MagnaChip Semiconductors, Ltd.
The Corporate NPI Process - New Technology & Product Introduction (V 3.0)
January 30, 2010
2MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
ContentsContents1. General Provisions1.1 Purpose, scope, and standardization committee1.2 Role & responsibility
2. NPI basics2.1 Project & NPI stages2.2 Project type definition2.3 Stepwise progress check2.4 Cross functional project management2.5 Change management2.6 Performance metrics
3. MC brand product development process3.1 Project classification3.2 Key activities3.3 Overall development process3.4 Key review points (P1 ~ P7)3.5 Summary of checkpoint approvers & deliverables3.6 Change management R&R
4. Foundry product development process4.1 ~ 4.6: Same order as section 3.1~3.6
5. MC brand technology development process5.1 Project classification5.2 Key activities5.3 Overall development process5.4 Key review points (T1~ T7)5.5 Summary of checkpoint approvers & deliverables5.6 Change management R&R5.7 DK update process
6. COTT process6.1 ~ 6.6: Same order as section 5.1 ~ 5.6
7. Qualification criteria7.1 Key summary of qualification test criteria7.2 Technology qualification items7.3 Product qualification items7.4 Product re-qualification criteria – general7.5 Product re-qualification criteria – power product7.6 Reliability test checklist
AppendixA1. Yield calculation modelA2. Terminologies
3MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
Keydeliverables
Keydeliverables
• Project charter
• Kick off material• Work sheet• Key process
module setup• Unit setup
R&D
MFG
DirCP &Approver
T1Planning
T1Planning
T2 Kick off &key process
T2 Kick off &key process
TDRB Dir DirManager TDRB
Communication for productionCommunication for production Equipment CorrelationEquipment Correlation
P7 Yield UpP7 Yield Up
T3Pre DK
T3Pre DK
T4Si verified spec
T4Si verified spec
T5Tech freeze
T5Tech freeze
T6Product level qual
T6Product level qual
StagereviewStagereview
5.4 Key review points (T1 ~ T7)
Full chip design & evaluationFull chip design & evaluation
Yield >70% Yield >70%
ProjectcharterProjectcharter
POR 1.0 review
POR 1.0 review
Product yield CUM ≥ 90%
Product yield CUM ≥ 90%
TDV with IP/Libdesign & eval
TDV with IP/Libdesign & eval
1st POR review
1st POR review
DK 0.0DK 0.0Kick off
Kick off
Key process module setupKey process module setup
POR 0.8
POR 0.8
Product level qualProduct
level qual
TDRBpassreject
TCP
MDV designMDV
design
CP
CP
PDK 0.1
PDK 0.1
CP
TCP TDRB
TuningTuning
RevisionRevisionCP
Internalreview
Internalreview
SpecSpec
CP
• DR doc• Tooling
spec• Pre DK
v 0.0• POR 0.0
• Si verified spec• 1st POR data• PDK v 0.1
• Development report• Qualification data
- Product, IP/Lib qual- 2nd & 3rd WLR data
• POR 1.0 review• PDK 1.0
• Product yield trend
• Equipment multiplication
• Tech maintenance
TDRB TCPCPTCP TCP
WBSWBS
CP CPCP CP CP CP CP
Device checklistDevice
checklistIP / Lib qual passIP / Lib qual passPlatform
reviewPlatform review
Biz impact review
Biz impact review
DRDR
TCP
Si verified specPOR 0.1
Si verified specPOR 0.1
Process freeze
Process freeze
1ST WLRpass
1ST WLRpass
CP
PDK 0.9
PDK 0.9
ESD ruleESD rule
CP
Final WLRpass
Final WLRpass
CP
Tech maintenance
Tech maintenance
PDK 1.0
PDK 1.0
PDK 1.x
PDK 1.xTP planTP plan
MilestoneRisk reviewMilestone
Risk review
TDRB
Unit process setup
Unit process setup
• Tech setup report- TDV (w IP/Lib) evaluation data- POR v 0.8
• 1st WLR data• FMEA• PDK & POR 0.9
4MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.1.1 T1 – deliverables (platform / derivative / option)
• Marketability (Marketing)
Category
Project code(PM)
Deliverables Key contents
• Technical feasibility & risks (PM)
• Market trend & competitiveness• Business impact analysis• Target customer & spec
Project charter
(Marketing, PM, & QRA)
• Technical issues- equip capability, patent, etc
• Lesson learned
• Project priority (Marketing)
• NPV (ROI) data• Strategic importance• Project priority setting
• Project code generation • Code generation request
Timeline
AfterT1 TDRB approval
BeforeT1 TDRB review• Development plan (PM)
• Key milestones, development cost• Risk assessment
• Qualification plan (QRA)• Qualification criteria• Key milestones• Risk assessment
• For Option project: Some owners can be changed (Project manager Div PE, Marketing account manager)
5MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.2.1 T2 – deliverables (platform / derivative)
CategoryDeliverables Key contents
Kick off material
(PM)
Timeline
At T2kick off meeting
• Target spec & schedule (PM)
• Device implementation target• Development schedule• Project staffing & organization
