Page 1: Making Building Systems Sing in Harmony Retrocommissioning

Making Building Systems Sing in Harmony

Retrocommissioning in Vermont

Daniel Tuhus-Dubrow

Cx Associates

Presented by:

Page 2: Making Building Systems Sing in Harmony Retrocommissioning
Page 3: Making Building Systems Sing in Harmony Retrocommissioning

Agenda

What is Retrocommissioning?

The RCx program in Vermont

RCx Process

Common RCx Findings

Case Studies

Challenges and Opportunities

Page 4: Making Building Systems Sing in Harmony Retrocommissioning

Retrocommissioning is…..

Process for ensuring systems and equipment are operating per the current facility requirements

Repairing Deficiencies

Optimization of Existing Building Operation

Measures are typically low or no cost to implement

Page 5: Making Building Systems Sing in Harmony Retrocommissioning

Retrocommissioning is…..

Other Potential Benefits Operations and Maintenance Occupant Thermal Comfort Improved Indoor Air quality

Page 6: Making Building Systems Sing in Harmony Retrocommissioning

Retrocommissioning is NOT…..

Capital improvement projects:

However… Equipment at the end of its useful life will often be identified through the RCx process.

Lighting retrofits

Equipment replacement

Window upgrades

Page 7: Making Building Systems Sing in Harmony Retrocommissioning

Reducing Greenhouse Gas Emissions

Commercial buildings consume nearly half of the building energy used in the United States (around 20% of total U.S. energy consumption and greenhouse gas emissions)

RCx Potential

Saving Money

Median whole building energy savings of 16%

Median cost of $0.25 per sf

Median payback time of 1.1 years

Page 8: Making Building Systems Sing in Harmony Retrocommissioning

RCx Potential

Page 9: Making Building Systems Sing in Harmony Retrocommissioning

The RCx Program in Vermont

Programs from Efficiency Vermont and BED

Qualify Develop Implement Verify

Page 10: Making Building Systems Sing in Harmony Retrocommissioning

Steps in Qualifying Phase

Pre-qualify

Walkthrough by team

Findings and Recommendations

Estimate energy savings

Page 11: Making Building Systems Sing in Harmony Retrocommissioning

Development Phase

Document Baselines

Refine Savings Estimates

Develop Scopes of Work

Obtain Pricing for Implementation

Page 12: Making Building Systems Sing in Harmony Retrocommissioning

Implementation Phase

Pay for performance

$0.10/kWh up to $25,000

Vendors implement recommendations

Page 13: Making Building Systems Sing in Harmony Retrocommissioning

RCx Process

Building Energy Benchmarking

Review Available Documentation

Utility Data Analysis

Site Visits and Field Investigations

Trend Data Analysis

Measure Development

Implementation

Page 14: Making Building Systems Sing in Harmony Retrocommissioning

Benchmarking

Energy Star Portfolio Manager

DOE Building Performance Database

Page 15: Making Building Systems Sing in Harmony Retrocommissioning

Benchmarking

Page 16: Making Building Systems Sing in Harmony Retrocommissioning

Building Documentation

Mechanical/Electrical Drawings

Controls Drawings

TAB reports

Previous energy assessments

Page 17: Making Building Systems Sing in Harmony Retrocommissioning

Utility Data Analysis

Monthly Bills

Electric Interval Data

Delivered Fuels

Page 18: Making Building Systems Sing in Harmony Retrocommissioning

Utility Data Analysis

Page 19: Making Building Systems Sing in Harmony Retrocommissioning

Interval Data Analysis

Opportunity to Adjust Operating Schedule?

Page 20: Making Building Systems Sing in Harmony Retrocommissioning

Interval Data Analysis

Page 21: Making Building Systems Sing in Harmony Retrocommissioning

Interval Data Analysis

Occupied Baseload

Cooling Balance Temp

Cooling Demand

Page 22: Making Building Systems Sing in Harmony Retrocommissioning

Interval Data Analysis

0 25 50 75 100

Page 23: Making Building Systems Sing in Harmony Retrocommissioning

Site Visits

Meeting with Key Stakeholders

Systems Assessment

Datalogger Deployment

Targeted Testing

Page 24: Making Building Systems Sing in Harmony Retrocommissioning

Kickoff Meeting

Page 25: Making Building Systems Sing in Harmony Retrocommissioning

Teamwork

Have the

right people!

