minutes - indian railways
TRANSCRIPT
Page 1 of 59
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
MINUTES of
63rd
Meeting of
ELECTRICAL STANDARDS COMMITTEE (ESC)
held at
Diesel Locomotive Works (DLW), Varanasi
on
20th
& 21st
September-2019
RESEARCH DESIGNS AND STANDARDS ORGANISATION MANAK NAGAR, LUCKNOW – 226 011
vuqla/kku vfÒdYi v©j ekud laxBu
y[kuÅ & 226 011
Page 2 of 59
INDEX
S
N
Subject Group Proposed
by
Item
No.
Page
No.
Members Present 3
General Proceedings of meeting 5-6
Part – I NEW ITEMS
1. Preparedness of Railways for push-pull operation of
trains.
ELECT.(TRS) RB 424 7-9
2. Adequate availability of Electric trained crew for newly
electrified sections.
ELECT.(TRS) RB 425 10-11
3. Automatic activation of TELS on vulnerable identified
bridges using GPS in locomotives.
ELECT.(TRS) RDSO 426 12-15
4. Increase in workshops for repair of 3-phase traction
motors.
ELECT.(TRS) NR 427 16-17
5. Incorporation of facility for online transfer of DDS
messages on three locos equipped with RTIS.
ELECT.(TRS) NR 428 18-19
6. 160 kmph OHE up-gradation- options available. T.I. RB 429 20-21
7. Courses module at IRIEEN- In light of new advances in
electrical department.
EEM RB 430 22-23
8. New Technological Up-gradation and Advances – in
TRD and ‘G’ services.
T.I. RB 431 24-25
9. SCADA requirement and up-gradation needed- In light
of open access.
T.I. RB 432
26
10. Procurement Policy of Lift and Escalator. EEM RB 433 27--28
11. Review of Height of top member of gauge at LC gates in
Electrified sections – amendment to ACTM.
T.I. SWR 434 29-30
12. Replacement of Overhead Track Crossing Up to 66 kV
by underground cable and use of monopole in place of
tower.
T.I. NWR 435 31-32
13. Standardisation of luminaries fittings for PFs, Street
light, Yards, Washing lines & Circulating areas &
Railway colony.
EEM NR 436 33-34
14. Standardization of Electrical vehicle charging station at
Railway station & their running policy.
EEM NR 437 35-36
15. Tower Wagon Maintenance. T.I. NR 438 37-38
16. Creation of man power for TRD maintenance of
additional assets by transferring man power of Diesel
loco maintenance proportionately to the extent of
reduction in Diesel locos.
T.I. SCR 439 39-40
17. Elimination of one power car from HOG compliant
mixed trains.
ELECT (G) RB 440 41-42
18. Digital Train Communication Network (TCN) for
EOG/HOG trains.
ELECT (G) RB 441 43-44
19. Electric power supply voltage (110 or 230V) in
passenger area of departmental coaches.
ELECT (G) RB 442 45
20. Various issues related to reliability of Metro Railway,
Kolkata.
ELECT(G) RB 443 46-47
Other Issues (Non agenda items) Discussed. 48
Part - II Review of Status of recommendations of the
62nd
ESC meeting. Annexure-I 50-58
Part – III List of new items proposed by Railways/PUs but
not featuring in main Agenda for discussion. Annexure-II 59
Page 3 of 59
MEMBERS PRESENT
S.No. Name(S/Shri/Smt.) Designation
Railway Board
1. Rajesh Tiwari Member Traction
2. Manju Gupta Add. Member Electrical
3. Kishore Kumar EDEE/RS
4. R.K.Jain EDEE/DEV
5. Jaideep EDEE/G
6. B.S.Bodh EDEE/RE
RDSO
1. O.P.Kesari PED/SE
2. Sanjeev Swaroop PED/PS
3. Sudhir Ranjan EDTI(Co-ord)
4. Dinesh Kumar ED/PS&EMU
Railways
1. A.K.Singhal PCEE/DLW
2. N.K.Gupta PCEE/ICF
3. Sanjay Deep Director/IRIEEN
4. Anand Dev PCEE/NFR
5. R.K.Atolia PCEE/NWR
6. Alok Gupta CAP/CORE
7. B.Rai PCEE/NER
8. Avnesh Kumar Gupta PCEE/WCR
9. Rakesh Tiwari PCEE/ECR
10. A.A.Phadke PCEE/SCR
11. Shailendra Kumar Singh PCEE/NR
12. M.K.Gupta PCEE/RWF
13. S.P.Vavre PCEE/CR
14. Raj Narayan PCEE/NCR
15. S.N.Dubey PCEE/SECR
16. Sanjeev Bhutani PCEE/WR
17. Ram Prakash PCEE/CLW
18. Prem Chand PCEE/RCF
19. B.G.Mallya PCEE/SWR
20. C.S.Jeenger PCEE/ER
21. B.Panda PCEE/ECoR
22. R.K.Gupta PCEE/SR
23. Ashim Majumdar CEE/CON/Metro
Page 4 of 59
Part-I (Technical Session)
Page 5 of 59
PROCEEDINGS OF THE MEETING 63rd Electrical Standards Committee (ESC) at Diesel Locomotive Works (DLW), Varanasi
1. Inaugural Session PCEE/DLW Address: PCEE/DLW welcomed all the Members of Electrical Standards Committee (ESC). DLW, Varanasi have taken all the efforts for the smooth conduction of ESC meeting and comfortable stay of participants. However, if any lapses are noticed, the same may be brought to the notice for corrective action. DLW successfully adopted to manufacturing of electric locomotives and met the expected production target. PED/SE/RDSO Address: At the outset, PED/SE expressed hearty thanks to the team of officers and staff of DLW for making excellent arrangements for meeting. Electrical Standards Committee is a highest forum of electrical engineers for discussion on matters related to electrical engineering, as used in Indian Railways. The first meeting of Electrical Standards Committee took place in Shimla in the year 1935 which was chaired by Mr. A.F. Wilson, Chief Electrical Engineer of Madras and Southern Maharashtra Railway, as known at that time. Thereafter, this meeting had been held regularly. The Electrical Standards Committee has contributed a lot by way of useful deliberations and decisions, which helped the electrical engineers for improving the transportation system for Indian Railways. During the Electrical Standards Committee meeting, the issues pertaining to reliability of assets and its maintenance, technological upgradation or switching over to a new technology, recruitment, training, standardisation of electrical assets etc. are discussed to provide better services to our passenger as well as freight customers. For this meeting, total 42 items were proposed by various Zonal Railways and Production Units. Out of that, total 20 items have been included in the agenda for discussion. The items, which could not be included due to limited time, are available in Part-III of agenda booklet. Some of these items may be discussed, if time permits with the permission of Chair. Additional Member Electrical Address: Consequent upon 100% electrification, expectation from Electrical Engineers to deliver in their area of work has increased. The training of newly recruited ALPs should be ensured in electric traction so that operation on newly electrified territories is taken over smoothly. Open access should be utilized to reduce the energy cost. Outsourcing of the maintenance activities should be adopted on need basis. AMC should be limited to items which are highly technical in nature and where skilled manpower is not available with Railways. Maintenance in critical and safety area should be done in-house. Ways and means for condition monitoring should be adopted for predicting the failures and adopting need based maintenance. Passenger amenities like lifts & escalators should be maintained in good fettle. IREEN has big responsibility for training Electrical Engineers in various fields of electric traction including high speed. Field officers should be advised to carry out more inspections in field to take care of asset maintenance. IRIEEN should interact with Bureau of Energy Efficiency (BEE) regarding latest development in Energy area and technology up gradation. They may also be in touch with DMRC, DFCCIL, NHSRCL, so that its knowledge regarding use of modern technology gets updated.
Page 6 of 59
GM/DLW Address: DLW/Varanasi extended a heart welcome to all the delegates. GM/DLW thanked Railway Board for choosing DLW as a venue for Electrical Standards Committee meeting, which is the highest forum of electrical engineers for discussion and deliberation on matters related to electrical engineering for Indian Railways. In this meeting, future action plan will be decided to take Indian Railways forward and making it capable of meeting the challenges. Member Traction Address:
DLW/Varanasi has contributed a lot towards production of electric locomotives and for that
purpose, it deserves congratulations. As the operating ratio is not at expected level, efforts should
be made to reduce staff as well as fuel cost. Electric traction is an energy efficient mode of
transport, therefore, by adopting 100% electrification, energy bills are likely to reduce substantially.
Expectations of passengers are increasing day-by-day with the upgradation of technology,
therefore, electrical engineers, have to innovate and provide better services at least cost. Lifts and
escalators as well as cleanliness of the stations are the important passenger amenities and it
should be given proper attention to avoid passenger complaints. Development of composite
converters for 3-phase locomotives should be expedited so that WAP5 locos are turned out with
hotel load converters on regular basis. Since production of electric locomotives has increased,
there is a need to widen the vendor base. Wherever approved sources are less than three, more
efforts are required for those items. At the same time, vendor approval process has to be critically
examined and it should be expedited to ensure faster vendor development. Wide vendor base will
lead to economy in procurement as well as improvement in quality.
Page 7 of 59
Technical Session
New Item
Item No. : 424
Subject : Preparedness of Railways for push-pull operation of trains.
Group : ELECT (TRS)
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
i) In a normal Multiple Unit (MU) operation, the wired communication is established between
the front and the rear loco through UIC control cables. The operational data are
communicated between the front and rear locomotives based on the established
communication protocol. However, in the concept of Push-Pull operation, the front and rear
locomotives are operated in Multiple Unit (MU) formation separated by the coaches in
between. Thus, the principle of working of Push-Pull is same as that exists in MU operation
but with rear loco at a distance and without connection of MR & BC equalizing pipes.
ii) To achieve Push-Pull operation, software logic and MU hardware installed in the
locomotive have been optimized. The scheme is as below:
iii) Indian Railways has started the operation of Train no. 22221/22222 Special Rajdhani
Express from CSTM to NZM on synchronized Push-Pull concept. In synchronized Push-
Pull concept, the locomotives are connected on the both ends of the rake and are operated
such that the tractive and electrical braking efforts are always synchronized.
iv) RDSO has prepared a modification sheet no. RDSO/2019/EL/MS/0477 (Rev.0) dated
18.06.2019 to elucidate the modification required to facilitate operation of WAP5/WAP7
locos in Push-Pull mode. PS&EMU Directorate issued the modification to be carried out in
coaches vide modification sheet no. RDSO/PE/MS/AC/0080-2019 (Rev. ‘0’).
v) Generic Speed Certificate has been issued vide RDSO letter no. MC/LHB/COACH/Push-
Pull-Gen dated 12.07.2019 for operation of Special Rajdhani Express & similar trains
comprising maximum 22 numbers of LHB AC EOG variant coaches (including two LHB
Generator Vans) in Push-Pull mode operation up to maximum speed of 130 kmph.
vi) Railway Board has also communicated sanction vide letter no. 2019/CEDO/Push Pull/0/1
dated 13.08.2019.
vii) RDSO has issued speed certificate for Special express trains comprising 24 LHB AC/non
AC (EOG) coaches for conducting coupler force including jerk, EBD and COCR trials.
