ppp projects rajasthan

35
1 Rajasthan Annexure - I Status of Public Private Partnership (PPPs) Projects in Infrastructure (As on December 31- 2011) – Completed Projects S. No. Project Name Department /Agency Estimated Cost (Rs. in crores) Structure BOT/BOOT etc. Date of Completion Remarks If any 1 2 3 4 5 6 7 A. Road Sector 1. Karaunti Bridge, Pali District PWD 2.95 BOT 25.02.1997 Completed and handed over to Government. 2. Strengthening & Improvement of Mangalwar– Nimbaheada - Neemuch Road (km.40/0 to 50/0 PWD 6.35 BOT 01.04.2000 Completed and handed over to Government. 3. Widening, Strengthening and Improvement of Kekri - Nasirabad Road (SH-26) Km. 0/0 to 25/0 PWD 4.00 BOT 10.02.1999 Completed and handed over to Government. 4. Improvement & Strengthening of Sirohi - Anadar - Reodar - Mandar Road upto State Border (km.197/0 to 214/0)km.0/0 at Beawar PWD 7.29 BOT 01.04.2002 Completed and handed over to Government. 5. Improvement of Sirohi – Mandar - Deesa Road SH-27 upto State Border (km 214/0 to 268/400 PWD 26.01 BOT 17.05.2003 Completed and handed over to Government. 6. Construction of submersible bridge by providing RCC Hume Pipe on existing causeway at Luni River on Jodhpur Balotra Guda Road SH-289 PWD 4.00 BOT 10.06.2003 Completed and handed over to Government. 7. Improvement & strengthening of Hanumangarh - Suratgarh Road via peelibanga (km. 0/0 to 26/0) PWD 10.24 BOT 26.03.2001 Completed and handed over to Government. 8. Upgradation by Strengthening & Renewal of Kherwara - Dungarpur Road SH-10 (km 0/0 to 20/0) Km. 0/0 Start from Malai chouraha PWD 3.69 BOT 18.02.2001 Completed and handed over to Government.

Upload: etechajay2350

Post on 27-Oct-2014

780 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: PPP Projects Rajasthan

1

Rajasthan Annexure - I

Status of Public Private Partnership (PPPs) Projects in Infrastructure (As on December 31- 2011) – Completed Projects

S.

No.

Project Name Department

/Agency

Estimated

Cost

(Rs. in crores)

Structure

BOT/BOOT

etc.

Date of

Completion

Remarks

If any

1 2 3 4 5 6 7

A.

Road Sector

1. Karaunti Bridge, Pali District PWD 2.95 BOT 25.02.1997 Completed and handed

over to Government.

2. Strengthening & Improvement of Mangalwar–

Nimbaheada - Neemuch Road (km.40/0 to 50/0

PWD 6.35 BOT 01.04.2000 Completed and handed

over to Government.

3. Widening, Strengthening and Improvement of Kekri -

Nasirabad Road (SH-26) Km. 0/0 to 25/0

PWD 4.00 BOT 10.02.1999 Completed and handed

over to Government.

4. Improvement & Strengthening of Sirohi - Anadar -

Reodar - Mandar Road upto State Border (km.197/0 to

214/0)km.0/0 at Beawar

PWD 7.29 BOT 01.04.2002 Completed and handed

over to Government.

5. Improvement of Sirohi – Mandar - Deesa Road SH-27

upto State Border (km 214/0 to 268/400

PWD 26.01 BOT 17.05.2003 Completed and handed

over to Government.

6. Construction of submersible bridge by providing RCC

Hume Pipe on existing causeway at Luni River on

Jodhpur Balotra Guda Road SH-289

PWD 4.00 BOT 10.06.2003 Completed and handed

over to Government.

7. Improvement & strengthening of Hanumangarh -

Suratgarh Road via peelibanga (km. 0/0 to 26/0)

PWD 10.24 BOT

26.03.2001 Completed and handed

over to Government.

8. Upgradation by Strengthening & Renewal of Kherwara

- Dungarpur Road SH-10 (km 0/0 to 20/0) Km. 0/0

Start from Malai chouraha

PWD 3.69 BOT 18.02.2001 Completed and handed

over to Government.

Page 2: PPP Projects Rajasthan

2

9. Strengthening, Widening & Improvement of road and

reconstruction of narrow & weak culverts on

Nathdwara - Mavali Road MDR-36(Km. 0/0 to 26/700

Km. 0/0.)

PWD 4.50 BOT 06.03.2002 Completed and handed

over to Government.

10. Bharatpur Bye-Pass PWD 13.25 BOT 12.04.2000 Completed and handed

over to Government.

11. Construction of Udaipur Bye-pass Phase – II PWD 23.99 BOT 1997 Completed and handed

over to Government.

12. Improvement of Alwar - Bhiwadi Road SH-25Km. 146/0

to 225/0

PWD 18.62 BOT 09.06.2004 Completed and handed

over to Government. (Toll

actually stopped on

16.10.2008 litigation

pending).

13. Sikar Bye-Pass PWD 13.75 BOT 15.01.2000 Completed and handed

over to Government.

14. Improvment of Banswara - Udaipur Road SH-32 (Km

91/500 to 165/0)

PWD 11.50 BOT 05.02.2002 Completed and handed

over to Government.

15. Strengthening of Banswara - Dahod Road (Km. 396/0

to 411/0 SH-4

PWD 2.65 BOT 04.11.2001 Completed and handed

over to Government.

16. Widening & Strengthening of Challa- Neem-ka-thana -

Kotputli Road SH- 13 &MDR- 25 (Km.60/800 to 125/0)

PWD 64.20 BOT 29.04.2005 Completed and handed

over to Government

17. Widening & Strengthening and Improvement of

Mangalwar- Nimbahera Road (Km. 0/0 to 40/0)

PWD 10.26 BOT 01.03.2002 Completed and handed

over to Government

18. Construction of H.L. Bridge on River Massi (Km. 48/200

of Sanganer-Malpura – Kekri Road) SH-12

PWD 1.94 BOT 08.04.2002 Completed and handed

over to Government

19. Improvement of Manglana-Makrana Road (Km. 400/0

to 415/0) and Makrana-Bidiyad Road (Km. 0/0 to 6/0)

PWD 6.54 BOT 21.04.2002 Completed and handed

over to Government

20. Widening & Improvement of Dantiwara-Pipar City –

Merta City Road (Km 0/0 to 26/500)

PWD 5.47 BOT 11.02.2002 Completed and handed

over to Government

21. Construction of Four Lane Road with Median Strip of

1.2 Mtr. Wide on Bar-Bilara-Jodhpur Road SH-5 (Km.

PWD 8.93 BOT 24.07.2002 Completed and handed

over to Government

Page 3: PPP Projects Rajasthan

3

90/0 to 105/0)

