matt report feb. 20, 2008 1 philip christensen (chair) lars borg (nd-sag co-chair) wendy calvin (mso...
TRANSCRIPT
MATT Report Feb. 20, 2008 1
Philip Christensen (Chair)Lars Borg (ND-SAG Co-Chair)Wendy Calvin (MSO SAG Chair)Mike Carr Dave Des Marais (ND-SAG Co-Chair)Francois Forget Noel Hinners Scott Murchie (MSS SAG Chair)Jack Mustard (MEPAG Chair)Lisa Pratt
Mars Architecture Tiger Team (MATT)
Chip Shearer (CAPTEM)Mike Smith (MSO SDT Chair)Steve SquyresRich ZurekDave Beaty Jan Chodas Richard MattinglyLisa May (NASA HQ)Michael Meyer (NASA HQ)
Membership
MATT Report Feb. 20, 2008 2
Background
• The OMB requested an architecture from NASA for the Mars Exploration Program for the next decade
• NASA chartered an assessment group to develop this architecture and provide an evaluation of the Mars Program relative to the SMD budget proposal submitted in the President’s 5-year budget plan
• Group consisted of 19 members of Mars science and engineering community, including the Chairs of MEPAG, the MEPAG Next Decade (ND), Mars Science Orbiter (MSO) and Mars Science Strategy (MSS) Science Analysis Groups, the MSO Science Definition Team, and CAPTEM
• Group met in Washington D.C. on Feb. 14-15, 2008
Mars Architecture Tiger Team Report
MATT Report Feb. 20, 2008 3
Key elements of this study included:
1. Assessment of the Mars Exploration Program architectures based on the President’s FY09 Budget release for 2009-2013 and SMD planning estimates for 2014-2020
2. Incorporation of the recommendations from the NRC Decadal Survey and the ND-SAG, MSS-SAG, and CAPTEM reports• Options for 2016 from MSS-SAG• Science priorities for collected samples from ND-SAG
3. The SMD stated desire for an MSR landed element no later than 2020 with a U.S. contribution to MSR of no more than $3.5B
4. Assessment of possible architectures relative to the stated science goals of the Mars Exploration Program
5. The assumption of significant international contribution
Mars Architecture Tiger Team Report
MATT Report Feb. 20, 2008 4
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
FY08 Dollars
Mars Architecture Tiger Team Report
Past funding
2020
MATT Report Feb. 20, 2008 5
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
FY08 Dollars
Mars Architecture Tiger Team Report
Past funding
5-year plan
2020
MATT Report Feb. 20, 2008 6
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
FY08 Dollars
Mars Architecture Tiger Team Report
Past funding
5-year plan
SMD Planning Budget
2020
MATT Report Feb. 20, 2008 7
Group looked at two types of architectures:
1) A science-driven architecture based on the SMD plan and the recommendations of the NRC Decadal Survey, the MEPAG Goals committees, and the MEPAG Science Analysis Groups over the past 5 years
2) Budget-driven architectures based on the recently released President’s 5-year budget (FY09-FY13). For the FY14-FY20 period the group considered 2 options:a) The current SMD Planning budget with a significant
funding increase in FY17 through FY20b) A flat funding profile that was based on the
average of FY10-FY12 for FY14 through FY20
Mars Architecture Tiger Team Report
MATT Report Feb. 20, 2008 8
Mars Architecture Tiger Team Report
2a
2b
Architecture Assessment Summary
Key points• Given adequate funding the SMD plan can maintain the Mars Program and
achieve its science goals• With the SMD Budget plan
• MSR options have only Scout mission between MSL and MSR• ≥11 year period between NASA Mars landings (2009 to ≥2020)• A 4 year gap exists between flight elements of MSR• Only 5 months of surface operations for MSR rover launched in 2022
Option 2009 2011 2013 2016 2018 2020 2022 Outcome
SMD Balanced
Program (1)MSL Scout MSO
MSR-L
MSR-O
Exceeds total funding;Improper cost phasing
SMD Budget Plan (2a)
MSL ScoutMSR-
OMSR-
LScout with MSR in
2022
SMD Budget Plan (2a);
Earliest MSRMSL
MSR-O
MSR-L
MSR-only programMSR in 2020
Level Mars funding FY14-
20 (2b)MSL Scout MSO Rover No MSR
CONCEPT
MATT Report Feb. 20, 2008 10
1. The Mars Architecture Tiger Team strongly endorses the Mars architecture as proposed by SMD that has a balanced scientific program and the launch of all MSR mission elements by 2020
