marymount university 26th street project€¦ · presentation outline project overview marymount...
TRANSCRIPT
Marymount University
26TH STREET PROJECT
BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT1FINAL PRESENTATION | APRIL 13, 2010
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Structural BreadthStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII. Questions
2
Project OverviewPresentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Project Overview
Location4763 Old Dominion DriveArlington, VA
OwnerMarymount UniversityCatholic University
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design Catholic University
3,600 Students.Project Goals
Expand Academic SpacesExpand Student HousingExpand Parking Capacity
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
3
Project OverviewPresentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Project Overview
Occupancy TypeResidential, Business, Storage/Garage & Assembly
Size267,000 Square Feet
Number of Stories(4) Below Grade Parking (3) Above Grade + Penthouse
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design (4) Below Grade Parking, (3) Above Grade + Penthouse
Construction DatesApril 2009 – September 2010
Building Cost$42 Million
Delivery MethodDesign‐Bid‐Build w/ CM Agent
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
4
Project OverviewPresentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Project Overview
Residential Facility62 Units Housing 239 Students77,000 Square Feet
Academic Facility52,000 Square FeetLaboratories Classrooms Offices
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design Laboratories, Classrooms, Offices
Below Grade Parking Garage138,000 Square Feet
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
5
Project TeamPresentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Project TeamPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Owner: Marymount UniversityOwner's Representative/CM: Stranix Associates
General Contractor: James G. Davis Construction Corp.Architect: Davis, Carter, Scott LTD.
Structural Engineer: Structura, Inc.MEP Engineer: GHT Limited
PROJECT TEAM
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
6
Civil Engineer: VIKALandscape Architect: Lewis Scully Gionet
LEED Consultant: Sustainable Design ConsultingCast‐In Place Concrete Subcontractor: Brothers Concrete Construction, Inc.
Pre‐Cast Concrete Subcontractor: Arban & CarosiMechanical/Plumbing Subcontractor: Tyler Mechanical Contracting, Inc.
Electrical Subcontractor: Power Design, Inc.
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Introduction to AnalysesPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Introduction to Analyses
Analysis I: Short Interval Production SchedulingAnalysis II: MEP Coordination TechniquesAnalysis III: Green Roof Design
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
7
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Analysis I: Short Interval Production SchedulingPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Analysis I: Short Interval Production Scheduling
Problem Statement:The repetitive nature of the activities involved with this phase of theproject provides an opportunity to attempt to bring the efficiencies ofthe “manufacturing process” to the construction industry.
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
8
Goal:This type of work will allow the workforce to maximize theirproductivity, without sacrificing quality. In turn, this will create aschedule that is more predictable, easier to track, and easier tocommunicate.
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Current Project SchedulePresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Current Project Schedule
February 2010 – September 201026Week Duration
Dependent upon the Building Dry MilestoneFebruary 19, 2010
Involves all Interior Finish Activities for the Residential Facilityy gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
9
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Current Project SchedulePresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Current Project Schedule
February 2010 – September 201026Week Duration
Dependent upon the Building Dry MilestoneFebruary 19, 2010
Involves all Interior Finish Activities for the Residential Facilityy gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
10
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Development of a SIP ScheduleLevel Zones OccupancyG3 5 26G2 7 36
Building Zones
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Development of a SIP Schedule
Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet
G2 7 36G1 7 36L1 9 42L2 12 53L3 12 53
Totals 52 246
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
11
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Development of a SIP Schedule Number Color Critical ActivityNumber Color Critical ActivityPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Development of a SIP Schedule
Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet
Determine the Sequence of the Critical Path
Number Color Critical Activity
1 Frame Metal Studs
2 Rough‐In MEP
3 Preform In Wall QC
4 Hang/Tape/Finish GWB
5 Prime Walls
6 Point‐Up Drywall
7 Paint Final Coat
Number Color Critical Activity
1 Frame Metal Studs
2 Rough‐In MEP
3 Preform In Wall QC
4 Hang/Tape/Finish GWB
5 Prime Walls
6 Point‐Up Drywall
7 Paint Final Coaty gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
12
8 Install Ceramic Tile
9 Install Plumbing Fixtures
10 Install Millwork & Countertops
11 Install VCT & Carpet
8 Install Ceramic Tile
9 Install Plumbing Fixtures
10 Install Millwork & Countertops
11 Install VCT & Carpet
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Development of a SIP Schedule Number Color Critical ActivityNumber Color Critical ActivityPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Development of a SIP Schedule
Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet
Determine the Sequence of the Critical PathLevel Resources to Ensure Consistent Durations
Number Color Critical Activity
1 Frame Metal Studs
2 Rough‐In MEP
3 Preform In Wall QC
4 Hang/Tape/Finish GWB
5 Prime Walls
6 Point‐Up Drywall
7 Paint Final Coat
Number Color Critical Activity
1 Frame Metal Studs
2 Rough‐In MEP
3 Preform In Wall QC
4 Hang/Tape/Finish GWB
5 Prime Walls
6 Point‐Up Drywall
7 Paint Final Coaty gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
13
8 Install Ceramic Tile
9 Install Plumbing Fixtures
10 Install Millwork & Countertops
11 Install VCT & Carpet
8 Install Ceramic Tile
9 Install Plumbing Fixtures
10 Install Millwork & Countertops
11 Install VCT & Carpet
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Development of a SIP SchedulePresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Development of a SIP Schedule
Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet
Determine the Critical Path of the ScheduleLevel Resources to Ensure Consistent DurationsCreate the SIPS Scheduley g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
14
Create the SIPS Schedule
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
SIP SchedulePresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
SIP Schedule
Typical Zone Duration17Working Days
February 2010 – August 201024Week Duration
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
15
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Conclusions & RecommendationsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Conclusions & Recommendations
Activity Shortened by 10 Working Days (8% Reduction)Reduces General Conditions CostsDelays or Stoppages will be Accounted For
Potential for Early Project CompletionAvoid Liquidated Damages
Schedule can be Utilized as Visual Tooly gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
16
Schedule can be Utilized as Visual ToolExtremely PredictableEasy to CommunicateEasy to Track
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Analysis II: MEP Coordination TechniquesPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Analysis II: MEP Coordination Techniques
Problem Statement:The coordination of the MEP Systems have the potential to beextremely problematic. The practice of 3D Coordination has provenitself to be an extremely effective and efficient alternative to 2DCoordination. However, it has yet to become an Industry StandardP ti
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
17
Practice.
Goal:Generate a survey that will help establish motives as to why thispractice is not being utilized more frequently within the Organization,and more specifically the Construction Industry
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Current MEP Coordination MethodPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Current MEP Coordination Method
Project Team Utilized “Traditional” Coordination2D Composite Drawings
Very Time ConsumingGenerating Composite DrawingsApproval ProcessCoordination Meetingsy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
18
Coordination MeetingsMultiple Parties InvolvedClashes are Inevitable
Generate Unnecessary Change OrdersCause Schedule Delays
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
3D MEP CoordinationPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
3D MEP Coordination
Computer Software the Combines 3D Modeling & Clash DetectionNumerous Initial and Long‐Term Benefits
Initial BenefitsEfficient Coordination of an Intricate SystemProvides a 3D Model that is Easily Visualizedy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
19
Provides a 3D Model that is Easily VisualizedIncreased Interaction Between trades
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
3D MEP CoordinationPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
3D MEP Coordination
