manufacturing planning and control systems
DESCRIPTION
Manufacturing planning and control systems Chapter 4 1.Capacity Planning 2.CAPACITY PLANNING'S ROLE IN MPC SYSTEMS. 3.CAPACITY PLANNING AND CONTROL TECHNIQUES. 4.MANAGEMENT AND CAPACITY PLANNING. 5.DATA BASE REQUIREMENTS.TRANSCRIPT
MANUFACTURING PLANNING AND CONTROL
SYSTEMSCh.4 Capacity Planning
Prepared by:
Eng.Haitham Shehata HusseinEng.Ahmed Safwat
Under Supervision :
DR.Mohamed Emad Sdeek
Index
1. Capacity Planning Using Overall Factors (CPOF).
2. Capacity Bills.
3. Resource Profiles.
4. Capacity Requirements Planning (CRP).
5. Input/Output Control
6. The Capacity "Bath Tub“
Capacity Planning
CAPACITY PLANNING'S ROLE IN MPC SYSTEMS.
CAPACITY PLANNING AND CONTROL TECHNIQUES.
MANAGEMENT AND CAPACITY PLANNING.
DATA BASE REQUIREMENTS.
EXAMPLES OF APPLICATIONS.
1. Hierarchy of Capacity Planning Decisions.
2. Links to Other MPC System Modules.
1. Capacity Planning in the MPC System
2. Choosing the Measure of Capacity
3. Choice of a Specific Technique4. Using the Capacity Plan
•Data Base Design Considerations
1. Capacity Planning at Montell USA, Inc.
2. Capacity Planning at Twin Disc3. Capacity Planning at Applicon
1. Definition
CAPACITY PLANNING.
Capacity Planning
Capacity is defined as the ability to achieve, store
or produce.
For an organization, capacity would be the ability
of a given system to produce output within the
specific time period.
In operations, management capacity is referred
as an amount of the input resources available to
produce relative output over period of time.
In general, terms capacity is referred as maximum
production capacity, which can be attained within a
normal working schedule.
Capacity Planning
Capacity planning is essential to be
determining optimum utilization of resource
and plays an important role in decision-making
process.
CAPACITY PLANNING'S ROLE IN MPC SYSTEMS
Hierarchy of Capacity Planning DecisionsFinite capacity scheduling uses basically the same data as capacity
requirements planning but adjusts the schedule to ensure that the capacity required never exceeds a work center’s defined capacity limits in a given time period.
Hierarchy of Capacity Planning Decisions
The previous figure depicts the hierarchy of capacity planning decisions that can be made within a planning and control environment.
1)Planning resource capacities over long time horizons.
2)The rough-cut evaluation of capacity required by the
master production schedule.
3)Detailed capacity requirements of a particular
production schedule.
4)The use of finite loading procedures.
5)Monitoring actual outputs versus plan.
Links to Other MPC System Modules
The source of the loading data changes as you move
down this hierarchy:
Resource planning takes its capacity requirements from
the business plan.(Production Planning)
rough-cut capacity planning uses the master production
schedule as the source of its information.
Capacity requirements planning and the remainder of
these shorter-term planning modules take their loading
data from the Material Requirements Planning output.
Finite loading related to firms using details material
plans, but it can be better viewed as a shop scheduling
technique.
Input/output analysis linked to the shop-floor system and
data base for shop-floor control.
CAPACITY PLANNING AND CONTROL TECHNIQUES.
Capacity Planning and Control Techniques.
What capacity is needed to meet the production plan ?
For the aggregate plan, we reviewed different methods (resource planning) which all aim to find the required capacity in facilities, equipment and manpower.
From the aggregate planning, a MPS was built. And from the MPS, an MRP was derived. We have not yet considered the capacity aspects of these plans.
For the MPS, the Rough-cut capacity plans will provide estimates of the load of the different workcenters over the corresponding time horizon.
For the MRP, the capacity requirement plan will provide such an estimate.
We will review 4 techniques successively:
1) Capacity Planning using Overall Factors (CPOF).
2) Capacity bills.
3) Resource profiles.
4) Capacity Requirement Planning (CRP).