22. Bharatpur-Mathura Bye pass SH-1 PWD 13.25 BOT 07.04.2008 Completed and handed

over to Government

23. Kharka Bridge Udaipur (Bhinder-Salumber Road SH-53) PWD 1.35 BOT 01.08.1995 Completed and handed

over to Government

24. Bondu Nallah RSRDC 1.58 BOT 16.04.2009 Completed and handed

over to Government

25. Beedach Bridge RSRDC 4.43 BOT 25.08.1996 Completed and handed

over to Government

26. Jojri River Bridge RSRDC 1.26 BOT 1996 Completed and handed

over to Government

27. Bhilwara Bypass RSRDC 17.97 BOT 05.07.2001 Completed and handed

over to Government

28. D' Zone Bypass RSRDC 5.17 BOT 1999 Completed and handed

over to Government

29. Kherli Bridge RSRDC 0.18 BOT 01.04.1995 Completed and handed

over to Government

30. Khatoli Bridge RSRDC 1.84 BOT 24.07.1997 Completed and handed

over to Government

31. Sri Madhopur Bypass (SH) RSRDC 0.63 BOT 03.11.1999 Completed and handed

over to Government

32. Kankroli Bypass (SH) RSRDC 4.74 BOT 10.08.1998 Completed and handed

over to Government

33. Badgaon- Jaitpura Bridge (SH) RSRDC 1.72 BOT 01.04.1997 Completed and handed

over to Government

34. Gangapur City Bypass (SH) RSRDC 5.68 BOT 27.10.1999 Completed and handed

over to Government

35. Bikaner Bypass RSRDC 8.73 BOT 15.12.1999 Completed and handed

over to Government

36. Morel Bridge (SH) RSRDC 12.09 BOT 16.09.2002 Completed and handed

over to Government

Page 4: PPP Projects Rajasthan

4

37. Palighat Bridge (SH) RSRDC 9.42 BOT 01.04.1995 Completed and handed

over to Government

38. Kharer- Banmi Bridge (SH) RSRDC 1.97 BOT 01.04.1996 Completed and handed

over to Government

39. Jindoli Ghati Tunnel (SH) RSRDC 12.45 BOT 16.05.2001 Completed and handed

over to Government

40. Kali Sindh Bridge (NH) RSRDC 16.99 BOT 05.11.1997 Completed and handed

over to Government

41. Parvati Bridge (NH) RSRDC 8.04 BOT 1997 Completed and handed

over to Government

42. Pali Bye-Pass (Beawar - Bar - Pali - Sirohi NH-14 Km.

106/0 to 112/0)

PWD 10.25 BOT 05.12.1998 Completed and handed

over to Government

43. Construction of Pali Bye-Pass on Jodhpur-Sumerpur

Road NH-65 Km. 0/0 to 11/500 (0 at Km. 366/0)

PWD 30.00 BOT 04.05.2006 Project completed and toll

is on.

44. Improvement of Jhalawar-Indore Road SH-1A

(Strengthening & Widening Km. 9/700 to 29/900) 6.0

Km. away from Patan to State Border

PWD 7.15 BOT 01.04.2002 Project completed and toll

is on.

45. Upgradation (Strengthening and Renewal) of SH-32

Udaipur-Salumber-Banswara Road (Km. 5/0 to 72/0)

PWD 13.57 BOT 02.06.2004 Project completed and toll

is on.

46. Widening & Strengthening of Shri Ganga Nagar-

Hanuman Garh Road SH-36 Km. 1/500 to 56/0

PWD 16.03 BOT 18.02.2005 Project completed and toll

is on.

47. Construction of Nimbhahera Bye-pass on NH-79

(Ajmer-Bhilwara-Chittorgarh-Nimbahera-Ratlam-

Indore Road) Km. 209/087 to 217/400

PWD 31.48 BOT 18.05.2005 Project completed and toll

is on.

48. Widening & Strengthening of Sikar-Jhunjhunu-Loharu

Road SH-8 Km. 0/0 to 119/700

PWD 49.78 BOT 21.07.2004 Project completed and toll

is on.

49. Construction of Kelwa-Amet Road 0/0 to 18/0 PWD 5.70 BOT 05.05.2006 Project completed and toll

is on.

50. Widening & Strengthening and Improvement of

Nasirabad-Kekri-Deoli Road SH-26 Km. 25/0 to 56/500

PWD 21.40 BOT 15.12.2006 Project completed and toll

is on.

51. Widening & Strengthening and Delhi-Ramgarh-Alwar

Road (SH-13) Km. 125/400 to 160/300

PWD 25.28 BOT 19.04.2008 Project completed and toll

is on.

Page 5: PPP Projects Rajasthan

5

52. Strengthening and Improvement of Riding Quality of

Existing Bikaner Bye-Pass Road Km. 0/0 to 28/0

PWD 12.02 BOT 09.05.2008 Project completed and toll

is on.

53. Widening & Improvement of Kama-Nand Goan-Kosi

Road 56/200 to 64/200 and kama Bye Pass (SH-44)

Kama Jurehera Punhana Road (MDR-72) Km. 0/0 to

20/0 and Kama Pahari Road (ODR-16) Km. 0/0 to 22/0

PWD 35.66 BOT 05.08.2009 Project completed and toll

is on.

54. Widening & Strengthening of Nasirabad to Mangliawas

Road Km. 0/0 to 24/200 (MDR-39)

PWD 21.52 BOT 02.04.2009 Project completed and toll

is on.

55. Strengthening, Widening & Improvement of riding

Quality of Road Sirohi-Reodar-Mandar-Deesa Road

(Up to Gujrat Border) SH-27 Km. 197/0 to 268/400

PWD 133.79 BOT 2010 Project completed and toll

is on.

56. Hanuman Garh –Suratgarh Raod including ROB and

Hanumangarh (LC-71A)

RSRDC 39.90 BOT 01.07.2006 Project completed and toll

is on.

57. Chomu-Ajitgarh-Shahpura (Km. 0/0 to 50/500) RSRDC 38.38 BOT 01.04.2007 Project completed and toll

is on.

58. Bikaner Bye-Pass Connecting NH-15 (BK-JSL) to NH-15

(BK-SGR) Km. 0/0 to 26/0

RSRDC 41.69 BOT 31.12.2009 Project completed and toll

is on.

59. Phalodi to Ramgi ki Gol

RIDCOR 386.30 BOT 28.12.2007 Project completed and toll

is on. Indicated tolling

period is 30 years. Tolling

will commence uptill re-

payment of loan thereafter

GoR to take a decision on

utilization of surplus in SRF

or development of other

Roads.

60. Hanumangarh to Kishangarh

RIDCOR 627.20 BOT 28.02.2008

61. Alwar to Sikandra

RIDCOR 128.10 BOT 31.08.2008

62. Baran to Jhalawar

RIDCOR 111.70 BOT 15.04.2008

63. Lalsot to Kota

RIDCOR 303.70 BOT 15.12.2008

64. Hanumangarh to Sangaria (upto Haryana Border) RIDCOR 51.40 BOT 01.11.2011 Project completed and toll

is on. Indicated tolling

period is 30 years. Tolling

will commence uptill re-

payment of loan thereafter

Page 6: PPP Projects Rajasthan

6

GoR to take a decision on

utilization of surplus in SRF

or development of other

Roads.

Sub Total (A)

2521.62

(B)

Urban Infrastructure

1. Common Bio- Medical Waste Treatment Facility

(CBWTF), to cover Jhalawar and Baran

Local Bodies 0.70 DBOOT December,

2008

Plant is working through Sh.

Ankur M/s Hoswin

Incinator, Jhalawar

2. Common Bio- Medical Waste Treatment Facility

(CBWTF), to cover Kota and Bundi

Local Bodies 0.70 DBOOT 28.08.2010 Plant is working through Sh.

Rajdeep Biotech, Kota

3. Common Bio- Medical Waste Treatment Facility

(CBWTF), to cover Jaipur, Dausa, Nawa and Kuchaman

Local Bodies 0.70 DBOOT 2005 Plant is working through Sh.

Ranjeet Singh Rajputana,

Biotech Ltd. Sawai

Madhopur

4. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Ajmer, Bhilwara, Parbatsar, Makrana

and Merta City

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Anil Jain sales promoters,

Ajmer.

5. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Jodhpur and Pali

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Basant Rathore sales

promoters, Ajmer.

6. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Hanumangarh and Shri Ganganagar

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Ghanshyam, E-Tech Project,

Ganganagar

7. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Bikaner, Nagaur and Ladnun

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Manish Rajpurohit, E-Tech

Project, Bikaner

8. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Sawai Madhopur, Tonk and Karauli

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Sumer Singh Rajputana,

Biotech Ltd. Sawai

Page 7: PPP Projects Rajasthan

7

Madhopur

9. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Alwar and Bharatpur

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Arvind Sharma, M/s Hoswin

Incinator, Alwar

10. Common Bio-Medical Waste Treatment Facility

(CBWTF) to cover Jaipur City.

