marymount university 26th street project€¦ · presentation outline project overview marymount...

42
Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT 1 FINAL PRESENTATION | APRIL 13, 2010

Upload: others

Post on 14-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Marymount University

26TH STREET PROJECT

BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT1FINAL PRESENTATION | APRIL 13, 2010

Page 2: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Structural BreadthStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII. Questions

2

Page 3: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Project OverviewPresentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Project Overview

Location4763 Old Dominion DriveArlington, VA

OwnerMarymount UniversityCatholic University

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design Catholic University

3,600 Students.Project Goals

Expand Academic SpacesExpand Student HousingExpand Parking Capacity

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

3

Page 4: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Project OverviewPresentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Project Overview

Occupancy TypeResidential, Business, Storage/Garage & Assembly

Size267,000 Square Feet

Number of Stories(4) Below Grade Parking (3) Above Grade + Penthouse

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design (4) Below Grade Parking, (3) Above Grade + Penthouse

Construction DatesApril 2009 – September 2010

Building Cost$42 Million

Delivery MethodDesign‐Bid‐Build w/ CM Agent

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

4

Page 5: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Project OverviewPresentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Project Overview

Residential Facility62 Units Housing 239 Students77,000 Square Feet

Academic Facility52,000 Square FeetLaboratories Classrooms Offices

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design Laboratories, Classrooms, Offices

Below Grade Parking Garage138,000 Square Feet

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

5

Page 6: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Project TeamPresentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Project TeamPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Owner: Marymount UniversityOwner's Representative/CM: Stranix Associates

General Contractor: James G. Davis Construction Corp.Architect: Davis, Carter, Scott LTD.

Structural Engineer: Structura, Inc.MEP Engineer: GHT Limited

PROJECT TEAM

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

6

Civil Engineer: VIKALandscape Architect: Lewis Scully Gionet

LEED Consultant: Sustainable Design ConsultingCast‐In Place Concrete Subcontractor: Brothers Concrete Construction, Inc.

Pre‐Cast Concrete Subcontractor: Arban & CarosiMechanical/Plumbing Subcontractor: Tyler Mechanical Contracting, Inc. 

Electrical Subcontractor: Power Design, Inc. 

Page 7: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Introduction to AnalysesPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Introduction to Analyses

Analysis I: Short Interval Production SchedulingAnalysis II: MEP Coordination TechniquesAnalysis III: Green Roof Design

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

7

Page 8: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Analysis I: Short Interval Production SchedulingPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Analysis I: Short Interval Production Scheduling

Problem Statement:The repetitive nature of the activities involved with this phase of theproject provides an opportunity to attempt to bring the efficiencies ofthe “manufacturing process” to the construction industry.

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

8

Goal:This type of work will allow the workforce to maximize theirproductivity, without sacrificing quality. In turn, this will create aschedule that is more predictable, easier to track, and easier tocommunicate.

Page 9: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Current Project SchedulePresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Current Project Schedule

February 2010 – September 201026Week Duration

Dependent upon the Building Dry MilestoneFebruary 19, 2010

Involves all Interior Finish Activities for the Residential Facilityy gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

9

Page 10: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Current Project SchedulePresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Current Project Schedule

February 2010 – September 201026Week Duration

Dependent upon the Building Dry MilestoneFebruary 19, 2010

Involves all Interior Finish Activities for the Residential Facilityy gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

10

Page 11: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Development of a SIP ScheduleLevel Zones OccupancyG3 5 26G2 7 36

Building Zones

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Development of a SIP Schedule

Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet

G2 7 36G1 7 36L1 9 42L2 12 53L3 12 53

Totals 52 246

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

11

Page 12: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Development of a SIP Schedule Number Color Critical ActivityNumber Color Critical ActivityPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Development of a SIP Schedule

Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet

Determine the Sequence of the Critical Path

Number Color Critical Activity

1 Frame Metal Studs

2 Rough‐In MEP

3 Preform In Wall QC

4 Hang/Tape/Finish GWB

5 Prime Walls

6 Point‐Up Drywall

7 Paint Final Coat

Number Color Critical Activity

1 Frame Metal Studs

2 Rough‐In MEP

3 Preform In Wall QC

4 Hang/Tape/Finish GWB

5 Prime Walls

6 Point‐Up Drywall

7 Paint Final Coaty gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

12

8 Install Ceramic Tile

9 Install Plumbing Fixtures

10 Install Millwork & Countertops

11 Install VCT & Carpet

8 Install Ceramic Tile

9 Install Plumbing Fixtures

10 Install Millwork & Countertops

11 Install VCT & Carpet

Page 13: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Development of a SIP Schedule Number Color Critical ActivityNumber Color Critical ActivityPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Development of a SIP Schedule

Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet

Determine the Sequence of the Critical PathLevel Resources to Ensure Consistent Durations

Number Color Critical Activity

1 Frame Metal Studs

2 Rough‐In MEP

3 Preform In Wall QC

4 Hang/Tape/Finish GWB

5 Prime Walls

6 Point‐Up Drywall

7 Paint Final Coat

Number Color Critical Activity

1 Frame Metal Studs

2 Rough‐In MEP

3 Preform In Wall QC

4 Hang/Tape/Finish GWB

5 Prime Walls

6 Point‐Up Drywall

7 Paint Final Coaty gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

13

8 Install Ceramic Tile

9 Install Plumbing Fixtures

10 Install Millwork & Countertops

11 Install VCT & Carpet

8 Install Ceramic Tile

9 Install Plumbing Fixtures

10 Install Millwork & Countertops

11 Install VCT & Carpet

Page 14: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Development of a SIP SchedulePresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Development of a SIP Schedule

Break the Building down into Zones/Sections52 Zones, In Total1 Zone ~ 900 Square Feet

Determine the Critical Path of the ScheduleLevel Resources to Ensure Consistent DurationsCreate the SIPS Scheduley g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

14

Create the SIPS Schedule

Page 15: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

SIP SchedulePresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

SIP Schedule

Typical Zone Duration17Working Days

February 2010 – August 201024Week Duration

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

15

Page 16: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Conclusions & RecommendationsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Conclusions & Recommendations

Activity Shortened by 10 Working Days (8% Reduction)Reduces General Conditions CostsDelays or Stoppages will be Accounted For

Potential for Early Project CompletionAvoid Liquidated Damages

Schedule can be Utilized as Visual Tooly gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

16

Schedule can be Utilized as Visual ToolExtremely PredictableEasy to CommunicateEasy to Track

Page 17: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Analysis II: MEP Coordination TechniquesPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Analysis II: MEP Coordination Techniques

Problem Statement:The coordination of the MEP Systems have the potential to beextremely problematic. The practice of 3D Coordination has provenitself to be an extremely effective and efficient alternative to 2DCoordination. However, it has yet to become an Industry StandardP ti

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

17

Practice.

Goal:Generate a survey that will help establish motives as to why thispractice is not being utilized more frequently within the Organization,and more specifically the Construction Industry

Page 18: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Current MEP Coordination MethodPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Current MEP Coordination Method

Project Team Utilized “Traditional” Coordination2D Composite Drawings

Very Time ConsumingGenerating Composite DrawingsApproval ProcessCoordination Meetingsy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

18

Coordination MeetingsMultiple Parties InvolvedClashes are Inevitable

Generate Unnecessary Change OrdersCause Schedule Delays

Page 19: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

3D MEP CoordinationPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

3D MEP Coordination

Computer Software the Combines 3D Modeling & Clash DetectionNumerous Initial and Long‐Term Benefits

Initial BenefitsEfficient Coordination of an Intricate SystemProvides a 3D Model that is Easily Visualizedy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

19

Provides a 3D Model that is Easily VisualizedIncreased Interaction Between trades

Page 20: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

3D MEP CoordinationPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

3D MEP Coordination

Numerous Initial and Long‐Term Benefits

Long‐Tem Benefits3D Model can be Utilized for Digital FabricationEvaluating Model Promotes an Increased ProductivityDecreases the number of RFI’s and Change Ordersy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

20

Decreases the number of RFI s and Change OrdersOwner Provided with a Higher Quality ProductPhysical Model serves as a 3D “As‐Built”

