marine and offshore power system
TRANSCRIPT
TET4200 MARINE AND OFFSHORE POWER SYSTEM
PROJECT WORK SPRING 2012
Mamta Maharjan, Linda Rekosuo
ii
iii
SUMMARY In this project an electrical power system for a though offshore platform is studied. Short
circuit analysis are done for single-phase, two-phase and three-phase to ground faults.
Especially fault currents are under examination. Also power flow and transient analysis are
done and critical clearing times for induction machines are solved. Motor starting analysis are
done in two different ways. First start-up is analyzed when motor is connected to system.
Later start-up is examined when motor is connected to long subsea cable and star-up is
controlled by converter.
iv
Table of content
1. Introduction ......................................................................................................................... 1
1.1. System description ....................................................................................................... 1
2. SIMPOW Simulations ........................................................................................................ 2
1.1. Power flow ................................................................................................................... 2
1.2. Characteristics for induction machines ........................................................................ 3
1.3. Short-circuit analysis ................................................................................................... 4
1.1.1. Single phase to ground fault ................................................................................. 4
1.1.2. Two-phase fault .................................................................................................... 5
1.1.3. Three phase fault .................................................................................................. 5
1.4. Motor starting analysis ................................................................................................ 9
1.5. Transient analysis ...................................................................................................... 10
1.1.4. Contingency analysis .......................................................................................... 10
1.1.5. Critical clearing time .......................................................................................... 11
3. ATPDraw simulations ....................................................................................................... 12
4. Conclusions ....................................................................................................................... 14
1
1. Introduction
In this project an electrical power system for a though offshore platform is studied. Four
analyses are done: power flow, short-circuits, motor starting and contingencies. Also start-up
of induction motor from frequency converter via long subsea cable is examined more detail.
First four analyses are done by using SIMPOW. Start-up with converter is analyzed with
ATPDraw.
1.1. System description Single-line-diagram for system is shown in Figure 1. It consists of three turbine/generator
sets, eight motors, three passive loads and three transformers. The number of generators
running in each simulation is varied. Voltage levels are 13.8 kV, 6.0 kV and 0.44 kV.
Generators are two pole synchronous machines with brushless excitation system (type
IEEEX2). Turbines are twin-shaft aero-derivative gas turbine engines. The speed is controlled
with regulator. Motors are induction machines with squirrel-cage designed rotor.
All transformers have two windings and isolated neutral. Passive loads act as constant
impedances and they consist of active and reactive part. Cables are three-phase types and they
are modeled with resistance, inductance and susceptance. Detailed data for each component
can be seen in Appendix 1.
2
2. SIMPOW Simulations
1.1. Power flow Power flow analyses are done in two different situations. In Figure 1 can be seen power flow
results when two of the three generators are working. Generator G3 is not connected to
system.
Figure 1 Single-line-diagram and power flow results for system with two generator sets
working.
00
0
0
0 0
BUS1
U = 1 p.u.
FI = -3.02274E-022
degrees
P = -4.16264 MW
Q = -2.4933 Mvar
P = -4.16032 MW
Q = -2.49386 Mvar
P = 15.3636 MW
Q = 9.08899 MvarP = 15.36 MW
Q = 9.1 Mvar
P = 0 MW
Q = -0 Mvar
P = -4 MW
Q = -1.9373 Mvar
P = -4.86918 MW
Q = -3.21012 Mvar
P = -1.04447
MW
Q = -0.562251
Mvar
M1
P = -6.237 MW
Q = -3.74218 Mvar
M2
P = -6.25 MW
Q = -3.74998 Mvar
BUSG3
U = 1 p.u.
FI = -3.02274E-022
degrees
P = 0 MW
Q = -0 Mvar
G3
P = 0 MW
Q = -0 Mvar
BUSG1
U = 1 p.u.
FI = 0 degrees
P = -15.3636 MW
Q = -9.08899 Mvar
G1
P = 15.3636 MW
Q = 9.08899 Mvar
BUS2
U = 0.998661 p.u.
FI = -0.0214586
degrees
P = 4.158 MW
Q = 2.49442 Mvar
M3
P = -4.158 MW
Q = -2.49442 Mvar
BUSG2
U = 1 p.u.
FI = -3.02274E-022
degrees
P = -15.36 MW
Q = -9.1 Mvar
G2
P = 15.36 MW
Q = 9.1 Mvar
BUS7
U = 1 p.u.
FI = -3.02274E-022
degrees
P = 4 MW
Q = 1.9373 Mvar
0
P = -4 MW
Q = -1.9373 Mvar
BUS3
U = 0.968803 p.u.
FI = -2.76627
degrees
P = 1.037
MW
Q = 0.49524
Mvar
0
M4
P = -1.037 MW
Q = -0.49524 Mvar
BUS4
U = 0.94939 p.u.
FI = -4.19837
degrees
P = 4.83346 MW
Q = 2.70104 Mvar
0
P = -0.95078 MW
Q = -0.579376 Mvar
0
P = -1.80268 MW
Q = -0.87304 Mvar
M5
P = -1.04 MW
Q = -0.624314 Mvar
M6
P = -1.04 MW
Q = -0.624314 Mvar
BUS5
U = 0.923247 p.u.
