malcolm pirnie inc - final design report · the ll and ltr sites were licensed from 1969 until...

210

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between
Page 2: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUDOUV4KRNIE

FINAL DESIGNREPORT

Lemberger Transport &Recycling Site Closure

Preparedfor:

Lemberger Site Remediation Group

Submitted By:

MALCOLMPIRNIE

Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, Minnesota 55416-1262

October 6, 19952049-007-940

Page 3: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LEMBERGER TRANSPORT & RECYCLING SITE CLOSURE SYSTEM

FINAL DESIGN REPORT

TABLE OF CONTENTSPage

1.0 INTRODUCTION AND BACKGROUND .................................... 1-11.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11.2 B a c k g r o u n d . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-21.3 Purpose and Contents of the Final Design R e p o r t . . . . . . . . . . . . . . . . . . . . . . . . . 1-3

2.0 SITE DESCRIPTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12.1 Topography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12.2 Regional Geology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12.3 Hydrogedogy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-22.4 Summary of the Nature and Extent of Contamination . . . . . . . . . . . . . . . . . . . . . . 2-32.5 Previous RD/RA Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4

2.5.1 Phase 1 Site Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-42.5.2 Phase 2 Drum Excavation and Removal . . . . . . . . . . . . . . . . . . . . . . . . . 2-52.5.3 Phase 3 Predesign Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52.5.4 Operable Unit 1 Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-6

3.0 LANDFILL CLOSURE DESIGN COMPONENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13.2 Purpose of Closure System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13.3 Construction of the Cover System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-23.4 Components of the Cover System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-2

3.4.1 Grading Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-23.4.2 Gas Control and Foundation Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-33.4.3 Lower Geotextile Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-43.4.4 Clay Barrier Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-43.4.5 Geomembrane Liner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-63.4.6 Drainage Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-103.4.7 Upper Geotextile Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-113.4.8 Cover L a y e r . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123.4.9 Topsoil Layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123.4.10 Vegetation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13

3.5 Storm Water Management and Erosion Control . . . . . . . . . . . . . . . . . . . . . . . . . 3-133.5.1 G e n e r a l . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-133.5.2 Diversion Swales . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153.5.3 Downchutes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153.5.4 Energy Dissipators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-163.5.5 Sedimentation Basin . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-16

3.6 Stability Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-173.6.1 Analytical Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-173.6.2 Cover Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-183.6.3 Analytical Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-18

3.6.3.1 Soils . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-183.6.3.2 Geosynthetics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19

3.7 Landfill Gas Venting System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-203.8 Well A b a n d o n m e n t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-20

2049-007-940

Page 4: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE OF CONTENTS (Con't)

__________________________________________________Page

4.0 REQUIRED PERMITS, LICENSES, AND APPROVALS . . . . . . . . . . . . . . . . . . . . . . . . 4-1

5.0 COST ESTIMATE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

6.0 CONSTRUCTION SCHEDULE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

7.0 HEALTH AND SAFETY PLAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-1

LIST OF TABLESTable FollowingNo. Description_______________________________________Page

2-1 Summary of Previous Investigations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3

2-2 Number of Drums Removed by Anomaly Area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

3-1 Properties of HDPE Liner Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6

3-2 Drainage Structure Design Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-15

3-3 Minimum Soil Strength Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19

5-1 Final Construction Cost Estimate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

5-2 Operation and Maintenance Final Cost Estimates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

LIST OF FIGURES

Figure FollowingNo. Description_______________________________________Page

1-1 Site Location Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1

2-1 Anomaly Locations Where Drums Were Found . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

2-2 Anomaly Locations Where Cylinders Were Found . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

6-1 Final Project Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

2049-007-940

Page 5: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LIST OF APPENDICES

Appcndii___Description__________________

A Volume, Drainage, and Riprap Calculations

B Cover Stability Analysis Calculations

C Oversight Health and Safety Plan

D Final Design Drawings (Under Separate Cover)

E Final Technical Specifications (Under Separate Cover)

2049-007-940 iii

Page 6: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

1.0 INTRODUCTION AND BACKGROUND

1.1 INTRODUCTION

The Lemberger Transport and Recycling (LTR) site is an inactive landfill which accepted

industrial waste and operated in conjunction with a landfill directly to the north called the LembergerLandfill, Inc. (LL). Both sites, shown on Figure 1 -1, are on the National Priorities List.

The United Stated Environmental Protection Agency (USEPA) has, administratively, divided

remedial activities associated with the LTR Site and the LL site into two operable units. Operable Unit1 includes source control at the LL site and a treatment system for contaminated ground water associatedwith both the LL site and the LTR Site. Operable Unit 2 addresses source control at the LTR Site.

An Administrative Order by Consent (AOC), addressing source control activities at the LTRSite, was executed on July 15,1993. The AOC requires the Lemberger Site Remediation Group (LSRG)

to conduct certain remedial activities pursuant to Section 106 of the Comprehensive EnvironmentalResponse, Compensation and Liability Act (CERCLA) of 1980, as amended, 42 U.S.C. Section 9606(a).

The AOC divides LTR remedial activities into three phases:• Phase 1 - Conduct boundary and geophysical survey, and construct a fence

around the site.

• Phase 2 - Excavate and remove buried drums.

• Phase 3 - Treat "hot spots" and soils adjacent to the drums recovered in Phase2 with soil vapor extraction (SVE) and close the site.

Phase 1 activities were completed during the Fall of 1993. Phase 2 activities were started inNovember of 1993 and completed in November 1994. The results of Phase 2 drum removal activitiesare discussed in the Phase 2 Report for Drum Excavation and Removal dated July 18,1994. Phase 3predesign activities have been completed and are presented in the Phase 3 Predesign Report. Phase 3activities included several predesign activities including a soil vapor survey and a soil vapor extraction

pilot study. The soil vapor survey identified areas of elevated vapor concentrations at the site with thehighest concentrations occurring in the central portion of the site which corresponded to areas to where

buried drums were found and removed Based upon the results of the SVE pilot study, it was concluded

that SVE was not a feasible remediation technology due to the soils at the site not being of sufficientpermeability to allow adequate air flow through the geologic structure. Based on the conclusions of thepredesign activities, it was decided that a solid waste composite cover will be designed and constructed

2049-007-930 1-1

Page 7: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TOWN OF FRANKLINWISCONSIN

LembergerSites

SUNNY SLOPE RD.

T SAN RD. .WHITELflW

LEMBERGERLANDFILL

LEMBERGERTRANSPORTRECYCLING

MA1COUAPIRNIE

LEMBERGER SUPERFUND SITESSITE LOCATION MAP I FIGURE

1-1

Page 8: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

at the site, in accordance with NR 504 Wis. Adm. Code. The Phase 2 and 3 reports are listed in thefollowing subsection as Reference Documents and are discussed in Section 2 of this report.

The Lemberger Transport & Recycling Site Closure System Final Design Report is composedof the following sections:

• Section 1.0 - Introduction and Background• Section 2.0 - Site Description

• Section 3.0 - Landfill Closure Design Components

• Section 4.0 - Required Permits, Licenses and Approvals

• Section 5.0 - Cost Estimate• Section 6.0 • Construction Schedule• Section 7.0 - Health and Safety Plan

1.2 BACKGROUND

The LTR Site is located southwest of the intersection of Hempton Lake Road and Sunny SlopeRoad in Manitowoc County, Wisconsin, in the northeast quarter of Section 34, Township 20 North,

Range 22 East The size of the LTR Site, as defined during Phase 1 remedial activities, is approximately49 acres, with an estimated 16 acres of the LTR Site used for industrial waste disposal.

In 1969 the Wisconsin Department of Natural Resources (WDNR) issued a license for thenearby LL site as a sanitary landfill. The LTR Site operated under the same license issued by the WDNR

for the LL site and accepted industrial waste which was diverted from the LL site and other landfills.The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill

license.LTR Site records indicate that between 1969 and 1977 industrial wastes, including drums and

a variety of liquids, sludges and slurries, were deposited into trenches at the site. Records of waste types

and quantities were maintained, although no records were kept regarding the types of waste depositedin specific trenches.

In September 1984, the LTR Site was added to the National Priorities List (NPL) and the

USEPA became the lead regulatory agency.

Additional site background information is detailed in the following documents:• Reference Document 1: Final Remedial Investigation (RI) Report, January, 1991.

• Reference Document 2: LTR Site Source Control Operable Unit, Remedial

2049-007-930 1-2

Page 9: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Investigation Technical Memorandum (RTTM), dated October, 1992.• Reference Document 3: Administrative Order by Consent for Source Control Activities,

executed by the USEPA on July 15,1993.• Reference Document 4: Phase 2 Report for Drum Excavation and Removal, July 18,

1994.

• Reference Document 5: Phase 3 Predesign Report, February 17,1995.

13 PURPOSE AND CONTENTS OF THE FINAL DESIGN REPORT

The purpose of the Final Design Report is to present the details for the Phase 3 remedial action.

The design of the Phase 3 remedial action was initially structured to have two main components: the soilvapor extraction system and a landfill cap. As discussed in the Phase 3 Predesign Report, SVE is not

a viable remedial technology at this site. Without SVE the USEPA has required construction of a

composite cap meeting the requirements of NR 504.07, Wis. Adm. Code.

The Final Design Report includes the following items:

• Design Criteria;

• Construction specifications prepared in accordance with Construction SpecificationsInstitute format;

• Engineering drawings identifying existing Site conditions and an illustration of thework to be constructed.

• Cost Estimate;

• Construction Schedule;

• and Health and Safety Plan.

The Final Design Report incorporates comments from the USEPA regarding the Prefinal DesignReport.

2049-007-930 1-3

Page 10: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

2.0 SITE DESCRIPTION

2.1 TOPOGRAPHY

The topography of the LTR is characterized by west-northwest sloping terrain, which is

relatively flat on the west side of the site and has steeper slopes to the east. The rolling to hilly terrainis characterized by glacial deposits and variable bedrock topography. The LTR Site is in the Branch

River drainage basin which lies less than one mile to the northwest of LTR. Elevations range from 870

feet in the northeast to 852 feet on the west portion of the site. Slopes to the east range from 2 to 10percent, and slopes of 0.1 to 3 percent exist to the west. A drainage ditch with flow directed westward

along Sunny Slope Road borders the site to the north.

2.2 REGIONAL GEOLOGY

The study area is underlain by a bedrock of dolomitic limestone, the Niagara Limestone, over

which lies a buried glacio-fluvial valley. Bedding trends (slopes) northwest with a bedrock ridgeculminating at the southeast corner of the site. The southeastern wall of the glacial valley rises to meetthe bedrock ridge at the east and south edges of the area. The valley has been filled with glacial deposits.

Most of the glacial sediments fill the broad, flat bedrock valley and are more or less flat lying. Along

the valley wall, however, where the bedrock forms the topographic ridge line, the sediments follow theslope of the wall and in some cases pinch out at the higher elevations. This is particularly evident at thearea immediately south of the LTR Site.

The lowermost unit of interest to this project is the uppermost 30 to 80 feet of the NiagaraLimestone. This is the deepest unit exhibiting contaminants in the ground water. Overlying thelimestone are an outwash sand and gravel unit (the LGU), a clay till unit (the cohesive unit or CU), andlocally a unit of combined glacio-lacustrine and glacio-fluvial deposits (the UGU).

The UGU is medium to well-graded, loose to medium-dense and consists of sand to gravel sizedgrains. The thickness of the UGU varies over the LTR Site from non-existent in the southeast, wherebedrock elevation is high, to 11 feet in the west-northwest, where bedrock is well below the surface.

The CU is firm to hard and composed of particles ranging from clay to silt-size. This glacio-lacustrine deposit is randomly interbedded with coarse-sand to gravel erratics. The thickness of the CU

2049-007-930 2-1

Page 11: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

varies over the LTR Site from 10 feet along the northern boundary to 2 feet at the southern border, whereit exists as a thin layer over the raised bedrock.

The LGU is well-graded, dense to very-dense and is composed of sand to gravel sized grainswith minor interbedded silts and clays. The lower LGU contains cobble to boulder-sized fragments ofweathered bedrock, which increase in volume with depth and proximity to the bedrock surface. Thethickness of the LGU varies across the LTR Site from not encountered over the bedrock ridge in thesouth, to 16 feet in the northwest portion where bedrock is low.

The Silurian-age Niagara Formation comprises the bedrock which underlies the unconsolidatedPleistocene deposits. It is a thick to massively-bedded, dolomitic fossilifcrous-limestone. Solutioncavities containing precipitate calcite are common throughout the unit. It ranges in thickness across theLTR Site from 2.5 feet in the southeast corner to 30 feet in the northwest corner.

2J HYDROGEOLOGY

Two aquifers are found in the study area. The regional aquifer, known locally as the LowerGroundwater System (LGS) consists of the bedrock and the overlying sand and gravel unit (the LGU).A perched aquifer locally occurs in the UGU, in the northern portion of the LTR Site. The regionalaquifer occurs beneath the entire study area.

Ground water elevation contours from 1990 show ground water flow is from the divide, whichruns along the ridge line in the east and south, toward the Branch River in the northwest. Because of theL-shaped configuration of the ridge and its orientation with respect to the river, the direction of groundwater flow varies locally depending upon the location within the study area. Generally, flow directionlies between westward and northward.

The water table in the regional aquifer is found in the limestone bedrock beneath the ridge linesin the east and south. As the bedrock slopes downward away from the ridge to the northwest, the glacialsediments occur at lower and lower elevations until the water table is found within the LGU. Still fartherfrom the ridge, the top of the LGU slopes further downward, with the result that the water table is foundin the overlying clay till (the CU). This results in a transition from unconfined to confined conditionsacross the study area, from the southeast to northwest.

Because of these widely varying conditions, the pattern of ground water flow is complex. Mostof the recharge occurs along the ridge line, where the layer of relatively impermeable clay till is thethinnest, or absent. This mounds the water table beneath the ridge, forming the ground water divide.

2049-007-930 2-2

Page 12: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Lateral flow is then towards the river. However, in the vicinity of the bedrock ridge, ground water flowslaterally from the bedrock into the LGU. Even though vertical gradients are generally downward in theLGU and bedrock, the unusual geometry of the LGU proximal to the bedrock face along the ridge in the

southeastern portion of the study area results in recharge to the LGU from the bedrock along the edgeof the ridge line, south and east of the LTR Site.

The perched aquifer occurs in the UGU and occurs in the southern portion of the LTR Site. Theaquifer is drained by two wetlands along its western margin; therefore, flow is from the northern, easternand southern portions of the aquifer towards the western margin.

There appears to be little, if any, vertical communication with the regional aquifer. Water levelsin the two aquifers differ by 30 to 40 feet There is an unsaturated zone of as much as seven feet of sand

and gravel at the top of the LGU. There is potential for some movement along fractures in the till, butfractures identified in boring samples were limited to the upper portion of the till, and did not penetrate

the full thickness of the unit. In any event, there is insufficient ground water flux through the till tosaturate the upper portion of the LGU. There is no evidence of a mounding effect that would be

indicative of recharge from the UGU to the LGU. Consequently, vertical flow between the aquifersappears negligible.

2.4 SUMMARY OF THE NATURE AND EXTENT OF CONTAMINATION

Numerous investigation reports have been prepared for the LL and LTR Sites, addressing thenature and extent of contamination and its potential impact to the surrounding area. A list of the

Lemberger LL and LTR Site reports, authors, and submittal dates is included in Table 2-1. Results ofprevious investigations at the LTR Site are discussed in Reference Documents 1 thru 5, as identified inthe Section 1 of this Report. Results of the LTR Site Source Control Operable Unit, RemedialInvestigation Technical Memorandum (RITM) - Reference Document 2 are summarized below.

The RITM subsurface investigation of test pits and test borings identified fill soils (silt, sand,day and gravel) intermixed with varying amounts of roots, wood, concrete, brick fragments, scrap metal,and, at some locations, a black tar-like substance with a burnt wood/charcoal odor. The investigationshowed that potential sources of contamination existed at most of the test pit and test boring locations.

Test pit and test boring fill material samples were collected during the LTR investigation for analyses.Results from the test pit sample analyses indicated the presence of volatile and semi-volatile organiccompounds. A number of pesticides were identified from the pcsticides/PCB analyses.

2049-007-930 2-3

Page 13: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 2-1SUMMARY OF PREVIOUS INVESTIGATIONS AND REPORTS

LEMBERGER TRANSPORT AND RECYCLING, INC. SITE

INVESTIGATION OR REPORT

Preliminary In-Field Conditions Analysis ofthe Closed Transport Recycling Inc Land-fill, Manitowoc County, WI

Environmental Investigation Report,Closed Transport Recycling Inc. Landfill,Manitowoc County, WI

Preliminary Remedial InvestigationFranklin Township, Manitowoc County,WI

Ongoing Investigation of ContaminatedPrivate Wells, Franklin Township, WI

Report of Investigation, Well Pollution byLandfills Located in Franklin Township,WI

Work Plan for Remedial Investiga-tion/Feasibility Study at die LembergerTransport and North Landfill Sites,Manitowoc County, WI

Final Remedial Investigation Report forLemberger Landfill, Inc. Site andLemberger Transportation and Recycling,Inc. Site

Lemberger Transport and Recycling, Inc.Site Source Control Operable Unit Re-medial Investigation Technical Memoran-dum

Geophysical Survey Results at the Lemb-erger Transport and Recycling Site

PREPARED BY

Residuals Management Technology, Inc.

Foth & Van Dyke and Associates Inc.for Lemberger Landfills, Inc.

Soils Exploration Company for WDNR

Wisconsin Department of Natural Re-sources

Ayres Associates, Inc. for Radosivich,Mozinski, Mozinski & Cashman

Residuals Management Technology, Inc.for USEPA, Region V

B & V Waste Science & TechnologyCorporation for USEPA, Region V

B & V Waste Science & TechnologyCorporation for USEPA, Region V

Geosphere Midwest, Inc.

DATE

August 1981

May 15, 1982

September 12, 1985

December 1984 topresent

March 1986

September 1986

January 18, 1991

October, 1992

October, 1993

Source for Early Reports: Final Remedial Investigation Report, January 18, 1991.

Page 14: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Subsurface soil samples were also collected and submitted for chemical analyses during the

R1TM subsurface investigation at the LTR Site. Nine inorganic compounds were detected atconcentrations exceeding established background levels. Calcium and magnesium were mostconsistently encountered and lead was detected at the highest concentrations above background, ranging

from 15 to 119 mg/kg. Concentrations generally varied from less than two times to ten times the

background levels.In addition to the fill material and soil samples collected during the RITM investigation, a liquid

sample was collected for analysis from one of two drums excavated from the LTR Site. Analytical

results from the drum sample indicated the following levels of volatile organics and metals: 49,000 partsper million (ppm) 4-methyl-2-pentanone, 23,000 ppm 2-butanone, 280,000 ppm toluene, 22,000 ppmethylbenzene, and 140,000 ppm total xylene; and 120 ppm lead, 4.5 ppm chromium, 4 ppm barium, and27 ppm zinc. The contents of the sampled drum had a flash point of 54 degrees Fahrenheit and a pH ofapproximately 4.5. Based on the results of previous investigative findings, the USEPA determined that

an actual or threatened release of hazardous substances from the LTR Site may present an imminent andsubstantial endangerment to public health, welfare or the environment.

2JS PREVIOUS RD/RA ACTIVITIES

2.5.1 Phase 1 Site ActivitiesThe Phase 1 Site Activities at the LTR Site included a site boundary survey, a geophysical

survey and fence construction. A site boundary survey of the LTR Site was conducted as part of thePhase 1 remedial action activities, before initiation of the geophysical survey and construction of aperimeter fence. The site boundary survey was based on results from the RI and verified in the field byrepresentatives of the USEPA and WDNR. Representatives from the USEPA and WDNR were presenton-site during the survey to verify and approve the location of comer stakes by the surveyor. This surveywas conducted to define the boundaries of the LTR Site for future remedial action activities.

The LTR Site (defined during the Site Boundary Survey) was surveyed with a Geonics EM-31DL electromagnetic instrument Readings were taken digitally at 2.5 foot intervals along lines spaced10 feet apart The close spacing is necessary to identify anomalies caused by objects the size of a singleburied 55-gallon drum. A 100 by 100 foot grid was surveyed and marked prior to the survey. Additionalflagging at 20 foot intervals in one direction was placed at the start of the survey. Data point locations

were interpolated in the field using the grid stakes and flags. Data interpretation was presented in a

2049-007-930 2-4

Page 15: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

report prepared by the geophysical subcontractor, Geosphere Midwest and a map of subsurfaceconductivity anomalies was prepared from the data collected during the survey.

A fence was constructed along the entire length of the LTR Site boundary (defined during thesite boundary survey). The fence around the LTR Site consists of a minimum 6-foot-high chain link.The fence includes one 12-foot wide double swing gate with appropriate locking mechanism alongSunny Slope Road Warning signs were posted at 200 foot intervals along the fence and at the gate. Thewarning signs advise that the area is hazardous due to the presence of chemicals in soil and ground waterwhich may pose a risk to public health through direct contact or ingestion. The signs also provide atelephone number to call for further information.

2.5.2 Phase 2 Drum Excavation and RemovalThe objective of the Phase 2 work at the LTR Site was to excavate, classify, and properly

dispose of drums and the associated hazardous materials within the drums. Westinghouse RemediationServices (WRS) was contracted by the LSRG to perform the Phase 2 activities. These activities includedexploratory trenching, excavating drums, sampling and analysis of drum contents, and transportationand disposal of drums and their contents. Malcolm Pirnie provided oversight during the excavation,classification and disposal activities on behalf of the LSRG. The findings and conclusions for Phase 2activities are presented in the Phase 2 Report for Drum Excavation and Removal, dated July 18,1994.

WRS conducted exploratory trenching at the LTR Site between December 3 and December 15,1993. Excavation and staging of drums was initiated December 13,1993; all Phase 2 activities werecompleted by November 5, 1994, except for the transportation and disposal of approximately 16compressed gas (valved) cylinders found during the investigation. Approximately 1,380 drums, 99compressed gas cylinders, and 180 small laboratory reagent containers were excavated during the Phase2 activities. Figures 2-1 and 2-2 indicate the areas at the LTR Site where drums and cylinders wereexcavated, respectively. Table 2-2 lists the number of drums recovered from individual anomalies.

2.5.3 Phase 3 Predesign ActivitiesThe Phase 3 Predesign Activities included conducting a soil vapor survey and a soil vapor

extraction pilot study. The work plan for the predesign activities was conditionally approved by USEPAon October 17,1994. The soil vapor survey and soil vapor extraction pilot study were completed bycarry November, 1994. The results of the soil vapor survey and the pilot study demonstrated that SVEis not a viable remedial technology for the LTR Site. The results of these activities have been completed

and are detailed in the Phase 3 Predesign Report dated February 17,1995.

2049-007-930 2-5

Page 16: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

•«• MOO MOO MOO tMO t«00 (IL ' ' ' '"™* MOO

I I•

•i r ^ '"y, 1;/I e> ™

! tA "" |-

~5 ,*••" !-*> ***" j-f a* v* t:

H *fc \I Jl-

r M «*i ev* ^7te* •> 2

-1 f •" ,,f !fi »» 5I-;. T r -:1 I

I !1 1400 MOO MOO WOO tWO f4« |«QO MOO1 1 I 1 1 1 I 1 1 1 1 1 1 1 1 1 ._ J 1 _l I 1 I 1 1 1 1 1 1 , J1 Grid tasting (feet)

SOURCE: Geo6pher« MWweel. Inc. 'Geophysical Survey Results * °" *ur n <rv* p<"-t*/uwn«an*the Umbe<0er Tr«nspod end RecycHng Site. October 1993.

MAIGDLM ANOMALY LOCATIONS WHERE DRUMS WERE FOUND FIGURE 2-1PiRNIE LTRSITE

Page 17: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

•400 MOO IMO"11000

I

I

0 -

O

I

1400I I

MOO tooo tm1 i i i i——I—I——I——I——L

1*00• I • ' I I I ' •

I Grid Eastinc (feet)

SOURCE: G*o«phtftMldw««.lnc. 'Geophysical SurvtyResuRstfIho L4>mb«xo«f Transport and RacycHng Sflo. Oclob«r 1993.

Contour M(crv«l

PIRNIEANOMALY LOCATIONS WHERE CYLINDERS WERE FOUND

LTR SITE FIGURE 2-2

Page 18: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 2-2NUMBER OF DRUMS REMOVED BY ANOMALY AREA

Area

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

No. ofDrums

*

NT

1

1

1

*

*

*

NT

23

*

0

3

*

0

1

*

NT

Area

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

No. ofDrums

i l l

NT

9

3

1

1

*

NT

*

*

*

*

*

1

*

*

*

*

Area

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

No. ofDrums

*

0

*

*

*

*

NT

NT

*

21

1

NT

14

8

NT

1

1

1

Area

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

No. ofDrums

1

12

1

*

NT

16

NT

NT

42

NT

NT

NT

NT

NT

NT

47

3

*

Area

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99

100

No. ofDrums

**

NT

NT

NT

74

79

NT

57

NT

NT

215

200

8

13

NT

94

NT

NT

NT

Area

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120

No. ofDrums

i*

*

NT

1

26

*

*

NT

67

»

145

NT

1

2

*

*

Area

121

122

123

124

125

126

127

128

129

130

131

132

133

134

No. ofDrums

4

NT

»

*

4

*

NT

60

*

*

4

»

"Drums" are overpack drums with: 1. One 55 gallon or 35 gallon buried drum, or; 2. Several small containers or crushed empty drums within.NT- Anomaly area not trenched due to its size being equal to or less than 10 feet in diameter (see Final Phase 2 Work Plan, Section 2.3.4 1).* - Anomaly area trenched but no buried drums found.1, 125, 1 and 99 gas cylinders were found in anomaly areas 31, 33, 45, and 93, respectively.

Page 19: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

2.5.4 Operable Unit 1 ConstructionRemedial action activities are being implemented which include the collection and treatment of

contaminated groundwater from the vicinity of both die LL and LTR Sites. There will be some disposalof wastes at LTR before closure activities at the LTR Site commence resulting from other remedialactivities being conducted for the Operable Unit 1 Source Control. Certain of the OU1 remedial action

activities which specifically involve the LTR Site. They include the following:

1. Collection Trench - This trench and associated sump is designed as part of the groundwater treatment system for OU1 to collect shallow groundwater through a perforatedpipe buried in an interception trench for conveyance to a groundwater treatment facilitybeing built south of LL. The trench extends 7 to 11 feet below ground surface and will

be located 20 feet south of the north-side LTR fence. It will run east-west from 100

feet west of Monitoring Well RM-7S to 700 feet east of Well RM-7S for a total length

of 800 feet The trench will be backfilled with crushed stone 3 to 4 feet below ground

surface and then with clay to the surface. [Note: This design is subject to change based

on new subsurface information.]

2. Thin Spreading of Investigation Derived Wastes at LTR - During earlier work by

others, free liquids were pumped, to the extent possible, from 99 drums that were

stored within the fenced Investigative Waste Storage Area in the southeast corner of

LL. The contents of these drums are primarily investigation derived waste and somemiscellaneous debris such as wood and personal protective equipment from previous

activities at the Sites. Drums containing soils and boring cuttings that may still retainsome liquids will be transported to LTR, where any free water will be dewatered on an

earthen dewatering pad underlain by a 40 mil HOPE liner. Following dewatering, thecontents of the dewatered drums and the contents of drums not containing free liquids

will be thin-spread on the LTR Site. Drill corings and sample jars and their contents

also located in the fenced area at LL will be disposed by transporting them and thin-spreading on the LTR Site in designated areas. These materials will immediately be

covered with a minimum of six inches of select fill by the OU1 Contractor. The

designated disposal areas will be marked in the field. Placement of the grading layer

component of the cover will be conducted so as not to excavate or expose the above-

2049-007-930 2-6

Page 20: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

described wastes. Once the grading layer is placed, no disturbance of the those wastesis expected

Material excavated from the ground water collection trench will be stored on the LTRSite and covered with plastic and sampled for hazardous constituents in order todetermine appropriate disposal alternatives. If not considered hazardous, the material

will be immediately thin spread on the LTR Site. If considered hazardous, the materialwill be left stockpiled with the plastic covers with surface run-on controls in-place. Thematerial will be thin spread later on the LTR Site during construction of the gradinglayer of the LTR cover. Any saturated spoils removed from the trench would likewisecontain listed hazardous waste. The saturated spoils will be dewatered at a dewatering

pad constructed at LTR and then added to the stockpile with the unsaturated materialsexcavated from the trench. Also to be disposed of at the LTR Site are the componentsof the dewatering pad which will include the 40 mil HOPE and its base of sand andcoarse aggregate. Water from the dewatering operations at LTR will be disposed of bythe OU1 construction contractor.

3. Installation of Extraction and Monitoring Wells - The remedial action associated withOU1 also includes the installation of extraction and monitoring wells at the LTR Site.Extraction Well EW-1D will be located in the northwestern portion of the LTR Site.

This is near the major source of contaminants to the regional aquifer, and its purposeis to remove the most heavily contaminated groundwater and provide source control.Located near Well EW-1D are several observation wells including OW-101A, OW-101B, RM-7XD, RM-7D, and RM-7S. These wells are not located where the cover

will be constructed. There are several existing monitoring wells which are locatedwithin the area to be covered or very close where construction may affect them. Theseinclude RM-2091D, RM-303D, RM-304D, RM-305D, RM-306D, OW-2B, OW-4,OW-5, OW-6, OW-7, and OW-8. The construction contractor will be required to

protect the wells from construction activities and to raise those within the area to becovered so that they protrude through the new cover for continued use.

2049-007-930 2-7

Page 21: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

3.0 LANDFILL CLOSURE DESIGN COMPONENTS

3.1 INTRODUCTION

This section of the report discusses the design features required to close the LTR Site and

represents the Final Design based upon existing site information. The design features discussed in thissection are structural regrading, final cover structure and placement, stability, final cover vegetation,

storm water management and erosion control, and a landfill gas venting system. The closure design willbe constructed in compliance with NR 504.07, Wis. Adm. Code. The final grading plan, cross-section

and details of the closure system are provided in the Final Design Drawings.The capping of the landfill will be accomplished by first performing regrading of the landfill to

attain a minimum slope of two percent and to provide a stable base for subsequent cover components.The cover structure will include a 24 inch composite clay and geomembrane cap with gas control,drainage and cover layers for protection. The cover structure will be uniform throughout the site, withslopes ranging between 2 to 6 percent, however at the perimeter of the landfill the slopes increase to

approximately 33%. The individual components of the closure system are discussed in subsequentparagraphs. They are listed in order from the bottom to the ground surface.

3.2 PURPOSE OF THE CLOSURE SYSTEM

The purpose of final cover placement is to minimize surface water infiltration to ground water,

control surface water runoff, control landfill gas and odors, and support vegetative cover. The reductionof surface water infiltration will reduce the quantity of leachate generated. The cover for the LTR Site

will achieve these objectives by the placement of a capping system which combines several different soil

layers and a synthetic geomembrane designed to: 1) support vegetation and landscaping; 2) protect thecomposite barrier layer from physical damage; 3) protect the barrier layer from frost damage; 4) controlsurface water runoff and protect the upper layers of the cover system from erosion; 5) restrict surface

water from entering the waste mass (thereby reducing leachate generation); and, 6) control venting of

landfill gases.