Page 21: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

MEP Coordination SurveyPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

MEP Coordination Survey

Distributed to Representative from James G. Davis ConstructionGenerated Ten ResponsesIncluded Project Engineers to Senior Vice Presidents

Completely Anonymous10 Total Questions

4 Questions Regarding 2D Coordination

Num. Current PositionYears of 

Experience1 Senior Project Manager 122 Project Engineer 33 Project Manager 134 Virtual Construction Manager 25 Project Engineer 46 Project Executive 11

Survey Participants

Num. Current PositionYears of 

Experience1 Senior Project Manager 122 Project Engineer 33 Project Manager 134 Virtual Construction Manager 25 Project Engineer 46 Project Executive 11

Survey Participants

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

21

4 Questions Regarding 2D Coordination6 Questions Regarding 3D Coordination

j7 Senior Vice President 328 Project Engineer 119 Project Executive 1210 Senior Vice President 19

j7 Senior Vice President 328 Project Engineer 119 Project Executive 1210 Senior Vice President 19

Page 22: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

MEP Coordination Survey ResultsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

MEP Coordination Survey Results

Questions Regarding 2D MEP Coordination

What resources are typically involved with the MEP Coordination process?What is the typical turn‐around time for receiving “approved” 

it d i ?y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

22

composite drawings?Is there money allocated in your budget for MEP Coordination?

Page 23: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

MEP Coordination Survey ResultsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

MEP Coordination Survey Results

Questions Regarding 3D MEP Coordination

Are you aware if any trades are beginning to model equipment / components in 3D?What trade would be most likely to accept / reject the change to 3D MEP C di ti ?

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

23

MEP Coordination? What have been reasons for not pursing 3D MEP Coordination on projects that you have been involved with in the past?

Page 24: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Organizational ImpactsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Organizational Impacts

80% of Employees feel that that they can successfully manage the 3D MEP Coordination processJames G. Davis is currently utilizing 3D Coordination on 3 projects

Committed to utilizing it on major projects in the futureTo ensure that the Projects are Successful, a new role within the Organization has been developedy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

24

Organization has been developed.

Page 25: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Integrated Construction Engineer (ICE)Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Integrated Construction Engineer (ICE)

Educational program that provides employees with the adequate knowledge base to successfully manage 3D Coordination effortsCurrently, 11 ICEs within the Organization

Former Project EngineersFormer Asst. SuperintendantsFormer Layout Engineersy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

25

Former Layout EngineersMain Role: Guide project teams through this processRemain intact within Project Teams

Page 26: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Conclusions & RecommendationsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Conclusions & Recommendations

Project Team Guidelines Seek assistance from an ICEStart the Coordination Process as soon as possibleIf possible, involve the Engineer / DesignerEstablish a clear order of CoordinationForeman should be involved during clash resolutiony g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

26

Foreman should be involved during clash resolution

Page 27: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Analysis III: Green Roof DesignPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Analysis III: Green Roof Design

Problem Statement:Design a Green Roof that will increase the thermal efficiency of the building’s envelope, improve stormwater management, and increase the durability of the roofing membrane. 

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

27

Goal:Increasing the thermal efficiency of the building’s envelope will help to reduce the overall loads on the HVAC System.  The higher initial costs of a Green Roof are expected to be offset by the extended lifecycle  and energy savings. 

Page 28: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Current Roofing SystemPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Current Roofing System

White, Fully Adhered, Thermoplastic Polyefin (TPO) MembraneCovers Entire Roofing Area

Residential Facility Roof Area ~ 11,500 Square FeetAcademic Facility Roof Area ~ 16,900 Square Feet

Membrane adhered to Extruded Polystyrene Insulationy gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

28

Page 29: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Green Roof SelectionPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Green Roof Selection

Extensive V. Intensive Green RoofsExtensive 

LightweightLow Maintenance CostsNo Irrigation Required

Intensivey gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

29

IntensiveBetter Insulating ValueBetter Stormwater ManagementGenerally Accessible

Page 30: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Marymount University Green RoofPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Marymount University Green Roof