FI = -6.36011
degrees
P = 0.945192 MW
Q = 0.528144 Mvar
0
0
P = -0.426192 MW
Q = -0.206448 Mvar
M7
P = -0.519 MW
Q = -0.321697 Mvar
BUS6
U = 0.999331 p.u.
FI = -0.0107136
degrees
P = 4.158 MW
Q = 2.49443 Mvar
M8
P = -4.158 MW
Q = -2.49443 Mvar
3
Table 1 shows power flow when all the three generators are running. Single-line diagram for
this situation is in Appendix 2. In both cases voltage levels on several buses are lower than
they should be. Generators can be a little overloaded and they cannot keep voltage levels high
enough.
Table 1 Power system results when all three generators are working
1.2. Characteristics for induction machines Torque-speed and current-speed characteristics for induction motors are shown in Figure 2. It
can be seen that torque is maximum when speed reaches its nominal value.
Figure 2 Torque-speed and torque-current charasteristics for induction motor
30
0
0.000 0.100 0.200 0.300 0.400 0.500 0.600 0.700 0.800 0.900
ASYNC M1 SPEED p.u.
0.0
2.0
4.0
6.0
8.0
10.0
TET 4200 "Marine and Offshore power systems". Spring 2012.
DATE 15 MAR 2012 TIME 13:49:18 JOB mini_project_2012_Part4 Simpow 11.0.008 Diagram:3STRI Software
ASYNC M1 ME TORQUE MNm/ W0
30
0
0.000 0.100 0.200 0.300 0.400 0.500 0.600 0.700 0.800 0.900
ASYNC M1 SPEED p.u.
0.00
0.20
0.40
0.60
0.80
1.00
TET 4200 "Marine and Offshore power systems". Spring 2012.
DATE 15 MAR 2012 TIME 13:49:18 JOB mini_project_2012_Part4 Simpow 11.0.008 Diagram:4STRI Software
ASYNC M1 I POS. kA
4
Current stays 1.2 kA first and starts to decrease when speed is reaching a nominal value.
1.3. Short-circuit analysis Three different short-circuit analysis are done: during three-phase, two-phase and one-phase
to ground faults. In every case fault impedance is assumed to be zero.
1.1.1. Single phase to ground fault Single-phase to ground fault is examined. Two generator/turbine sets are running and system
is under normal load. First fault occurs on Bus 1, between phase A and ground, at t=1.0 s.
Phase fault currents (RMS) for phase A is shown in Figure 3. As can be seen a maximum fault
current in phase A is 4.10 kA. Also generator currents in phase A during the fault are shown
in Figure 3. Before the fault current is 750 A and just after fault it increases to 2.28 kA.
Figure 4 shows current when fault occurs on Bus 3.Now fault current is 51.5 A. Generator
current just after fault is 747 A. In this case currents are significantly smaller than when fault
occurs on Bus 1.
Figure 3 Phase A fault current and generator G1 current. Fault occurs on Bus 1.
Figure 4 Phase A fault current and generator G1 current. Fault occurs on Bus 3.
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
0,00
0,50
1,00
1,50
2,00
2,50
3,00
3,50
4,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 with regulator (one-phase fault)
DATE 26 APR 2012 TIME 21:24:05 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
1,020, 4,10
FAULT FEL1 I PHASE A kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
0,80
1,00
1,20
1,40
1,60
1,80
2,00
2,20
0,80
1,00
1,20
1,40
1,60
1,80
2,00
2,20
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 with regulator (one-phase fault)
DATE 26 APR 2012 TIME 21:24:05 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
1,019, 2,28
SYNC G1 I PHASE A kA
SYNC G2 I PHASE A kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
0,0000
0,0100
0,0200
0,0300
0,0400
0,0500
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 3 with regulator (one-phase fault)
DATE 26 APR 2012 TIME 21:27:38 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
1,012, 0,0515
FAULT FEL1 I PHASE A kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
0,75400
0,75500
0,75600
0,75700
0,75800
0,75900
0,76000
0,74700
0,74800
0,74900
0,75000
0,75100
0,75200
0,75300
0,75400
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 3 with regulator (one-phase fault)
DATE 26 APR 2012 TIME 21:27:38 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
1,020, 0,74707
SYNC G1 I PHASE A kA
SYNC G2 I PHASE A kA
5
1.1.2. Two-phase fault Next two-phase, phases A and B, line-to-ground fault is simulated. During the fault system is
working without load. Generator G3 is disconnected from the system. Fault current and
generator G1 current in phase A are shown in Figure 5 . Fault current is 7.21 kA which is also
the sum of generator currents of the system.
Figure 5 Fault current in phase A and generator current during the fault
1.1.3. Three phase fault
System working without load
Three-phase fault occurs on Bus 1 at t=1.0. System is working with one generator/turbine set
which is running without mechanical load. Initial maximum short-circuit current and
instantaneous fault current can be calculated following way:
√
√
Details of calculations can be seen in Appendix 3. Figure 6 shows simulation result of this
case. From the simulation fault current is approximately 4.8 kA which is quite close to
calculated value.
