 %(2S1 - 2S2) 40 %

80 %CORE III 20 %

(3S1 - 3S2) 40 %80 %

CORE IV 20 %(4S1 - 4S2) 40 %

80 %

d R - PHASE INTERMEDIATE VOLTAGE SIDES1 - S2 20 %CORE I 40 %

(1S1 - 1S2) 80 %20 %

CORE II 40 %(2S1 - 2S2) 80 %

20 %CORE III 40 %

(3S1 - 3S2) 80 %20 %

CORE IV 40 %(4S1 - 4S2) 80 %

e Y - PHASECORE I 20 %

(1S1 - 1S2) 40 %80 %

CORE II 20 %(2S1 - 2S2) 40 %

80 %CORE III 20 %

(3S1 - 3S2) 40 %80 %

CORE IV 20 %(4S1 - 4S2) 40 %

80 %

f B - PHASECORE I 20 %

(1S1 - 1S2) 40 %

CORE II 20 %(2S1 - 2S2) 40 %

80 %CORE III 20 %

(3S1 - 3S2) 40 %80 %

CORE IV 20 %(4S1 - 4S2) 40 %

80 %

Page 18 of 25 TRANSFORMER

Page 119: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

24

(NOT TO BE DONE FOR METERING CORE)

KNEE POINT VOLTAGE (KVp) = ______________ VOLT

a R - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

b Y - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

c B - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

NOTE : 1.0 CT SHOULD NOT SATURATE AT 110 % OF KNEEPOINT VOLTAGE ( KVp )

2.0 IF KNEE POINT VOLTAGE IS NOT MENTIONED THEN KNEE POINT

CURRENT MAY BE TAKEN INTO CONSIDERATION

d R - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

CURRENT MEASUREMENT

1.10 X KVp

VOLTAGE CURRENT MEASUREMENT

TO BE APPLIED ACTUAL VALUE

MAGNETISING CURVES PERFORMANCE

HV SIDE

INTERMEDIATE VOLTAGE SIDE

O.50 X KVp

O.75 X KVp

1.O0 X KVp

1.O0 X KVp

O.25 X KVp

VOLTAGE

TO BE APPLIED ACTUAL VALUE

O.50 X KVp

O.75 X KVp

1.O0 X KVp

1.10 X KVp

O.25 X KVp

O.50 X KVp

O.75 X KVp

VOLTAGE CURRENT MEASUREMENT

TO BE APPLIED ACTUAL VALUE

O.25 X KVp

O.50 X KVp

O.75 X KVp

1.O0 X KVp

1.10 X KVp

1.10 X KVp

VOLTAGE CURRENT MEASUREMENT

TO BE APPLIED ACTUAL VALUE

O.25 X KVp

Page 19 of 25 TRANSFORMER

Page 120: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

e Y - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

f B - PHASE

CORE - I CORE - II CORE - III CORE - IV

1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

mA

mA

mA

mA

mA

25 AT 100 AMPS

NOTE : THE VALUE OF CONTACT RESISTANCE SHOULD NOT BE MORE THAN

10 MICRO-OHMS PER JOINT / CONNECTOR

R-PH Y-PH B-PH

MICRO OHM

MICRO OHM

MICRO OHM

MICRO OHM

MICRO OHM

26

STYLE NO./ DRAWING NO. :

DETAILS R-PH Y-PH B-PH R-PH Y-PH B-PH

MAKE

TYPE

SL. NO

DETAILS LOW VOLTAGE SIDE

R-PH Y-PH B-PH

MAKE

TYPE

SL. NO

O.25 X KVp

O.50 X KVp

O.75 X KVp

HIGH VOLTAGE SIDE INTERMEDIATE VOLT. SIDE

BUSHING DETAILS

CONTACT RESISTANCE MEASUREMENT

INTERMEDIATE VOLTAGE SIDE

INTERMEDIATE VOLTAGE SIDE

CURRENT MEASUREMENT

ACTUAL VALUE

VOLTAGE

TO BE APPLIED

1.O0 X KVp

1.10 X KVp

VOLTAGE

1.10 X KVp

CURRENT MEASUREMENT

TO BE APPLIED ACTUAL VALUE

O.25 X KVp

1.O0 X KVp

O.50 X KVp

O.75 X KVp

CONTACT RESISTANCE

ACROSS HV BUSHING TERMINAL JOINT

ACROSS IV BUSHING TERMINAL JOINT

ACROSS LV BUSHING TERMINAL JOINT

ACROSS NEUTRAL CONNECTION POINT

ACROSS SURGE ARRESTOR CONNECTION

Page 20 of 25 TRANSFORMER

Page 121: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

27

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

a

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

b

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

CAPACITANCE ( MEASURED VALUE )

TAN DELTA ( MEASURED VALUE )

CAPACITANCE ( MEASURED VALUE )

INTERMEDIATE VOLTAGE SIDE

HIGH VOLTAGE SIDE

TAN DELTA AND CAPACITANCE MEASUREMENT OF BUSHING

MEASUREMENT OF C2 CAPACITANCE*

MEASUREMENT OF C1 CAPACITANCE

MEASUREMENT OF C1 CAPACITANCE

MEASUREMENT OF C2 CAPACITANCE*

TAN DELTA ( MEASURED VALUE )

MEASUREMENT OF C1 TAN DELTA

MEASUREMENT OF C1 TAN DELTA

MEASUREMENT OF C2 TAN DELTA*

TESTING INSTRUMENT DETAILS

MEASUREMENT OF C2 TAN DELTA*

Page 21 of 25 TRANSFORMER

Page 122: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

c

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

VOLTAGE R PHASE Y PHASE B PHASE REMARK

SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

FACTORY TEST REPORT REF NO :

* NOTE C2 VALUES SHALL BE ONLY FOR RECORD PERPOSE.

28

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

SITE FACTORY SITE

2 KV

10 KV

2 KV

10 KV

2 KV

10 KV

2 KV

10 KV

2 KV

10 KV

2 KV

10 KV

FACTORY TEST REPORT REF NO :

FACTORY

TAN DELTA *

HV-IV/ LV with Guard

REMARK

HV-IV/LV

LV/ HV-IV+G

HV-IV/ LV

GST

UST

GST

GSTg

UST

HV-IV/ LV+G

LV/ HV-IV with Guard GSTg

Test ModeWINDING COMBINATIONVOLTAGE

* SHOULD BE COMPARABLE (+/- 0.001) WITH FACTORY VALUE SUBJECTED TO MAX OF 0.005.