2049-007-930 3-1

Page 22: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

3.3 CONSTRUCTION OF THE CLOSURE SYSTEM

The general procedures for construction of the final cover and capping system is included in this

section. The individual components of the cover are then described in the following sections.

• The contractor will regrade existing cover soils and place general fill as subgradematerial as necessary to achieve the design grades of the cover subgrade.

• The contractor will place the 12 inch gas control and foundation layer along with gasvents and the lower geotextile filter fabric as required to reach the intermediate gradingcontours as close as practical with the least amount of excavation possible.

• The contractor will place and compact the 24 inch thick clay barrier layer above thelower geotextile filter fabric.

• The contractor will place the synthetic geomernbrane liner on the surface of the claybarrier layer and install the gas vent risers, as required.

• The contractor will place the 12 inch thick drainage layer and then the upper geotextilefilter fabric as required.

• The contractor will place 30 inches of general fill as cover soil above the uppergeotextile filter fabric.

• The contractor will spread six inches of topsoil followed by the vegetative cover andseeding.

• The contractor will shape the final grades as necessary to conform to requirements ofthe Contract Documents and provide required drainage structures.

• The contractor will seed and vegetate the cap surface.

Quality assurance and quality control procedures will be followed during the construction, asdescribed in the Technical Specifications and the approved Final Construction Quality Assurance Planprepared by Malcolm Pimie. Data from the construction contractor's proposed clay borrow source willbe provided to the USEPA and WDNR in the form of a clay borrow source report meeting therequirements of s. NR 512.18, Wise. Adm. Code for review and approval after construction bids arereceived and prior to notice-to-proceed.

3.4 COMPONENTS OF THE COVER SYSTEM

3.4.1 Grading Layer

The existing landfill cover consists of silty, sandy, clay materials that were imported from a

2049-007-930 3-2

Page 23: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

local borrow site. The present cover of the landfill has been significantly disturbed by trenching anddrum removal activities which were conducted in late 1993 through spring 1994. Existing covervegetation consists mainly of native grass species with barren areas throughout the landfill. Slopes of

the present landfill vary between less than 1 percent in the southwest comer of the landfill to S percentin the northeast corner. The existing landfill cover has no planned erosion control devices such as

diversion swales or downchutes, therefore any runoff and sediment from the landfill arrives unchecked

to a wet area located at the northwest comer of the site. Existing topsoil, if any, is of poor quality andwill not be removed and stored for later use as topsoil described in Section 3.4.9.

The Final Design Drawings and Technical Specifications, bound separately, detail the modifica-

tions to the existing grades. The primary purpose of the grading layer is to reshape the surface of thelandfill to the contours shown on the subgrade plan (Drawing CD-2) while providing a minimum of 6

inches of clean, imported general fill over the entire landfill surface. In most locations, the thickness ofgeneral rill will exceed the minimum of 6 inches in order for the desired contours to be attained. In areaswhere the presently existing surface elevations equal or exceed the desired grading plan elevations(shown as "Proposed Cut Areas" on Drawing CD-2), the present surface will be cut at least 6 inchesallowing a minimum of 6 inches of general fill to be placed in order to meet the desired elevation.

The contractor will be allowed to use soil from cut areas including topsoil as fill for areasrequiring fill (shown as "Proposed Fill Areas" on Drawing CD-2) in order to assist in meeting the

grading plan contours. However, a minimum of 6 inches of the imported general fill will still be required

above this relocated material to provide cover and to meet the grading plan contour elevations.Reshaping of the landfill surface will result in a minimum slope of 2 percent and a maximum

of 6 percent except for the side slopes. The new side slopes are designed to be between 20 and 33percent, to follow the existing ground as close as possible, and to minimize earth work. Approximately

51,000 cubic yards of imported fill will be required to attain the desired slopes and contours.Calculations deriving this volume are given in Appendix A. The grading layer will form the base forthe 12 inch thick gas control and foundation layer. The top of the gas control and foundation layer will

form the contours of the intermediate grading plan (Drawing CD-3) over which the clay layer will beplaced

3.4.2 Gas Control and Foundation LayerThis layer is designed to allow conveyance of gases which may include volatile organics to the

gas venting system with subsequent emission to the atmosphere. It will be placed immediately above

2049-007-930 3-3

Page 24: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

the grading layer in 12 inch (after compaction) lifts. The gas control and foundation layer will consistof 12 inches of sand with a minimum coefficient of permeability of 1 x 10'3 cm/sec and be obtained from

an off-site source. This material will be classified as SP based on the Unified Soil Classification System

with no individual particle size being greater than 1/2 inch. The percent fines, particles less than 0.0074

mm, will be less than 10% by weight of the total weight. The soil for the gas control layer shall becompacted to not less than 95% of the maximum index density in accordance with ASTM D 4253 (1991

Edition). The contractor will be required to perform in-place density testing to determine the degree ofcompaction. A minimum of 5 density and moisture tests using a nuclear densitometer shall be performedper acre per lift of completed layer to verify in-place density.

3.4.3 Lower Geotextile Layer

A layer of geotextile filter fabric will be used to separate the clay barrier layer from theunderlying gas control and foundation layer. The primary purpose of this fabric is to provide physicalseparation of clay particles and the soil of the gas control and foundation layer. Separation will berequired to prevent clogging of the intersticial pathways in the gas control layer, thereby allowing the free

flow of gases through that layer. Geotextile filter fabric shall be needle punched, non-wovenpolypropylene fabric composed of filaments formed into a stable network such that the filaments retaintheir relative position. The fabric shall be inert to biological degradation and naturally encounteredchemicals, alkalies, and acids. Average minimum values for the filter fabric's apparent opening sizeshall be 0.3 mm and a typical thickness of 55 mils. The contractor will be required to prevent damage

to the underlying gas control layer during placement of the fabric. In addition, the contractor will be

required to not expose the fabric to precipitation and construction traffic prior to its installation and to

place the fabric on a smooth, dry surface. Fabric will be overlapped by 12 inches with overlaps orientedin the direction of earth filling.

3.4.4 Gay Barrier LayerTwenty-four inches thick of clay barrier will be placed above the lower geotextile layer. The

clay will have a classification of CL or CH soil based on Unified Soil Classification System and havea maximum recompacted permeability of 1 x 10"7 cm/sec. The permeability test results will include anassessment of whether the field construction procedures specified are able to achieve the specifiedpermeability. The Plasticity Index will in no case be less than 12% on average for all samples or lessthan 10% for individual samples for clay placed as part of the final cover construction and documented

2049-007-930 3^1

Page 25: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

in accordance with NR 516, Wis. Adm. Code. The Liquid Limit will in no case be less than 25% onaverage for all samples and less than 20% for individual samples for clay placed as part of the final coverconstruction and documented in accordance with NR 516, Wis. Adm. Code.

Clay to be used will have a clay content of 25% by weight or better and a minimum of 50% byweight shall pass the No. 200 sieve. The contractor will be required to secure the clay from an off-sitelocation. At the borrow source, testing will be employed to confirm that the clay material complies with

minimum requirements. Ten test pits or borings for the first 5 or less acres and one test pit or boring for

each additional one or less acre shall be excavated or drilled on a uniform grid pattern across eachproposed borrow source to document the depth, lateral extent and uniformity of acceptable material.Logs identifying the geologic origin, testing results, USCS classification and a visual description of eachmajor soil unit encountered shall be maintained. A minimum of 2 representative samples from each testpit or boring shall be collected and tested in soils testing laboratory for grain size distribution to the0.002 millimeter particle size and for Atterberg limits. A minimum of 5 representative samples for the

first 10 or less acres and one additional sample for each additional 5 or less acres shall be tested for the

relationship of water content to dry density using the modified or standard Proctor method. A minimum

of 20% of the samples used to develop the Proctor curves will be used to evaluate the relationshipbetween compaction and hydraulic conductivity by testing the sample corresponding to each pointestablished on the chosen Proctor curves for hydraulic conductivity.

The degree of in-place compaction of the clay barrier layer will be determined by having thecontractor conduct a minimum of 5 density and moisture tests using a nuclear densitometer on a 100-footgrid pattern per acre per lift of completed clay barrier layer. The soil shall be compacted to not less than90% of the Modified Proctor maximum density or as needed to meet the permeability requirement of 1

x 10'7 cm/sec.One moisture-density curve shall be developed for every 5,000 cubic yards or less of clay placed.

At least 5 points shall be established on each curve. A representative sample for every 5,000 cubic yards

or less of clay placed shall be analyzed for grain size distribution through the .002 millimeter particlesize and for Atterberg limits. The contractor will be required to perform 1 additional moisture contenttest per acre of the previous lift before placement of additional lifts. If evidence of desiccation (drying)

cracks is noted, the affected area shall be scarified to the depth of the cracks, moistened to specifiedmoisture content, recomputed and retested to meet all requirements of the specifications.

A minimum of one undisturbed sample for each acre or less for each lift of clay placement shallbe retrieved and analyzed by the contractor's testing laboratory for Atterberg limits, grain size

2049-007-930 3-5

Page 26: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

distribution through the 0.002 millimeter particle size, moisture content and dry density. Laboratoryhydraulic conductivity tests using the falling head method shall be performed on every third undisturbedsample. The maximum allowable in-place soil permeability for the barrier layer shall be 1 x 10'7 cm/sec.

The clay barrier layer will be constructed in segments so that all work on each segment iscomplete by the end of the construction season. The contractor will be required to protect the completed

and approved clay from freezing, erosion, and desiccation. The first lift of the clay barrier layer will beconstructed in a 9 inch maximum (before compaction) lift. The rest of the clay barrier shall be

constructed in a 6 inch maximum (after compaction) lifts, for a total minimum thickness of 24 inches.

The top inch of each completed and approved lift shall also be scarified prior to placement of successivelayers. The compaction equipment shall be a sheepsfoot type compactor to compact the lifts of the claybarrier layer to not less than 90 percent of the modified proctor maximum density as determined by theModified Proctor Compaction Test, ASTM D 1557. Material shall be mixed and spread in a mannerto assure uniform lift thickness after placement. The contractor will be required to construct finished

elevations for each layer of the cover system true to within a tolerance of zero inches to plus 2 inches of

final design thickness. The moisture content of materials utilized in the clay barrier layer shall bemaintained at or above the optimum moisture content during placement. When necessary, moisture willbe added using approved sprinkling equipment. The placement or compaction of clay material will notbe permitted during rainfall. Construction of the clay barrier layer will be conducted in such manner thata minimum of rain water will be retained thereon. Compacted material that is damaged by washing shall

be replaced by the contractor in an acceptable manner.

3.4.5 Geomembrane Layer

A high density polyethylene liner will be placed immediately above the clay barrier layer. The

clay barrier layer and the overlying HDPE geomembrane liner will be the key components of thecomposite cover for the LTR closure system. The flexible polyethylene membrane liner will bemanufactured from pure resins supplied by only one manufacturer such as Gulf HD9642 or Phillips TR

400 Resin having a density of 0.940 g/cm3. Materials used to manufacture the polyethylene liner willbe formulated from appropriate polymers and compounding ingredients to form a polyethylene sheetmaterial meeting all requirements for use as a liner for a waste landfill. Material that is capable of beingbonded to itself by thermal bonding will be used The liner will be manufactured to the minimum design

thickness of 60 mils. For the LTR closure system, extruded sheets will be at least 10 feet in width.

Table 3-1 provides certain physical properties required for the polyethylene material used for the LTRSite.

2049-007-930 3-6

Page 27: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 3-1PROPERTIES OF HOPE LINER MATERIAL

PROPERTY

1. Thickness

2. Specific Gravity Method A

3. Melt Flow Rate Condition E

4. Low Temperature Brittleness

5. Coefficient of LinearThermal Expansion

6. Water Absorption

7. Shore D Hardness

8. Tear Resistance Tie C

9. Percentage Elongation at Yield

10. Percentage Elongation at Break

11. Tensile Strength at Yield

12. Modulus of Elasticity

13. Tensile Strength at BreakWidth

14. Carbon Black Content

TEST METHOD

ASTM D 1593

ASTMD792

ASTM D 1238

ASTM D 746 Procedure B

ASTM D 696

ASTM D 570

ASTM D 2240

ASTM D 1004

ASTM D 638*

ASTM D 638*

ASTM D 638*

ASTM D 688

ASTM D 638*

ASTM D 1248

VALUE

60

0.94

0.3-0.2

-112

2.0xlO'4

0.10

65

45

13

700

240

1.1

75

2Min.3 Max.

UNITS

mils minimum

g/cm3

g/lOMin

oF

oC-i

max. % wt change

Shore D

Ib. min

%

%

Ibs/inch width

psi

Ibs/inch

%%

2049-007-930

Page 28: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 3-1PROPERTIES OF HOPE LINER MATERIAL

PROPERTY TEST METHOD VALUE UNITS

15. Dimensional Stability %change, each direction,212 °F, 1 hr. ASTMD1204 ±2 % change

16. Resistance to Soil BurialASTM D 3083 (as modified inNSF Standard 54 Appendix A)

Max. change inorignial value Value

a. Tensile Strength YieldASTM D 3083 (as modified inNSF Standard 54 Appendix A) 10±

b. Tensile Strength atBreak

ASTM D 3083 (as modified inNSF Standard 54 Appendix A) 10±

c. Elongation at YieldASTM D 3083 (as modified inNSF Standard 54 Appendix A) 10±

d. Elongation at BreakASTM D 3083 (as modified inNSF Standard 54 Appendix A) 10±

e. Modulus of ElasticityASTM D 3083 (as modified inNSF Standard 54 Appendix A) 10±

17. Environmental Stress CrackASTM D 1693 (as modified inNSF Standard 54 Appendix A) 1500 Min. hours

FIELD SEAM REQUIREMENTS

1. Bonded Seam Strength ASTM D 3083Film Tear Bond

and 120 Ibs/inch min.

2. Peel Adhesion ASTM D 413Film Tear Bond

and 78 Ibs/inch min.

2049-007-930

Page 29: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Prior to laying the geomembrane liner, the contractor will be required to prepare the linersubgrade (clay barrier layer) so that it is a smooth surface free of stones, organic matter, irregularities,protrusions, loose soil, and any abrupt changes in grade that could damage the liner. In addition, the claybarrier layer will be free of desiccation cracking prior to liner installation. Prior to placement of

polyethylene liner, the liner subgrade will be inspected and approved for placement of the liner by thecontractor's liner installer or liner manufacturer who will document in writing the acceptability of thesurface for installation of the liner.

Placement of the liner sheets will be preplanned and shown on a layout plan provided toMalcolm Pirnie in advance for review and approval. The contractor will be required to minimize thelength of field seaming which will be shown on the layout plan. Placement of polyethylene liner sheets

will result in a good fit in all comers and grade changes, without bridging. Excessive slack will beavoided to minimize rippling of the liner during placement of overlying soil. The amount ofpolyethylene liner unrolled and laid each day will be limited to the amount of liner that the contractor or

liner installer can properly seam during a one day operation.The contractor or liner installer will be required to prevent damage to the polyethylene liner or

underlying clay barrier layer by handling, wheeled or tracked vehicle traffic, leakage of hydrocarbons,or other means. A minimum of 12 inches of soil material will be provided between low pressure dozersand the polyethylene liner when spreading soil material. Any traffic by wheeled vehicles will be confinedto ramps of soil material at least 3 feet thick to prevent damage to the polyethylene liner.

A thermal fusion process will be utilized as the primary method of producing seams. Anextrusion fillet process will be used on patches, cross seams, or other areas where double seam thermal

fusion is impractical. Thermal fusion-welding apparatus to be used will be automated vehicular-mounteddevices producing a double seam with an enclosed space (hot wedge dual track). The seaming apparatus

will be equipped with gauges giving temperatures and pressures. The contractor or liner installer will

log ambient, seaming apparatus, and polyethylene liner surface temperatures as well as seamingapparatus pressures.

For the extrusion fillet process, welding apparatus will be equipped with gauges giving the

temperature in the apparatus and at the nozzle. The contractor or liner installer will providedocumentation regarding the polyethylene liner extrudate to Malcolm Pirnie and will certify extrudatetemperatures, ambient temperatures, and polyethylene liner surface temperatures at appropriate intervals.The extruder will be purged prior to beginning a seam until all heat degraded extrudate has been removed

from the barrel

2049-007-930 3-7

Page 30: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Seaming will extend to the outside edge of panels to be placed in the anchor trench. As required,a firm substrate will be provided by using a flat board, a conveyor belt, or similar hard surface directly

under the seam overlap to achieve proper support. Fishmouths or wrinkles at the seam overlaps will be

cut along the ridge of the wrinkle in order to achieve a flat overlap. The cut fishmouths or wrinkles willbe seamed and any portion where the overlap is inadequate will then be patched with an oval or round

patch of the same polyethylene liner material extending a minimum of six (6) inches beyond the cut inall directions. The liner installer will take samples from start and stop of each seam weld. Each sample

will be tested in peel and shear. All seams that fail will be reconstructed.The contractor or liner installer will make test seams on fragment pieces of polyethylene liner

to verify that seaming conditions are adequate. Such test seams will be made at the beginning of eachseaming period, at Malcolm Pirnie's discretion, and at least once every 4 hours, for each seaming

apparatus used that day. Also, each seamer will make at least 1 test seam each day. Test seam sampleswill be at least 2 feet long by 1 foot wide with the seam centered lengthwise. Two adjoining specimens,each 1 inch wide, will be cut from the test seam sample by the contractor or liner installer. Thesespecimens will be tested in the field by hand or tensiometer, and will not fail in the seam. If a test seamfails, the entire operation will be repeated If the second test seam fails, the seaming apparatus or seamerwill not be accepted and will not be used for seaming until the deficiencies are corrected and 2

consecutive, successful, frill test seams are achieved. Malcolm Pirnie will observe all test seamprocedures. The remainder of the successful test seam samples will be assigned a number and marked

accordingly by the contractor or liner installer, who will also log the date, hour, ambient temperature,

number of seaming unit, name of seamer, and pass or fail description. One sample will be labeled andsubmitted to Malcolm Pirnie to verify field test results by an independent laboratory. The contractor or

liner installer will be required to conduct both destructive and non-destructive testing as part of the fieldquality assurance program. A minimum of one sample per 500 feet of seam will be cut from the installed

polyethylene liner. Random specimens will then be cut from the sample. The specimens will then betested using the tests described above. The resulting hole will be patched by the contractor or linerinstaller with an oval-shaped piece of sheet material and thermally seamed in accordance with themanufacturer's directions. A log will be maintained by the contractor or liner installer for the purpose

of recording all test results. All destructive samples must pass the peel and shear tests. If a sample failsdestructive testing, the seam will be reconstructed between the location of the next acceptable sample;or the welding path will be retraced to an intermediate location at least 10 feet from the location of the

sample which failed the test, and a second sample taken for an additional field test. If this second testsample passes, the seam will then be then reconstructed between the location of the second test and the

2049-007-930 3-8

Page 31: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

original sampled location. If the second sample fails, this process must be repeated. For nondestructive

testing of seams the contractor or liner installer will use the vacuum box testing method or the air

pressure testing method to verify that the test procedures are valid. Nondestructive tests will beperformed by experienced personnel thoroughly familiar with the specified test methods and equipment

to be used and will be performed as the seaming work progresses. Vacuum box testing will be theprimary nondestructive test method on extrusion fillet welds. If it is not possible to test a fillet seam

using a vacuum box tester, air pressure will be utilized as the alternate nondestructive test method. Airpressure testing will be used to test thermal fusion welds.

All seams and non-seam areas of the polyethylene liner will be inspected for identification ofdefects, holes, blisters, undispersed raw materials, and any sign of contamination by foreign matter.Each suspect location, both in seam and non-seam areas, will be non-destructively tested using themethods described, as appropriate. Each location which fails the non-destructive testing will be markedand repaired by the contractor or liner installer. Tears or pinholes will be repaired by seaming orpatching. Blisters, larger holes, undispersed raw materials, and contamination by foreign matter will be

repaired by patches. All seams used in repairing procedures will be approved, extrusion welded seamsand will be subject to the same non-destructive and destructive test procedures as described for all otherseams.

Once installation of the liner is complete, no soil material will be placed over the polyethyleneliner prior to acceptance by Malcolm Pirnie, The polyethylene liner will be completely flat and smooth

with no bubbles or wrinkles immediately prior to covering with soil. If bubbles occur due to heat

expansion of the material, the polyethylene liner will be allowed to cool and smooth itself prior tocovering. The polyethylene liner will be firmly supported on the clay barrier layer prior to covering. Novehicles will be permitted directly on the polyethylene liner.

Following placement of the polyethylene liner, the contractor or liner installer will prepare awritten report of the installation work for submittal to Malcolm Pirnie. The report will include:

1. Complete identification of the polyethylene liner, including, but not limited to,resin type, physical properties and other pertinent data.

2. Complete description of seaming system used, including material, method,temperatures, seam overlap width and cure or aging time.

3. Complete description of field sampling and testing including test equipment

used, location of field tests, copy of field test results, conditioning procedure

prior to destructive seam testing, method of recording loading and determiningaverage load for destructive test methods, and type of failure in tests (i.e.,

2049-007-930 3-9

Page 32: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

within the scam, within the sheet material, clamp edge, seam edge).4. "As-Built" drawings showing:

actual layout of liner sheetspanel identification numbersanchor trench details

pipe boot details

dimensions of panelslocation and type of repairs made

location of destructive tests and seams5. Copies of independent laboratory test results of test seams6. Copies of the following information

Affidavit of Compliance certifying that all liner materials furnished

comply with all requirements specified in the Contract Documents.Test Reports of all factory independent testing laboratory and field

quality control test reportsCertification that all laboratory and field testing equipment has beencalibrated and checked for accuracy as recommended by theequipment manufacturer.

The liner manufacturer's warranty

The name, address, and qualifications of the independent testinglaboratory

7. Certified copies of the manufacturer's test results during manufacture of the

liner

8. Manufacturer's information regarding resin quality

9. Written acceptance of liner subgrade by the liner manufacturer or liner installer10. Seaming equipment calibration information11. A certification by the contractor that the installation of the polyethylene liner

was completed in accordance with the terms and conditions of the Contract

Documents.

3.4.6 Drainage Layer

Twelve inches of sand having a minimum permeability of 1 x 10*3 cm/sec will be placed in 12inch (after compaction) lifts immediately above the geomembrane liner to transmit water collected above

2049-007-930 3-10

Page 33: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

the liner. The drainage layer sand will be obtained from an off-site source. This material will beclassified as SP based on the Unified Soil Classification System with no individual particle size being

greater than 1/2 inch. The percent fines, particles less than 0.0074 nun, will be less than 10% by weightof the total weight The contractor will be required to perform grain size distribution analysis to the No.200 sieve for each 1,000 cubic yards of material placed and one remolded laboratory hydraulicconductivity test for each 2,500 cubic yards of material placed. The samples will be tested at 95% ofmaximum index density in accordance with ASTM D 4253 (1991 Edition). The moisture content anddensity of each sample will be recorded. The contractor will be required to perform in-place densitytesting to determine the degree of compaction. A minimum of 5 density and moisture tests using a

nuclear densitometer shall be performed per acre per lift of completed layer to verify in-place density.The soil for the drainage layer will be compacted to not less than 95% of the maximum index density.

Also, the contractor's equipment will not be allowed to come into direct contact with or puncture the

geomembrane liner when placing the sand.

3.4.7 Upper Geotextile Layer

A layer of geotextile filter fabric will be used to separate the sand drainage layer and the coversoil layer. The primary purpose of this fabric is to provide physical separation of cover soil particles andthe sand of the drainage layer. Separation will be required to prevent clogging of the intcrsticial

pathways in the drainage layer, thereby allowing the free flow of water through that layer. Geotextile

filter fabric shall be needle punched, non-woven polypropylene fabric composed of filaments formedinto a stable network such that the filaments retain their relative position. The fabric shall be inert tobiological degradation and naturally encountered chemicals, alkalies, and acids. The fabric shall becompatible with both the cover soil layer and the drainage layer to prevent clogging of the drainage layer

or clogging of the geotextile structure and shall have an apparent opening size as measured accordingto ASTM D4751 capable of retaining the cover soil layer fines and prevent clogging of the underlyingdrainage layer due to fines migration out of the upper cover soil layer. The contractor will be requiredto prevent damage to the underlying gas control layer during placement of the fabric. In addition, thecontractor will be required to not expose the fabric to precipitation and construction traffic prior to its

installation and to place the fabric on a smooth, dry surface. Fabric will be overlapped by 12 inches withoverlaps oriented in the direction of earth filling.

2049-007-930 3-11

Page 34: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

3.4.8 Cover LayerThe cover layer will consist of 30 inches of clean general fill to provide additional rooting depth

for vegetation and to protect the clay barrier layer from damage due to freeze-thaw action. This material

will be natural soil, free from excessive moisture or frost when placed. In addition, the material will be

free of stumps, roots, muck, marl, and stones exceeding 2 inches in greatest dimension. The contractorwill be required to perform grain size distribution analysis to the No.200 sieve for each 5,000 cubic yards

of material placed The moisture content and density of each sample will be recorded. The contractorwill be required to perform in-place density testing to determine the degree of compaction. A minimum

of 5 density and moisture tests using a nuclear densitometer shall be performed per acre per lift ofcompleted layer to verify in-place density. The soil for the cover layer will be compacted to not less than

95% of the Standard Proctor maximum density. Also, the contractor's equipment will not be allowedto come into direct contact with or puncture the underlying upper geotextile filter or damage the drainagelayer when placing the cover soil.

3.4.9 Topsoil LayerSix inches of topsoil after natural settlement and light rolling and capable of supporting

vegetation will be placed over the cover soil layer. Topsoil will be a fertile, friable, natural loam, surfacesoil, capable of sustaining vigorous plant growth, and free of any admixture of subsoil, clods of hardearth, plants or roots, sticks or other extraneous material harmful to plant growth. It will be obtained

off-site from local sources from naturally well-drained sites (excluding bogs or marshes) where topsoiloccurs in depth of not less than 4 inches. Topsoil with a minimum of 5 percent and no more than 20percent by weight of organic matter will be used. The contractor will be required to conduct a soil

analysis by an approved soil testing laboratory stating porosity, the percentages of silt, clay, sand andorganic matter, the pH and the mineral and plant nutrient content of the topsoil.

When placing the topsoil, the contractor will be required to remove stones over 1-1/2-inches inany dimension and sticks, roots, rubbish and other extraneous matter. Loosen subgrade of planting areasto a minimum depth of 4 inches. Limit preparation to areas which will be planted promptly afterpreparation.. Topsoil will not be spread while in a frozen condition or when moisture content is so greatthat excessive compaction will occur nor when so dry that dust will form in the air or that clods will not

break readily.

2049-007-930 3-12

Page 35: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

3.4.10 Vegetation

Vegetative cover is a cost effective method to stabilize the surface of the landfill, to minimizethe erosive impact of wind and rain, and to improve the appearance of the site. The erosive impact of

wind is minimized by the developed root structure of the vegetation which acts as an anchor to hold thesoil together. Similarly, the vegetation protects the soil against storm water erosion by decreasing runoffspeeds, retaining water and increasing concentration times. Another benefit of vegetation is that it

improves the aesthetic appearance of the site.Vegetative cover suitable for the environmental conditions existing at the LTR Site will be

created to satisfy the requirements of the Wisconsin Department of Transportation, Standard

Specifications for Road and Bridge Construction, Section 630, Seeding, Prairie Seed Mixture, Item9000X The entire surface of the landfill will be seeded with 61 pounds per acre of seed conforming tothe mix shown. In addition, 45 pounds per acre of oats or rye seed will be sowed over the entire site to

provide quick shade cover, and to minimize the erosive effects described above immediately followingcompletion of construction.

3.5 STORM WATER MANAGEMENT AND EROSION CONTROL

3.5.1 GeneralDrainage control is essential to ensure that site storm water runoff is properly managed. A well

designed drainage plan will both reduce soil erosion from the surface of the landfill and minimize anypotential leachate generation due to storm water infiltration. The final grading plan as indicated in theFinal Design Drawings includes drainage conveyance structures necessary to control storm water runoff,In areas where velocities exceed the maximum acceptable for grassed surfaces, riprap, or erosion controlmatting will be used as the means of swale stabilization.

Overland flow is proposed to be intercepted by a series of grassed diversion swales, lined witherosion control matting where needed and conveyed to one of two erosion control matting lined

downchutes oriented from east to west on the landfill. At the toe of each downchute, riprap structureswill be constructed to protect the downchutes and to decelerate storm water runoff flow beforedischarging into a sedimentation basin to be located along the west side of the site near Sunny SlopeRoad The basin will be used to settle suspended matter. Overflow from the sedimentation basin willdischarge below Sunny Slope Road to the existing wetlands immediately north of the site after losing

most of its suspended sediment.

2049-007-930 3-13

Page 36: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

According to NR 504, Wis. Adm. Code, surface water drainage systems must be designed toprotect the final cover system from a storm event equivalent to a rainfall intensity of 24 hour durationand a 10 year return period The methods used to compute these runoff quantities are outlined in UrbanHydrology for Small Watersheds - Technical Release No. 55 (TR-55), prepared by the United States SoilConservation Service. Principal considerations used in this proposed drainage system design aresummarized below.

To ensure adequate operation, the proposed drainage structures have been designed to withstandthe above-mentioned storm event Furthermore, additional capacity has been provided via freeboard for

the drainage structures. The calculations for the drainage structure sizing are provided in Appendix A.A sedimentation basin gabion will allow flow through before liquid levels reach freeboard. The

intent of the sedimentation pond is to store the water for a period of time so that suspended sediment isallowed to settle to the bottom of the pond Therefore, the majority of the sediment is left on the bottomof the pond and only the smallest diameter particles of sediment are left in the water. These panicles will

either pass through the openings in the gabion or will be blocked at the interior of the gabion. Ifsediment does block the openings at the bottom of the gabion, the water must build to a higher level

before it is discharged. This allows for longer storage times within the pond with minimal amounts ofwater that cannot discharge from the pond The gabion is used to allow water to slowly leave thesedimentation pond after the sediment has settled out The gabion, with its small rock, provides a longerpath and smaller cross-sectional flow area for the water. Therefore, water will be contained in the pond

for a longer period of time. This longer time allows for more sediment to settle before the water isdischarged from the sedimentation basin. Sediment removal, as necesssary, will be addressed in theOperation & Maintenance Plan.

Runoff from the slopes of the cover structure will not travel more than 250 feet before beingintercepted by a diversion swale on the sideslopes; therefore, the concentration of sheet flow is prevented

to mitigate the potential for erosion.The need for erosion protection in the drainage channels is determined by the velocity of the

water and the stability of the geometric configuration of the structures. The limiting criteria for thedesign of the channels is three feet per second for grassed swales and eight feet per second for swaleswith erosion control matting. The actual velocity in each of the drainage swales, is less than three feetper second, therefore the swales do not need to be lined with erosion control matting. The methodology

evaluates the stability and the capacity of each swale. The stability analysis is based on the worst casescenario for vegetal retardance (i.e., after mowing, early spring etc.) which would allow for higher

2049-007-930 3-14

Page 37: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

velocities in the swales. The capacity analysis evaluates the swales based on the expected vegetalretardance in the field. This analysis yields a more typical flow velocity in the swale.