WAP7/WAP5 WAP7/WAP5
Page 8 of 59
viii) For conducting COCR trial for operation of train above 120 kmph and upto 130 kmph,
Sanction of General Manager for conducting COCR based on the JSC signed by all
concerned departments will be required. Zonal Railways shall specify the train composition
and route details for conducting COCR trial.
ix) RDSO has issued a compendium (Report no. RDSO/2019/EL/RM/0188, Rev. 0) on push-
pull operation for better understanding of push-pull operation in short.
Deliberations:
Based on satisfactory trials, generic speed certificate has been issued by RDSO vide
No.MC/LHB/COACH/push pull-Gen dated 12.7.2019. Thereafter, Railway Board have also
accorded sanction vide letter no. 2019/CEDO/Push Pull/0/1 dated 13.8.2019.PCEE/WR pointed out
frequent failures due to communication failures while working Rajdhani trains by using existing
cables meant for miscellaneous purpose like P.A. system etc. for the use of S&T department. It was
also felt necessary that reliable and redundant communication system is essential for reliable
operation of trains in Push-Pull mode. Therefore, it is necessary to carry out the Coach Wiring as
per the modification sheet no. RDSO/PE/MS/AC/0080-2019 (Rev. ‘0’) issued by PS&EMU
Directorate of RDSO. This modification sheet is as per the scheme approved by Railway Board
vide letter no. 2007/Elect(TRS)/440/15 Pt. dated 09.05.2019. Members expressed that redundant
and reliable Coach wiring should be done to ensure proper communication in between front & rear
loco.
PCEE/ECR informed that the contract for the Coach Wiring has been awarded by ER and
work is likely to be completed by Oct’2019. Thereafter, ER will send the proposal for COCR to
RDSO duly complying with all the conditions as stipulated in Railway Board letter
2019/CEDO/Push Pull/0/1 dated 13.8.2019. A copy of compendium on Push-Pull operation was
given all the PCEEs for ready reference.
Members also pointed out for making suitable provision for indication of door
closing/opening if locos in Push-Pull mode are connected with rake comprising of the coaches
whose doors are operated by the guard of the train centrally. It was also pointed out to work on the
interchangeability among various types of propulsion system in Push-Pull mode. At present,
multiple operations of M/s Medha and M/s BHEL have already been tested. Similar efforts are to be
made for other makes also.
Use of DPWCS for push-pull operation was also discussed. It was pointed out that no where
in world, passenger operation is done with wireless communication in push–pull mode.
Recommendations:
(i) Zonal Railways to plan and complete the coach wiring as per the modification sheet no.
RDSO/PE/MS/AC/0080-2019 (Rev. ‘0’) issued by PS&EMU Directorate of RDSO in
compliance to Railway Board guideline issued vide letter no. 2007/Elect(TRS)/440/15 Pt.
dated 09.05.2019
(ii) After comply with the conditions as per Railway Board letter no. 2019/CEDO/Push Pull/0/1
dated 13.8.2019. Zonal Railways may send the proposal for COCR for speed above 120
kmph and upto 130 kmph to RDSO.
(iii) RDSO/CLW should work and finalise the scheme for interchangeability among various
makes of propulsion system.
Page 9 of 59
Railway Board’s decision:
(i) (i) & (iii) may be accepted. Zonal Railways, all PUs (CLW, DLW, DMW, ICF, RCF, MCF)
to ensure compliance by 31.03.2020 under advice to this office.
(ii) It is a reliability improvement measure and should not be considered as mandatory
requirement for induction of push-pull trains. It may further be noted that very first train
(train no. 22221/22 CSMT-NZM Rajdhani Express) was introduced on 13th
Feb’2019 and
still running with same rake without any operational difficulty.
(iii) RDSO to ensure compliance of directives advised in the meeting held on 30.10.19 at
Railway Board, with minutes circulated vide Railway Board letter no. 97/Elect(G)/114/Pt.1
dated 27.11.19. RDSO to examine and consider the option of utilizing both types of
connectors in locomotives and coaches for more flexibility in communication network.
RDSO to ensure compliance by 31.03.2020.
Page 10 of 59
New Item
Item No. : 425
Subject : Adequate availability of Electric trained crew for newly
electrified sections.
Group : ELECT (TRS)
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
1. The electric loco conversion training should be planned well in advance keeping with the
target date for commencement of electric traction.
2. Adequate numbers of instructors should be made available in Zonal Training Centres for
imparting training.
3. Special courses may also be arranged by Zonal Railways in training centres as per need.
Deliberations:
1. Large numbers of ALPs have joined recently. Therefore, ALPs training has to be planned
properly. It was noted that duration of ALP training is different over Zonal Railways.
Moreover, there is inconsistency in policy of giving diesel and electric loco training to
ALPs. Since Electrification is planned for 100% routes, the training of ALP in electric
traction is now essential. Training in diesel traction should be decided by Zonal Railways as
per the local need. Duration of 36 working days training to ALP was considered adequate as
most of the Zonal Railways are following it.
2. Zonal Railways pointed out that psycho test is being conducted at entry level as well as
when LP is promoted to work Rajdhani/ Shatabdi type super fast trains. There is no need of
psycho test at any other stage.
3. Training Centre should be equipped with necessary models and facilities for electric loco
training. Adequate number of instructors should also be available in training centres for
training the ALP in electric traction. Zonal Railways were also requested to use existing
training centres of loco sheds for training the ALPs by deputing suitable number of
instructors in these training centres. It will enhance the training capacity.
4. Where ever engine km earned by electric traction is more than 50%, PCEEs should shift the
crew control to Sr.DEE/Operations in that division.
Recommendations:
(i) Uniform period of 36 working days for initial training to ALPs should be followed by Zonal
Railways.
(ii) All ALPs must be given training in electric traction during their initial training.
(iii) Zonal Railways may upgrade or create training facilities as per the need.
Page 11 of 59
Railway Board’s decision:
May be accepted. EDME (Tr.) may process the case for Board’s approval.
Page 12 of 59
New Item
Item No. : 426
Subject : Automatic activation of Tractive Effort Limiting Switch (TELS)
on vulnerable identified bridges using GPS in locomotives.
Group : ELECT (TRS)
Proposed by : RDSO
RDSO Ref. :
RDSO’s Note:
1. Introduction:
In a normal course the maximum TE generated by WAG9H is about 500 kN. TELS (Tractive- Effort
Limiting Switch) is a feature available in 3-phase electric locomotives to limit the tractive effort to 300 kN.
For the purpose of limiting the TE, a spring loaded switch has been provided on ‘C’ panel on the driver desk
of 3-phase electric locomotives. It has two stable positions namely ‘ON’ & ‘OFF’. The nomenclature used
for this switch is ZTEL. The location of ZTEL is given in fig-1 & fig-2 below:
TE/BE meter for Bogie1 &2
ZTEL Switch
Fig1: Location of ZTEL on Driver Desk
Page 13 of 59
TE/BE meter for Bogie1 &2 ZTEL Switch
Fig 2: Close up of Driver Desk
2. Function of TELS:
The main function of TELS is to limit the TE as per the operational requirements. Whenever the
Tractive Effort is to be restricted within 300 kN, LP operates the switch by bringing master controller to ‘O’
and putting ZTEL in ‘ON’ position. After the operation of ZTEL switch, if LP brings master controller to
max position the generated TE will be limited to 300 kN only. When this switch is in ‘OFF’ position there
will not be any limitation of TE. This TE effort limitation function is implemented in the software of 3-phase
electric locomotive. Whenever, the driver operates ZTEL switch a 110 V signal is generated and is sent to
VCU. The software application in VCU limits the maximum TE to 300 kN.
3. Loco operation on distressed bridges:
Engineering department has identified distressed bridges, where TE has to be limited to 30 T/loco.
Earlier Bridge manual (Para 224 of A&C Slip No.34 dated 04.10.2016) provided following guidelines for
operation of loco with higher TE on such distressed bridges as under-
(i) For allowing higher powered locomotives on old bridges, the TE may have to be limited
(30T/loco) for multiple loco operations.
(ii) TE may be limited by TELS (if provided) OR by controlling the TM current (If TELS is not
provided).
Caution indicator for TE limitation, Indicator for TE limit operation & termination indicator for TE
limitation shall be provided as under:
Page 14 of 59
Case-I: In case of multiple locos in front only X
*= 100 m.
Case-II: In case where multiple locos are provided in mid or rear of train.
X*= Train length upto last Engine + 30 m.
As the operation of TELS is done by the LP, Engineering Department has contended on occasions if
system of TELS is entirely foolproof. They have questioned what if the LP forgets to operate the TELS
while negotiating the distressed bridge.
The solution to obviate such apprehensions is the provision of GPS enabled tractive effort limitation
system.
4. GPS enabled tractive effort limitation system:
In order to eliminate the possibility of overlooking the operation of TELS by mistake by LP the
entire system of tractive effort limitation can be made automatic by providing GPS enabled Tractive Effort
limitation system (GETELS).
5. The components and operation of the GETELS:
The components of the GETELS and its operation shall be as follows:
a. GPS receiver
b. SSD memory containing the GIS location of the distressed bridge.
c. Requisite hardware and software to continuously compare the GIS locations of the distressed bridge
with the current location of the locomotive. It will generate a signal of 110 V DC in case the current
location is within 500 meter of the location (or any suitable programmable location) of the upcoming
distressed bridge.
d. This generated 110 V signal shall be interfaced with the VCU in place the existing TELS signal.
e. The existing application in the VCU shall limit the max TE to 300 kN. Thus, no changes in the VCU
software shall be required.
f. As the VCU shall be interfaced only with the hardwired 110 V signal, the proposed GETELS shall
be interoperable.
Page 15 of 59
In this way, whenever the locomotive shall be within a predefined location of the distressed bridge
the VCU will receive 110 V signal, which will be used to limit the maximum TE of the locomotive to 300
kN.
Block Diagram of propose system
Deliberations:
Some of the PCEEs pointed out that LP would follow the instructions as given in bridge
manual. There is no need to doubt that Loco Pilot would not obey the instructions displayed near
bridge meant to operate TELS to control the Tractive Effort of locomotives. However, there was
other school of thought for minimizing the human intervention to the extent possible. GPS enabled,
tractive effort control will not need any change in loco control electronics. Since arrangement is
simple, it can be provided in few locos on trial basis to see its efficacy.
Recommendations:
RDSO shall prepare Functional Requirements Specification (FRS) for GETELS and based
on this CLW will provide it in 5 locos on trial basis for field trials. Based upon the performance,
decision will be taken for its proliferation duly consulting PCEEs of Zonal Railways. Railway Board’s decision:
May be accepted for commencement of trials along with stringent implementation of
providing caution orders to LP/ALP for locations identified as vulnerable bridges.
Page 16 of 59
New Item
Item No. : 427
Subject : Increase in workshops for repair of 3-phase traction motors.
Group : ELECT (TRS)
Proposed by : NR
RDSO Ref. : EL/3.2.182
Note of proposing Railway:
At present there exist only TMW / NKRD for repair of 3 phase TMs which are quite
distant. With increasing 3-phase locos, there is need to increase workshops to four / five in
nos., which may take care of sheds nearer to them.
RDSO’s Note:
1. Traction motor rewinding for conventional locomotives is presently carried out by
TMW/NKRD, TMS/CNB, KPA & TATA.
2. At present only TMW/NKRD is carrying out repairs of 3 phase traction motors and with
increasing loco holding of 3 phase locomotives, more workshops may be developed for
repair of 3 phase traction motors.
