MBTA WOLLASTON Station Improvements
Public MeetingJanuary 14, 2016
Kleinfelder, Inc.Architectural Engineers, Inc.| Code Red Consultants, LLC
Keville Enterprises, Inc. | Vertical Transportation Excellence | WSP Group
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
AGENDA
Project Update
Design Improvements
Comments & Questions
Next Steps
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
• Project schedule
• Project funding
• New station and site layout
PROJECT UPDATE
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
EXISTING CONDITIONS
PROJECT AREA
3
4
5
2
1
SOUTH PARKING LOT
LOT
ATTENDANT
BOOTH
NORTH PARKING LOT
PICK-UP/DROP-
OFF AREA
WE
ST
ON
AV
E.
NE
WP
OR
T A
VE
NU
E
GR
EENW
OO
D A
VEN
UE
OL
D C
OLO
NY
AV
E.
STATION
PLATFO
RM
BEALE S
TREET
BROO
K STREET
WO
OD
BIN
E
ST
RE
ET
WA
YL
AN
D
ST.
NEWPORT AVENUE ENTRY
PARKING LOT ENTRY2 PEDESTRIAN & BIKE ACCESS POINT
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
EXISTING CONDITIONS
PLATFORMEDGE
CONCRETEENTRANCECANOPY
INBOUND TRACK
COMMUTER RAIL TRACK
OUTBOUND TRACK
Storage Shelter Shelter Lightwell
Porter RmBench, Typ.
LightsLights
0' 8' 16' 32' NPLATFORM LEVEL PLAN
DN
DN DN
CONCRETE
ENTRANCE
CANOPY
ABOVE
EDGE OF
PLATFORM
ABOVE
64'32'16'8'0'N
NEWPORT AVE
PARKING LOT
UNEXCAVATED UNEXCAVATED
UP TO
PLATFORM
ESCALATOR
AFC
W
FA
ELEC
STO
JAN
MC O M M W/ FA
ELEC & PUMP
LOBBY LEVEL PLAN
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PLATFORMEDGE
CONCRETEENTRANCECANOPY
INBOUND TRACK
COMMUTER RAIL TRACK
OUTBOUND TRACK
Storage Shelter Shelter Lightwell
Porter RmBench, Typ.
LightsLights
0' 8' 16' 32' N
EXISTING
DN
DN DN
CONCRETE
ENTRANCE
CANOPY
ABOVE
EDGE OF
PLATFORM
ABOVE
64'32'16'8'0'N
NEWPORT AVE
PARKING LOT
UNEXCAVATED UNEXCAVATED
UP TO
PLATFORM
ESCALATOR
AFC
W
FA
ELEC
STO
JAN
MC O M M W/ FA
ELEC & PUMP
PLATFORM LEVEL PLAN
LOBBY LEVEL PLAN
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
DN
DN DN
CONCRETE
ENTRANCE
CANOPY
ABOVE
EDGE OF
PLATFORM
ABOVE
64'32'16'8'0'N
NEWPORT AVE
PARKING LOT
UNEXCAVATED UNEXCAVATED
UP TO
PLATFORM
ESCALATOR
AFC
W
FA
ELEC
STO
JAN
MC O M M W/ FA
ELEC & PUMP
PLATFORMEDGE
CONCRETEENTRANCECANOPY
INBOUND TRACK
COMMUTER RAIL TRACK
OUTBOUND TRACK
Storage Shelter Shelter Lightwell
Porter RmBench, Typ.
LightsLights
0' 8' 16' 32' NPLATFORM LEVEL PLAN
Lobby LeveL PLan
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
STATION DESIGN PROCESS
Develop Alternatives
(15% Design)
Consensus Option
(30% Design)
Develop Design
(60% Design)
Finalize Design
(100% Design)
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PROGRAM OF IMPROVEMENTS
•Flooding
•Accessibility
•Coordination with City
& Planning Agencies
•Code
•Additional Station
Improvements
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
ACCESSIBILITY REQUIREMENTS
• Accessible pathways around the site
• Accessible entrances
• Accessiblity between platform and lobby
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
• Electrical upgrades
• Replace escalator
• Updateirealarmandiresuppression
• Remedy drainage and looding
• Site improvements
• Security upgrades
• Enhance architecture
• Mechanical upgrades
• Replace signage
ADDITIONAL FULL STATION IMPROVEMENTS
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
NEW NORTH HEADHOUSE
NEW SOUTH HEADHOUSE
NEW CANOPY
NEW BRIDGE
w/ AFC NEW
BRIDGE
NEW ADA RAMP
NEW PLATFORM
CANOPY
CONSENSUS STATION OPTION AT 30%
N
PN
•2 Headhouses
•Maintain passthrough
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
NEW NORTH HEADHOUSE
NEW SOUTH HEADHOUSE
NEW CANOPY
NEW BRIDGE
w/ AFC NEW
BRIDGE
NEW ADA RAMP
NEW PLATFORM
CANOPY
DESIGN IMPROVEMENTS FOR 60%
N
PN
•Quicker route to the platform
•More compact footprint
ONE CENTRAL HEADHOUSE
COMBINING NORTH + SOUTH
HH FROM 30%
MAINTAIN UNDERGROUND
PASSTHROUGH AND
USE IT AS A LOBBY
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
Elev 1
Elev 3
Elev 1
UpUp
Up
Up
Stair
Esc 1
M W
Escr
Port
Supv
Starter/Break
Fire
L.S.