Numerous Initial and Long‐Term Benefits
Long‐Tem Benefits3D Model can be Utilized for Digital FabricationEvaluating Model Promotes an Increased ProductivityDecreases the number of RFI’s and Change Ordersy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
20
Decreases the number of RFI s and Change OrdersOwner Provided with a Higher Quality ProductPhysical Model serves as a 3D “As‐Built”
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
MEP Coordination SurveyPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
MEP Coordination Survey
Distributed to Representative from James G. Davis ConstructionGenerated Ten ResponsesIncluded Project Engineers to Senior Vice Presidents
Completely Anonymous10 Total Questions
4 Questions Regarding 2D Coordination
Num. Current PositionYears of
Experience1 Senior Project Manager 122 Project Engineer 33 Project Manager 134 Virtual Construction Manager 25 Project Engineer 46 Project Executive 11
Survey Participants
Num. Current PositionYears of
Experience1 Senior Project Manager 122 Project Engineer 33 Project Manager 134 Virtual Construction Manager 25 Project Engineer 46 Project Executive 11
Survey Participants
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
21
4 Questions Regarding 2D Coordination6 Questions Regarding 3D Coordination
j7 Senior Vice President 328 Project Engineer 119 Project Executive 1210 Senior Vice President 19
j7 Senior Vice President 328 Project Engineer 119 Project Executive 1210 Senior Vice President 19
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
MEP Coordination Survey ResultsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
MEP Coordination Survey Results
Questions Regarding 2D MEP Coordination
What resources are typically involved with the MEP Coordination process?What is the typical turn‐around time for receiving “approved”
it d i ?y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
22
composite drawings?Is there money allocated in your budget for MEP Coordination?
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
MEP Coordination Survey ResultsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
MEP Coordination Survey Results
Questions Regarding 3D MEP Coordination
Are you aware if any trades are beginning to model equipment / components in 3D?What trade would be most likely to accept / reject the change to 3D MEP C di ti ?
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
23
MEP Coordination? What have been reasons for not pursing 3D MEP Coordination on projects that you have been involved with in the past?
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Organizational ImpactsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Organizational Impacts
80% of Employees feel that that they can successfully manage the 3D MEP Coordination processJames G. Davis is currently utilizing 3D Coordination on 3 projects
Committed to utilizing it on major projects in the futureTo ensure that the Projects are Successful, a new role within the Organization has been developedy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
24
Organization has been developed.
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Integrated Construction Engineer (ICE)Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Integrated Construction Engineer (ICE)
Educational program that provides employees with the adequate knowledge base to successfully manage 3D Coordination effortsCurrently, 11 ICEs within the Organization
Former Project EngineersFormer Asst. SuperintendantsFormer Layout Engineersy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
25
Former Layout EngineersMain Role: Guide project teams through this processRemain intact within Project Teams
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Conclusions & RecommendationsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Conclusions & Recommendations
Project Team Guidelines Seek assistance from an ICEStart the Coordination Process as soon as possibleIf possible, involve the Engineer / DesignerEstablish a clear order of CoordinationForeman should be involved during clash resolutiony g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
26
Foreman should be involved during clash resolution
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Analysis III: Green Roof DesignPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Analysis III: Green Roof Design
Problem Statement:Design a Green Roof that will increase the thermal efficiency of the building’s envelope, improve stormwater management, and increase the durability of the roofing membrane.
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
27
Goal:Increasing the thermal efficiency of the building’s envelope will help to reduce the overall loads on the HVAC System. The higher initial costs of a Green Roof are expected to be offset by the extended lifecycle and energy savings.