3. Railway Board had already allotted rewinding of 60 Hitachi TM and 100 3-phase TM to
DMW in 2019-20.
4. Present shop capacity for rewinding of 3-phase traction motors is :
TMW/NKRD - 192 stator + 350 Rotors
DMW - 100 stator + 100 Rotors
5. There is already one sanctioned work for ‘Extension of TM Shed Kanpur for rewinding of
Three Phase Traction Motors of Electric Locomotives’ (Pink Book item no. 500 of 2011-12,
Pink Book item no. 637 of 2017-18, Pink Book item no. 672 of 2018-19) at a cost of Rs.
14.07 Crore.
6. KPA & TATA may also be upgraded for repairs of 3-phase traction motors.
7. If arising exceeds the shop capacity, possibility of rewinding of three phase traction motors
through trade may also be explored.
Deliberations:
Sufficient capacity is already available. Moreover, trade is also in a position to meet the
requirement of repair of TMs. Members were unanimous that there is no need to establish any new
workshop for TM repair of 3-phase locomotives.
Page 17 of 59
Recommendations:
(i) NCR should expedite the development of repair facilities for 3-phase loco TMs as per
sanctioned estimate.
(ii) There is no need to develop any additional workshop for 3-phase TMs repair. However,
Kanchrapara and Tata Nagar may develop facilities for 3-phase TM repair as per the need.
Railway Board’s decision:
(i) & (ii) may be accepted. Existing workshops to implement the review and streaming of
processes by removing bottlenecks to improve the productivity. Workshops to take steps for
commencing the repair of 3-phase traction of EMU/MEMU. Target date of implementation-
31.3.2020.
Page 18 of 59
New Item
Item No. : 428
Subject : Incorporation of facility for online transfer of DDS messages on
three locos equipped with RTIS.
Group : ELECT (TRS)
Proposed by : NR
RDSO Ref. :
Note of proposing Railway:
On-line transfer of DDS generated on three phase locos to PPIOs is possible through GPRS.
Since coaching three phase locomotives are being equipped with RTIS, which provides location of
the locomotive / train through satellite and the equipment has additional channel for transfer of
additional small data, DDS generated on 3-phase locos can be easily transferred on line for ease of
the sheds and operations.
RDSO’s Note:
There is possibility for online transfer of DDS messages on three phase locomotives
equipped with RTIS. The scheme requires suitable interfacing of DDS with RTIS which will be
evolved duly consulting the matter with CRIS. As per CRIS during meeting at ELS/GZB,
bidirectional flow of contextual messages is possible through RTIS but is restricted to control
stations. The scope of RTIS will be further enhanced to address the proposal.
Deliberations:
At present about 2300 locos have been provided with RTIS. CRIS have indicated regarding
their willingness to develop the system for transfer of DDS data on their server by using existing
RTIS & GSAT-6 satellite.
However, various modalities require detailed study as given below:
(i) Identification of data to be transferred.
(ii) Format of the data required at CRIS server.
(iii) Compatibility for data transfer with various makes of propulsion system.
For above, a detailed proposal from CRIS is required indicating the feasibility and its cost.
Thereafter, decision should be taken in this regard.
Recommendations:
RDSO should interact with CRIS for getting the details for transfer of DDS data as proposed
by NR and apprise the Railway Board for needful action.
Page 19 of 59
Railway Board’s decision:
May be accepted. RDSO may formulate action plan for interfacing of VCU with RTIS and
on-line transfer of DDS data. Target date of completion- 31.03.2020.
Page 20 of 59
New Item
Item No. : 429
Subject : 160 kmph OHE up-gradation- options available.
Group : T.I.
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
When Gatiman express was introduced in Palwal-Agra Section at 160 kmph, there were
several cases of Panto entanglement at turnout locations. RDSO report no.
TI/Report/OHE/2016/00114 on the rubbing marks on Pantographs during run of Gatimaan Express
at 160 kmph prepared by CEDE/NR, CEDE/NCR and EDTI (Co.ord.)/RDSO was sent to Railway
Board vide this office letter no. TI/OHE/HS/10/04 dated 08.06.2016.
Railway Board accepted the recommendation of the report and issued guideline for OHE
modification to the NR and NCR, vide letter no. 2003/RE/161/1 Vol-III/pt dated 13.06.2016. Based
on successful trial run of Gatiman express, Railway Board issued the guidelines to Zonal Railways
for running one or two trains on trial basis on Delhi-Mumbai & Delhi-Howrah Route.
Number of trains, which can be run at 160 kmph are limited by the OHE capacity of 600
Amp. For running more trains Up-gradation of OHE capacity will also be necessary. Number of
trains will depend upon type of signaling- Automatic or absolute block. One 24 coach train, at 160
kmph may require 10 MVA power. Hence more than one train will overload existing OHE of 600
A, 15 MVA capacity.
For up-gradation of OHE following option are available:
CATENARY WIRE 65 SQ. MM Cd Cu
CONTACT WIRE (i) 107 Sq. mm HDGC contact wire-600Amp
(ii) 107 Sq.mm Silver Bearing Copper Contact wire 785Amp
(iii) 150Sq.mm Copper contact wire-800 Amp
FEEDER WIRE
ARRANGEMENT
Provision of 234 sqmm all aluminum spider conductor (Feeder
Wire) current carrying capacity 665 Amp.
PSI Up-gradation:
• On the basis of the study for Power Supply requirements based on the calculations results,
following assessment is arrived at:
• The existing 2 X 21.6/30 MVA 25 kV system can cater maximum 4 (2 each in both lines)
nos. of HS trains through one TSS feed. The far end voltage in this condition will be 24.9
Page 21 of 59
kV. If the number of trains is increased beyond this the transformer current will exceed its
rated current.
• The power supply can be augmented by providing one additional 21.6 MVA transformer
and using the two 21.6/30 MVA transformer for feeding separately on both sides of PTFE,
while the third one will be stand by. In this condition the TSS can power maximum 10
trains (5 each in both lines) through one TSS and the far end Voltage in this condition will
be 22.7 kV.
• For further augmentation of the TSS 3X30/40 MVA transformers can be provided in place
of 3X21.6/30 MVA transformers. In this condition this TSS can power maximum 14 trains
(7 each in both lines) through one TSS and the far end voltage in this condition will be 22
kV.
Deliberations:
It was decided that 150 sq.mm copper feeder wire on new masts will be preferable for
enhancing the capacity of OHE instead of spider conductor. For power supply augmentation,
reduction in size of sub-stations and AT stations will be required, if 2x25kv system is to be adopted.
TSS capacity augmentation of 25 KV system can also be achieved by providing a 3rd transformer
of 21.6/30 MVA in the existing sub-stations so that separate transformers feed on both sides of
insulated overlap/PTFE and 3rd transformer can act as standby. Augmentation of infrastructure for
receiving required amount of power at each TSS will also have to be done depending upon the
requirements on case to case basis.
Recommendations: (i) RDSO to study the actual enhancement in capacity with provision of feeder.
(ii) RDSO to study & finalize layout for TSS & AT stations for 2x25 kV system with reduced space
requirement.
(iii) Concerned Zonal Railways to submit details of power supply system, including transmission lines,
to RDSO.
Railway Board’s decision:
May be accepted.
Page 22 of 59
New Item
Item No. : 430
Subject : Courses module at IRIEEN- In light of new advances in electrical
department.
Group : EEM
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
Course modules on following topics may be developed at IRIEEN:
(a) EEM:
BMIS, SCADA, Smart Metering, smart Grid, Pump automation, Modern Switch Gears, packaged
type sub-stations, lifts escalators, green building, renewable energy-solar, wind etc.
(b) T.I.:
Standards & traction technology for high speed (200 kmph & above).
(c) Elect.(TRS):
End of train Telemetric (EOTT), Distributed Power Wireless Control System (DPWCS), Train
Collision Avoidance System (TCAS), Train Protection Warning System (TPWS), Remote
Diagnostic System (RDS), procedure certifications for Introduction of new rolling stock and State of
art of electric loco technology.
Deliberations:
(i) The Committee members were of the view that all the items related to new technology, current
development related to Energy Management and softwares being used for Indian Railways in its day
to day operation should be included in the course module of IRIEEN. Some of the topics in this area
are Electricity Act, Energy Conservation, Energy Audit, FOIS, CMS, Rail Saver, TMS package and
should be considered for inclusion in the new module.
(ii) Railway Board desired that experts from Bureau of Energy Efficiency (BEE) and other Institutes
may be called as Guest Lecturer for imparting training on current topics related to Energy
Management. The modules for Probationers and posted other officers should be updated separately.
(iii) Director/IREEN however pointed out that the response of the Zonal Railways in sending the
nominated officers for different trainings is very poor, although the matter is followed up regularly
before commencement of any course with the Zonal Railways. Sometimes, even the nominations are
Page 23 of 59
not made. Only a few Railways are particular about sending officers for training and many a times
the training is required to be cancelled, if the number of participants is less than three.
Recommendations:
(i) IRIEEN should consider upgrading of training modules for Probationers and posted officers
separately based on the latest developments/technology in use on IR as mentioned above.
(ii) Zonal Railways should assist IRIEEN in development of training modules for new topics and send
their officers to IRIEEN for imparting training and generating more interest in the subject among the
trainee officers.
(iii) Outside experts/Guest Lecturers from BEE and other Institutes should also be called regularly by
IREEN on recent topics/subjects.
(iv) Simulators for 3 phase electric loco and other rolling stock may be procured and installed by
IRIEEN for giving hands on training to the trainee officers.
Railway Board’s decision:
May be accepted with slight correction in point (iv),
(iv) Models for 3-phase electric loco and other rolling stock may be procured and installed by
IRIEEN for giving hands on training to the trainee officers.
Page 24 of 59
New Item
Item No. : 431
Subject : New technological up-gradation and advances – in TRD and ‘G’
services.
Group : T.I.
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
Development of Copper Magnesium Catenary Wire:
• In 25 kV traction system, cadmium copper catenary wire is used in OHE.
• As Cadmium is hazardous and not environment friendly, world over railways are using other alloy like
Copper Magnesium or Copper Tin in place of Copper Cadmium.
• RDSO have prepared a draft specification (TI/SPC/OHE/CAT(Cu-Mg)/0150(11/2016)) for Copper
Magnesium Catenary Wire and got approval of Railway Board for further development.
• Expression of Interest (EOI) was called for development of Copper Magnesium Catenary Wire.
• As per response of EOI, Select Panel of 15 Vendors was formed and deliberations on draft specification
and STR were taken. Based on this final draft specification and STR was issued.
• Prototype testing of two firms namely M/s APAR Industries Ltd. and M/s VTL has been conducted and
test results are as per RDSO specification.
• Mechanical and Electrical Properties like Tensile strength, Resistance of Cu-Mg catenary wire are
similar to Cu-Cd catenary wire
• CORE (200-225 MT) and ECoR (75-100 MT) have been advised to procure Cu-Mg catenary wire and
put on field trials.
Development of spring type regulating equipment:
• Railway Board Vide letter no. 2014RE/161/19/Vol.1 (FTS: 144644), New Delhi dated 31.12.2015
instructed that “RDSO may finalize the specification of spring type ATD and develop sources for the
same.”
• In compliance of the above, the specification no. TI/SPC/OHE/SPRING ATD/ 0110 (03/2012) for
Spring based Auto Tensioning Device has been finalized on 28.01.2016.