Erosion control matting will be used in the downchutes to increase the stability of these channelssince the velocities are between three and eight feet per second. At the toe of each downchute where theslope reaches 5:1, a riprap structure will be installed to protect the stability of the downchute, and todissipate the energy and decrease flow velocities before discharging into the sedimentation basin. Table

3-2 is a summary of the drainage structure design data.

3.5.2 Diversion SwalesFollowing the procedures outlined in Urban Hydrology for Small Watersheds - Technical

Release No. 55 (TR 55), prepared by the United States Soil Conservation Service, the diversion swaleshave been designed using Manning's equation for open channel flow. The trapezoid shaped diversion

swales will have a three foot wide bottom, 3:1 sideslopes and will be constructed on compacted generalfill embankments along the slopes of the landfill surface. The diversion swales are locatedapproximately 150 to 250 feet apart horizontally to capture overland flow before the storm water couldform shallow concentrated flow patterns with high velocities which may cause excessive sideslopeerosion.

Information regarding the diversion swales for the landfill is given in Table 3-2. The diversion

swales will be seeded and vegetated only. Downchutes DC-1 and DC-2 with grades of 2 percent eachwill be lined with erosion control matting. The downchutes and swales will utilize a minimum of one

foot of freeboard to introduce an additional factor of safety in the sizing of these structures.The soil embankments, which form the outside face of each swale, will be constructed of

compacted general fill. The surface of this fill will be covered with soil capable of supporting vegetative

growth and seeded along with the remainder of the cover system as detailed in Section 3.4.10 of thisreport.

3.5.3 DownchutesTwo downchutes, DC1 and DC2 are proposed for collecting the runoff from the diversion

swales. They will be constructed of compacted general fill and lined with erosion control matting to

prevent erosion of the underlying cover structure. Details of these downchute structures are provided

on Drawing CD-5.Both downchutes will have velocities under eight feet per second (fps), 5.33 fps in DC 1 and 4.55

fps in DC2, respectively. Peak volumes from the 10 year 24 hour storm events are 17 cfs in DC 1 and

2049-007-930 3-15

Page 38: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 3-2DRAINAGE STRUCTURE DESIGN DATA

SUMMARY TABLE

STRUCTURE

1. Diversion SwalesSIS2S3S4S5S6S7S8S9S10SllS12

2. Downchutes

DC1DC2

3. PerimeterSedimentation Basin

SLOPE (%)

0.51.10.81.61.11.01.10.90.81.01.11.1

2.02.0

0

CUMULATIVEFLOW RATE (cfs)

334335221221

1710

Overflow Capacity 284,900cf

Peak Flow37 cfs

Page 39: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

10 cfs in DC2. To ensure a further level of safety, the 18 inch depth will provide at least 12 inches offreeboard The last 25 feet of both downchutes, where grades reach 20 percent, will be lined with riprap

to protect them from erosion and to dissipate flow and speed.Downchutes DC1 and DC2 will discharge at the toe of the landfill into a riprap apron. The

trapezoidal channel configuration of these downchutes has been selected and sized based upon the peakdischarge from the 24-hour, 10-year storm event.

3.5.4 Energy Dissipators

The energy dissipator riprap aprons will be located al the toe of Downchutes DC 1, DC2, andSwale S1 inside the sedimentation basin. The purpose of these structures is to dissipate the velocity of

the flow from the downchutes before it enters the sedimentation basin. The details of the structures are

provided on the Final Design Drawings.

3.5.5 Sedimentation Basin

The proposed surface water sedimentation basin is an important part of the storm water runoffcontrol system before the surface waters are discharged below Sunny Slope Road to the wetlandimmediately north of the road. The basin will have a runoff storage capacity of approximately 284,900cubic feet at the overflow height of the gabion. This volume is larger than the total runoff from a 10 year24 hour rain storm event, which is calculated to be 144,000 cubic feet. The design storage capacity will

enable the basin to significantly reduce the volume of suspended sediment in the runoff.The perimeter sedimentation basin will receive the storm water runoff from the slopes of the

landfill through the diversion swales and downchutes listed in Table 3-2. Volume calculations are

presented in Appendix A.It should be noted that the rate of infiltration through the base of the sedimentation basin into

the subsurface soils has not been factored into the analysis as a result of the observation during previous

visits to the site indicating that the soils at the lower elevations of the basin locations drain poorly andthat the ground water elevation is approximately 848, three feet below the bottom of the basin.

Therefore, the calculations regarding the capacity of the basin represents a conservative estimate of theability of the sedimentation basin to retain all of the on-site precipitation from the landfill's slopes.

As part of the closure, one rock gabion outlet structure will be installed in the berm of the basin

with invert elevation of 854 feet which is 12 inches below the top of the berm. The approximate locationof the spillway is provided in the Final Design Drawings.

2049-007-930 3-16

Page 40: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

3.6 STABILITY ANALYSIS

The stability of the LTR Site closure was evaluated based on the proposed final grading planhaving a maximum slope area of approximately 6 percent That slope does not appear to pose anysignificant problems with respect to stability. Stability analyses were, therefore, focused on determining

the minimum strength requirements for the capping materials required to maintain acceptable factors of

safety under dry and saturated conditions. The cap configuration, critical cross section, and the analyticalmethodology used to determine the minimum cap strength requirements are presented below. Cover

stability analysis calculations are included in Appendix B.

3.6.1 Analytical Methodology

The stability of the LTR closure was evaluated using Geoslope computer model version 5.1developed by Geocomp Corporation (1992). The Geoslope computer program performs stabilitycalculations according to the STABL V analytical subroutine developed at Purdue University. STABLsolves slope stability problems by a two-dimensional limiting equilibrium method. The factors of safety

against slope instability are calculated by the Modified Bishop's method for circular shaped failuresurfaces, and the simplified Janbu method of slices when evaluating failure surfaces other than circular

in shape. STABL features a unique random technique which generates potential failure surfaces anddetermines the critical failure surfaces and the corresponding critical factors of safety.

The sliding block analysis, using the Janbu method of slices and modified according to theRankine theory of earth pressure, was used to calculate the factor of safety against failure along thegcomembrane interfaces and within the clay barrier layer. The sliding block generator has the capability

to conduct a concentrated search for the critical failure surface within a well defined weak zone or soilprofile. The factor of safety against shear failure is calculated in general by dividing the cohesional andfrictional resistive forces along the trial failure surface by the driving forces of the overlying soil andwaste material. A factor of safety of 1.0 represents a system at equilibrium, whereas values greater than

1.0 indicate a stable condition. Typically, a factor of safety of 1.3 to 1.5 or greater is considered anacceptable value to characterize short and long term stability, respectively.

Circular failure analyses, using the Modified Bishop method, were used to calculate the factorof safety against rotational slip through the cover soils. The circular shaped failure surface, usingsuccessive short line segments as chords of a circle, is generated by changing direction of each successiveline segment by a randomly selected constant angle. This continues until an intersection of the trialfailure surface and the ground surface occurs. The factor of safety against shear failure is calculated in

2049-007-930 3-17

Page 41: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

general by dividing the cohesive and frictional moments (about the center of rotation) by the driving

moments of the overlying soil and waste materials.

3.6.2 Cover ConfigurationThe proposed cover system includes from the ground surface down, a six inch thick topsoil layer

underlain by a 30 inch general fill layer, 12 inch soil drainage layer, a 24 inch composite liner, and a 12inch soil gas control and foundation layer. The composite liner consists of a 24 inch thick clay barrier

layer overlain by a geomembrane liner. The stability analyses were used to determine the minimuminternal shear strength of the general fill, drainage layer, clay barrier, and gas control layer, and theminimum interfacial shear strength at all geosynthetic to soil interfaces within the capping system for

the critical landfill cross section.

The critical cross section used to characterize the stability of the LTR closure was taken fromwest to east along the northern portion of the LTR Site. The cross section was developed to maximizethe diving forces resulting from the maximum elevation difference and the steepest slopes. As a result,

the section is considered to approximate "worst case" conditions and, therefore, was used to characterizethe stability of the landfill closure. The remaining areas of the cover are less critical than this sectionbecause the slopes are shallower with a smaller vertical elevation difference between the toe of slope andthe top of the landfill. Based on this critical cross section, the steepest section of the landfill top area (6percent) was used to model the landfill cap over a 500 foot length. This model represents a conservative

approximation of the cap cross section and, therefore, represents a true worst case representation of thelandfill cover.

3.6 J Analytical Results

The minimum strength required to satisfy the stability criteria and provide a minimum factorof safety of 1.3 and 1.5 under dry and saturated conditions for the LTR closure are presented in thefollowing table for the soils and geosynthetic interfaces, respectively.

3.6J.1 SoilsThe stability analyses were performed for the critical cross section in the dry and saturated

conditions to determine the minimum strength requirements of the cover materials required to achieve

the required short term (saturated) and long term (dry) factors of safety. Saturated conditions weremodelled using full saturation of the 12 inch drainage layer. Based on HELP analyses, the drainage layershould possess a coefficient of permeability equal to or greater than lxlO"2cm/s in order to maintain

2049-007-930 3-18

Page 42: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

head levels within the drainage layer. The Technical Specifications require the contractor to submit testdata demonstrating that the drainage material to be provided has the capability to satisfy this criteria.

The minimum strength required within the soils of the final cover required to maintain theminimum factors of safety are as follows:

TABLE 3-3MINIMUM SOIL STRENGTH REQUIREMENTS

Material

Topsoil

General Fill

Clay Barrier

Drainage Soil

Gas Venting Soil

Internal Friction,degrees

25

25

0

25

25

Cohesion, psf

25

0

250

0

0

Based on our experience with regional soils, these strength values are easily achievable.Detailed testing will not be conducted during material placement to demonstrate compliance with thesecriteria. However, the Technical Specifications specify that the contractor submit test data indicatingthat the general fill, drainage sand, and gas venting soil comply with these strength criteria.

3.6.3.2 GeosyntheticsThe factor of safety against sliding in the dry and saturated condition are 1.6 and 1.4,

respectively, when the interface friction angle at all geosynthetic to soil interfaces exceeds 9 degrees.

It is our experience that this interface friction value may be achieved by using PVC geomembrane,

2049-007-930 3-19

Page 43: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

It is our experience that this interface friction value may be achieved by using PVC geomembrane,smooth low density polyethylenes, textured HOPE, and potentially smooth HDPE. The TechnicalSpecifications outline the interface friction direct shear testing requirements and the minimum acceptableinterface friction value of 9 degrees. The contractor will be required to submit test results for thematerials proposed for installation prior to construction of the cover that demonstrate the interfacial

strength criteria of 9 degrees is satisfied at all geosynthetic interfaces within the cover according toASTMD5321.

3.7 LANDFILL GAS VENTING

An active gas collection system is not required by the State and a passive landfill gas ventingsystem will be installed on the LTR Site. The gas venting system will consist of 6 inch diameter densityHDPE gas vents and slotted risers with lateral piping and a 12 inch thick gas control and foundationlayer installed below the clay barrier layer. Altogether 36 gas vents have been allocated.

The HDPE gas vents and risers will be constructed as required in the specifications. The gasvents will extend down through the whole depth of the waste to the top of the CU unit or the top of the

bedrock, and two lateral pipes will extend under the cap from each vent for a minimum of 10 feethorizontally in opposite directions. The gas risers will have a goose-neck cap and extend a minimumof four feet from the topsoil to the opening on the goose-neck. A bird screen will prevent the entranceof vectors or debris into the vents. A typical gas venting detail is provided in the Final Design Drawings.

The hydraulic gas venting layer, as described earlier, will consist of 12 inches of sand with apermeability of 1 x 10'3 cm/sec or greater. The lower geotextile layer located between the gas controllayer and clay barrier layer will provide separation of these two layers.

3.8 WELL ABANDONMENT

The six existing OW-Series wells installed in 1982 by Foth and Van Dyke (OW-2B, OW-4,OW-5,OW-6,OW-7 awl OW-8)wm be abawkmcd in accordance with NR 141.25, Wis. Adm. Code.The wells will be abandoned prior to the subgrade preparation of the landfill cap.

2049-007-930 3-20

Page 44: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

4.0 REQUIRED PERMITS, LICENSES, AND APPROVALS

Section 121 of the Comprehensive Environmental Response, Compensation, and Liability Act

of 1980 (CERCLA) as amended by the Superfund Amendments and Rcauthorization Act of 1986

(SARA) states that "on-site" actions are not subject to state permits. However, SARA states that theRemedial Action must comply with Applicable or Relevant and Appropriate Requirements (ARARs),or justify a waiver. ARARs for Phase 3 remedial design and construction are presented below:

Description/Title Law, Code, Order or Regulation

Action Specific:

1. Standards for Landfill Cap Design.

2. Standards Wetlands Water Quality

NR 504.07, Wis. Adm. Code.

NR103, Wis. Adm. Code.

AH groundwater issues and appropriate ARARs for groundwater associated with the Lemberger sitesare addressed under the OUI RA. Applicable ARARs for Phase 3 activities at LTR are discussed below.

1. NR 504.07 Wis. Adm. Code; Final Cover System Design. NR 504.07 provides

information on minimum design requirements for the final landfill cover system. NR

504.07 is applicable to landfill cap design and construction activities during Phase 3. TheTechnical Specifications (Appendix E) have been written to require compliance with NR

504.07, Wis. Adm. Code and applicable Federal, State, and local regulations andordinances.

2. NR 103 Wis. Adm. Code; Water Quality Standards for Wetlands. NR 103establishes water quality standards for wetlands. NR 103 is applicable to the Wisconsin

solid waste composite cover construction. The Technical Specifications have been

written to require compliance with NR 103, Wis. Adm. Code and applicable Federal,State, and local regulations and ordinances.

2049-007-930 4-1

Page 45: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Several other appropriate requirements which will be considered during construction include thefollowing:

1. NR 512.18 Wis. Adm. Code; Identification and Characterization of Potential

Borrow Sources. This code requires certain characterization of borrow sources to be

used for providing soil materials for the landfill cover. Testing of soil material for its

suitability in construction of the cover is included in the Technical Specifications. LSRG

is not intending to use an on-site borrow source for materials used to construct the

composite cap. The construction contractor will be responsible for procurement ofmaterials from off-source locations and will therefore be required to comply with these

requirements.

2. NR 514.07 Wis. Adm. Code; Closure Plan. Requirements listed under NR 514.07

have been considered in the development of the closure of the LTR Site. In general, these

include the submittal of engineering plans and a design report.

3. NR 516.05 Wis. Adm. Code; Soil Testing Requirements. This code details soil

testing of soil materials during the construction of a landfill cover. The testingrequirements have been incorporated into the Technical Specifications and will berequired of the construction contractor.

4. NR 516.06 and 516.07 Wis. Adm. Code; Construction of Landfill Areas and

Closure of Landfill Areas. These require that documentation be prepared and submitted

at the end of construction detailing the construction of the landfill cover and appurte-nances. The Construction Quality Assurance Plan for the LTR cover will include a

requirement that a Construction Completion Report consistent with NR 516.06 and

516.07 be prepared at project completion. The report will document that the remedial

action has been properly implemented in accordance with the drawings and specifica-

tions.

2049-007-930 4-2

Page 46: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

5.0 FINAL COST ESTIMATE

The Final Cost Estimate for construction of the LTR Site closure is shown in Table 5-1. TheFinal Cost Estimate for the operation and maintenance of the LTR Site after closure is shown in Table5-2.

All costs shown in Tables 5-1 and 5-2 are in 1995 dollars and do not include periodic technicalconsulting or legal costs. The operation and maintenance cost estimate assumes the following:

• Labor would be employed directly by an entity formed by LSRG or by one of the LSRGparties.

• The scope of the cover maintenance program is as defined in the operation andmaintenance plan.

2049-007-930 5-1

Page 47: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 5-1FINAL CONSTRUCTION COST ESTIMATE

LTR SITE CLOSURE SYSTEMITEM

LTR SITE CLOSURE

MOBILIZATION

SITE PREPARATIONClearing and GrubbingAbandon Wells

COMPOSITE CAP CONSTRUCTIONGeneral Fill for SubgradeGas Control and Foundation LayerLower GeoiexlileClay Barrier LayerGeomenibrane LinerDrainage LayerUpper GeotextileCover LayerTopsoilVegetal ionGas Vents

EROSION CONTROL SYSTEM

SITEWORKGravel RoadwaySoil Stabilization Fabric

SUBTOTAL

CONTRACTOR OVERHEAD, PROFIT AND CONTINGENCY

TOTAL FINAL CONSTRUCTION COST ESTIMATE

QUANTITY

1

16

30,00045,119

134,22090,235

134,21951,784

155,360129,45925,892

32442

1

1,26050,700

(30%)

UNITS

LS

LSEA

CYCYSYCYSYCYSYCYCYACLF

LS

CYSF

UNIT COST

S250.000

$50,000$2.500

$5.00$8.05$0.85$945$7.00$805$0.85$5.00$8.40

$2,100.00$100.00

$80,000

$20.00$0.25

TOTAL COST

$250,000

$50,000$15,000

$150,000$363,208$114,087$852,721$939,533$416,861$132,056$647,295$217,493

$67,410$44,200

$80,000

$25,200$12,675

$4,378,000

$1,313,000

$5,691,000

2049-007-930 10/6/95

Page 48: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE 5-2OPERATION AND MAINTENANCE

FINAL COST ESTIMATELTR SITE CLOSURE SYSTEM

Item 0 1 2Year: 1996 1997 1998

LTR SITE POSTCLOSURE CARE

LABORSite Inspections and Reporting - 13,000 $3,000

SITE MAINTENANCE AND REPAIR CONTRACTSMowing - $3,000 $3,000Cap Repair - $5,000 $5,000

SUBTOTAL $0 $11,000 $11,000

CONTINGENCY (@ 30%) $0 $3,300 $3,300

TOTAL ANNUAL O&M COST EST. $0 $14,000 $14,000

31999

$3,000

$3,000$5,000

$11,000

$3^00

$14,000

4 162000 2012

$3,000 $3,000

$3,000 $3,000$5,000 $5,000

$11,000 $11,000

$3,300 $3,300

$14,000 $14,000

302026

$3,000

$3,000$5,000

$11,000

$3,300

$14,000

Total

$90,000

$90,000$150,000

$330,000

$99,000

$420,000

2049-007-930 9/27/95

Page 49: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

6.0 FINAL PROJECT SCHEDULE

The Final Project Schedule for construction of the LTR cover is shown in Figure 6-1. ThescheduJe assumes USEPA approval of the Final Design and Final Construction Quality Assurance Plan

by November 1,1995 and December 1,1995, respectively.

2049-007-930 6-1

Page 50: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ActivityDescription

Contractor's Notice to ProceedMobilizationPreconstruction Inspection andClearing and GrubbingSubgrade PreparationGas Control LayerGas VentsClay Barrier LayerGeomembraneDrainage LayerSedimentation BasinCover LayerTopsoilSeedingPrefinal InspectionPrepare Prefinal InspectionFinal InspectionPrepare RA ImplementationPrepare Final Inspection ReportIssue RA Implementation

Or*Our

0519

281421901621142872161

/O70

earlyStart

01APR96'14APR9615APR9619APR96

r28APR9626MAY9629MAY9602JUN9631AUG9616SEP9623SEP9623SEP9619OCT9626OCT9628OCT9629OCT9604NOV9605NOV9605NOV9614JAN97

carfyFinish

31MAR9618APR9615APR9627APR9625MAY9608JUN9618JUN9630AUG9615SEP9606OCT9606OCT9620OCT9626OCT96270CT9628OCT9603NOV9604NOV9613JAN9711NOV9613JAN97

•y

: : • : • : • • " • • ••• •'•' '" '"' •^wm&w&Kfr: - V = - : '--'- : * " \ 99$ ' : ; - -" -:"-- ' '"' "":~ :'":' '*"*?<*• ••-••«;^ vX::.m®ffi^imi$^m?$- £*£*•APR i - M A Y - - - ' ] -'JUN i . '.ju£.:........l ' AUG 1- :vsEf>1;''::'';^v16cr!'''^*• ;ww A> t* ,tiiW< JET A- -io ,17 ;24 1 M ,1$ a* A A ,12 M.-M ,2 ,» ,16 jwt M $ ,14 JH

ntractor's Notice to Proceed.W MobilizationAj1^ Preconstruction Inspection and M

t;: MTCIearlng and Grubbing

f i

eetlng

rationrol Layer_ —————— ._ ___ - _. — VG&S Vents

•••WGeom

f |

t-'• ' NOV '' " "bCfcJI '"'...^......TjTT •*""'HTrT5a ' A 4 ' Jl ,11 il« «Z9 >« ,» ilVtZ9t<

jyerMnbrane•W Drainage Layer•T Sedimentation Basin

T•••• •W Cover Layer

•TTOpsotlf^V SeedingJTPreflnal Inspection•f Prepare Prefinal Inspectkw& Final Inspection

LTBC 9Mt1tf1

Lembeffler Sites Remediation GroupLTR Construction

Figure 6-1 Final Protect Schedule

,„„„.,.

l*T,i'

iRepor

i

i

Page 51: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

7.0 HEALTH AND SAFETY PLAN

LTR Site closure oversight activities by Malcolm Pimie will be conducted in accordance withthe Oversight Health and Safety Plan. The Oversight Health and Safety Plan is included in AppendixC of this document.

The construction contractor will be responsible for developing, implementing and monitoring

a detailed Site Safety Plan for construction activities. The contractor's Site Safety Plan will be required

to detail the means, methods, procedures and activities which will be implemented to minimize oreliminate health and safety hazards resulting from the performance of individual tasks or from theoperation of particular tools or equipment. The Site Safety Plan shall be consistent with all applicable

local, state and federal requirements including but not limited to the OSHA regulations in 29 CFR 1910

and 29 CFR 1926. The requirements of the Site Safety Plan are included in Specification Section

01060, titled Site Safety Plan. In summary, the Site Safety Plan will address the following:

• Facility Description: Facility background information and availability of resources suchas roads, utilities and structures will be provided.

• Personnel: Identification and organization of site specific personnel, their responsibilities,employee training and medical monitoring.

• Safe Work Practices: The contractor will provide detailed construction, installation andfield engineering safe working procedures to be followed for all on-site activities.

• Hazard Assessment: The contractor will address the characteristics, toxicity and potentialrisks associated with the contaminants and physical hazards that may be encountered.

• Site Control and Work Zones: The contractor shall specify project work zones inaccordance with 29 CFR 1910.120 and 29 CFR 1926, subparts C & G. Procedures forsite security to control access to the work zones shall also be described. As a minimum,the area surrounding each hazardous work area will be divided into the following zones:

Exclusion (Hot) ZoneContamination Reduction (Buffer) ZoneSupport (Clean) Zone

• Communication Procedures and Employee Training: The contractor will address the needfor pre-field activities health and safety orientation, safety meetings, health and safetyorientation training and hazard communication.

• Medical Surveillance and Exposure Monitoring: The contractor will describe his/hermedical surveillance and exposure monitoring program for employees engaged inhazardous waste remediation work activities.

2049-007-930 7-1

Page 52: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Personnel Protective Equipment: The contractor will address personnel protectiveequipment to be used on-site. Equipment will be in accordance with USEPA Levels A,B, C and D for each element of the work. The contractor will provide Mine Safety andHealth Administration (MSHA) and National Institute for Occupational Health andSafety (NIOSH) approved air line respirator for Level B work. Data from the airmonitoring program shall be used to determine if an alternative level of protection isappropriate. Procedures for protecting workers against heat stress and/or cold stress willalso be provided.

Air Monitoring: An air monitoring program will be designed to detect and quantify therelease or volatilization of contaminants during landfill closure and ground watertreatment activities. Air monitoring data shall be used to determine appropriate levels ofpersonnel protection and need to enact emergency response plan provisions in the eventof a contaminant release. The type(s) and quantity of air monitoring equipment to beutilized will be stated in the contractor's proposal.

Decontamination: The contractor will describe decontamination procedures to be utilizedin the intended work. Procedures will describe, at a minimum, the decontamination ofprotective clothing, equipment, heavy equipment and machinery, disposal of decontami-nation wastes, and medical emergencies decontamination.

Documentation and Reporting: The contractor shall describe procedures to establish andmaintain adequate records related to project-related injuries or illnesses, accidentinvestigations, reports to insurance carriers or state compensation agencies, records orreports required by regulatory agencies, property or equipment damage, and inspectionsand citations.

Contingency and Emergency Response Plan: The contractor will develop a site-specificEmergency Response and Contingency Plan. This plan will address on-site emergencywarning and notification procedures and personnel injury response plan.

Emergency References, Contacts and Phone Numbers.

2049-007-930 7-2

Page 53: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

! •' '•• :~^i'^^M:.^';;Mi^f^i^f;^iaM^^^^,' • ' ': • -.'^-- '\''-?^j.''''^''^'^^^^"0^t^M•• - M ji , , 'U3 •T'iF^"-1 '-''1f:;'Sl 'S^KH'sM

iMii ^E.i k . as^Lis l,lw^ r1 .*

Page 54: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX A

Volume, Drainage, andRiprap Calculations

FINAL DESIGN REPORT

LTR Site Closure

Prepared for:

Lemberger Site Remediation Group

Submitted by:

Malcolm Pirnie, Inc.Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, MN 55416

Page 55: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

VOLUME CALCULATIONS

Page 56: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Preftnal DesignCut and Fill Calculations j

Total Area of LTR Boundary and Contour #866 = 2.028,106.85 sq. ft.

Subgrade Contour DataThird Iteration

Contour

841842843844845846847848849850851852853854855856857858859860861862863864865866867868869870871872873874875876877878879880881882883884885

885+

AutocadArea, sq.ft.

621.079,039.70

26.648.3150.434.6669.395.8097,492.10

121,876.97170,960.01222,830.28272,005.15322.113.47103,069.43613,452.17692,080.36774,871.66863,018.84953,204.98

1.038.737.441,127.082.471,211,867.101,292,321.181,365,640.771,436,527.641 .503.941 .92

AutocadArea, sq.ft.

AutocadArea, so.. ft.

TotalAutocad

Area4 so. ft

621 .079.039.70

26.648.3150,434.6669,395.8097,492.10

121,876.97170.960.01222.830.28272,005.15

369,073.24

1 .575,787.911,645,352.79

322,113.47472,142.67

F

i

Contour ! ContourArea. so. ft. Volume, cu. ft.

2.027.485782,019,067.152,001,458.541.977,672.191.958,711,051.930,614.751,906,229.881,857.146.841,805.276.571,756,101.701,705,993.381,555,964.18

613,452.17 1,414,654.68! 692,080.36 1.336.026.49

—————————

—————————

"

38.93 339,570.60301,844.94261,946.77214,198.67167.580.64130,759.62109,840.1197,301.8784,905.7778,440.8771,533.1464,079.7255,482.8547,912.3038,106.0329,764.1719,054.368,209.361.618.69

774,871.66 1,253,235.19

2,027,485.782.023.275.012.010,256.421,989.553.521,968,184.011,944,645.991,918.409.401,881,635.011,831,150.481,780,632.551,730,987.101,630,403441,484,748.951,375.153.251,294,410.18

863.018.84 1,165,088.01 | 1.208.893.77953,204.98 1,074,901.87

1,038,737.44 989,369.411,119,692.231,031,840.18

1,127,082.47 901,024.38 944,852.651.211.867.10 816.239.75 • 858,283.021.292,321.18 ' 735,785.67 775,664.931,365,64077 662.466.08 698.805.271,436,527.641,503,941.921,575,787.911.645,352.79

339,609.53301 ,844.94261 ,946.77214,198.67167,580.64130,759.62109,840.1197.301.87

' 84.905.7778,440.87

; 71,533.14I 64,079.72

55,482.8547,912.3038,106.03

591,579.21 626.688.46524,164.93 557,532.32452,318.94 487,800.82382,754.06 : 417,05274339,60953301,844.94261,946.77214,198.67167,580.64130,759.62109,840.1197,301.8784.905.7778.440.8771,533.1464,079.7255,482.8547,912.3038.106.03

29.764.17 . 29.764.1719.054.36 19,054.368,209.361.618.69

8,209.361,618.69

360,966.86320,541.80281,660.27237,672.69190,413.51148,789.97120,148.00103.507.6991 .033.4681.651.9974,960.4867,772.2759,729.7151.651.3242.9157033,849.3324,211.0613,256.894,491.13

539.56

TOTAL VOLUME, CD. FT. 37,927.801.16

Page 57: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Cut and Fill Calculations !

Total Area of LTR Boundary and 866 Contour - 2,028,106.85 sq. ft.Existing Contour Data

Contour

841842843844845846847846849850851852853854855856857858859860861862863864865866867868869870871872873874875876877878879880881882883884885885+

AutocadArea. so. .ft.

621.077.098.39

20.181.7248,636.0771,589.32

105,265.44146.133.60187,961.62234,899.26283,035.07334,764.62426.345.82717,806.18831.700.76926,821 .50

1.020,798.681.091.605.391,180.157.871 .270.899.341,324.668.851.377.669.391,427,113.741.477,148.371,526.102.751,577,112.461,637.135.33

352.621.74315,384.93270,505.01224,480.16168.337.78130.759.62109.840.1197,301 .8784,905.7778,440.8771,533.1464,079.7255,482.8547,912.3038.106.0329,764.1719.054.368.209.361,618.69

AutocadArea, sq.ft.

11.472.6590,246.00

27.601,770.44

512.2838.93

AutocadArea, sq.ft.

————————

TotalAutocad

Area, sq.ft.

621.077.098.39

20.181.7248,636.0771.589.32

105,265.44146,133.60187.961.62234.89926283.035.07346,237.27516,591.82717,806.18831,700.76926,821 .50

1 ,020,826.261 ,093,375.831,180.157.871 ,270,899.341 ,324,668.851 .377,669.391,427,113.741,477,148.371,526,102.751,577,112.461 ,637,647.61

352.660.67315.384.93270.505.01224,480.16168,337.78130,759.62109,840.1197,301.8784,905.7778,440.8771,533.1464,079.7255,482.8547,912.3038.106.0329,764.1719,054.368,209.361,618.69

ContourArea, sq.ft.

2,027,485.782.021 ,008.462,007.925.131 .979.470.781,956.517.531.922.841.411,881.973.251.840,145.231,793.207.591.745.071.781,681,869.581,511,515.031.310.300.671,196.406.091.101,285.351,007,280.57

934.731.02847,948.98757,207.51703,438.00650,437.46600,993.1 1550,958.48502,004.10450,994.39390,459.24352,660.67315,384.93270,505.01224,480.16168,337.78130,759.62109,840.1197,301.8784,905.7778,440.8771.533.1464.079.7255,482.8547.912.3038.106.0329.764,1719.054.368,209.361,618.69

TOTAL VOLUME, CU. FT.

TOTAL VOLUME NEEDED. CU. FT.TOTAL VOLUME AVAILABLE, CU. FT.