Team

Commissioning Engineer

Controls Contractor

Facilities Staff

Introduce Perspectives

Brainstorm

Identify Opportunities

Evaluate Merit

Page 26: Making Building Systems Sing in Harmony Retrocommissioning

Building Walkthrough

Page 27: Making Building Systems Sing in Harmony Retrocommissioning

Systems Assessment

Page 28: Making Building Systems Sing in Harmony Retrocommissioning

BAS Remote Monitoring

Page 29: Making Building Systems Sing in Harmony Retrocommissioning

BAS Remote Monitoring

Page 30: Making Building Systems Sing in Harmony Retrocommissioning

Dataloggers

Page 31: Making Building Systems Sing in Harmony Retrocommissioning

Trend Data Analysis

Verify existing control sequences

Are setpoints being maintained?

Is economizer operating properly?

Are resets working as intended?

Is equipment running per schedule?

Page 32: Making Building Systems Sing in Harmony Retrocommissioning

Trend Data

Analysis

Spreadsheet based charting

Universal Translator

Dedicated analytics software

Other Tools

Page 33: Making Building Systems Sing in Harmony Retrocommissioning

Trend Data Analysis

Page 34: Making Building Systems Sing in Harmony Retrocommissioning

Trend Data Analysis

Page 35: Making Building Systems Sing in Harmony Retrocommissioning

Methods for Estimating Savings

End Use Disaggregation

Engineering Calculations Bin Calcs Hourly Spreadsheets

Regression Models

Energy Simulation

Page 36: Making Building Systems Sing in Harmony Retrocommissioning

Common RCx Findings

• Scheduling

• Economizer Operation

• Simultaneous heating and cooling

• Calibrating or relocating sensors

• Return Equipment to AUTO control

• Release BAS Overrides

• VAV box minimum flow settings

• Correct VFD settings

• Optimize Control Sequences

Page 37: Making Building Systems Sing in Harmony Retrocommissioning

Operating Schedules

Page 38: Making Building Systems Sing in Harmony Retrocommissioning

Throttled Valves

Page 39: Making Building Systems Sing in Harmony Retrocommissioning

Stuck Dampers

Page 40: Making Building Systems Sing in Harmony Retrocommissioning

Equipment Overrides

Page 41: Making Building Systems Sing in Harmony Retrocommissioning

Damaged Sensors

Page 42: Making Building Systems Sing in Harmony Retrocommissioning

Measure Development

Document baselines

Focused PFCs and FPTs

Refine savings estimates

Develop scopes of work

Obtain pricing

Page 43: Making Building Systems Sing in Harmony Retrocommissioning

Project Case Studies

Building Types Hospitals Universities K-12 Schools Office Buildings Ski Resorts Food Processing Municipal

Page 44: Making Building Systems Sing in Harmony Retrocommissioning

Projects Overview

N = 28 6,000 – 200,000 sf Median = 34,800

Page 45: Making Building Systems Sing in Harmony Retrocommissioning

Projects Overview

> $350,000 potential savings 0.5 – 4.5 years Median = 1.9

Page 46: Making Building Systems Sing in Harmony Retrocommissioning

Hospital AHU Optimization

Page 47: Making Building Systems Sing in Harmony Retrocommissioning

Measure Summary

Dehumidification setpoints unnecessarily low (40-45%)

Economizer lockout setpoints unnecessarily low

Economizer controlling to MAT setpoint rather than SAT setpoint

Implement static pressure reset

Enable supply air temperature reset

Used Guideline 36 recommendations where possible

Verify calibration of controlling sensors

Unnecessary filters with higher efficiency than required

Page 48: Making Building Systems Sing in Harmony Retrocommissioning

Hospital AHU Optimization

Pre Post

Page 49: Making Building Systems Sing in Harmony Retrocommissioning

Challenges

Getting to Implementation Measure Persistence

Page 50: Making Building Systems Sing in Harmony Retrocommissioning

Implementation

Facility buy-in

EVT / BED involvement

Incentives help

Page 51: Making Building Systems Sing in Harmony Retrocommissioning

Measure Persistence

Training is KEY

Post-Implementation BAS Monitoring

Establish continuous energy improvement program

Page 52: Making Building Systems Sing in Harmony Retrocommissioning

Opportunities

LARGE MARKET POTENTIAL

ONGOING COMMISSIONING

ENERGY MANAGEMENT INFORMATION

SYSTEMS

Page 53: Making Building Systems Sing in Harmony Retrocommissioning

Ongoing Cx

Page 54: Making Building Systems Sing in Harmony Retrocommissioning

Thank You!

Daniel Tuhus-Dubrow

Senior Engineer

Cx Associates

Burlington, VT

802-861-2715 x21

[email protected]