Local Bodies 0.70 DBOOT 21.02.2005 Plant is working through Sh.

Himanshu, Instromedics

Pvt. Ltd, Jaipur.

11. Solid Waste Treatment Plant, Jaipur JMC,

Jaipur

20.00 DBOOT April, 2007 Plant is working through

Grashim India Ltd. at

Langariwas

12. Construction of Foot Over Bridge at Collectorate

Circle, Jaipur

JDA 2.50 BOT August,

2006

Project completed by M/s

Pioneer Publicity

Corporation, Jaipur.

Concession period is 34

years 4 months including

the construction period

w.e.f. 15.07.2005.

Sub Total (B)

29.50

(C)

Water Sector

1. Desalination Plant, Matasukh (Nagaur) RSMM Ltd. 300.00

DBOOT 30.09.2010 Project completed by

Nagaur Water Supply

Company Pvt. Ltd.

(promoted by Doshion Ltd.)

Sub Total (C) 300.00

(D) Social Sector

1. Shree Devi Women Polytechnic College, Hanumangarh Technical

Education

5.49 BOT 09.03.2010 Classes running in its own

building.

2. Veena Institute of Technical Education, Karauli Technical

Education

5.49 BOT December,

2011

Classes running in its own

building.

3. Mantram Women Polytechnic College, Dungarpur Technical 5.49 BOT December, Classes running in its own

Page 8: PPP Projects Rajasthan

8

Education 2011 building.

4. Vikas Polytechnic College, Madera, Deeg Bhartpur

Road, Deeg (Bhartpur)

Technical

Education

9.30 BOT March,

2011

College running in its own

building

5. Saraswati Polytechnic College, School Building, Village:

Rajota, (Khetri)

Dist. - Jhunjhunu

Technical

Education

9.30 BOT March,

2011

College running in own

building.

6. Bright Career Polytechnic College, Bhamatsar, Nokha

[Bikaner]

Technical

Education

9.30 BOT March,

2011

College running in its own

building

7. Sugan Inst. Of Tech. & Engg.,Paramveer Near Electric

Board, Pokhran – Phalodi Road, Phalodi [Jodhpur]

Technical

Education

9.30 BOT March,

2011

College running in rented

building.

8. Rajasthan Polytechnic College,Behind State Middle

School, R.S.E.B. Raod, Ratangarh

Technical

Education

9.30 BOT March,

2011

College running in its own

building

9. Satyam Institute of Technology, Abhishek

Bhawan,Outside Nehru Gate, Beawar [Ajmer]

Technical

Education

9.30 BOT March,

2011

College running in rented

building.

10. Rajasthan Institute of Engineering & Technology ,

Bhankrota, Ajmer Road, Chittorgarh-302026

Technical

Education

16.40 BOT March,

2011

College running in its own

building

11. Dungarpur College of Engineering and Technology, Vill.

Bori Simalwada Road, Dungarpur

Technical

Education

16.40 BOT March,

2011

College running in its own

building

12. Chartered Institute of Technology, Kh. No. 276/252 at

Vill. Danvav, Abu Road

Technical

Education

16.40 BOT March,

2011

College running in its own

building

13. Tagore Engineering College, Technical 16.40 BOT March,

2011

College running in its own

Page 9: PPP Projects Rajasthan

9

Near DIET Vill. Pnwari, Kunchamancity, Nagaur Education building

14. Asians Institute of Technology

Viil. Bhunja Via Kathun, Techsil Newai,Tonk

Technical

Education

16.40 BOT March,

2011

College running in its own

building

15. Shri Digambar Prashikshan Avum Anusandhan

Sansthan, Gulzar Bagh, Bharatpur

Technical

Education

16.40 BOT March,

2011

College running in its own

building

16. Vedant College of Engineering and Technology, Bundi Technical

Education

16.40 BOT March,

2011

College running in its own

building

17. Regional Engineering College, Dhamotar, Pratapgarh Technical

Education

16.40 BOT March,

2011

College running in its own

building

Sub Total (D)

203.47

Grand Total (A+B+C)

3054.59

Page 10: PPP Projects Rajasthan

10

Rajasthan Annexure – II

Status of Public Private Partnership (PPPs) Projects in Infrastructure (As on December 31, 2011) – Projects under Implementation

S.

No.

Project Name Department/

Agency

Estimated

Cost

(Rs. in crores)

Structure

BOOT/

BOT

Date of

Award

Likely date of

Completion

Remarks

If any

1 2 3 4 5 6 7 8

(A)

Road Sector

1. Jaipur to Bhilwara (SH-12) PWD 220.00 DBFOT 16.03.2010 Dec., 2012 Agreement signed on 12.07.10

with M/s Jaipur-Bhilwara Tollway

Pvt. Ltd. Jaipur (M/s SPML).

Performance Security deposited

by Entrepreneur Supplementary

agreement signed on dated &

work started on 02.02.2012

2. Chomu to Mahala via Renwal

Jobner (SH -19 & 2C)

PWD, 134.20 DBFOT 22.02.2011 Jun, 2013 Fin. Bid Recd. with 13.41% VGE

from M/s Unity. Agreement

signed on 05.06.11 with Chomu-

mahala toll Way Pvt. Ltd. Jaipur

(SPV). Performance Security

deposited by entrepreneur.

3. Hanumangarh - Suratgarh RSRDC 255.84

BOT-

Annuity

07.09.2010 March, 2012 Km 9/0 to 50/0 and byepass road

furniture in progress protection

work in progress in km 36/0 to

15/0 work of gaggar bridge is also

in progress.

4. Chittorgarh – Kapasan - Mavli- RSRDC 425.96 BOT - 14.10.2010 March, 2012 Work of major bridge in km, 5/600

Page 11: PPP Projects Rajasthan

11

Dabok Annuity in progress and road signage in km

50/0 to 60/0 in progress

5. Pali – Nadol – Narlai - Gomti

Choraya

RSRDC 193.95

BOT -

Annuity

May, 2010 March, 2012 Tender for balance work in km

290/0 to 306/0 are in process of

approval.

6. (a) Merta-Ras (50)

(b) Ras-Mangliawas (35)

RSRDC 294.83

BOT -

Annuity

02.09.2010 March, 2012 Work in progress. Land acquisition

in progress.

7. Fatehnagar Dariba mines RSRDC 25.00 BOT -

Annuity

16.02.2010 March, 2012 Work in progress.

8. Mahuwa – Hindon - Karauli RSRDC 168.03

BOT -

Annuity

19.01.2011 April, 2012 Work in progress.

9. Jodhpur – Osiya - Phalodi RSRDC 208.74

BOT -

Annuity

03.02.2011 April, 2012 Work in progress.

10. Salumber - Keer ki Chowki RSRDC 163.50

BOT -

Annuity

03.02.2011 March, 2012 Work in progress.

11. Gotan – Pundulu – Borunda-

Ransigaon – Sojat

RSRDC 167.45

BOT -

Annuity

02.02.2011 March, 2012 Work in progress.

12. Banswara – Ratlam (Upto M.P.

Border)

RSRDC 117.03 BOT -

Annuity 23.05.11

June, 2012 Work in progress.

13. Mangalwar – Nimbahera RSRDC 86.73 BOT-

Annuity 5/11

July, 2012 Work in progress.

14. Bharatpur – Deeg- Alwar RSRDC 135.69 BOT-

Annuity

5/11 July, 2012 Work in progress.

15. Jahajpur – Mandalgarh RSRDC 197.37 BOT-

Annuity

- November,

2012

Work in progress. Likely date of

completion Nov. 2012

16. Alwar to Bhiwadi (4-Lane) RIDCOR 330.11 BOT

- - Work in progress. Indicated tolling

period is 30 years. Tolling will

commence uptill re-payment of

loan thereafter GoR to take a

decision on utilization of surplus in

SRF or development of other

17. Arjunsar to Pallu

RIDCOR 83.93 BOT -

-

18. Jhalawar to Jhalawar Road

RIDCOR 79.73 BOT - -

Page 12: PPP Projects Rajasthan

12

Roads.

