1 MICE VC Alain Blondel 2 August 2007 Summary of the MICO meeting 26 July 2007 Overview Target (CB) Beam line engineering & installation (CN) ToF0 (MB) CKOV (GG / LC ) ToF0 & CKOV integration (WL) Spectrometer spectrometer magnet (MZ) tracking detector (KL) Integration (SV / KL / WL) Diffuser (WL) Control room (PK) Network (AO) DAQ (JSG) Controls Infrastructure (BM) Electrical Installation (IM) Mechanical Services (CN) AoB see details in MICO meeting web page http://hep04.phys.iit.edu/cooldemo/ei/ins3/ins3.html and summary in MICE note 174

Upload: keenan-meece

Post on 16-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

1MICE VC Alain Blondel 2 August 2007

Summary of the MICO meeting26 July 2007

OverviewTarget (CB)Beam line engineering & installation (CN)ToF0 (MB)CKOV (GG / LC)ToF0 & CKOV integration (WL)Spectrometer

spectrometer magnet (MZ)tracking detector (KL)Integration (SV / KL / WL)

Diffuser (WL)Control room (PK)Network (AO)DAQ (JSG)Controls Infrastructure (BM)Electrical Installation (IM)Mechanical Services (CN)AoB

see details in MICO meeting web page http://hep04.phys.iit.edu/cooldemo/ei/ins3/ins3.htmland summary in MICE note 174

Page 2: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

2MICE VC Alain Blondel 2 August 2007

Target (Sheffield; C. Booth and P. Smith)

•Target functioning reliably – 3.7 M actuations over 12 weeks.this is about what we expect from >1 year of operation of MICE

Bearing wear considerably reduced with use of leaded bronze

further studies to be done with Diamond-like Carbon

aim to install in early november

Page 3: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

3MICE VC Alain Blondel 2 August 2007

Leaded bronze bearings after 1.5 M pulses

<-- Brass bearing after x pulses

Page 4: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

4MICE VC Alain Blondel 2 August 2007

Dust at bottom of housing (after 1.5 M operations)

Expect <1% of this to fall in ISIS vacuum pipe

Is this acceptable to ISIS?

proposal will be discussed with Steve Pin, writen up and sent to David Findlay for approval.

Alternative – DLC (Diamond-like carbon) coated shaft & bearingsreceived new shafts from Oxford.Will send off shaft & bearings for commercial coatingTest will take at least 3 weeks (2 M pulses) once received.ready in october?

Page 5: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

5MICE VC Alain Blondel 2 August 2007

Beam line engineering and installation(sketch!)

magnets Q1-3 and B1 installed, not connected to power and servicesMagnets Q1 and B1 have been measured

Sand bags will be requested in the hole from MICE to ISISonly after measurements in shielded area

Magnet B2 is in placein recess positionneed alignment, water, power

shielding is complete(today)

PSI solenoid will be moved there for cold test

Q4-Q9 refurbishment in this zone, Q4 is reassembledschedule for completion to be drawn

MICE Local Control Room MLCR to be finished in october

Linde plant

Page 6: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

6MICE VC Alain Blondel 2 August 2007

THE DIPOLE B2 in place(recess position)

Page 7: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

7MICE VC Alain Blondel 2 August 2007

PSI solenoid

successful repair with help of Walter Gloor one of the tie-rods to the cold mass had also fallen off. Magnet is actually in good condition. Plan is to finish off repairs at front of solenoid, MLI insulation and replace the cover.

Next is cold test and Linde refrigerator will be needed, but there is a legal issue as the certification of the whole assembly by Linde is missing (not just parts).

next is collecting cold box etc... timescale is September mid October the latest. The position in the hall for cold testing is on the south side of the hall It does not interfere with possible test or installation of detectors on the beam line.

Action keep pushing for the Linde contract to be signed. (Tom Bradshaw)

Page 8: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

8MICE VC Alain Blondel 2 August 2007

Tracker-- 9 tracker stations have been completed by now. (5 for one tracker) Still a few problems with the light validation bench. No dead channels seen and a few only have apparently a little less light. Main and urgent issuesthe need for specification of path of the low voltage cablesand need to define the fire alarm system to have permission take the spares from D0. Fermilab will go ahead with a design using the VESDA system.

