Meeting of the Verdun / Le Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Elgar - 8 february 2017
Projet de corridor du nouveau pont Champlain 2
Verdun Marie-Pierre Bouchard Philippe Dubeau Hubert Fortin François Labelle Seraya Speer Billy Walsh – business community
Leanne Ruberry – business community Mario Langlois – community organizations Le Sud-Ouest Nathacha Alexandroff Daniel Brasseur Sarah Chouinard Michel Langlois– business community Cédric Glorioso-Deraiche– community organizations Partners Dan Genest – Signature on the Saint Lawrence team Jean-François Parenteau – Verdun Borough
Benoît Dorais – Le Sud-Ouest Borough James Byrns – City of Montréal Vincent Jarry – Infrastructure Canada
Committee Members
Projet de corridor du nouveau pont Champlain
1. Discuss the work completed, underway and to come from now until spring 2017
2. Follow up on the various files under the responsibility of Infrastructure Canada and Ville de Montréal
3. Answer questions, identify potential solutions and discuss the issues
Meeting Objectives
3
Projet de corridor du nouveau pont Champlain
Agenda
4
Series Item Duration Time 1. Opening 10 min. 7:00 to 7:10 p.m.
2. Work completed, underway and to come • Land sector • L’Île-des-Sœurs sector
40 min. 7:10 to 7:50 p.m.
3. Question period for Committee members 10 min. 7:50 to 8:00 p.m.
4. Question period for general public 15 min. 8:00 to 8:15 p.m.
5. Follow up on the various files under the responsibility of Infrastructure Canada
15 min. 8:15 to 8:30 p.m.
6. Question period for Committee members and the public
10 min. 8:30 to 8:40 p.m.
7. Follow up on the various files under the responsibility of Ville de Montréal
15 min. 8:40 to 8:55 p.m.
8. Question period for Committee members and the public
10 min. 8:55 to 9:05 p.m.
9. Adjournment: next meeting and topic 5 min. 9:05 to 9:10 p.m.
Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months Verdun / Le Sud-Ouest
Projet de corridor du nouveau pont Champlain
• Well-started reconstruction of the new viaducts of the highway 15: Atwater, LaSalle et Wellington
• Progress of the Gaétan-Laberge boul. : planned to open in summer 2017
• Advanced work on the new Île-des-Sœurs bridge : 25% of the beams installed from Gaétan-Laberge side
• Demolition of the toll plaza on Île-des-Sœurs completed and opening of the deviation at the exit of the bidge (IDS side)
• Extensive work on the new Champlain Bridge: Maritime excavation completed Off-site manufacturing progressing well Installation of footings, piers bases and segments First delivery of the beams Construction of the main pylon and the rear span
Overview of Completed Work
6
Projet de corridor du nouveau pont Champlain
Completed Work: Observations
• Significant progress at Atwater Interchange, Gaétan-Laberge Sector and Île-des-Sœurs Bridge
• Slowdown of works in the area between LaSalle and Wellington : resumption of works in Spring 2017
• Planned opening of the southern A15 direction for Fall 2017
Projet de corridor du nouveau pont Champlain
Complaint Management (1st October to 6 February 2017)
8
Topic Land L’Île-des-Sœurs
Total Closed Open Total Closed Open Total
Noise 3 - 3 8 1 9 12
Air quality - - - - - - -
Traffic 2 - 2 3 - 3 5
Vibrations 1 1 2 - - - 2
Brightness - - - 2 - 2 2
Other - 1 1 1 - 1 2
Total 6 2 8 14 1 15 23
From 11 June to 30 September : 34 complaints, for 10 per month on average
Last period : 6 complaints per month on average
Projet de corridor du nouveau pont Champlain
A great achievement of our workers
›Dons
Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months Verdun / Le Sud-Ouest
Projet de corridor du nouveau pont Champlain
Description of work Approximate duration
Time frame
Legend: Works and Impacts
• Traffic: • Residential proximity: • Public transit: • Active transportation:
Minor Moderate
Major
Impact by colour code
11
Projet de corridor du nouveau pont Champlain
1 2
12
Land
L’Île-des-Soeurs
Location of Sectors: Verdun / Le Sud-Ouest
Projet de corridor du nouveau pont Champlain
Construction of new H15S structures, walls and roads
Overall Plan: Spring 2016 to Fall 2017
Construction of Gaétan-Laberge urban
boulevard
13
Construction of new L’Île-des-Sœurs Bridge
Dismantling of existing H15S structures, walls and roads
(completed)
Construction of the L’Île-des-Sœurs new structures
Projet de corridor du nouveau pont Champlain
Design and planning underway so modifications are possible
Key Activities Underway and to Come: Land
Projet de corridor du nouveau pont Champlain
Objective: Widening of H15S and construction of the new Gaétan-Laberge urban boulevard
Current and upcoming work:
• Final connexion of watermains
• Reconstruction of Highway15S overpasses, retaining walls and roadbed
• Major reconfiguration of Atwater interchange and of Gaétan-Laberge area