19. Khushkhera to kasola Chowk RIDCOR 34.50 BOT - - Work in Progress. Land acquisition

issue in 2.5 KM is under process.

20. Kapren to Mangrol RIDCOR 121.69 BOT - - DPR completed. Part work being

taken up. Forest clearance

awaited from GOR, RFQ has been

submitted by 5 Agencies

21. Jhalwar to Ujjain (upto Raj.

Border)

RIDCOR 75.88 BOT - - CD works in progress in part

length, existing concession period

of BOT will end on 17.01.2012

22. Rohat-Jalor PWD 56.38 BOT 12.12.2011 - Concession agreement executed

on 17.01.2012 with M/s. Chetak

Enterprises.

23. Jalore – Ramsingh – Revdar PWD 51.75 BOT 09.12.2011 - LOA issued to M/s. D.K. Infra. Pvt.

Ltd. Mumbai.

24. Sanchore – Makhupura – State

Border

PWD 11.61 BOT - - Agreement signed on 04.11.2011

with M/s D.K. Infra Pvt. Ltd.

Mumbai. Commencement date

16.11.2011.

25. Chirawa – Singhana – Pacheri up

to Haryana Border

PWD 35.87 BOT - - Agreement signed on 09.12.2011

with M/s SPC Chetak Toll Roads

Pvt. Ltd. Jaipur

26. Kota – Jharal-Ke-Balaji – via Tather

– Sultanpur-Ganesh Ganj Itawa.

PWD 64.56 BOT - - Agreement signed on 09.12.2011

with M/s. Chetak Jainco Toll way

Pvt. Ltd. Jaipur. Commencement

date 05.02.2012

.

27. Bali – Sewaro – Pinwara PWD 25.21 BOT 25.10.2011 - LOA issued to M/s HG infra Pvt.

Ltd. Jaipur.

28. Laxmangarh – Salasar PWD 13.96 BOT - - Agreement signed on 03.01.2012

Page 13: PPP Projects Rajasthan

13

with M/s Deepak & Co., Sri

Ganganagar. Commencement

date 05.01.2012

29. Sriganganar – Padampur –

Raisinghnagar – Anupgarh

PWD 17.57 BOT - - Agreement signed on 30.11.2011

with M/s Deepak & Co., Sri

Ganganagar. Commencement

date 22.12.2011

30. Salumbar – Banswara PWD 46.33 BOT - - Agreement signed on 22.12.2011

with M/s GHV India Pvt. Ltd.

Mumbai. Commencement date

22.12.2011

31. Ring Road around Jaipur City

Jaipur

Development

Authority

890.00 DBFOT 16.05.2011 April, 2013 Land acquisition is in progress.

Around 30 km length has been

taken under possession out of 47

km.

32. Alternate route to Ghat Ki Guni by

construction of tunnel through

Jhalana hills to connect NH-11,

Agra Road

Jaipur

Development

Authority

150.00 DBFOT 13.10.2009 30.06.2012

The work is in progress. In about

860 mtr length, Tunnel Tube (each

tube) has been excavated;

excavation of tunnel inter

connector at two places have

been completed. Flyover work on

Agra Road near Chulgiri along with

RE wall work is in progress. CD

works at one location is

completed and at two locations

are in progress. Other works like

construction of drain, RCC

retaining wall, earth work & rock

excavation for roads is in progress.

Sub - Total (A)

4883.40

Page 14: PPP Projects Rajasthan

14

(B) Urban Infrastructure

1. Common Bio- Medical Waste

Treatment Facility (CBWTF), to

cover Sikar, Jhunjhunu, Didwana,

Mundwa and Kuchara

DLB 0.70 DBOOT 21.02.2005 - Civil work completed.

Establishment of Plant is in

process.

2. Common Bio- Medical Waste

Treatment Facility (CBWTF), to

cover Udaipur City

DLB 0.70 DBOOT 2005 - Agreement due.

3. Common Bio- Medical Waste

Treatment Facility (CBWTF),

Jalore

DLB 0.70 DBOOT 16.09.2008 - Agreement due.

4. Rope Way from Manikya Lal

Verma Park to Karni Mata

Temple, Udaipur

UIT,

Udaipur

3.00 BOT - - Work in progress.

5. Special Economic Zone (SEZ),

Jaipur

RICCO 1500.00 JV - - Work in progress.

6. Jal Mahal Tourism Project, Jaipur Tourism

(RTDC)

200.00 BOOT 22 Nov.,

2005

- Phase-I near completion and

phase-II will take 3 years after

completion of Phase-I.

7. Restoration and Conservation of

Tijara Fort, Alwar

Tourism

(RTDC)

25.00 BOOT 22 July,

2009

- Work in progress.

Sub – Total (B)

1730.10

(C)

Social Sector

1.

Affordable housing with focus on

EWS & LIG housing, Mukandpura

near Bhankrota, Jaipur through

M/s Vinkash Estess Pvt. Ltd.

UDH 17.90 Model No. 2

(Private

Developers

on land

owned by

them)

09.02.2011 08.02.2014 Under Affordable Housing Policy –

2009. Total 512 Flats Comprising

of 288 EWS, 144 LIG and 80 MIG.

Page 15: PPP Projects Rajasthan

15

2.

Affordable housing with focus on

EWS & LIG housing, Village Ramla

ka vaas Teshil, Kalwar, Jaipur

through M/s Bhairav Township

Pvt. Ltd.

UDH 19.36 Model No. 2

(Private

Developers

on land

owned by

them)

23.02.2011 22.02.2014 Under Affordable Housing Policy –

2009. Total 576 Flats Comprising

of 320 EWS, 192 LIG and 64 MIG.

3.

Affordable housing with focus on

EWS & LIG housing, village

Mahapura near Sez, Jaipur

through M/s Majestic Realmart

Pvt. Ltd.

UDH 31.95 Model No. 2

(Private

Developers

on land

owned by

them)

23.02.2011 22.02.2014 Under Affordable Housing Policy –

2009. Total 960 Flats Comprising

of 608 EWS, 224 LIG and 128 MIG.

4.

Affordable housing with focus on

EWS & LIG housing, near Pink

pearl, Ajmer Road, Jaipur through

M/s Sintex Industries Ltd.

UDH 14.30 Model No. 2

(Private

Developers

on land

owned by

them)

07.01.2011 06.01.2013 Under Affordable Housing Policy –

2009. Total 432 Flats Comprising

of 256 EWS, 128 LIG and 48 MIG.

5.

Affordable housing with focus on

EWS & LIG housing, Village Bagru

Khurd, Thikerya, Ajmer Highway,

Jaipur through M/s Siddha Infra

project Pvt. Ltd.

UDH 13.54 Model No. 2

(Private

Developers

on land

owned by

them)

23.02.2011 22.02.2013 Under Affordable Housing Policy –

2009. Total 400 Flats Comprising

of 224 EWS, 128 LIG and 48 MIG.

6.

Affordable housing with focus on

EWS & LIG housing, Village Bagru

UDH 25.38 Model No. 2 04.02.2011 03.02.2013 Under Affordable Housing Policy –

2009. Total 704 Flats Comprising

Page 16: PPP Projects Rajasthan

16

Khurd Omex city, Ajmer Road,

Jaipur through M/s Shiv Shakti

Real Homs Pvt. Ltd.

(Private

Developers

on land

owned by

them)

of 384 EWS, 192 LIG and 128 MIG.

7.

Affordable housing with focus on

EWS & LIG housing, Village

Shyampur Buhariya Vatika Road,

Sanganer, Jaipur through M/s

Regency Buildhome Pvt. Ltd.