ContourVolume, cu ft.

2,027.485.782.024.246.262.014.463.251,993.681.031,967,983.001,939,655.111,902.370.751.861,020.071.816,625.881,769.085.111,713,373.541,595.934.451,409,710.671,252.921.911,148,517.431 ,053,933.54

970,779.86890,987.74802,150.43730,157.75676,764.76625,552.42575,794.61526,291.52476.271.56420,363.43371,399.63333,849.34292,658.06247,135.19195,736.85149,153.70120,148.00103,507.6991 .033.4681,651.9974,960.4867,772.2759,729.7151,651.3242,915.7033.849.3324,211.0613,256.894,491.13

539.56

36.545,773.20

37,927,801.1636,545,773.20

NET VOLUME NEEDED, CU. FT. 1 ,382.027.95NET VOLUME NEEDED, CU. YD. 51,186

The volumes were calculated using the truncated cone or truncated pyramid formula as given below:I

Volume - h x ( A1 + A2 + SQRT ( A1 x A2))/3

I lh * distance between areas A1 and A2 'h-1ft.

A1 , A2 » contour areas ' '

Page 58: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Prefmal DesignEstimate of Quantities for LTR Cap Construction

Waste Area: 1,167,491 sq.ft.Waste Area + 8 ft. outside of waste area: 1,207,974 sq. ft.Waste Area + 10 ft. outside of waste area: 1,218,158 sq. ft.

All areas were calculated using Autocad.

General Fill for Subgrade: 51,072 cu. yd.(See Spreadsheets for calculations)

Gas Control and Foundation Layer:

= 1,218,158 sq. ft. (Waste Area + 10 ft outside of waste area) x 1 ft thick

- 1,218,158 cu. ft.

= 45,117 cu. yd.

Lower Geotextile Fabric:

= 1,207,974 sq. ft. (Waste Area + 8 ft. outside of waste area)

= 134,220 sq. yd.

Clay Barrier Layer:

= 1,218,158 sq. ft. x 2 f t thick

= 2,436,316 cu. ft.

= 90,234 cu. yd.

Geomembrane Liner:

- 1,207,974 sq.ft.

= 134,219 sq. yd.

Page 59: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Drainage Layer:

= Drainage Layer + Gravel Drain

= 1,218,158 sq. ft. x 1 ft. thick + 6,000 ft. x 30 ft. wide x 1 ft. thick

= 1,398,158 cu. ft.

= 51,784cu. yd.

Cover Layer:

= Cover Layer on Cap + Cover Material to match to existing contours

= 1,218,158 sq. ft. x 2.5 ft thick + 6,000 ft. x 30 ft. wide x 2.5 ft. thick

= 3,495,395 cu. ft.

= 129,459 cu. yd.

Topsoil:

= Topsoil on Cap + Topsoil to match to existing contours

= 1,218,158 sq. ft. x 6 in. thick + 6,000 ft. x 30 ft. wide x 6 in. thick

= 699,079 cu. ft.

= 25,892 cu. yd.

Vegetation:

= 1,218,158 sq. ft. + 6,000 ft x 30 ft. wide

= 1,398,158 sq.ft.

= 32.1 Ac

Page 60: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

DRAINAGE CALCULATIONS

Page 61: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE SI RUNOFF CALCS FOR 5

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250482.6

Slope(ft/ ft)

.02

.0052

; ^J

WALES ANI

ibarea # 1SurfacecodeEU

User: MAM Date: 05-18-95Checked: Date:) DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.115

Time of Concentration = 0.48*

—— Sheet Flow Surface Codes ——A Smooth SurfaceB Fallow (No Res.)C Cultivated < 20 % Res.D Cultivated > 20 % Res.E Grass-Range, Short

F Grass, DenseG Grass, BurmudaH Woods, LightI Woods, Dense

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 62: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S2 RUNOFF CALCS FOR i

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250481.6

Slope(ft/ ft)

.02

.0112

: WISWALES ANI

abarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:} DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.078

Time of Concentration = 0.44*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BunnudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 63: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAHEA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S3 RUNOFF CALCS FOR 5

_ ___ ____—— e»'

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

135485.5

Ol

Slope(ft/ ft)

.0459

.0082

WISWALES ANI

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:) DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.1590.092

Time of Concentration = 0.25*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow Concentrated•— Surface Codes

P PavedU Unpaved

Page 64: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TC and Tt THRU SUBAREA COMPUTATION VERSION 1,11 -

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S4 RUNOFF CALCS FOR i

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250334.1

Slope(ft/ ft).0200.0162

: WISWALES ANI

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:D DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.045

Time of Concentration = 0.41*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

-— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 65: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project : LTR PREFINAL DESIGNCounty : MANITOWOC State:Subtitle: SWALE S5 RUNOFF CALCS FOR £

___ _ ____.- <?»

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent fd

Length(ft)

250436.7

Slope(ft/ft).0200.0114

• WISWALES ANI

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:D DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.070

Time of Concentration = 0.43*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 66: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S6 RUNOFF CALCS FOR I

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

240491.3

Slope(ft/ft)

.0229

.0104

• WIWALES AN!

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:

:> DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0,3340.083

Time of Concentration = 0.42*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 67: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project : LTR PREFINAL DESIGNCounty : MANITOWOC State: WI __Subtitle: SWALE S7 RUNOFF CALCS FOR SWALES AND DOWNCHUTES

User: MAMChecked:

Date: 05-18-95Date:

Flow Type 2 year Length Slope Surfacerain (ft) (ft/ft) code

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

Sheet 2.5 250Shallow Concent*d 295.2

.0200 E

.0112 U0.3640.048

Time of Concentration = 0.41*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 68: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project : LTR PREFINAL DESIGNCounty : MANITOWOC State: WI

User: MAMChecked:

Date: 05-18-95Date:

Subtitle: SWALE S8 RUNOFF CALCS FOR SWALES AND DOWNCHUTES

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent *d

Length(ft)

250276.4

Slope(ft/ ft)

.0200

.0094

J.1JCI.L CO. tfJ-

Surfacecode

EU

n Area(sq/ft)

Wp(ft)

Velocity(ft/ sec)

Time(hr)

0,3640,049

Time of Concentration - 0.41*

—— Sheet Flow Surface Codes ——A Smooth SurfaceB Fallow (No Res.)C Cultivated < 20 % Res.D Cultivated > 20 % Res.E Grass-Range, Short

F Grass, DenseG Grass, BurmudaH Woods, LightI Woods, Dense

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 69: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project : LTR PREFINAL DESIGNCounty : MANITOWOC State: WI

User: MAMChecked:

Date: 05-18-95Date:

Subtitle: SWALE S9 RUNOFF CALCS FOR SWALES AND DOWNCHUTES

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250180.8

—— • —— 01Slope(ft/ ft).0200.0083

a u cared fj.Surfacecode

EU

n Area(sq/ft)

Wp(ft)

Velocity(ft/ sec)

Time(hr)

0.3640.034

Time of Concentration = 0.40*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 70: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S10 RUNOFF CALCS FOR

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250400.8

Slope(ft/ ft)

.0200

.0097

! WISWALES Al

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked : Date :*D DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.070

Time of Concentration = 0.43*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BunnudaC Cultivated < 20 % Res.D Cultivated > 20 % Res.E Grass-Range, Short

H Woods, LightI Woods, Dense

-— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 71: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE Sll RUNOFF CALCS FOR

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent *d

Length(ft)

250255.9

Slope(ft/ft)

.0200

.0113

WISWALES A*

ibarea #1Surfacecode

EU

User: MAM Date: 05-18-95Checked: Date:JD DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3640.041

Time of Concentration = 0.41*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 72: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TC and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle SWALE S12 RUNOFF CALCS FOR

Flow Type 2 yearrain

Sheet 2 . 5Shallow Concent 'd

Length(ft)

250188.3

Slope(ft/ ft)

.0210

.0111

WISWALES AI

ibarea #1SurfacecodeEU

User: MAM Date: 05-18-95Checked: Date:*D DOWNCHUTES

n Area Wp Velocity Time(sq/ft) (ft) (ft/sec) (hr)

0.3570.031

Time of Concentration = 0.39*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res.D Cultivated > 20 % Res.E Grass-Range, Short

H Woods, LightI Woods, Dense

-— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 73: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Project LTR PREFINAL DESIGNCounty MANITOWOC StateSubtitle BELOW SWALE S4 RUNOFF CALC5

_ __ __ — e^-Fi ow Type

Sheet

2 yearrain

2.5

Length(ft)

245

*jiSlope(ft/ft)

.0200

WI3 FOR SWA1

ibarea # 1Surfacecode

E

User: MAM Date: 05-18-95Checked: Date:^ES AND DOWNCHUTES

n Area Wp Vel oc i ty(sq/ft) (ft) (ft/sec)

Time(hr)

0.358Time of Concentration = 0.36*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res.D Cultivated > 20 % Res.E Grass-Range, Short

H Woods, LightI Woods, Dense

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 74: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

Pro j ectCountySubtitle

LTR PREFINALMANITOWOCBELOW SWALE

Flow Type 2 yearrain

DESIGNState:

S7 RUNOFF CALCS

Length(ft)

Slope(ft/ ft)

WIFOR SWA]

barea #1Surfacecode

User: MAMChecked :JES

n

Date: 05-18-95Date:

AND DOWNCHUTES

Area(sq/ft)

Wp(ft)

Velocity(ft/ sec)

Time(hr)

Sheet 2.5 230 .0200 0.340Time of Concentration = 0.34*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 75: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 Tc and Tt THRU SUBAREA COMPUTATION VERSION 1.11

ProjectCountySubtitle

LTR PREFINAL DESIGNMANITOWOC State: WI

User: MAMChecked :

Date: 05-18-95Date:

BELOW SWALE S10 RUNOFF CALCS FOR SWALES AND DOWNCHUTES

#1Flow Type 2 year Length Slope Surface

rain (ft) (ft/ft) coden Area Wp Velocity Time

(sq/ft) (ft) (ft/sec) (hr)

Sheet 2.5 230 .0200 0.340Time of Concentration = 0.34*

—— Sheet Flow Surface Codes ——A Smooth Surface F Grass, DenseB Fallow (No Res.) G Grass, BurmudaC Cultivated < 20 % Res. H Woods, LightD Cultivated > 20 % Res. I Woods, DenseE Grass-Range, Short

•— Shallow ConcentratedSurface CodesP PavedU Unpaved

Page 76: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TABULAR DISCHARGE METHOD VERSION 1.11 -

Proj ectCountySubtitle

LTR PREFINAL DESIGNMANITOWOC State: WI

User: MAMChecked:

Date: 05-18-95Date: ______

OWUtJ 0UCLI.C. »,j_ , . — — _ _ , _ _ „ _ _______

SIZE BASIN BASED ON ALL WATER REACHING BASIN AT THE SAME TIME

Total watershed area: 0.036 sq mi Kaj.nj.axj. «-y^———————————————————— Subareas0.036 sq mi Rainfall type: II Frequency: 10 years

Area(sq mi)Rainfall(in)Curve numberRunoff(in)Tc (hrs)

(Used)TimeToOutletla/P

Time Total •(hr) Flow

ALL0.043.879

1.800.410.400.000.14

ALL

11.011.311.611.912.012.112.212.3

12.412.512.612.712.813.013.213.4

13.613.814.014.314.615.015.516.0

16.517.017.518.019.020.022.026.0

11248152837P

3627191411754

43332222

21111110

11248152837P

3627191411754

43332222

21111110

Subarea Contribution to Total Flow (cfs)

p - Peak Flow

Page 77: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignSedimentation Basin CalculationBased on calculations completed on 5/18/95CN = 79Time of concentration = .41 hours

Time(Hr)

11.011.311.611.912.012.112.212.312.412.512.612.712.813.013.213.413.613.814.014.314.615.015.516.016.517.017.518.019.020.022.026.0

Flow(Cfsj

11248

15283736271914117544333222221111110

Total Volume(Cfi

1,0801,6203,2402,1604,1407,740

11,70013,14011,3408,2805,9404,5006,4804,3203,2402,8802,5202,1603,2402,7002,8803,6003,6003,6002,7001,8001,8003,6003,6007,2007,200

Basin Volume Needed (cf) 144,000

Pagel

Page 78: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TABULAR DISCHARGE METHOD VERSION 1.11 -

Project LEMBERGER LTR PREFINAL DESIGN User: MCounty MANITOWOC State: WI Checked:Subtitle SUBAREA FLOW CALCULATONS

Total watershed area:

SIArea(sq mi) 0.00Rainfall (in) 3.8Curve number 79Runoff (in) 1.80Tc (hrs) 0.36

(Used) 0.40TimeToOutlet 0 . 00la/P 0.14

Time Total ——(hr) Flow

11.0 011.3 011.6 011.9 212.0 812.1 1512.2 2412.3 27P

12.4 2312.5 1812.6 1212.7 1012.8 913.0 513.2 213.4 0

13.6 013.8 014.0 014.3 014.6 015.0 015.5 016.0 0

16.5 017.0 017.5 018.0 019.0 020.0 022.0 026.0 0

SI

00001123P

32211100

00000000

00000000

0.027 sq mi

S20.003.879

1.800.360.400.000.14

—— SubareaS2

00001123P

32111100

00000000

00000000

Rainfall type:———— Subareas -

S30.003.879

1.800.160.200.000.14

Contribution toS3

000124P43

11111000

00000000

00000000

IIS40.003.879

1.800.360.400.000.14

TotalS4

00001123P

32111100

00000000

00000000

AM Date: 05-22-95Date:

Frequency: 10 years

S50.003.879

1.800.360.400.000.14

Flow (cfs) ———————————S5

0000113P3

33211110

00000000

00000000

p - Peak Flow

Page 79: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TABULAR DISCHARGE METHOD VERSION 1.11

ProjectCountySubtitle

LEMBERGER LTR PREFINAL DESIGNMANITOWOC State: WI

User: MAMChecked:

Date: 05-22-95Date:

Area(sq mi)Rainfall(in)Curve numberRunoff(in)Tc (hrs)

(Used)TimeToOutletla/P

Time(hr)

11.011.311.611.912.012.112.212.3

12.412.512.612.712.813.013.213.4

13.613.814.014.314.615.015.516.0

16.517.017.518.019.020.022.026.0

BAREA FLOW CALCULATONS

Continuation of subarea

S60.003.879

1.800.330.300.000.14

S6

0001135P5

32111110

00000000

00000000

S70.003.879

1.800.360.400.000.14

ouJJd j. cdS7

0000012P2

22111000

00000000

00000000

S80.003.879

1.800.360.400.000.14

Contribution toS8

00000112P

21111000

00000000

00000000

information

S90.003.879

1.800.360.400.000.14

Total FlowS9

00000IP11

11110000

00000000

00000000

S100.003.879

1.800.360.400.000.14

( CIS f •"•S10

0000112P2

22111000

00000000

00000000

P - Peak Flow

Page 80: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TR-55 TABULAR DISCHARGE METHOD VERSION 1.11 -

Proj ectCountySubtitle

LEMBERGER LTR PREFINAL DESIGNMANITOWOC State: WISUBAREA FLOW CALCULATONS

User: MAMChecked: __

Date: 05-22-95Date: ______

Total watershed area: 0.003 sq mi Rainfall type: II Frequency: 10 years- - — — e?-iiVvavj=»ae — _ — . — —. — —. — —, — — — — — — — — — — — — .— — — —

Area(sq mi)Rainfall(in)Curve numberRunoff(in)Tc (hrs)

(Used)TimeToOutletla/PTime Total(hr) Flow

11.011.311.611.912.012.112.212.3

12.412.512.612.712.813.013.213.4

13.613.814.014.314.615.015.516.0

16.517.017.518.019.020.022.026.0

)n)er

)et

1 -

00000223P

32221000

00000000

00000000

Sll0.003.879

1.800.360.400.000.14

Sll

00000112P

21111000

00000000

00000000

S120.003.879

1.800.360.400.000.14

———— Subarea Contribution to Total Flow (cfs)S12

00000IP11

11110000

00000000

00000000

P - Peak Flow

Page 81: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignCalculation of velocities for downchutes and swalesManning's equation usedn=.025

Down chuteor Swale

S1

ActualFlowcfs

ActualSlope

ft/ft

0.0052

Trial

Wetted Hydraulic Estimated Estimated

1234

Depthft

0.200.300.310.32

Area Perimetersoft

0.841.441.511.57

ft

4.264.904.965.02

Radiusfi

0.1970.2940.3040.313

Flowcfs

1.212.722.913.10

Velocityft/sec

1.441.891.931.97

S2 0.0112 1234

0.200.250.260.27

0.841.131.191.25

4.264.584.644.71

0.1970.2460.2550.265

1.782.762.993.22

2.122.462.522.58

S3 0.0082 1234

0.200.300.320.33

0.841.441.571.64

4.264.905.025.09

0.1970.2940.3130.323

1.523.413.894.15

1.812.372.472.52

S4 0.0162 1234

0.200.220.230.24

0.840.951.011.07

4.264.394.454.52

0.1970.2160.2260.236

2.142.582.823.06

2.552.712.792.87

S5 0.0114 1234

0.200.240.250.26

0.841.071.131.19

4.264.524.584.64

0.1970.2360.2460.255

1.792.572.793.01

2.142.412.482.54

S6 0.0104 1234

0.300.330.340.35

1.441.641.711.79

4.905.095.155.21

0.2940.3230.3330.342

3.844.674.975.28

2.672.842.902.96

S7 0.0112 1234

0.190.200.210.22

0.790.840.890.95

4.204.264.334.39

0.1870.1970.2070.216

1.611.781.962.14

2.052.122.192.26

Page 1

Page 82: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignCalculation of velocities for downchutes and swalesManning's equation usedn=.025

Downchuteor Swale

S8

ActualFlowcfs

ActualSlope

ft/ft

0.0094

S9 0.0083

S10 0.0097

S11 0.0113

S12 0.0111

DC1 17 0.0200

DC2 10 0.0200

Wetted Hydraulic Estimated Estimated

Trial

1234

1234

1234

1234

1234

1234

Depthft

0.200.210.220.23

0.100.140.150.16

0.180.200.210.22

0.180.200.210.22

0.100.120.140.15

0.300.500.520.53

Area Perimetersoft

0.840.890.951.01

0.360.540.590.63

0.730.840.890.95

0.730.840.890.95

0.360.450.540.59

1.443.003.183.28

Erosion Control Matting

1234

0.350.390.400.41

1.792.082.162.24

ft

4.264.334.394.45

3.633.893.954.01

4.144.264.334.39

4.144.264.334.39

3.633.763.893.95

4.906.166.296.35

Needed

5.215.475.535.59

0.0990.1380.1480.158

0.1770.1970.2070.216

0.1770.1970.2070.216

0.0990.1190.1380.148

0.2940.4870.5060.516

0.3420.3810.3910.400

0.410.770.881.00

1.351.661.822.00

1.461.791.972.15

0.480.670.891.02

5.3315.5716.9517.67

7.329.179.67

10.19

1.151.441.511.57

1.841.972.042.10

1.982.132.202.27

1.331.501.661.74

3.705.195.335.39

4.104.404.484.55

Erosion Control Matting Needed

Page 2

Page 83: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

RIPRAP CALCULATIONS

Page 84: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignCalculation of velocities for downchutes and swalesManning's equation used

n=.025

Down chuteor Swale

ActualFlowcfs

ActualSlope

B/Q

S1 0.0052

Wetted Hydraulic Estimated Estimated

Trial

1234

Depthfi

0.200.300.350.38

Areason

0.721.171.421.57

Perimeterfi

4.264.905.215.40

Radiusn

0.1690.2390.2720.291

Flowcfs

0.941.922.542.95

Velocit;ft/sec

1.301.641.791.88

S2 0.0112 1234

0.200.250.300.31

0.720.941.171.22

4.264.584.904.96

0.1690.2050.2390.246

1.382.042.822.99

1.912.172.412.46

S3 0.0082 1234

0.200.300.400.39

0.721.171.681.63

4.264.905.535.47

0.1690.2390.3040.297

1.182.414.073.89

1.632.062.422.39

S4 0.0162 1234

0.200.250.300.28

0.720.941.171.08

4.264.584.904.77

0.1690.2050.2390.225

1.652.453.393.00

2.302.612.902.79

S5 0.0114 1234

0.200.250.300.31

0.720.941.171.22

4.264.584.904.96

0.1690.2050.2390.246

1.392.062.853.02

1.932.192.432.48

S6 0.0104 1234

0.300.350.400.42

1.171.421.681.79

4.905.215.535.66

0.2390.2720.3040.316

2.723.594.585.02

2.322.532.732.80

S7 0.0112 1234

0.190.200.250.24

0.680.720.940.89

4.204.264.584.52

0.1610.1690.2050.198

1.261.382.041.90

1.851.912.172.12

Page 1

Page 85: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignCalculation of velocities for downchutes and swalesManning's equation used

n=.025

Actual ActualDownchute Flow Slopeor Swale cfs ft/ft

S8 2 0.0094

Wetted Hydraulic Estimated Estimated

Trial

1234

Depthft

0.200.240.250.26

Areason

0.720.890.940.98

Perimetera

4.264.524.584.64

Radiusfl

0.1690.1980.2050.212

FlowCfs

1.261.741.872.00

Velocitft/sec

1.751.941.992.04

S9 0.0083 1234

0.100.150.160.18

0.330.520.560.64

3.633.954.014.14

0.0910.1310.1390.154

0.360.720.800.99

1.091.391.441.55

S10 0.0097 1234

0.180.200.250.26

0.640.720.940.98

4.144.264.584.64

0.1540.1690.2050.212

1.061.281.902.03

1.671.782.022.07

S11 0.0113 1234

0.180.200.250.24

0.640.720.940.89

4.144,264.584.52

0.1540.1690.2050.198

1.151.382.051.90

1.801.922.182.13

S12 0.0111 1234

0.100.150.160.17

0.330.520.560.60

3.633.954.014.08

0.0910.1310.1390.146

0.410.830.931.03

1.261.601.671.73

Page 2

Page 86: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LTR Prefinal DesignCalculation of velocities for downchutes and swalesManning's equation used

n=.025

Downchuteor Swale

DC1

ActualFlowcfs

17

ActualSlopefl/S

0.0200

Wetted Hydraulic Estimated Estimated

Trial

1234

Depthfi

0.400.700.680.67

Areasqft

1.683.573.433.36

Perimeterft

5.537.437.307.24

RadiusS

0.3040.4810.4690.464

FlowCfs

6.3618.3717.3616.86

Velocitft/sec

3.785.155.065.02

Erosion Control Matting Needed

DC1 17 0.2000

At 5:1 grade

Riprap Needed

For Design of Riprap

Equivalent Diameter of Circular Pipe, inches

1234

0.300.350.360.37

1.171.421.471.52

4.905.215.285.34

0.2390.2720.2780.285

11.9215.7516.5717.42

10.1911.1111.2811.46

Using Figure 4.47 (attached)Riprap Size = 0.65 feetLength of Apron = 16 feet

Use 0.75 feet

16.70

DC2 10 0.0200 1234

0.350.450.500.51

1.421.962.252.31

5.215.856.166.23

0.2720.3350.3650.371

4.987.919.6310.00

3.514.044.284.33

Erosion Control Matting Needed

DC2 10 0.2000

At 5:1 grade

Riprap Needed

For Design of Riprap

Equivalent Diameter of Circular Pipe, inches

1234

0.200.300.280.27

0.721.171.081.03

4.264.904.774.71

0.1690.2390.2250.219

5.8111.9210.539.87

8.0710.199.809.60

Using Figure 4.47 (attached)Riprap Size = 0.45 feetLength of Apron = 14 feet

Use 0.50 feet

13.73

Page 3

Page 87: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Figure 4.47Outlet Protection Design - Minimum Tallwater Condition

New York Guidelines for UrbanErosion and Sediment Control

Page 4.104 March 1988

Page 88: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAlCOUViPIRNIE

B

Page 89: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX B

Cover Stability AnalysisCalculations

FINAL DESIGN REPORT

LTR Site Closure

Prepared for:

Lemberger Site Remediation Group

Submitted by:

Malcolm Pirnie, Inc.Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, MN 55416

Page 90: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

I A A I rV~y I 4/VtAllXJIJVlPi DM II-nKINIt

MALCOLM PIRNIE, INC. / I

b <v"CHKP. BYi............ DATE..

SHEET NO

JOB NO

I C......I.OF......X.....

Page 91: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

PIRNIEMALCOLM PIRNIE, INC.

r$r?^p........ DATE.

f/........... DATE-

SHEET NO..

JOB Ma.B^i-.CO'a... iyc i........

(! M

Page 92: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

\wcoyviPIRNIE

MALCOLM PIRNIE. INC.

BY..

CHKfl, BY.A.-........ DATE.............

SHEET NO.....r?..... OF.

JOBN

Page 93: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUOOUVtPIRNIEMALCOLU-PIRNIE, INC. T^ /> x^" i

fo!il.JA. SHEET N0.....a

CHKD. fc¥^............ DATE.

SUBJECT..,

SHEET N0........1... OF.,

JOB NO..... ?.«O. '

2.' j k l '-i -*—\—

>iS°i -

.-l!2."l3ePTtl_i I.3Q£

>I3

Page 94: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUOOUVIPIRNIE

MALCOLM PIRNIE, INC.

CHKD.B*.............. DATE.

SUBJECT.

SHEET NO..S....... OF

JOB

. J.

JSJJE_

Page 95: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

tt 10 X 10 TO THE INCH. ; x 10 INCHESKLUff-'Li. a. tSSEH CO UAUI m u s t 46 0782

Page 96: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

********************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

***** RESULTS *****

Critical Surface

Page 97: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Factor of Safety : 1.727

Page 98: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

L-T1Z-GeoSlope

Version 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

*************************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

***** RESULTS *****

Critical Surface

Page 99: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Factor of Safety : 1.419

Page 100: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

********************

Problem Title : LEMBERGER TRANSPORT & RECYCLING CLOSUREDescription : CAP STABILITY

Remarks : LTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

***** RESULTS *****

Critical Surface

Page 101: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Factor of Safety : 1.571

Page 102: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

*************************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

Piezometric Surfaces

Number of Surfaces : 1Unit Weight of Water : 62.40 pcf

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

Page 103: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

***** RESULTS *********************!

Critical Surface

Factor of Safety : 1.373

Page 104: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

*************************

Problem Title : LEMBERGER TRANSPORT & RECYCLING CLOSUREDescription : CAP STABILITY

Remarks : LTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

Piezometric Surfaces

Number of Surfaces : 1Unit Weight of Water : 62.40 pcf

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

Page 105: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

***** RESULTS *********************:

Critical Surface

Factor of Safety : 1.318

Page 106: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

********************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

Piezometric Surfaces

Number of Surfaces : 1Unit Weight of Water : 62.40 pcf

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

Page 107: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

***** RESULTS *********************?

Critical Surface

Factor of Safety : 1.379

Page 108: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

********************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

Piezometric Surfaces

Number of Surfaces : 1Unit Weight of Water : 62.40 pcf

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

Page 109: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

***** RESULTS *********************!

Critical Surface

Factor of Safety : 5.154

Page 110: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

*************************

GeoSlopeVersion 5.10

(c)1992 by GEOCOMP Corp, Concord, MALicensed to Malcolm Pirnie

********************

Problem TitleDescription

Remarks

LEMBERGER TRANSPORT & RECYCLING CLOSURECAP STABILITYLTR-1

***** INPUT DATA *****

Profile Boundaries

Number of Boundaries : 13Number of Top Boundaries : 6

Soil Parameters

Number of Soil Types : 6

Piezometric Surfaces

Number of Surfaces : 1Unit Weight of Water : 62.40 pcf

***** TRIAL SURFACE GENERATION *****

Data for Generating Rankine Block Surfaces

Number of Trial Surfaces : 500Number of Boxes : 2

Segment Length, ft : 1.00 ft

Page 111: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

***** RESULTS *********************]

Critical Surface

Factor of Safety : 5.091

Page 112: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

******************

HYDROLOGIC EVALUATION OF LANDFILL PERFORMANCEHELP MODEL VERSION 3.01 (14 OCTOBER 1994)

DEVELOPED BY ENVIRONMENTAL LABORATORYUSAE WATERWAYS EXPERIMENT STATION

FOR USEPA RISK REDUCTION ENGINEERING LABORATORY

******************

PRECIPITATION DATA FILE:TEMPERATURE DATA FILE:SOLAR RADIATION DATA FILE:EVAPOTRANSPIRATION DATA:SOIL AND DESIGN DATA FILE:OUTPUT DATA FILE:

C:\HELP3\DATA4.D4C:\HELP3\DATA7.D7C:\HELP3\DATA13.D13C:\HELP3\DATA11.D11C:\HELP3\DATA10.D10C:\HELP3\LTR.OUT

TIME: 10:24 DATE: 6/ 6/1995

TITLE: LTR STABILITY CHECK

NOTE: INITIAL MOISTURE CONTENT OF THE LAYERS AND SNOW WATER WERECOMPUTED AS NEARLY STEADY-STATE VALUES BY THE PROGRAM.

LAYER 1

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 9

THICKNESS = 6.00 INCHESPOROSITY = 0.5010 VOL/VOLFIELD CAPACITY = 0.2840 VOL/VOLWILTING POINT = 0.1350 VOL/VOLINITIAL SOIL WATER CONTENT = 0.3321 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.190000006000E-03 CM/SEC

NOTE: SATURATED HYDRAULIC CONDUCTIVITY IS MULTIPLIED BY 3.00FOR ROOT CHANNELS IN TOP HALF OF EVAPORATIVE ZONE.

Page 113: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LAYER 2

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 7

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =

30.00 INCHES0.4730 VOL/VOL0.2220 VOL/VOL0.1040 VOL/VOL0.2044 VOL/VOL

EFFECTIVE SAT. HYD. COND. = 0.520000001000E-03 CM/SEC

LAYER 3

TYPE 2 - LATERAL DRAINAGE LAYERMATERIAL TEXTURE NUMBER 5

12.00 INCHES0.4570 VOL/VOL0.1310 VOL/VOL0.0580 VOL/VOL0.1394 VOL/VOL

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT -EFFECTIVE SAT. HYD. COND.SLOPEDRAINAGE LENGTH

0.100000005000E-02 CM/SEC3.00 PERCENT

950.0 FEET

LAYER 4

TYPE 4 - FLEXIBLE MEMBRANE LINERMATERIAL TEXTURE NUMBER $5

THICKNESS = 0.06v INCHESPOROSITY = 0.0000 VOL/VOLFIELD CAPACITY = 0.0000 VOL/VOLWILTING POINT = 0.0000 VOL/VOLINITIAL SOIL WATER CONTENT = 0.0000 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.199999996000E-12 CM/SECFML PINHOLE DENSITY - 0.00 HOLES/ACRE'FML INSTALLATION DEFECTS = 0.00 HOLES/ACREFML PLACEMENT QUALITY = 4 - POOR

LAYER 5

TYPE 3 - BARRIER SOIL LINERMATERIAL TEXTURE NUMBER 16

THICKNESS = 24.00 INCHESPOROSITY = 0.4270 VOL/VOLFIELD CAPACITY = 0.4180 VOL/VOLWILTING POINT = 0.3670 VOL/VOL

Page 114: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

INITIAL SOIL WATER CONTENT = 0.4270 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.100000001000E-06 CM/SEC

LAYER 6

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 5

THICKNESS = 12.00 INCHESPOROSITY = 0.4570 VOL/VOLFIELD CAPACITY = 0.1310 VOL/VOLWILTING POINT = 0.0580 VOL/VOLINITIAL SOIL WATER CONTENT = 0.1272 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.100000005000E-02 CM/SEC

GENERAL DESIGN AND EVAPORATIVE ZONE DATA

NOTE: SCS RUNOFF CURVE NUMBER WAS COMPUTED FROM DEFAULTSOIL DATA BASE USING SOIL TEXTURE # 9 WITH AFAIR STAND OF GRASS, A SURFACE SLOPE OF 3.%AND A SLOPE LENGTH OF 950. FEET.