• Technical issues (PM)
• Risk assessment (patent, etc)• Equipment / measurement capability review (PM / MEC)
• Reliability test methodology (QRA)• Customer urgency, implementation difficulties, etc
Work sheet(PM)
• Work breakdown structure
• Key activities & deliverable listof each NPI stage
At T2 TCP review
Key process module setup
report (PM)
• Key process module setup review
• Implementation target, risks, and resultsAt T2 TCP review
(if exist)Unit process setup report
(PM)
• Unit process & OPC review
• New unit process & equipment review• OPC rule review
6MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.3 T3 Preliminary design kit – CP (platform / derivative)
• Design rule doc & tooling spec (v 0.0)
CategoryDeliverables Key contents
• DR doc v 0.0• Preliminary tooling spec
DR & tooling(CE tech)
Timeline
At T3 CP review• Spice model v 0.0• Preliminary rule deck
• Preliminary design kit
• Control plan & e-sheet v 0.0• Control plan
Pre DK(CE infra)
POR 0.0 (CE tech)
7MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.4.1 T4 – deliverables (platform / derivative)
• Device checklist• TCAD simulation result• MDV description & evaluation data
• Fab data (inline, PCM)
CategoryDeliverables Key contents
• Device checklist• TCAD simulation result• MDV description & evaluation data• Equipment capability review• DR margin review- TP readiness checkup
• Fab data - inline data, PCM data
Si verified spec(PM)
Timeline
At T4 TCPFE design review
meeting• Control plan & e-sheet
• 1st POR which is reviewed with Div PE & MEC
• Control plan & E-sheet
POR v 0.1(PM)
• Si verified DR & tooling• Si verified E-para• Si verified Spice model• Rule deck & Pcell• Bit cell data (if exist)
• DR doc (v 0.1)• Si verified mask tooling spec• Si verified E-parameters• Si verified model• Si verified rule deck • Preliminary Pcell & symbol• Bit cell ready (if exist)
PDK v 0.1(Infra)
8MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.5.3 T5 – deliverables (platform / derivative)
CategoryDeliverables Key contents Timeline
• Device checklist• TDV plan & evaluation
• Device checklist• TDV (with ESD TP, IP/Lib, etc) plan & evaluation data
• E-test data – DR margin reviewTech setup
report(PM)
At T5 TCP review
• 1st WLR test data• WLR test condition & pass/fail criteria• WLR test data
1st WLR(QRA)
• DR doc• Tooling spec• PCM spec• E-para• Interconnect para• Spice model• Rule deck • Pcell & symbol• Bit cell ready (if exist)
• DR doc (core & ESD)• Mask tooling & reverse tooling spec• PCM spec• E-parameters• Interconnect parameters• Basic, matching, noise, etc.• DRC, LVS, XRC, auto JDV rule deck• Pcell & symbol• SRAM, 1T, NVM, etc.
PDK v 0.9(Infra)
• Control plan & e-sheet • Control plan & e-sheetPOR v 0.9
(PM)
• FMEA (technical issues) • Technical issues review dataFMEA(PM)
• Fab data– Inline, PCM data
• In-line data, PCM data• Equipment capability review
9MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.5.4 T5 – deliverables (option)
CategoryDeliverables Key contents Timeline
Device setup report(PE)
At T5 TCP review• 1st WLR test data
• WLR test condition & pass/fail criteria• WLR test data
1st WLR(if exist)(QRA)
• DR doc (core & ESD)• Mask tooling spec• PCM spec• E-parameters• Interconnect parameters• Basic, matching, noise, etc.• DRC, LVS, XRC• Pcell & symbol
PDK v 0.9(Infra)
• Control plan & e-sheet • Control plan & e-sheetPOR v 0.9
(PE)
• FMEA (technical issues) • Technical issues review dataFMEA(PE)
• DR doc• Mask tooling spec• PCM spec• E-para• Interconnect para• Spice model• Rule deck • Pcell & symbol
• Device target spec• TP plan & evaluation• TCAD simulation result
• Device target spec review• TP description & & evaluation data• TCAD result – DR margin review• E-test data
• In-line data, PCM data• Equipment capability review
• Fab data – Inline, PCM data, corner split result
10MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.6.1 T6 – WLR transfer criteria (to MFG)
• GDS data
itemCategory Key contents
• GDS data
WLR
• E-sheet• Cpk
• E-sheet• Cpk (each layer)• CD measurement sample (each layer)
Process
• 2nd & 3rd WLR test result• WLR test history (with improvement items)• Wafer requirements for each item
Device
• TP description• Keithley program & limit file name• Probe card (with pin number)• W-test spec• PCM capability index
DB
• TP & measurement program
• P-card• PCM spec
• Mask tooling• PG rule file• Mask data
• Mask tooling spec• Mask description (including wafer layout)• Mask revision history• Final mask set
Mask
• WLR maintenance shall start at T7.• After WLR transfer, lot owner of WLR maintenance becomes MEC (MFG).
