Monthly Progress Report 35, May 2014 Page 1 of 39 FOUR LANING OF JAIPUR TONK DEOLI SECTION OF NH12 FROM KM 18.70 TO KM 165.000 IN STATE OF RAJASTHAN ON DBFOT PATTERN UNDER NHDP PHASE III INDEPENDENT ENGINEER MONTHLY PROGRESS REPORT NO. 35 MAY- 2014 Authority : National Highways Authority of India Independent Engineer : Aarvee Associates, Architect, Engineers & Consultant Pvt Ltd. Concessionaire : IRB Jaipur Deoli Tollway Pvt. Ltd. EPC Contractor : IRB Infrastructure Developers Ltd. Supervision Team : Stup Consultant Pvt. Ltd.

Upload: truongliem

Post on 30-Jun-2018

290 views

Category:

Documents


25 download

TRANSCRIPT

Page 1: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 1 of 39

FOUR LANING OF JAIPUR TONK DEOLI SECTION OF NH12 FROM KM

18.70 TO KM 165.000 IN STATE OF RAJASTHAN ON DBFOT PATTERN

UNDER NHDP PHASE III

INDEPENDENT ENGINEER

MONTHLY PROGRESS REPORT NO. 35MAY- 2014

Authority : National Highways Authority of India

Independent Engineer : Aarvee Associates, Architect, Engineers

& Consultant Pvt Ltd.

Concessionaire : IRB Jaipur Deoli Tollway Pvt. Ltd.

EPC Contractor : IRB Infrastructure Developers Ltd.

Supervision Team : Stup Consultant Pvt. Ltd.

Page 2: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 2 of 39

.

TABLE OF CONTENTS

1. Chapter 1- Introduction 3 – 7

1.1. Project Brief 3

1.2. Location Map 4

1.3. Executive Summary 5

1.4. Related Agencies 6

1.5. Salient Features 7

2. Chapter 2 - Scope of Project 8 – 9

2.1. Scope of Work 8

2.2. Milestones 9

3. Chapter 3 – Organization 10 – 13

3.1. Authority 10

3.2. Independent Engineer 10

3.3. IE Organization Chart 11

3.4. Concessionaire 12

3.5. EPC Contractor 12

3.6. Overall Organization Chart 13

4. Chapter 4 – Project Status 14 – 17

4.1. Summary of Highway Progress 14 – 15

4.2. Summary of Structure Progress 16

4.3. Present Progress – Highway 17

4.4. Physical Progress – Highway 17

4.5. Physical Progress – Structure 17

Page 3: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 3 of 39

5. Chapter 5 - Project Inspection 18 – 26

5.1. Development Phase 18

5.2. Construction Phase 19 – 26

5.2.1 Safety 19

5.2.2 Quality Control 20

5.2.3 Environment 20

5.2.4 Applicable Permits 20

5.2.5 Witnessed Field/Lab Tests by IE 21 – 26

6. Chapter 6 – Correspondences 27 – 31

6.1 Independent Engineer Correspondence 27 – 29

6.2 Drawings Section 30

7. Chapter 7 – Weather Report 31

8. Chapter 8 – Constraints 32

8.1 Concessionaire 32

9. Chapter 9 – Conclusions 33

10. Chapter 10 – Strip Plan 34 - 36

11. Chapter 11 – Project Photographs 37 - 38

12. Chapter 12 – Monthly Inspection Report of Independent Engineer 39

Page 4: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 4 of 39

CHAPTER – 1

INTRODUCTION

1.1 Project Brief:

The Government of India has taken policy initiatives to promote Public Private

Partnership (PPPs) on Design, Build, Finance, Operate and Transfer (DBFOT)

basis for upgrade and maintenance of highways. The Committee or Infrastructure

has prepared a Model Concession Agreement (MCA) for PPPs.

The National Highways Authority of India (Authority under NHDP Phase – III B

programme of four/six laning) has resolved to augment the existing road from Km.

18.700 to Km 165.000 (Approximately 148.770 Km.) on the Jaipur – Deoli Section

of National Highway No. – 12 (NH-12) in the state of Rajasthan to four lane on

Design, Build, Finance, Operate and Transfer basis through Concessionaire in

accordance with terms and conditions set forth in Concession Agreement.

The Highway Road is a Section of National Highway – 12, starting at Jaipur in the

State of Rajasthan and traversing through the States of Rajasthan and Madhya

Pradesh. Total length of NH-12 is about 915 km with stretches lying in various

states as under:

Rajasthan - 416 km

Madhya Pradesh - 499 km

Important cities and town’s enroute are Jaipur, Tonk, Deoli, Bundi, Kota, Bhopal

and Jabalpur and in the state of Rajasthan, NH-12 passes through the districts of

Jaipur, Tonk and Bhilwara.

The project traverse between latitude 25 45’ & 26 45’ and longitude 75 15’ & 75

45’ respectively. Project stretch runs in mostly plain terrain and has mostly flat

gradients which have 1 - Major Bridge and 26 - Minor Bridge, 4 - Flyovers, and 2-

ROB's on the main Carriageway.