When two generator sets are running fault currents are twice as big as in previous case:
Using these values κ-value can be examined
0,9900 0,9950 1,0000 1,0050 1,0100 1,0150 1,0200 1,0250 1,0300 1,0350 1,0400
TIME SECONDS
0,00
1,00
2,00
3,00
4,00
5,00
6,00
7,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. No load.
Short-circuit on BUS1 (two-phase symmetric fault)
DATE 15 APR 2012 TIME 12:04:10 JOB mini_project_2012_Part5-2-a-ii Simpow 11.0.009 Diagram:1STRI Software
1,0000, 7,21
FAULT FEL1 I PHASE A kA
0,9900 0,9950 1,0000 1,0050 1,0100 1,0150 1,0200 1,0250 1,0300 1,0350 1,0400
TIME SECONDS
0,00
0,50
1,00
1,50
2,00
2,50
3,00
3,50
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. No load.
Short-circuit on BUS1 (two-phase symmetric fault)
DATE 15 APR 2012 TIME 12:04:10 JOB mini_project_2012_Part5-2-a-ii Simpow 11.0.009 Diagram:2STRI Software
1,0001, 3,61
SYNC G1 I PHASE A kA
6
√
√
This situation is also shown in Figure 6. From the figure fault current is about 9 kA and it is
almost the same as calculated value.
Figure 6 Initial maximum currents when system is running with 1/3 (on left) and 2/3
generator sets
System under load
Now two generators are working and system is under
normal load. Balanced three-phase fault occurs on
Bus 1. Calculations of generator current during the
fault give
and for the maximum instantaneous current
Details of calculations can be seen in Appendix 3. Figure 7
shows simulation results of this current. DC-offset of
generator current can be calculated as
Fault currents are shown in Figure 8. As can be seen current is approximately 12.8 kA and a peak
value of instantaneous current is about 35 kA.
0,800 0,850 0,900 0,950 1,000 1,050 1,100 1,150 1,200 1,250 1,300
TIME SECONDS
0,00
0,50
1,00
1,50
2,00
2,50
3,00
3,50
4,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 1 T/G set in operation. No load.
Short-circuit on BUS1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 11:12:00 JOB mini_project_2012_Part5-2-a-i Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I POS. kA
0,800 0,850 0,900 0,950 1,000 1,050 1,100 1,150 1,200 1,250 1,300
TIME SECONDS
0,00
1,00
2,00
3,00
4,00
5,00
6,00
7,00
8,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. No load.
Short-circuit on BUS1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 12:17:46 JOB mini_project_2012_Part5-2-a-ii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I POS. kA
0,990 1,000 1,010 1,020 1,030 1,040 1,050 1,060 1,070 1,080 1,090
TIME SECONDS
1,00
1,50
2,00
2,50
3,00
3,50
4,00
4,50
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 w ithout regulator (three-phase symmetric fault)
DATE 6 APR 2012 TIME 12:32:23 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
1,000, 4,59
SYNC G1 I PHASE A kA
Figure 7 Generator current during fault
7
Figure 8 Initial short-circuit current and instantenous fault current. Fault on Bus 1.
Using these simulation results, κ-value can be calculated as
√
√
This is almost the same value than in case that generator was working without load.
Also situations where fault occurs on Bus 4 and 5 are simulated. Figure 9 shows fault current
when fault is on Bus 4. Maximum RMS value of fault current is 6 kA and peak value of
instantaneous current is 14.5 kA.
Figure 9 Initial short-circuit current and instantenous fault current. Fault on Bus 4.
When fault occurs on Bus 5 fault current is 25.5 kA and peak value of instantaneous current is
about 64 kA as can be seen in Figure 11.
Figure 10 Initial short-circuit current and instantenous fault current. Fault on Bus 5.
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100 1,120 1,140 1,160 1,180 1,200
TIME SECONDS
0,0
2,0
4,0
6,0
8,0
10,0
12,0
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 12:32:52 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I POS. kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
-30,0
-25,0
-20,0
-15,0
-10,0
-5,0
0,0
TET 4200 "Marine and Offshore power plants". Spring 2012. (MASTA)
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 13:36:27 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I PHASE A kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100 1,120 1,140 1,160 1,180 1,200
TIME SECONDS
0,00
1,00
2,00
3,00
4,00
5,00
6,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 12:48:55 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I POS. kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
-14,0
-12,0
-10,0
-8,0
-6,0
-4,0
-2,0
0,0
TET 4200 "Marine and Offshore power plants". Spring 2012. (MASTA)
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 13:28:53 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I PHASE A kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100 1,120 1,140 1,160 1,180 1,200
TIME SECONDS
0,0
5,0
10,0
15,0
20,0
25,0
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 12:50:31 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
FAULT FEL1 I POS. kA
0,900 0,920 0,940 0,960 0,980 1,000 1,020 1,040 1,060 1,080 1,100
TIME SECONDS
-60,0
-50,0
-40,0
-30,0
-20,0
-10,0
0,0
TET 4200 "Marine and Offshore power plants". Spring 2012. (MASTA)
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 13:20:39 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
FAULT FEL1 I PHASE A kA
8
Contribution of induction machines and currents of outgoing feeders
RMS values of induction machine currents during the fault are examined. Results are seen on
Table 2. Curves of currents can be found on Appendixes 4, 5 and 6. It can be seen motor M7
has the highest current in every case. This is because motor M7 has the highest rated current.