MEASUREMENT OF C1 TAN DELTA

TESTING INSTRUMENT DETAILS

TAN DELTA AND CAPACITANCE MEASUREMENT OF WINDINGS

LOW VOLTAGE SIDE

CAPACITANCE ( MEASURED VALUE )

MEASUREMENT OF C2 TAN DELTA*

CAPACITANCE

MEASUREMENT OF C1 CAPACITANCE

MEASUREMENT OF C2 CAPACITANCE*

TAN DELTA ( MEASURED VALUE )

Page 22 of 25 TRANSFORMER

Page 123: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

29

:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :

AMBIENT TEMPERATURE AT THE TIME OF TEST :

TEMPERATURE OF OIL :

a HV TO IV

b IV TO LV

TAP NO. 9b

c HV TO LV

TAP NO. 9b

TAP NO. 17

TAP NO. 1

(IV OF Y Ф AND N SHORTED, LV OPEN) (IV OF B Ф AND N SHORTED, LV OPEN)

SHORT CIRCUIT IMPEDANCE TEST

1U1 ( R ) 1V1 (Y)

TESTING INSTRUMENT DETAILS

VOLTAGE CURRENT

TAP NUMBER

VOLTAGE CURRENT VOLTAGE CURRENT

1W1 (B)

(IV OF R Ф AND N SHORTED, LV OPEN)

1

9b

17

…………………….V …………………….A

…………………….V …………………….A

…………………….V …………………….A

…………………….V …………………….A

…………………….V …………………….A

…………………….V …………………….A

SUPPLY

…………………….V …………………….A…………………….V …………………….A …………………….V …………………….A

SHORT ALL 3 LV BUSHINGS, HV OPEN SHORT ALL 3 LV BUSHINGS, HV OPEN SHORT ALL 3 LV BUSHINGS, HV OPEN

…………………………………………………………A

1U1-N, …………………….V …………………………………………………………A

1W1-N, ……………………V

1V1-N,……………………..V …………………………………………………A

2U1-N, …………………….V

SHORT ALL 3 LV BUSHINGS, IV OPEN

2V1-N,……………………..V …………………………………………………A

2W1-N, ……………………V

SUPPLY SHORT ALL 3 LV BUSHINGS, IV OPEN SHORT ALL 3 LV BUSHINGS, IV OPEN

…………………………………………A

SHORT ALL 3 LV BUSHINGS, IV OPEN

……………………………………………A

SUPPLY SHORT ALL 3 LV BUSHINGS, IV OPEN SHORT ALL 3 LV BUSHINGS, IV OPEN

1V1-N,……………………..V ………………………………………………A

1U1-N, …………………….V …………………………………………………………A

1W1-N, ……………………V ………………………………………A

SUPPLY SHORT ALL 3 LV BUSHINGS, IV OPEN SHORT ALL 3 LV BUSHINGS, IV OPEN SHORT ALL 3 LV BUSHINGS, IV OPEN

1U1-N, …………………….V …………………………………………………………A

1V1-N,……………………..V ……………………………………………A

1W1-N, ……………………V ………………………………………A

Page 23 of 25 TRANSFORMER

Page 124: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

30

SL DEVICE SET FOR PROVED

NO ALARM TRIP ALARM TRIP

1 EXCESSIVE WINDING TEMPERATURE.

2 EXCESSIVE OIL TEMPERATURE.

3 OIL FLOW FAILURE NA NA

4 PRESSURE RELIEF VALVE NA NA

5 MAIN TANK BUCHHOLZ RELAY

6 OLTC BUCHHOLZ RELAY NA NA

7 FAN FAILURE NA NA

8 LOW OIL LEVEL (MOG) NA NA

9 DIFERENTIAL RELAY NA NA

10 OVER LOAD RELAY NA NA

11 EARTH FAULT RELAY ( REF ) NA NA

12 OVER CURRENT RELAY NA NA

13 INTER TRIP , IF ANY NA NA

14 TRIP FREE CHECK NA NA

15 BACKUP OVER CURRENT NA NA

16 OVER FLUX

17 PROTECTION SETTINGS APPLIED AS PER ENGG. APPROVED SETTINGS YES NO

18 STABILITY TEST OF DIFFERENTIAL & REF PROTECTION: OK NOT OK

31

a CARRIED OUT AFTER COMPLETION OF ALL COMMISSIONING ACTIVITIES YES NO

b INTERPRETATION OF TEST RESULTS CARRIED OUT YES NO

c TEST RESULTS MATCHING WITH THE FACTORY RESULTS YES NO

d FACTORY & SITE FRA TEST REPORT AVAILABLE AT SITE YES NO

32

33

a YES NOANY ABNORMAL SOUND EMANATING FROM THE TRANSFORMER: REMARKS

NO

CHECKS AFTER CHARGING OF TRANSFORMER

YES

PROTECTION AND ALARMS

RECORD THE FOLLOWING AFTER CHARGING

ALL ELECTRICAL TEST RESULTS COMPARED WITH FACTORY TEST RESULTS AND FOUND TO BE IN ORDER

FREQUENCY RESPONSE ANALYSIS (FRA)

NOTE : PROVE THE TRIPPING OF ASSOCIATED BREAKERS BY ACTUAL OPERATION OF THE VARIOUS DEVICES AND RELAYS AS PER THE SCHEMES.

Page 24 of 25 TRANSFORMER

Page 125: 71281912 Pgcil Latest Testing Format

DATE OF TESTING :TRANSFORMERS

POWER GRID CORPORATION OF INDIA LIMITEDासफॉमरर का ी किमशिनग/ किमशिनग फौमट

PRE-COMMISSIONING OF TRANSFORMER/ COMMISSIONING FORMATS

DOC NO.: MR/CF/ICT/06/R-2 DATED : 01/04/2008

SUB STATION :

BAY NO :

EQUIPMENT IDENTIFICATION NO :

b NO LOAD CURENT AT RELAY TERMINAL

R PHASE

Y PHASE CT RATIO

B PHASE

c TEMPERATURE (AT THE TIME OF CHARGING)

OTI

WTI

AMBIENT

d

e YES NO

f YES NO

34

a FACTORY TEST RESULTS ARE AVAILABLE YES NO

b FINAL DOCUMENT OF PRE-COMMISSIONING CHECKS YES NO

REVIEWED AND APPROVED

c DOCUMENTS REGARDING SPARES, EQUIPMENT, O & M YES NO

MANNUALS ETC AVAILABLE AT SITE FOR O & M

PURPOSE

d AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS" YES NO

ARE AVAILABLE AT SITE

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :

NAME : NAME : NAME : NAME :

DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :

ORGANISATION : ORGANISATION :

( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )

(WHEREVER APPLICABLE)

OLTC ELCTRICAL OPERATION CHECKED IN IDLE CHARGED CONDITION FROM MIN POSITION TO MAX POSITION AND BACK TO NORMAL POSITION

THERMOVISION SCANNING DONE ATLEAST AFTER 24 HOURS OF LOADING AND REPEATED AFTER ONE WEEK REMARKS

MAXIMUM TEMPERATURE AFTER 24 HOURS

FINAL DOCUMENTATION REVIEW

REMARKS

ºC

A

A

A

ºC

ºC

ºC

Page 25 of 25 TRANSFORMER

Page 126: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

1

` a REGION : b DATE OFRECEIPT AT SITE :

c DATE OF COMPLETION OF d DATE OFERECTION & OIL FILLING : ENERGISATION :

e DETAILS OF EQUIPMENT :

i LOA NO :

ii MAKE :

iii TYPE :

iv RATING :

v SL NO. :

vi VOLTAGE CLASS :

vii COOLING TYPE :

viii TYPE OF NEUTRAL GROUNDING :

ix YEAR OF MANUFACTURE :

x OIL QUANTITY :

xi OIL MAKE & TYPE :

xii FEEDER NAME :

2

SL. NO.