• Application: Applicable for places where space is constraint like tunnel/Viaduct.
• Two Firms, M/s D2 Engineering Seoul Korea and M/s Pfisterer Ltd. applied for manufacturing and
supply of Spring ATD, in which M/s Pfisterer Ltd. were rejected due to non submission of compliance of
documents as per ISO.
• Proto type test has been carried out of M/s D2 ENGINEERING Co. Limited Seoul, South Korea. Test
reports are under scrutiny.
Page 25 of 59
Development of Automatic Phase Switching Section (APSS) for 25 kV single phase 50 Hz AC
traction power supply system:
• The APSS has been developed to facilitate automatic changeover of supply coming from different
phases as soon as the electric loco/EMU negotiates the IOLs meant for phase separation. No neutral
section is required in APSS for separation of different phase supply at SP and hence, loco pilot can run
the train at desired speed without any hassle and stress and without worrying about DJ ON/OFF.
Deliberations:
i) Development of copper magnesium catenary wire: CORE enquired about the locations for trial.
It was suggested that CORE may do trial at places near RDSO/LKO and ECoR may decide the
location of trial in areas having high corrosive atmosphere.
ii) Development of spring type regulating equipment:
The prototype test has been successfully carried out during 15th
to 19 April’2019 and 17th
to 19th
July’2019 for spring ATD of M/s D2 Engineering, Seoul, Korea. The field trial approval is in
progress.
(iii)Development of Automatic Phase Switching Sections (APSS) for 25 kV Single phase 50 Hz AC
traction power supply system:
The trial has been successfully completed. However, it was felt that ASPS should be installed
in some more locations to prove its utility and performance.
Recommendations:
(i) The trial for 65 sq.mm. Cu-Mg catenary wire may be conducted by CORE/ ECoR as already
advised.
(ii) Ductability test should also be included in the specification, if not available.
(iii) Central Railway shall provide one set of Automatic Phase Switching Section (ASPS) in each
division.
Railway Board’s decision:
May be accepted with following correction in point (i) & (iii):
(i) The trial for 65 sq.mm. Cu-Mg catenary wire may be conducted by CORE/ECoR as already
advised. CORE & ECoR to conduct trial by Nov’2020.
(iii)Central Railway shall provide one set of Automatic Phase Switching Section (APSS) in each
division. CR to provide one set by Nov’2020.
Page 26 of 59
New Item
Item No. : 432
Subject : SCADA requirement and up-gradation needed- In light of open
access.
Group : T.I.
Proposed by : Railway Board
RDSO Ref. :
Note of proposing Railway:
• Energy management system is already explained in section-9 of SCADA specification no.
TI/SPC/RCC/SCADA/ 0130 (Rev.2) issued in July 2016. Load profile parameters required
for open access is available at RCC.
• It is not feasible to upgrade old SCADA to meet the requirement of OPEN access.
Deliberations:
It was informed by RDSO that specification No. TI/SPC/RCC/SCADA/0130 (Rev’2’),
effective from 26.7.2016 contains all the required provisions to suit open access. However, SCADA
systems procured through older specifications may need replacement in order to implement the new
features. It was informed by EDRE/Rly. Board that instructions regarding maintenance of OFC
links between switching stations & Railway stations have been issued by Board. Recommendations:
(i) Replacement of SCADA system may be taken up by the railways going in for open access,
on need basis.
(ii) A committee of ED/TI/ RDSO & ED/Tele/ RDSO has been constituted by Rly. Board for
looking into issues of availability of E-1 channel. Railway Board’s decision:
May be accepted.
Page 27 of 59
New Item
Item No. : 433
Subject : Procurement Policy of Lift and Escalator.
Group : EEM
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
1. Zonal Railways are procuring lifts & escalators through open tenders till development of
approved vendors by RDSO.
2. RDSO had formulated specification for Lift/Elevator during 2013. The
modification/improvement in this specification based on stakeholder’s feedback was made in
2016. This specification has still not been validated since board has directed ZRs to procure
lifts as per CPWD system/specification.(ref.: Railway Board’s letter no.
2013/Elect(G)/150/13/Pt II dated 13.06.2019). Zonal Railways have to procure lifts as per
CPWD specifications vide Railway Board’s letter no. 2015/Elect(G)/150/2 dated 07.04.2015. It
is suggested that procurement of Elevator/Lift should be done as per RDSO specification no.
RDSO/2013/EM/SPEC/0016 (Rev ‘0’), Amendent.1 for two to three P.Os for stations, which
are less sensitive. Based on the experience of first few procurement of Elevator/Lift as per
RDSO specification the necessary changes in the specification may be made and further
procurement over Indian Railways may be done as per RDSO specification.
Escalators are being procured as per RDSO specification no. RDSO/PE/SPEC/TL/0095
(Rev.2)-2017.Escalator is being procured from open tender. Prototype test of Escalator has
been delegated to Zonal Railways vide SN 3(d) of Railway Board’s letter no.
2003/Elect(G)/161/1/Vol-III/Pt dated 03/05.12.2018.
Deliberations:
(i) RDSO informed that at present CPWD specification is being used for procurement of lifts by
Zonal Railways and for escalators, the existing practice is to procure as per RDSO
specification. Suggestions for eligibility criterion in tender specifications have been sent to
Railway Board.
(ii) Railway Board informed that eligibility criteria for lifts and escalators to be included in the
tender specification are under finalization and would be issued shortly.
(iii) The Committee members were generally of the view that we should use generic specification
for lifts and escalators and should not have a specification which is too restrictive in nature and
inhibits participation by prospective bidders.
Page 28 of 59
Recommendations:
(i) The existing practice of procurement of lifts as per CPWD specification and procurement of
escalators as per RDSO’s specification may be continued by Railways. However, the
performance of these equipment by different suppliers may be monitored by Zonal Railways
and feedback given to RDSO regularly.
(ii) Zonal Railways may follow the eligibility criteria for procurement of these items once it is
notified by Railway Board.
Railway Board’s decision:
May be accepted with slight correction in point (i) & (ii):
(i) The existing practice of procurement of lifts as per CPWD specification and procurement of
escalators as per RDSO’s specification may be continued by Railways. However, the
performance of these equipment by different suppliers may be monitored by RDSO/Zonal
Railways and feedback given to RDSO regularly.
(ii) Zonal Railways may follow the eligibility criteria for procurement of these items.
Page 29 of 59
New Item
Item No. : 434
Subject : Review of Height of top member of gauge at LC gates in
Electrified sections – amendment to ACTM.
Group : T.I.
Proposed by : SWR
RDSO Ref. :
Note of proposing Railway:
As per item 11.2 (e) of Appendix-VIII of ACTM Vol. II (Page no. 151) the height of top
member of height gauge shall not exceed 4.67 metre and further Pare 3 (iii) of Chapter V-A of
Schedule-I of IRSOD-2004 stipulates that minimum height of contact wire from rail level at LC
gates to be kept at minimum 5.5 metre.
At few places, State Authorities have seriously objected for erecting height gauge at 4.67
metre especially on highway roads, City suburbs, road leading to industrial belts etc. during
electrification and have demanded for higher height. Railway Board has also mentioned regarding
request received from Ministry of Commerce for raising height of the boom gauge at LC so that
trucks of height upto 4.75 metre can pass, vide letter no. 2008/Elect(G)/161/8 Punct dated
02.05.2019.
There have been cases where top member of the height gauge has got dislodged /damaged
because of the movement of container with height more than 4.7 metre.
As per the dimension given in ACTM, for contact wire height and height gauge, a clearance
of 830 mm (5500 mm – 4670 mm) is to be maintained between lowest OHE conductor and top
member of height gauge. In view of the revised long time clearance from 320 mm to 250 mm,
clearance of 830 mm can be further reduced by 70 mm, i.e. clearance of 760 mm can be adopted
instead of 830 mm.
Further, as per latest guidelines, height of the contact wire adopted in open section is 5.8
metre from the rail level. If this height is maintained even at LC gate, it gives a flexibility of further
300 mm for height of height gauge.
Therefore, it is proposed that the height of top member of LC gauge above the road shall be
maintained so that it will be lower by at least 760 mm from the contact wire i.e. it shall be between
5040 to 4740 mm, depending upon the locations where wire height is maintained between 5.80
metre to 5.50 metre. Even if height of contact wire is maintained at least at 5.50 metre as at present,
the height of LC gauge can be kept as 4740 mm.
Accordingly relevant Para in ACTM are required to be amended. In this connection a
proposal has been sent to Railway Board vide letter no. SWR/EL/T-601 dated 6.07.2016.
Page 30 of 59
RDSO’s Note:
Vide RDSO’s letter no. TI/OHE/GA/2018 dated 06.08.2019, following proposal for changes in the
height gauge have been sent to Railway Board:
a) Clearances of height gauge from ground has been fixed at 4.77 m.
b) Following drawing of height gauges has been revised:
1. TI/DRG/CIV/H.GAUGE/RDSO/00001/14/0 (Mod. B) for standard plan height gauge for level
crossing (for clear span 7.3 m to 10m).
2. TI/DRG/CIV/H.GAUGE/RDSO/00001/05/0 (Mod. A) for standard plan height gauge for level
crossing (for clear span 7.3 m).
3. TI/DRG/CIV/H.GAUGE/RDSO/00002/05/0 (Mod. A) for standard plan height gauge for level
crossing (for clear span 7.3 m upto 12.2 m).
c) Draft A & C Slip no. to ACTM Vol II Part I for modification in Proforma 10.02 (Para 21020) &
ACTM Vol II Part II Appendix-VIII, Para 11.2 (e).
Deliberations:
RDSO informed that recommendations have already been submitted to Railway Board vide
letter no. TI/OHE/GA/2018 dated 06.8.2019.
Recommendations:
Railway Board has issued Advance Correction Slip no. 30. Same will be again reiterated.
Railway Board’s decision:
May be accepted.
Page 31 of 59
New Item
Item No : 435
Subject : Replacement of overhead track crossing up to 66 kV by
underground cable and use of mono pole in place of tower.
Group : T.I.
Proposed By : SECR
RDSO Ref. :
Note of proposing Railway:
As per Regulation for Power Line Crossings of Railway Track 1987-
(i) All Track crossings up to 11 kV are to be underground.
(ii) Track Crossings up to 33 kV may be modified to underground cable.
It is creating confusion for the executing agencies whether to modify 33 kV overhead Lines,
which already has sufficient clearance as per IRSOD. Now reliable cables are being
manufactured up to 132 kV and are being used by Vidyut Prasaran Nigams. Moreover,
Right of Way is a major problem in the inhabited areas and difficult to erect towers and
Overhead crossings.
It is, therefore, proposed to:
(i) Use underground cables up to 66 kV Power Line Track Crossing modifications.
(ii) Use of Mono-Pole in place of tower.
RDSO’s Note:
1. As per Addendum & Corrigendum slip no. 20 of IRSOD (BG), Revised 2004 & Addendum
& Corrigendum slip no. 27 to ACTM Vol. II Part II appendix-IV-1994, upto and including
11 kV, power line crossing should be by underground cable.
Further as per Para no. 7 of chapter no. 4 of AC Traction manual Volume II, Part II-
“Regulation of power line crossing of Railway Tracks” – All low, medium and high voltage
upto and including 11kV crossing(s) shall normally be done by means of underground
cable(s). While for voltage higher than 11kV, crossings may be overhead lines or
underground cables, the use of underground cable to the extent possible would be
advantageous particularly for 22 kV and 33 kV system.
