    NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks

    1 PPRC + UPVC Piping B- Mazznine B-M M.Bilal Grace Engineers 100 0 Not Provided Completed

    2 Acessories Installation B- Mazznine B-M M.Bilal Grace Engineers 60 40 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type

    wash basin still not received

    3 PPRC + UPVC Piping B-1 B-1 M.Bilal Grace Engineers 80 20 Not Provided Pipe & wash room Accessories awaited

    4 Installation of pumps Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 15 2012 Subjected of completion of foundations

    5 Installation of chillers Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 23 2012 Subjected to arrival of chillers

    6 Installation of piping Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 30 2012 Subjected to route cleaning

    7Installation of

    Electrical panelPlant Room B-1 B-1 By Electrical Dept. Mecatech 0 100 June 23 2012

    8Electrical & control

    workPlant Room B-1 B-1 By Electrical Dept. Mecatech 0 100 June 30 2012

    9Testing &

    commissioningPlant Room B-1 B-1 Awais & Yousuf Mecatech 0 100 July 15 2012 Subjected to availability of gas and power

    10 PPRC + UPVC Piping B-2 B-2 M.Bilal Grace Engineers 80 20 Not Provided Main line installation required

    11 Installation Of Pumps B-3 B-3 M.Bilal &Yousuf Ali Technofire/ GraceEngineers

    0 100 Not Provided Material procurment required

    12Installation Of main

    lineB-3 B-3 Arshad Ahsan Grace Engineers 0 100 Not Provided Material procurment required

    13 Cleaning of B-3 Lines B-3 B-3 M.Ayaz 0 100 Not Provided Contractor required for work

    14 Pipe riser connection G.F Yousuf AliMecatech

    40 60 May 31 2012 Work in progress

    15 Testing of FCUs G.F Yousuf AliMecatech

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    16Electrical & ControlConnection of FCUS

    G.F Yousuf AliMecatech

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    17Installation of

    multisplit units( LiftLobby)

    G.F Yousuf AliMecatech

    0 100 June 30 2012 Not yet started

    18Testing &

    CommissioningG.F Yousuf Ali

    Mecatech0 100 June 30 2012

    Subjected to arrival of chillers & installation of Cooling Towers

    19 Duct Risers G.F Yousuf Ali ATS 20 80 Not Provided ATS has not provided any data yet20 Grills & Diffusers G.F Yousuf Ali ATS 0 100 Not Provided ATS has not provided any data yet

    21FCU Connections of

    ducts G.F Yousuf Ali ATS 100 0 Not Provided Completed

    22Duct in common

    areasG.F

    Yousuf Ali ATS100 0 Not Provided Completed

    23 Installation of pipe G.F Arshad Ahsan Mecatech 100 0 Not Provided Completed

    Status Of Mechanical WorkThe CENTAURUS Shopping Mall

  • 7/31/2019 Mechanical Work

    2/4

    NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks

    24Installation of

    SprinklersG.F

    Arshad Ahsan Technofire60 40 Not Provided Work in process

    25 Installation of HRC G.F Arshad Ahsan Technofire 0 100 Not Provided Material Awaited26

    Installation of Breeching inlet

    G.FArshad Ahsan Technofire

    0 100 Not Provided Material Awaited

    27 Installation of Valves G.FArshad Ahsan Technofire

    0 100 Not Provided Material Awaited

    28 PPRC + UPVC Piping G.FM.Bilal Grace Engineers

    100 0 Not Provided Completed

    29 Acessories Installation G.FM.Bilal Grace Engineers

    85 15 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type

    wash basin still not received

    30Installation of cooling

    TowersG.F

    Yousuf Ali & M.Bilal Mecatech20 80 June 15 2012 Subjected to dismentling of scaff-folding

    31

    32 Pipe riser connection M-1Yousuf Ali Mechatech

    40 60 May 31 2012 Work in progress

    33 Testing of FCUs M-1Yousuf Ali Mechatech

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    34Electrical & ControlConnection of FCUS

    M-1Yousuf Ali Mechatech

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    35Testing &

    CommissioningM-1

    Yousuf Ali Mechatech0 100 June 30 2012

    Subjected to arrival of chillers & installation of Cooling Towers

    36 Duct Risers M-1 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion37 Grills & Diffusers M-1 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion

    38FCU Connections of

    ductsM-1

    Yousuf Ali ATS90 100 Not Provided

    FCU connection ic Atriums Still pending due toinsufficient duct material

    39Duct in common

    areasM-1

    Yousuf Ali ATS100 0 Not Provided Completed

    40 Installation of pipe M-1 Arshad Ahsan Mechatech 100 0 Not Provided Completed

    41Installation of

    SprinklersM-1

    Arshad Ahsan Technofire 60 40Not Provided

    Work in process42 Installation of HRC M-1 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited

    43Installation of

    Breeching inletM-1

    Arshad Ahsan Technofire 0 100Not Provided

    Material Awaited

    44Installation of Valves

    M-1Arshad Ahsan Technofire 0 100

    Not ProvidedMaterial Awaited

    45PPRC + UPVC Piping

    M-1M.Bilal Grace Engineers 100 0

    Not Provided

    46 Acessories Installation M-1M.Bilal Grace Engineers

    80 20 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type

    wash basin still not received47

    48 Pipe riser connection M-2 Yousuf Ali MECATECH 40 60 May 31 2012 Work in progress

    49Testing of FCUs

    M-2Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    50Electrical & ControlConnection of FCUS M-2

    Yousuf Ali MECATECH0 100 June 15 2012 Subjected to Provision of service doors in ceiling

