Ministry of Finance TThehe Division of PPP Projects Division of PPP Projects
PPP/PFI ProjectsPPP/PFI Projects in Israel in Israel
Ministry of FinanceMinistry of Finance
Mr. Hagai MillerMr. Hagai Miller
Senior Deputy Accountant GeneralSenior Deputy Accountant General
2 Ministry of FinanceMinistry of Finance 22 TThehe Division of PPP Projects Division of PPP Projects
PolicyPolicyIncreasing investments in infrastructure will help
sustain Israel’s economy growth
Increasing private sector involvement in government supplied services, mainly in the infrastructure sector
Enhancing efficiency and increasing resources available for financing infrastructure projects
Optimizing Risk allocation between Public and private sectors
3 Ministry of FinanceMinistry of Finance 33 TThehe Division of PPP Projects Division of PPP Projects
The government’s decision is to focus on six fundamental sectors:The government’s decision is to focus on six fundamental sectors:
Railroads
Transportation
Water desalination and sewage treatment
Electricity manufacturing & Gas delivery
Construction
E-Gov
4 Ministry of FinanceMinistry of Finance 44 TThehe Division of PPP Projects Division of PPP Projects
• Cross Israel Highway
• LRT’s
• Highway No 431
• Highway No 531
• Qrayot bypass road
• Desalination facilities
• IPP
• Prison
Map of PPP/PFI Projects in IsraelMap of PPP/PFI
Projects in Israel
5 Ministry of FinanceMinistry of Finance 55 TThehe Division of PPP Projects Division of PPP Projects
Volume of Operations in the PPP/PFI SegmentVolume of Operations
in the PPP/PFI SegmentDistribution of planned investments by sectors
Transportation: $ 5 billion
Water: $ 0.6 billion
Accommodation: $ 0.3 billion
Energy: $ 0.25 billion
83%
4%
8%5%
Transportation Energy
Water AccommodationTotal $ 6 billion
Details & Status
6 Ministry of FinanceMinistry of Finance 66 TThehe Division of PPP Projects Division of PPP Projects
Projects’ StatusProjects’ Status(■ Early stage; ■ After Short List; ■ After Agreement)
Projects’ StatusProjects’ Status(■ Early stage; ■ After Short List; ■ After Agreement)
Transportation:
• Cross Israel Highways• Jerusalem Light Railway• Carmel Tunnels
• Highway no. 431• Tel-Aviv Mass Transit System• Qrayot Bypass- toll road • Highway no. 531- toll road• Tel-Aviv Fast Lane
Energy:
• IPP - Mishor Rotem • IPP’s several locations
Status:
• operation
• Financial close
• Financial close
• RFP published• RFP published, Responding questions • Model under consideration• Model under consideration• RFP to be published
Status:
• PQ in process
7 Ministry of FinanceMinistry of Finance 77 TThehe Division of PPP Projects Division of PPP Projects
Water:• Ashkelon desalination facility• Palmachim desalination facility• “Western Galili” desalination facility
• Hadera desalination facility
Penitentiary :
• Prison - Be’er Sheva
Status:• Under construction• Financial close• Financial close
• RFP published
Status:
• RFP published, Responding
questions
Projects’ StatusProjects’ Status(■ Early stage; ■ After Short List; ■ After Agreement)
Projects’ StatusProjects’ Status(■ Early stage; ■ After Short List; ■ After Agreement)
8 Ministry of FinanceMinistry of Finance 88 TThehe Division of PPP Projects Division of PPP Projects
Project Feasibility StudyProject Feasibility Study Project Feasibility StudyProject Feasibility Study Project is
economically feasible
Project meets PPP/PFI criteria
Phase 1 - economic
feasibility study:Cost/benefit
analysis
Phase 2 - prior to onset
of tender process and during tender
process
Phase 3 - decision & implementation
No
No
Yes
Yes
Project will not be implemented
Public sector implementation
using alternative method
החלטת ממשלה
Analyzing the bids compared
to the PSC
YesSigning the
concession agreement &
following its execution
Business environment is
suitable for PPP/PFI
No
Yes
9 Ministry of FinanceMinistry of Finance 99 TThehe Division of PPP Projects Division of PPP Projects
Implementing Authority
Authorities involved Authorities involved throughout the processthroughout the process
Authorities involved Authorities involved throughout the processthroughout the process
Inter-Ministerial Inter-Ministerial Tender CommitteeTender Committee
The Tender
Steering Committee
Designated Company
Managing the Concession Agreement
Ministry of FinanceRelevant Government Ministries
Inbal – The Division of PPPExternal Consultants
WDA, JPTA, CTA
Cross Israel Highway,
Tel Aviv Mass Transit
10 Ministry of FinanceMinistry of Finance 1010 TThehe Division of PPP Projects Division of PPP Projects
The Tender ProcessThe Tender Process Decision to execute project in PPP/PFI method
Appointing a Tender Committee by the Accountant General
Establishing Work Teams
Studying the material \ Structuring the risk matrix
Preparation of tender documents
Tender publication - widespread distribution
The tender process is “transparent”
Foreign entities are invited to participate in the tenders.