Fault bus Peak RMS current during the fault [kA]
M1 M2 M3 M4 M5 M6 M7 M8
Bus 1 0.972 0.975 0.367 0.353 0.328 0.328 1.788 0.639
Bus 4 0.355 0.355 0.236 0.131 0.384 0.385 2.108 0.236
Bus 5 0.318 0.318 0.212 0.117 0.134 0.134 2.275 0.212
Table 2 Induction motor currents during the fault
If fault occurs on Bus 1 all currents coming from generators are almost the same. The highest
current of outgoing feeders from Bus 1 is between Bus 1 and transformer T1.
If fault occurs on Bus 4 or 5 current coming from generator G2 is the highest. When fault
occurs on Bus 4 motor, M5 and M6, currents are the highest of outgoing currents. Also when
fault occurs on Bus 5 motor (M7) is the highest current leaving from Bus 5.
If one generator is disconnected from the system and fault occurs on Bus 1 generetor currents
are almost the same than in case that every generator were working. If fault occurs on Bus 4
or 5 currents from generators become higher. Overcurrent breakers can be used to prevent
generators and othercomponents to be damaged by too high currents.
Influence of Automatic Voltage Regulator during three phase fault
Three-phase fault is examined with and without generator voltage regulators. Two
generator/turbine sets are working. Fault occurs on Bus 1.
Figure 11 Generator speed without (on the left) and with regulator
Figure 11 shows generator G1 speed with and without regulator during the fault. Graphs are
similar for generator G2. Voltages are seen on Figure 12. With regulator generator speed does
not get so high value and it becomes stable faster. Although speed also goes under nominal
value before it reaches 1 p.u.
Without regulator generator voltage drops about 8 kV and does not reach original value
anymore. With regulator voltage drops first but reaches original value in 2 seconds.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0
TIME SECONDS
1,000
1,020
1,040
1,060
1,080
1,100
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 17:06:52 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
SYNC G1 SPEED p.u.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0
TIME SECONDS
0,99800
1,00000
1,00200
1,00400
1,00600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 w ith regulator (three-phase symmetric fault)
DATE 5 APR 2012 TIME 17:17:01 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
SYNC G1 SPEED p.u.
9
Figure 12 Generator voltages without (on the left) and with regulator
1.4. Motor starting analysis Motor starting analysis for induction motor M1 without mechanical load is done. System is
running with two generator/turbine sets. All of the other motors are working under normal
load. Speed and current (RMS) curves of motor M1 during start-up are seen in Figure 13.
Figure 13 Voltage (RMS) and speed curves for motor during start-up. Motor without load
Motor speed reaches its nominal value in 9 seconds and its rising is almost linear. Voltage
drops almost to 6 kV. Figure 15 shows generator G1 and motor M2 speed changes when
motor is started.
1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00
TIME SECONDS
0,00
1,00
2,00
3,00
4,00
5,00
6,00
7,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 17:06:52 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
SYNC G1 U PHASE A kV
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,00
1,00
2,00
3,00
4,00
5,00
6,00
7,00
8,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 w ith regulator (three-phase symmetric fault)
DATE 5 APR 2012 TIME 17:17:01 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
SYNC G1 U PHASE A kV
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
7,00
7,50
8,00
8,50
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:10:22 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
ASYNC M1 U POS. kV
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,00
0,20
0,40
0,60
0,80
1,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:10:22 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
ASYNC M1 SPEED p.u.
10
Figure 14 Generator speed and motor M2 speed when motor M1 is started
Now motor is running with full load. Start-up voltage and speed curves are seen in Figure 15.
Speed is not rising linearly and it takes almost 40 s to reach nominal value. Minimum voltage
is 6.59 kV.
Figure 15 Start-up voltage and speed curves when motor under full load
1.5. Transient analysis
1.1.4. Contingency analysis System is working with two generator settings and under normal load. Motor M1 is
disconnected for a short time. Figure 16 shows speed and voltage changes of motor M2
during disconnection. Curves of other motors can be seen in Appendix 7. Speed of every
motor has become stable in 9 second after disconnection.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,9800
0,9850
0,9900
0,9950
1,0000
1,0050
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:10:22 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
SYNC G1 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,9700
0,9750
0,9800
0,9850
0,9900
0,9950
1,0000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:10:22 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
ASYNC M2 SPEED p.u.
0,0 5,0 10,0 15,0 20,0 25,0 30,0 35,0 40,0 45,0 50,0 55,0 60,0
TIME SECONDS
7,00
7,50
8,00
8,50
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:40:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
1,2, 6,59
ASYNC M1 U POS. kV
0,0 5,0 10,0 15,0 20,0 25,0 30,0 35,0 40,0 45,0 50,0 55,0 60,0
TIME SECONDS
0,000
0,200
0,400
0,600
0,800
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Motor starting analysis
DATE 7 APR 2012 TIME 11:40:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M1 SPEED p.u.