Spectrometer solenoidon track and progressing well (See Steve V. talk) EXPECTED delivery of solenoid I at FNAL end december 2007and at RAL 2 month later (late february) after magnetic measurements. ==> start step II in April. began winding of second solenoid

Integration in solenoid (lau): PID shield being finalized with GhislainDiffuser drawings internally reviewed; external reviewers will be sent material asap.

NB these are typical technical coordinator actions... ... we stumble on those at the moment

Page 9: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

9MICE VC Alain Blondel 2 August 2007

Magnet 1 Cold Mass after Banding

Coil M1

Coil M2End Coil 1

Center Coil

End Coil 1

Quench Protection System

Page 10: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

10MICE VC Alain Blondel 2 August 2007

Magnet 1 Cold Mass Supports

Cold Support BandIntercept Clevis

Warm Support Band

Warm Adjustment Screw

Cold Band Bearing

Page 11: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

11MICE VC Alain Blondel 2 August 2007

Magnet 1 Quench Protection System

Quench Protection ResistorsCold Diodes

Page 12: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

12MICE VC Alain Blondel 2 August 2007

CKOV

Parts of the first (of 2) detector have arrived at RAL (+ L.Cremaldi and David) Customs overcome with 'magic words' – not totally smooth, but getting there!Aerogel, box, mirrors (From USA) and phototubes (from Trieste)will be ready in september second CKOV could be there for November. Support being build under supervision by W. Lau (Oxford)

TOF0/1 being built in Milano, delivery at RAL 1st November with laser calibration system

DAQ delivered by JS Graulich and V Verguilov. All installed in R12. --> DAQ workshop 23-25 July: -- interface with software and data storage-- transmission of knowledge to tracker group (James Leaver et al) -- empahsized need for Controls and Monitoring task (Daresbury) to begin(Target control, beam magnets, safety)

Page 13: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

13MICE VC Alain Blondel 2 August 2007

DAQ -- Installation @ RAL

In R12 (East)

2 VME Crates- 2 Interfaces- 2 Trg Receiver- TDC V1290- Scaler V830- fADC V17241 PCs2 NIM Crate1 Network

Switch

2 Scint. + PMTfrom IC

Page 14: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

14MICE VC Alain Blondel 2 August 2007

this shows cable routings, control room etc...and was sent to all MICE for verification (A. Oates)WBS leaders should look at the diagram of electrical and mechanical services, and find out if any requirements that are known to them are close enough to the foreseen outlets.

Page 15: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

15MICE VC Alain Blondel 2 August 2007

MAIN MESSAGES

MICE is recovering from the major hickup (Project manager resignation) and associated collateral dammages (PSI solenoid, lapses of communication, delays in refurbishment of quads etc...) thanks to the dedication of many MICE and Ken Long and Chris Nelson in particular.

-- Priority #1 is to ensure that full beam line is ready for step I data taking at the end of the christmas shutdown (20 January)

-- It appears desirable and possible (though not certain at the moment) that beam provided by a simplified version of the beam line (target, Q1-Q3, B1, B2) could be operational in November together with a good fraction of detectors (CKOV, TOF, perhaps even the tracker) taking advantage of ISIS developments breaks in septembre and maintenance break on 4-8 November.

-- this is a natural step in the debugging of the beam line and would allow major test of the part of the beam line that is installed in the ISIS vault (--> possible fixes in the Xmas shut down) -- calibration of pions/ISIS irradiation, a major unknown at the moment. -- shake-down of the detectors and DAQ, installation in the control room -- generally keeps the momentum rolling and avoids work pilup in february

Meanwhile detectors will be integrated with Cosmics in R12 mezzanineUncertainties concern target, PSI solenoid, controls and Hall installation;

The rest of MICE is on schedule

Page 16: MICE VC Alain Blondel 2 August 2007 1 Summary of the MICO meeting 26 July 2007 Overview TargetTarget (CB) Beam line engineering & installationBeam line

16MICE VC Alain Blondel 2 August 2007

Aspirational MICE Schedule as of july 2007

15 November 2007Or January 2008

STEP I

April 2008

STEP III July 2008

STEP II

STEP IV Delivery of 1st FCMay 2009

STEP V summer 2009

STEP VI end 2009 (or 2010)

UK PHASE I

UK PHASE II