SCS RUNOFF CURVE NUMBER = 80.70FRACTION OF AREA ALLOWING RUNOFF = 100.0 PERCENTAREA PROJECTED ON HORIZONTAL PLANE = 1.000 ACRESEVAPORATIVE ZONE DEPTH = 20.0 INCHESINITIAL WATER IN EVAPORATIVE ZONE - 4.574 INCHESUPPER LIMIT OF EVAPORATIVE STORAGE = 9.628 INCHESLOWER LIMIT OF EVAPORATIVE STORAGE = 2.266 INCHESINITIAL SNOW WATER = V0-416 INCHESINITIAL WATER IN LAYER MATERIALS = 21.573 INCHESTOTAL INITIAL WATER = 21.989 INCHESTOTAL SUBSURFACE INFLOW = 0.00 INCHES/YEAR

EVAPOTRANSPIRATION AND WEATHER DATA

NOTE: EVAPOTRANSPIRATION DATA WAS OBTAINED FROMGREEN BAY WISCONSIN

MAXIMUM LEAF AREA INDEX = 2.00START OF GROWING SEASON (JULIAN DATE) = 130END OF GROWING SEASON (JULIAN DATE) = 275AVERAGE ANNUAL WIND SPEED = 10.10 MPHAVERAGE 1ST QUARTER RELATIVE HUMIDITY = 73.00 %AVERAGE 2ND QUARTER RELATIVE HUMIDITY = 68.00 %AVERAGE 3RD QUARTER RELATIVE HUMIDITY = 74.00 %AVERAGE 4TH QUARTER RELATIVE HUMIDITY - 76.00 %

Page 115: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

NOTE: PRECIPITATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

NORMAL MEAN MONTHLY PRECIPITATION (INCHES)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

1.19 1.05 1.90 2.70 3.13 3.173.25 3.16 3.17 2.10 1,76 1.42

NOTE: TEMPERATURE DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

NORMAL MEAN MONTHLY TEMPERATURE (DEGREES FAHRENHEIT)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

14.00 17.80 28.60 43.70 55.10 64.7069.50 67.50 58.90 48.40 34.20 20.80

NOTE: SOLAR RADIATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

STATION LATITUDE = 44.29 DEGREES

AVERAGE MONTHLY VALUES IN INCHES FOR YEAR£ 1 THROUGH 50

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

PRECIPITATION

TOTALS

STD. DEVIATIONS

RUNOFF

TOTALS

STD. DEVIATIONS

EVAPOTRANSPIRATION

1.013.75

0.471.83

0.1470.057

0.2780.133

1.033.01

0.601.33

0.5050.025

0.6340.061

2.032.94

0.851.26

1.4870.016

1.0950.042

2.741.98

1.171.06

0.9540.016

0,7950.093

3.221.87

1.490.85

0.0550.087

0.1550.250

3.321.34

1.590.62

0.0190.270

0.0510.380

Page 116: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TOTALS

STD. DEVIATIONS

0.4.

0.1.

LATERAL DRAINAGE COLLECTED

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

0.0.

0.0.

THROUGH

0.0.

0.0.

THROUGH

0.0.

0.0.

488709

078318

0.5332.418

0,1340.949

12

00

.241

.876

.406

.754

21

00

.375

.204

.548

.311

20

10

.964

.635

.091

.168

30

10

.955

.446

.273

.082

FROM LAYER 3

05010532

01080105

LAYER

00010001

00000000

LAYER

00060006

00060005

0.04470.0517

0.00960.0091

5

0.00010.0001

0.00000.0000

6

0.00050.0006

0.00050.0005

00

00

00

00

00

00

.0493

.0501

.0106

.0089

.0001

.0001

.0000

.0000

.0006

.0005

.0006

.0005

00

00

00

00

00

00

.0484

.0524

.0107

.0098

.0001

.0001

.0000

.0000

.0006

.0005

.0006

.0005

00

00

00

00

00

00

.0529

.0515

.0126

.0100

.0001

.0001

.0000

.0000

.0006

.0005

.0006

.0005

00

00

00

00

00

00

.0523

.0515

.0116

.0086

.0001

.0001

.0000

.0000

.0005

.0005

.0005

.0005

AVERAGES OF MONTHLY AVERAGED DAILY HEADS (INCHES)

DAILY AVERAGE HEAD ACROSS LAYER 5

AVERAGES

STD. DEVIATIONS

24.7881 24.5993 24.4125 24.9788 27.2827 28.041427.3209 26.0655 26.1116 26.6283 27.2945 25.9500

6.32197.2736

6.28066.1211

6.23976.2863

6.71886.7794

8.46007.2088

8.50055.6028

AVERAGE ANNUAL TOTALS & (STD. DEVIATIONS) FOR YEARS 1 THROUGH 50

INCHES CU. FEET PERCENT

PRECIPITATION 28.24 ( 4.153) 102501.8 100.00

RUNOFF 3.637 ( 1.4832) 13201.77 12.880

EVAPOTRANSPIRATION 23.845 ( 3.0174) 86557.53 84.445

Page 117: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LATERAL DRAINAGE COLLECTEDFROM LAYER 3

PERCOLATION/LEAKAGE THROUGHFROM LAYER 5

AVERAGE HEAD ACROSS TOPOF LAYER 5

PERCOLATION/LEAKAGE THROUGHFROM LAYER 6

0.60802 ( 0.11676)

0.00108 ( 0.00027}

26.123 ( 6.455)

0.00665 ( 0.00654)

2207.121 2.15325

3.928 0.00383

24.131 0.02354

CHANGE IN WATER STORAGE 0.141 ( 2.3484) 511.22 0.499

Page 118: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

PEAK DAILY VALUES FOR YEARS 1 THROUGH 50

PRECIPITATION

RUNOFF

DRAINAGE COLLECTED FROM LAYER 3

PERCOLATION/LEAKAGE THROUGH LAYER 5

AVERAGE HEAD ACROSS LAYER 5

PERCOLATION/LEAKAGE THROUGH LAYER 6

SNOW WATER

MAXIMUM VEG. SOIL WATER (VOL/VOL)

MINIMUM VEG. SOIL WATER (VOL/VOL)

(INCHES)

3.53

3.484

0.00256

0.000005

46.755

0.000107

3.86

0.

0.

(CU. FT.)

12813.899

12647.7920

9.30783

0.01924

0.38695

14007.1230

4737

0991

Page 119: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

FINAL WATER STORAGE AT END OF YEAR 50

LAYER

1

2

3

4

5

6

SNOW WATER

(INCHES)

1.7997

10.0171

5.4840

0.0000

10.2480

1.2476

0.000

(VOL/VOL)

0.3000

0.3339

0.4570

0.0000

0.4270

0.1040

Page 120: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

******************

HYDROLOGIC EVALUATION OF LANDFILL PERFORMANCEHELP MODEL VERSION 3.01 (14 OCTOBER 1994)

DEVELOPED BY ENVIRONMENTAL LABORATORYUSAE WATERWAYS EXPERIMENT STATION

FOR USEPA RISK REDUCTION ENGINEERING LABORATORY

******************

PRECIPITATION DATA FILE:TEMPERATURE DATA FILE:SOLAR RADIATION DATA FILE:EVAPOTRANSPIRATION DATA:SOIL AND DESIGN DATA FILE:OUTPUT DATA FILE:

C:\HELP3\DATA4.D4C:\HELP3\DATA7.D7C:\HELP3\DATA13.D13C:\HELP3\DATA11.D11C:\HELP3\DATA10.D10C:\HELP3\LTR-2.0UT

TIME: 10:34 DATE: 6/ 6/1995

TITLE: LTR STABILITY CHECK

NOTE: INITIAL MOISTURE CONTENT OF THE LAYERS AND SNOW WATER WERECOMPUTED AS NEARLY STEADY-STATE VALUES BY THE PROGRAM.

LAYER 1

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 9

THICKNESS = 6.00 INCHESPOROSITY = 0.5010 VOL/VOLFIELD CAPACITY = 0.2840 VOL/VOLWILTING POINT = 0.1350 VOL/VOLINITIAL SOIL WATER CONTENT = 0.3321 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.190000006000E-03 CM/SEC

NOTE: SATURATED HYDRAULIC CONDUCTIVITY IS MULTIPLIED BY 3.FOR ROOT CHANNELS IN TOP HALF OF EVAPORATIVE ZONE.

00

Page 121: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LAYER 2

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 7

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =EFFECTIVE SAT. HYD. COND.

30.00 INCHES0.4730 VOL/VOL0.2220 VOL/VOL0.1040 VOL/VOL0.2044 VOL/VOL

0.520000001000E-03 CM/SEC

LAYER 3

TYPE 2 - LATERAL DRAINAGE LAYERMATERIAL TEXTURE NUMBER 1

INCHESTHICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =EFFECTIVE SAT. HYD. COND.SLOPEDRAINAGE LENGTH

12.000.4170 VOL/VOL0.0450 VOL/VOL0.0180 VOL/VOL0.0491 VOL/VOL

0.999999978000E-02 CM/SEC• 3.00 PERCENT950.0 FEET

LAYER 4

TYPE 4 - FLEXIBLE MEMBRANE LINERMATERIAL TEXTURE NUMBER f5

THICKNESS = 0.06-i1 INCHESPOROSITY = 0.0000 VOL/VOLFIELD CAPACITY = 0.0000 VOL/VOLWILTING POINT = 0.0000 VOL/VOLINITIAL SOIL WATER CONTENT = 0.0000 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.199999996000E-12 CM/SECFML PINHOLE DENSITY = 0.00 HOLES/ACRE-FML INSTALLATION DEFECTS = 0.00 HOLES/ACREFML PLACEMENT QUALITY = 4 - POOR

LAYER 5

TYPE 3 - BARRIER SOIL LINERMATERIAL TEXTURE NUMBER 16

THICKNESS = 24.00 INCHESPOROSITY = 0.4270 VOL/VOLFIELD CAPACITY = 0.4180 VOL/VOLWILTING POINT = 0.3670 VOL/VOL

Page 122: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

INITIAL SOIL WATER CONTENT - 0.4270 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.100000001000E-06 CM/SEC

LAYER 6

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 5

THICKNESS = 12.00 INCHESPOROSITY = 0.4570 VOL/VOLFIELD CAPACITY = 0.1310 VOL/VOLWILTING POINT = 0.0580 VOL/VOLINITIAL SOIL WATER CONTENT = 0.1272 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.100000005000E-02 CM/SEC

GENERAL DESIGN AND EVAPORATIVE ZONE DATA

NOTE: SCS RUNOFF CURVE NUMBER WAS COMPUTED FROM DEFAULTSOIL DATA BASE USING SOIL TEXTURE # 9 WITH AFAIR STAND OF GRASS, A SURFACE SLOPE OF 3.%AND A SLOPE LENGTH OF 950. FEET.

SCS RUNOFF CURVE NUMBER = 80.70FRACTION OF AREA ALLOWING RUNOFF = 100.0 PERCENTAREA PROJECTED ON HORIZONTAL PLANE = 1.000 ACRESEVAPORATIVE ZONE DEPTH = 20.0 INCHESINITIAL WATER IN EVAPORATIVE ZONE = 4.574 INCHESUPPER LIMIT OF EVAPORATIVE STORAGE = 9.628 INCHESLOWER LIMIT OF EVAPORATIVE STORAGE = 2.266 INCHESINITIAL SNOW WATER = V0-416 INCHESINITIAL WATER IN LAYER MATERIALS = ZD.488 INCHESTOTAL INITIAL WATER = 20.904 INCHESTOTAL SUBSURFACE INFLOW = 0,00 INCHES/YEAR

EVAPOTRANSPIRATION AND WEATHER DATA

NOTE: EVAPOTRANSPIRATION DATA WAS OBTAINED FROMGREEN BAY WISCONSIN

MAXIMUM LEAF AREA INDEXSTART OF GROWING SEASON (JULIAN DATE)END OF GROWING SEASON (JULIAN DATE)AVERAGE ANNUAL WIND SPEEDAVERAGE 1ST QUARTER RELATIVE HUMIDITYAVERAGE 2ND QUARTER RELATIVE HUMIDITYAVERAGE 3RD QUARTER RELATIVE HUMIDITYAVERAGE 4TH QUARTER RELATIVE HUMIDITY

= 73

2.00130275

10.10 MPH00

68.0074.0076.00

Page 123: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

NOTE: PRECIPITATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

NORMAL MEAN MONTHLY PRECIPITATION (INCHES)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

1.19 1.05 1.90 2.70 3.13 3.173.25 3.16 3.17 2.10 1.76 1.42

NOTE: TEMPERATURE DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

NORMAL MEAN MONTHLY TEMPERATURE (DEGREES FAHRENHEIT)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

14.00 17.80 28.60 43.70 55.10 64.7069.50 67.50 58.90 48.40 34.20 20.80

NOTE: SOLAR RADIATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR GREEN BAY WISCONSIN

STATION LATITUDE = 44.29 DEGREES

AVERAGE MONTHLY VALUES IN INCHES FOR YEARS' 1 THROUGH 50

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

PRECIPITATION

TOTALS

STD. DEVIATIONS

RUNOFF

TOTALS

STD. DEVIATIONS

EVAPOTRANSPIRATION

1.013.75

0.471.83

0.1440.051

0.2760.125

1.033.01

0.601.33

0.4940.024

0.6210.059

2.032.94

0.851.26

1.4480.014

1.0350.039

2 . 7 41.98

1.171.06

0.9250.016

0.7540.092

4

3.221.87

1.490.85

0.0490.085

0.1430.249

3.321.34

1.590.62

0.0160.257

0.0490.363

Page 124: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TOTALS

STD. DEVIATIONS

0.4884.029

0.0781.453

0.5332.220

0.1341.006

1.2322.783

0.3790.753

2.4171.217

0.5360.312

2.9610.641

1.0930.174

3.9550.447

1.2580.086

LATERAL DRAINAGE COLLECTED FROM LAYER 3

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

0.16380.1578

0,08870,0787

THROUGH LAYER

0.00000.0000

0.00000,0000

THROUGH LAYER

0.00060.0006

0.00060.0006

AVERAGES OF MONTHLY

DAILY AVERAGE HEAD

AVERAGES

STD. DEVIATIONS

ACROSS LAYER

3.61603.3581

2.62982.1202

0.13640.1703

0.07750.0796

5

0.00000.0000

0.00000.0000

6

0.00050.0006

0.00060.0005

AVERAGED

5

3.29423.6782

2.48672.1793

0.13700.1589

0.08180.0766

0.00000.0000

0.00000.0000

0.00060.0005

0.00060.0005

0.12120.1617

0.07660.0787

0.00000.0000

0.00000.0000

0.00060.0005

0.00060.0005

0.12360.1567

0.07730.0761

0.00000.0000

0.00000.0000

0.00060.0005

0.00060.0005

0.12810.1684

0.07640.0848

0.00000.0000

0.00000.0000

0.00050.0005

0.00060.0005

DAILY HEADS (INCHES)

I•*2.92953.5253

2.28172.1439

2.59093.4541

2.07622.1285

2.51593.4846

1.92932.2289

2.75633.7415

2.02492.5727

AVERAGE ANNUAL TOTALS & (STD. DEVIATIONS) FOR YEARS 1 THROUGH 50

INCHES CU. FEET PERCENT

PRECIPITATION 28.24 ( 4.153) 102501.8 100.00

RUNOFF 3.522 ( 1.3741) 12784.99 12.473

EVAPOTRANSPIRATION 22.925 ( 2.8571) 83217.29 81.186

Page 125: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LATERAL DRAINAGE COLLECTEDFROM LAYER 3

PERCOLATION/LEAKAGE THROUGHFROM LAYER 5

AVERAGE HEAD ACROSS TOPOF LAYER 5

PERCOLATION/LEAKAGE THROUGHFROM LAYER 6

1.78396 ( 0.81135)

0.00013 ( 0.00008)

3.245 ( 1.869)

0.00662 ( 0.00667)

6475.774 6.31772

0.488 0.00048

24.041 0.02345

CHANGE IN WATER STORAGE 0.000 ( 2.1000) -0.34 0.000

Page 126: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

PEAK DAILY VALUES FOR YEARS 1 THROUGH 50

PRECIPITATION

RUNOFF

DRAINAGE COLLECTED FROM LAYER 3

PERCOLATION/LEAKAGE THROUGH LAYER 5

AVERAGE HEAD ACROSS LAYER 5

PERCOLATION/LEAKAGE THROUGH LAYER 6

SNOW WATER

MAXIMUM VEG. SOIL WATER (VOL/VOL)

MINIMUM VEG. SOIL WATER (VOL/VOL)

(INCHES)

3.53

3.380

0.01200

0.000001

11.827

0.000107

3.86

0

0

(CU. FT.)

12813.899

12270.1094

43.55378

0.00487

0.38700

14007.1230

.3439

.0991

Page 127: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

FINAL WATER STORAGE AT END OF YEAR 50

LAYER (INCHES) (VOL/VOL)

1 1.7991 0.2999

2 6.7505 0.2250

3 0.6665 0.0555

4 0.0000 0.0000

5 10.2480 0.4270

6 1.2014 0.1001

SNOW WATER 0.000

Page 128: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAlHDUVtPIRNIE

tfTMX

YCLED PAPER

Page 129: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX C

Oversight Health andSafety Plan

FINAL DESIGN REPORT

LTR Site Closure

Prepared for:

Lemberger Site Remediation Group

Submitted by:

Malcolm Pirnie, Inc.Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, MN 55416

Page 130: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

HEALTH AND SAFETY PLANTABLE OF CONTENTS

Page

1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11.1 Scope and Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11.2 Regulatory Requirements and Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-21.3 Site Description and Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 -2

2.0 ORGANIZATION OF HEALTH AND SAFETY RELATED FUNCTIONS . . . . . . . . . 2-1

3.0 SAFE WORK PRACTICES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1

4.0 HAZARD ASSESSMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-14.1 Description of Field Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-14.2 Chemical Exposures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-24.3 Physical Hazards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4

5.0 SITE CONTROL AND WORK ZONES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15.1 Access/Egress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15.2 WorkZones . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

6.0 COMMUNICATION PROCEDURES AND EMPLOYEE TRAINING . . . . . . . . . . . . . 6-16.1 Prefield Activities Health and Safety Orientation . . . . . . . . . . . . . . . . . . . . . . . . . 6-16.2 Safety Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-26.3 Health and Safety Orientation Training . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-26.4 Hazard Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2

7.0 MEDICAL SURVEILLANCE AND EXPOSURE MONITORING . . . . . . . . . . . . . . . . . 7-17.1 Medical Surveillance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-17.2 Exposure Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2

7.2.1 Air Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-27.2.2 Cold Exposure/Heat Stess Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-4

8.0 LEVELS OF PERSONAL PROTECTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-18.1 General Protection Levels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-18.2 Required Levels of Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-3

9.0 DECONTAMINATION PROCEDURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-19.1 Protective Clothing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-19.2 Respirators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-19.3 Sanitizing of Personal Protective E q u i p m e n t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-29.4 Equipment and Machinery . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-29.5 Disposal of Decontamination Wastes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-39.6 Medical Emergencies Decontamination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-3

2049-001-331 TOC-1

Page 131: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TABLE OF CONTENTS (continued)

Page

10.0 DOCUMENTATION AND REPORTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10-1

11.0 EMERGENCY RESPONSE PLAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i 1-111.1 Pre-Emergency Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-111.2 Emergency Recognition and Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-1

11.2.1 Personnel Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-111.2.2 Emergency Contact Telephone Numbers . . . . . . . . . . . . . . . . . . . . . . . . 11-111.2.3 Emergency Alarm Signals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-211.2.4 Emergency Site Evacuation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-3

11.3 Fire Prevention and Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-311.4 Emergency Medical T r e a t m e n t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 -411.5 Incident Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11-6

12.0 EMERGENCY REFERENCES, CONTACTS AND PHONE NUMBERS . . . . . . . . . . 12-1

LIST OF TABLES

Table No.___Description Following Page

4-1 Compounds of Concern and Clean-Up Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4

LIST OF FIGURES

Figure No. Description Following Page

1-1

6-1

11-1

12-1

Lemberger Superfund Sites Site Location Map . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3

Health and Safety Label Lemberger Landfill RD/RA . . . . . . . . . . . . . . . . . . . . . . 6-4

Lemberger Superfund Sites Emergency Egress Route . . . . . . . . . . . . . . . . . . . . . 11-6

Lemberger Superfund Sites Route to Hospital . . . . . . . . . . . . . . . . . . . . . . . . . . 12-2

2049-001-331 TOC-2

Page 132: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

LIST OF ATTACHMENTS

Attachment Description

Attachment A

Attachment B

Attachment C

Attachment D

Lemberger Landfill Sign-In Sheet

Confined Space Entry Permit

Malcolm Pirnie, Inc. Hazard Communication Program

Supervisor's Incident Investigation Report

Appendix

LIST OF APPENDICES

Description

Appendix A On-Site Physical Hazards

2049-001-331 TOC-3

Page 133: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

OVERSIGHTHEALTH AND SAFETY PLAN

LEMBERGER SITEFRANKLIN TOWNSHIPMANTTOWOC COUNTY

WISCONSINMAY, 1994

Prepared by:Regional Health and

Reviewed By:Manager, Corporate Health and Safety

Reviewed by:Project Manager

MALCOLM PIRNffi, INC.5500 Wayzata BoulevardMinneapolis, MN 55416-1262

204WJ01-331/HASP

Page 134: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

1.0 INTRODUCTION

1.1 SCOPE AND PURPOSE

This Oversight Health and Safety Plan (HASP) has been developed to protect the health and

welfare of Malcolm Pimie personnel during the performance of the Lemberger Landfill (LL and LTR)

Sites closure and ground water treatment system oversight activities to be undertaken at the Lemberger

Sites, Franklin Township, Manitowoc County, Wisconsin. The United States Environmental Protection

Agency (USEPA) approval of this HASP is required prior to the commencement of the field activities

requiring a HASP.

Safety, health and emergency response procedures are outlined for preventing accidents and

protecting personnel from injury and occupational illness. Included in this HASP are the assignments

of responsibilities, personnel protection requirements, safe work practices and emergency response

procedures. Specific project objectives and scope of work are found in the Design Report or other

associated documents. The basis for this document includes available historical information and

assessment of potential physical and chemical hazards associated with the Site.

Environmental monitoring will be performed as necessary during the course of the oversight

activities to determine personnel exposures. The HASP will be modified as appropriate to address

current Site conditions, to present corrective procedures, and to address activities not covered herein.

Modifications will be made by written addenda to this HASP.

Consistent with the contents of this HASP, work will be conducted in a safe and environmentally

acceptable manner, and all Malcolm Pirnie oversight personnel shall be required to comply with the

health and safety requirements specified herein. The contractor(s) will be responsible to develop,

implement and monitor their own HASP that will interface with Malcolm Pirnie's HASP. All personnel

participating in the oversight activities shall be required to read and familiarize themselves with the

contents of this HASP and to document this competency through the entry of a signature and date as

specified in Attachment A. A copy of this HASP will be available from the Site Safety and Health

Officer during all oversight activities.

2049-001-331 1-1 HASP

Page 135: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

1.2 REGULATORY REQUIREMENTS AND GUIDELINES

This HASP has been developed in conformance with the Occupational Safety and Health

Administration (OSHA) requirements in 29 Code of Federal Regulations (CFR) Part 1910.120, to

minimize personnel exposure to environmental contamination. Contractors are responsible for their own

safety obligations as specified in applicable sections of the OSHA General Industry and Construction

Industry Standards (29 CFR Parts 1910 and 1926, respectively). Guidance from the Occupational

Safety and Health Guidance Manual for Hazardous Waste Site Activities jointly prepared by the

National Institute for Occupational Safety and Health (NIOSH), OSHA, the U.S. Coast Guard (USCG)andUSEPA, and the USEPA's Standard Operating Safety Guide has been incorporated in this HASP.

All field activities must be conducted in compliance with this HASP and with all applicable

Federal, State and Local Health and Safety regulations. Personnel covered by this HASP who cannot

or will not comply with the HASP will be excluded from Site activities. Contractors will develop their

own HASP related to their specific on-site activities.

13 SITE DESCRIPTION AND BACKGROUND

The Lemberger Site is located in Franklin Township, Manitowoc County, Wisconsin as shown

in Figure 1-1. The Site includes the Lemberger Landfill, Inc. (LL) and the Lemberger Transport and

Recycling, Inc. (LTR) properties. The two former landfills are within 1/4 mile of each other, near the

intersection of Hempton Lake Road and Sunny Slope Road (Figure 1-1). The village of Whitelaw is

located approximately three miles southeast of the Site and the Branch River is located less than one mile

northwest of the Site.

The Lemberger Site landfills are located in areas which were formerly used for gravel mining.

The LL Site functioned as an open dump from approximately 1940 to 1969. In 1969, the LL Site was

licensed as a sanitary landfill. The LTR Site was licensed in 1969 as an industrial landfill and operated

until 1976. Prior to 1969, area industrial waste had been disposed of at the LL Site and other facility

locations. Records indicate that the industrial wastes were disposed of in shallow (about five feet deep)trenches and consisted primarily of wood tar distillates and oil/water mixtures.

2049-001-331 1-2 HASP

Page 136: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Numerous Site investigations and reports have been conducted and prepared since 1976.Investigations were initiated based on leachate seeps identified at the LL Site and organic contaminantsfound in nearby residential wells. A Remedial Investigation was conducted from April 1988 to January

1990 and detailed descriptions are included in other sections of the RD/RA Work Plan. Detailed

descriptions of the landfill closure and ground water treatment system activities are discussed in theDesign Report.

2049-001-331 1-3 HASP

Page 137: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

JOHN OF FRANKLINNISCONSIN1 Lemberger

Si tes

LEMBERGERLANDFILLS

SUNNY SLOPE RD.

LEMBERGERTRANSPORTRECYCLING

SAN RD

WHITELflW

MAUOOUV1 IPiRNIE I

LEMBERGER SUPERFUND SITESSITE LOCATION MAP

FIGURE1-1

Page 138: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

2.0 ORGANIZATION OF HEALTH AND SAFETYRELATED FUNCTIONS

The Malcolm Pimie Project Officer, Program Manager, Health and Safety Manager, and Site

Safety Officer will be responsible for the implementation of this HASP. Provided below are the key

personnel for implementing and performing landfill closure and ground water treatment system oversightactivities.

Program Manager - The Program Manager provides overall direction for the implementation

of field activities in accordance with this HASP. The Program Manager will also serve as the programliaison to Federal, State, and Local authorities as well as news reporters and other media personnel inregards to all Site activities. Incident reports and specific program questions are to be directed to thisindividual.

Health and Safety Manager - The Health and Safety Manager supervises development of health

and safety guidelines and ensures that all personnel are aware of the provisions of the HASP, have been

informed of the nature of the risk of chemical exposure, and are trained in the proper use of safety

equipment and protective clothing. Safety procedures employed at the Site may be audited. [The Health

and Safety Manager will designate qualified on-site personnel to carry out safety-related functions The

Health and Safety Manager is authorized to direct any person to stop work if safety requirements are not

being met. The Health and Safety Manager is also authorized to direct resumption of work when

satisfied that any hazardous conditions are corrected.]

Site Safety Officer - The Site Safety Officer, designated by the Health and Safety Manager,

directs the implementation and field evaluation of the HASP. The Site Safety Officer has the authorityto order work to be stopped if health and safety requirements are not being met by the contractor.

Resumption of work will require concurrence of the Site Manager. The Site Safety Officer will be in

charge during any emergency.

The Site Safety Officer will be on-site during all major field activities. The Site Safety Officerwill be responsible for directing exposure monitoring when such field activities are undertaken to deem

2049-001-331 2-1 HASP

Page 139: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

monitoring necessary as outlined in this HASP. The Site Safety Officer is responsible for the final

interpretation for all air monitoring data collected.The Site Safety Officer will conduct health and safety briefings for Malcolm Pimie employees.

The frequency of these briefings will be based upon potential hazards specific to the designated work

tasks scheduled.If and when conditions arise on-site that are not fully addressed in this HASP, addenda will be

prepared by the Site Safety Officer specifying immediate health and safety procedures for those changed

conditions. Following the discovery of new conditions and the implementation of immediate protective

measures, the Site Safety Officer will consult with the Health and Safety Manager and staff to determinethe best course of action for continued work. The written addenda, containing appropriate procedures,will be submitted to the Program Manager by the Site Safety Officer for signed approval by the

Corporate Health and Safety Manager. The Addenda will then be distributed to all those included onthe distribution list for this HASP. The Site Safety Officer will be responsible for conducting a special

health and safety briefing to apprise all affected Site personnel of the new procedure.

2049-001-331 2-2 HASP

Page 140: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

3.0 SAFE WORK PRACTICES

The understanding of basic, precautionary concepts regarding personal health and safety isessential for workers assigned to sites where chemical contamination is known or suspected to bepresent. The following measures are designed to augment the specific health and safety guidelines

provided in this HASP.

• Avoidance of contamination is of the utmost importance. Whenever possible, contactwith contaminated or potentially contaminated surfaces/materials will be avoided tominimize the potential for transfer to personnel. Walk around, not through, puddles anddiscolored surfaces. Do not kneel on or set equipment on contaminated ground.

• Eating, drinking, chewing gum or tobacco, smoking or any practice which increases theprobability of hand-to-mouth transfer of contaminated material is strictly prohibitedthroughout the Site with the exception of the field command post.

• The hands and face must be thoroughly washed upon leaving the work area and prior toengaging in any activity indicated above. Each individual must shower as soon aspossible after the removal of protective clothing and equipment after the completion ofthe daily field activities.

• Any required respiratory protective equipment and clothing must be worn by all personnelentering those designated areas of the Site. Excessive facial hair (i.e., beards, longmustaches or sideburns), which interferes with the desired respirator-to-face seal isprohibited.

• When it is necessary for a visitor to observe the field work, that person will be issuedappropriate personal protective equipment, briefed on potential hazards, safety practices,decontamination procedures and Site communications. Respiratory equipment and proofof medical clearance and training/fit testing must be provided by all Site visitors to theSite Safety Officer prior to gaining access to work areas requiring respiratory protection.