Sika Sarnafil Extensive Green Roof SystemLightweight System will have Minimal Impact on the PT Roof DeckIndigenous Vegetation Requires no IrrigationMaintenance Costs Comparable to Existing Roofing SystemSoil Cover Protects the Membrane from Ultra‐Violet LightPotential Reduction in Energy Costsy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

30

Potential Reduction in Energy CostsReduction in Stormwater Run‐Off

Page 31: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Green Roof: Structural BreadthPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Green Roof: Structural Breadth

Original Design CriterionAcademic Facility

Slab Thickness = 9” Post‐Tensioned ConcreteLive Loads = 30 PSFf’c = 5,000 psiy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

31

Residential FacilitySlab Thickness = 7” Post‐Tensioned ConcreteLive Loads = 30 PSFf’c = 5,000 psi

Page 32: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

New Design Criterion TOTAL DEAD LOAD ‐ Residential Facility Green RoofTOTAL DEAD LOAD ‐ Residential Facility Green RoofPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

New Design Criterion

Loads:Framing Dead Load = Self‐WeightSuperimposed Dead Load = 40 psf (Green Roof)Live Load = 30 psf (Section 1607.0, IBC)Snow Load = 20 psf

Concrete:

Mark Density Total (lbs.) Total (psf)Growth Media 85.00 327618.33 28.333Separation Layer 0.03 38.54 0.003Drainage Pannel 60.00 115630.00 10.000XPS Insulation 1.80 6937.80 0.600Waterproofing Membrane 0.14 1618.82 0.140

40

11563.00 1.0011563.00 0.17

TOTAL11563.00 1.0011563.00 0.33

TOTAL DEAD LOAD   Residential Facility Green RoofArea (sf.) Area Comparison11563.00 0.33

Mark Density Total (lbs.) Total (psf)Growth Media 85.00 327618.33 28.333Separation Layer 0.03 38.54 0.003Drainage Pannel 60.00 115630.00 10.000XPS Insulation 1.80 6937.80 0.600Waterproofing Membrane 0.14 1618.82 0.140

40

11563.00 1.0011563.00 0.17

TOTAL11563.00 1.0011563.00 0.33

TOTAL DEAD LOAD   Residential Facility Green RoofArea (sf.) Area Comparison11563.00 0.33

Mark Density Total (lbs ) Total (psf)Area (sf ) Area ComparisonTOTAL DEAD LOAD ‐ Academic Facility Green Roof

Mark Density Total (lbs ) Total (psf)Area (sf ) Area ComparisonTOTAL DEAD LOAD ‐ Academic Facility Green Roofy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

32

Concrete:f ’c = 5,000 psi

Rebar:fy =60,000 psi

PT:Un‐Bonded Tendons = ½”, 7‐Wire Strands

Mark Density Total (lbs.) Total (psf)Growth Media 85.00 478720.00 28.333Separation Layer 0.03 56.32 0.003Drainage Pannel 60.00 168960.00 10.000XPS Insulation 1.80 10036.22 0.594Waterproofing Membrane 0.14 2365.44 0.140

40TOTAL16896.00 1.00

16896.00 0.1716896.00 0.33

Area (sf.) Area Comparison16896.00 0.3316896.00 1.00

Mark Density Total (lbs.) Total (psf)Growth Media 85.00 478720.00 28.333Separation Layer 0.03 56.32 0.003Drainage Pannel 60.00 168960.00 10.000XPS Insulation 1.80 10036.22 0.594Waterproofing Membrane 0.14 2365.44 0.140

40TOTAL16896.00 1.00

16896.00 0.1716896.00 0.33

Area (sf.) Area Comparison16896.00 0.3316896.00 1.00

Page 33: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Two-Way Post-Tension DesignPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Two-Way Post-Tension Design

Slab Design:Slab Thickness = 8”Bottom Bars = #5 @ 10 in. O.C.Top Bars = 6 ‐ #5 @ Int. Supports

= 6 ‐ #5 @ Ext. SupportsPT Tendons 22 Un bonded Tendonsy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

33

PT Tendons = 22, Un‐bonded TendonsSupporting Columns: OKResidential Columns Extended

Page 34: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Green Roof: Mechanical BreadthPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Green Roof: Mechanical Breadth