12 Ministry of FinanceMinistry of Finance 1212 TThehe Division of PPP Projects Division of PPP Projects
The Division of Public-Private Partnership Projects
The Division of Public-Private Partnership Projects
The Division is in charge of managing, coordinating, planning and executing the tender processes, and the concession agreements.
The division’s main tasks are:
Creating a professional body in the PPP/PFI field in Israel
Making the tender process as efficient and speedy as possible
Being a leading force in the implementation of the Concession
Agreement during the concession term
Setting the Standards in the PPP/PFI field in conjunction with
governmental authorities and the private sector
13 Ministry of FinanceMinistry of Finance 1313 TThehe Division of PPP Projects Division of PPP Projects
Risk AllocationRisk AllocationRisk Public PrivateShared
Land acquisition
Detailed design
Cost overruns
Completion delay
Archaeological findings
Maintenance costs
Force Majeure
Interest. Rate
Legislation changes
Political risks
Collection risks
Demand risks
Ministry of Finance TThehe Division of PPP Projects Division of PPP Projects
Water Water DesalinationDesalination
PPP/PFI ProjectsPPP/PFI Projects
Ministry of FinanceMinistry of Finance
16 Ministry of FinanceMinistry of Finance 1616 TThehe Division of PPP Projects Division of PPP Projects
Water in Israel: Key FactsWater in Israel: Key Facts
• Israel’s utilization of its natural water sources is complete• Main natural source (Coastal Aquifer) is under risk of contamination• Almost full brackish water utilization and wastewater reuse
Year2005201020152020
Increasing demand*2,0602,5052,5582,805
Limited natural sources1,470
* All figures in million m3/year
Seawater Desalination: One of the solutions for meeting future demand
17 Ministry of FinanceMinistry of Finance 1717 TThehe Division of PPP Projects Division of PPP Projects
PPP/PFI – A Strategic InstrumentPPP/PFI – A Strategic Instrument
• Desalination technology (RO) has been improved significantly within the recent decade
• Israeli private sector plays a key role within the global industry of desalination
• Large scale projects
• Lack of experience & capabilities within the public sector
PPP/PFI Method : The right thing in the right time
18 Ministry of FinanceMinistry of Finance 1818 TThehe Division of PPP Projects Division of PPP Projects
Current Main ProjectsCurrent Main Projects
Desalination Desalination FacilitiesFacilities
Million m3 Million m3 p/ap/a
$US $US (m)(m)MethodMethodStatusStatus
Ashkelon (South of Israel)
100270BOTConstruction
Finish 12/2005
Hadera(North center of Israel)
100220 (est.)
BOTTender
Palmachim(South center of Israel)
3080BOOFinancial Closing1/2005
“Western Galili”(North of Israel)
3075 (est.)
BOOFinancial Closing6/2005
19 Ministry of FinanceMinistry of Finance 1919 TThehe Division of PPP Projects Division of PPP Projects
Ashkelon Sea Water Desalination FacilityAshkelon Sea Water Desalination Facility
World’s largest facility based RO technology
IPP based natural gas
First Israeli project that raised finance from institutional lenders
JV between I.D.E – Israeli firm & a
leading global player
Veolia Water S.A.