Approach:
• Daytime work especially when impact is major (e.g. noise level)
• Nighttime work when impact on daytime traffic is too significant
• Weekend work when necessary
Land
15
Projet de corridor du nouveau pont Champlain
Works and Impacts : Land
Widening of H15S between Atwater and Wellington
Duration: 1 year with limited work between November and May
Time frame: May 2016 to Summer 2017
• Characterization of soils with potential for asbestos contamination (underway)
• Drainage work • Earthwork • Retaining walls • Paving (fall 2017)
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
17
Wellington
Partial construction of overpasses Duration: 10 months
Time frame: June 2016 to March 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
18
Work Status: Atwater • Girders installations and pouring (completed) • Creation of temporary access roads (underway) • Retaining walls (underway)
Projet de corridor du nouveau pont Champlain
Reconfiguration of Exit 61 of H15S
19
›Bla Bla
x x x x x x x x
Reconfiguration of Exit 61 • New configuration on temporary road • Management of new intersection with traffic lights • Left turn towards the Southwest • Right turn towards Verdun • Preparation for the demolition of the existing exit
Construction Zone
Roads
Legend
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
20
Work Status: LaSalle • Relocation of watermains (underway) • Retaining walls (underway) • Girders installations (week of 13 February : night closure)
and pouring • Relocation of the pedestal (to come: February)
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
Wellington
Relocation of the pedestal on LaSalle Duration : two months
Time frame : February to April
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
Work Status : Wellington • Retaining walls (underway) • Relocation of a pedestal (underway) • Girders installations(13-15 Feb : closing of Wellington at
nighttime) and pouring • Connexion of watermain (to come)
Projet de corridor du nouveau pont Champlain
Wellington
Relocation of the pedestal on Wellington Duration : two months
Time frame : February to April
Works and Impacts: Land
Projet de corridor du nouveau pont Champlain
Relocation of the exit 60 of H15S
24
Via-Rail
Comité technique sur la mobilité des personnes - 17 février 2016
Relocalisation of the exit 60 (printemps 2017) • New configuration on temporary road ( 6 months) • Temporary intersection on Wellington street • Left turn towards the Southwest • Right turn towards Verdun • Modification of the phasing of traffic lights in periphery • Police presence
Construction zone
roads
Legend
Projet de corridor du nouveau pont Champlain
Exit 60 of H15S towards Wellington
Via-Rail Construction zone
roads
Legend
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
26
Construction of the new Gaétan-Laberge urban Boul.
Duration: 12 months Time frame: July 2016 to july 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: Land
27
Work Status: Gaétan-Laberge • Reconstruction of the overpasses (underway) • Tree cutting for the new bike path (underway) • Creation of temporary access roads (underway) • Retaining walls (underway)
Projet de corridor du nouveau pont Champlain
Design and planning underway so modifications are possible
Key Activities Underway and to Come: L’Île-des-Soeurs
Projet de corridor du nouveau pont Champlain
L’Île-des-Soeurs
29
Objective: Construction of the New Champlain Bridge's west approach, the new L’Île-des-Sœurs Bridge and the road connecting them
Current and upcoming works:
• Construction of new L’Île-des-Sœurs Bridge • Reconfiguration of L’Île-des-Soeurs Boul. overpass • Preparatory works at the pedestrian tunnel and at the René-Lévesque Boul. overpass • Construction of the new Champlain Bridge's west approach and west abutment
Approach: • Daytime work especially when impact is major (e.g., noise level)
• Nighttime work when impact on daytime traffic is too significant
• Weekend work when necessary
• West approach: work increase in the evening and at night (approximately 20 workers) and during week-ends
Projet de corridor du nouveau pont Champlain
Works and Impacts: L’Île-des-Soeurs
Work Status : L’Île-des-Sœurs Bridge • Columns and pier caps (underway) • Deck slabs installation (underway) • Transfert of the L’Île-des-Sœurs jetty (february-march)
Construction of new L’Île-des-Sœurs Bridge Duration: 19 months
Time frame: March 2016 to September 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: L’Île-des-Soeurs
Construction of the L’Île-des-Sœurs Boul. overpass
Duration : 1 year Time frame: summer 2016 to summer 2017
Projet de corridor du nouveau pont Champlain 32
P-12
Construction of the pedestrian tunnel
Construction of René-Lévesque boul.