• Medicine and alcohol can potentiate the effects of exposure to toxic chemicals. Due topossible contraindications, use of prescribed drugs should be reviewed with the MalcolmPimie (or contractor) occupational physician. Alcoholic beverage and illegal drug intakeare strictly forbidden during Site work activities.

• On-site personnel shall use the "buddy" system. No one may work alone; i.e., out ofearshot or visual contact with other workers.

2049-001-331 3-1 HASP

Page 141: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Personnel and equipment in contaminated areas shall be minimized, consistent witheffective Site operations.

All employees have the obligation to correct or report unsafe work conditions.

Use of contact lenses on-site will not be allowed for work conducted under respirator-required conditions. Spectacle kits for insertion into full-face respirators will be providedfor Malcolm Pirnie employees, as required.

All personnel shall be familiar with standard operating safety procedures and additionalinstructions contained in this HASP.

2049-001-331 3-2 HASP

Page 142: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

4.0 HAZARD ASSESSMENT

4.1 DESCRIPTION OF FIELD ACTIVITIES

The specific protocols to conduct landfill closure and ground water treatment system activities

at the Sites, as required by the Consent Decrees, are currently identified in the Design Report and

Technical Specifications. However, although all methodologies have not yet been fully determined, a

majority of the materials and areas for the landfill closures and ground water treatment system activities

have been identified and quantified. These include, but are not limited to:

• Field engineering and surveying.

• Roadways, access, clearing and grubbing.

• Temporary construction facilities.

• Unloading and storage of incoming materials.

• Installation of 6 ground water extraction wells and adaptation of 1 existing pumping testwell with all associated piping, pitless adaptors, valves and accessories.

• Installation of 8 leachate collection wells with all associated piping, pitless adaptors,valves and accessories at the LL Site.

• Installation of 16 observation wells and 14 additional monitoring wells with allaccessories.

• Construction of a ground water collection trench and sump (well) with all associatedpiping and accessories.

• Installation of metering vaults and raw water lines.

• Construction of pre-engineered metal building to house the ground water treatmentfacilities.

• Construction of untreated ground water storage tanks.

• Installation of a ground water treatment system.

2049-001-331 4-1 HASP

Page 143: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Installation of pumps, with all associated piping, valves and accessories.

Instrumentation and control systems installation.

Plumbing, HVAC, electrical and auxiliary mechanical systems installation.

Construction of a complete landfill cover at the LL Site including landfill wasterelocation, slurry wall, clay cap and final cover.

Decontamination.

Construction of a complete landfill cover at the LTR Site.

4.2 CHEMICAL EXPOSURES

The chemicals identified in the Lemberger Sites study area may be grouped into four categories:

VOCs, semi-volatile organic compounds, inorganic contaminants, and pesticides/PCBs. The volatile

and semi-volatile compounds are subdivided into categories based on general chemical and behavioral

similarities. The volatile compounds are divided into halogenated alkanes and alkenes, ketones, and

aromatics. The semi-volatile compounds are divided into phenols, polynuclear aromatics, phthalates,and other semi-volatiles.

Based on the results of the RI, the source of contamination from the Lemberger Sites is thelandfill waste. The presence of hazardous constituents in the landfill is indicated by the chemical

composition of the ground water. Volatile and semi-volatile organic compounds, and inorganic

compounds were detected in the ground water including 1,1-dichloroethane; trichloroethelene; 1,2-

dichloroethene; acetone; toluene; ethylbenzene; xylene; 4-methyl-2-pentanone; chloroethane; 1,1,1-

trichloroethane; barium; chromium; methylene chloride; 2-butanone and cadmium. Contamination above

MCL's was found at a depth of 95.4 feet.The upper aquifer contained high concentrations (3,000 to 5,000 ug/L) of acetone and 2-

butanone, and high concentrations (41,800 to 1.3 million ug/L) of calcium, iron, magnesium, potassium

and sodium. Moderate concentrations (100 to 220 ug/L) of methylene chloride, 1,2-dichloroethene, and

tetrachloroethene were detected. Three semi-volatile phenols were also identified.Extensive volatile compounds (greater than 1,000 ug/L) were found in the lower aquifer

including chloroethane; methylene chloride; 1,1-dichloroethane; 1,2-dicloroethene; and 1,1,1-

2049-001-331 4-2 HASP

Page 144: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

trichloroethane. Phenols, phthalates, pesticides and PCBs were also detected in the lower aquifer.Concentrations begin to decrease north of the LTR Site and toward the Branch River.

Surface and subsurface soil samples at the LL Site indicate the presence of volatile compounds

ranging from 1 to 12 ug/kg and semi-volatile organic compounds ranging from 71 to 3,800 ug/kg.

Pesticides including 4,4-DDE, 4,4-DDD and 4,4-DDT were found at concentrations of 70 ug/kg, 190

ug/kg, and 42 ug/kg, respectively.At the LTR Site, surface soils contain volatile organic compounds at concentrations ranging

from 230 to 2,000 ug/kg, semi-volatile compounds ranging from 94 to 2,000 ug/kg and pesticidesincluding Aldrin at concentrations of 240 ug/kg and Dieldrin at concentrations of 200 ug/kg. Subsurface

soils at the LTR Site had lower concentrations of volatile compounds than the surface soils, ranging from

3 to 620 ug/kg. Semi-volatiles, pesticides, and PCBs were not found in the LTR subsurface soils.In January 1992, U.S. EPA collected two drum samples from the Lemberger T & R Site.

Analytical results showed levels of volatile organics ranging from 49,000 parts per million (ppm) 4-

methyl-2-pentanone, 23,000 ppm 2-butanone, 250,000 ppm toluene, 25,000 ppm ethylbenzene, and140,000 ppm total xylenes. Metals ranged from 120 ppm lead, 4.6 ppm chromium, 3.9 ppm barium,

and 27 ppm zinc. Each drum sample had a flash point of 54 degrees Fahrenheit and a pH of around 4.5.

Sediment and surface water samples were collected at and near the LL and LTR Sites,including the wetland area. Sediment samples showed low concentrations of volatile compounds;however, one sample south of the LL Site contained acetone detected at 510 ug/kg. Surface water

samples contained phthalates, methylene chloride and acetone at low levels. Of the four leachate samplelocations planned, leachate was found at only one location, in the northwest corner of the LL Site.

Organics were not detected in this sample.

The medium of concern for human exposures for current and future scenarios was identified

primarily as ground water which has been contaminated by the vertical infiltration of precipitation

through the waste and by direct contact of the waste with the ground water. The RJ detected severalchemicals in different media at both Sites and developed a list of "chemicals of potential concern" using

the following criteria:

• Chemicals retained included those positively detected in more than one sample in a givenmedium, including chemicals with no qualifiers attached and chemicals with qualifiersattached that indicated known identities and estimated concentrations (such as J-qualifieddata).

2049-001-331 4-3 HASP

Page 145: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

• Chemicals were retained that were detected at levels at least five times greater than levelsdetected in associated blank samples.

• Future LL soil risks assume on-site exposures due to residential use.

Chemicals of potential concern are listed in Table 4-1.Potential exposure to contaminants from the LL and LTR Sites may occur through:

• Exposure to ground water by direct ingestion, dermal contact, or inhalation of VOCs inthe ground water.

• Direct contact with, or ingestion of, contaminants or contaminated soil.

4.3 PHYSICAL HAZARDS

Physical hazards pose safety risks that warrant consideration. These include wet and loose soils,

jagged debris andmatenals, lifting operations, mechanical and power tools, excavation and construction

equipment and machinery, drill rigs, trip and fall hazards on the Site. A discussion of other physical

hazards including background information, is included in Appendix A.

2049-001-331 4-4 HASP

Page 146: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MA1OXMPIRNIE TABLE 4.1

COMPOUNDS OF CONCERN AND CLEAN-UP CRITERIA

Compounds of Concern

MaximumConcentrationDetected inGround Water0*/i)

Ground WaterClean-upLevels0*/l)

EffluentDischargeLevels0*/I)

VOIATILESAcetoneButanone, 2*Carbon Tetrachloride

Chloroform

Dichloroethane, lfl*Dichloroethene, 1,1-

Dkhloroethene, 1,2*

Methyl-2-pentanone, 4-Methylene ChlorideTetrachloroethene

Toluene

TrichloroetheneTrichloroethane, 1,1,1-Vinyi ChlorideXylene

14,000

21,000

82242,200

200

4,000

2,4005,000200400

510

3,20028480

1,000

500OJ0.6850.02410

100150.1

68.6

0.18400.0015124

NA

NA195*167*

NA1951

2S.1001

NA4,400*

4281

TOT.OOO1

4681

18.6001

14.01

NA

SEMI-VOLATILES

bis(2-ethylhexyl) phthalate 160 2 552,000*

1 Monthly Average LimitNA Not Available - Limit not calculated in 3/13/91 memo

Page 147: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

5.0 SITE CONTROL AND WORK ZONES

To prevent both exposure of unprotected personnel and migration of contamination due totracking by personnel or equipment, work zones will be clearly identified and partitioned as practically

possible by the contractor. Wind direction indicators, including, but not limited to wind direction socks

and weather vains, will be visibly displayed in and around the work areas. Malcolm Pirnie's Site Safety

Officer and personnel will be subject to the established site control and work zones.

5.1 ACCESS/EGRESS

Access and egress routes for both LL and LTR Sites are limited to the major roadways adjacent

to each landfill. The LL Site is located off Hempton Lake Road and the LTR Site is located off SunnySlope Road. Both Sites have access to a major roadway, and are relatively flat with vegetation cover.

During oversight activities, all vehicles will enter the LL site through an entrance road and main

gate located on the south side of the site. The pre-existing access road, located on the eastern side of the

landfill, off Hempton Lake Road, will serve as an alternate access/egress route,

5.2 WORK ZONES

To ensure that landfill closure and ground water treatment system activities go smoothly andthat worker safety is protected, time and effort will be spent in preparing the Site prior to the

commencement of field activities. Work zones around the construction and remediation areas will be

established by the contractor and communicated to all site personnel by the contractor's Site Safety

Officer. The zones include:

• Exclusion Zone ("Hot Zone"):The area where contamination may be present. All personnel entering the Exclusion Zonemust wear the prescribed level of personal protective equipment. The hotline would beinitially defined as an area 25 feet in radius originating at the proposed area underinvestigation/remediation.

2049-001-331 5-1 HASP

Page 148: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Support Zone:Outermost part of the Site which is considered non-contaminated or "clean." This areashould be located upwind from the Hot Zones with regard to prevailing winds. Supportequipment is located in this zone and personnel may wear normal work clothes within thiszone. Any potentially contaminated clothing, equipment and samples must remain in theContamination Reduction Zone until decontaminated.

Contamination Reduction Zone:This transition zone lies between the Exclusion and Support Zones. Decontamination ofpersonnel and equipment takes place in this zone. Personnel entering this zone withintentions to physically interact and/or assist persons in the Exclusion Zone must wearthe prescribed level of personal protection equipment currently required in the ExclusionZone.

Due to the size and nature of the study area, controlling Site access will be limited to minimizing

access to individual work areas. The contractor will be responsible for maintaining procedures to prevent

unauthorized personnel from entering work zones and all personnel from entering work zones without

the prescribed level of protection.

2049-001-331 5-2 HASP

Page 149: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

6,0 COMMUNICATION PROCEDURES AND EMPLOYEETRAINING

6.1 PREFIELD ACTIVITIES HEALTH AND SAFETY ORIENTATION

All Malcolm Pirnie and contractor personnel involved with the field activities associated with

the Site will attend a site-specific health and safety orientation program. The topics to be discussed

include, but are not limited to:

• Characteristics and potential hazards of chemical and other contamination known to bepresent at the Site;

• Personal protective clothing: function, donning/doffing;

• Respirators: selection, use, care;

• Personal hygiene;

• Environmental monitoring;

• General decontamination procedures;

• Work zone designations;

• Heat stress/cold stress;

• General safety concepts; and

• Site contingency plans.

Visitors will be properly orientated to existing Site conditions, planned activities, Site workzones and corresponding levels of personal protection and other procedures outlined in this HASP

relevant to their planned activities on-site. Visitors will be escorted at all times by trained Site personnel.

2049-001-331 6-1 HASP

Page 150: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

6.2 SAFETY MEETINGS

The contractor's Site Safety Officer will conduct health and safety briefings for site personnel.

The frequency of these briefings will be based upon potential hazards specific to the designated work

tasks either currently being undertaken or scheduled to be undertaken shortly.

63 HEALTH AND SAFETY ORIENTATION TRAINING

The required level of training workers must have prior to entering the Site is dependent on their

planned activities. All Malcolm Pirnie personnel involved with the landfill closure and ground watertreatment system oversight activities will have completed the health and safety training requirements of

29 CFR 1910.120 as applicable to their activities on-site.

Contractor is responsible for providing its employees applicable training to meet requirements

for construction, installation, and remediation activities conducted on Site. This includes complying with

OSHA regulations 29 CFR 1910 and 29 CFR 1926 where applicable.

6.4 HAZARD COMMUNICATION

Malcolm Pirnie, Inc. has a written communication program which was established to meet the

requirements of 29 CFR 1910.1200, and oversight activities shall be implemented in accordance withthat program, as described below.

The comprehensive list of hazardous chemicals for this job site, noting the names and

anticipated location of hazardous chemicals introduced by Malcolm Pirnie, Inc. at the worksite, will be

appended to this Health and Safety Plan (see Attachment C), and posted in the on-site trailer (ifapplicable) or command post. Material safety data sheets (MSDs) for hazardous chemicals introduced

to the Site by Malcolm Pimie, Inc. will also be provided.Labels on containers used by Malcolm Pirnie are as originally received (not to be defaced) and

are to contain the following information: (1) the identity of the hazardous chemical(s); (2) the

appropriate hazard warnings; and (3) the name and address of the chemical manufacturer. If an

employee transfers chemicals from a labeled container to a portable container, a label which contains

2049-001-331 6-2 HASP

Page 151: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

those three items must be affixed to it (see Figure 6-1). If the portable container is intended only for thatemployee's immediate use (during the same workshift), only a contents label is required. The employee

will be responsible to properly empty, clean or dispose of the portable container immediately after use.

The contractor's Site Safety Officer shall obtain the appropriate hazard communicationinformation for hazardous chemicals introduced by all employers, including:

• Explanation of that firm's labeling system.

• The name and location of each hazardous chemical, and location of MSDSs.

• Any precautionary measures other employers need to take to protect their employees fromharmful exposure to hazardous chemicals under normal operating conditions and inforeseeable emergencies.

As part of the site-specific health and safety orientation conducted by the contractor's Site SafetyOfficer, a review of the contractors hazard communication program will be conducted to inform

employees of hazardous chemicals to which they may be exposed during field activities. Other

employers may also attend this hazard communication training session. If the chemical hazard changesor a new chemical hazard is introduced into the area after work begins, additional training will be

provided by the contractor's Site Safety Officer.

Site-specific hazard communication training of hazardous chemicals introduced to the Site bythe contractor or Malcolm Pirnie will include:

• Properties and hazards (chemical, physical, lexicological) of hazardous chemicals.

• Health hazards, including signs and symptoms of exposure and any medical conditionknown to be aggravated by exposure.

• Measures employees can take to protect themselves, including: appropriate workpractices or methods for proper use and handling, procedures for emergency response,and the proper use and maintenance of personal protective equipment, as required.

• Work procedures for employees to follow to protect themselves when cleaning hazardouschemical spills and leaks.

• Use of the container labeling system and the MSDSs including: where MSDSs arelocated, how to read and interpret the information on both labels and MSDSs, and howemployees may obtain additional hazard communication information.

2049-001-331 6-3 HASP

Page 152: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Site-specific hazard communication training will also cover hazardous chemical introduced by

others and shall emphasize:

• Information about the hazardous chemicals to which the contractor's or Malcolm Pirnie'semployees may be exposed.

• An explanation of the labeling system other employers are using.

• Information about the precautionary measures that on-site personnel need to take toprotect themselves during normal operating conditions and in emergencies.

• Location of MSDSs for hazardous chemicals brought to the Site by others.

This subsection of the Health and Safety Plan, and the hazard communication training conducted

as described above, shall be the mechanism for informing on-site personnel of the hazardous chemicals

introduced to the Site.

2049-001-331 6^ HASP

Page 153: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

OMGESTIONOSKM OR EYE CONTACT

O NO HEALTH HAZARD D IRRITANTO TOXIC D CORROSIVEO HIGHLY TOXtC D SENSITIZE*D REPRODUCTIVE TOXIN O CARCINOGEN

PHVSICAL HAZARDSO NO PHYSICAL HAZARDSO COMBUSTIBLE LKXJlDO COMPRESSED GASO OXIOiZERD FLAMMABLE GASQ EXPLOSIVEO FLAMMABLE LIQUID/SOLIDD PVROPMORICD ORGANIC PEROXIDEO WATER REACTIVED UNSTABLE (REACTIVE)

TARGET ORGANS & EFFECTSD LUNGS O CENTRAL NERVOUS SYSTEMO HEART Q CARDIOVASCULAR SYSTEMO KIDNEY D MUCOUS MEMBRANESO EYES D AUTONOMtC NERVOUS SYSTEMO SKIN D RESPIRATORY SYSTEMD PROSTATE D BLOODO BLOOD D MUTAGENO LrVEM O TERATOGEN

HEALTH

FLAMMABILITY

REACTIVITY

O PROTECTIVEEQUIPMENT

Corm* MSOS tor fc*tMf fwardot* rtomttkon and

MAUDOyViPIRNIE HEALTH & SAFETY LABEL

LEMBERGER LANDFILL RO/RAFIGURE 6-1

Page 154: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

7.0 MEDICAL SURVEILLANCE AND EXPOSURE MONITORING

7.1 MEDICAL SURVEILLANCE

Malcolm Pirnie personnel, whose work may involve potential chemical exposure or presents

unusual physical parameters, will have initial or preplacement, annual and termination examinations inaccordance with 29 CFR 1910.120(f). Medical evaluations will be performed by an occupational

physician designated by Malcolm Pirnie in accordance with Malcolm Pimie's Medical Monitoring

Program.

Purpose - The purpose of the medical evaluations are to determine fitness for duty on hazardous

waste sites and to establish baseline data for future reference. Such an evaluation is based upon the

employee's occupational and medical history, a comprehensive physical examination and an evaluation

of the ability to work while wearing protective equipment,

Supplemental Examination • Supplemental examinations may be performed whenever there is

an actual or suspected excessive exposure to chemical contaminants, upon experience of exposure

symptoms or following injuries or temperature stress.Medical Records - In conformance with OSHA regulations, Malcolm Pirnie has a program to

maintain and preserve medical records for a period of 30 years plus tenure. Employees have access to

results of medical testing and to full medical records and analysis.

Contractors - Contractors must supply medical monitoring certification to the project Program

Manager for all employees scheduled to conduct work on-site. These individuals must undergo a baseline

medical examination, in accordance with 29 CFR 1910.120(f), at the expense of the contractor and

conducted by a physician practicing occupational medicine. Contents of the examination must be

determined by the contractor's physician, who will have been provided by the contractor with adequate

information to enable an evaluation of fitness to be made. The examination must include an OSHA-type

evaluation of the workers' ability to use respiratory protective equipment. Personnel who have

undergone the medical examination and been analyzed within the past year may not need to be re-

examined. Medical approval from the contractor's physician is required prior to the start of work.

2049-001-331 7-1 HASP

Page 155: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

7.2 EXPOSURE MONITORING

Exposure monitoring will be implemented by the Site Safety Officer for those oversight

activities which involve Malcolm Pirnie personnel.

7.2,1 Air Monitoring

Air monitoring will be used to identify and quantify airborne levels of hazardous substances andsafety and health hazards. Monitoring will be performed when there may be the potential of employee

exposure to hazardous substances in order to assure proper selection of engineering controls, workpractices and personnel protective equipment. This will ensure that employees are not exposed to levels

which exceed permissible exposure limits or published exposure levels for hazardous substances.Explosive Conditions • To determine the actual LEL present during landfill activites, the work

area will be periodically monitored by a direct reading combination combustible gas and oxygen (02)(and possibly carbon monoxide) meter. The frequency of monitoring will be based upon the potentialhazards specific to the designated work tasks scheduled. The LEL/O2 meter will be equipped with both

audible and visual alarms. The alarms will activate automatically if 20% of the actual LEL or if less than

19.5% O2 has been measured. Before each day's usage, sensitivity of the combustible gas meter will be

tested on a known concentration of pentane (or similar gas) in air equivalent to 25-50% of full scale

concentration. The daily sensitivity testing will be conducted following the manufacture's instructions

and will be documented in the designated field log book.

When combustible gas/02 monitoring is deemed necessary by the Site Safety Officer, the

following action levels will be followed:

Explosive Gas Reading Action

< 10% LEL Normal operation

10% - 25% LEL Proceed with caution

> 25% LEL Explosive hazard - all activitiescease; withdraw from area

2049-001-331 7-2 HASP

Page 156: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

If > 25% of the actual LEL is measured in the ambient air, the area will be allowed to vent untilthe reading drops to less than about 15% LEL. If, after a reasonable time period, the LEL does notsubside, measures will be initiated to eliminate the source of LEL or to ventilate the air space.

O, Reading Action

< 19.5% Cease activities and withdrawfrom area.

19.5 - 25.5% Continue with caution.

>25% Firehazard potential. Discontinueinvestigation. Consult fire safetyspecialist.

Note: Combustible gas readings are not valid in atmospheres with less than 19.5% oxygen.

DustAs a rule of thumb, persistent dust levels greater than 2.5 times background should be cause for

concern. Engineering controls, including dust suppression, should be used to reduce the level of airbornedust. If dust levels persist consideration should be given to upgrading to air-purifying respirators. Asappropriate, action levels for dust tainted with specific contaminants may be developed.

Volatile Organic Vapors - Direct reading instruments will be utilized to measure abovebackground concentrations of airborne volatile organic compounds (VOCs). A flame ionization detector(FID), a photoionization detector (PID), or similar instrument will be employed to measure the airborne

VOC concentration. The organic vapor detectors will be calibrated prior to use in accordance with the

manufacturer's instructions. Designated personnel will conduct daily response and span checks of theinstruments in accordance with the manufacturer's instructions. This activity will be documented in thefield log book.

Monitoring will be conducted in the breathing zone directly adjacent to work areas. If anypositive results are encountered, monitoring will be continued away from the area until background levels

are found and the distance from the source activity and wind direction will be noted.Adjustments to the prescribed level of personnel protection will be considered based on general

guidelines associated with ambient air readings. These guidelines are as follows;

2049-001-331 7-3 HASP

Page 157: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Air Reading Level of Respiratory(vapor/gas concentration) Protection

• Background D

• Background to 5 ppm above background C

• 5 ppm above background to 500 ppm Babove background

D = noneC = air purifying cartridge respiratorB = self contained breathing apparatus

Although total vapor/gas concentration measurements are useful for the selection of protective

equipment, the protection level will not be based solely on the total vapor/gas criterion. Rather, the level

will be selected case by case, with special emphasis on potential exposure and chemical and lexicological

characteristics of the known or suspected material(s). The 5 ppm action level is for unknown

compounds. If specific constituents are identified, the level may be adjusted based on establishedexposure guidelines. In addition, the presence of visible dust may trigger the upgrade of protective gear

to include an air purifying respirator.

7.2.2 Cold Exposure/Heat Stress MonitoringSince some field activities may be scheduled during colder months, measures will be taken to

minimize worker exposure to the cold. Persons working outdoors in temperatures at or below freezingmay be subject to frostbite. Extreme cold for a short time may cause severe injury to the surface of the

body, or result in profound generalized cooling of the body core, resulting in coma and death. Areas of

the body which have high surface area-to-volume ratio such as fingers, toes, and ears are the mostsusceptible.

Local injury resulting from cold is included in the generic term frostbite. There are severaldegrees of damage. Frostbite of the extremities can be categorized into:

• Frost nip or incipient frostbite: Characterized by sudden blanching or whitening of skin.

• Superficial frostbite: Skin has a waxy or white appearance and is firm to the touch, buttissue beneath is resilient.

2049-001-331 1-* HASP

Page 158: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

• Deep frostbite: Tissues are cold, pale, and solid; extremely serious injury.

Prevention of frostbite is vital. Keep the extremities warm; check for symptoms at every break.

The onset is painless and gradual, you may never know you have been injured until it's too late.To administer first aid for frostbite, bring the victim indoors and rewarm the areas quickly in

watebetween 39°C and 4rC(102°F- 105°F). Give a warm drink - not coffee, tea or alcohol The

victim should not smoke. Keep the frozen parts in warm water or covered with warm clothes for 30

minutes, even though the tissue will be very painful as it thaws. Then elevate the injured area and protectit from injury. Do not allow blisters to be broken. Use sterile, soft, dry material to cover the injured

areas. Keep victim warm and get immediate medical care.After thawing, the victim should try to move the injured areas a little, but no more than can be

done alone without help.

• Do not rub the frostbitten part (this may cause gangrene)• Do not use ice, snow, gasoline or anything cold on frostbite• Do not use heat lamps or hot water bottles to rewarm the part• Do not place the body part near a hot stove

Systemic hypothermia is caused by exposure to freezing or rapidly dropping temperature. Its

symptoms are usually exhibited in five stages: (1) shivering; (2) apathy, listlessness, sleepiness, and

(sometimes) rapid cooling of the body to less than 95°F; (3) unconsciousness, glassy stare, slow pulse,and slow respiratory rate; (4) freezing of the extremities; and, finally (5) death.

There may also be the potential for heat stress during oversight activities conducted duringwanner months. Measures will be taken to minimize heat stress to workers. The following signs and

symptoms of heat stress include:

• Heat rash may result from continuous exposure to heat or humid air.

• Heat cramps are caused by heavy sweating with inadequate electrolyte replacement.Signs and symptoms include:

muscle spasmspain in the hands, feet, and abdomen

• Heat exhaustion occurs from increased stress on various body organs includinginadequate blood circulation due to cardiovascular insufficiency or dehydration. Signsand symptoms include:

pale, cool, moist skin

2049-001-331 7-5 HASP

Page 159: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

heavy sweatingdizzinessnauseafainting

• Heat stroke is the most serious form of heat stress. Temperature regulation fails and thebody temperature rises to critical levels. Immediate action must be taken to cool the bodybefore serious injury and death occur. Competent medical help must be obtained. Signsand symptoms are:

red, hot, usually dry skinlack of or reduced perspirationnauseadizziness and confusionstrong, rapid pulsecoma

Measures to minimize heat stress may include:

• The erection of temporary devices to provide shade.

• Monitored work breaks.

• The availability of liquids and monitoring of liquid replenishment.

• Personnel monitoring of heart rate, oral temperature, skin temperature, and body weight.

• The suspension of activities above specific temperature and humidity limits.

The frequency of monitoring depends upon air temperature adjusted for solar radiation and the

level of physical work. Energy levels for work rarely exceed 250 kcal/hour, except for short bursts of

hard labor. The length of the work cycle will be governed by the required monitoring as follows:

ADJUSTEDTEMPERATURE'

90°F or above

87.5° -90°F

82.5°-87.5°F

77.5°-82.5°F

72.5°-77.5°F

SEMIPERMEABLEENSEMBLEb

After each 45 minutes of work

After each 60 minutes of work

After each 90 minutes of work

After each 1 20 minutes of work

After each 1 50 minutes of work

IMPERMEABLEENSEMBLE"

After each 1 5 minutes of work

After each 30 minutes of work

After each 60 minutes of work

After each 90 minutes of work

After each 1 20 minutes of work

2049-001-331 7-6 HASP

Page 160: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

^culate the adjusted air temperature (ta adj) by using this equation: ta adj °F + (13 x % sunshine). Measure airtemperature (ta) with a standard mercury-in-glass thermometer, with the bulb shielded from radiant heat. Estimatepercent sunshine by judging what percent time the sun is not covered by clouds that are thick enough to producea shadow. (100 percent sunshine = no cloud cover and a sharp, distinct shadow; 0 percent sunshine = no shadows.)

Nvhen semipermeable or impermeable protective clothing is worn open, raise each temperature adjustment in theleft-hand column of the table by about 5 percent (this increases the threshold for each monitoring time). The exactadjustment depends on the level of permeability of the clothing or the extent to which an impermeable garment canbe safely opened.

20494)01-331 7-7 HASP

Page 161: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

8.0 LEVELS OF PERSONAL PROTECTION

8.1 GENERAL PROTECTION LEVELS

Personnel protective equipment (PPE) must be worn when work activities involve potential

exposure to known or suspected atmospheric contaminants; when vapors, gases, or particulates may begenerated; or when direct contact with Site contamination may occur. Respirators can protect the lungs,the gastrointestinal tract and the eyes against air toxicants. Chemical-resistant clothing can protect the

skin from contact with skin-destructive and skin-absorbable chemicals. Good personal hygiene reduces

or eliminates the ingestion of materials.

The level of PPE selected will be based primarily on:

• Types and concentrations of chemical substances in the ambient atmosphere and theirassociated toxicity; and

• Potential for exposure to substances in air, splashes of liquids or other indirect contactwith material due to the task being performed.

In situations where the types of chemical, concentrations, and possibility of contact are not

known, the appropriate level of protection will be selected based on professional experience andjudgement until the hazards are further characterized. The individual components of clothing andequipment will be assembled into an ensemble to protect the oversight personnel from site-specific

hazards, while at the same time minimizing hazards and drawbacks of the personal protective gear itself,Ensemble components outlined in the following subsection are based on the widely used USEPA Levels

of Protection.In general:

• All protective head gear shall meet the requirements of the American National StandardsInstitute (ANSI) Z89.1, Class A or ANSI Z89.2, Class B.

• Persons will be provided with eye and face protective equipment required to protectagainst potential eye or face injury from physical, chemical or radiological agents. Eye

2049-001-331 8-1 HASP

Page 162: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

and face protective equipment shall meet the requirements in ANSI Z87.1, Practice forOccupational and Educational Eye and Face Protection.

Persons needing corrective lenses for Site activities, required to wear eye protection, willbe protected by one of the following:

Eyeglasses whose protective lenses provide optical correction;

Goggles that can be worn over corrective lenses without disturbing the adjustmentof the spectacles; or

Goggles that incorporate corrective lenses mounted behind the protective lenses.

Contact lens use will not be permitted under a full-face respirator. Spectacle kits forinsertion into full-face respirators will be provided for Malcolm Pirnie, Inc. personnel asrequired.

If excessive noise levels are anticipated, particularly during large equipment operation,the contractor will comply with 29 CFR 1910.95 and amendments, including arrangingfor noise level monitoring. Pending the results, or based on engineering judgement,administrative or engineering controls or hearing protection will be provided asappropriate.

Persons handling rough, sharp-edged, abrasive materials or where the work subjects thehand to lacerations, punctures, bums, or bruises, will use general purpose outer handprotection in addition to chemical resistant inner and outer gloves specified.

Employees will wear clothing suitable for the weather and work conditions. Theminimum will be short sleeve shirt, long trousers and steel-toed/shanked leather or otherprotective work shoes or boots. Canvas tennis or deck shoes are not acceptable.

Each employer shall provide respiratory protection approved by NIOSH or MSHA forall employees subject to harmful concentrations of dusts, gases, fumes, mists, toxicmaterials or atmospheres deficient in oxygen.