UDH 39.17 Model No. 2

(Private

Developers

on land

owned by

them)

14.06.2011 13.06.2014 Under Affordable Housing Policy –

2009. Total 1120 Flats Comprising

of 672 EWS, 256 LIG and 192 MIG.

8.

Affordable housing with focus on

EWS & LIG housing, Village Nevta,

Teshil Sanganer, Jaipur through

M/s Siddhi Vinayak Affordable

Homes Ltd.

UDH 36.37 Model No. 2

(Private

Developers

on land

owned by

them)

11.03.2011 10.03.2014 Under Affordable Housing Policy –

2009. Total 1072 Flats Comprising

of 592 EWS, 352 LIG and 128 MIG.

9.

Affordable housing with focus on

EWS & LIG housing, Chakshu,

Jaipur through M/s Patni Builders

Pvt. Ltd.

UDH 59.76 Model No. 2

(Private

Developers

on land

owned by

them)

07.01.2011 06.01.2014 Under Affordable Housing Policy –

2009. Total 1880 Flats Comprising

of 1104 EWS, 648 LIG and 128

MIG.

10.

Affordable housing with focus on

EWS & LIG housing, Village

Biranvaas Tehsil Kotkasim,

UDH 13.75 Model No. 2

(Private

02.02.2011 01.02.2013 Under Affordable Housing Policy –

2009. Total 400 Flats Comprising

of 208 EWS, 144 LIG and 48 MIG.

Page 17: PPP Projects Rajasthan

17

Bhiwadi Distt. Alwar through

Falcon Reality services Pvt. Ltd.

Developers

on land

owned by

them)

11.

Affordable housing with focus on

EWS & LIG housing, Village

Biranvaas Tehsil Kotkasim,

Bhiwadi Distt. Alwar through Sun

System Institute of Information

UDH 13.57 Model No. 2

(Private

Developers

on land

owned by

them)

22.01.2011 21.01.2013 Under Affordable Housing Policy –

2009. Total 400 Flats Comprising

of 224 EWS, 128 LIG and 48 MIG.

12.

Affordable housing with focus on

EWS & LIG housing, panwadi

sargod, Trisingiya, Kuchaman city

Nagaur through Shree Ram Balaji

Developers & Infrastructures Pvt.

Ltd.

UDH 28.22 Model No. 2

(Private

Developers

on land

owned by

them)

16.06.2011 15.06.2013 Under Affordable Housing Policy –

2009. Total 848 Flats Comprising

of 496 EWS, 256 LIG and 96 MIG.

13.

Affordable housing with focus on

EWS & LIG housing, Ajmer-

Beawar Road NH-8, In front of

Tabiji Railway Station, Ajmer

through Golden Line

Infrastructure Pvt. Ltd.

UDH 20.24 Model No. 2

(Private

Developers

on land

owned by

them)

01.09.2011 31.08.2014 Under Affordable Housing Policy –

2009. Total 544 Flats Comprising

of 240 EWS, 192 LIG and 112 MIG.

14.

Affordable housing with focus on

EWS & LIG housing, Village Jirota

Khurd, near shyam sarowar, Distt.

Dausa on Main NH-11 through

UDH 14.66 Model No. 2

(Private

Developers

19.05.2011 18.05.2013 Under Affordable Housing Policy –

2009. Total 416 Flats Comprising

of 224 EWS, 128 LIG and 64 MIG.

Page 18: PPP Projects Rajasthan

18

Amit Colonizers Ltd. on land

owned by

them)

15 Baba Saheb Ambedker Technical

Education Society, B-75, Raksha

Vikash Appartment, Vikashpuri,

New Delhi-110018 (for Dholpur)

Technical

Education

16.40 BOT 2011-12 31.03.2013 New Society Selected. Land

allotted to society. Letter of

Approval from AICTE not received.

16 Kailker Awareness & Relief

Welfare Society, A-13, Mohan

Garden Ext. Uttam Nagar, New

Delhi-110059 (for Barmer)

Technical

Education

16.40 BOT 2011-12 31.03.2013 New Society Selected. Land

allotment under process

17 Veena Memorial Seva Society,

Gulab Baag, Karauli (for Karauli)

Technical

Education

16.40 BOT 2011-12 31.03.2013 New Society Selected. Land

allotment under process

18 Nav Uday Welfare & Charitable

Society, 29-A, Pocket-1, Sector-7,

Dwarla, Delhi (for Baran)

Technical

Education

16.40 BOT 2011-12 31.03.2013 New Society Selected. Land

allotment under process

19 Gyan Jyoti Shikshan Sansthan, 74,

Sharma Colony Ward no. 24,

Churu, Raj. (for Churu)

Technical

Education

16.40 BOT 2011-12 31.03.2013 New Society Selected. Land

allotment under process

20 Rajasthan Institute of Engineering

& Technology, Jaisalmer

Technical

Education

16.40 BOT 2011-12 31.03.2013 Land allotted to society. Letter of

Approval from AICTE not received.

21 Sawai Madhopur College

Engineering & Technology, Sawai

Madhopur

Technical

Education

16.40 BOT 2011-12 31.03.2013 Land allotted to society. Letter of

Approval from AICTE not received.

Page 19: PPP Projects Rajasthan

19

22 Swami Vivekanand College of

Engineering and Technology,

Jalore

Technical

Education

16.40 BOT 2011-12 31.03.2013 Land allotted to society. Letter of

Approval from AICTE not received.

23. Swasthya Kalyan Women

Polytechnic College Tonk

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

24 Shri Jawahar Women Polytechnic

College, Dausa

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

25 Vivakanand Institute of

Technology, Bhilwara.

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

26 Bhadariya Mateshwari

Polytechnic College for Women,

Jalore

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

27 Rajasthan Institute of Engineering

and Craft, Dholpur

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

28 Rajasthan Girls Polytechnic

College, Baran

Technical

Education

5.49 BOT 2007-08 31.03.2013 College is running in own building

and building construction is under

progress.

29 Chandrawati Girls Polytechnic

College, Jaisalmer

Technical

Education

5.49 BOT 2007-08 31.03.2013 College building construction is

now not in progress. Admission nil

since last 2 sessions.

30 Emergency Response Service –

Knowingly as 108 Ambulance

Project

M & H

Deptt.

55.68 O & M 01.07.2010 Agreement

signed with

consortium

ZHL Ltd. on

07.04.2010

for 3 years

period

A consortion of Ziqitza Health

Care Ltd. and International Centre

for Emergency Techniques,

Bombay are operating 108-

Ambulance service since July,

2010 in the State. Presently A fleet

of 411 Ambulances including 14

Page 20: PPP Projects Rajasthan

20

which is

extendable

for next 2

year.

provided by Disaster Management

are in operation. As per the

agreement, operation cost per

Ambulance is Rs. 94,899/- and

Medicine cost approx. Rs. 5,000/

Ambulance/Month. As per

agreement, the ZHC Ltd. has to do

5 Trips/ Day /Ambulance,

otherwise amount is deducted

proportionately.

31 Rajiv Gandhi Mobile Medical

Services in Rajasthan

Medical &

Health

25.92 O & M October,

2011

- Presently State has 52 Medical

Mobile Units and 150 Medical

Mobile Vans. These are being

operated through NGOs/Service

Provider. Operation cost of Rs.

31.00 lacs is per year and Capex of

Rs. 37.88 lacs per year which

include procurement cost of

Medical Mobile Units and Vans.

32 Toll Free 104 Medical Advice

Service

M & H

Deptt.

1.15 O & M 06.09.2011 - Contract Agreement signed with

Health Management and Research

Institute (HMRI), Hyderabad

initially for 3+2 years on

21.09.2011. The service is

operational through a centralized

24X7 call centre which is

established at State HQ. The

service is started from 21.11.2011

however; formally launched on

16.01.2011.