These techniques are more and more accurate but require more and more
information.
1.Capacity Planning using Overall Factors (CPOF). EX. Let us assume, we have only two end
products H and h with the following demand.
Total
Time period : 1 dayConsider 3 workcenters (or shops)CPOF method need the average relative workload
1.Capacity Planning using Overall Factors (CPOF). Modular Description
Here is specified the complete list of all the components.
Product components
Cup assembly Tray assembly
1.Capacity Planning using Overall Factors (CPOF). CPOF need Total amount of resource for
producing one unit of each end products.
Assume the unit to be the working hour.
1 H requires 0.15 hour = 9 min.1 h requires 0.1 hour = 6 min.Workcenter load = [(H total capacity/product)x(H product/period) + (h total capacity/product )x (h product/period)] x relative load Eq.1
1.Capacity Planning using Overall Factors (CPOF).At period time 5
Cup assembly = [9*100+6*150]*0.55 = 990 min = 990/60 = 16.5
hours
Tray label = [9*100 +6*150]*0.10 = 180 min = 180/60 = 3 hours
Tray assembly = [9*100+6*150]*.35= 630 min = 630/60 = 10.5 hours
Total capacity = 16.5 + 3 + 10.5 =30 hours The same calc with period 6,7,8
The method implicitly assume that for every production hour, 55 % are spent at the Cup Assembly, 35 % at the Tray Assembly and 10 % at the Tray Label.
Total
55%
10%35%
Hours
2.Capacity Bills.
Compared to CPOF, capacity bills take into account the detailed need of the different products at the different workcenters.
These needs can be specified as follows.
For each workcenter, the setup time is distributed on each unit of the lot size. The capacity bills can then be computed.
2.Capacity Bills.
Note that the production of 1 H TRAY requires 4 cups. The total is of course identical to what we already knew: the production of one H requires 0.15 hour.
Notes:When H is in production, the cup assembly requires 60% of the total work.When h is in production, the cup assembly requires only 50% of the total work. The CPOF method assumes a 55% average. This average is only correct when the same amount of H and h are manufactured. This means that the CPOF method is correct as long as the product mix remains the same.
2.Capacity Bills.
Capacity requirements Using Capacity BillsWorkcenter load = [H capacity bill/product )x (H
products/period) + (h capacity bill/product )x (h products/period)] Eq.2At period time 5 Cup assembly = [0.09*100+0.05*150] = 16.5 hours
Tray label = [0.02*100 +0*150] = 2 hours
Tray assembly = [0.04*100+0.1*150]= 11.5 hours
Hours
3.Resource Profiles
The idea here is to take the timing of the different workcenters into account.
Example. The production of 100 H units in
period 5 will lead to a workload of the
workshops. However, this load will not be
in period 5 but earlier, maybe in period 4 or
3 depending on the lead times.
3.Resource Profiles
Explode the demand for 1 end product in period iAssume: lead time for each operation =
1day
Except: lead time for assembly of the G
cups = 2 days.
3.Resource Profiles
Explode the demand for end products in period 7
3.Resource Profiles
This last calculation can be repeated for all the demands.
Hours
4.Capacity Requirements planning
Time bucket / Period / HorizonThe time bucket is the unit of time in use. One week is typical. The horizon is how much in the future one is looking, how many time buckets or periods we consider. By definition, we are at the beginning of period 1.Gross RequirementThis is the firm or forecast demand for the corresponding period. It is time-phased.Scheduled ReceiptsThese are parts which we are guaranteed to receive at the beginning of the corresponding period.On-hand (Projected available balance)This is the inventory at the end of the corresponding period. It should remain positive.Planned Order ReleaseHere are the orders which are planned to be launched to prevent the inventory from becoming negative. These orders are not yet placed. They are planned to be placed !
4.Capacity Requirements planningLead timeThis is the time required for an order to be completed. It is the time between the moment an order is placed and the the moment the products are delivered. It is made of 4 main parts.