Underground cable installation is expensive. There are large no. of existing 33 kV overhead
crossings. Replacement of these by underground cable will increase cost of electrification.
It is easier to detect and repair faults in overhead lines. The overhead lines are better suited
to carry higher voltages compared to the underground cables, which are limited by the
expensive construction and limited heat dissipation. For these reasons, the underground
Page 32 of 59
cables are mostly used for transmitting up to 33 kV. For 33 kV line protection system with
fast acting Relay & CB are mandatory.
Existing 33 kV overhead power line crossing can continue, if clearances are available as per IRSOD.
New power line crossings, upto 33 kV can be provided with underground cable instead of overhead
lines on case to case basis with the approval of PCEE of the Railway.
2. In power line crossing various clearances is checked for the compliance of IR SOD/ACTM. The
suitability of the Mono pole for the power line crossing should be checked in the light of guidelines
given in the annexure A.4.01 of Appendix IV of ACTM Volume II, Part-II. Mono poles have
following advantages over Tower.
a) Requirement of Small foundation.
b) Issue of ROW is less.
c) Fast & easy erection.
Dis-advantages:
a) For erection purpose crane is required at site.
b) It is more expensive than Tower.
Deliberations:
Presently, it is mandatory to replace 11 kV overhead track crossings without cable while
doing the electrification of the section. It was discussed that 33 kV/66 kV overhead track crossings
in electrified sections are frequently failing causing serious disruption to traffic and these should
also be considered for replacement with underground cable.
Recommendations:
RDSO to submit the draft A&C slip to include 66 kV overhead crossings also, as ‘desirable
to be converted into underground cable crossing’.
Railway Board’s decision:
May be accepted with following:
RDSO to collect data and study the impact on execution of on-going works. New 33 kV
overhead crossings, however, if laid by DISCOMs/SEBs should be of underground cable crossings.
Page 33 of 59
New Item
Item No. : 436
Subject : Standardization of luminaries fittings for PFs, Street light, Yards,
Washing lines & Circulating areas & Railway colony.
Group : EEM
Proposed by : NR
RDSO Ref. : EL/EM/0122/ESC
Note of proposing Railway:
As on date the dimension of different size pole and different watt fitting is not standardised,
difficulty being faced at the time of replacement.
RDSO’s Note:
Several kinds of luminaires/ fittings are available in market & new fittings, etc. are getting
developed with technological advancements. Therefore, replacement by same luminaires or fittings
at the time of replacement will not be appropriate in most of the cases and earlier fittings will not be
available in the market itself in many cases.
Hence such standardization is not desirable. Furthermore selection of fittings has to take
local conditions into account like max / min temperature, wind condition, corrosion prone section
(costal region), proneness to theft etc.
Therefore, selection of luminaires/ fittings may be left to PCEE to suit local conditions.
Deliberations:
(i) It was discussed and considered by the group that the technology for luminaires/fittings to
be used by Indian Railways is changing at a very fast pace and its requirement also depends
on the climatic conditions, geographical locations where they would be used. Therefore its
standardization may not be useful for the Railways. Each Platform, Yard, Washing lines,
Circulating areas, Railway Colony etc has its own peculiarity and design and uniform
specification may not help in such conditions.
(ii) Illumination levels in Lux have already been defined by Railway Board at important
locations/assets of Railways in its communication in February, 2019, which may be
followed by them.
Recommendations:
The existing practice of procurement of luminaires/fittings by different Zonal Railways
depending upon their requirement may be continued.
Page 34 of 59
Railway Board’s decision:
May be accepted with slight correction:
The existing practice of procurement of luminaires/fittings by different Zonal Railways
depending upon their requirement may be continued. Zonal Railways to take decision as per site
requirement.
Page 35 of 59
New Item
Item No. : 437
Subject : Standardization of Electrical vehicle charging station at Railway
station & their running policy.
Group : EEM
Proposed by : NR
RDSO Ref. : EL/EM/0122/ESC
Note of proposing Railway:
Different size, wattage, facility etc. charging station available in market.
RDSO’s Note:
Board vide letter no. 2011/Elect(G)/150/3(Dup) dated 21.08.19 has advised Zonal Railways
to download the policy issued by MoP for setting up of e-charging stations at Railway Stations and
Railway Office complexes preferably near parking area.
Currently, there is no standard for defining design requirement of electrical vehicle charging
station. However, International Electro-Technical Commission has classified these charging
stations in four modes depending upon connection scheme and speed of charging. As per Ministry
of Power (MoP) circular no. 12/2/2018-EV dated 14.12.18 Public charging station shall have one or
more electric boards with installation of all the chargers models as follows:
Table
Charger type Charger connectors* Rated voltage (V) No. of charging
points/no. of connector
guns (CG)
Fast CCS (Min 50kW) 200-1000 1/1 CG
CHAdeMO (Min 50kW) 200-1000 1/1 CG
Type -2 AC (min 22kW) 380-480 1/1 CG
Slow/Moderate Bharat DC-001 (15kW) 72-200 1/1 CG
Bharat AC-001 (10kW) 230 3/3 CG of 3.3kW each
The standard specification of the equipments/product to be used in charging infrastructure
considering the interoperability of the device is being developed by BIS. The safety standard
requires are also being developed by Central Electricity Authority (CEA). The protocol for
verification of equipment with respect to standard is being developed by ARAI, ICAT.
Till these agencies prepare necessary technical requirements, the Zonal Railways may
identify suitable locations and density/penetration of charging. It is estimated that for two charging
stations minimum 200 kW additional load will be added. The capacity of existing transformer and
cabling requirement may be assessed for enhancement in order to connect these additional loads.
Page 36 of 59
Commercial vehicle charging place may be developed at Railway Station. The facility may
be developed by Railway and its operation may be outsourced with collection of usage charges
depending on energy consumption and fixed charges based on the expenditure incurred in
development of facility.
Deliberations:
(i) RDSO informed that this being a new item, there is no specification for the same at present.
However, Ministry of Power and Department of Heavy Industry under Ministry of Heavy
Industry have issued certain guidelines and its specification is being developed by Bureau of
Energy Efficiency (BEE). Some Zonal Railways informed that contractors who have been
allotted parking area at Railway Stations have tied up with concerned State Government and
started providing the Electrical Vehicle charging stations at some places, where subsidy is
availed and Non Fare Revenue (NFR) also gets generated.
(ii) It was generally felt by the Committee Members that this item is a new item and we should
wait for some time before its specification can be developed by Railways.
Recommendations:
(i) The matter will be pursued with BEE for finalization of specification by them. Zonal
Railways may be permitted to continue provision of EV Charging stations at vehicle
targeting locations and share their experience with RDSO/Railway Board.
(ii) Zonal Railways should develop adequate power supply arrangement for installation of this
equipment.
Railway Board’s decision:
May be accepted with slight correction in point (ii) as follows:
(ii) Zonal Railways should develop adequate power supply arrangement for installation of this
equipment, as per requirement.
Page 37 of 59
New Item
Item No. : 438
Subject : Tower Wagon Maintenance.
Group : T.I.
Proposed by : NR
RDSO Ref. :
Note of proposing Railway:
The number of OHE depots & Tower Wagons is going to almost double in near future due
rapid electrification. However, the Shed/Workshop presently nominated for POH for Tower
Wagons are already getting over loaded and are not able to meet the requirement of POH/ Major
repair of tower wagons. In the recent cases of axle breakage in two Tower Wagons in Northern
Railway, even the drawings of axle were not available in EMU Car Shed/GZB & RDSO.
EMU/Cars Shed/GZB as well as DMW Patiala have not been able to repair the same for past more
than one year. Therefore, ESC may deliberate on the future course of action.
RDSO’s Note:
In view of the mission 100% electrification, the population of Tower Wagons for attending
break down/maintenance of electrified routes will increase significantly. Considering
electrification of 65000 RKM of Indian Railway BG Network in the next few years there
will be approx. 1000 Tower Wagon in service. If periodicity of POH is taken as 6 years then
every year 167 Tower wagon will required to be POHed. Therefore, it suggested that a
diesel/electric loco shed may be nominated for POH of Tower Wagons. Review of
periodicity of POH is also under consideration at RDSO. However, even after review, the
no. of Tower Wagon is going to increase manifold.
USFD test on axles of Tower Wagons to be carried as per RDSO’s SMI no. TI/MI/0043
Rev.2 (for 8-Wheeler) & TI/MI/0052 Rev.’0’ (for 4-Wheeler).
As per RDSO’s Specification for 8-W DETC and 8-W DHTW, complete set of drawings to
be supplied by Tower Wagon manufacturer to the purchaser with Tower Wagon. Therefore,
required drawings may be obtained from Railways/manufacturer of tower Wagon.
Deliberations:
It was discussed that due to sharp increase in the number of tower wagons as a result of
100% electrification, it is necessary to develop facilities for POH of tower wagon as the existing
system of using workshops and EMU sheds for POH of tower wagon is not able to cater to the
requirements. The practice of ‘safe to run’ examination by Mechanical Department is also required
to be reviewed. Periodicity of POH of Tower Wagon also needs to be reviewed.
Page 38 of 59
Recommendations:
A committee consisting of EDRE/Railway Board, ED/TI/ RDSO (Convenor), CEDE/NCR &
CEDE/NWR is nominated to deliberate on the issues and submit recommendations.
Railway Board’s decision:
May be accepted with slight correction:
A committee consisting of EDRE/Railway Board, ED/TI/ RDSO (Convenor), CEDE/NCR
& CEDE/NWR is nominated to deliberate on the issues and submit recommendations. Committee
to submit report by 31.03.2020.
Page 39 of 59
New Item
Item No. : 439
Subject : Creation of man power for TRD maintenance of additional assets
by transferring man power of Diesel loco maintenance
proportionately to the extent of reduction in Diesel locos.
Group : T.I.
Proposed by : SCR
RDSO Ref. :
Note of proposing Railway:
With electrification of new sections there is an increase in TRD assets which calls for
creation of proportionate man power required for end to end maintenance. The proportion of
Electric loco hauled trains would increase, with corresponding reduction in Diesel loco hauled
trains. Railways have already started the exercise to take up maintenance of electric locomotives in
diesel sheds as per the Board guidelines vide lt. no.2016/Elec(TRS)/138/17 dated 17.1.17 and
28.9.2017 and RDSO Technical circular no. 0138.
Progressively with increasing electrification the infrastructure as well as the existing man-
power of diesel loco sheds will transform to a resource for electric locomotives and traction
distribution (TRD). As diesel locos in diesel shed are being replaced with Electric locos, there is a
reduction in the man power required for maintenance, as the electric loco requires less maintenance
compared to diesel loco, ultimately accounting to saving in men required for maintenance. Hence,
there is a saving in man power by the difference in number of men required for maintenance of
diesel loco vis-a-vis electric loco. This man power saved can be utilized as a man power bank for
creation of maintenance staff for TRD for the newly electrified sections.
For a clear understanding of the proposal, let us assume that the men required for
maintenance of a diesel loco is ‘A’, and the men required for maintenance of electric loco is ‘B’,
and also assuming that ‘N’ diesel locomotives are replaced with electric locomotives then:
Man power saving for ‘N’ diesel locomotives replaced with electric locomotives is say ‘S’,
‘S’ = (A-B)*N.