U.S. Coast Guard approved personal flotation devices, vest-type, will be worn by allpersonnel conducting field investigative activities or other activities from boats.

No person will be permitted in atmospheres containing less than 19.5 percent oxygenunless provided with a source of air meeting USP or Compressed Gas AssociationSpecification G7.1, Grade D.

Air purifying respirators will be permitted only where the toxic content of the air is knownto be of the type and concentration which the mask will effectively remove.

2049-001-331 8-2 HASP

Page 163: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

PPE will be inspected regularly and maintained in serviceable and sanitary condition, andbefore being reissued to another person or returned to storage, will be cleaned,disinfected, inspected and repaired.

8.2 REQUIRED LEVELS OF PROTECTION

The proper personal protection equipment (PPE) should be worn during landfill closure and

ground water treatment system oversight activities which may expose oversight personnel to chemical

or physical hazards. The estimated level of protection required for the oversight activities is Level D.

If the need for respiratory protection from organic vapors or dust are determined during the task-specific

activities, the level of PPE may be upgraded to Level C. Factors affecting this decision may include:(1) known or suspected presence of dermal hazards, (2) occurrence or likely occurrence of organic

vapors, and (3) change in work task that will increase contact or potential contact with hazardous

materials. Personnel will have current respirator fit-tests prior to upgrading to respiratory' protection.

The following is the minimum personal protection equipment required under each level (Level

D and Level C) as defined in 29 CFR 1910.120 of the General Industry Standards:

Level D:• Coveralls

• Gloves

• Boots/shoes, chemical resistant, steel toe and shank

• Boots, outer, chemical resistant (disposable)

• Safety glasses or chemical splash goggles

• Hard hat

• Escape mask

Level C:• Full-face air purifying respirators with combination cartridge (NOISH approved)

• Hooded chemical resistant clothing (overall, two-piece chemical-splash suit;disposable chemical resistant overalls)

2049-001-331 8-3 HASP

Page 164: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Coveralls

Gloves, outer, chemical resistant

Gloves, inner, chemical resistant

Boots (outer), chemical resistant, steel toe and shank

Boot covers, outer, chemical resistant (disposable)

Hard hat

Escape Mask

Face Shield

2049-001-331 8-4 HASP

Page 165: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0September, 1994

9.0 DECONTAMINATION PROCEDURES

9.1 PROTECTIVE CLOTHING

The majority of oversight activities at the Site may be conducted wearing normal work clothes

and minimal PPE. Unless otherwise specified by the Site Safety Officer, personnel decontamination will

not be necessary or required.

When the Site Safety Officer determines that material or PPE has been contaminated or may

potentially be contaminated, decontamination will be accomplished by following a systematic procedure

of cleaning and removing the protective clothing. All clothing will be either discarded or rinsed free of

gross contamination, scrubbed clean in a detergent solution and then rinsed clean. The decontamination

protocol is listed below:

1) Remove hard hat (if worn) and wipe clean with moist towel;

2) Rinse overboots and gloves of gross contamination;

3) Scrub overboots and gloves clean;

4) Rinse overboots and gloves clean;

5) Remove latex overboots;

6) Remove outer latex and inner nitrile gloves;

7) Remove Tyvek coveralls;

8) Remove respirator (if worn); and

9) Remove inner Latex gloves.

9.2 RESPIRATORS

2049-001-340 9-1 HASP

Page 166: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0September, 1994

Components of respirators will be soaked in a cleanser/sanitizer solution and scrubbed with abrush as per the manufacturer's instructions. The clean and sanitized respirators will be stored in plasticbags in a clean and dry place.

9.3 SANITIZING OF PERSONAL PROTECTIVE EQUIPMENT

Respirators, reusable protective clothing and other personal articles will be decontaminated andsanitized before being reused. The insides of masks and clothing may become soiled due to exhalation,body oils and perspiration. The manufacturer's instructions will be used to sanitize the respirator mask.Protective clothing will be discarded, machine washed or cleaned by hand, as appropriate.

9.4 EQUIPMENT AND MACHINERY

All heavy equipment including, but not limited to: drill rigs, back-hoe tractors, construction andother equipment will be steam cleaned and wire brushed before arrival on-site by the contractor. Thepre-site cleaning is to ensure no rust, soil or other material will be introduced from off-site locations.

The equipment will be inspected by the contractor to ensure its cleanliness and that all seals and gasketsare intact and that no fluids are leaking.

Prior and subsequent to equipment contact with known or suspected contamination, theequipment will be decontaminated at the Contamination Reduction Zone (decon area) by the following

procedure:

• Clean with tap water and low phosphate detergent, using a brush if necessary, to removeparticulate matter and surface films; and

• Thorough steam cleaning of parts of equipment which had, or will have, direct contactwith waste materials.

AH downhole drilling, excavation, sampling and associated equipment that may come intocontact with Site contaminants will be decontaminated. All solvent rinsates will be collected in separate

containers for proper disposal.

2049-001-340 9-2 HASP

Page 167: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0September, 1994

9.5 DISPOSAL OF DECONTAMINATION WASTES

All waste material generated as a result of decontamination activities will be discarded into steel

55-gallon drums. Plastic garbage bags may be used at work zones to consolidate waste material before

placing in drums. The drums will be prominently labeled "Decontamination Waste," inventoried and

stored on-site until disposal. The waste material will be disposed of in accordance with applicable

Federal, State and Local regulations. Liquid waste may be treated on-site in accordance with theapproved on-site ground water treatment system.

9.6 MEDICAL EMERGENCIES DECONTAMINATION

If workers require medical attention in a contaminated work zone, or have recently exited a

contaminated work zone, the procedures to follow when assisting are presented in Section 11.0 of this

HASP.

2049-001-340 9-3 HASP

Page 168: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

10.0 DOCUMENTATION AND REPORTING

It will be the responsibility of the Program Manager to establish and assure adequate records

for all Malcolm Pirnie oversight activties are maintained with respect to:

• Occupational injuries and illnesses;

• Accident investigations;

• Reports to insurance carrier or state compensation agencies;

• Records and reports required by Federal, State and Local agencies;

• Property or equipment damage;

• Third party injury or damage claims; and

• Records of inspections and citations.

Any incident (other than minor first aid treatment) resulting in injury, illness or property damage

will require an accident/incident investigation and report. The investigation will be conducted by the SiteSafety Officer as soon as emergency conditions are under control. The purpose of the investigation will

be to determine pertinent facts relating to the accident or incident in order to prevent a similar occurrence.

Specific documentation of incident reporting is outlined in Section 11.0 of this HASP.

Within three working days of any reportable incident, the Site Safety Officer will complete and

submit to the USEPA contact an accident report. OSHA record-keeping, Workers' Compensation forms

and documentation log books are required in all cases of accident record-keeping.

2049-001-331 10-1 HASP

Page 169: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

11.0 EMERGENCY RESPONSE PLAN

11.1 PRE-EMERGENCY PLANNING

All Malcolm Pirnie and contractor personnel involved with the landfill closure and ground water

treatment system activities will attend a site-specific Emergency Planning meeting. The topics to be

discussed include, but are not limited to:

• Overview of Emergency Response objectives;

• Personnel responsibilities;

• Emergency recognition and communication procedures;

• Emergency egress routes and directions to the Holy Family Memorial Medical Center(Manitowoc);

• Emergency contingency plan; and

• Incident reports.

11.2 EMERGENCY RECOGNITION AND COMMUNICATION

11.2.1 Personnel Responsibilities

The Site Safety Officer will be in charge of Malcolm Pirnie personnel during all emergencies.

The Site Safety Officer's documentation and reporting requirements are presented in Section 10.0 of this

HASP. Malcolm Pimie's Site Safety Officer and the contractor's Site Safety Officer will discuss andestablish emergency response plans and procedures prior to initiating site activities.

11.2.2 Emergency Contact Telephone Numbers

The telephone numbers of the Manitowoc Police and Fire Department, Holy Family Memorial

Medical Center and ambulance service, and Malcolm Pirnie project representatives are provided in the

emergency reference sheet included in Section 12.0 found at the end of this HASP. Also included at the

2049-001-331 11-1 HASP

Page 170: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

end of this HASP is a map and written directions to the Medical Center. The emergency reference sheet

of telephone numbers will be available on-site at all times.

11.2.3 Emergency Alarm SignalsAn emergency communication system will be in effect at the Site to communicate emergency

situations to workers. The most simple and effective emergency communication system in many

situations will be direct verbal communications. Verbal communications will be supplemented any time

voices cannot be clearly perceived above ambient noise levels (i.e., noise from heavy equipment, drillingrigs, backhoes, etc.) and any time a clear line-of-sight cannot be easily maintained among all Sitepersonnel because of distance, terrain or other obstructions. When verbal communications must be

supplemented, the following Emergency Signals (using hand held portable air horns) shall be implement-ed:

• ONE Horn Blast: General WarningOne horn blast is used to signal relatively minor, yet important events on-site. Anexample of this type of event would be a minor chemical spill or discovery of contami-nants during excavation where there is no immediate danger to life or health yet personnelworking on-site should be aware of the situation so unnecessary problems can be avoided.If one horn blast is sounded, personnel must stop all activity and equipment on-site in thearea of the alarm and await further instructions from the Site Safety Officer.

• TWO Horn Blasts: Medical EmergencyTwo horn blasts are used to signal a medical emergency where immediate first-aid oremergency medical care is required. If two hom blasts are sounded, all first-aid and/orCPR trained personnel should respond, as appropriate, all other activity and equipmentshould stop and personnel should await further instructions from the Site Safety Officer.Medical treatment to be rendered can range from bandaging minor cuts and abrasions toperforming life-saving techniques.

• THREE Horn Blasts followed bv ONE continuous blast: Immediate Danger to Life orHealth, Site EvacuationThree hom blasts followed by another extended or continuous horn blast signal a situationwhich could present an immediate danger to the life or health (IDLH) of personnel on-site. Examples of possible IDLH situations could include fires, explosions or majorhazardous chemical releases. If three horn blasts followed by a continuous blast aresounded, all activity and equipment must stop; all personnel must immediately evacuatethe Site.

2049-001-331 11-2 HASP

Page 171: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

11.2.4 Emergency Site Evacuation

General emergency egress routes are shown on Figure 11-1. Because both Sites are comprisedof large open land immediately adjacent to roads, emergency egress is generally limited through the Sitesto either Hempton Lake or Sunny Slope Roads.

Specific escape routes for work zones will be established at the time of initial work by the SiteSafety Officer and updated in accordance with any change in project scope. As deemed necessary by theSite Safety Officer, planned activities with inadequate emergency egress routes will be postponed untilprovisions are made to remedy the situation. Updated escape routes will be communicated verbally bythe Site Safety Officer to applicable contractor supervisors.

Evacuation routes will be formulated from the Exclusion Zone through the upwind Contami-nation Reduction Zone to the Support Zone.

After a Site evacuation, a sign-in log will be checked to ensure that all persons on-site are

accounted for. If the Site is evacuated due to an emergency, personnel shall not re-enter until:

• The conditions resulting in the emergency have been corrected.

• The hazards have been reassessed.

• The Health and Safety Plan has been revised and reviewed as needed.

• Site personnel have been briefed on any changes in health and safety equipment orprocedures.

11.3 FIRE PREVENTION AND PROTECTION

When required by site-specific activities or the regulatory authorities, the Program Manager willdirect the preparation and submittal of a Fire Protection Plan for the approval of the authorizedrepresentative or other designated official. The development and application of a Project Fire ProtectionProgram will follow the recommended practices and standards of the National Fire ProtectionAssociation (NFPA) and other applicable Federal, State and Local regulations. The essential consider-

ations for the Fire Protection Plan would include:

• Proper Site preparation and safe storage of combustible and flammable materials,

2049-001-331 11-3 HASP

Page 172: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

• Coordination with private and public fire authorities.

• Job-site fire protection and inspections for fire prevention.

• Indoctrination and training of employees.

• All storage, handling or use of flammable and combustible substances will be under thesupervision of qualified persons.

• All tanks, containers and pumping equipment, portable or stationary, used for the storageor handling of flammable and combustible liquids, will meet the recommendations of the

NFPA.

11.4 EMEGENCY MEDICAL TREATMENT

Emergency Response Actions - In the event that an injury or illness requires more thansuperficial first aid treatment, victims shall be transported to the Holy Family Memorial Medical Centerof Manitowoc for treatment. Pertinent information regarding the cause and extent and/or the type and

extent of contamination the victims were exposed to, will be provided to the responding medical

paramedics and the receiving hospital. If such information is not readily available upon the injured

victim's transport, the information will be provided to the hospital as it is obtained. A co-worker willaccompany the victim to the hospital and will remain with the victim until release or admittance is

determined. The escort will relay all appropriate medical information to the Site Safety Officer.

Reaching Victims in Work Zone • In the event that workers are injured or stricken ill in a

contaminated work zone, extreme care must be taken when assisting. Rescue personnel must be

cognizant of the level of PPE required in the area and if the injury is a consequence of inadequate or

failure of PPE. If the injury is the result of inadequate PPE, rescue personnel shall not enter the work

zone until their PPE has been upgraded to address the situation.Emergency Decontamination - The preliminary assessment of the cause and severity of the

injury in combination with the potential for and consequences of contamination exposure to the victims

and rescue personnel, will determine if:

• Immediate medical care should be administered or if the victims should be removed fromthe contaminated work zone prior to medical treatment.

2049-001-331 11-4 HASP

Page 173: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

• Whether or not the victims and rescue personnel must be decontaminated before exitingthe contaminated work zone.

• Whether or not the victims and rescue personnel must be decontaminated prior toadministering first aid or transport to Holy Family Memorial Medical Center.

Should decontamination be deemed necessary, the protocol to follow will be that currentlydesignated for the work zone. If a victim is contaminated and injuries require immediate physician

attention prior to decontamination, the victim should be wrapped in a tarp or space blanket andtransported to Holy Family Memorial Medical Center.

Immediate Interim First Aid - Interim first aid to assist the injured may include:

• Skin contact: Use copious amounts of soap and water. Wash/rinse affected area for atleast 15 minutes. Decontaminate and provide medical attention. If necessary, transportindividual to Holy Family Memorial Medical Center.

• Inhalation: Move to fresh air and, if necessary, transport individual to the Holy FamilyMemorial Medical Center,

• Ingestion: Decontaminate and transport individual to Holy Family Memorial MedicalCenter.

• Snakebite: The treatment of a snakebite depends on whether or not the snake ispoisonous. If the snake is non-poisonous, the bite should be washed thoroughly with soapand water. A poisonous snakebite requires medical attention.

In many cases, the bite of a poisonous snake can be recognized by one or more puncturescaused by the fangs. By comparison a non-poisonous snake leaves only a group ofsurface bites sometimes shaped like a horseshoe. The first thing to do in case of apoisonous snakebite is to keep the victim motionless and transport to Holy FamilyMemorial Medical Center. During transport, the bitten portion of the victim's bodyshould be kept at a level below that of the heart.

The victim may be given water unless nausea or vomiting develops. Do not give thevictim any form of alcohol to drink and do not give aspirin. Also, do not give the victima snakebite serum without a physician's advice.

To facilitate the administration of interim first aid, a first aid kit will be provided and maintained

at the Site.

2049-001-331 11-5 HASP

Page 174: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

11.5 INCIDENT REPORTS

In the event of injury or exposure to any field personnel, the Field Team Leader is responsible

for the preparation and submission of an incident report to the Site Safety Officer. The ProgramManager, in consultation with the Corporate Health and Safety Manager is required to conduct all follow

up investigative, documentation and reporting requirements. In accordance with OSHA

regulations, Malcolm Pirnie supervisors must prepare a written report of each employee injury and sendit to the Benefits Administrator in the Malcolm Pirnie, Inc. White Plains, New York Office with a copy

to the Corporate Health and Safety Manager, for processing- A copy of the Supervisor's incidentinvestigation report, with directions, is presented in Attachment D.

2049-001-331 11-6 HASP

Page 175: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

TOWN OF FRANKLIN

SUNNY SLOPE RD.

LEMBERGERLANDFILL-

LEMBERGERTRANSPORTRECYCLING

I MU

MAICOMPIRNIE

LEMBERGER SUPERFUND SITESEMERGENCY EGRESS ROUTE

FIGURE11-1

Page 176: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

12.0 EMERGENCY REFERENCES, CONTACTS AND PHONENUMBERS

Malcolm Pirnic. Inc. Representatives:

Project Officer (Terry Ritter): (614) 888-4953

Technical Directors: (Richard Brownell): (201) 529-0858 Ext. 260(John Isbister): (201) 529-0858 Ext. 209

Program Manager: (William Mahlum): (612) 591-1394

Corporate Health & Safety Manager (Mark McGowan): (914) 694-2100 Ext. 2484

Regional Health & Safety (Michael Kunz): (612) 591-1394

Directions to Hospital (map attached):Exit the Site and go south on Hempton Lake Road to U.S. Highway 10. Go east (left) on U.S.

Highway 10 to County Road P (Homestead Road). Make a right onto County Road P and follow to theintersection of County Road R (North Rapids Road). Make a right (south) onto County Road R andfollow to Waldo Boulevard. Make a left (east) onto Waldo Boulevard and follow to 18th street (1 st stop

light). Make a right (south) on 18th Street and continue south (18th Street becomes Revere Drive)across the Manitowoc River. Holy Family Memorial Medical Center is located just south of the river,

on the right.

Emergency Contacts:The Manitowoc County Area is serviced by the 911 Emergency Service for Ambulance, Fire,

Police, and Sheriff. Additional numbers include:

Hospital: (414) 684-2233 (Holy Family Memorial Medical Center Emergency Response)

National Response Center: 1-800-424-8802 (24-hour number)

2049-001-331 12-1 HASP

Page 177: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

Revision 0May, 1994

Nearest Phone: East of Site on Hempton Lake Road at the Ridgeview Landfill.(414)732-4473

Note: Portable phones will be available for conducting specific tasks at the Site.

2049-001-331 12-2 HASP

Page 178: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

I•N-i

APPROXIMATE SCALEfeinch - 1 mik

MAUOOUViPIRNIE

LEMBERGER SUPERFUNO SITESROUTE TO HOSPITAL

FIGURE12-1

Page 179: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX AON-SITE PHYSICAL HAZARDS

Page 180: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ON-SITE PHYSICAL HAZARDS

A discussion on the following physical hazards has been prepared for background information

on each topic. Each of the seven topics directly relates to potential conditions which may occur duringthe Lemberger Landfill Closure and Ground Water Treatment System oversight activities.

1. Heat StressPersonal protective equipment may place a worker at considerable risk of developing heat stress,

probably one of the most common (and potentially serious) illnesses encountered at hazardous waste

sites. The potential for heat stress is dependent on a number of factors, including environmentalconditions, clothing, workload and the physical condition and age of the worker. Personal protective

equipment may severely reduce the body's normal ability to maintain equilibrium (via evaporation,convection and radiation), and by its bulk and weight increases energy expenditure. Therefore, in the

selection of outer protective clothing, the intent of protection against chemical splashes or other potential

skin exposure must be carefully weighed against the added heat stress that may be associated with theimpermeability of the suit. The signs and symptoms of heat stress are as follows:

m Heat rash may result from continuous exposure to heat or humid air.

• Heat cramps are caused by heavy sweating with inadequate electrolyte replacement.Signs and symptoms include:

muscle spasms; andpain in the hands, feet and abdomen.

• Heat exhaustion occurs from increased stress on various body organs includinginadequate blood circulation due to cardiovascular insufficiency or dehydration. Signsand symptoms include:

pale, cool, moist skin;heavy sweating;dizziness;nausea; orfainting.

• Heat stroke is the most serious form of heat stress. Temperature regulation fails and thebody temperature rises to critical levels. Immediate action must be taken to cool the body

A-l

Page 181: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

before serious injuiy and death occur. Competent medical help must be obtained. Signsand symptoms are:

red, hot, usually dry skin;lack of or reduced perspiration;nausea;dizziness and confusion;strong, rapid pulse; orcoma.

Preventive measures to preclude heat stress include regular work breaks during field activities,

regular fluid replenishment and the availability of shelter (i.e., shaded area).

2. Cold StressHypothermia is defined as a decrease in a person's body core temperature to 95 °F (35 °C). A

freezing or rapidly dropping temperature is not needed to produce hypothermia. A person's ability to

maintain normal body temperature may be affected by medications/drugs, alcohol, wind or becomingwet. The use of prescribed drugs during Site activities should be reviewed with the occupational

physician.Although clothing shields protect the wearer from many sources of external wetting, perspiration

often increases while working, causing the skin and clothing to become moist or wet. Wet clothes and

skin can conduct body heat at a rapid rate. In addition, the effects of wind and water are more than

additive, creating a condition for extreme loss of body heat. Exposed skin should not be permitted whenthe wind chill factor results in a relative temperature - 25 °F or below, wet clothes should be replaced at

temperatures below -f 36°F.Dehydration, or the loss of body fluids, occurs insidiously in the cold environment and may

increase the susceptibility of the worker to cold injury due to a significant change in blood flow to the

extremities. Warm sweet drinks and soups should be provided for caloric intake and fluid. The intake

of coffee should be limited because of its diuretic and circulatory effects.Shielding the work area from the wind or wearing wind-breaker clothing will reduce wind chill

effect. A water-repellant outer garment with good ventilation should be worn in rainy weather. Olderworkers or workers with circulatory problems require special protection against cold injuries. The useof extra insulation clothing and/or a reduction in the duration of exposure period are among the special

precautions which should be considered. If the available clothing does not give adequate protection toprevent hypothermia or frostbite, work shall be modified or suspended until adequate clothing is made

A-2

Page 182: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

available or until weather conditions improve. Since the Site is located in Wisconsin, cold stress is of

real concern during winter months.

3. Fire and Explosion

A flammable substance present at a specified concentration, in a confined space, with a sourceof ignition such as a spark, open flame, or very hot surface, may result in a fire or explosion.

Many flammable compounds have a lower explosion limit (LEL) of 5 percent and an upper

explosion limit (UEL) of 15 percent. The LEL of a substance is the minimum concentration of gas or

vapor in air below which the substance will not burn when exposed to a source of ignition. Thisconcentration is expressed in percent by volume, below which the mixture is "too lean" to burn or

explode. The upper explosion limit (UEL) of a substance is the maximum concentration of vapor in air

above which the substance will not bum when exposed to a source of ignition. Above this concentration,

the mixture is "too rich" to bum or explode. The explosive range is the range of concentrations betweenthe LEL and UEL where the gas-air mixture will support combustion,

4. Heavy Machinery

Each contractor shall require appropriate safety equipment for work around heavy equipment.

Malcolm Pirnie employees are required to wear hard hats and steel toed footwear when on-site nearheavy machinery. No person will walk underneath a piece of equipment when it is carrying a load of

debris or material or if it is transporting materials to another area. The contractor will contact the properauthorities and get a utility map before initiating any subsurface work. The need for noise protection

should be evaluated by each employer pursuant to his obligations under OSHA. Workers exposed to85 dBA for 8 hours will be issued hearing protection equipment. Noise exposure shall not exceed 120

dBA. Each employer shall provide the necessary hearing protection for their Site activities.

5. Electrical Hazards

Electricity is a potential danger that requires certain precautions. Electricity may kill byparalyzing the nervous system and stopping muscular action, or by preventing the heart from pumping.

Under certain conditions, any electrical device can transmit a fatal shock. Although voltage is required

for current flow, the measure of the shock intensity is due to the amount of current (amperes) forced

through the body.

The amount of shock current will vary depending on conditions, body resistance between points

of contact, and of course available current. Skin resistance may vary, for example, from 1000 ohms to

A-3

Page 183: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

over 500,000 ohms for dry skin. Body resistance decreases with time of contact. Painful or severe shock

can result from a current flow as low as 10 milliamps with breathing being stopped at levels around 75milliamps. Currents above 200 milliamps cause severe burns and unconsciousness, but are not fatal if

the victim is given immediate attention.Some basic guidelines are listed below which, if followed, may eliminate electrical hazards and

reduce the possibility of accidental injury:

• Designate authorized personnel to work on electrical equipment and repairs. Allow onlythose personnel to do electrical work.

• Clearly mark all electrical controls.

• Keep electrical controls accessible.

• Do not make any electrical safety device inoperative unless it is absolutely necessary forrepair or maintenance.

6. Confined Space EntryLandfill closure and ground water treatment system activities which involve confined spaces,

such as trenches, tunnels and open pits, must be conducted with extreme caution and in accordance with

29 CFR 1910.146. The potential for atmospheric conditions to be present in the confined space that are

immediately dangerous to life and health (1DLH) are greatly increased due to the inherently poor

ventilation of confined spaces. The following specific procedures will be followed when entering into

confined spaces is required.

Some general guidelines and procedures include:

• Spaces identified by Malcolm Pirnie or the contractor as "permit required confinedspaces" will be required to have a prepared entry permit which identifies conditions to beevaluated to ensure safe entry (Attachment B).

• Malcolm Pirnie and contractor will notify each other of any confined spaces.

• The contractor shall authorize entry, fill out and sign the confined space entry permit andassume direct charge of the entry for its duration.

• Training of confined space entrants, attendants, and persons-in-charge of authorizingentry is the responsibility of employers. Malcolm Pirnie staff will be trained throughMalcolm Pimie, contractors will be required to train their staff accordingly.

Air monitoring utilizing direct reading instruments will be conducted prior to and during

confined space entry. Monitoring instruments commonly utilized include combustible gas indicators,

A-4

Page 184: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

oxygen meters, carbon dioxide meters and organic vapor meters which will detect common IDLH

conditions such as: flammable or explosive atmosphere; oxygen-deficient environments; or high levels

of airborne toxic substances.

All contractor confined space entries, procedures and permits will be the responsibility of thecontractors and their employees as per the OSHA standard 29 CFR 1910.146 - Permit Required

Confined Spaces. General guidelines for contractors to comply with this standard include, but are not

limited to:

• Pre-planning prior to entry;

• Hazard identification;

• Hazard control;

• Permit system;

• Posting of signs;

• Proper safety training;

• Isolation of all equipment;

• Electrical lock-out/tag-out;

• Direct-reading air monitoring and testing of confined space atmosphere at variouselevation for: oxygen, LEL, hydrogen sulfide, toxic gases and temperature;

• Proper safety equipment including intrinsically safe electronic equipment and non-sparking tools for activities adjacent to and in the confined space;

• Standby observer/outside attendant;

• Prevention of unauthorized entry;

• Rescue procedures;

• Protection from external hazards; and

• Respiratory protection as appropriate.

7. Poisonous Snakes, Plants and Insects

Persons working on the Site should be aware of the presence of poisonous snakes, plants and

insects. Both poisonous and non-poisonous snakes are likely to be present at the Site. With the

A-5

Page 185: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

exception of some rare species of poisonous snakes, snakes will not attack unless provoked. All snakes

encountered should be avoided. If a snake is discovered, the Field Team Leader should be immediatelyinformed of the snake's location, size and type, if known. In most cases, only a brief interruption of work

will be necessary to allow the snake to vacate the work area on its own.

Poison ivy is a climbing plant with ternate leaves (arranged in three's), with white berries.Poison oak is similar to poison ivy, but its leaves appear oak-like in form, The leaves of these poisonous

plants produce an irritating oil which causes an intensely itching rash and characteristic bullous lesions.

Personnel working at the LL and LTR sites should take the precautions described below againstpossible deer tick bites. Deer ticks are carriers of the spirochete (borrelia bergdorfi] which causes Lyme

Disease, which can be transmitted to humans when bitten.Signs and symptoms of Lyme Disease may include the following;

• The most well-known warning sign is a rash, classically described as a small red area thatstarts at the site of a tick and gradually enlarges over several days. The rash, which doesnot appear until three to 30 days after the tick bite, may grow to several inches in diameterand is circular with a central clearing. It may be obvious or very faint. Multiple, usuallysmaller rashes without central clearing may develop in some individuals.

• Flu-like symptoms may precede or accompany the onset of the rash. Symptoms mayinclude chills and fever, headache, malaise and fatigue, stiff neck and, in some cases, painin the joints.

• If Lyme Disease is diagnosed and treated early, the prognosis is excellent. If the initialstage is not discovered and treated promptly, later stages my develop. Chronic arthritis,and in some cases heart and nervous system disorders, may develop weeks to months afterthe tick bites.

Some infected individuals may not develop either rash or symptoms. Thus, anyone bitten orthought to be bitten by a deer tick, or developing signs or symptoms of Lyme Disease is advised to see

a physician promptly for an examination and possibly a blood test. Prophylaxis or treatment with

antibiotics (tetracycline) may be a recommended course of action.

To prevent tick bites, personnel should wear long pants, made of light colored, tightly woven

cloth, tuck pant legs inside of socks, use an insect repellant, check themselves frequently and washthemselves thoroughly at the end of each day. The Site Safety Officer will advise personnel of the risk

of deer tick bites, the initial symptoms, and the precautions to be taken.

A-6

Page 186: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ATTACHMENT A

To be signed by all Malcolm Pimie, Inc. and subcontractor employees prior to their work on-site

at the LL and LTR sites - Franklin Township, Manitowoc County, Wisconsin.I acknowledge that I have reviewed the information in this oversight Health and Safety Plan and

understand the potential hazards which may confront me during activities at the LL and LTR sites. I

understand the contents of this oversight Health and Safety Plan to minimize those hazards and agreeto comply with them.

EMPLOYEE (print) TITLE/COMPANY SIGNATURE DATE

2049-001-331 A-l

Page 187: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

EMPLOYEE (print) TITLE/COMPANY SIGNATURE DATE

2049-001-331 A-2

Page 188: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

EMPLOYEE (print) TITLE/COMPANY SIGNATURE DATE

2049-001-331 A-3

Page 189: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

EMPLOYEE (print) TITLE/COMPANY SIGNATURE DATE

2049-001-331

Page 190: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

EMPLOYEE (print) TITLE/COMPANY SIGNATURE DATE

2049-001-331 A-5

Page 191: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ATTACHMENT B CONFINED SPACEENTRY PERMIT

PERMIT X? 13TT

DATE: ___________

JOB NO: __________

Pteax refer to Pre-Eatry Inspection Checklist.Permit valid during duration of entry only. All copies of permit will remain at job site until job b compkied.

CltercSue tocaoan end description:

Puipoar of Entry:Supervaor Emp. No. Date Supv. Trained:

SHADED AREAS DENOTE MINIMUM REQUIREMENTS TO BE COMPUTED AND REVIEWED PRIOR TO ENTRY

Requirements

L~kO^D~~r»*~T.. . _ r

ve^m*.

Serve *Kt(B*nen/hM/FUf)

}»•••* beep Qua** (BCBA)

M •••> «vw ««r Bai

fn ..mm.jfil.nJUtri»yEoa»

UHh.

-i • » _. .

lam *m m. R^h Md VmilM

FVrT I > HI ifflnlAMIU

L -f Eviouo.Praon

S ftoM.Tool.