11
Figure 16 Voltage and speed curves of motor M2 during disconnection
1.1.5. Critical clearing time Critical clearing time for system is examined. System is working with two generators. Three-
phase fault occurs on Bus 1. Clearing times for induction motors are seen on Table 1. Curves
are shown in Appendix 8. As can be seen from table the critical clearing time is 8.5 s.
Clearing times [s]
M1 M2 M3 M4 M5 M6 M7 M8
8.3 8.3 8.5 8.4 8.4 8.4 8.5 8.3
Table 3 Clearing times when two generators are running.
Same analysis is done when all three generators are working. Results are seen in Table 4.
Now critical clearing time is 10.1 s.
Clearing times [s]
M1 M2 M3 M4 M5 M6 M7 M8
10.1 10.1 9.9 9.9 9.9 9.9 9.9 10
Table 4 Clearing times when three generators are running.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
0,991700
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:13STRI Software
ASYNC M2 SPEED p.u.
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
7,960
7,980
8,000
8,020
8,040
8,060
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M2 U PHASE A kV
12
3. ATPDraw simulations
Starting of induction motor with frequency converter via long subsea cable is examined.
Virhe. Viitteen lähdettä ei löytynyt. shows a picture of the system. First starting currents of
motor are calculated. Cable capacitances and motor and transformer magnetizations are
neglected. Boost is assumed to be 65 %. Cable has rated 12 kV and 288 A. Starting currents
and frequencies needed to cause the correct starting torque are seen on Table 5Table 5. It can
be seen starting current rises with increasing cable length and break-away torque. In case of
30 km, 40 km and 50 km length cable start-up currents are quite high. Also start-up
frequencies in some cases reach too high values.
Calculations are seen in Appendix 9.
Same situation is examined with simulations using
ATPDraw. Figure 18 shows current and speed when cable
length is 10 km and break-away torque is 0.1 p.u. Starting
current with converter is almost one third smaller than
current without converter. Appendix 10 shows other
simulations. Simulations and calculations are not equal. This
is because neglected parameters of calculations.
Break
away
torque
[pu]
Start-up current /Start-up frequency
Cable length
10 km 20 km 30 km 40 km 50 km
0.1 191 A 7.0
Hz
221
A
9.4
Hz
255 A 12.5
Hz
290 A 16.2
Hz
327A 20.6
Hz
0.2 381 A 14.9
Hz
442
A
18.9
Hz
509 A 25.0
Hz
580 A 32.4
Hz
654A 41.1
Hz
0.3 572 A 21.0
Hz
664
A
28.3
Hz
764 A 37.5
Hz
870 A 48.6
Hz
980A 61.7
Hz
0.4 762 A 28.0
Hz
885
A
37.7
Hz
1019A 50.0
Hz
1161A 64.8
Hz
1307A 82.3
Hz
Table 5 Starting currents and frequencies of induction motor with converter controlled start-
up. Boost is 65 %.
Also simulations show that increasing cable length increases starting current. For cable
lengths 10 km and 20 km motor can be started with previous cable. When length is higher
than this starting is not possible anymore. To able motor starting cable resistance have to be
increased. For 30 km and 40 km a cable with rated 12 kV and 464 A is used. But this cable
cannot start 50 km length cable. Cable data is seen in Appendix 11.
Figure 17 Induction motor connected
to long cable and converter
13
Figure 18 Motor current and speed during start-up when breakaway torque is 0.1 pu and
cable legth 10 km. Green and pink curves are for system with converter. Other are without
converter
Figure 19 shows starting current and speed with cable length 30 km and break-away torque
0.1 p.u. Initial frequencies are varied. It can be seen the starting current with initial frequency
20 Hz is almost 500 A higher than current with 10 Hz initial frequency. Starting current can
be minimized by decreasing initial frequency.
Figure 19 Starting current and speed when cable lenght is 30 km, break-away torque is 0.1
p.u. and boost is 65 %. Initial frequencies are 10 Hz (on the left) and 20 Hz (on the right)
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM m:I1 0 5 10 15 20 25[s]
0
150
300
450
600
750
900
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM
0 5 10 15 20 25[s]0
100
200
300
400
500
600
700
800
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM
0 5 10 15 20 25[s]0
200
400
600
800
1000
1200
14
4. Conclusions
In this report an electrical system for offshore platform was examined. Analyses were done by
using programs SIMPOW and ATPDraw. Simulations shower that under normal conditions
system cannot keep voltage levels high enough. This can mean generators are working
overloaded. From short circuit analysis it can be seen three-phase-to-ground fault causes the
highest fault currents. If fault occurs on Bus1 and system is running with two generator sets it
takes 8.5 seconds for induction motors to cover. If all three generator are working the clearing
time increases to value 10.1 s. Also if one motor is disconnected from the system the
recovering time is about 9 seconds. For generators automatic voltage regulators can be used to
control speed and voltage and make the generator stable faster after fault.