Page 5: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 5 of 39

1.2 Location

Gunsi

Page 6: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 6 of 39

1.3 EXECUTIVE SUMMARY:

The Highway Project described in this report is in construction and operation period, and runs from km 18+700 to 165+000 between Jaipur and Deoli on NH-12 in the State of Rajasthan.

The project was awarded to the M/s. IRB – MRM Consortium and created SPV for Concessionaire M/s IRB Jaipur Deoli Toll Way Pvt. Ltd. and the LOA was issued on 14th Oct. 2009. The Concession agreement was signed in between M/s IRB Jaipur Deoli Toll Way Pvt. Ltd., and National Highways Authority of India on 16th Dec. 2009 for Concession Period of 25 years including construction period of 910 days. The financial closer had to be completed within 180 days from the date of Agreement. The financial closer has been achieved & appointed Date is 14 June. 2010. The concession Agreement specifies project completion schedule & the Project Mile Stones are described in chapter 2.

Aarvee Associates Architects, Engineers & Consultant Pvt. Ltd has been appointed as Independent Engineer (IE) of the project .The LOA was issued on 23rd Oct-2010. Contract for Consultants Service was signed in between M/S Aarvee Associates Architects, Engineers & Consultant Pvt. Ltd and National Highways Authority of India on 6th Sep. 2010. Independent Engineer mobilized since September 2010. The IE has established their office and all of the key professionals & sub professional staff have been appointed and placed.

The Concessionaire has established himself and with his nominated EPC contractor. M/s IRB Infrastructure Developers Ltd. Concessionaire has deployed M/s. Halcrow Consulting India Pvt. Ltd. as Design Consultant for Highways & Structures. Concessionaire has deployed M/s. Stup Consultants Pvt. Ltd., as Supervision Team for construction-supervision and operation-maintenance.

Page 7: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 7 of 39

1.4 RELATED AGENCIES:

Project: Design, Construction, Development, Finance, Operation Maintenance Four Laning of Jaipur Tonk Deoli Section of NH12 from Km 18.700 to Km 165.000 in State of Rajasthan on DBFOT Pattern Under NHDP Phase III

Client / Employer: National Highways Authority of India

G 5&6, Sector – 10, Dwaraka, New Delhi – 110075

National Highways Authority of India, (Site Office) Project Implementation Unit,

3, Preeti Bhlagwat Niwas Behind Chandralok Hotel Malviya Nagar, Tonk, Rajasthan - 304001.

Phone: - - 22354135. Fax 044-22354134. E-mail:- [email protected].

Independent Engineer: M/s Aarvee Associates Architects, Engineers &

Consultants Private Limited. 8-2-5, Srinagar Colony, Hyderabad – 500 082. Andhra Pradesh India Phone: - 044 - 26512607, Fax:- 044 – 26512608 IRB Office address Aarvee Associates Architects, Engineers & Consultant Private Limited. Plot No. 15-16, Param Hans Colony Near Saraswati Vidya Mandir,Jhilai Road IRB, Dist.- Tonk 304021 E-mail:- [email protected]

Concessionaire: M/s. IRB Jaipur Tonk Deoli Toll Way Limited,

39, Bapu Nagar, 80 feet ring road, IRB Dist.- Tonk. Rajasthan 304021 Phone:- 01438 – 223166 E-mail:- [email protected]

EPC Contractor: M/s. IRB Infrastructure Developers Ltd

Design Consultant: M/s. Halcrow Consulting India Pvt. Ltd.

Supervision Team: M/s Stup Consultants Pvt. Ltd.,

Page 8: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 8 of 39

1.5 SALIENT FEATURES:

Date of Agreement : 16th Dec. 2009

Period of Construction : 910 days

Extension of Time Recommended : 202 days

Appointed date : 14th June 2010

Completion Date : 9th Dec. 2012

Total Project Cost (TPC) : Rs. 792.00 Crores

Equity Support/Grant by the Authority : Rs. 306.00 Crores

Capital Cost : Rs. 1733.00 Crores

Concession Period : 25 Years

Project Length : 148.770 Kilometers

No. of Bypasses : 08

No. of Major Bridge : 01

No of Minor Bridge : 26

No of Flyovers : 04

No of ROB : 02

No of VUP’s : 11

No of PUP’s/CUP : 08

No of Toll Plazas : 02

No of Widening of Box Culverts : 34

No of New RCC Box Culverts : 09

No of Improvement of Pipe Culverts : 81

Page 9: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 9 of 39

CHAPTER – 2

SCOPE OF PROJECT

2.1 Scope of Work:

The scope of the Access Controlled Highway Project as detailed in the Concession

Agreement shall be broadly classified as follows: -

Four-Lane Access Controlled Highway N.H. 12 from Km. 18.700 to Km. 165.00

in the State of Rajasthan

Exit & Entry ramps on the project highway to be provided

A length of Km 18.381 service road is to be provided on either side of Project

Highway.

4 nos. of flyovers, 11 nos. of VUP, 5 nos. of CUP and 3 nos. of PUP are to be

constructed.