Annual Energy SavingsQ = Area (ft2) * (Cumulative Ann Savings) * (Hr/Day) * (Day/Yr)Q = (28,450 ft2 ) * (1.9 BTU/HR*ft2) * (24 Hr/D) * (365 D/Yr)Q = 473,521,800 BTU/Year

Annual Energy Savings $2 705y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

34

Annual Energy Savings = $2,705

Page 35: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

LEED NCv2 2 AnalysisPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

LEED NCv2.2 Analysis

Green Roof Direct ImpactsSustainable Sites

Credit 5.1: Site DevelopmentCredit 6.1: Stormwater Design

Water EfficiencyCredit 2 0: Innovation Wastewater Technologiesy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

35

Credit 2.0: Innovation Wastewater TechnologiesInnovation & Design Process

Credit 1.4: Green Roof DesignProject Score = 33

LEED Silver

Page 36: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Cost ImpactsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Cost Impacts

Green Roof Cost Impacts

TPO Membrane Extensive Green RoofCost $11.00/SF $20.00/SF

Roofing System Cost ComparisonTPO Membrane Extensive Green Roof

Cost $11.00/SF $20.00/SF

Roofing System Cost Comparison

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

36

Lifecycle 15 Years 40 YearsInitial Cost $312,950.00 $709,000Energy Savings ‐ $2,705

Lifecycle 15 Years 40 YearsInitial Cost $312,950.00 $709,000Energy Savings ‐ $2,705

Page 37: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Schedule ImpactsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Schedule Impacts

Existing Fully Adhered, White, TPO Roofing Membrane62 Days

Sika Sarnafil Extensive Green Roof69 Days

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

37

Page 38: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

M A E RequirementPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

M.A.E. Requirement

Incorporation of a Green Roof System

AE 597D: Sustainable Building ConstructionLEED Analysis

AE 542: Building Enclosure Science and Designy gStructural BreadthMechanical Breadth

VI. Final ConclusionsVII. AcknowledgementsVIII.Questions

38

AE 542: Building Enclosure Science and DesignEvaluation of the Building Envelope

Page 39: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Conclusions & RecommendationsPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Conclusions & Recommendations

Financial ImpactsIncreased Thermal Efficiency Generates $2,705 AnnuallyHigher Initial Costs offset by Lifecycle Costs30 Year Return on Initial Investment

Sustainable Impactsy gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

39

Sustainable ImpactsReduces Overall Load on the Mechanical EquipmentExtended LifespanLEED Silver Status

Page 40: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Lessons LearnedPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Lessons Learned

Analysis I: Short Interval Production SchedulingA repetitive schedule is an efficient scheduleReduces the total duration and generates savings

Analysis II: MEP Coordination TechniquesEmployees need to be educated on new technologiesy g

Structural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

40

Employees need to be educated on new technologiesVery time & resource extensive process

Analysis III: Green Roof DesignHigher initial cost can be offset by durabilityDifferent systems have varying levels of sustainability

Page 41: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Special ThanksPresentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

Special Thanks

Penn State FacultyMr. James FaustDr. Chris MagentDr. David RileyMr. Craig Dubler

Marymount UniversityDr. Ralph KidderMr. Upen MalaniDr. James Bundschuh

St i A i ty gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

41

Davis ConstructionErik KanieckiRami NatourAaron Galvin

Stranix AssociatesMs. Bhavna Mistry Lee

OthersMaddieMy Family & Friends

Page 42: Marymount University 26TH STREET PROJECT€¦ · Presentation Outline Project Overview Marymount University | CONSTRUCTION MANAGEMENT 26TH STREETBENJAMIN J. MAHONEY PROJECT FINAL

Presentation Outline

Marymount University

26TH STREET PROJECTBENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010

Presentation Outline

I. Project OverviewII. Introduction to AnalysesIII. Analysis I: Short Interval Production SchedulingIV. Analysis II: MEP CoordinationV. Analysis III: Green Roof Design

QUESTIONS?

y gStructural BreadthMechanical Breadth

VI. Lessons LearnedVII. AcknowledgementsVIII.Questions

42