Israelis investors
Ministry of Finance TThehe Division of PPP Projects Division of PPP Projects
Mr. Marc HanhartMr. Marc Hanhart
Projects Management DirectorProjects Management Director
Roads Roads PPP/PFI ProjectsPPP/PFI Projects
21 Ministry of FinanceMinistry of Finance 2121 TThehe Division of PPP Projects Division of PPP Projects
Transportation / RoadsTransportation / Roads
22 Ministry of FinanceMinistry of Finance 2222 TThehe Division of PPP Projects Division of PPP Projects
Highway No 431Highway No 431 Toll free suburban highway constituting the southern part of the Circular Highway
around the Tel Aviv metropolitan area, 20 km long with 3 basic lines in each direction, inc. 12 interchanges
Concession period of 25 years, inc. 3 years construction phase Private sector investment (cost of construction) assessment - $ 300 M Public sector investment assessment: $ 120 M (Including land expropriation) Payment scheme to the Private sector:
Fixed periodic payment (Subject matter for competition) $ 90 M Construction Grant to be disbursed at completion of construction Variable payment (Shadow toll) is to be paid as an incentive to maximize the demand Bidders may request payment in Shekels, Dollars and/or Euro, according to cost/
financing structure. Bids to be submitted on February 3, 2005 4 Bidders qualified for tendering :
• Denya Cebus group• Shapir Civil & Marine Engineering group• Ashtrom,,Solel Boneh, Housing & Construction group• Arenson, Ramet, Roichman group
Foreign companies invited to be either member of bidding groups or subcontractor.
23 Ministry of FinanceMinistry of Finance 2323 TThehe Division of PPP Projects Division of PPP Projects
Fast Line projectFast Line project Construction of a one way lane from Lod interchange (near Ben Gurion
Airport) to Kibbutz Galuyot interchange (Tel Aviv entrance ) on Highway no 1 ( Jerusalem-Tel Aviv ) , construction of Park and Ride facility for 2000 cars and operation of bus shuttle service (free of charge for passengers) to the Business Center of Tel Aviv.
Fast line of about 9 km for Public Transportation Vehicles, and excess capacity will be offered to private car drivers willing to pay a toll, which amount will be constantly adjusted according to demand.
A Fast Lines Law was legislated and its purpose is to encourage the use of public transportation instead of private cars. This project will serve as a model for further similar expected projects.
Concession period of 30 years, incl. 3 years construction phase.
Private sector investment (cost of construction) assessment - $ 75 M.
24 Ministry of FinanceMinistry of Finance 2424 TThehe Division of PPP Projects Division of PPP Projects
Fast Line project (continued )Fast Line project (continued )
Payment scheme to the Private sector: Fixed periodic payment (Subject matter for competition) Construction Grant ( amount to be decided ) to be disbursed at completion of
construction 25% of toll income fixed amount for each private car left at the Park and Ride facility during morning peak
hours. Income from additional commercial activities to be approved by the State. Bidders may request payment in Shekels, Dollars and/or Euro, according to cost
structure. Tender documents expected to be published in February 2005.
4 Bidders qualified for tendering : • Africa Israel, Housing & Construction, Egged (Public Transportation), Aecon group• Shapir Civil & Marine Engineering, Nahor( Dan Transportation Company ) group• Tahal Consulting Engineers, Kavim (Public Transportation) group• Malrag Engineering, Terre-Armee, Connex group
Foreign Companies invited to be either member of bidding groups or subcontractor.
25 Ministry of FinanceMinistry of Finance 2525 TThehe Division of PPP Projects Division of PPP Projects
Highway No 531Highway No 531 suburban highway constituting the nothern part of the
Circular Highway around the Tel Aviv metropolitan area, 13 km long, incl. 9 interchanges ( half of the way will be executed in partnership with the private sector ).
Private sector investment (cost of construction) assessment - $ 300 M.
Public sector investment assessment: $ 50 M (Including land expropriation).
Toll payment concept is currently under review, based on traffic forecast.
Construction of the highway to be coordinated with the planned construction of a new railways track in the central part of the highway.