Move - Queue - Setup - RunNote that queuing time depends on the workload and on the schedule !Safety timeThis is a time which is added to the lead time for safety reasons, typically when the lead time is not very reliable.Lot sizeThis is the technique used for deciding how much to order. The "lot for lot" technique means that we order exactly what is needed. Other methods are reviewed at the end of the chapter.Safety stockBy principle, an order is launched to prevent the inventory from becoming negative. With a safety stock, an order is launched as soon as the inventory would drop below this safety stock level. This security is often needed when scrap is common.
4.Capacity Requirements planningThe Kuczma Company makes sign mounts
for commercial customers. One
product is the H mount which is made up of a
painted surface on both sides of a wooden H
frame. The H mount is put together in final
assembly. The surfaces are painted in the
paint shop, and frame is made in the frame
shop. Kuczma wants to estimate the H mount
capacity needs for next five periods in final
assembly, the paint shop, and the frame shop.
Setup
Operation Work Center Time Run time
Mount assembly Final Assembly 2 hours 1.0 hours
Fabricate H frame Frame Shop 3 hours 0.5 hours
Paint surfaces Paint Shop 4 hours 0.4 hours
4.Capacity Requirements planning
1 2 3 4 5 615 20 20 20 20 015
Projected available balance 10 10 20 0 10 20 2030 0 30 30 0 0
1 2 3 4 5 630 40 40 40 40 050
Projected available balance 25 45 5 15 25 35 350 50 50 50 0 0
1 2 3 4 5 620 20 20 20 20 20
Projected available balance 25 5 0 0 0 0 015 20 20 20 20
Item: H framePeriod
Gross requirementsScheduled Receipts
Gross requirementsScheduled Receipts
Planned order releaseQ = 50, LT = 1, SS = 5
Planned order releaseQ = 30, LT = 1, SS = 0
Item: Painted SurfacePeriod
Planned order releaseQ = L4L, LT = 1, SS = 0
Item: H mountPeriod
Gross requirementsScheduled Receipts
LT: Lead Time LS: Lot Size SS: Safety Stock
4.Capacity Requirements planning
H Mount Assy S/U Time* Run Time/unit*
PAB15 20 20 20 20 2 1
H Frame15
PAB30 0 30 30 0 0 3 0.5
Painted Surface50
PAB0 50 50 50 0 0 4 0.4
GRSR
PORGRSR
PORGRSR
POR
4.Capacity Requirements planning
Capacity RequirementsPeriod
Dept 1 2 3 4 5 6H Mount Assy 17 22 22 22 22 0H Frame 28.5 0 18 18 0 0Painted Surface 24 24 24 24 0 0
Note: 28.5 = 3 + 0.5(15) + 3 + 0.5(30)
Requires: Planned order and schedule receipt information from the MRP system, and setup and run times from the product routing file.
5.Input / output control.
Input-output Control is a technique that allows operation to manage
facility work flow.
It is used to control the size of the queues in front of work centers,
thereby helping to control manufacturing lead times. Refer to as "push
system" of linking work centers. When a batch of items is completed at
one work centre, it is pushed to the next work centre, where it waits in
a queue until it is selected to be worked at that work centre.
Input-output Control is important because it is a form of queue control,
and a great
portion of the time that a job spends in a plant is spent waiting in
queues. In many job shops and batch manufacturing factories 80 to
95 percent of the total time is queue time.
5.Input / output control.
Advantages of using Input-output Control
Customer service may improve due to the items or products
are produced on time.
Efficiency may be improved because of the less work-in-
process in cluttering the work centre and adding to overhead
costs.
Quality may be improved because less work-in-process hides
fewer problems.
MANAGEMENT AND CAPACITY PLANNING
1.Capacity Planning In MPC System From Hierarchy of Capacity Planning figure
there are relationship between MPC framework and various capacity planning modules (five modules range [long range –day to day] ):
o Vertical relationship among the capacity
planning modules
o Horizontal relationship with the material
planning modules of the MPC system .
1.Capacity Planning In MPC System
These relationships can affect managerial choices for capacity planning systems design and use in a specific firm.
1.Capacity Planning In MPC System
To illustrate the importance of cps, let consider the
impact of production planning and resource planning
decisions on short-term capacity planning decisions.
To extent the production planning and resource
planning are done well, problems faced in capacity
planning can be reduced, since appropriate resources
have been provided.