2.12.22.32.42.52.62.7 MAGNETIZING CURRENT TEST2.8 VIBRATION MEASUREMENT2.9

2.102.112.122.132.142.152.16 FREQUENCY RESPONSE ANALYSIS

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

WINDING RESISTANCE MEASUREMENT OF NGR

SEC WDG RESISTANCE OF BUSHING CTs

INSULATION RESISTANCE MEAS OF BUSHING CT

NAME OF TEST PERFORMED YES/ NO TEST RESULTS OK/ NOTOK

INSULATION RESISTANCE MEASUREMENT

CONTACT RESISTANCE MEASUREMENT

CAPACITANCE & TAN DELTA OF BUSHING

CONTINUITY TEST OF BUSHING CTs

PROTECTION AND ALARM TESTSTABILITY TEST OF DIFFERENTIAL & REF PROT.

POLARITY TEST OF BUSHING CTs

CAPACITANCE & TAN DELTA OF NGR WINDINGCAPACITANCE & TAN DELTA OF WINDING

GENERAL INFORMATION

CHECK LIST FOR ELECTRICAL TESTS CARRIED OUT FOR REACTOR

WINDING RESISTANCE MEASUREMENT

PAGE 1 OF 16 SHUNT REACTOR

Page 127: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

3

a

* Please write 'NIL' in case of No Remarks

b

YES NO

c

APPLY 1.0 KV DC BETWEEN CL & CC+G

( RECOMMENDED VALUE > 10 M Ohms)'

4

a ACTIVE PART OF REACTOR SHOULD MINIMUM EXPOSED TO ATMOSPHERE

b DURING EXPOSURE OF ACTIVE PART OF REACTOR TO ATMOSPHERE :

c DRY AIR GENERATOR/ DRY AIR CYLINDERS USED : YES NO

d

e

YES NO

CORE INSULATION CHECK

REMARKS*N2 PRESSURE DEW POINT

AFTER RECEIPT AT SITE

DURING DISPATCH AT FACTORY

IMPACT RECORDER ANALYSIS

RECEIVED IN HEALTHY CONDITION AT SITE

CHECKS/ PRECAUTIONS DURING ERECTION

Note: Impact Recorder should be detached from the Transformer/ Reactor preferably when the main unit has been placed on its foundation.

REMARKS

DURING STORAGE AT SITE BEFORE COMM.

BRIEF ANALYSIS STATUS

NOTE: N2 PRESSURE AND DEW POINT SHOULD BE WITHIN PERMISSIBLE RANGE AS PER GRAPH PROVIDED BY MANUFACTURER AND ALSO GIVEN IN OS DOC NO D-2-03-XX-01-01 REV-01. DURING STORAGE AT SITE, DEW POINT HAS TO BE MEASURED WHENEVER ANY DROP IN N2 PRESSURE IS OBSERVED. DURING STORAGE AT SITE BEFORE COMMISSIONING, N2 PRESSURE HAS TO BE MEASURED DAILY AND RECORD TO BE MAINTAINED IN A SEPARATE SHEET.

CHECKS AFTER RECEIPT OF REACTOR AT SITE

N2 PRESSURE AND DEW POINT RECORD

ANALYSIS REPORT RECEIVED FROM MANUFACTURER BEFORE CHARGING

YES NO

INSULATION VALUEBETWEEN CC-GBETWEEN CL-GBETWEEN CC-CL

Note: SHORTING LINK BETWEEN CC, CL & G TO BE REMOVED AND IR VALUE TO BE TAKEN BETWEEN CC-G, CL-G & CC-CL

REMARKS

WHILE ENTERING IN REACTOR TANK, CHECK AVAILABILITY OF PROPER OXYGEN

REACTOR KEPT SEALED WITH N2 IN BETWEEN DIFFERENT ERECTION ACTIVITIES

PAGE 2 OF 16 SHUNT REACTOR

Page 128: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

5

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY

5.1 REACTOR AND ITS AUXILIARIES ARE FREE FROM

VISIBLE DEFECTS ON PHYSICAL INSPECTION

5.2 ALL FITTINGS AS PER OUT LINE

GENERAL ARRANGEMENT DRAWING .

5.3 CHECK MAIN TANK HAS BEEN PROVIDED WITH

DOUBLE EARTHING

5.4

5.5 CHECK THAT MASHALLING BOX,RADIATOR BANK,

PUMP & FAN MOTOR ETC HAS BEEN EARTHED

5.6 ALL NUTS AND BOLTS ARE TIGHTENED

CORRECTLY AS PER SPECIFIED TORQUE(AS PER MANUFACTURER RECOMMENDATION)

5.7 CHECK TIGHTNESS OF TERMINAL CONNECTORS

5.8 CHECK LEVELLING OF REACTOR AND ITS

ACCESSORIES

5.9 ERECTION COMPLETION CERTIFICATE ALONG

WITH LIST OF OUTSTANDING ACTIVITIES

REVIEWED

5.10 ANY PAINT REMOVED / SCRATCHED IN

TRANSIT HAS BEEN TOUCHED UP

5.11 BUSHINGS ARE CLEAN AND FREE FROM

PHYSICAL DAMAGES

5.12 OIL LEVEL IS CORRECT ON ALL BUSHINGS

5.13 CHECK HERMETICALLLY SEALING IS

INTACT IN ALL BUSHINGS

5.14 CHECK OIL LEAKAGE THROUGH ANY

JOINTS / VALVES ETC.

CHECK NEUTRAL IS GROUNDED THROUGH SEPARATE CONNECTIONS. ENSURE METALLIC REQUIREMENTS AS PER SPECIFICATION (e.g. Cu) IN EARTHING STRIPS USED

DETAILS :

PRE-COMMISSIONING CHECKS:

PAGE 3 OF 16 SHUNT REACTOR

Page 129: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

5.15 CHECK OIL DRAIN VALVES ARE PROPERLY

CLOSED AND LOCKED.