PDMe»CMMa.H»

Date Sopr Init Requirements

Ky

Chemcal Cofj la

FKtShieU

W^Cte.

rii ••MB*

GK»a

BOOB

Mj

U^D^ESOA

Level Cw/ESOA

• *• -—•V J IIIIWBH

Air UK RcspMMM vffSCBA^

III MIHDIIBTM|. n

Date S«pv Init

Ite Ha.teld.M.m^MrWA.i.la..

A*«—— T^-WT——

„'•• <«yma

ll.»*em.iatm

H^nvCy^k

H «»«

PtrBbefM* EMIT LM«|

tutoixnlta*wlt«

<»mt+<»rm*i5iTM< *4 PTM (Skin}

< 1 PW*»»5PTM

rr

mtt*4 m «ca S how* (Looper with jffraprui

A,«___Mo*t

A*» in Moort:

*-"—————*

: tan

K faspniory Pratteno*

Seruthto

Send No.

StTNlNo.

: MlTMW $•*« Thae hqn

: hafe

'C-™»D«

CaBhnionOMe:

C-*——— ,0.*:

Emp. Number Anendinl Traininf Due

Nune/Sifnaiurr Emp. Number Enmni Tninmf Due

ALL Of THE ABOVE CONDITIONS ARE SATISFIED SUPERVISOR SIGNATURE,DATE: TIME:

PtA.-**Tr CANCELLED SUPERVISOR SIGNATURE,DATE: TIME:

Page 192: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAIOXMPIRNIE

ATTACHMENT C

MALCOLM PIRNIE, INC.

HAZARD COMMUNICATION PROGRAM

WORKPLACE

HAZARDOUS CHEMICALS INTRODUCED BY MALCOLM PIRNIE INC.

Chemical MSDS LOCATION____ Use ofProduct Constituents Appended? Storage Use Chemical

This notice will be updated, as required by the Hazard Communication Standard.

Signature Date

Site Safety Officer

Page 193: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUXXMPIRNIE

HAZARD COMMUNICATION PROGRAMTABLE OF CONTENTS

EASEHAZARD COMMUNICATION PROGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1

INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1

PROGRAM ORGANIZATION AND RESPONSIBILITIES . . . . . . . . . . . . . . . . . . . . . . . . 2-1

Manager, Health and Safety ............................................ 2-2Regional Officers/Branch Manager* . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2Hazard Communications Coordinators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2Project Managers/Designates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3

RECORDS RETENTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4

THE WRITTEN HAZARD COMMUNICATION PROGRAMProgram Availability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4

COMPREHENSIVE UST OF HAZARDOUS CHEMICALS ....................... 2-4

How to Develop ..................................................... 2-4

MATERIAL SAFETY DATA SHEETS (MSDSs) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

Establishing an MSDS Station . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5Removing MSDSs ................................................... 2-5Updating MSDSs .................................................... 2-6Help in Obtaining MSDSs ............................................. 2-6Chemical Data Sheets No Substitute for MSDSs ............................ 2-6

IJ^BELS AND OTHER FORMS OF WARNING ................................ 2-6Label Requirements .................................................. 2-6Hazardous Materials Identification Guide (HMIG)

Labeling System ............................................... 2-6Hazardous Waste Sample Labeling ...................................... 2*7Temporary Container* Must Be Labeled .................................. 2-7Longer-term Containers Require HMIG Labels ............................. 2-7

MULTI-EMPLOYER WORKPLACESInforming Other Employers ................................................. 2-7

Obtaining Information from Other Employees .............................. 2-S

June 1993

Page 194: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

>IRN1HAZARD COMMUNICATION PROGRAM

TABLE OF CONTENTS

PAGE

(Continued)

HAZARD COMMUNICATION TRAINING .......................................... 2-«

Hazard Communication Training Program for Hazardous ChemicalsMalcolm Pirnie Introduces to the Work Place,Minimum Requirements ......................................... 24

Hazard Communication Training Program For Hazardous ChemicalsOther Employers Introduce to the Work Place,Minimum Requirements .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-9

Hazard Communication Training Program Review .......................... 2-9

NON-ROUTINE TASKS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-9

FOR MORE INFORMATION ON HAZARD COMMUNICATION TRAINING ....... 2-10

COMPREHENSIVE LIST OF HAZARDOUS CHEMICALS (FORM) ............... 2-11

APPENDIX A ................................................................. 2-12

The OSHA Hazard Communication Standard 29 CFR 1910.1200 .............. 2-12 to 2-29Appendix A to 1910.1200 Health Hazard Definitions

(Mandatoiy) ........................................... 2-30 to 2-33Appendix B to 1910.1200 Hazard Determination (Mandatoiy) ................. 2-34Appendix C to 1910.1200 Information Sources (Advisory) .............. 2-35 to 2*36Appendix D to 1910.1200 Definition of Trade Secret"

(Mandatory) ........................................... 2-37 to 2-38

HAZARDOUS MATERIALS IDENTIFICATION GUIDE (HMIG)LABELING SYSTEM ............................................... 2-39 to 2-41

APPENDIX B ................................................................. 2-42

Examples, Portable Container Labels ...................................... 2-42 to 46

APPENDIX C................................................................. 2-47

Approved Letter Formats, Multi-Employer Work Sites ............................ 2-47

June 1993

Page 195: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

HAZARD COMMUNICATION PROGRAM

INTRODUCTION

PROGRAM ORGANIZATIONAND RESPONSIBILITIES

Malcolm Pirnie's Hazard Communication Program was developedto meet the requirements of the OSHA Hazard CommunicationStandard, Title 29 Code of Federal Regulations 1910.1200 et seq.A copy of this standard appears at the end of this section.

OSHA requires that employers make information available to itaffmembers about hazardous chemicals they may be exposed to in theworkplace. This information includes, but is not limited to,toxicology, physical and chemical hazards, means of detection, andprotection against exposure.

Malcolm Pirnie makes this information available to staff membenthrough lists of chemicals in use, current copies of Material SafetyData Sheets (MSDSs), container labeling, and staff training.

The OSHA Hazard Communication Standard rccognfacs thatMalcolm Pirnie may be the only employer on some work sites, andone of several employers on others. This Hazard CommunicationProgram has provisions for requesting and communicating informa-tion on hazardous chemicals others bring to the work site, thatMalcolm Pirnie staff may be exposed to during the course of theirduties.

For this reason, Malcolm Pirnie maintains a copy of this programat all Malcolm Pirnie work shea, whether or not the firm isresponsible for the presence of hazardous chemicals at the site.

Some states or local municipalities may have specific Right-To-Know or Community Right-To-Know requirements not addressedin this Hazard Communication Program. Accordingly, OfficeManagers, Project Managers, or their designates should determinethe specific requirements of the localities where they operate.

The Manager, Health and Safety, WHI, is responsible for HazardCommunication Program content Regional Officers and BranchManagers are responsible for seeing that the program is implement-ed in their regions or company locations. They may delegate theadministration of the program to a staff member they dnignatr aathe Hazard Communication Coordinator. This individual istypically the local Health and Safety Coordinator.

Project Managers or their designates are responsible for HazardCommunication Program implementation on their projects. TheManager, Construction Services, WHI, is responsible for overseeingHazard Communication Programs at Malcolm Pirnie constructionsites.

June 1993 2-1

Page 196: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

IRNIIHAZARD COMMUNICATION PROGRAM

Manager, Health and Safety

Regional Officers/BranchManagers

Hazard CommunicationCoordinators

The Manager, Health and Safety, WHI, is responsible for

Preparing and updating the written program, the HazardCommunication labeling program, and Hazard Communica-tion training materials.

Maintaining corporate Hazard Communication trainingrecords.

Serving as a ti*4infcai resource on chemical safety fortechnical and administrative staff.

Regional Officers and Branch Managers are responsible for

Designating a staff member (typically the Health and SafetyCoordinator) at each company location in their Region toserve as Hazard Communication Coordinator.

Providing the resources and support the designated HazardCommunication Coordinator needs to comply with MalcolmPirnie's Hazard Communication Program.

Seeing that these resources are allocated for appropriatetraining for staff who may be exposed to hazardous chemi-cals or materials, before they start a task or assignment

Hazard Communication Coordinators are responsible for

Maintaining a current copy of the written Hazard Commu-nication Program, and the OSHA Hazard CommunicationStandard in a place that is accessible to staff at theirlocation.

Developing and maintaining a comprehensive list of hazard-ous chemicals used by staff at their location.

Maintaining Material Safety Data Sheets (MSDSs) forhazardous chemicals used by staff at their location, and forgathering and filing MSDSs for hazardous chemkalscontractors, vendors and cleaning services use at theirlocation.

Inspecting incoming shipments of hazardous chemicals frommanufacturers, wholesalers, retailers, formulators, labora-tories, and others, for proper labeling, after being notifiedof their arrival

June 1993 2-2

Page 197: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MALOCXAtPIRNIE

HAZARD COMMUNICATION PROGRAM

Training, or arranging training, on the hazards of dtemkabin the work place, for aU potentially exposed employee*.The training shall include protective measures for KatJiBnghazardous chemicals. Also, as needed, providing any specialtraining within their competence for staff who perform non-routine tasks.

Maintaining a record of Hazard Communication trainingreceived by each employee, including type of training dateand name of instructor.

Communicating to the Administrator, Health and Safety,WJfl, the completion of Hazard Communication training foreach employee at their location.

Project Managers/Designates Project Managers or their designates are responsible for

Making a copy of the following available at their job aites:the written Hazard Communication Program, the OSHAHazard Communication Standard, and up-to-date MaterialSafety Data Sheets for hazardous chemicals Malcolm Piraieintroduces to the site.

Developing and maintaining a comprehensive list of hazard-ous chemicals Malcolm Pirnie introduces to the job tile, andmaking it accessible to all staff on the site.

Notifying the designated Hazard Communication Coordina-tor when shipments of hazardous chemicals arrive frommanufacturers, wholesalers, retaflers, formulaton, labora-tories, and others; giving Materials Safety Data Sheets(MSDSs) which accompany incoming shipments to theHazard Communication Coordinator for review and filing.

Contacting the source of the hazardous chemicab if theMSDSs are not complete or if an MSDS is not suppliedwith an initial shipment

Ensuring that temporary and permanent hazardous chemicalcontainers are labeled.

At multi-employer aites, telling the other employers thelocation of the written Malcolm Pirnie Hazard Communica-tion Program, which b to include labeling procedures andcopies of MSDSs for the site.

Communicating with other employers e.£, Owner, Contrac-tors, Subcontractors, to obtain information about the

June 1993 2-3

Page 198: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

HAZARD COMMUNICATION PROGRAM

RECORDS RETENTION

THE WRITTEN HAZARDCOMMUNICATION PROGRAMProgram Availability

COMPREHENSIVE LIST OFHAZARDOUS CHEMICALS

How to Develop

location of their written hazard communication program(sXlabeling program, and Material Safety Data Sheets, and, ifapplicable, information on the hazardous chemicals theymay produce or introduce to the job lite that MalcolmPirnie employees may be potentially exposed to*

Project Managers are also responsible for health and safety datastorage after their projects are complete. Specific changes to theHazard Communication Program developed for the project,correspondence, and copies of the MSDSs and other pertinent dataon hazardous chemicals Malcolm Pirnie or others introduced to thejob site are to be retained and stored together with the otherproject documents. Copies of occupational exposure data are to befiled in the employee's Health and Safety File with a copy forward-ed to the Administrator, Health and Safety, WHI, for evaluationand retention.

Copies of the written Hazard Communication Program and theOSHA Hazard Communication Standard are maintained at anaccessible MSDS station. MSDS stations are designated in eachpermanent or long-term company location, including regionaloffices, branch offices, field offices, and field trailers.

At temporary job sites, if Malcolm Pirnie is bringing hazardouschemicals to the work site or it based on past experience, anotheremployer is expected to bring hazardous chemicals to the work site,a copy of this written Hazard Communication Program and relevantMSDSs are maintained on-site for the duration of field activities.

If Malcolm Pirnie is the only employer on a site, and if no hazard-ous chemicals are being brought to the site, it is strongly suggestedthat a copy of this written program be maintained on-tite duringfield activities. However this is not a requirement.

Hazard Communication Coordinators are responsible for creatinga Comprehensive List of Hazardous Chemicals used at theirlocation. Project Managers are responsible Cor developing aComprehensive List of Hazardous Chemicals used on their job sites.

On a copy of the Comprehensive List of Hazardous Chemicals format the end of this section, list each product containing a hazardouschemical, as defined in Appendix A of this section, 29 CFR1910.1200 (d). Use the trade or common name of the product, themanufacturer, the hazardous chemical ingredients it contains, andthe location where it is used and/or stored Use as many lines asnecessary. This list is to be updated as required.

June 1993 2-4

Page 199: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

IRN1

HAZARD COMMUNICATION PROGRAM

MATERIAL SAFETY DATASHEETS (MSDSs)

Establishing an MSDS Station

Removing MSDS*

A copy of the Comprehensive Lbt of Hazardous Chemicals ihaO bemaintained at the MSDS Stations of company and field locations,together with the written Hazard Communication Program.

Malcolm Pirnie asks that its suppliers provide MSDSi for anypurchased materials that contain hazardous chemicals as defined byOSHA. This request is made through language on Malcolm PirniePurchase Orders or verbally by staff members ordering materials,at the time an order is placed or a purchase made. MSDS* aremade available to employees at company locations and work site*to give staff members information on specific hazards and controlsassociated with hazardous chemicals they may use.

Regional Officers, Branch Manager*, Project Managers, or theirdesignates shall provide sufficient space and resources to establishan MSDS Sution within their company or field locations. OfficeMSDS Stations should consist of a labeled three ring binder and asign (Laboratory Safety Supply 1992 model No. JX*12441 orequivalent). In temporary locations, an MSDS Station may be abulletin board or a three-ring binder kept on-site.

Each MSDS Station shall be located in an accessible, common areasuch as a break room, copier room, or site trailer* It shall abocontain a copy of: the written Hazard Communication Program,the OSHA Hazard Communication Standard, and the Comprehen-sive List of Hazardous Chemicals.

Original Material Safety Data Sheets are preferred, but copies maybe substituted. Copies are to be current and published by themanufacturer, importer, or formulator of the hazardous chemical.For small projects, or projects of short duration, the contents of theMSDS Station, described above, may be included with the site*specific Health and Safety Flan or other project Ayum^**

Each MSDS shall be filed alphabetically according to the first letterof the common name, chemical name, or product name. MSDSamust be written in English using OSHA Form 174 or equivalentformat

If a product is no longer used or if its MSDS has become dated, theHazard Communication Coordinator, Project Manager,removes the corresponding MSDS from die station and places it ina permanent health and safety file labeled with the actual orapproximate dates the chemical was used

June 1993 2-5

Page 200: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

RNI

HAZARD COMMUNICATION PROGRAM

Updating MSDSi

Help in Obtaining MSDSs

Chemical Data SheetsNo Substitute for MSDSs

LABELS AND OTHERFORMS OF WARNING

Label Requirements

Hazardous MaterialsIdentification Guide(HMIG) Labeling System

MSDSs are to be updated whenever

New information on the hazards of chemicals present in thework place becomes available.

Relevant occupational exposure standards change.

The issue date of the MSDS is more than three yean old.

MSDSs must be readily accessible to Malcolm Pirnie staff plus rtaffof any other employer at the work place during regular work shifts.It after repeated attempts, an MSDS cannot be obtained from themanufacturer or supplier, contact the Manager, Health and Safety,WHL for assistance. A written request for help in obtaining therequired MSDSs wfll be made to the Assistant Secretary of Laborfor Occupational Safety and Health (OSHA) and the Director ofthe National Institute for Occupational Safety and Health (NIOSH).

Chemical hazard data retrieved from electronic data bases may beuseful in assessing hazards posed by on-site chemical contamination.But these chemical 'data sheets" may not be substituted fororiginal, current MSDSs published by the manufacturer, Uaporter,or fonnulator. Data sheets lack the name of the manufacturer andemergency phone number.

All containers of hazardous chemicals received from mamrfkrtitr.ers.importers, or distributors of hazardous chemicals, or others,shall be properly labeled

A proper label provides the following information:

The identity of the hazardous chemicals) in the container.

The name and address of the chemical manufacturer,importer, fonnulator, or other responsible party.

Appropriate hazard and target organ warnings1.

Each container of hazardous chemicals (hazardous waste andenvironmental samples are exempt) shipped to or from MalcolmPirnie shall be checked by the Hazard Communication Coordinator,the site Health and Safety Officer, or their A*«ign«t» for propercontainer labeling as deserted above.

1 Tuftt orpa wvmiap we optioMl oa •tMfectuer'i bbch.

June 1993 2-6

Page 201: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUDOLMPIRN1I

HAZARD COMMUNICATION PROGRAM

Hazardous WasteSample Labeling

Temporary ContainersMust Be Labeled

Longer-term ContainersRequire HMIG Labels

MULTI-EMPLOYERWORKPLACESInforming Other Employers

The HMIG labeling system identifies chemicals with standardhazard ratings from 0 * 4 for health, flammabflity and reactivity, plusalphabetical designations for required personal protective equip-ment A complete explanation of the rating and PPE designationscan be found at the end of this section in Appendix B.

Malcolm Pirnie staff shall apply labels to temporary or portablecontainers, using the Hazardous Materials Identification Guide(HMIG) labeling system described in Appendix B. Labels shallcontain at least the information provided on Laboratory SafetySupply 1993 type QA-809 label or equivalent Appendix B also hasexamples of pre-completed labels that may be copied and appliedto commonly used chemicals.

OSHA exempts shipments of hazardous waste samples from hazardcommunication labeling requirements. However, Department ofTransportation (DOT) labeling requirements (49 CFR 173 et si)may apply to DOT defined hazardous substances shipped in largequantities. Hazardous materials or compressed gases shipped by airor common carrier will have special packaging, marking, andlabeling requirements. Contact the airline or common carrier formore information.

When transferring chemicals from a labeled container to a portablecontainer intended for immediate use, a label identifying thecontents e.g.. Acetone, must be applied Staff members areresponsible for properly emptying, cleaning, removing the label, anddisposing of the portable container immediately after use.

When transferring chemicals from a labeled container to a portablecontainer intended for longer than immediate use, or use by morethan one employee, a completed HMIG label should be used

Project Managers or their designates shall provide other employersat the work place with appropriate hazard communication informa-tion about hazardous chemicab Makolm Pirnie introduces to thework site that their staff could be exposed to*

Hits hazard communication information shaU indude:

The location of thi written Hazard Communication Pro-gram, the MSDSs or MSDS Station, and the ComprehensiveLast of Hazardous Chemicals.

For hazardous chemicab Makolm Pirnie introduces to awork site, any precautionary measures being taken toprotect Malcolm Pirnie staff from harmful exposure undernormal operating conditions, and foreseeable emergencies.

June 1993 2-7

Page 202: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUOOLMP1RNIE

HAZARD COMMUNICATION PROGRAM

Obtaining Information fromOther Employees

HAZARD COMMUNICATIONTRAINING

Hazard Communication TrainingProgram for HazardousChemicals Malcolm PimieIntroduces to the Workplace, Minimum Requirements

Project Managers or their designates shall make diligent efforts toobtain appropriate hazard communication Infbnnatloa abouthazardous substances used by other employers that Malfflla Pfanhstaff may b* exposed to. This information should indude:

The location of the other employees) written HazardCommunication Programs, their Comprehensive List(s) ofChemicals, MSDSs or MSDS Station, and an explanation ofthe labeling system the other employees) use.

Precautionary measures Makolm Piraie staff should take toprotect themselves from harmful exposure to these hazard-ous chemicals under normal operating conditions, andforeseeable emergencies.

Appendix C at the end of this section has sample letters appropriatefor soliciting this information from owners and other contractors.

Malcolm Pimie staff complete initial Hazard Communication Train-ing at the beginning of their employment and before starting tasksor assignments that may expose them to hazardous chemicals.

Staff members who work with or are potentially exposed tohazardous chemicals Malcolm Pimie introduces to the work placeshall receive additional training on the safe use of them. RegionalOfficers, Branch Managers, and Project Managers shall provideresources sufficient to assure the availability of this training;

Hazard Communication Coordinators are responsible for conduct-ing Hazard Communication Training or arranging for k to beprovided. Both the training and associated materials may bedeveloped locally to supplement materials provided by the Manager,Health and Safety, WHL

The Hazard Communication Training program for hazardouschemicals Malcolm Pirnie introduces to the work place MnphaMT^the following:

A summary of the Hazard Communication Standard (seeAppendix A, this section) and details of Malcolm Pirate'swritten Hazard Communication Program.

Use of MSDSs and the HMIG container labeling systemdiscussed in this section, MSDSs locations, reading andinterpreting labels and MSDSs, and how employees canobtain more hazard communication information.

June 1993

Page 203: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUOOLMPIRNIE

HAZARD COMMUNICATION PROGRAM

Measures employees can take to protect themselves againstthe physical and health hazards of chemicals in the workplace, including appropriate work practices or methods forusing and handling chemicals, emergency response proce-dures, and, as required, the proper use and maintenance ofpersonal protective equipment

Chemical and physical properties of hazardous chemicalse.g., flash point, and reactivity. Also, ways to detect thepresence or release of hazardous chemicals in the workplace, e.£, the visual appearance or odor of hazardouschemicals released Also, sir sampling devices to determineexposure concentrations.

Health hazards, including signs and symptoms of exposure,associated with exposure to chemicals, and medical condi-tions aggravated by chemical exposure.

Hazard Communication Training The Hazard Communication Training program for hazardousProgram For Hazardous Chemicals chemicals other employers introduce to the work place emphasizesOther Employers Introduce to the the following:Work Place, Minimum Requirements

Information about hazardous chemicals Malcolm Pirnie staffmay be exposed to at the work site, including ways to detecttheir presence, and exposure to them.

An explanation of the other employers' labeling system.

Information about precautionary measures Malcolm Pirniestaff members can take to protect themselves during normaloperating conditions and in emergencies.

The location of MSDSs for hazardous chemicals otheremployers introduce to a work site.

Hazard Communication The Manager, Health and Safety, Wffl, or designate shall reviewTraining Program Review Malcolm Pirnie's Hazard Communication Training program and

advise Branch Managers on training or retraining needs. Eaplop*ces who may be exposed to hazardous chemicals are to be retrainedwhenever the chemical hazards change, and when MaJcoha PinkIntroduces a new chemical hazard to the work place.

The Hazard Communication Training program assessment processincludes periodically obtaining opinions from employees about thequality of the training they receive.

NON-ROUTINE TASKS When planning a new or unusual method, protocol, procedure ortask with perceived potential or certain staff exposure to new

June 1993 2-9

Page 204: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

HAZARD COMMUNICATION PROGRAM

hazardous chemicals, supplemental Hazard CommunicationTraining and health and safety planning are to be discussed with theProject Manager, the Health and Safety Officer designated for the•he, the local Health and Safety Coordinator and/or the Manager,Health and Safety, WHL

FOR MORE INFORMATION ON Employees can obtain more information on this written HazardHAZARD COMMUNICATION Communication program, the Hazard Communication Standard,TRAINING MSDSs, training, and labeling by contacting the Manager, Health

and Safety, WHI, their Regional Officer, Branch Manager ordesignate.

The Manager, Health and Safety, Regional Officers, BranchManagers, or their site designates, shall make Malcolm Pirnie'swritten Hazard Communication Program available, upon request,to staff members, the Assistant Secretary of Labor for OccupationalSafety and Health, and the Director of the National Institute forOccupational Safety and Health.

June 1993 2-10

Page 205: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ATTACHMENT D

SUPERVISOR'S INCIDENT INVESTIGATION REPORT(Refer to /averse side for directions)

1. Offloa Location (No. a> Straat) (Oty or Town) (Slate) (Zip) 2. Projact No.

3. Nama of fcnjurad and Emptoyaa # 4. Soda! Sacurtty No. s. Aga 6. Sax Mala

7. Addraaa of tnjurad

•.Group* 9. Occupabon 10, Y«ar» of Saw. 11. Data &T)ma of Injury or Dnaaa

12. Natura of Injury of Hnaaa Including body part

13. Location of acddant or cauaa of Hnaaa (GK* addratt for locations of •mptoyar'* pramlaa*)

14. Daacriba afl avanla laadtng up to tha Injury, Including Injurad't actiona.

15. Paaorlba tfw root cauaa of ttta actfdant/nnatt and tot any othar contributing factors.

15a. Waa paraonal protactfon aqulpmant raqulrad? Waa N balng worn?

16. Nama ttta objact or aubatanca which dlractty injurad tha amployaa.

17. Data & tima of traatmant

IS. Nama & addraaa of traattng phyaiclan or atlandant

19. Nama & addraaa of hoapttal 0f appQcabla)

20. Traatmant provtdad to Injured

21. Oaacflba tha acbonfi) takan to pravant a raourranoa of tha InJury/Dlnata and ravlaw thia raport wHh ttta Injurad.

22. NamaM of p*rton(t) raaponaibla for oorracova actton and data action* ara to ba oomplatad.

23. Nama(t) of wto>aaa(aa) ftf appflcabto) • 24. Suparviaor'ft Signatura Date

25. Oaaamcatton of Injury or INnaaa tdrda ona) (Chaok ona) 28. Infury ___

AWCaaa_______RACaaa_____NFCaaa_____FACaaa_____PCCaaa_____NFRCaaa________Bnaaa27. Aaaodata't S^natura Da» Officar'* Signatura Data Comp. & Bfta. Mgr'a Sgnatura Date

A COPY OF AU CASE REPORTS MUST BE SENT TO THE CORPORATE HUMAN RESOURCES DEPARTMENT WTTHW 0 WORKING DAYS.

Page 206: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

ATTACHMENT D (continued)INSTRUCTIONS FOR COMPLETING THIS FORM

1.-7. Saff Explanatory

8. Group fwhara ragularly wnployvd). Enter tha nama of tha group or sactlon In which the individual to ragularty amployad, avsn toughtemporarily working In anothar dapartmant at tha tima of tht Injury.

9. Occupation (regular Job titia). Enter ragular Job titto. not tht spacffic activity balng parformad «t tha tima of Injury or (Unas*.

10.-13, Satf Explanatory

14. Nature of tha Injury of Mnaaa Oaaoriba lha Injury or lllnass In datafl and Indicate tha part of lha body affacted (a.g. amputation of rightIndax fingar at aaoond joint; fraetura of ribs; darmatitis of laft hand. ate.). Whara antira body la affactad, lha antry "body" can ba uaad.

15. Satf Explanatory

16. Traatmant Oaaoriba brlafly traatrnant grvan for Injury or Ulnasa, {a.g., suturad laceration on toft wrist, x-rayed right arm for poaaibto fractura.hoepftaAzed for observation, ate.)

17. Location of tha Accident or Mneaa Ba aa apadfic at poasibto • building, floor, machlna or unft. V aoddant oocurrad outakto oompanypremises at an Identifiable addraaa. glva that address. If H oocurrad on a public highway or at any othar plaoa which cannot ba ktenttftedby numbar or street, provlda references locating tha placa of Injury as accurate aa possfbto.

1$. Describe the AoeUant/Unaaa. BE SPECIFIC, If tha paraon was using tools or aqulpmant or handling a material, narna tham and telwhat ha/aha was doing with tham. Uat aafaty aqulpmant amployaa was using, i naoasaary add a supplemental paga, but ba as brtafaa poeaJbte.

tg. Describe tha Root Causa What was tha fundamental cause(s) of this aoddant/Blnast. This would not hava oocurrad K _______Uat aH tha othar contributing causas that you can think pUyad a rola In thto Injury/Illness. Including unsafa

acts, conditions and waathar factors, V naoassary add a supplamantal paga. but ba as bdaf as posslbto.

20. Narna Aa Object or Subatanoa WWch Dtractiy Injurad tha Employ** E.Q., tha machlna or thing tha paraon struck agalnat or whlohstruck lha paraon; tha vapor or potoon tha parson inhaiad or swallowad; tha chamical or radtotion which krfteted tha parson's akin; or Incaaas of strains, hamlas, ate., tha thing tha parson was lifting, pulling, ate.

21. Daacrfea tha Actfon(s) Takan to Prwant a Racurranca of tha InJury/Klnass Ba spadflc. What has or wU ba dona Including ohangaof mathod, addtttona) training, substitution of tools or matarials, ate.

2Z.-24, Salf Explanatory

25. AW, Away-rVom-Work-Caao - to any occupational injury or lllnass which rasutts in daath, parmanant Irnpajrmant, or which randan lhaInjurad paraon unabto to work for a &lj.day on any Job on any ragulariy schsdulad work day after tha Injury. (Do not Induda partial dayoff)

RA, Raalricted Acthrity Caaa- to any occupational Injury or lllnass which randan an amployaa unabto to parfonn aft dutias of hto ragulariyachadutod fob or tha amployaa was assignad to do a temporary Job on any ragularty schadulad day after tha Injury or Hnaas.

NF, Non-Fatal Caaa • to an occupation*/ Injury or lllnass which did not Involva a fatality or lost work days, but did rasuft In: a) tranafar toanothar Job or termination of amploymant or b) madical traatmant othar than first air or c) diagnosis of occupational Bnass or d) loss ofoonadouanaas.

FA, First AM Caaa - Ona ttma traatmant and subsaquant obsarvation of minor acratchas, cuts, bums, apOntora which do not onxnarlyroqulra profaaalonaJ madlcaj can avan though tha traatmant was providad by a physician or raglsterad profaaalonal panonna(.

PC, Pracautionary Caaa- Whan no Injury or lllnass can ba datactad by qualHiad parsonnal or physicians, but tha amployaa aM sBagsaInjury or Hnaas, tha caaa to pracautionary. Oocumantetion to mandatory.

NFR, Not For Racord - In many situations which a casa to PC tha casa wUI not ba raoordad on Company Racords or in tha U.S. on t*aLog 200. Dooumontotion to mandatory.

h ganaral an Injury to tha raautt of an instantanaous avant In tha workplaos. Thara ara axotptiona such aa: Back Casas ara Injurtoaand Waldlng Flashaa ara Olnasaa*. Rafar to OMB Publication No. 1220-0029 axposuras to Itlnaas. In ganaral an Hnaas to any abnormalcondition resulting from prolongad or rapaatad anvironmantal factors assodatad with amploymanL Thosa can ba eausad by Inhalation,absofptkxi, Ingaation or dlract contact

27. AM algnaturas ara raqulrad for Daatha and AW Casas.

Page 207: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between
Page 208: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX D

Final Design Drawings(Under Separate Cover)

FINAL DESIGN REPORT

LTR Site Closure

Prepared for:

Lemberger Site Remediation Group

Submitted by:

Malcolm Pirnie, Inc.Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, MN 55416

Page 209: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

MAUDOUViPIRNIE

E

Page 210: MALCOLM PIRNIE INC - FINAL DESIGN REPORT · The LL and LTR Sites were licensed from 1969 until 1976, when WDNR did not renew the landfill license. LTR Site records indicate that between

APPENDIX E

Final TechnicalSpecifications(Under Separate Cover)

FINAL DESIGN REPORT

LTR Site Closure

Prepared for:

Lemberger Site Remediation Group

Submitted by:

Malcolm Pirnie> Inc.Environmental Engineers, Scientists & Planners5500 Wayzata BoulevardMinneapolis, MN 55416