1.Capacity Planning In MPC System
For example: the production plan specifies a
very stable rate of output, then changes in
MPS requiring capacity changes are minimal .
If the material planning modules functions
effectively, the MPS will be converted into
detailed component production plans with
relatively few unexpected execution problems.
2.Choosing the Measure of Capacity
In this section, we can learn a method of measuring a capacity of system. Consider anything for which you need to measure the capacity, as a system.
Analyze the system into input, processing and output. When you analyze, see to that, where there is a less variability, choose that side and identify the product, process-resources, the input resources and attach time frame to provide the capacity measure.
2.Choosing the Measure of Capacity
Measure of Capacity through output Consider an automobile mass production
industry. You can’t find much variation in the output side compared to the input resources and processing parts. So the number of cars/time is considered as the measure. Mostly in the case of mass production industry the output side is considered to measure the capacity.
2.Choosing the Measure of Capacity
Measure of the capacity through Input Consider an educational institution; here
the output side is not taken into consideration because the number of outgoing students per time may vary depending upon the pass result. But the intake is always constant because the intake depends upon the government approved. So, the capacity of educational institution is measured through the input namely the number of students intake.
2.Choosing the Measure of Capacity
Measure of the capacity through processing Consider a sugarcane industry, the capacity of
that industry is not measured in terms of the output and input. There is a variability in terms of yield rate that means some times “y” tons of sugarcane may give “x” tons of sugar or some times same “y” may give more than or less than the “x” tons of sugar. Since variability is existing in both the input side and output side. Inputs and outputs are not considered for measuring the capacity. But in the processing side there is a less variability namely the crushing capacity or the number of tons of sugarcane could be crushed by the crushing machine is considered to be a best measure to measure the capacity of the sugarcane industry from the processing point of view.
2.Choosing the Measure of Capacity
System Components of System considered for capacity measure
Unit of Measure
Automobile Industry Bottling Plant University Auto repair shop Restaurant
Output
Output
Input
Processing
Processing
Number of Automobiles Gallons / Day Number of students intake per year Number of machines hour per day Seating Capacity
The table provides some of the systems and their corresponding measure to measure the capacity.
2.Choosing the Measure of Capacity
In summary, if you want to fix the measure
for the capacity, then see the system as
input, processing and output. Find where
there is a less variability choose that side
and correspondingly choose the product or
the resources to estimate the measure.
3. Choice of a Specific Technique.
CP Techniques for converting a material plan
into capacity requirements include three
different methods for rough-cut CP (CPOF,
Capacity Bills, and Resource Profiles) and
CRP. The choice of method depends heavily
on characteristics of the manufacturing
process.
3. Choice of a Specific Technique.
The three rough-cut methods are
most general, being applicable even in
companies using JIT methods for shop-
floor control.
Rough-cut can be useful in JIT
operations to estimate the impact of
changes in requirement called for by
revisions to the MPS.
3. Choice of a Specific Technique.CP Techniques Pros Cons
Capacity Bills 1. Easy to use2. Minimal
computational requirements
3. Consider product mix
1. Doesn’t consider lead times, inventory information, or gross-to-netting
2. Less accurate
Resource Profiles 1. Easy to use2. Minimal
computational requirements
3. Consider product mix
4. Considers lead times
1. Doesn’t consider inventory information or gross-to- netting
2. Less accurate
Capacity Requirements Planning
1. Considers: gross-to-netting, Inventory information, lead times
2. More accurate3. Consider product
mix
1. Requires MRP system, Time-phased records, Extensive computational requirements
4.Using the CP.
Capacity planning has seen an increased emphasis due to the financial benefits of the efficient use of capacity plans within MRP systems and other information systems.
Insufficient capacity can quickly lead to deteriorating delivery performance, unnecessarily increase work-in-process, and frustrate sales personnel and those in manufacturing. However, excess capacity can be costly and unnecessary.
The inability to properly manage capacity can be a barrier to the achievement of maximum firm performance. In addition, capacity is an important factor in the organization's choice of technology.
DATA BASE REQUIREMENTS.
Data Base Design Considerations
To be continue