5.16 CHECK OIL LEVEL IN MAIN TANK AND

CONSERVATOR TANK

5.17 CHECK OTI AND WTI POCKETS AND REPLENISH

THE OIL , IF REQUIRED

5.18 CKECK ALL VALVES FOR THEIR OPENING &

CLOSING SEQUENCE

5.19 CHECK THE COLOUR OF BREATHER SILICA GEL

( BLUE WHEN DRY )

5.20 CHECK AVAILABILITY OF OIL IN THE

BREATHER CUP

5.21 CHECK ALL ROLLERS ARE LOCKED AND

TACK WELDED WITH RAILS

( WHEREEVER APPLICABLE )

5.22 CHECK BUSHING TEST TAP IS GROUNDED

5.23 CHECK NO DEBRIS , LOOSE T & P AND OIL

STRAINS ON AND AROUND THE REACTOR

5.24 CHECK DOOR SEALS OF MARSHALLING BOX

IS INTACT AND ALL UNUSED HOLES ARE SEALED

5.25 CHECK THAT PRESSURE RELIEF VALVE ISCORRECTLY MOUNTED

5.26 ENSURE UNUSED SECONDARY CORES OF

BUSHING CT's, IF ANY, HAS BEEN SHORTED

Ì 5.27 CHECK CT STAR POINT HAS BEEN FORMED

PROPERLY AND GROUNDED AT ONE END ONLY

AS PER SCHEME

5.28 CKECK THAT PERMANENT AND ADEQUATE

LIGHITING ARRANGEMENTS ARE READY

5.29 CHECK THAT LABELLING AND IDENTIFICATION

IS PERMANENT AND SATISFACTORY

PAGE 4 OF 16 SHUNT REACTOR

Page 130: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

5.30 CHECK THAT BUCHHOLZ RELAY IS

CORRECLY MOUNTED WITH ARROW POINTING

TOWARDS CONSERVATOR

5.31 CHECK CABLES ARE PROPERLY FIXED AND

ENSURE CABLE ENTRY AT THE BOTTOM.

5.32 ENSURE ALL POWER AND CONTROL CABLE

TERMINALS ARE TIGHTENED

5.33 CHECK THAT ALL CABLES ARE CORRECTLY

GLANDED

5.34 CHECK EXTERNAL CABLING FROM JUNCTION-

BOX TO RELAY / CONTROL PANEL COMPLETED

5.35 CHECK ALL CABLES AND FERRULS AREPROVIDED WITH NUMBER AS PER CABLE

SCHEDULE (CROSS FERULING TO BE CHECKED)

5.36 CHECK THAT AIR HAS BEEN RELEASED FROMTHE RADIATORS AND THEIR HEADERS /

BUCHHOLZ RELAY / MAIN TANK / BUSHING TURRETS ETC.

5.37 CHECK FIRE PROTECTION SYSTEM &

EMULSIFIRE SYSTEM IS ADEQUATE & READY

5.38

5.39

5.40

5.41 CHECK VARIOUS INTERLOCKS PROVIDED WITH FIRE FIGHTINGAS PER THE SCHEMATIC REF. DRG NO :

NAME OF INTERLOCKS CHECKED

6 MEASUREMENT OF EARTH RESISTANCE OF ELECTRODE

NOTE: VALUE OF EARTH RESISTANCE < 1,0 OHM

7 CALIBRATION OF OTI AND WTI DONE AS PER PROCEDURE YES NO

CHECK THAT CC, CL & G ARE SHORTED

CHECK THAT ALL RADIATOR BANK VALVES ONTOP AND BOTTOM HEADERS ARE OPEN

CHANGE OVER OPERATION OF AC SUPPLY FROMSOURCE-1 TO SOURCE-2 CHECKED

LOCATION

VALUE (BEFORE CONNECTION TO GRID)

VALUE (AFTER CONNECTION TO GRID)

PAGE 5 OF 16 SHUNT REACTOR

Page 131: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

8

MAKE SERIAL NO. NO+NC

9

9.1 YES NO

9.2a CAPACITY :b MAKE :c LUBRICATING OIL OF VACUUM PUMP CHANGED OR NOT :d FILTER PACKS CLEANED OR NOTe WHOLE FILTER MACHINE FLUSHED WITH FRESH OIL OR NOT :f VACUUM OBTAINED WITHOUT LOAD (milli bar)

9.3a LUBRICATING OIL CHANGED OR NOT :b VACUUM OBTAINED WITHOUT LOAD (milli bar) :c DIAMETER OF VACUUM HOSE (50 mm) :d DRY ICE CHAMBER EMPLOYED OR NOT :

9.4a INSIDE PAINTED OR NOT :b SILICA GEL BREATHER PROVIDED OR NOT :c ANY OPENING LEFT UNCOVERED :d CAPACITY & QUANTITY :e CLEANLINESS OF INSIDE OF PIPES/ HOSES TO THE STORAGE TANK :

9.5

a) First day Hrs :b) Second day Hrs :c) Third Day Hrs :d) N2 pressure applied after each days erection work PSI :e) Ambient Temperature DegC :f) Average Relative Humidity :g) Weather Condition rainy/ stormy/ cloudy/sunny :

9.6

a) No. of Cylinders used for displacing the air inside the tank :b) N2 admitted from bottom valave :c) Valve at diametriccaly opposite end at top kept open :d) No. of Cylinders used for building up 2 PSI :

BEFORE FILLING OIL, EACH DRUM IS PHYSICALLY CHECKED FOR FREE MOISTURE & APPEARANCE

N2 SEALING IN CASE OF DELAY IN OIL FILLING

EXPOSURE DURING ERECTION

OIL FILTER MACHINE :

OIL STORAGE TANK :

VACUUM PUMP FOR EVACUATION OF REACTOR :

EVACUATING AND OIL FILLING

CIRCUIT REFERENCE TYPE

DETAILS OF RELAYS/ CONTACTORS USED: SCHEMATIC DRAWING NO.:

PAGE 6 OF 16 SHUNT REACTOR

Page 132: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

INSPECTION ACTIONS DATE TIME CHECKED REMARKS

I. TIGHTNESS TEST

a. START EVACUATING ON COMPLETE UNIT

b. STOP EVACUATING AT 0.3 kPa (3 mbar)

c. PRESSURE P1 ..... kPa

1 HOUR AFTER STOP EVACUATING

d. PRESSURE P2 ..... kPa

0.5 HOUR AFTER READING PREASURE P1

e. LEAKAGE = (P2-P1)xV=....

V=OIL VOL OF REACTOR IN Cu mtr

IF LEAKAGE >3.6, CONTINUE EVACUATING

2 VACCUM

b. VACUUM IS KEPT FOR

3 OIL FILLING

a. oil filling is made

4. OIL CONSERVATOR

oil coservator with air cell

5. DIVERTER SWITCH HOUSING

diverter switch housing filled and has an

air cushion

6. STANDING TIME

9.7

DATE : TIME :

(HOURLY READING TO BE TAKEN)

DRYING OUT STARTED ON

AMBIENT TEMP :

a. PRESSURE 0.13 kPa (1,3 mbar) REACHED

Upto 145 KV , 12 HRS

145 & upto 420 KV, 24 HRS

Above 420 KV, 36 HRS

Upto 145 KV , 12 HRS

145 & upto 420 KV, 48 HRS

Above 420 KV, 120 HRS

RECORD OF DRYING OUT PROCESS (IF CARRIED OUT)

TIMEDATE REMARKS & SIGN OF MTC ENGINEER

CONDENSATE COLLECTED TOTAL/

RATE

OTI OF MAIN TANK

VAC IN RE. TANK

VAC IN FILT. M/C

RECORD OF FILTRATION AND DRY OUT SHALL BE KEPT IN A REGISTER AND SHALL BE MADE A PART OF THE PRE-COMMISSIONING DOCUMENT

PAGE 7 OF 16 SHUNT REACTOR

Page 133: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

10 a

SL.NO DESCRIPTION STATUS REMARK, IF ANYYES NO

A CONTROL WIRING

B COOLING SYSTEM

a) MOTOR FAN

b) MOTOR PUMP

c) CONTROL WIRING

b

MAIN WINDING DIELECTRICABSORPT.