This surplus man power bank ‘S is proposed for utilization towards creation of manpower
required for maintenance of TRD assets.
The committee may deliberate on the proposal which accounts for creation of man power
required for TRD maintenance.
RDSO’s Note:
There is one school of thought to outsource all PSI activities and some OHE activities and the
yardstick to be revised suitably to reduce the requirement of posts to minimum.
Page 40 of 59
Deliberations:
Yardstick for maintenance staff required for mainline OHE has been reduced from 0.45 staff
per TKM to 0.22 staff per TKM. Posts required as per latest yardstick are to be created after
adjusting the surpluses at other divisions/railways.
Recommendations:
Vacancies to be transferred to other Railways requiring new creations.
Railway Board’s decision:
May be accepted with slight correction:
Vacancies to be created as per laid down policies from time to time.
Page 41 of 59
New Item
Item No. : 440
Subject : Elimination of one power car from HOG compliant mixed trains.
Group : ELECT (G)
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
As per decision of Rolling Stock Directorate of Railway Board, one of the power car has
been decided to be replaced by a SLRD equipped with HOG switch board cabinet but without DA
sets, from the mixed trains running on HOG system. One power car on other end will be retained.
Under emergent condition arising due to discontinuity in both the 750 V feeders & failure of
HOG loco/OHE will result into non-working of even ventilation system in AC coaches. (existing
battery-75 Ah is not adequate to feed blower motor for required period of time).
Non working of blower will lead to suffocation in AC coaches & consequent agitation from
the passenger.
To provide working of Air-conditioning for at least 3 hrs & ventilation for over 5 hrs.
Proposal to provide 1100/650 Ah battery & 2/1, 25 kVA inverters as stand by in EOG/HOG
AC coach is therefore agreed to keeping the passengers comfort in view.
Since in non AC coaches, 120 Ah battery is already available which can cater lighting & fan
load for over 3 hours, no changes are required.
Since this is an important technical issue hence comes under the ambit of Railway Board
order 2019/O&M/8/3 dated 18.07.19.
Deliberations:
(i) Committee members were of the view that to avoid inconvenience to passengers even under
extreme exigency, it is desirable to provide one power car on each end. Number of DA set
per power car can however be one or two depending on the train hotel load.
(ii) Provision of power cars on each end can however be reviewed in case of train being hauled
by locos in push pull mode. In that case only one power car to take care of OHE failure for a
limited period of time.
(iii) In case, one of the power car is planned to be replaced by SLR, it would be necessary to
provide adequate battery backup for working partial AC for about 3 hrs in AC coaches. For
this standard capacity battery along with 25 kVA inverters can be provided.
Page 42 of 59
(iv) The trials with permanent magnet alternator developed for FIAT bogie up to 130 kmph may
also be pursued. It may be utilized for RAs on LHB platform.
Recommendations:
(i) For mixed trains planned to be provided with SLR in place of one of the power car,
provision of adequate capacity battery & 25 kVA inverter may be made in AC coaches.
(ii) Push-pull operation of trains to be proliferated.
Railway Board’s decision:
(i) It is recommended that one power car may be eliminated from HOG compliant LSLRD
coach.
(ii) A committee consisting of CESE/ER as Convener and CESE/NR, CESE/WR,
Director/TLAC system design/RDSO as members has been formed to frame guidelines for
working of such trains (TDC: 31.01.2020).
(iii) 25 kVA inverter may not be provided in AC coaches. In its place 300 Ah battery to be
provided for light/fan & blower motor for ventilation. RDSO should study & give its
feedback. This may facilitate removal of one power car also (TDC: 30.06.2020).
Page 43 of 59
New Item
Item No. : 441
Subject : Digital Train Communication Network (TCN) for EOG/HOG
trains.
Group : ELECT (G)
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
Day by day more & more automated sub systems like automated door control, CCTV
surveillance, fire detection & suppression system etc. are being introduced on LHB variant of
coaches. Moreover, Railway is also working on push pull hauled trains.
To provide effective train communication for all automated systems and also to cater
requirements of push-pull mode operation, proposal to provide train communication with
appropriate redundancy and integrating all the existing and future requirements will be good step.
It is however, worth pointing out that with the adoption of TCN, flexibility of any coach
detachment/ attachment will be lost as it will require updation in TCMS, the modalites for which
will have to be worked out.
Since this is an important technical issue hence comes under the ambit of Railway Board
order 2019/O&M/8/3 dated 18.07.19.
Deliberations:
(i) TCN may be developed for coaches with DDU/HMI placed in end coaches (SLR or power
car).
(ii) Only safety related signals viz. all doors closed indication (if automated doors provided),
fire alarm, air spring failure indication etc should be interfaced with VCU of locomotive.
(iii) Provision of TCN will however reduce the flexibility of attachment /detachment of
individual coach.
Recommendations:
TCN as per international standard & open protocol may be developed.
Railway Board’s decision:
(i) TCN may be developed for coaches with Digital Display Unit (DDU)/Human Machine
Interface (HMI) placed in power car or LSLRD.
Page 44 of 59
(ii) Safety related inputs like all doors close indication (if doors available), Fire alarm,
Passenger Chain pulling, air spring failure.
Page 45 of 59
New Item
Item No. : 442
Subject : Electric power supply voltage (110 or 230V) in passenger area of
departmental coaches.
Group : ELECT (G)
Proposed by : Railway Board
RDSO Ref. :
RDSO’s Note:
As per RDSO’s code of practices for electric wiring/prevention of fires in coaches
(EL/TL/48, EL/TL/56, ELPS/SPEC/EOG/01-March’1994) only 110 DC/AC (nominal voltage) is
permissible in passenger area. It is however indispensable to provide, supply/ appliances working
on 230 V & above in departmental coaches which run under the direct supervision of Railways
trained staff.
It is therefore recommended that necessary amendment in the RDSO code of practices may
be authorized.
Since this is an important technical issue hence comes under the ambit of Railway Board
order 2019/O&M/8/3 dated 18.07.19.
Deliberations:
(i) Any voltage higher than 110V AC/DC poses fire & Electrical safety hazard.
(ii) Even in inspection cars, all appliances/sockets should be 110 AC/DC operated.
(iii) No voltage higher than 110V AC/DC should be accessible to passenger/ human beings in all
type of coaches including inspection car & departmental coaches.
Recommendations:
RDSO’s code of practices should be strictly followed for all type of coach including RAs &
departmental coaches.
Railway Board’s decision:
(i) In all coaches carrying passenger should have 110 V DC/AC supply or less.
(ii) In coaches carrying Railway staff can have power supply upto maximum of 230 V AC.
Necessary precautions should be taken while using it.
Page 46 of 59
New Item
Item No. : 443
Subject : Various issues related to reliability of Metro Railway, Kolkata.
Group : ELECT (G)
Proposed by : Kolkata Metro
RDSO Ref. :
RDSO’s Note:
Presentation was made by PCEE/Metro/Kolkata highlighting the following problems in
recently received rakes from ICF;
a) Door system
Different operating mechanism viz belt driven, pneumatic & Electric operated.
Different values of obstruction test gap.
Different door operating logics.
b) Brake system
Here too there is no standardization in respect of brake & compressor management.
c) PA/PIS & CCTV
Standardization of PA/PIS & CCTV specification along with their integration with safety
loop is required. Moreover, emergency talkback also to be standardized.
d) Location of 3rd
rail current collector shoe in rake equipped with Medha Electrics is just
below the door. This needs to be relocated to avoid any mishap.
e) The high speed circuit breaker with faster response time to be provided in the rake to avoid
tripping of TSS HSCB.
f) For traction simulation study & L/R measurement, Metro sought, RDSO authorization to get
study & measurement done through any of the IITs at their end.
Recommendation:
(i) RDSO in consultation with ICF & respective manufacturers will make all out efforts to
resolve the problems highlighted by PCEE/Metro.
(ii) RDSO has no objection for Metro getting traction simulation study & L/R measurements
done through any of the IITs.
Railway Board’s decision:
(i) RDSO should prepare specification for door mechanism of Kolkata Metro TDC:
31.03.2020.
Page 47 of 59
(ii) Brake system and compressor management should be standardized by RDSO for Kolkata
Metro (TDC: 31.03.2020).
(iii) PA/PIS & CCTV should be integrated with TCMS. This should be formed part of the
specification (TDC: 31.03.2020).
(iv) Shifting of TRCC depending upon platform should be studied by RDSO & detailed
comment may be given (TDC: 31.03.2020).
(v) RDSO should study & submit the detailed comments about TCCU bogie for traction
protection in BHEL AC rakes (TDC: 31.03.2020).
(vi) RDSO should study & submit the detailed comments about tripping of TSS HSCB (TDC:
31.03.2020).
(vii) Kolkata Metro should get traction simulation study L/R measurement done through any of
IITs as recommended by RDSO (TDC: One year from date of approval).
Page 48 of 59
Other Issues (Non agenda items) Discussed
1. PCEE/ECoR pointed out that adoption of Doppler Radar System of slip-slide control should
also be tried in electric locomotives since it is working satisfactorily in WDG4 loco. It was
pointed out by RDSO that this system was tried long back but could not be successful.
However, it was decided to try this again in some electric locomotives. CLW may give some
developmental orders for slip-slide control by Doppler Radar System for trials.
2. Orders of composite Converters should be expedited by CLW to accelerate its development and
proliferation.
3. MTR’s Points
i) Wherever there are less than 3 venders for any items, efforts should be made to develop
more sources for the same.
ii) RDSO & PUs should decide on the trial period of components of equipment and the
trials should not continue for a very long period.
iii) Vendor approval process should be stream lined and done in a time bound manner with
monitoring of each stage by officers. For this, check sheets for each stage need to be
developed.
iv) There were discussions about introduction and monitoring of energy consumption for
Traction and non-traction area as one of the KTIs of DRMs in the field, so that its proper
control can be exercised.
4. Electrification of washing lines
It was discussed that electrification of washing lines is necessary to eliminate need of shunting
of coaching rakes by diesel locos. Railway Board instructed that top/full wiring of washing lines
should be done as per available standard designs.
5. Provision for non-electrified territories in SOD.
It was discussed that since IRs have gone for 100% electrification, there is no need of any items
in the SOD pertaining to non-electrified routes. RDSO to initiate draft A&C Slip
Page 49 of 59
Part-II (Review of Items of 62
nd ESC)
Page 50 of 59
Part-II ANNEXURE-I
Railways remarks against decision/recommendation of the 62nd
ESC Meeting held at
Ernakulam, Southern Railway on 10th
& 11th
May’ 2018
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
403 Battery
operated cum
25 kV shunting
loco.
Group is of opinion that this is a good development
for IR & will eliminate lot of problems in yards like
noise pollution, fuelling, air pollution etc. As the
group has also suggested that initially the
development should be with 3000 Ah battery. Once
it is developed, better technology option for battery
like Li-Fe-Sulphate, fuel cell may be thought of. As
far as battery rating is concerned, that will be further
reviewed after development of prototype. There can
be two versions –one with 3000 Ah battery & other
with 1000 Ah. Both versions may be used as per
requirement.
Accepted. WCR: ELS/TKD has already
converted one loco using one
over aged WAM4 loco with 199
Ah battery for shunting
operations inside shed. This loco
can be operated in 25kV AC as
well as battery mode.