09 nos. of RCC Box culverts are to be newly constructed, 34 nos. of Box

culverts are to be widened and 81 nos. of pipe culverts are to be improved.

26 no of Minor Bridges and 1 no of Major Bridge on LHS Main carriage way are

to be constructed.

At 25 locations at grade junctions are to be improved.

29 Kms of drain is to be constructed.

During the entire construction period, the Highway Project is to be maintained

by the Concessionaire at his cost from the appointed date.

Traffic Management and Safety of Workers and the public shall be maintained

at all times in accordance with the relevant IRC/IS Codes as stipulated in the

Concession Agreement without any deviations.

Page 10: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 10 of 39

2.2 Mile Stones:

S# Milestone Period from Appointed

date

Completion Date

Description Remarks

1 Milestone-I 270 days 10.03.2011

Concessionaire shall have commenced construction of Project Highway and expended not less than 10% of the total capital cost set forth in the Financial Package.

Achieved

2 Milestone-II 455 days 11.09.2011

Concessionaire shall have commenced construction of all bridges and expended not less than 35% of the total capital cost set forth in the Financial Package.

Achieved and reviewed by IE letter no. ARV/JTD/NH-12/11-12/0563 dated 10.09.2011

3 Milestone-

III 650 days 24.03.2012

Concessionaire shall have commenced construction of all Project Facilities and expended not less than 70% of the total capital cost set forth in the Financial.

Achieved on 20.06.2012 within 90 days of Schedule date of milestone-III per Clause 12.4.2 and reviewed by IE letter no. AA/HW/1009/12-13/5 dated 06.10.2012

4 Scheduled Completion

Date

910 days 09.12.2012

Concessionaire shall have completed the Four-Lane Project Highway in accordance with this Agreement.

Four laning have not been completed on schedule date, IE have notified to the Concessionaire under Clause 5 of Schedule “G” vide letter no. ARV/JTD/NH-12/12-13/1315 dated 10.12.2012 and requested to submit action plan for completion of Four-Lane

5 Extension of Time for Completion

202 days 29.06.2013

Concessionaire shall have completed the Four-Lane Project Highway in accordance with this Agreement.

EOT has been recommended vide letter no. AA/HW/NHAI/1009/12-13/262 dated 13.02.2013.

6 Provisional

COD 27.09.2013

COD has been given vide letter no. AA/HW/NHAI/1009/12-13/262 dated 27.09.2013.

7 Provisional

COD - 2

Page 11: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 11 of 39

CHAPTER – 3

ORGANIZATION

3.1 Authority

In terms of Concession Agreement, National Highways Authority of India is working

as Authority. Project Implementation Unit at Tonk is headed by Project Director

followed by Managers (Technical) and other Administrative staffs overall

Organization Chart of project is given in Fig 3.1.

3.2 Independent Engineer

Independent Engineer took charge of duty in the Mid of Sep-2010. The team at site

is headed by Team Leader. All key staff members and supporting staff have been

mobilized. Part-time / Intermittent staff is visiting site as and when required, basis

apart from reviewing Design, Drawings and Submittals from main/satellite offices.

In addition to above, Project Coordinator works as link between site office and

main office for coordinating issues beyond day to day works. Table 3.2.1 shows the

deployment of IE and Fig: 3.2.2 represents IE organization chart.

Table 3.2.1 Independent Engineer Deployment Status

No. Designation Name Mobilization Date

Key Staff

1 Team Leader Mr. Ernest A. Posey 17th January 11

2 Resident Engineer Cum Highway Engineer Mr. Anil Garg 17th September 10

3 Senior Pavement Expert Mr. Ziauddin A Khan 14th September 10

4 Senior Bridge Design Engineer Mr. Atanu Dhara 28th September 10

5 Senior Quality Cum Material Expert Mr. Mohan Pandey 1st October 10

6 Bridge / Structural Engineer Mr. Kiran Dandapat 13th September 10

7 Highway Design Engineer Mr. N S Chary 15th September 10

8 Traffic & Transportation Expert Dr. B Raghvendra Available from HO when required.

9 Road Safety Expert Mr. Gautam Ghosh Available from HO when required.

10 Financial Expert Mr. Rajendra Available from HO when required.

Page 12: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 12 of 39

Page 13: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 13 of 39

Table 3.2.1 IE Deployment Status (Cont'd)

3.3 Concessionaire

The organization of Concessionaire’s is represented by its Project Director who is

based at site office. The position is responsible for day to day activities conducted

by EPC Contractor and also provides information to IE as and when necessary.

Monthly review progress meetings chaired by IE the Concessionaire is represented

by the position. Concessionaire has appointed agency (M/s. Stup Consultants Pvt.

Ltd.) for Supervision of Project see Fig: 3.3.1 represents Concessionaire's and

Supervision Team organization chart

3.4 EPC Contractor

The Contractor/Agency is appointed by Concessionaire for the construction of the

project. Contractor is headed by Project Head, followed by construction managers,

senior managers, engineers and other site and administration personnel. EPC

Contractor has separate teams for road works and structures’ works.