2. However, the SMD planning budget, which includes the President’s 5-year decreasing budget, does not support this architecture even with the planned rapid increase in funding beginning in FY17 • Estimated cost of this balanced architecture is ~$6B,
including an estimated cost of an MSR mission with modest scientific goals of ~$4-5B; however total SMD funding for new missions through FY20 is ~$4B
• Phasing of SMD funding does not ramp up in time for a mission in 2016 nor for MSR launches in 2018 and 2020
3. The MSR mission would require a substantial international contribution above the $3.5B U.S. contribution currently planned
Conclusions
MATT Report Feb. 20, 2008 11
4. The SMD planning budget through FY20, together with substantial international contribution could support MSR with some adjustment in phasing. However, the options would be:• An MSR program with Scout in 2013 followed by the launch
of the MSR mission elements in 2018 and 2022; or• An architecture dedicated to the earliest launch of MSR, with
no missions following MSL and the launch of the MSR mission elements in 2016 and 2020
5. If the projected reinstatement of the funding for Mars exploration to levels of $500-900M per year does not occur sometime after 2013, then MSR will not happen• Projected funding levels in FY11-FY16 are ~$390M per year• Level funding could support medium-sized missions
launched every other opportunity (not flagships)
Conclusions
MATT Report Feb. 20, 2008 12
6. A Mars architecture consisting of MSL followed by the launch of MSR elements in 2016 & 2020 (no Scout) or 2018 & 2022 (with Scout) would have a devastating effect on the Mars Program• Lack of progress toward the four goals of planetary science
set out by the NRC Decadal Survey • Loss of scientific balance• Loss of technical and scientific expertise as a result of the >11
year hiatus between landed missions of MSL and MSR
Conclusions
MATT Report Feb. 20, 2008 13
7. In all planning exercises the Mars Program should remember that:
• Major technology development is required starting at least 5 years prior to the MSR development
• The existing assets at Mars have great capabilities that can be utilized to support future missions, including site characterization and certification, atmospheric characterization, and relay
Conclusions
Architecture Assessment Summary
Key points• Given adequate funding the SMD plan can maintain the Mars Program and
achieve its science goals• With the SMD Budget plan
• MSR options have only Scout mission between MSL and MSR• ≥11 year period between NASA Mars landings (2009 to ≥2020)• A 4 year gap exists between flight elements of MSR• Only 5 months of surface operations for MSR rover launched in 2022
Option 2009 2011 2013 2016 2018 2020 2022 Outcome
SMD Balanced
Program (1)MSL Scout MSO
MSR-L
MSR-O
Exceeds total funding;Improper cost phasing
SMD Budget Plan (2a)
MSL ScoutMSR-
OMSR-
LScout with MSR in
2022
SMD Budget Plan (2a);
Earliest MSRMSL
MSR-O
MSR-L
MSR-only programMSR in 2020
Level Mars funding FY14-
20 (2b)MSL Scout MSO Rover No MSR
MATT Report Feb. 20, 2008 15
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
FY08 Dollars
Mars Architecture Tiger Team Report
Past funding
5-year plan
SMD Planning Budget
2020
MATT Report Feb. 20, 2008 16
Backup
Mars Architecture Tiger Team Report
Option 2009 2011 2013 2016 2018 2020 2022 Outcome
SMD Balanced
Program (1)MSL Scout MSO
MSR-L
MSR-O
Exceeds total funding;Improper cost phasing
SMD Budget Plan (2a)
MSL ScoutMSR-
OMSR-
LScout with MSR in
2022
SMD Budget Plan (2a);
Earliest MSRMSL
MSR-O
MSR-L
MSR-only programMSR in 2020
Level Mars funding FY14-
20 (2b)MSL Scout MSO Rover No MSR
CONCEPT
MATT Report Feb. 20, 2008 18
Mars Architecture Tiger Team Report
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
FY08 Dollars
Real Year Dollars
MATT Report Feb. 20, 2008 19
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
Real Year Dollars
Mars Architecture Tiger Team Report
Past funding
MATT Report Feb. 20, 2008 20
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
Real Year Dollars
Mars Architecture Tiger Team Report
Past funding
5-year plan
MATT Report Feb. 20, 2008 21
Mars Exploration Funding
0
100
200
300
400
500
600
700
800
900
1000
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
Fu
nd
ing
Level
($M
)
Real Year Dollars
Mars Architecture Tiger Team Report
Proposed funding
Past funding