ELS/ET is indigenously
converting one WAM4 loco into
battery operated cum 25 kV
shunting loco. It is in final stage
of commissioning.
404 Push Pull
operation of
Electric
Locomotive.
1. Rajdhani/Shatabdi type trains should be operated
with push-pull operation equipped with EP
assisted brake system to get more benefit in
terms of time saving in
acceleration/deceleration.
2. Use of DPWCS may be tried during trial.
3. Manning of rear loco by a tech staff is also a
necessity to take care of technical requirement
which a guard may not be able to do properly.
Accepted. SWR:
The JSC is under preparation for
permitting push pull operation of
Rajdhani over DMM-SBC
section. GM’s sanction is
expected to be obtained during
May 2019.
NR:
All 3-phase locos equipped with
MICAS based VCU and HOG
have been made fit for Push Pull
application.
WCR: 04 locos (two pair) of
ELS/TKD shed have been
modified for push pull operation
so far.
Two locos 30620 & 30628 ABB
full propulsion with HOG
(working) have been made ready
for push pull. However software
yet to be released by ABB.
Hence locos working on line
with push pull circuit but without
software.
loco no. 30645 & 30604 (Micas
VCU) with HOG have been
made compliant and released for
working.
No other locos with Micas VCU
and HOG which can be made in
pair.
ECR: At present 04 nos. of
Gomoh based WAP7 locos are
equipped with Micas S-2 control
system. out of which, 03 nos. of
Page 51 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
locos have been provided with
push pull operation system and
provision of provision of push-
pull in 4th
one is under progress
& is likely to be completed
within a week. Further 10 nos.
(05 pairs) of Gomoh locos are
equipped with DPWCS and all
are working in pairs.
NCR: No. holding of WAP5
locos.
405 Indigenous
development of
Radio
equipment for
Distributed
Power
Wireless
Control System
(DPWCS).
1. RDSO should develop indigenous Radio
equipments for DPWCS as well as specification
to achieve Interoperability with standard DMI &
common communication protocol.
2. The licensing from WPC to be processed for
changed frequency band of 424-430 MHz by
CLW.
3. CLW will turnout the locos after carrying out the
necessary wirings for DPWCS to reduce
commissioning time in Zonal Railways.
4. Specification for brake system of 3-phase loco
should have provision of separate port (RS
485/Ethernet) for interfacing of DPWCS with
brake system.
Accepted.
406 a) Pan
India
maintenance
schedule (IA,
IB and IC
only) for
Electric
Locomotives.
b) All
Electric Locos
to be attended
in the nearest
Electric Loco
Sheds for
attending all
defects not
involving
lifting and also
for attending
schedule
maintenance of
IT, IA and IB.
This proposal is not accepted. Existing system of
maintenance should continue.
Agreed. This item is closed.
407 Provision of
EP Assist
Brake System
in Electric
Locomotives.
1. EP assisted brake system should be provided in
3-phase locomotives for faster
application/release of brakes. This will also
ensure additional safety feature in train
operations.
Accepted. Railway
Board vide letter no.
2005/Elect(TRS)/44
0/18/1 Pt. dated
27.03.2018 has
In compliance to Railway
Board’s letter no:
2005/Elect(TRS)/440/18/1 Pt.
dated 27.03.2018, RDSO
specification for EP assisted
Page 52 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
2. The JPO should be processed only after trial, so
that if any shortcomings are noted .Same will be
addressed. ED/Carriage and ED/PS&EMU will
be consulted for JPO. The draft JPO will be sent
to Zonal Railways for comments before
approval.
already advised
RDSO to firm up
specification and
CLW to provide EP
assisted brake in 20
locos.
brake system no.
RDSO/EL/Spec/2018/0138 Rev
‘0’, April 18 was issued. CLW
has been informed to provide
EP assisted brake system in 20
locos vide RDSO letter no
EL/3.2.19/EP Assist dated
04.04.2018.
408 Hosting, of
Remote
Diagnostic
System (RDS)
and GPS data
of for Electric
locomotive on
Railtel portal
along with
failure portal
developed by
RDSO on
Railtel Server.
RDSO should interact with RAILTEL for hosting
the remote diagnostic data for electric locomotives
with a provision for accommodating the proposed
GPS data from Electric Locomotives. The format
for data display on RAILTEL server may be
standardized in consultation with Zonal Railways.
Accepted.
409 Creation of a
centre of
excellence for
technical
know-how and
guidance on 3-
phase locos.
Basic training centers of Zonal Railways in Electric
Loco Shed & other places under control of
Electrical Department should be upgraded for
imparting training to supervisors as well as Artisan
staff in hardware as well as software used in Rolling
stock as well as TRD installations.
Accepted.
NR: Sheds themselves are
facing crises of expertise &
therefore, it may be prudent to
develop center of excellence at
CLW.
WCR: 3-phase loco related
training facilities are being
developed in BTC of WCR
Sheds (ET & TKD).
ECR: At present there is no any
training centre for imparting
training to the supervisors &
staff of TRS/GMO is available in
the shed. However, a basic
training school for imparting
training to the Artisan staff of the
shed is under development stage,
which will be completed by end
of March’2020.
NCR: NCR has Electric
Training Centre, Kanpur to
impart training to LPs/ALPs,
supervisors, artisan staff as well
as TRD staff. The Training
centre has Computer Based
Training (CBT) system with 50
nos. computers for effectively
imparting training to running and
maintenance staff.
410 On-board
Surveillance
and Data
Recorder
(OSDR) for
CLW should provide RDS & CVVRS in Electric
locomotives. Any further up-gradation may be
taken after evaluating the performance of existing
arrangements.
Accepted. SCR: CVVRS provided in
32101 loco of ELS/KZJ is not
properly working since
commissioning.
Rear camera-2 and Panto-2
Page 53 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
Electric
Locomotives.
camera are frequently not
working even after replacement
by firm. The quality of audio
recording was found to be very
poor and it is not audible.
Performance is being reported
to CLW from time to time.
WCR: Item pertains to CLW,
however locally On-board Crew
Audio-Video recorder has been
provided in two nos. WAP4
loco for trial by ELS/ET.
411 Up-gradation
of existing
OHE from 160
kmph to 200
kmph.
Existing OHE and Panto Contact Wire interaction is
fit for 160 kmph. Sample simulation study of OHE
and power supply system for Mathura-Hindaun
section of Kota Division was recently conducted by
M/s ALSTROM. RDSO to also study the parallel
operations of TSS open delta arrangement for power
supply for augmentation. RDSO mentioned that
simulation study of OHE/PSI for 160/200 kmph for
various types of rolling stocks is including train sets
in Delhi-Howrah section, work amounting to
Rupees one crore approximately is to be sanctioned
under powers of DG on out of turn basis. Requisite
fund may be allocated by Railway Board for getting
the work sanctioned. Simultaneously, action has
already been initiated for finalization of assumption
and deliverables in consultation with Railway
Board. Various TDCs are as under:
Sanction for work/estimate: 15.06.2018.
Preparation of bid documents: 25.06.2018
Tender invitation/opening: 27.07.2018.
Award of contract/completion: 31.08.2018/
31.12.2018.
RDSO to expedite
completion of
simulation study.
Target is
31.10.2018.
1. Sanction of DG has been taken
for two works-
a) Power Supply simulation
b) Dynamic simulation of OHE
Panto interaction.
Tender has been discharged on
27.03.2019 due to bidders have
not fulfilled the minimum
eligibility criteria & Tender
committee has recommended to
call global tenders.
2. Vide this office letter dated
04.04.2019 technical approval of
Railway Board sought. Reply
awaited.
3. Vide this office letter dated
07.05.2019, RB was requested to
take prior approval of Election
Commission for floating global
tenders as model code of conduct
of election commission is in
forced due to parliament election
is in process.
412 Reduction in
the cost of RE
work.
This proposal has been given by TI
Directorate/RDSO directly to Board.
Proposal has been
received and
Board’s in
Principal approval
communicated to
RDSO.
CORE may finalize the list of
such items at their end & final
approval may be taken from
Railway Board.
413 Low cost OHE
design.
This proposal has been given by TI
Directorate/RDSO directly to Board.
Proposal has been
received and
Board’s in
Principal approval
communicated to
RDSO.
1. Railway Board vide letter no.
2017/RE/161/29 (3241642)
dated 18.05.2018 had advised to
RDSO to issue formal
instructions to Zonal Railways
and executing agencies so that
cost of new electrification work
can be reduced.
In this regard RDSO vide this
office letter no.
TI/CIV/MS/18/17 dated
18.05.2018 had issued the
Page 54 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
instruction to Zonal Railways.
2. This office letter no
TI/PSI/RELAY/POLICY/02
dated 23/24.05.2018 regarding
relay setting guidelines in low
density routes.
3. Similarly RDSO has instructed
railways vide this office letter no
TI/CIV/MFNDS/18 dated
28.03.2019 regarding use of
cylindrical type foundation.
4. Vide this office letter no.
TI/CIV/FNDS/2017/01 dated
26.09.2017 RDSO issued the
guidelines for use of buried
foundation for OHE
Mast/Portals.
WCR: Low cost OHE design
has been implemented in
Vijaypur-Maxi and Guna-
Gwalior section on WCR).
414 a) Strategies for
increasing
open access
including
provision of
metering CT
and PT for
open access
power.
b) Metering at
important
feeders for
energy
monitoring &
energy
efficiency
requirements.
For the layout of CTs and PTs in the existing TS for
ABT metering, drawing to be revised to suitably
locate CT/PT without any increase in TSS area by
reducing the distances between various equipments,
whenever possible. For new TSS, suitable drawings
may be issued separately.
a) PCEEs to go
whole hog to
ensure open
access power
flow in the
balance States of
West Bengal,
Uttar Pradesh,
Tamil Nadu,
Karnataka,
Kerala, Andra
Pradesh,
Telangana,
Odisha,
Chhattisgarh &
Punjab.
b) Cross-subsidy
charge are not
due to be paid by
Indian Railway
being a deemed
Licensee
(Electricity Act,
Regulation).
c) Training of staff
in open access;
Course in
IRIEEN &
capacity
development
programme by
REMCL.
d) Timely provision
a) SWR started availing power on
open access from 25.10.17 for
RWF and traction substations ie
BWT, WFD, SMWA, BID, Y &
Martur of C.Railway. SWR also
got NOC from KPTCL for
directly availing power on open
access for all future TSS in
Karnataka.
NR: Power flow in Uttar
Pradesh through Open Access
started on 08.07.2018. Issuance
of NOC for power flow in the
state of Punjab is under process
and to be issued shortly.
WCR: Open access is fully
implemented by WCR.
b) NR: Cross subsidy is not being
paid. However, charges being
levied by State Utilities not as
per CERC guidelines in Open
Access are being contested by
REMCL on behalf of Railways.
WCR: RVPNL/Jaipur had filed
a petition for levy of open access
charges like cross subsidy
surcharge and additional
surcharge on unit drawn by
Indian Railway vide petition No.
Page 55 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
of CT, PT &
ABT meters by
Zonal Railways
and Railway
Electrification
organizations
like CORE,
RVNL etc.
e) RDSO to issue
drawing for new
substation and
guidelines for
existing
substations.
RERC/1452/2019. WCR in
consultation with REMCL had
defended the case; however
RERC’s order went against
Railway. RERC order is being
challenged in Hon’ble APTEL.
c) NR: This item pertains to
IRIEEN & REMCL. However,
presently no regular training
course is being provided by
IRIEEN or REMCL for training
of staff in Open Access.
d) NR: Being provided by NR as
well as RE/RVNL.