33 Manas Arogya Heart - Care

Hospital & Research Institute in

Medical

Education

56.00 O & M June 09,

2011

November,

2012

Preferred bidder has been

identified and concession

Page 21: PPP Projects Rajasthan

21

Jaipur agreement executed for 30 years.

DPR of the concessionaire

approved. Works are in progress.

Sub – Total (C)

656.55

(D)

Power Sector

1. Lignite based Power Plant,

Bhadresh (Barmer)

RSMM Ltd. 5000.00 BOOM 29.05.2006 April, 2012 Total 8 units are to be setup. 4

units have started generating

power while remaining 4 units

are likely to generate power by

April, 2012.

2. 400 kV S/C Bikaner- Deedwana

– Ajmer Line with 400 kV/220

kV GSS at Deedwana

RRVPN

Ltd.

285.00 BOOM TSA with

DISCOM on

15.02.2011

2012-13 The firm has started work on the

line i.e. taking Transmission

licence from the regulator and

preliminary survey etc. It also

filed petitions for (i) Adoption of

Transmission charges and (ii)

Grant of Transmission License.

RERC ordered the petitions

adversely. The firm and RVPN

have filed appeal with appellate

tribunal APTEL.

3. 400 kV S/C Hindaun-Alwar Line

with 400/220 kV GSS at

Alwar

RRVPN

Ltd.

188.32 BOOM TSA with

DISCOM

signed on

19.01.2011

2012-13 The firm has started work on the

line i.e. taking Transmission

licence from the regulator and

preliminary survey etc. It also

filed petitions for (i) Adoption of

Transmission charges and (ii)

Grant of Transmission License.

RERC ordered the petitions

adversely. The firm and RVPN

Page 22: PPP Projects Rajasthan

22

have filed appeal with appellate

tribunal APTEL.

4.

220 kV S/C Sikar – Nawalgarh –

Jhunjhunu Line with 220/132

kV GSS at Nawalgarh

RRVPN

Ltd.

36.28 BOOM LoI issued

on

23.02.2011

2012-13 SPA and Transmission Service

Agreement (TSA) are to be signed

after signing of Sub-lease

agreement between SPV and

RVPN which is under process.

Sub – Total (D)

5509.60

(E)

IT Sector

1. Rajasthan State Wide Area

Network (RajSWAN) Project -

IT, Deptt. 120.21 BOOT 15 April,

2011

2015

Work order has been issued to

Bharti Airtel in the month of

April, 2011. The project will be

rolled out in the next financial

year.

2. Common Service Centres

Project.

RajComp 106.40 BOO - 2014 Work in progress. Total 6,626

kiosks will be set up across the

State under the project out of

which 2612 kiosks have been

made operational.

Sub – Total (E)

226.61

(F)

Any Other Sector

1.

Multi Chamber Cold Storage

(4000 M. T.) at Mandi Yard,

Alwar

RSAMB 3.85 O & M on

lease basis

22.03.2010 31.03.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Agency - Shri Shubham Logistics

Ltd. Santacruz (E), Mumbai.

Page 23: PPP Projects Rajasthan

23

2. Multi Chamber Cold Storage

(2000 M. T.) at Mandi Yard,

Sikar

RSAMB 2.38 O & M on

lease basis

22.03.2010 31.01.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Agency – Blue Star Ltd.,

Gurgaon, Haryana

3. Multi Chamber Cold Storage

(2000 M. T.) at Mandi Yard,

Udaipur

RSAMB 2.54 O & M on

lease basis

22.03.2010 31.03.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Agency – Blue Star Ltd.,

Gurgaon, Haryana

4.

Multi Chamber Cold Storage

(1000 M. T.) at Mandi Yard,

Sumerpur, District Pali

RSAMB 1.28 O & M on

lease basis

15.04.2010 30.04.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Agency – Blue Star Ltd.,

Gurgaon, Haryana

5.

Multi Chamber Cold Storage

(6000 M. T.) at Mandore

Mandi, Jodhpur

RSAMB 4.90 O & M on

lease basis

15.04.2010 31.01.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Page 24: PPP Projects Rajasthan

24

Agency - Shri Shubham Logistics

Ltd. Santacruz (E), Mumbai.

6. Multi Chamber Cold Storage

(2000 M. T.) at Mandi Yard,

Bhilwara

RSAMB 2.28 O & M on

lease basis

22.03.2010 31.03.2012 Construction work is likely to be

completed by March 31, 2012

and operation will be done for a

5 year period after completion of

civil works by the selected Private

Agency – Blue Star Ltd.,

Gurgaon, Haryana

Sub – Total (F)

17.23

Grand Total

13023.49

Page 25: PPP Projects Rajasthan

25

Rajasthan Annexure - III

Status of Public Private Partnership (PPPs) Projects in Infrastructure (As on December 31, 2011) – Projects under Planning /

Pipeline

S.

No

Project Name Department

/Agency

Estimated Cost

(Rs. In crores)

Structure

BOOT/BOT

Likely Date of

Award

Remarks

If Any

1 2 3 4 5 6 7

(A)

Road Sector

1. Bikaner – Suratgarh ( NH-15 ) PWD 501.08 DBFOT January, 2012 RFQ process completed. (33/41)

Approved in the DEA/EI meeting held on

20 July, 2011 at Delhi & PPPAC meeting

on 10.08.2011. Approved in CCI dt.

16.11.2011 vide MoRTH letter dt.

02.12.2011. RFP issued BDD 12.12.2011

(mod.) 06 Nos RFP BID received on BDD.

Bids submitted to MoRTH for approval

on 19.12.2011. Bid of Highest Premium

Bidder (Rs. 251 Cr.) M/s MBL-SREI

Consortium approved by MoRTH on

02.01.2012 for LOA, which is issued on

09.01.12.

2. Chittorgarh – Neemuch

( MP Boarder) ( 38 KM) and

Nimbahera – Pratapgarh

( 80 KM ) ( NH- 79 & 113)

PWD 511.21 DBFOT - RFQ process completed. (36/42)

Approved in the DEA/ EI meeting held on

20 July, 2011 at Delhi & PPPAC meeting

held on 10.08.2011. Approved in CCI

dated 16.11.2011 vide MoRTH letter

dated 02.12.2011. RFP issued. BDD

07.12.2011 (Mod.) 09 Nos RFP BID

received on BDD. Bids submitted to

Page 26: PPP Projects Rajasthan

26

MoRTH for approval on 19.12.2011 with

highest bidder premium of Rs. 22.61 Cr.

By M/s Chetak Enterprise. Approval

awaited.

3. Suratgarh – Sriganganagar

(NH-15)

PWD 224.03 DBFOT - RFQ process completed. (39/44)

Approved in the DEA/EI meeting held on

20 July, 2011 at Delhi and PPPAC

meeting held on 10.08.2011. Competent

approval awaited. RFP issued. BDD is

18.01.2012 (Mod.) One No. Bid of M/s

Unity Infra projects Ltd. Quoting grant

of Rs. 5.70 Cr. recd.

4. Ajmer – Nagaur ( NH- 89) PWD 377.15 DBFOT - RFQ process completed. (38/44)

Approved in the DEA/EI meeting held on

20 July, 2011 at Delhi and PPPAC

meeting held on 10.08.2011. Competent

approval awaited. RFP issued. BDD is

18.01.2012 (Mod.) 4 No. Bids recd. with

lowest grant of Rs. 45.00 Cr. quoted by

M/s GVR infraprojects ltd. Chennai.