Motor starting analyses were done in two different situations. First one induction were started
while other system were running normally. If motor is running without mechanical load start-
up time is about 9 s and almost linear. When motor is running full load start-up lasts almost
40 s. In other situation motor start-up where examined when motor was connected to long
subsea cable and converter. Analyses showed the cable length increased starting current and
finally made start-up impossible. If cable was changed to other cable with higher rated current
start-up were possible also cable lengths 30 km and 40 km. Although when cable got length of
50 km start-up were not able anymore. Other thing which affected to start-up was initial
frequency. Increased initial frequency also increased starting current.
15
Appendixes
Appendix 1
Component data
16
Appendix 2
Power Flow
First table shows power flow when two of the three generators are working. Second table is
for the system of three generators.
17
00
0
0
0 0
BUS1
U = 1 p.u.
FI = 3.16042E-021
degrees
P = -4.16264 MW
Q = -2.4933 Mvar
P = -4.16032 MW
Q = -2.49386 Mvar
P = 0.363609 MW
Q = 2.08899 MvarP = 15.36 MW
Q = 9.1 Mvar
P = 15 MW
Q = 7 Mvar
P = -4 MW
Q = -1.9373 Mvar
P = -4.86918 MW
Q = -3.21012 Mvar
P = -1.04447
MW
Q = -0.562251
Mvar
M1
P = -6.237 MW
Q = -3.74218 Mvar
M2
P = -6.25 MW
Q = -3.74998 Mvar
BUSG3
U = 1 p.u.
FI = 3.16042E-021
degrees
P = -15 MW
Q = -7 Mvar
G3
P = 15 MW
Q = 7 Mvar
BUSG1
U = 1 p.u.
FI = 1.1416E-033
degrees
P = -0.363609 MW
Q = -2.08899 Mvar
G1
P = 0.363609 MW
Q = 2.08899 Mvar
BUS2
U = 0.998661 p.u.
FI = -0.0214586
degrees
P = 4.158 MW
Q = 2.49442 Mvar
M3
P = -4.158 MW
Q = -2.49442 Mvar
BUSG2
U = 1 p.u.
FI = 3.16042E-021
degrees
P = -15.36 MW
Q = -9.1 Mvar
G2
P = 15.36 MW
Q = 9.1 Mvar
BUS7
U = 1 p.u.
FI = 3.16042E-021
degrees
P = 4 MW
Q = 1.9373 Mvar
0
P = -4 MW
Q = -1.9373 Mvar
BUS3
U = 0.968803 p.u.
FI = -2.76627
degrees
P = 1.037
MW
Q = 0.49524
Mvar
0
M4
P = -1.037 MW
Q = -0.49524 Mvar
BUS4
U = 0.94939 p.u.
FI = -4.19837
degrees
P = 4.83346 MW
Q = 2.70104 Mvar
0
P = -0.95078 MW
Q = -0.579376 Mvar
0
P = -1.80268 MW
Q = -0.87304 Mvar
M5
P = -1.04 MW
Q = -0.624314 Mvar
M6
P = -1.04 MW
Q = -0.624314 Mvar
BUS5
U = 0.923247 p.u.
FI = -6.36011
degrees
P = 0.945192 MW
Q = 0.528144 Mvar
0
0
P = -0.426192 MW
Q = -0.206448 Mvar
M7
P = -0.519 MW
Q = -0.321697 Mvar
BUS6
U = 0.999331 p.u.
FI = -0.0107136
degrees
P = 4.158 MW
Q = 2.49443 Mvar
M8
P = -4.158 MW
Q = -2.49443 Mvar
18
Appendix 3
Short circuit calculations
Generator without load:
Nominal current is
√
√
Initial maximum value of short-circuit current with one generator working is
Total short circuit current is
DC-offset:
√
It gets the maximum value when .
First peak is when t=0.0083 s
√ √
With load
Load of generator:
( )
( )
( )
( )
19
√
DC-offset:
√
It gets the maximum value when .