WCR: Work of provision of CT,
PT & ABT meter is being carried
by MPPTCL in MP area while
work of provision of CT, PT and
ABT meters has been completed
by Railway in Rajasthan area i.e.
Kota division.
e) The TSS drawing for provision
of CTs & PTs for ABT metering
has been revised and issued vide
this office letter no
TI/PSI/POLICY/18 dated
26.07.18.
SCR: Work has started in TSS’s
located in Telangana state.
Efforts are on for
implementation of open access in
Andhra Pradesh also.
ECR: Open access being availed
in DVC (75 MW) & Bihar (50
MW). NOC for additional 50
MW from BSPCL &15 MW
from DVC is pending.
NCR: 07 nos. TSS of NCR in
UP state are yet to be taken
under open access. NR as
coordinating nodal agency for
UP state has been requested for
the same. Cross subsidy charges
are not being paid by CR.
415 Tower Wagon
Maintenance
schedule and
its
implementatio
n
For NR/NER/NCR/NWR POH and rehabilitation of
tower wagon will be done at DMW Patiala. For
other Zonal Railways, this activity will be carried
out in Zonal Railways; this activity will be carried
out in Zonal Railway Workshops. Different
practices are being followed in Zonal Railways for
TXR fitness of tower wagons. In some Railways, it
is monthly, whereas in other Zonal Railways, three
a) USFD every year
as per SMI, both
for 4W and 8W.
b) Railways to
implement
instructions
issued by RDSO
as per SMIs
a) NR: USFD checking of tower
wagon axles is being carried
out over all the divisions.
WCR: USFD is being done
yearly as per SMI. ECR:
Maintenance of 4 W Tower
wagon as per SMITI/MI/0052
(Rev. 0) and 8 W Tower
Page 56 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
monthly committee to be nominated by Railway
Board for standardizing the periodicity. Workshops
to procure the tower wagon spares.
including USFD.
c) Maintenance of
tower wagons at
DMW, Patiala
has been started
to cater to the
increasing load
of tower wagon
numbers.
d) Committee of
EDTI/RDSO,
CEDE/WR is
nominated for
deciding the
TXR checking
periodicity.
wagon as per SMITI/MI/0043
(Rev. 1) is being done.
b) NR: Divisions have been
advised for following RDSO
SMIs including USFD.
WCR: RDSO’s instructions
being implemented.
c) NR: No programme for POH
of tower wagons at DMW
Patiala has yet received by
NR (For
NR/NER/NCR/RE(UMB, JP
and LKO)POH of 105 nos.
Tower Wagon is still being
done at EMU car Shed GZB).
WCR: POH of 8W TW is
being done at Dahod
workshop, while POH of 4W
TW is being done at
WRS/KTT. POH of Engine
& transmission system of 4W
TW is being done by
divisions. NCR: POH of
NCR TWs is carried out at
JHS/WS for 4-wheeler Mark-
II & others including 4-
wheeler Mark-III, IV & 8
wheeler at EMU/Maripat.
KGP/WS has also allotted a
quota of 4 no. 8-wheeler TWs
of NCR in 2019-20.
d) RDSO: A meeting of
committee members (EDTI &
CEDE/WR) is schedule on
15.05.2019 in RDSO, to
study the schedule for TXR
checking for different similar
rolling stocks, in order to
decide the TXR checking
periodicity for tower wagons.
SCR: TXR checking is being
done monthly over SCR.
416 Modification
of TSS
Drawings.
For the layouts of CTs and PTs in the existing TSS
for ABT metering, drawings to be revised to
suitable locate CT/PT without any increase in TSS
area by reducing the distances between various
equipment, wherever possible. For new TSSs
suitable drawings may be issued separately.
RDSO to issue the
revised drawings
and guidelines.
The TSS drawing for provision
of CTs& PTs for ABT metering
has been revised and issued vide
this office letter no
TI/PSI/POLICY/18 dated
26.07.18
417 Provision of
only one
number Retro
Reflective
number plate
in each
kilometer at
SWR recommended for one number retro reflective
OHE number plate in each kilometer, whereas other
Zonal Railways recommended for provisions at
every mast as per recent Railway Board’s directives.
Railway Board’s
existing directives
to be strictly
adhered to.
WCR: Being provided at each
mast as per Board’s directives.
Vide letter no.
2001/Elect(G)/170/1 dated
22.11.16.
NCR: NCR has provided retro
reflective number plates on each
Page 57 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
the beginning
of kilometer
and not on
every OHE
mast.
locations as per Railway Board
guidelines.
418 Replacement
of Overhead
Cross Feeders
at SP/SSP/TSS
locations by
under-ground
cables to avoid
up and down
power block as
well as to
improve
reliability.
This item has already been discussed during 30th
MSG (Tr.D) meeting. Decision has already been
taken to insure mandatory power blocks required for
maintenance rather than changing the standard OHE
cross feeding arrangement.
Proposal of SCR
not accepted as
already decided in
30th MSG (Tr.D)
meeting.
This item is closed.
419 Cadre of
Tower Wagon
Driver to be
made part of
Running Staff.
This is an establishment matter and dropped from
ESC.
Accepted. This item is closed.
420 3-Phase
propulsion
system for
Tower Car and
manufacturing
on LHB
platform.
To be given by TI Directorate/RDSO.
Not accepted.
421 Guidelines for
installation of
Solar Plants on
vacant Railway
land.
1. Identification of land for solar power plant to be
done by Zonal Railways.
2. Scheduling of power is to be decided by Zonal
Railways.
3. Feasibility of net metering to be decided by
Zonal Railways in consultation with State
Electricity Authorities.
4. Based on above, Zonal Railways will send
proposal to Railway Board for approval.
Instructions for
actions to be taken
by Railways for
Solar Plant on
vacant Railway
land already issued
from Railway
Board vide letter
no.
2009/Elect(G)/150/
13/Pt. I dated
18.04.2018
NWR:
As per Railway Board’s letter
no. 2009/Elect(G)/150/Pt-I,
dated 18.04.2018, Vacant land
have been identified. 03 SAG
level committee has been formed
to finalized the land on which
Solar Plants be erected.
NR: 1. As regards land for solar PV
land installation, it is informed
that availability of land with long
term clearance commitment is
practically nil. However, in
Diwana 2 MW land based Solar
based PV in under progress.
2. As regards to schedule of
power, power supply
organization is having severe
shortage of manpower and needs
to be strengthened with energy
management cell which can
study and compile power
demand and forward the same.
3. Net metering installation is
being coordinated with
Page 58 of 59
Item
no.
Subject Recommendation of ESC Decision of Board Present Status obtained from
RDSO and concerned
directorate of Railway Board
concerned Electricity
Authorities. However, recently
Uttar Pradesh State Regulatory
Commission has withdrawn this
for Railways.
The proposal for above referred
points is already in Railway
Board.
ECR:
1. Details of 480 acre Railway
vacant land for harnessing solar
energy have been already sent to
Railway Board vide this office
letter no. ECR/ELE/G/201, dated
10.12.2014. Feasibility of these
lands will be examined
according to Railway Board’s
letter dated 18.04.2018.
2. To be injected at suitable point in
Railway Power supply network.
422 Enhancing
codal life of
internal wiring
in buildings
from 10 years
to 25 years.
The codal for wiring with copper conductor should
be as under:
i. 20 years for non-coastal areas.
ii. 15 years for coastal areas.
With copper
conductor life
should be 25 years
for internal wiring
of buildings.
NR: As regards to codal life for
wiring: with copper conductor of
20 years for Non Coastal areas
and 15 yrs for Costal areas is
appropriate.
ECR: Railway Board’s
directives for enhancing codal
life to 25 years for copper wiring
will be followed.
423 Diesel to
Electric loco
conversion.
Members expressed that conversion of WDG3A
and WDG4 loco should be done since it is
beneficial to Indian Railways.
Accepted. NR: After conversion of 02
diesel locos (WDG3A & WDG4)
into electric locos (WAG10 &
WAG11) respectively have been
received from DLW. WAG10
electric locos have been
introduced for revenue service
and Railway Board’s 1st sanction
for WAG11 is awaited from
RDSO.
Page 59 of 59
Part-III ANNEXURE-II
List of new items proposed by Railways/ PUs but not featuring in main Agenda
for discussion S N Item description Proposed by
1. Requirement of LIs for Assistant Loco Pilots SWR
2. Review of TRD maintenance schedule NWR
3. Posting of Electrical Officer in Diesel sheds NWR
4. Broadening of vendor base for loco items and spares CR
5. (i) Holding of Push-pull loco by Zonal Railways
(ii) Feasibility of modification in conventional loco for Pull Push operation
(iii) Maintaining of spare push-pull compliant coaches at Coaching Maintenance Depot
CR
6. Development of Fire Detection Unit (FDU) in conventional locomotives CR
7. Switching of administrative control of loco operation from Diesel to Electric NR,SCR
8. Re-homing TCN propulsion locos so as have not more than two makes in a shed NR
9. Review of the utility of undertaking POH of 3-phase locomotives in workshops NR
10. Umbrella sanctions for RSP & M & P items. NR,SCR
11. Infrastructural facilities to homed 300 electric locos in sheds. NR
12. Development of higher capacity compressors to fit on the existing footprints/ available
envelope for conventional and three phase locomotive
NR
13. Development of AC to DC power converter for conventional locomotives NR
14. Design / Facilities on washing line for inspection for push- pull rakes. NR
15. Guideline for Provision of Lift & Escalator manning NR
16. Standardization of Electrical vehicle charging station at Railway station & their running policy NR
17. Emergency Telephone Socket NR
18. Power procurement under Open Access NR
19. Proliferation of C-DAC VCU DLW
20. Use of Doppler radar based Slip –Slide control in 3-phase electric locomotives DLW,ECoR
21. Integration of wired and wireless options for distributed power control DLW
22. Conversion of GTO based propulsion system to IGBT based propulsion system for WAG-9 in 2nd
POH
SCR
23. Linking of reliability parameter like FRPCPY for implementation of penalty in AMC SCR
24. Rescheduling IT schedule of WAG-9HC locos WCR
25. Out sourcing of OHE maintenance during Breakdown WCR
26. Improvement of OHE current carrying capacity SECR
27. Development of technical Institute for Training on OHE upkeep and maintenance SECR
28. Vendor approval of Traction Substation equipments including of Transformers according to the
upper voltage rating
CORE
29. a) Use of PVC pipe at SP/SSP instead of Concrete cable trenches
b) Use of pre-casted concrete trenches at TSS instead of in- situ casting of cable trenches
CORE
30. Bifurcation of Workshop Plan Head (4200) as Motive Power and Rolling stock. SCR
31. Authority of EIG SCR
32. Event Recorder with short and long term recording facility ECoR
33. Introduction of 2x25 kV OHE system in East Coast Railway ECoR
34. Introduction of Cylindrical foundations in OHE system for Electrification works ECoR
35. Withdrawal of engineering restrictions in Solar Plant Installation ECoR
36. Homing of Electric locos in Diesel sheds. RB
37. Uniformity in major schedule of WAP5 and WAP7 electric locomotives. RDSO
38. Use of TM speed sensors for speed indication. RDSO
39. Real time measurement of electric locomotive parameters. CR