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Current Roofing SystemPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Current Roofing System
White, Fully Adhered, Thermoplastic Polyefin (TPO) MembraneCovers Entire Roofing Area
Residential Facility Roof Area ~ 11,500 Square FeetAcademic Facility Roof Area ~ 16,900 Square Feet
Membrane adhered to Extruded Polystyrene Insulationy gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
28
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Green Roof SelectionPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Green Roof Selection
Extensive V. Intensive Green RoofsExtensive
LightweightLow Maintenance CostsNo Irrigation Required
Intensivey gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
29
IntensiveBetter Insulating ValueBetter Stormwater ManagementGenerally Accessible
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Marymount University Green RoofPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Marymount University Green Roof
Sika Sarnafil Extensive Green Roof SystemLightweight System will have Minimal Impact on the PT Roof DeckIndigenous Vegetation Requires no IrrigationMaintenance Costs Comparable to Existing Roofing SystemSoil Cover Protects the Membrane from Ultra‐Violet LightPotential Reduction in Energy Costsy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
30
Potential Reduction in Energy CostsReduction in Stormwater Run‐Off
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Green Roof: Structural BreadthPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Green Roof: Structural Breadth
Original Design CriterionAcademic Facility
Slab Thickness = 9” Post‐Tensioned ConcreteLive Loads = 30 PSFf’c = 5,000 psiy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
31
Residential FacilitySlab Thickness = 7” Post‐Tensioned ConcreteLive Loads = 30 PSFf’c = 5,000 psi
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
New Design Criterion TOTAL DEAD LOAD ‐ Residential Facility Green RoofTOTAL DEAD LOAD ‐ Residential Facility Green RoofPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
New Design Criterion
Loads:Framing Dead Load = Self‐WeightSuperimposed Dead Load = 40 psf (Green Roof)Live Load = 30 psf (Section 1607.0, IBC)Snow Load = 20 psf
Concrete:
Mark Density Total (lbs.) Total (psf)Growth Media 85.00 327618.33 28.333Separation Layer 0.03 38.54 0.003Drainage Pannel 60.00 115630.00 10.000XPS Insulation 1.80 6937.80 0.600Waterproofing Membrane 0.14 1618.82 0.140
40
11563.00 1.0011563.00 0.17
TOTAL11563.00 1.0011563.00 0.33
TOTAL DEAD LOAD Residential Facility Green RoofArea (sf.) Area Comparison11563.00 0.33
Mark Density Total (lbs.) Total (psf)Growth Media 85.00 327618.33 28.333Separation Layer 0.03 38.54 0.003Drainage Pannel 60.00 115630.00 10.000XPS Insulation 1.80 6937.80 0.600Waterproofing Membrane 0.14 1618.82 0.140
40
11563.00 1.0011563.00 0.17
TOTAL11563.00 1.0011563.00 0.33
TOTAL DEAD LOAD Residential Facility Green RoofArea (sf.) Area Comparison11563.00 0.33
Mark Density Total (lbs ) Total (psf)Area (sf ) Area ComparisonTOTAL DEAD LOAD ‐ Academic Facility Green Roof
Mark Density Total (lbs ) Total (psf)Area (sf ) Area ComparisonTOTAL DEAD LOAD ‐ Academic Facility Green Roofy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
32
Concrete:f ’c = 5,000 psi
Rebar:fy =60,000 psi
PT:Un‐Bonded Tendons = ½”, 7‐Wire Strands
Mark Density Total (lbs.) Total (psf)Growth Media 85.00 478720.00 28.333Separation Layer 0.03 56.32 0.003Drainage Pannel 60.00 168960.00 10.000XPS Insulation 1.80 10036.22 0.594Waterproofing Membrane 0.14 2365.44 0.140
40TOTAL16896.00 1.00
16896.00 0.1716896.00 0.33
Area (sf.) Area Comparison16896.00 0.3316896.00 1.00
Mark Density Total (lbs.) Total (psf)Growth Media 85.00 478720.00 28.333Separation Layer 0.03 56.32 0.003Drainage Pannel 60.00 168960.00 10.000XPS Insulation 1.80 10036.22 0.594Waterproofing Membrane 0.14 2365.44 0.140
40TOTAL16896.00 1.00
16896.00 0.1716896.00 0.33
Area (sf.) Area Comparison16896.00 0.3316896.00 1.00
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Two-Way Post-Tension DesignPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Two-Way Post-Tension Design
Slab Design:Slab Thickness = 8”Bottom Bars = #5 @ 10 in. O.C.Top Bars = 6 ‐ #5 @ Int. Supports
= 6 ‐ #5 @ Ext. SupportsPT Tendons 22 Un bonded Tendonsy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