5. Sikar – Bikaner (NH-11) PWD 650.84 DBFOT - RFQ process completed. (42/49)

Approval of SFC/PPPAC/DEA from

MoRTH is awaited. Appraisal reply of

DEA & Planning Commission submitted

to MoRTH on 16.09.2011. RFP issued on

04.01.2012. Approved in PPPAC on

13.12.2011. BDD is 12.03.2012.

6. Nagaur – Bikaner (NH- 89) PWD 378.07 DBFOT - RFQ process completed. (37/44)

Modified PPACC & DEA proposal

submitted on 05.07.2011 & 18.08.2011

EI meeting held on 06.01.2012 New

Delhi. Approval awaited. BDD is

Page 27: PPP Projects Rajasthan

27

12.03.2012.

7. Nagaur– Jodhpur( NH- 65) PWD 411.18 DBFOT - RFQ process completed. (38/45)

Modified SFC/PPPAC/DEA proposals

submitted to MoRTH on 16.09.2011. EI

meeting held on 06.01.2012 at New

Delhi. Approval awaited.

8. Jodhpur – Pali ( NH-65) PWD 342.72 DBFOT - RE-RFQ (38 Nos) received on 09.11.2011

Approval/Evaluation under process.

Modified SFC/PPPAC/DEA proposals

submitted on 27.09.2011, 16.11.2011.

Approval awaited.

9. Bharatpur – Alwar – Beheror –

Narnaul Road (SH-14)

RSRDC 131.92 BOT-Annuity

- Tender Due on 12.03.2012

10. Kotputali to Kuchaman and

Daulatpura via Neem-Ka-

Thana (SH-37B &7)

RSRDC 357.75 BOT- Annuity - Tender Due on 12.03.2012

11. Jaipur to Nagaur via Jobner

( SH-2 & 7)

RSRDC 342.00 BOT- Annuity - Tender Due on 12.03.2012

12. Mathura (Raj. Border) to

Bharatpur to Hinduan via

Bayana (SH-1A)

RIDCOR 350.00 BOT- Annuity - No Financial bid received by RSRDCC on

due date. Project is awarded to RIDCOR.

13. Rawatsar – Nohar – Bhadra

upto Haryana Border (Km.

30/400 to Km. 148/00) (GREF-

Road)

RIDCOR 291.56 BOT- Annuity - Delisted from PPP model. Project

awarded to RIDCOR.

14. Dausa Chaksu Dudu (SH-2) PWD 165.00 BOT- Annuity - No Financial bid received on due date

29.09.2010. Proposed to transfer the

road to RSRDCC for development on BOT

(Annuity) and Toll basis.

15. Dudu Sambhar ( SH-2) PWD 40.00 BOT- Annuity - No Financial bid received on due date

08.12.2010. Proposed to transfer the

road to RSRDCC for development on BOT

Page 28: PPP Projects Rajasthan

28

(Annuity) and Toll basis.

16. Rishabhdeo – Salumber RSRDC 90.00

BOT - Annuity - DPR under preparation.

17. Dungarpur – Banswara RSRDC 165.00

BOT - Annuity - DPR under preparation.

18. Dhabadeh – Ramaganj mandi RSRDC 69.63

BOT - Annuity - To be taken up after comp. Of ROB.

19. Jhunjhunu – Udaipurwati –

Khandela

PWD 86.22 BOT - Bid received, tenders under approval.

20. Khandela – Srimadhopur –

Reengus – Khatushyamji

PWD 43.26 BOT - Bid received, tenders under approval.

21. Metra – Gotan – Piparcity –

Jodhpur

PWD 74.47 BOT - Bid received, tenders under approval.

22. Fatehpur – Jhunjhunu –

Malsisar – Rajgarh Road

PWD 25.44

BOT 20.03.2012. –

23. Aspur – Doongarpur PWD 64.10 BOT-VGF 20.02.2012.

24. Sardulshahar (Punjab state

Border) Hanumangarh- Tibbi-

Alinabad (Hariyana Border)

PWD 93.84 BOT-VGF 20.02.2012. –

25. Sirsa (Hariyana) Ludesar-

Bhadra-Sidhmukh-Rajgarh

PWD 45.16 BOT-VGF 20.02.2012. –

26. Lunkaransar (NH-15) Kalu-

Shreedoongargarh (NH-11)

Sardarsahahar (NH-64)

PWD 96.85 BOT-VGF 20.02.2012. –

27. Sardarsahahar (NH-64)

Tarangar – Rajarh (NH-64)

PWD 70.78 BOT-VGF 20.02.2012. –

Sub – Total (A)

5999.26

(B)

Urban Infrastructure

1. Exhibition cum Convention RIICO 216.65 BOT February, The preferred bidder has been identified

Page 29: PPP Projects Rajasthan

29

Centre at Sitapura Industrial

Area , Jaipur

2012 consequent upon the Request for

Proposal for the project. LoA has been

issued on 13 Feb., 2012 to preferred

bidder.

2. International Convention

Center, Pratap Nagar, Jaipur

RHB 1026.00 DBFOT - EoI was released in Oct., 2010 and

technical bids have also been received;

only one offer received. Final decision is

to be taken on the project.

3. Jalore Area Development

Program – Drinking Water

Supply & Sanitation Project

PHED 962.00 - - Implementation structure is under

approval.

4. Convention Centre, Kota UIT, Kota

81.46 BOT - Under bidding.

5. Jaipur Metro Rail Project Jaipur Metro

Rail

Corporation

(JMRC)

9732.00 - - Sanctioned under IIPDF scheme of

Government of India for project

development. Stage-II of this project for

development of Corridor (Ambabari –

Sitapura and Chandpole – Badi Chaupar),

acquisition of all rolling stock and

operation and maintenance of the entire

metro rail system are proposed on PPP

mode. Applications have been invited

through RfQ. 5 applications were

received, out of which 4 applications

have been qualified.

6.

Restoration and Conservation

of Forts in the State and

Conversion of same into

Heritage Hotels

Tourism/

RTDC

0.00 BOT (60 Year

Lease Basis)

- After successful biding out of the Tijara

Fort, Government decided to lease out

16 selected properties on the same lines.

Initial study found 3 forts as most

feasible ones out of total 16 and

Government is planning to bid out two

forts. Estimated cost will be in the range

Page 30: PPP Projects Rajasthan

30

of 20 Cr. to 30 Cr. for properties selected

under Phase-I.

7. Solid Waste Treatment Plant

at Sewapura

Nagar

Nigam,

Jaipur

20.00 DBOOT 2010-11 Work is yet to be started.

8. Solid Waste Treatment Plant

at Sikar

Municipal

Council, Sikar

13.00 DBOOT - LoA issued to M/s Ruchem Ltd. Mumbai.

Land has been allotted.

9. Integrated Solid Waste

Management Project Jaipur

Nagar

Nigam,

Jaipur

60.00 DBOOT - RfP is being issued.

10. Integrated Solid Waste

Management Project, Jodhpur

Nagar

Nigam,

Jodhpur

40.00 DBOOT - RfP is being issued.

11. Integrated Solid Waste

Management Project, Ajmer,

Kishangarh and Pushkar

DLB 0.00 DBOOT - -

12. Integrated Solid Waste

Management Project, Kota,

Bikaner and Udaipur

DLB 0.00 DBOOT - -

13. Amusement Park with Snow

Theme at Jawahar Circle,

Jaipur

JDA 33.50 DBFOT - Proposal dropped as the financial

module of the concessionaire M/s Pink

Paradise Fun & Food park, Faridabad

was not appropriate and viable.

Sub - Total (B)

12184.61

(C)

Water Sector

1. Bisalpur-Tonk – Uniyara

Drinking Water Supply Project

PHED 400.00 BOT with

Annuity based

- Consequent upon RfQ, 14 firms have

been short listed. RfP and Draft

Page 31: PPP Projects Rajasthan

31

for 2 towns (Tonk & Uniyara)

and 436 villages in Deoli,

Uniyara and Tonk Tehsils of

Tonk District

payments Concession Agreement are being

finalized.

2. Water Supply & Sewerage

System for Udaipur town

PHED 1000.00 DBFOT - Technical consultant has been

appointed.