Mezz Stair
Jan
CSA
AFC
Unpaid Lobby
PaidLobby
Ram
p
StairRamp
Jan
MainElec
Ecr
Comm
Mezz Stair
Mezz
Mezzanine Level
Elev 2 abv
DESIGN IMPROVEMENTS FOR 60%
N
PN
•More active lobby in passthrough
ONE CENTRAL HEADHOUSE
COMBINING NORTH + SOUTH
HH FROM 30%
MAINTAIN UNDERGROUND
PASSTHROUGH AND
USE IT AS A LOBBY
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
STATION LOBBY LEVEL LAYOUT
N
PN• EXISTING LOBBY REMAINS PASSTHROUGH AND BECOMES DOUBLE ACCESS TO PLATFORM
• SECURED BIKE PARKING MOVES
• NEW HEADHOUSE + PASSTHROUGH ELEVATORS
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PASSTHROUGH SECTION
• MAINTAIN PASSTHROUGH
• BASEMENT LOBBY ON BOTH SIDES WITH ACCESS TO THE PLATFORM
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PLATFORM SECTION
• BRIDGE OVER TRACKS AT HEADHOUSE
• NEW PLATFORM ELEVATORS
• NEW PLATFORM STAIRS
• REPLACE PLATFORM CANOPY
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
N
PN
BRIDGE LOBBY LEVEL LAYOUT
• BRIDGE OVER TRACKS FROM HEADHOUSE
• NEW ESCALATORS AND ELEVATORS TO/FROM BRIDGE
• REPLACE PLATFORM CANOPY
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
DN
UP
RD RD
DROP OFF
INBOUND RED LINE
OUTBOUND RED LINE
COMMUTER RAIL
NEWPORT AVE
PARKING LOT
PLATFORM CANOPYBELOW
MEDIUM ROOF
NORTHBRIDGE
CANOPY BELOW
LOWER ROOF BIKE STORAGE
PLATFORMPLATFORM CANOPY
BELOW
BRIDGELOBBY
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
HEADHOUSE ELEVATOR SECTION
• BRIDGE OVER TRACKS AT NEW HEADHOUSE
• ELEVATORS AT NEW HEADHOUSE AND PLATFORM
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
STATION PLATFORM LEVEL LAYOUT
N
PN
• ELEVATOR TO HEADHOUSE BRIDGE
• ELEVATOR TO PASSTHROUGH LOBBY
• NEW STAIR FROM LOBBY TO PLATFORM
DN
NEWPORT AVE
SECURED BIKEPARKING
WESTENTRANCE
PLATFORM
DROP OFFPARKING LOT PARKING LOT
HEADHOUSEMEZZANINE
LOWERROOF
INBOUND RED LINE
OUTBOUND RED LINE
COMMUTER RAIL
BRIDGE
HEADHOUSE
SERVICE SPACE
SECURED BIKE PARKING
CIRCULATION
STAIR/ RAMP
ELEVATOR
ESCALATOR
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PERSPECTIVE VIEWS
12
1
2
FROM THE PARKING LOT SIDE
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PERSPECTIVE VIEWS
1
2
1
2
FROM BROOK STREET AND NEWPORT AVENUE
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
PERSPECTIVE VIEWSFROM THE HEADHOUSE LOBBY AND FROM PASSTHROUGH
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
N
PN
•Separate pedestrians
and bicyclists from
the parking
•Plan for integration
with future
neighborhood bike
lanes
•Allow for future site
development
•Maintain parking
capacity
SITE LAYOUT
SOUTH LOT
PLATFORM
NEWPORT AVE
GREENWOOD AVE
WO
OD
BIN
E S
T
BE
ALE
ST
WESTON
AVENORTH LOT
BROOKE ST
WA
YLA
ND
ST
2
2
24
2
5
21
3
* TBD pending coordination w/ City
*
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
COMMENTS & QUESTIONS
WWW.MBTA.COM/ABOUT_THE_MBTA/T_PROJECTS
WOLLASTON STATION PROJECT @ GMAIL.COM
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
NEXT STEPS
Final Design
Summer 2016
Next Public Meeting
Spring 2016
60% Design
January 2016
MBTA WOLLASTON - STATION IMPROVEMENTS PUBLIC MEETING - JANUARY 14, 2016
THANK YOU!