33
PT Tendons = 22, Un‐bonded TendonsSupporting Columns: OKResidential Columns Extended
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Green Roof: Mechanical BreadthPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Green Roof: Mechanical Breadth
Annual Energy SavingsQ = Area (ft2) * (Cumulative Ann Savings) * (Hr/Day) * (Day/Yr)Q = (28,450 ft2 ) * (1.9 BTU/HR*ft2) * (24 Hr/D) * (365 D/Yr)Q = 473,521,800 BTU/Year
Annual Energy Savings $2 705y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
34
Annual Energy Savings = $2,705
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
LEED NCv2 2 AnalysisPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
LEED NCv2.2 Analysis
Green Roof Direct ImpactsSustainable Sites
Credit 5.1: Site DevelopmentCredit 6.1: Stormwater Design
Water EfficiencyCredit 2 0: Innovation Wastewater Technologiesy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
35
Credit 2.0: Innovation Wastewater TechnologiesInnovation & Design Process
Credit 1.4: Green Roof DesignProject Score = 33
LEED Silver
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Cost ImpactsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Cost Impacts
Green Roof Cost Impacts
TPO Membrane Extensive Green RoofCost $11.00/SF $20.00/SF
Roofing System Cost ComparisonTPO Membrane Extensive Green Roof
Cost $11.00/SF $20.00/SF
Roofing System Cost Comparison
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
36
Lifecycle 15 Years 40 YearsInitial Cost $312,950.00 $709,000Energy Savings ‐ $2,705
Lifecycle 15 Years 40 YearsInitial Cost $312,950.00 $709,000Energy Savings ‐ $2,705
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Schedule ImpactsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Schedule Impacts
Existing Fully Adhered, White, TPO Roofing Membrane62 Days
Sika Sarnafil Extensive Green Roof69 Days
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
37
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
M A E RequirementPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
M.A.E. Requirement
Incorporation of a Green Roof System
AE 597D: Sustainable Building ConstructionLEED Analysis
AE 542: Building Enclosure Science and Designy gStructural BreadthMechanical Breadth
VI. Final ConclusionsVII. AcknowledgementsVIII.Questions
38
AE 542: Building Enclosure Science and DesignEvaluation of the Building Envelope
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Conclusions & RecommendationsPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Conclusions & Recommendations
Financial ImpactsIncreased Thermal Efficiency Generates $2,705 AnnuallyHigher Initial Costs offset by Lifecycle Costs30 Year Return on Initial Investment
Sustainable Impactsy gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
39
Sustainable ImpactsReduces Overall Load on the Mechanical EquipmentExtended LifespanLEED Silver Status
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Lessons LearnedPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Lessons Learned
Analysis I: Short Interval Production SchedulingA repetitive schedule is an efficient scheduleReduces the total duration and generates savings
Analysis II: MEP Coordination TechniquesEmployees need to be educated on new technologiesy g
Structural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
40
Employees need to be educated on new technologiesVery time & resource extensive process
Analysis III: Green Roof DesignHigher initial cost can be offset by durabilityDifferent systems have varying levels of sustainability
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Special ThanksPresentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
Special Thanks
Penn State FacultyMr. James FaustDr. Chris MagentDr. David RileyMr. Craig Dubler
Marymount UniversityDr. Ralph KidderMr. Upen MalaniDr. James Bundschuh
St i A i ty gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
41
Davis ConstructionErik KanieckiRami NatourAaron Galvin
Stranix AssociatesMs. Bhavna Mistry Lee
OthersMaddieMy Family & Friends
Presentation Outline
Marymount University
26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010
Presentation Outline
I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design
QUESTIONS?
y gStructural BreadthMechanical Breadth
VI. Lessons LearnedVII. AcknowledgementsVIII.Questions
42