S.No. Position Name Mobilization Date

Sub-Professional Staff

1 Survey Engineer Mr. Badan Singh 9th May 11

2 Assistant Highway Engineer I Mr. Varun Yadav 12th May 11

3 Assistant Highway Engineer II TBN

4 Assistant Highway Engineer III TBN

5 CAD Expert TBN

6 Environmental Engineer Dr. B. Mishra 20th October 10

7 Asst. Bridge Engineer I TBN

8 Asst. Bridge Engineer II Mr. Rajesh Kumar 1st January 11

9 Asst. Bridge Engineer III Mr. Naveen Mahavar 4th October 11

10 Asst. Quality cum Material Engineer I Mr. Rajendra Prasad 1st December 10

11 Asst. Quality cum Material Engineer II Mr. Hariom Agrawal 23rd

December 11

12 Asst. Quality cum Material Engineer III TBN

13 Electrical Engineer Mr. Ramesh Gupta September 10

14 HTMS/Toll Expert Mr. Guru Raja Rao 17th January 11

15 Horticulturist TBN

Page 14: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 14 of 39

3.3.1 ORGANIZATION CHART

Overall Project Organization

Independent Engineer

Aarvee Associates architects engineers &

consultants pvt. ltd.

Concessionaire

IRB Jaipur Deoli Toll Way Pvt. Ltd

Project Supervision Team

STUP Consultants P. Limited

Design Consultant Halcrow Consulting India

Pvt. Ltd.

Owner Client

National Highways Authority

of India

EPC

IRB Infrastructure Developers Ltd

Page 15: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 15 of 39

CHAPTER – 4

PROJECT STATUS

The project progress for highways and structures are shown in following Tables.

Table 4.1 Summary of Highway Progress

S. No.

Item Section

Quantity in KM

Side Total Completed Work in

Progress Balance

1 Earthwork of Roadway

Package - I I B/S 49.340 48.239 0.375 0.726

Package - II II B/S 50.070 50.070 0.000 0.000

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.823 0.375 0.726

2 Subgrade

Package - I I B/S 49.340 48.245 0.605 0.490

Package - II II B/S 50.070 50.070 0.000 0.000

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.829 0.605 0.490

3 G S B

Package - I I B/S 49.340 48.230 0.275 0.835

Package - II II B/S 50.070 50.070 0.000 0.000

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.814 0.275 0.835

4 WMM

Package - I I B/S 49.340 48.205 0.025 1.110

Package - II II B/S 50.070 50.070 0.000 0.000

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.789 0.025 1.110

5 D B M

Package - I I B/S 49.340 48.176 0.375 0.790

Package - II II B/S 50.070 49.944 0.000 0.000

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.633 0.375 0.790

Page 16: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 16 of 39

S. No.

Item Section

Quantity in KM

Side Total Completed Work in

Progress Balance

6 B C

Package - I I B/S 49.340 47.959 0.000 1.382

Package - II II B/S 50.070 49.913 0.000 0.158

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924 147.385 0.000 1.539

7 Kerb

Package - I I B/S 49.340 49.340 0.000 1.167

Package – II II B/S 50.070 49.985 0.000 0.085

Package – III III B/S 49.514 49.332 0.000 0.182

Total B/S 148.924 147.491 0.000 1.434

8 Road Furniture

Package - I I B/S 49.340 47.040 24.080 2.300

Package - II II B/S 50.070 48.410 0.000 1.660

Package - III III B/S 49.514 49.514 0.000 0.000

Total B/S 148.924

144.964

0.000

3.960

Page 17: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 17 of 39

Table 4.2 Summary of Structures Progress

Sr. No.

Type of Structure

Section Unit

Quantity

Total Completed Work in

Progress Balance

1 Fly Over

Section -I No. 2 2 0 0

Section -II No. 2 2 0 0

Section -III No. - - - -

Total No. 4 4 0 0

2 Major Bridge

Section -I No. - - - -

Section -II No. 1 1 0 0

Section -III No. - - - -

Total No. 1 1 0 0

3 Railway Over Bridge

Section -I No. 1 0 1 0

Section -II No. 1 0 1 0

Section -III No. - - - -

Total No. 2 0 2 0

4 Minor Bridge

Section -I No. 6 6 0 0

Section -II No. 9 9 0 0

Section -III No. 11 11 0 0

Total No. 26 26 0 0

5 Vehicular Underpass

Section -I No. 5 5 0 0

Section -II No. 5 5 0 0

Section -III No. 1 1 0 0

Total No. 11 11 0 0

6 Cattle Underpass

Section -I No. 2 2 0 0

Section -II No. 1 1 0 0

Section -III No. 2 2 0 0

Total No. 5 5 0 0

7 Pedestrian Underpass

Section -I No. - - - -

Section -II No. 1 1 0 0

Section -III No. 3 3 0 0

Total No. 4 4 0 0

8 Slab / Box Culvert

Section -I No. 14 14 0 0

Section -II No. 16 16 0 0

Section -III No. 16 16 0 0

Total 46 45 0 0

9 Hume Pipe Culvert

Section -I No. 25 25 0 0

Section -II No. 32 32 0 0

Section -III No. 40 40 0 0

Total 97 97 0 0

Total Structures 196 194 2 0

Page 18: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 18 of 39

Table 4.3 Present Progress – Highways

S. No. Particular % Completed Remarks

1 Road works Completed in % 75.660%

2 Structures completed in % 22.560%

Total Progress in % 98.220%

Table 4.4 Physical Progress – Highways

Sr. Type of Activity

Unit Total KM Percentage Factor Physical progress

Physical

progress KM in

%

Physical

Progress in %.