First peak is when t=0.0083 s
√
√
20
Appendix 4
Current contribution from induction machines during three-phase fault on Bus 1
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,300
0,400
0,500
0,600
0,700
0,800
0,900
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
ASYNC M1 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,200
0,300
0,400
0,500
0,600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
ASYNC M3 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,300
0,400
0,500
0,600
0,700
0,800
0,900
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
ASYNC M2 I POS. kA
21
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,100
0,150
0,200
0,250
0,300
0,350
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
ASYNC M4 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,150
0,200
0,250
0,300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M5 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,80
1,00
1,20
1,40
1,60
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
ASYNC M7 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,150
0,200
0,250
0,300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
ASYNC M6 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,200
0,300
0,400
0,500
0,600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:13:57 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
ASYNC M8 I POS. kA
22
Appendix 5
Current contribution from induction machines during three-phase fault on Bus 4
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,2900
0,3000
0,3100
0,3200
0,3300
0,3400
0,3500
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
ASYNC M1 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,2800
0,2900
0,3000
0,3100
0,3200
0,3300
0,3400
0,3500
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
ASYNC M2 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1050
0,1100
0,1150
0,1200
0,1250
0,1300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
ASYNC M4 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1900
0,2000
0,2100
0,2200
0,2300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
ASYNC M3 I POS. kA
23
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,80
1,00
1,20
1,40
1,60
1,80
2,00
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
ASYNC M7 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,150
0,200
0,250
0,300
0,350
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
ASYNC M6 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,150
0,200
0,250
0,300
0,350
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M5 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1900
0,2000
0,2100
0,2200
0,2300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 4 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:35:10 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
ASYNC M8 I POS. kA
24
Appendix 6
Current contribution from induction machines during three-phase fault on Bus 5
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,2850
0,2900
0,2950
0,3000
0,3050
0,3100
0,3150
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
ASYNC M1 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,2900
0,2950
0,3000
0,3050
0,3100
0,3150
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
ASYNC M2 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1950
0,2000
0,2050
0,2100
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
ASYNC M3 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1060
0,1080
0,1100
0,1120
0,1140
0,1160
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
ASYNC M4 I POS. kA
25
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1200
0,1220
0,1240
0,1260
0,1280
0,1300
0,1320
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M5 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1200
0,1220
0,1240
0,1260
0,1280
0,1300
0,1320
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
ASYNC M6 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
1,00
1,20
1,40
1,60
1,80
2,00
2,20
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
ASYNC M7 I POS. kA
0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00
TIME SECONDS
0,1950
0,2000
0,2050
0,2100
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 5 (three-phase symmetric fault)
DATE 5 APR 2012 TIME 14:47:09 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
ASYNC M8 I POS. kA
26
Appendix 7
Voltage variation of induction motors when motor M1 is disconnect
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
7,960
7,980
8,000
8,020
8,040
8,060
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
ASYNC M1 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
7,960
7,980
8,000
8,020
8,040
8,060
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
ASYNC M2 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
7,940
7,960
7,980
8,000
8,020
8,040
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
ASYNC M3 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
3,4350
3,4400
3,4450
3,4500
3,4550
3,4600
3,4650
3,4700
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
ASYNC M4 U PHASE A kV
27
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
3,3600
3,3650
3,3700
3,3750
3,3800
3,3850
3,3900
3,3950
3,4000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
ASYNC M5 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
3,3600
3,3650
3,3700
3,3750
3,3800
3,3850
3,3900
3,3950
3,4000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:9STRI Software
ASYNC M6 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
0,24600
0,24650
0,24700
0,24750
0,24800
0,24850
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:10STRI Software
ASYNC M7 U PHASE A kV
0,80 0,90 1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00 2,10 2,20 2,30
TIME SECONDS
7,940
7,960
7,980
8,000
8,020
8,040
8,060
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:11STRI Software
ASYNC M8 U PHASE A kV
28
Frequency variations when motor M1 is disconnect
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991200
0,991400
0,991600
0,991800
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:12STRI Software
ASYNC M1 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
0,991700
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:13STRI Software
ASYNC M2 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,990900
0,991000
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:14STRI Software
ASYNC M3 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,988900
0,989000
0,989100
0,989200
0,989300
0,989400
0,989500
0,989600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:15STRI Software
ASYNC M4 SPEED p.u.
29
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
0,991700
0,991800
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:16STRI Software
ASYNC M5 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
0,991700
0,991800
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:17STRI Software
ASYNC M6 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,989600
0,989700
0,989800
0,989900
0,990000
0,990100
0,990200
0,990300
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:18STRI Software
ASYNC M7 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,991000
0,991100
0,991200
0,991300
0,991400
0,991500
0,991600
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:25:07 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:19STRI Software
ASYNC M8 SPEED p.u.
30
Appendix 8
Induction motor curves for critical clearing analysis, Mechanical load k=0.85
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
9,3, 0,99121
ASYNC M1 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
9,5, 0,99107
ASYNC M3 SPEED p.u.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98400
0,98500
0,98600
0,98700
0,98800
0,98900
0,99000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
9,4, 0,98904
ASYNC M4 SPEED p.u.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
9,3, 0,99121
ASYNC M2 SPEED p.u.
31
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
9,4, 0,99123
ASYNC M5 SPEED p.u.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
9,4, 0,99123
ASYNC M6 SPEED p.u.
0,0 1,0 2,0 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,0 11,0 12,0 13,0 14,0 15,0
TIME SECONDS
0,98400
0,98500
0,98600
0,98700
0,98800
0,98900
0,99000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
9,5, 0,98975
ASYNC M7 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 12:35:35 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
9,3, 0,99108
ASYNC M8 SPEED p.u.
32
Three generator/turbine sets working
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:1STRI Software
11,1, 0,99121
ASYNC M1 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:2STRI Software
11,1, 0,99121
ASYNC M2 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:3STRI Software
10,9, 0,99107
ASYNC M3 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98400
0,98500
0,98600
0,98700
0,98800
0,98900
0,99000
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:4STRI Software
10,9, 0,98904
ASYNC M4 SPEED p.u.
33
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:5STRI Software
10,9, 0,99123
ASYNC M5 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:6STRI Software
10,9, 0,99123
ASYNC M6 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98400
0,98500
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:7STRI Software
10,9, 0,98975
ASYNC M7 SPEED p.u.
0,0 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0
TIME SECONDS
0,98600
0,98700
0,98800
0,98900
0,99000
0,99100
0,99200
TET 4200 "Marine and Offshore power plants". Spring 2012.
Dynpow file for Mini-project. 2 T/G sets in operation. Normal load.