15 60 600INDEX (60S/ 15S)

11

a WINDING RESISTANCE OF REACTOR WINDING:

TESTING EQUIPMENT CALIBRATION VALID OR NOT :AMBIENT TEMPERATURE AT THE TIME OF TEST :TEMPERATURE OF OIL :

WINDING RESISTANCE RESISTANCEAT 75 DEG C FACTORY VALUE REMARKS R-PHASE Y-PHASE B-PHASE R | Y | B R Y B

| |

b WINDING RESISTANCE OF NGR WINDING

REMARKS

12

:TESTING EQUIPMENT CALIBRATION VALID OR NOT :AMBIENT TEMPERATURE AT THE TIME OF TEST :TEMPERATURE OF OIL :

CURRENT MEASURED REMARK

R - N V R - PH m AM

Y - N V Y - PH m AM

B - N V B - PH m AM

NGR WINDING

HV - EARTH

FACTORY VALUE

MEASUREMENT OF WINDING RESISTANCE (IN OHM)

WINDING RESISTANCE RESISTANCE AT 75 DEG C

NGR mAMPS

INSULATION RESISTANCE MEASUREMENT : (USING 500 V MEGGER)

INSULATION RESISTANCE MEASUREMENT : (USING 5000 V MEGGER)

TEMPERATURE

POLARIZATION INDEX (600S/ 60S)

IR VALUE TIME IN SECONDS

VOLTAGE APPLIED

MAGNETISATION CURRENT TEST

TESTING INSTRUMENT DETAILS

TESTING INSTRUMENT DETAILS

PAGE 8 OF 16 SHUNT REACTOR

Page 134: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

13(SAMPLE TO BE TAKEN PRIOR TO CHARGING OF REACTOR AND IT SHOULD FULFILL THE RECOMMENDATIONS AS PER IS 1866 )

B.D.V MOISTURE TAN DELTA RESISTIVITY INTERFACIAL REMARKS( MIN ) ( MAX ) ( MAX ) ( MIN ) TENSION AT 27 DEG.(KV) (PPM) (90 Deg C) (OHM-CM) ( MIN ) N/m FOR kV CLASS

12IS-1866 60 10 0.01 6 X 10 O,O35 > 170 Kv

12IS-1866 50 15 0.015 6 x 10 O,O35 < 170 Kv BUT > 72.5 kV

12IS-1866 40 20 0.015 6 x 10 O,O35 < 72.5 kV

MAIN TANK SAMP. DATE :

NGR SAMP. DATE :The limiting values given in the above table to be revised as per revision in IS 1866 in future

14

DISSOLVED JUST 24 HRS 7 DAYS 15 DAYS 01 MONTH 03 MONTHGASES BEFORE AFTER AFTER AFTER AFTER AFTER

CHARGING CHARGING CHARGING CHARGING CHARGING CHARGINGTOTAL GAS

(%)H2

CH4C2H4C2H6C2H2COCO2O2N2

15 ( USING 500 V MEGGER)

a BETWEEN HV NEUTRAL R -PHASE Y -PHASE B -PHASE

EARTH - CORE I MOHM

EARTH - CORE II MOHM

EARTH - CORE III MOHM

EARTH - CORE IV MOHM

b BETWEEN HV USING 500 V R -PHASE Y -PHASE B -PHASE MEGGER

CORE I - CORE II MOHM

CORE I - CORE III MOHM

CORE I - CORE IV MOHM

CORE II - CORE III MOHM

CORE II - CORE IV MOHM

CORE III - CORE IV MOHM

OIL SAMPLE

REMARKS IF ANY

OIL SAMPLE

OIL CHARACTERISTICS

DISSOLVE GAS ANALYSIS

INSULATION RESISTANCE MEASUREMENT OF BUSHING CT's

PAGE 9 OF 16 SHUNT REACTOR

Page 135: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

16

CONTINUTY, CHECK BETWEEN TERMINALS : OK / NOT OKCORE BETWEEN LV NEUTRAL

TERMINAL R-PHASE Y -PHASE B -PHASE

CORE I 1S1 - 1S2

CORE II 2S1 - 2S2

CORE III 3S1 - 3S2

CORE IV 4S1 - 4S2

17

aCORE BETWEEN R -PHASE Y -PHASE B -PHASE

TERMINAL FACTORY SITE FACTORY SITE FACTORY SITE

CORE I 1S1 - 1S2 OHM

CORE II 2S1 - 2S2 OHM

CORE III 3S1 - 3S2 OHM

CORE IV 4S1 - 4S2 OHM

b NEUTRAL SIDECORE BETWEEN NEUTRAL

TERMINAL FACTORY SITE

CORE I 1S1 - 1S2

18 WITH 1.5 V DC SUPPLY (CONNECT +VE AT P1 AND - VE AT P2 )

CORE BETWEEN HV NEUTRAL R -PHASE Y -PHASE B -PHASE

CORE I 1S1 (+VE) 1S2 (-VE)

CORE II 2S1 (+VE) 2S2 (-VE)

CORE III 3S1 (+VE) 3S2(-VE)

CORE IV 4S1 (+VE) 4S2 (-VE)

19

PRIMARY INJECTION THROUGH PRIMARY INJECTION KIT AT PRIMARY TERMINAL P1 - P2MEASURE CURRENT ON THE SECONDARY TERMINALS

a HIGH VOLTAGE R - PHASECORE PRIMARY CURRENT SECONDARY THEORET- ACTUAL % OFS1 - S2 % ACTUAL CURRENT ICAL RATIO RATIO ERROR

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

CONTINUTY TEST OF BUSHING CT's

SECONDARY WINDING RESISTANCE OF BUSHING CT's (IN OHM)

HIGH VOLTAGE SIDE

POLARITY TEST OF BUSHING CT's

CURRENT RATIO TEST

PAGE 10 OF 16 SHUNT REACTOR

Page 136: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

b Y - PHASE

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

c B - PHASE

CORE I 20 %

(1S1 - 1S2) 40 %

80 %

CORE II 20 %

(2S1 - 2S2) 40 %

80 %

CORE III 20 %

(3S1 - 3S2) 40 %

80 %

CORE IV 20 %

(4S1 - 4S2) 40 %

80 %

20

(NOT TO BE DONE FOR METERING CORE)KNEE POINT VOLTAGE (KVp) = ______________ VOLT

a R - PHASE HV SIDE

VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - III CORE - IV

APPLIED VALUE 1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

MAGNETISING CURVES PERFORMANCE

PAGE 11 OF 16 SHUNT REACTOR

Page 137: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

b Y - PHASE

VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - III CORE - IV

APPLIED VALUE 1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

c B - PHASE

VOLTAGE CURRENT MEASUREMENT

TO BE ACTUAL CORE - I CORE - II CORE - III CORE - IV

APPLIED VALUE 1S1-1S2 2S1 - 2S2 3S1 - 3S2 4S1 - 4S2

O.25 X KVp mA

O.50 X KVp mA

O.75 X KVp mA

1.O0 X KVp mA

1.10 X KVp mA

NOTE : 1.0 CT SHOULD NOT SATURATE AT 110 % OF KNEEPOINT VOLTAGE ( KVp )