Ministry of Finance TThehe Division of PPP Projects Division of PPP Projects
Ministry of FinanceMinistry of Finance
Mr. Yaron KestenbaumMr. Yaron Kestenbaum
Projects Management DirectorProjects Management Director
TransportationTransportation Mass Transit SystemMass Transit System
PPP/PFI ProjectsPPP/PFI Projects
27 Ministry of FinanceMinistry of Finance 2727 TThehe Division of PPP Projects Division of PPP Projects
Railways Transportation Solutions
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
The promotion of the Tel-Aviv LRT Red Line is an integral part of the Israeli government policy to expand the sub-urban railways services and to develop and promote urban railways transportation solutions, both being complementary transportation crisis modes.
The Israeli government acknowledges that investments in railways transportation infrastructures can provide an appropriate solution to the transportation crisis in the country. Lately the government of Israel has decided to invest a sum of 20 billion NIS in Israeli railway.
This acknowledgment is reflected in increased long run budgetary investments in railway solutions in the recent and in the coming years.
28 Ministry of FinanceMinistry of Finance 2828 TThehe Division of PPP Projects Division of PPP Projects
Network of Planned Lines
Petah Tikva - Tel Aviv - Bat Yam
Holon To Red Line in Tel Aviv
Kfar saba, Raanana, Herzliya and Ramat Hasharonto the Red Line in Ramat Gan
Bikat Ono to Tel Aviv
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
29 Ministry of FinanceMinistry of Finance 2929 TThehe Division of PPP Projects Division of PPP Projects
The Red Line
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
Serves 5 cities - Bat Yam, Jaffa, Tel Aviv, Bnei Brak, Ramat Gan andServes 5 cities - Bat Yam, Jaffa, Tel Aviv, Bnei Brak, Ramat Gan and
Petah TiqvaPetah Tiqva
Length of the line is 22 km, of which: Length of the line is 22 km, of which:
11 km are at grade 11 km are at grade
11 km are underground 11 km are underground
10 U/G stations10 U/G stations
21 at grade stops21 at grade stops
Crosses 55 intersections at gradeCrosses 55 intersections at grade
Travel time from Petach Tikva to Tel Aviv (Arlosoroff) - 19 minutesTravel time from Petach Tikva to Tel Aviv (Arlosoroff) - 19 minutes
Travel time from Bat Yam to Tel Aviv (Arlosoroff) - 28 minutesTravel time from Bat Yam to Tel Aviv (Arlosoroff) - 28 minutes
30 Ministry of FinanceMinistry of Finance 3030 TThehe Division of PPP Projects Division of PPP Projects
The Concessionaire is required to:
Undertake Final Design & Construction
Supply Rolling Stock and Electro-Mechanical Systems
Implement & Manage Operations and maintenance
Finance the Project
Prove Experience in Specified Areas
B.O.T- Build Operate Transfer
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
31 Ministry of FinanceMinistry of Finance 3131 TThehe Division of PPP Projects Division of PPP Projects
A 32 year commitment
Eligible for all derivative
income
during this period
After concession period
expiry,
ownership transfers to the
state
The Concession Period
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
32 Ministry of FinanceMinistry of Finance 3232 TThehe Division of PPP Projects Division of PPP Projects
Public Sector Commitments
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
Financial Contribution
The State undertakes to pay the Concessionaire a State Grant in accordance with a structured milestones progress payment mechanism
Sharing Ridership Revenue Risks
The state is willing to share with the Concessionaire the risks related to variations between the actual ridership revenues and the state’s ridership revenue reference set out in the Concession Documents
33 Ministry of FinanceMinistry of Finance 3333 TThehe Division of PPP Projects Division of PPP ProjectsThe Division of Public Private Partnership projectsThe Division of Public Private Partnership projects
Project’s Risks Allocation The Contract Documents allocate the following risks:
Antiquities Contamination Ground Condition Special Circumstances Site delivery Changes in the Statutory Plan
Government support : Limited competition along the LRT line Priority at traffic intersections Traffic regulation
Public Sector Commitments
34 Ministry of FinanceMinistry of Finance 3434 TThehe Division of PPP Projects Division of PPP Projects
Red Line - Project Status
Engineering Design completed
Statutory Process - completion
Utility relocation and advance works - in
progress
Bat Yam, Jaffa, Ramat Gan, Bnei Brak, Petach
Tikva.
The Division of Public Private Partnership projectsThe Division of Public Private Partnership projects