Short-circuit on BUS 1, 4 and 5 (three-phase symmetric fault)
DATE 7 APR 2012 TIME 13:08:03 JOB mini_project_2012_Part5-2-a-iii Simpow 11.0.009 Diagram:8STRI Software
11,0, 0,99108
ASYNC M8 SPEED p.u.
34
Appendix 9
Matlab code for starting currents and frequencies
function [] = torque_marine( )
clear all hold off %control values B=0.65;
Tba1=0.1; Tba2=0.2; Tba3=0.3; Tba4=0.4;
%system
fn=50; l=50; %motor:
Tn=9900; Un=6.6*10^3; Unpu=1.0; Sn=1.2*10^6; In=Sn/(sqrt(3)*Un); Zbase=Un^2/Sn; sn=(2*fn*pi-996*2*pi/60)/(2*pi*fn);
Rs=0.0215; Rr=0.011; X1s=0.0673; Xs2=0.0673; Rr1=Zbase*Rr;
%cable: %In=241;
Rac=0.25; Racpu=Rac/Zbase; Xc=0.37*10^(-3)*2*pi*50; Xcpu=Xc/Zbase;
%transformer St=5*10^6; Zt=St*0.0403/Sn; Rt=Zt/sqrt(8.9^2+1); Xt=8.9*Rt;
Rsys=Rs+Rr+Racpu*l+Rt; Xsys=X1s+Xs2+Xt+Xcpu*l;
Zpu=sqrt(Rsys^2+Xsys^2) Z=Zpu*Zbase f=0.0;
while f <= 50
35
Tpu=(3*(Unpu*(1+B)*f/(fn*Zpu))^2*Rr/(f/fn));
plot(f,Tpu);
hold on f=f+0.1; end
xlabel('Frequency [Hz]') ylabel('Torque [pu]') title(['Start-up torque,B=',num2str(B), ', l=',num2str(l), ' km']); grid;
%current fba1=Tba1/(3*(Unpu*(1+B)/(fn*Zpu))^2*Rr*fn) Ist1=sqrt(Tba1*Tn*2*pi*fba1/(3*Rr1))
fba2=Tba2/(3*(Unpu*(1+B)/(fn*Zpu))^2*Rr*fn) Ist2=sqrt(Tba2*Tn*2*pi*fba2/(Rr1*3))
fba3=Tba3/(3*(Unpu*(1+B)/(fn*Zpu))^2*Rr*fn) Ist3=sqrt(Tba3*Tn*2*pi*fba3/(3*Rr1))
fba4=Tba4/(3*(Unpu*(1+B)/(fn*Zpu))^2*Rr*fn) Ist4=sqrt(Tba4*Tn*2*pi*fba4/(Rr1*3)) end
36
Appendix 10
ATPDraw simulations of starting currents and speeds
Cable: 2XS(FL)2YRAA 6/10(12) kV, In=288 A
B=0.65, l=10 km, Tba=0.2, finit=14 Hz:
B=0.65, l=10 km, Tba=0.3, finit=21 HZ:
B=0.65, l=10 km, Tba=0.4, f=28 Hz
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM m:I1 0 5 10 15 20 25[s]
0
150
300
450
600
750
900
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM m:I1 0 5 10 15 20 25[s]
0
150
300
450
600
750
900
37
B=0.65, l=20 km, Tba=0.1, finit=9.4 Hz
B=0.65, l=20 km, Tba=0.2, f=19 Hz
B=0.65, l=20 km, Tba=0.3, f=29 Hz
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM m:I1 0 5 10 15 20 25[s]
-2500
-2000
-1500
-1000
-500
0
500
1000
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
700
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
-2200
-1700
-1200
-700
-200
300
800
38
B=0.65, l=20 km, Tba=0.4, f=38 Hz
B=0.65, l=30 km, Tba=0.1, f=12.5 Hz, cannot start
Cable changed to In=327 A
B=0.65, l=30 km, Tba=0.1, f=10 Hz
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
-2200
-1700
-1200
-700
-200
300
800
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
-2500
-2000
-1500
-1000
-500
0
500
1000
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
-2000
-1000
0
1000
2000
3000
4000
5000
39
but when Tba=0.2 stalling again.
Cable changed to In=464 A
B=0.65, l=30 km, Tba=0.1, f=10 Hz:
B=0.65, l=30 km, Tba=0.2, f=10 Hz
B=0.65, l=30 km, Tba=0.3, f=10 Hz
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
40
B=0.65, l=30 km, Tba=0.4, f=10 Hz
Tba=0.1, l= 50 km, f=10 Hz, when Tba=0.2 stalling
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM
0 5 10 15 20 25[s]0
100
200
300
400
500
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
41
Tba=0.1, l= 40 km, finit=10 Hz
Tba=0.3, l= 40 km, f=20 Hz
Tba=0.4, l= 40 km, f=20 Hz
(file startup1(1).pl4; x-var t) m:I1 m:I2 u1:OMEGM u2:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
700
(file startup1(1).pl4; x-var t) m:I2 u1:OMEGM 0 5 10 15 20 25[s]
0
100
200
300
400
500
600
700
42
Appendix 11
Cable data