2.0 IF KNEEPOINT VOLTAGE IS NOT MENTIONED THEN KNEE POINT

CURRENT MAY BE TAKEN INTO CONSIDERATION

21

CONTACT RESISTANCE R-PHASE Y-PHASE B-PHASE

MICRO OHM

MICRO OHM

22

DETAILS R-PHASE Y-PHASE B-PHASE NEUTRAL

MAKE

TYPE

SL.NO

ACROSS NEUTRAL BUSHING TERMINAL JOINT

NOTE: THE VALUE OF CONTACT RESISTANCE SHOULD NOT BE MORE THAN 10 MICRO OHMS PER JOINT/ CONNECTOR

ACROSS HV BUSHING TERMINAL JOINT

NGR TERMINAL CONNECTOR

CONTACT RESISTANCE MEASUREMENT AT 100 AMPS

BUSHING DETAILS

PAGE 12 OF 16 SHUNT REACTOR

Page 138: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

23

CAPACITANCE ( MEASURED VALUE )

VOLTAGE R PHASE Y PHASE B PHASE NEUTRAL

SITE FACTORY SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

REMARKS :

TAN DELTA ( MEASURED VALUE )

VOLTAGE R PHASE Y PHASE B PHASE NEUTRAL

SITE FACTORY SITE FACTORY SITE FACTORY SITE FACTORY

2 KV

10 KV

1 KV

REMARKS :

FACTORY TEST REPORT REF NO :

24

HIGH VOLTAGE SIDE

VOLTAGE BETWEEN CAPACITANCE TAN DELTA REMARK

SITE FACTORY SITE FACTORY

2 KV HV / TANK+E

10 KV

REMARKS :

FACTORY TEST REPORT REF NO :

MEASUREMENT OF C1 CAPACITANCE

MEASUREMENT OF C2 CAPACITANCE

MEASUREMENT OF C1 TAN DELTA

MEASUREMENT OF C2 TAN DELTA

TAN DELTA AND CAPACITANCE MEASUREMENT OF BUSHING

TAN DELTA AND CAPACITANCE MEASUREMENT OF WINDING

PAGE 13 OF 16 SHUNT REACTOR

Page 139: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

25

HIGH VOLTAGE SIDE

VOLTAGE BETWEEN CAPACITANCE TAN DELTA REMARKSITE FACTORY SITE FACTORY

2 KV HV / TANK+E10 KV

REMARKS :

FACTORY TEST REPORT REF NO :

26

2 KV10 KV

2 KV10 KV

FACTORY TEST REPORT REF NO :

27

VIBRATION MEASUREMENTS ARE TO BE CARRIED OUT AFTER ENERGIZATION OF THE REACTOR. THIS PLAN WILL BE A REFERENCE DATA FOR FUTURE MEASUREMENTS. SIDE A

HIGH VOLTAGE SIDEVARIOUS LOCATIONS ARE TO BE SHOWN IN THE DIAGRAM WITH X,Y CO-ORDINATES FOR EASY SIDE SIDE IDENTIFICATION. C D

NEUTRAL SIDESIDE B

HIGH VOLTAGE SIDE A SIDE D

NEUTRAL SIDE B SIDE C

SITE FACTORY

TAN DELTA AND CAPACITANCE MEASUREMENT OF NGR BUSHING

SITETAN DELTA (MEASURED VALUE)

FACTORYVOLTAGE

VOLTAGE CAPACITANCE (MEASURED VALUE)

VIBRATION MEASUREMENT TEST

TAN DELTA AND CAPACITANCE MEASUREMENT OF NGR WINDING

PAGE 14 OF 16 SHUNT REACTOR

Page 140: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

SL. DATE OF LOCATION VALUE REMARKSNO MEASUREMENT

28

SL DEVICE SET FOR PROVEDNO ALARM TRIP ALARM TRIP

1 EXCESSIVE WINDING TEMPERATURE.

2 EXCESSIVE OIL TEMPERATURE.

3 PRESSURE RELIEF VALVE (MAIN TANK ) NA NA

4 PRESSURE RELIEF VALVE ( NGR ) NA NA

5 MAIN TANK BUCHHOLZ RELAY

6 NGR BUCHHOLZ RELAY

7 FAN FAILURE NA NA

8 LOW OIL LEVEL ( MAIN TANK ) NA NA

9 LOW OIL LEVEL ( NGR ) NA NA

10 HIGH OIL LEVEL ( MAIN TANK ) NA NA

11 OTI ( MAIN TANK )

12 OTI ( NGR )

13 WTI ( MAIN TANK )

14 DIFFERENTIAL NA NA

15 BACKUP IMPEDENCE RELAY NA NA

16 EARTH FAULT RELAY ( REF ) NA NA

17 INTER TRIP , IF ANY NA NA

18 TRIP FREE CHECK NA NA

19 TEED PROTECTION

20 PROTECTION SETTINGS APPLIED AS PER ENGG. APPROVED SETTINGS YES NO

21 STABILITY TEST OF DIFFERENTIAL & REF PROTECTION OK NOT OK

NOTE : PROVE THE TRIPPING OF ASSOCIATED BREAKERS BY ACTUAL OPERATION OF THE VARIOUS DEVICES AND RELAYS AS PER THE SCHEMES.

PROTECTION AND ALARMS

PAGE 15 OF 16 SHUNT REACTOR

Page 141: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITED DOC NO. : MR/CF/SR/07/R-2 DATED : 01/04/08CORPORATE OPERATION SERVICES SUB STATION :PRE-COMMISSIONING OF REACTOR BAY NO :COMMISSIONING FORMATS EQUIPMENT IDENTIFICATION NO :

DATE OF TESTING :

29

a CARRIED OUT AFTER COMPLETION OF ALL COMMISSIONING ACTIVITIES YES NOb INTERPRETATION OF TEST RESULTS CARRIED OUT YES NOc TEST RESULTS MATCHING WITH THE FACTORY RESULTS YES NOd FACTORY & SITE FRA TEST REPORT AVAILABLE AT SITE YES NO

30 YES NO

31

RECORD THE FOLLOWING AFTER CHARGING

a YES NO

b REACTOR CURENT AT RELAY TERMINAL

R PHASEY PHASE CT RATIOB PHASE

c TEMPERATURE (AT THE TIME OF CHARGING)

OTIWTIAMBIENT

d

e YES NO

32

a FACTORY TEST RESULTS ARE AVAILABLE YES NO

b FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

c DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & MPURPOSE YES NO

d AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

FREQUENCY RESPONSE ANALYSIS (FRA)