1 Earthwork km 148.975 10.62 0.071 146.69 98.47% 10.551%

2 SG km 148.975 6.46 0.043 145.28 97.52% 6.423%

3 GSB km 148.975 8.39 0.056 146.19 98.13% 8.332%

4 WMM km 148.975 9.5 0.064 145.49 97.66% 9.425%

5 D.B.M km 148.975 23.94 0.161 145.37 97.58% 23.754%

6 B.C. km 148.975 10.91 0.073 145.27 97.51% 10.794%

7 Toll Plaza nos. 2 1.02 0.510 1.95 97.50% 1.020%

8 Misc. Works LS 148.975 5.58 134.018 89.96% 5.360%

Total 76.42 75.660%

Table 4.5 Physical Progress – Structures

Sr. Type of Structure UNIT No. of

Structure

Percentage

Factor for one Structure

Completed Progress in %

Physical Progress in %

1 Major Bridge NO 1 2.77 2.770 100.00% 2.770%

2 ROB, Flyover NO 6 6.99 1.165 85.84% 6.000%

3 Minor Bridge NO 26 3.99 0.153 100.00% 3.990%

4 Underpass (VUP/PUP/ CUP)

NO 19 7.27 0.383 100.00% 7.270%

5 Culverts NO 124 2.02 0.016 99.00% 2.000%

6 Rehabilitation of structures

NO 20 0.53 0.027 100.00% 0.530%

Total 23.57 22.560%

Page 19: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 19 of 39

CHAPTER – 5

PROJECT INSPECTION

5.1 DEVELOPMENT PHASE In accordance to Concession Agreement, stipulated period of Development

Phase is over.

Pavement Design has been submitted by the Concessionaire and

reviewed by IE.

Plan & Profile of main carriageway are reviewed by IE.

The design, Drawings & calculations of two ROBs have been approved

by the Railway Authority. The construction works of both ROBs are

under progress.

GAD and structural design of a major bridge, minor bridges, vehicular

underpass, pedestrian underpass and flyovers has been reviewed.

The existing major bridge at km 76+499 has been rehabilitated and it is

in operation.

Page 20: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 20 of 39

5.2 CONSTRUCTION PHASE

5.2.1 Safety During Construction

Contractor has placed barrier, sand bags, bamboo sticks and warning/safety plastic tapes along the shoulder line where the C&G and earthworks are in progress at few of the locations; a few locations are yet to barricade to be placed.

Concessionaire has been instructed if there any excavation next to the travel way provide temporary barricades along the shoulder line to protect the motorists and pedestrians falling down in the excavation ditch. At a few locations, it is missing.

All workers engaged in the bore muck/flush work shall wear Gumshoes.

Those working with wire rope shall wear Gloves.

All workers shall be provided with safety helmets.

Safety cordon shall be provided at each Pile location and around the under water tanks / Bentonite tanks.

All switch boards shall be kept properly covered and all site electrical shall be carried on bamboo poles with insulated wires

Welders and Gas cutters should maintain Safety Precautions.

All earthings shall be done properly using insulated cables.

All movements shall be carried out with Supervisory staff on constant duty.

Emergency medical kit and other emergency movement facilities shall be maintained at site.

All lighting shall have properly covered insulated wires, Halogen lamps

and hand lamps with wire mesh covering.

All hot cutting scarps shall be announced and removed properly.

No free fire shall be burnt at site.

All oil, fuel installation/stockyard shall be properly protected with temporary firefighting equipment.

Page 21: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 21 of 39

5.2.2 Quality Control

Concessionaire has submitted the Quality Assurance Plan and IE have reviewed the same. IE’s representatives have been inspecting and checking the day to day work executed at the site & laboratory as per Concession Agreement.

5.2.3 Environmental Report

During the construction stage the Independent Engineer plays a vital role in

supervising the environmental aspects and adoption of the best suitable

mitigation measures for an effective implementation of the Environmental

Management Plan by the Contractor. As a part of the Independent Engineer

Services and “Schedule I” of compliance, Environmental monitoring has been

carried from 06.02.2014 to 11.02.2014 and report has been submitted to the

Authority vide letter no. 1009/ARV/JTD/NH-12/13-14/1838 dated 17.02.2014.

The joint inspection covers the inspection of borrow areas, crusher plant,

batching plant, wet mix macadam plant, camp site, etc. Based on the field

visit and subsequent discussions had with concerned officials from Contractor

and concessionaire, a standard environmental performs have been prepared

covering all the environmental issues related to major highway project.

5.2.4 Applicable Permits

Concessionaire has obtained the applicable permits from the respective

authority in accordance to the Schedule “E” of CA.