• Basic rule for WLR transfer to MFG is to pass the 2nd & 3rd WLR test results.• If satisfies WLR items below, WLR owner shall be transferred to MFG
11MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.6.2 T6 – deliverables (platform / derivative / option)
• Product or IP/Lib qualification data
CategoryDeliverables Key contents
• Reliability test data (QRA)
Development completion report (PM)
Timeline
At T6 TDRBProduct level qualification
review
Project code (PM) • Project code closure • Code close requestAfter T6 TDRB
approval
• WLR data• 2nd & 3rd WLR test data (QRA)• WLR transfer review
• Control plan & e-sheet• Inline spec
• Control plan & e-sheet, Inline spec which are reviewed with MEC (POR 1.0 review)
POR 1.0 (PM)
• Customer promotion material• Core rule & ESD rule• Mask tooling & reverse tooling spec• Final PCM spec• Basic, matching, noise, etc• E-para, Interconnect para• DRC, LVS, XRC, auto JDV rule deck• Pcell & symbol• SRAM, 1T, NVM, etc
PDK v 1.0(Infra)
• Development report• Development completion report• Product or IP/Lib evaluation data (Test)
Performance index (Develop mgnt)
• On-time rate, revision times, revenue hit rate, NPI obedience rate, etc.
Final qualification report (QRA)
• For option project: Div PE can do project manager’s role.
• Presentation material• DR doc• Mask tooling spec• PCM spec• Spice model• E-para, Interconnect para• Rule deck• Pcell & symbol• Bit cell (if exist)
• R&D performance• Market performance
12MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.4.7.1 T7 Yield up – deliverables
• Yield data• Process data
CategoryDeliverables Key contents
• Yield trend data• Process control data• Lesson learned & PFMEA
Yield trend data
(MEC)
Timeline
During yield up activities
• PCRB data
• Yield trend data• Process control data• Lesson learned & PFMEA• Reason for why platform technology changes
PCRB data
If required for platform change
(MEC)
During yield up activities
• Tech maintenance data
• Tech maintenance data- tech vehicle review- process control data- Fab data review- yield data- issues
• Reason for why platform technology changes
Afterquarterly tech maintenance
• Recipe review data• Process uniformity check
• Equipment model based recipe checkup• Cp / Cpk review
Equipment multiplication
(MEC)Before mass production
13MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.5 Summary of check point approvers & deliverables
Check point Deliverables Owner Meeting call Approver
Project type Platform Derivative Option P/D O P/D O P/D O
T1 TDRB Project charter TM AM CE planning TDRB
T2 TCP
Kick off materialWork sheetKey process module setup reportUnit process setup reportRisk assessment
CE PMCE tech director
T3 CPPreliminary DR doc & tooling specPre design kit (v 0.0)Preliminary POR (v 0.0)
CE PM PM
T4 TCPSi verified spec1st POR – control plan & e-sheetPDK v 0.1
CEMECCE
PMCE tech director
T5 TCP
Tech / device setup reportFMEA1st WLRPOR v 0.9 – control plan & e-sheetPDK v 0.9
CECE
QRACECE
PEPE
QRAPECE
PM PECE techdirector
Div PE director
T6 TCP
Development completion reportFinal qual report (PQV qual, WLR data)POR 1.0 – control plan & e-sheetPDK 1.0Performance index
CEQRAMECCECE
PEQRAMECCEPE
PM PE TDRB
T7Yield trend dataEquipment multiplicationPCRB data if tech changes
MEC MECMEC mgr
PCRB
* AM: account manager, PM: project manager
14MAGNACHIP CONFIDENTIAL. DO NOT COPY OR DISTRIBUTE.
5.6 Change management R&RCategory Key item Owner Approval Remark
Project type P/D O P/D O
Project initiation
Checkpoint review (TDRB) TM AM TDRB Deliverables registration onto MDCS
Project code generation PM PE CE director AM/PE mgr Use e-approval (Magnaware)
Development
Schedule revision PM PE GM PE directorIf delay to the coming TCP/CP >30%,
compared to the latest plan
Market revision(Biz potential, etc)
TM AMMarketing director
If market change > 30%,compared to the latest plan
Project drop
TM AM GM
Project code closure (e-approval)
Project holdProject inactivated (not counted for delay)
Revisit bimonthly for project drop or resume
Project resume Restarting from hold
Revision mask PM PE GM If revision occurs
Checkpoint review (T2-T5) - TCP - CP
PM PECE director
PMPE dir
PE mgrDeliverables registration onto MDCS
Completion
Final report (T6) PM PE TDRB Development completion & POR 1.0 review
Performance index - R&D performance - Marketing performance
PMTM
PEAM
TDRB Target, cost, & schedule
Revenue, gross margin, & hit ratio forecast
Project code closure PM PE CE director AM/PE mgr Use e-approval
Final DB registration PM PE CE director PE dir DB registration to DT team
Status monitoring
Project status monitoring - on time rate - deliverables status - revision times - NPI obedience status
Development planning part
GM Monthly status review
* AM: account manager, PM: project manager, GM: if CE project, CE head, and if Div project, Div head