ºC

THERMOVISION SCANNING DONE ATLEAST AFTER 24 HOURS OF LOADING AND REPEATED AFTER ONE WEEK

ºCºC

MAXIMUM TEMPERATURE AFTER 24 HOURS ºC

A

CHECKS AFTER CHARGING OF REACTOR

FINAL DOCUMENTATION REVIEW

AA

ALL ELECTRICAL TEST RESULTS COMPARED WITH FACTORY TEST RESULTS AND FOUND TO BE IN ORDER

ANY ABNORMAL SOUND EMANATING FROM THE REACTOR:

PAGE 16 OF 16 SHUNT REACTOR

Page 142: 71281912 Pgcil Latest Testing Format

DOC NO. MR/CF/ISO/08/R-2 DATED : 01/04/08POWER GRID CORPORATION OF INDIA LIMITED SUB STATION :CORPORATE OPERATION SERVICES BAY NO :PRE-COMMISSIONING OF ISOLATOR AND GROUND SWITCH EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II DATE OF III DATE OFERECTION : ENERGISATION :

IV DETAILS OF EQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. : R - PHASE Y - PHASE B - PHASE

YEAR OF MANUFACTURE :

V FEEDER NAME :

VI OPERATING VOLTAGE : kV TYPE OF OPERATINGMECHANISM :

VII CURRENT CARRYING CAPACITY : AMPERE

VIII CONTROL VOLTAGE : VOLT DC

IX DETAILS :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY1 EQUIPMENT IS FREE FROM DIRT/DUST

FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLEDEFECTS ON PHYSICAL INSPECTION

3 SUPPORT STRUCTURES, MARSHALLING BOXHAS BEEN PROVIDED WITH TWO EARTHINGPADS / POINTS

4 ALL NUTS AND BOLTS ARE TIGHTENEDCORRECTLY AS PER SPECIFIED TORQUE

5 EQUIPMENT ERECTION IS COMPLETE INALL RESPECT AS PER INSTRUCTION MANUAL(ATTACH REMAINING ACTIVITIES,IF ANY)

6 PERMANENT ISOLATOR LAVELLING ANDIDENTIFICATION IS DONE

7 LEVELLING AND ALIGNMENT OF STRUCTUREAND BASE FRAME IS CHECKED

PAGE 1 OF 5 ISOLATOR AND GROUND SWITCH

Page 143: 71281912 Pgcil Latest Testing Format

DOC NO. MR/CF/ISO/08/R-2 DATED : 01/04/08POWER GRID CORPORATION OF INDIA LIMITED SUB STATION :CORPORATE OPERATION SERVICES BAY NO :PRE-COMMISSIONING OF ISOLATOR AND GROUND SWITCH EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY8 CONTROL BOX / MARSHALLING KIOSK IS

FREE FROM ANY PHYSICAL DEFECTS

9 TIGHTNESS OF NUTS BOLTS OF TERMINALCONNECTORS ARE CHECKED

10 AUXILLARY CONTACTS AND RELAYS HAVEBEEN CLEANED AND FREE FROM RUST /DAMAGE

11 CORONA RINGS ARE PROVIDED AND PROPERLY FIXED

12 CABLE TERMINATION AND TIGHTNESSCHECKED AND UNUSED HOLES SEALED

13 EXTERNAL CABLING IS COMPLETED IN ALLRESPECT

14 ALL THE CABLE IDENTIFICATION TAGSPROVIDED AND ALL CORES ARE PROVIDEDWITH IDENTIFICATION FERRULES AT M.B.

15 ALL MOVING PARTS ARE LUBRICATED

16 ALIGNMENT OF ISOLATOR ALREADY MADEAND LOCKING BOLT PROVIDED, IF ANY

17 FREENESS OF MANNUAL OPERATION IS OK

18 GREASING HAS BEEN MADE ON THE MAINCONTACTS ACCORDING TO THE MANUFA-CTURERS INSTRUCTION

19 FUCTIONAL CKECKING OF AUXILLARY CONTACTS FOR INDICATIONS AND INTERLOCKS

20 ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIESREVIEWED

21

22 EARTH SWITCH CONNECTED TO EARTHTHROUGH BRAIDED WIRES

23

24 CHECK THAT EARTH SWITCH BLADE ALIGNMENT IN CONDITION IS AT SUFFICIENT DISTANT FROM ISOLATOR

ALL SPARE WIRES TO BE KEPT WITH FERRULES BUT NOT TERMINATED AT THE TERMINAL BLOCKS

INTERLOCKS CHECKED AS PER APPROVED SCHEME WITH ALL COMBINATIONS

PAGE 2 OF 5 ISOLATOR AND GROUND SWITCH

Page 144: 71281912 Pgcil Latest Testing Format

DOC NO. MR/CF/ISO/08/R-2 DATED : 01/04/08POWER GRID CORPORATION OF INDIA LIMITED SUB STATION :CORPORATE OPERATION SERVICES BAY NO :PRE-COMMISSIONING OF ISOLATOR AND GROUND SWITCH EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

25

26

27

28

X MOTOR DETAILS R PHASE Y PHASE B PHASE SWITCHMAKE :SL NO :TYPE :VOLT :AMPERES :HP / KW :

YR. OF MANUFACTURE :OVERLOAD SETTING :

(THERMAL OVERLOAD )XI INSULATION RESISTANCE VALUE OF MOTOR WINDING

( USING A 500 VOLT MEGGER MEASURE RESISTANCE BETWEEN THE WINDING OF MOTOR AND EARTH )

PHASER- PHASE Y- PHASE B- PHASE

WINDING TO EARTH

XII OPERATIONAL CHECKS :

A OPERATE THE ISOLATOR AND RECORD THE MOTOR CURRENT

ISOLATOR MOTOR CURRENTOPERAT- R - PHASE Y - PHASE B - PHASE

ION FACTORY SITE FACTORY SITE FACTORY SITE

CLOSE

OPEN

B OPERATION OF ISOLATOR FROM LOCAL / REMOTE OK / NOT OK

ISOLATOR CONTROL PANEL OPERATION LOCAL REMOTE

CLOSE

OPEN

BETWEEN

CHECK THAT OPERATION AND POSITIONING OF THE LIMIT SWITCH & THE AUXILIARY CONTACTS ASSEMBLY ARE OK

CHECK THAT ALL THREE PHASE ISOLATORS ARE CLOSING & OPENING AT A TIME

CHECK ALL 3 EARTH SWITCHES CLOSE AT THE SAME TIME

PROVISION OF BIMETALLIC STRIPS ENSURED WHEREVER APPLICABLE

PAGE 3 OF 5 ISOLATOR AND GROUND SWITCH

Page 145: 71281912 Pgcil Latest Testing Format

DOC NO. MR/CF/ISO/08/R-2 DATED : 01/04/08POWER GRID CORPORATION OF INDIA LIMITED SUB STATION :CORPORATE OPERATION SERVICES BAY NO :PRE-COMMISSIONING OF ISOLATOR AND GROUND SWITCH EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