IRB obtained the applicable permits as required and submitted to IE for

review. Permits obtained by concessionaire has been submitted to Authority.

Page 22: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 22 of 39

5.2.5 Witnessed Field/Lab Test by Independent Engineer

Quality Control Report for Feb – 2013

Page 23: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 23 of 39

Page 24: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 24 of 39

Page 25: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 25 of 39

Page 26: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 26 of 39

Page 27: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 27 of 39

Page 28: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 28 of 39

CHAPTER – 6

6.1 IE CORRESPONDANCE Jan 2014

S# Date Letter No. Subject Replied Add.

to CC To

1 03.03.2014 1009/ARV/JTD/

NH-12/13-14/1844

Submission of Monthly Invoice No. 38 for Foreign Currency & Invoice No. 42 for Local Currency for the month of February 2014.

NHAI

2 03.03.2014 ARV/JTD/NH-12/13-14/1845

Toll Information System (TIS) Data Sheet.

Email dated 28.02.2014 NHAI IRB

3 04.03.2014 ARV/JTD/NH-12/13-14/1846

Master Files for BOT Projects in Electronic From - reg.

NHAI

4 04.03.2014 ARV/JTD/NH-12/13-14/1847

Assembly Question 1137 Dt. 23.01.2014 Hon'ble MLA Shri Rajender Gurjar

1 NHAI Letter: Email dt: 04.04.2014 NHAI IRB

5 07.03.2014 ARV/JTD/NH-12/13-14/1848

Issues raised by AIMTC 1 NHAI Letter: Email dt: 06.04.2014 NHAI IRB

6 11.03.2014 ARV/JTD/NH-12/13-14/1849

Use of Reclaimed Asphalt Pavement (RAP) Material in NHAI Project.

1 NHAI Emai: dated 11.04.2014 2 NHAI HQ Letter no. NHAI/CGM(TIC)/RAP/2011/127 dated 10.03.2014

NHAI IRB

7 12.03.2014 ARV/JTD/NH-12/13-14/1850

Relase of withheld Payments.

1 IE Letter no. AA/HW/NHAI/1009/13-14/429 dated 25.09.2013 2 IE Letter no. 1009/ARV/JTD/NH-12/13-14/1830 dated 10.02.2014

NHAI

8 13.03.2014 ARV/JTD/NH-12/13-14/1851

Independent Engineer Inspection on dated 15th March 2014 for Package I II & III,

1 IRB Letter No. PD/JTDRP/2014/1690 dated on 10.03.2014

IRB NHAI

9 15.03.2014 ARV/JTD/NH-12/13-14/1852

Review of 'Monthly progress Report - January 2014' Prepared by m/s. RITES Ltd.

1 RITES Letter no. RITES/HW/NHAI/SAFETY/PKG-16/NH-12/FV51/6866/2011/14086 dated 10.02.2014

NHAI IRB

10 15.03.2014 ARV/JTD/NH-12/13-14/1853

Review of RITES Asset Updation & Inspection Reports- Q10 - February 2014

1 Asset Updation & Inspection- Q10 February 2014 Submitted by M/s. RITES Ltd. (Safety Consultant) 2 RITES Letter no. RITES/HW/NHAI/SAFETY/PKG-16/NH-12/FV51/6866/2011/14095 dated 10.02.2014

NHAI IRB

11 15.03.2014 ARV/JTD/NH-12/13-14/1854

Review of Baseline data Report Construction on stage Hy5.

1 RITES Letter no. RITES/HW/NHAI/SAFETY/PKG-16/NH-12/FV51/6866/2011/14094 dated 10.02.2014

NHAI IRB

12 15.03.2014 ARV/JTD/NH-12/13-14/1855

Independent Engineer O & M Inspection Report for the Month of February' 2014.

NHAI IRB

13 18.03.2014 ARV/JTD/NH-

12/13-14/1855A Access to Sohela mirchi Mandi.

1 NHAI Letter no. 11012/05/132-Tonk/LA(PR)/10387 dated 12.03.2014 2 NHAI Letter no. 11012/06/13-Tonk/LA(PR)/5600 dated 07.02.2014 3 IE Letter no. 1009/ARV/JTD/NH-12/13-14/1842 dated 27.02.2014 4 IRB Letter no. 1679 dated 04.03.2014

IRB NHAI

Page 29: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 29 of 39

14 15.03.2014 ARV/JTD/NH-

12/13-14/1856A

Independent Engineer Monthly Progress Report for the Month of February'2014.

NHAI IRB

15 18.03.2014 ARV/JTD/NH-12/13-14/1856

Detail of Median Opening / closing of unauthorised median cut .

1 NHAI Letter no. 11028/05/12-tonk/IE/4704 dated 03.05.2013 2 IE Ltter no. ARV/JTD/NH-12/13-14/1519 dated 09.05.2013 3 NHAI Letter no. 11026/08/2013-Tonk/IE/10389 dated 12.03.2014

IRB NHAI

16 18.03.2014 ARV/JTD/NH-12/13-14/1857

Testing of Project Highway As Per Schedule-I of CA.