overpass
Storage of beams
Works and Impacts: L’Île-des-Soeurs
Preparatory works at the pedestrian tunnel and at the René-Lévesque Boul. overpass
Duration : six months Time frame: October to March 2017
Work Status : L’Île-des-Sœurs road corridor • Pile caisson drilling of the new structures • Relocation of public services
Projet de corridor du nouveau pont Champlain
Completed Works: West Approach
33
38 out of 38 marine excavations for the west Approach were completed
Projet de corridor du nouveau pont Champlain
Completed Works: West Approach
38 footings of the West Approach out of 38 have been concreted, and 30 of them are completed with pier bases
Projet de corridor du nouveau pont Champlain
Completed Works: West Approach
35
23 out of 38 maritime footings of the west approach were installed
in the river
Projet de corridor du nouveau pont Champlain
Completed Works: West Approach
36
Work 24 hours per day, 7 days per week Smaller team in the evenings, and week-ends,
but effectives have doubled
Formwork and concreting of ‘’ground’’ footings and pier starters of the west approach
Projet de corridor du nouveau pont Champlain
Completed Works: West Approach
37
Temporary installations of prefabricated, preassembled and loading of the west jetty were completed
Work 24 hours per day, 7 days per week Smaller team in the evenings, and week-ends,
but effectives have doubled
Projet de corridor du nouveau pont Champlain 38
Completed Works: Cable-stayed Bridge
Construction of the lower pylon, the lower cross beam and the rear span
Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the seaway dike
39
Ponctual closing of variable duration for the seasons 2017 and 2018 et, if necessary, long term closing
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
Projet de corridor du nouveau pont Champlain
Anticipated Impacts
Projet de corridor du nouveau pont Champlain
Anticipated Impacts
• Noise • Traffic
41
Projet de corridor du nouveau pont Champlain 42
M1 : Sud-Ouest / Argenson M2 : Sud-Ouest / Butler et Charlevoix M3 : Verdun
Noise management Ambient noise levels (May 2015) / estimated
(October 2016)
Area
Activity
Période Exposed Sensitive
Area
Ambient Noise dBA
Criterion dBA
Estimated Noise dBA
Measures requised D / E / N
Land
Road demolition D M1 / M2 66 / 64 75 67 / 68 No D M3 61 75 67 à 83 Yes
Construction of overpasses D M2 64 75 66 No D M3 61 75 64 à 82 Yes
Widening preparation work D M2 / M3 64 / 61 75 66 / 67 No
Construction of retaining walls D M1 / M2 66 / 64 75 69 / 66 No D M3 61 75 79 Yes
Installation of beams N M2 / M3 59 / 59 64 / 64 60 69 No Yes
Underground pedestal D M1 / M2 66 / 64 75 73 / 72 Monitoring required D M3 61 75 72
Excavation of the ramp 60 D M2 / M3 64 / 61 75 66 80 No Yes
Noise sensitive areas
Projet de corridor du nouveau pont Champlain 43
I1 : Sax I2 : Pointe-Nord I3 : Cours des Fougères
Noise management Ambient noise levels (May 2015) / estimated
(October 2016)
Area
Activity
Time Exposed Sensitive
Area
Ambient Noise dBA
Criterion dBA
Estimated Noise dBA
Measures Required
D / E / N
L'Île
-des
-Sœ
urs
West jetty – various activities
D I2 / I3
64 / 57 75 I2 : 64 à 68 I3 : 58 ou 59
Monitoring required
for specific activites
E 59 / 52 64 / 57 63 / 57 N 57 / 52 62 / 57 62 / 57
West jetty- Sheet piling D I2 / I3 64 / 57 75 73 / 66 Monitoring
required
Construction of new L’Île-des-Sœurs Bridge D I1 57 75 70 No
Overpass reconfiguration work D I1 57 75 74
Monitoring
required
Drilled piles for the tunnel and for the overpass D I1 / I2 57 / 64 75 70 / 67 No
Noise sensitive areas
Projet de corridor du nouveau pont Champlain
Traffic
• Partial day closure and full night closure, over 3 to 5 nights, in February : LaSalle and Wellington
• Reconfiguration of exits 60 and 61 of H15S for the spring / summer 2017
• Important modifications to road users habits of L’Île-des-Sœurs network from the beginning of Summer 2017
44
Projet de corridor du nouveau pont Champlain
Follow-up on Actions and Measures from Last Meeting
Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
46
SSL • Landscaping and urban integration
INFC (discussed in the next presentation) • GHG file • Permanent anti-noise walls • LED lighting • Interations with the REM Project Ville de Montréal (discussed in the next presentation) • Access to the St-Lawrence River from Pointe Saint-Charles • Future of the Île-des-Sœurs Bypass Bridge
Projet de corridor du nouveau pont Champlain
Next Meeting
Projet de corridor du nouveau pont Champlain
• Good Neighbourly Relations Committee : 18 april at Verdun Topic:
Traffic Anti-noise walls
• Site visit for committee members : May 5, 2017 in the afternoon
Next meetings
48
Projet de corridor du nouveau pont Champlain
● Website: www.newchamplain.ca
● Newsletter: sign up online
● Email: [email protected]
● 24/7 phone line: 514-876-1020
Contact Us
49
@nouv_champlain
Projet de corridor du nouveau pont Champlain
Our Proud Builders