C MEASUREMENT OF OPERATING TIME

OPERATION PHASE

R- PHASE Y- PHASE B- PHASE

OPENING TIME SEC

CLOSING TIME SEC

D AUXILLARY CONTACTS CHECKINGISOLATOR AUXILLARY OPERATION TIMEOPERAT- RELAY R - PHASE Y - PHASE B - PHASE

ION TYPE NO NC NO NC NO NC

CLOSE

OPEN

REFERENCE DRAWING NO :

E OPERATION ON UNDER VOLTAGE CONDITION :

CONDITION COIL PHASER- PHASE Y- PHASE B- PHASE

PICK UP CLOSING VOLT DCVOLTAGE OPENING VOLT DC

INTERLOCK VOLT DC DROP CLOSING VOLT DC

VOLTAGE OPENING VOLT DCINTERLOCK VOLT DC

XIII INSULATION RESISTANCE TEST( USING 5000 VOLT MEGGER )

ISOLATOR OPEN CONDITIONBETWEEN PHASE

R- PHASE Y- PHASE B- PHASE MALE SIDE TO GROUND FEMALE SIDE TO GROUNDMALE SIDE TO FEMALE SIDE

XIV CONTACT RESISTANCE MEASUREMENT

(TO BE MEASURED AFTER 50 OPERATIONS)

A ISOLATOR CLOSE CONDITION(CONTACT RESISTANCE SHOULD BE LESS THAN 10 MICRO OHMS / CONNECTOR)

ACROSS PHASER- PHASE Y- PHASE B- PHASE

CONNECTOR (MALE SIDE) MICRO-OHM CONNECTOR (FEMALE SIDE) MICRO-OHM MAIN CONTACT (MALE & FEMALE) MICRO-OHM

PAGE 4 OF 5 ISOLATOR AND GROUND SWITCH

Page 146: 71281912 Pgcil Latest Testing Format

DOC NO. MR/CF/ISO/08/R-2 DATED : 01/04/08POWER GRID CORPORATION OF INDIA LIMITED SUB STATION :CORPORATE OPERATION SERVICES BAY NO :PRE-COMMISSIONING OF ISOLATOR AND GROUND SWITCH EQUIPMENT IDENTIFICATION NO :COMMISSIONING FORMATS DATE OF TESTING :

B ISOLATOR OPEN CONDITION & GROUND SWITCH CLOSE(CONTACT RESISTANCE SHOULD BE LESS THAN 150 MICRO OHMS / BREAK)

ACROSS PHASER- PHASE Y- PHASE B- PHASE

MAIN CONTACT (MALE & FEMALE) MICRO-OHM (GROUND SWITCH)

XVI A RESISTANCE OF OPERATING COIL

B RESISTANCE OF INTERLOCKING COIL

XVII FINAL DOCUMENTATION REVIEW :

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKSREVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & M PURPOSE YES NO

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C) ( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

PAGE 5 OF 5 ISOLATOR AND GROUND SWITCH

Page 147: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITEDCORPORATE OPERATION SERVICES

PRE-COMMISSIONING OF WAVE TRAPCOMMISSIONING FORMATS

I REGION :

II DATE OF III DATE OFERECTION : ENERGISATION :

IV DETAILS OF EQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. : R - PHASE : Y - PHASE : B - PHASE :

YEAR OFMANUFACTURE :

FEEDER NAME :

V RATING :

VOLTAGE RATING :

mH RATING :

CURRENT RATING : BAND WIDTH :

VI DETAILS : CHECKLIST / TESTING

SL. DESCRIPTION STATUS REMARKNO YES NO RECORD DEFICIENCIES, IF ANY1 EQUIPMENT IS FREE FROM DIRT / DUST

FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLEDEFECTS ON PHYSICAL INSPECTION

3 SUPPORT STRUCTURES HAS BEENPROVIDED WITH DOUBLE EARTH

4 ALL NUTS AND BOLTS ARE TIGHTENEDCORRECTLY AS PER SPECIFIED TORQUE

5 PERMANENT LAVELLING ANDIDENTIFICATION IS DONE

6 LEVELLING AND ALIGNMENT OF STRUCTUREAND BASE FRAME IS CHECKED

7 ALL INSULATORS & LINE MATCHING UNITARE FREE FROM ANY PHYSICAL DEFECTS

8 TIGHTNESS OF NUTS / BOLTS OF TERMINALCONNECTORS ARE CHECKED

DOC NO. :MR/CF/WT/09/R-2 DATED: 01/04/08

BAY NO : EQUIPMENT IDENTIFICATION NO : DATE OF TESTING :

SUB STATION :

1 OF 2 WAVE TRAP

Page 148: 71281912 Pgcil Latest Testing Format

POWER GRID CORPORATION OF INDIA LIMITEDCORPORATE OPERATION SERVICES

PRE-COMMISSIONING OF WAVE TRAPCOMMISSIONING FORMATS

DOC NO. :MR/CF/WT/09/R-2 DATED: 01/04/08

BAY NO : EQUIPMENT IDENTIFICATION NO : DATE OF TESTING :

SUB STATION :

9 ERECTION COMPLETION CERTIFICATE ALONG WITH LIST OF OUTSTANDING ACTIVITIESREVIEWED

10 CHECK THAT THE TUNING UNIT ANDARRESTOR ARE PROPERLY TIGHTENED AND FREE FROM ANY DAMAGE

VII INSULATION RESISTANCE MEASUREMENT :

SL. NO BETWEEN MEGGER PHASER-PHASE Y-PHASE B-PHASE

1 UPPER TEMINAL 5000 V 1000 M.OHM AND EARTH

2 LA OF THE 500 V 1 M.OHM WAVE TRAP

VIII CONTACT RESISTANCE MEASUREMENTTHE VALUE SHOULD NOT MORE THAN 5 MICRO-OHMS PER CONNECTOR / JOINT

SL. NO ACROSS PHASER-PHASE Y-PHASE B-PHASE

1 UPPER TEMINAL MICRO OHMS

2 BOTTOM TEMINAL MICRO OHMS

IX FINAL DOCUMENTATION REVIEW :

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKS

REVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES, EQUIPMENT, O & MMANNUALS ETC AVAILABLE AT SITE FOR O & M

PURPOSE YES NO

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"

ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :NAME : NAME : NAME : NAME :DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :ORGANISATION : ORGANISATION :( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY (POWERGRID SITE I/C( POWERGRID COMM TEAM )(WHEREVER APPLICABLE)

PERMISSIVE VALUE

2 OF 2 WAVE TRAP

Page 149: 71281912 Pgcil Latest Testing Format

पावरिमडपावरिमडपावरिमडपावरिमड कारपोरशनकारपोरशनकारपोरशनकारपोरशन ऑफऑफऑफऑफ इडयाइडयाइडयाइडया िलिमटडिलिमटडिलिमटडिलिमटडकियकियकियकिय चालनचालनचालनचालन सवाऐसवाऐसवाऐसवाऐPOWER GRID CORPORATION OF INDIA LIMITEDCORPORATE OPERATION SERVICES