  • 7/31/2019 Mechanical Work

    3/4

    NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks

    51Testing &

    CommissioningM-2

    Yousuf Ali MECATECH0 100 June 30 2012

    Subjected to arrival of chillers & installation of Cooling Towers

    52 Duct Risers M-2 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion53 Grills & Diffusers M-2 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion54 FCU Connections M-2 Yousuf Ali ATS 100 0 Not Provided Completed

    55Duct in common

    areasM-2

    Yousuf Ali ATS100 0 Not Provided Completed

    56 Installation of pipe M-2 Arshad Ahsan MECATECH 100 0 Not Provided Completed

    57Installation of

    SprinklersM-2

    Arshad Ahsan Technofire0 100 Not Provided Work in process

    58 Installation of HRC M-2 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited

    59Installation of

    Breeching inletM-2

    Arshad Ahsan Technofire0 100 Not Provided Material Awaited

    60Installation of Valves

    M-2Arshad Ahsan Technofire

    0 100 Not Provided Material Awaited

    61PPRC + UPVC Piping

    M-2M.Bilal Grace Engineers 100 0

    Not Provided

    62 Acessories Installation M-2M.Bilal Grace Engineers

    80 20 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type

    wash basin still not received63

    64Pipe riser connection

    M-3Yousuf Ali MECATECH 40 60 May 31 2012 Work in progress

    65 Testing of FCUs M-3 Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    66 Electrical & ControlConnection of FCUS

    M-3Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    67Testing &

    CommissioningM-3

    Yousuf Ali MECATECH 0 100 June 30 2012Subjected to arrival of chillers & installation of

    Cooling Towers68 Duct Risers M-3 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion69 Grills & Diffusers M-3 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion70 FCU Connections M-3 Yousuf Ali ATS 10 90 Not Provided Incompleted

    71Duct in common

    areas M-3 Yousuf Ali ATS 50 50 Not Provided Incompleted72 Installation of pipe M-3 Arshad Ahsan MECATECH 100 0 Not Provided Completed

    73Installation of

    SprinklersM-3

    Arshad Ahsan Technofire 0 100Not Provided

    Not yet started74 Installation of HRC M-3 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited

    75Installation of

    Breeching inletM-3

    Arshad Ahsan Technofire 0 100Not Provided

    Material Awaited

    76Installation of Valves

    M-3Arshad Ahsan Technofire 0 100

    Not ProvidedMaterial Awaited

    77 PPRC + UPVC Piping M-3 M.Bilal Grace Engineers 100 0 Not Provided

    78Acessories Installation

    M-3M.Bilal Grace Engineers 80 20

    Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type

    wash basin still not received79

    80 Pipe riser connection M-4Yousuf Ali MECATECH

    40 60 May 31 2012 Work in progress

  • 7/31/2019 Mechanical Work

    4/4

    NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks

    81 Testing of FCUs M-4Yousuf Ali MECATECH

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    82 Electrical & ControlConnection of FCUS

    M-4Yousuf Ali MECATECH

    0 100 June 15 2012 Subjected to Provision of service doors in ceiling

    83Testing &

    CommissioningM-4

    Yousuf Ali MECATECH0 100 June 30 2012

    Subjected to arrival of chillers & installation of Cooling Towers

    84 Duct Risers M-4 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion85 Grills & Diffusers M-4 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion86 FCU Connections M-4 Yousuf Ali ATS 60 40 Not Provided Testing of FCU connection still pending

    87Duct in common

    areasM-4

    Yousuf Ali ATS60 40 Not Provided Testing and Installation still pending

    88 Installation of pipe M-4 Arshad Ahsan MECATECH 100 0 Not Provided Completed

    89Installation of

    SprinklersM-4

    Arshad Ahsan Technofire0 100 Not Provided Not yet started

    90 Installation of HRC M-4 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited

    91Installation of

    Breeching inletM-4

    Arshad Ahsan Technofire0 100 Not Provided Material Awaited

    92 Installation of Valves M-4Arshad Ahsan Technofire

    0 100 Not Provided Material Awaited

    93 PPRC + UPVC Piping M-4M.Bilal

    Nadeem Akhter &Bro

    100 0 Not Provided

    94 Acessories Installation M-4 M.BilalNadeem Akhter &Bro 80 20 Not Provided

    Indian WC Flush Tank, Floor Drains, Padestle typewash basin still not received

    9596 AHU piping M-5 Yousuf Ali MECATECH 0 100 Not Provided Not yet started

    97 Control Connections M-5Yousuf Ali MECATECH

    0 100 Not Provided Not yet started

    98Testing &

    CommissioningM-5

    Yousuf Ali MECATECH0 100 Not Provided Not yet started

    99 Installation of FCUs M-5 Yousuf Ali MECATECH 0 100 Not Provided Not yet started

    100Duct Connection of

    AHUsM-5

    Yousuf Ali ATS0 100 Not Provided Not yet started

    101 Duct Risers M-5 Yousuf Ali ATS 0 100 Not Provided Not yet started102 Installation of pipe M-5 Arshad Ahsan MECATECH 100 0 Not Provided Completed

    103Installation of

    SprinklersM-5

    Arshad Ahsan TECHNOFIRE0 100 Not Provided Not yet started

    104 Installation of HRC M-5 Arshad Ahsan TECHNOFIRE 0 100 Not Provided Material Awaited

    105Installation of

    Breeching inletM-5

    Arshad Ahsan TECHNOFIRE0 100 Not Provided Material Awaited

    106 Installation of Valves M-5Arshad Ahsan TECHNOFIRE

    0 100 Not Provided Material Awaited

    107 Rain water piping M-5M.Bilal

    Nadeem Akhter& Brother

    60 40 June 30 2012 Materail arrived late