3. Water Supply & Sewerage

System for Ajmer and Pushkar

PHED 700.00 DBFOT - Technical consultant has been

appointed.

4. Rehabilitation & O&M of Raw

Water Pumping Stations for

Jaisamand

PHED 9.00 BOT - -

Sub – Total (C)

2109.00

(D)

Power Sector

1. 400 kV D/C Babai - Jaipur

(North) (Twin Moose) line

along with 400/220 kV GSS at

Jaipur (North)

RRVPN

Ltd.

221.80 BOOM 2013-14 Notice inviting Bid published on

31.3.2011 and Pre- Bid conference held

on 16.5.2011. Short listing of bids is

under process.

2. 400 kV D/C Jodhpur (New)-

Udaipur (Twin Moose) Line

along with 400/220 kV GSS at

Udaipur

RRVPN

Ltd.

379.53 BOOM 2013-14 Notice inviting bid published on

21.09.2011 and Pre-bid conference held.

Short listing of bids is under process.

3. 400 kV Bikaner – Sikar D/C line

(Twin Moose) – 210 Km

RRVPN

Ltd.

219.58 BOOM 2013-14 Being structured as per the guidelines

based on VGF.

4. 400 kV AKAL – Jodhpur (New)

D/C line (Quad Moose) -240

Km

RRVPN

Ltd.

512.27 BOOM 2013-14 Being structured as per the guidelines

based on VGF

Sub –Total (D)

1333.18

(E)

Social Sector

Page 32: PPP Projects Rajasthan

32

1. Gyanodaya PPP Schools

(Establishment of 50 New

Senior Secondary Schools in 10

districts of Ajmer and Udaipur

Division on 30 year Concession

period)

School

Education

172.00 BOT May, 2012 Sanctioned under IIPDF scheme of

Government of India for project

development. Consequent upon the RfQ

for 50 schools, eligible applicants have

been short listed. Application for VGF

has been submitted to Govt of India in

August, 2011. GoI is yet to sanctions

VGF. Thereafter, RFP documents inviting

financial bids will be issued to shortlisted

eligible applicants.

2. Sun & Sand Industries Ltd.,

Plot. No. I & III, Block XVI,

Ogun Housing State Industrial

Corporation, Sangootta, Ogun

State – Nigeria

Technical

Education

13.00 BOT - Proposed College at Ajmer

3. Samsung Overseas Ltd.

104, Adishwar Appt.,

Ferozshah Road, New Delhi –

110 016

Technical

Education

13.00 BOT - Proposed College at Bhiwadi, Alwar

4. Shri Taijal Shikshan Sansthan

At SMPR Road, Bhairuji Mode,

Reengus, Sikar – 332404

Technical

Education

13.00 BOT - Proposed College at Reengus, Sikar

5. Vijay Shikshan Sewa Sansthan,

C/o Vijay Hospital, Behind

Police Station

Bandikui, Dausa – 303313

Technical

Education

13.00 BOT - Proposed College at Rural Area Baswa,

Dausa

6. Society Affiliated to Rural

Development for Health &

Agriculture, Sardha Society,

C/o Post Box No. 20, Deoli,

Dist.-Tonk – 304804

Technical

Education

13.00 BOT - Proposed College at Rural Area, Devli,

Tonk

Page 33: PPP Projects Rajasthan

33

7. Shyam Knowledge Park

Shiksha Samiti,

E-562, Lal Kothi Scheme, Jaipur

Technical

Education

13.00 BOT - Proposed College at Teh.-Bassi, Agra

Road, Distt.Jaipur

8. PNB Shikshan Santhan

Ward No. 12, Mukandpura,

Bhankrota,Jaipur

Technical

Education

13.00 BOT - Proposed College at Vill.Jalsu, Tel. Amer,

Distt. Jaipur

9. Dhayawan Vikas Sanstha,

Luriyawas, Teh. Sanganer,

Jaipur

Technical

Education

13.00 BOT - Proposed College at Rural Area,

Shahpura, Bhilwara

10. Gurukul Shikshan Sansthan,

V/P – Rundal, Teh.-Amer,

Jaipur

Technical

Education

13.00 BOT - Proposed College at Vill.Khor Bassi, Teh.

Beharor,Distt.Alwar

11. Bhagwati Shiksha Samiti,

47, Satya Vihar Colony, Lal

Kothi,

Jaipur – 302005

Technical

Education

13.00 BOT - Proposed College at Bharatpur

12. St. Conard Shiksha Samiti,

St. Conard's Sr. Sec. School,

Jagdish Talkies Tiraha, Dholpur

– 328001

Technical

Education

13.00 BOT - Proposed College at Rural Area Dholpur

13. Adarsh Indian Public School

Shiksha Samiti, Near CISF

Campus, Deoli, Tonk

Technical

Education

13.00 BOT - Proposed College at Bundi

14. Praband Samiti, Bhartiya Vidya

Mandir, 319, Dadu Marg,

Barkat Nagar, Jaipur – 302015

Technical

Education

13.00 BOT - Proposed College at Jaipur Road, Kota

15. Stone Age Ltd.

117, Jaipur Tower, M.I. Road,

Jaipur

Technical

Education

13.00 BOT - Proposed College at Rural, Deoli, Tonk

16. Vijayaraje Sindhiya Shikshan Technical 13.00 BOT - Proposed College at Rural

Page 34: PPP Projects Rajasthan

34

Sansthan,

Awali Kalan, Gyan Mandir,

Magan Bhai Market,

Bhawanimandi, Jhalawar-

326502

Education Bhawanimandi, Jhalawar

17. Sharda Manohar Zila Jhalawar

Mahila Vikas Samiti,New

Master Colony,Jhalawar-

326001

Technical

Education

13.00 BOT - Proposed College at Rural Jhalawar

18. Dee Jay Neelum Marble

Industries Pvt. Ltd., NH-8,

Bhuwana, Udaipur

Technical

Education

13.00 BOT - Proposed College at Udaipur

19. Shri Vinayak Mission Medical

Education Society, P.No. 1,

Mahaveer Nagar 'A', Muhana

Road, Mansarovar, Jaipur –

302020

Technical

Education

13.00 BOT - Proposed College at Kishangarh, Ajmer

20. Apex Education Committee,

VPO – Bassni, Teh. –

Mundawar, Alwar – 301401

Technical

Education

13.00 BOT - Proposed College at Teh.Khairthal, Alwar

21. Surendra Public School Samiti,

25, Goverdhan Colony, New

Sanaganer Road,

Jaipur – 302019

Technical

Education

13.00 BOT - Proposed College at Kishangarh, Ajmer

22. Computed Tomography (CT)

Scan facilities in 14 Districts of

Rajasthan

Medical &

Health

30.00 - - Initial tender process done in Nov/Dec,

2010. This had been failed as there were

no tenders. Transaction consultant is

being appointed for preparation of

project documents.

23. Setting up of a University for Youth Affairs 0.00 - - IIPDF assistance has been approved by

Page 35: PPP Projects Rajasthan

35

Physical Education and Sports,

Jhunjunjhu

and Sports DEA. 75% of the project development

cost shall be met by GoI and remaining

25% is being borne by ADB. Ernst &

Young have been retained as transaction

advisor and have commenced work. EOI

for the project is expected to be released

in March, 2012.

Sub – Total (E)

462.00

(F) Any Other Sector

1.

Project at Khamnaur

(Rajsamand) under Provision

of Urban Amenities in Rural

Area (PURA) Scheme

Rural Dev. 132.03 BOT - DPR submitted to GoI for approval.

2.

Project at Sanganer (Jaipur)

under Provision of Urban

Amenities in Rural Area (PURA)

Scheme

Rural Dev. 120.17 BOT - DPR submitted to GoI for approval.

Sub - Total (F)

252.20

Grand Total

22340.25