1 IE Letter no. AA/HW/NHAI/1009/13-14/816 dated 14.03.2014 2 IRB Letter no. PD/JTDRP/2014/1677 dated 28.022014

IRB NHAI

17 20.03.2014 ARV/JTD/NH-12/13-14/1858

Blance Work to complete before Testing of Project Highway As Per Schedule-I of CA.

1 IE Letter no. AA/HW/NHAI/1009/13-14/816 dated 14.03.2014 2 IRB Letter no. PD/JTDRP/2014/1677 dated 28.022014 3 IE Letter no. 1009/ARV/JTD/NH-12/13-14/1857 dated 18.03.2014

IRB NHAI

18 20.03.2014 ARV/JTD/NH-12/13-14/1859

Assembly Question 1137 Dt. 23.01.2014 by Hon'ble MLA Shri Rajender Gurjar

1 NHAI Email: dated 04.03.2014 2 IE Letter no. ARV/JTD/NH-12/13-14/1847 dated 04.03.2014

NHAI IRB

19 20.3.2014 ARV/JTD/NH-12/13-14/1860

Information required under RTI Act 2005 by Mr Manoj Kumar Viswakarma.

1 NHAI EMail: dated 19.03.2014 IRB NHAI

20 20.3.2014 ARV/JTD/NH-12/13-14/1861

Request for Bus Shelter in front of Factory Gate of National Bearing Corporation (NBC)

1 NHAI Mail dated19.03.2014 IRB NHAI

21 20.3.2014 ARV/JTD/NH-12/13-14/1862

Access permission to private properties at Ch. 15+744 at national Highway

1 NHAI . RO/Km 15+744/Tonk-2012/10138 dt19.02.2014

NHAI IRB

22 21.03.2014 ARV/JTD/NH-12/13-14/1863

Non Compliance Repor No. 73-GSB at Km. 55+980 to 56+500 (RHS)Service Road.

1 IE Letter no. ARV/JTD/NH-12/13-14/1543 dated 27.05.2013 2 IRB Letter no. PD/JTDRP/2013/NCR/1655 dated 31.01.2014

IRB NHAI

23 24.03.2014 ARV/JTD/NH-12/13-14/1864

Service Tax for the Month of July '2013 to August ' 2013.

NHAI

24 26.03.2014 ARV/JTD/NH-12/13-14/1865

Non Conformance Report NCR-98-Aligator cracks & bleeding at Km 33+700 to Km 34+000-LHS on BC Layer.

1 IE Letter no. ARV/JTD/NH-12/13-14/1685 dated 16.08.2013 2 IRB Letter no. PD/JTDRP/2014/NCR/1710 dated 24.01.2014

IRB NHAI

25 26.03.2014 ARV/JTD/NH-12/13-14/1866

Regarding information for total length of National Highway for which reinstalling of new Km stone and re-numbering have been completed

1 NHAI Mail dated 26th March 2 IRB Mail dated 26th March

NHAI IRB

26 26.03.2014 ARV/JTD/NH-12/13-14/1867

Non Conformance Report NCR-108 Slippage in BC Layer at Km. 35+100 RHS on BC Layer

1 IE Letter no. ARV/JTD/NH-12/13-14/1815 dated 23.01.2013 2 IRB Letter no. PD/JTDRP/2014/NCR/1711 dated 24.03.2014

IRB NHAI

27 27.03.2014 ARV/JTD/NH-12/13-14/1868

Non Conformance Report NCR-110 cracks and settlement in BC Layer at Km. 42+900 to Km. 43+350 LHS on BC Layer

1 IE Letter no. ARV/JTD/NH-12/13-14/1829 dated 08.02.2013 2 IRB Letter no. PD/JTDRP/2014/NCR/1713 dated 24.03.2014

IRB NHAI

Page 30: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 30 of 39

28 27.03.2014 ARV/JTD/NH-12/13-14/1869

Non Conformance Report NCR-109 cracks and settlement in BC Layer at Km. 47+800 to Km. 48+000 RHS on BC Layer

1 IE Letter no. ARV/JTD/NH-12/13-14/1815 dated 23.01.2014 2 IRB Letter no. PD/JTDRP/2014/NCR/1712 dated 25.03.2014

IRB NHAI

29 27.03.2014 ARV/JTD/NH-12/13-14/1870

Non compliance Report no. 88 Settlement of RE Wall.

1 IE Letter no. ARV/JTD/NH-12/12-13/1662 dated 01.08.2013 2 IRB Letter no. PD/JTDRP/2013/NCR/1549 dated 21.10.2013

IRB NHAI

30 27.03.2014 ARV/JTD/NH-12/13-14/1871

Non Compliance Report no. 89 Settlement of RE Wall.

1 IE Letter no. ARV/JTD/NH-12/12-13/1675 dated 14.08.2013 2 IRB Letter no. PD/JTDRP/2013/NCR/1549 dated 21.10.2013

IRB NHAI

31 27.03.2014 ARV/JTD/NH-12/13-14/1872

Test Result of Project Highway and Compliance of NCR.

1 IE Letter no. AA/HW/NHAI/1009/13-14/851 dated 25.03.2014 2 IE Letter no. ARV/JTD/NH-12/1009/13-14/1872 Dt: 27.03.2014 1858 Dt:20.03.2014 3 IRB Letter no. PD/JTDRP/2014/1714 dated 27.03.2014 4 IRB Letter no. PD/JTDRP/2014/1715 dated 27.03.2014 5 IE Letter no. ARV/JTDRP/NH-12/1009/13-14/1838 dated 17.02.2014

NHAI IRB

32 29.03.2014 ARV/JTD/NH-12/13-14/1873

Shifting of Electrical utilities in the area of Newai sections IV Running Bill.

1 NHAI Letter no. 11012/4/2008-Tonk/JVVNL/10433 dated19.03.2014

NHAI IRB

33 29.03.2014 ARV/JTD/NH-12/13-14/1874

Shifting of Electrical utilities in the area of Chaksu sections IV Running Bill.

1 NHAI Letter no. 11012/4/2008-Tonk/JVVNL/10434 dated19.03.2014

NHAI IRB

Page 31: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 31 of 39

6.2 DRAWING SECTION

Sr. Drawing No. Drawing Name Submitted to NHAI /

IE

Nil

Page 32: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 32 of 39

CHAPTER – 7 WHEATHER REPORT

Date

Section-I (km 18.77 to 63.00) Section-II (km 63.00 to

114.00)

Section-III (km 114.00 to

165.00)

Max

Temp.

Min

Temp.

Average

Rain Fall

Max

Temp.

Min

Temp.

Average

Rain Fall

Max

Temp.

Min

Temp.

Average

Rain Fall

oC

oC (mm)

oC

oC (mm)

oC

oC (mm)

1-May-14 39.80 32.60 -

..

2-May-14 40.00 32.20 -

..

3-May-14 40.10 31.80 -

..

4-May-14 39.70 33.60 -

..

5-May-14 40.90 33.80 -

..

6-May-14 41.20 34.00 -

..

7-May-14 41.00 34.20 -

..

8-May-14 40.90 34.40 -

..

9-May-14 41.50 34.30 -

..

10-May-14 41.30 34.00 -

..

11-May-14 41.60 34.20 -

..

12-May-14 40.90 33.60 -

..

13-May-14 41.20 33.10 -

..

14-May-14 40.70 32.90 -

..

15-May-14 41.00 32.50 -

..

16-May-14 41.20 32.80 -

..

17-May-14 41.50 33.00 -

..

18-May-14 41.30 33.60 -

..

19-May-14 41.50 33.40 -

..

20-May-14 40.90 33.10 -

..

21-May-14 41.70 34.10 -

..

22-May-14 42.00 33.70 -

..

23-May-14 42.20 34.20 -

..

24-May-14 41.90 34.00 -

..

25-May-14 41.50 33.60 -

..

26-May-14 42.40 32.90 -

..

27-May-14 42.00 31.70 -

..

28-May-14 41.70 30.90 -

..

29-May-14 40.90 29.90 - ..

30-May-14 - ..

31-May-14 -

Page 33: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 33 of 39

CHAPTER – 8

CONSTRAINTS

8.1.1 CONCESSIONAIRE

Concessionaire has obtained CRS clearance from Railway Authority for

construction of ROB at Ch. 7+537 and Ch. 55+293. Concessionaire has

to take blockage for launching of Girders at Ch. 7+537 & existing level

crossing at Ch. 55+293 from Railway Authority.

Concessionaire has to keep ROW free from encroachment.

Page 34: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 34 of 39

CHAPTER - 9

CONCLUSIONS

Four laning of Km 119.748 have been completed and Provisional Completion

Certificate issued on 27.09.2013 and Project Highway has been put on

Commercial use from midnight at 23:47 PM on 27th Sep 2013 for 119.748 Km.

Concessionaire have submitted request for extension of time for balance

work up to 26th Feb 2014 vide letter no. PD/JTDRP/2013/1413 dated

15.07.2013.

Page 35: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 35 of 39

CHAPTER – 10

STRIP PLAN

Page 36: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 36 of 39

Page 37: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 37 of 39

Page 38: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 38 of 39

CHAPTER – 11

PROJECT PHOTOGRAPHS

Section I : Toll

plaza Weigh

bridge approach

slab RHS Jaipur

side

Section I :

Pouring of Toll

plaza Weigh

bridge approach

slab RHS Jaipur

side

Page 39: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 39 of 39

Section I :

Construction of

TOE WALL at

16+400 LHS

Section I : DBM

Laying at 8+600

RHS

Page 40: MAY- 2014 MONTHLY PROGRESS REPORT NO. 35 ...nhai.org.in/spw/IEReport/IE MPR May 2014.pdfGunsi Monthly Progress Report – 35, May – 2014 Page 6 of 39 1.3 EXECUTIVE SUMMARY: The Highway

Monthly Progress Report – 35, May – 2014 Page 40 of 39

CHAPTER – 12

Monthly O&M Report – 42 for the month of Mar - 2014