macarthur transit village project€¦ · macarthur transit village project volume 1. draft...

407
January 2008 Prepared for: City of Oakland MACARTHUR TRANSIT VILLAGE PROJECT Volume 1. Draft Environmental Impact Report SCH No. 2006022075

Upload: others

Post on 28-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

  • January 2008

    Prepared for: City of Oakland

    MACARTHUR TRANSIT VILLAGE PROJECTVolume 1. Draft Environmental Impact ReportSCH No. 2006022075

  • MACARTHUR TRANSIT VILLAGE PROJECT Volume 1. Draft Environmental Impact Report SCH No. 2006022075

    Prepared for: City of Oakland January 2008

  • N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008) i

    TABLE OF CONTENTS

    VOLUME 1. DRAFT EIR

    I. INTRODUCTION ............................................................................................................... 1 A. PURPOSE OF EIR................................................................................................ 1 B. PROPOSED PROJECT .......................................................................................... 1 C. EIR SCOPE......................................................................................................... 3 D. REPORT ORGANIZATION ................................................................................... 4

    II. SUMMARY ....................................................................................................................... 7 A. PROJECT UNDER REVIEW ................................................................................... 7 B. SUMMARY OF IMPACTS AND MITIGATION MEASURES......................................... 7 C. SUMMARY TABLE ............................................................................................ 10

    III. PROJECT DESCRIPTION ................................................................................................. 47 A. PROJECT SITE.................................................................................................. 47 B. PROJECT BACKGROUND .................................................................................. 52 C. PROJECT OBJECTIVES....................................................................................... 53 D. PROPOSED PROJECT ........................................................................................ 54 E. DISCRETIONARY ACTIONS............................................................................... 71

    IV. SETTING, IMPACTS, STANDARD CONDITIONS OF APPROVAL, AND MITIGATION MEASURES................................................................................................................. 75 A. LAND USE ....................................................................................................... 81 B. PUBLIC POLICY................................................................................................ 91 C. TRANSPORTATION, CIRCULATION AND PARKING........................................... 123 D. AIR QUALITY................................................................................................. 227 E. NOISE AND VIBRATION.................................................................................. 281 F. HYDROLOGY AND WATER QUALITY ............................................................... 311 G. GEOLOGY, SOILS AND SEISMICITY ................................................................. 329 H. PUBLIC HEALTH AND HAZARDS ..................................................................... 347 I. PUBLIC SERVICES........................................................................................... 365 J. UTILITIES AND INFRASTRUCTURE .................................................................. 381 K. CULTURAL AND PALEONTOLOGICAL RESOURCES........................................... 397 L. AESTHETIC RESOURCES................................................................................. 425

    V. ALTERNATIVES ........................................................................................................ 455 A. PROJECT OBJECTIVES AND IMPACTS .............................................................. 456 B. CEQA PROJECT ALTERNATIVES ...................................................................... 461 C. PLANNING PROJECT ALTERNATIVES ............................................................... 483 D. ENVIRONMENTALLY SUPERIOR ALTERNATIVE................................................. 526

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 T A B L E O F C O N T E N T S

    ii N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008)

    VI. CEQA REQUIRED ASSESSMENT CONCLUSIONS ...........................................................555 A. GROWTH-INDUCING IMPACTS ........................................................................555 B. SIGNIFICANT IRREVERSIBLE CHANGES.............................................................556 C. SIGNIFICANT UNAVOIDABLE AND CUMULATIVE IMPACTS................................557 D. EFFECTS FOUND NOT TO BE SIGNIFICANT ......................................................558

    VII. REPORT PREPARATION .............................................................................................561 A. REPORT PREPARERS .......................................................................................561 B. REFERENCES ..................................................................................................563 C. CONTACTS....................................................................................................571

    APPENDICES VOLUME 2 Appendix A: Notice of Preparation and Comment Letters A1. 2006 NOP and Comment Letters A2. 2007 NOP and Comment Letters Appendix B: Air Quality B1. Health Risk Assessment B2. URBEMIS Modeling B3. CA Line Source Dispersion Model Appendix C: FHWA Roadway Noise Level Analysis Appendix D: Water Supply Assessment Appendix E: Land Use Database and Cumulative Growth Scenario Memorandum VOLUME 3 Appendix F: Transportation, Circulation and Parking

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R T A B L E O F C O N T E N T S

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008) iii

    List of Figures

    Figure I-1 Project Location and Regional Vicinity Map .............................................. 2 Figure III-1 Project Location and Regional Vicinity Map ............................................ 48 Figure III-2 Parcels within Project Site ...................................................................... 49 Figure III-3 Conceptual Site Plan .............................................................................. 56 Figure III-4 Conceptual Garage Level Plan ................................................................ 57 Figure III-5 Conceptual Street Level Plan .................................................................. 58 Figure III-6 Conceptual Upper Level Plan.................................................................. 59 Figure III-7 Conceptual 40th Street Elevation............................................................. 60 Figure III-8 Conceptual Telegraph Avenue Elevation................................................. 61 Figure III-9 Conceptual Internal Street Elevation....................................................... 62 Figure III-10 Proposed Circulation Plan ...................................................................... 66 Figure III-11 Conceptual Landscape Master Plan ........................................................ 69 Figure IV.A-1 Existing Land Uses in the Project Area ................................................... 83 Figure IV.B-1 General Plan Land Use Designation Map................................................. 94 Figure IV.B-2 Zoning Designations Map .................................................................... 101 Figure IV.C-1 Project Location................................................................................... 124 Figure IV.C-2 Study Intersections .............................................................................. 127 Figure IV.C-3 Existing Site Access and Circulation..................................................... 128 Figure IV.C-4 Transit Service..................................................................................... 132 Figure IV.C-5 Transit and Shuttle Facilities ................................................................ 133 Figure IV.C-6 MacArthur BART Station Layout............................................................ 141 Figure IV.C-7 Existing Bicycle and Pedestrian Facilities .............................................. 144 Figure IV.C-8 On-Site Parking Facilities ..................................................................... 147 Figure IV.C-9 Existing Pedestrian Volumes and Designated Routes............................ 148 Figure IV.C-10 Existing Bicycle Volumes and Designated Routes ................................. 150 Figure IV.C-11 Surrounding On-Street Parking............................................................. 153 Figure IV.C-12a Study Intersections (1-19) Existing Geometry ....................................... 156 Figure IV.C-12b Study Intersections (20-24) Existing Geometry ..................................... 157 Figure IV.C-13a Study Intersections (1-19) Existing Traffic Volumes.............................. 158 Figure IV.C-13b Study Intersections (20-24) Existing Traffic Volumes............................ 159 Figure IV.C-14a Inbound Travel Routes and Project Trip Distribution (Residential)......... 174 Figure IV.C-14b Outbound Travel Routes and Project Trip Distribution (Residential) ...... 175 Figure IV.C-15a Inbound Travel Routes and Project Trip Distribution (Non-

    Residential) ......................................................................................... 176 Figure IV.C-15b Outbound Travel Routes and Project Trip Distribution (Non-

    Residential) ......................................................................................... 177 Figure IV.C-16a Study Intersections (1-19) Existing Plus Project Conditions................... 182 Figure IV.C-16b Study Intersections (20-25) Existing Plus Project Conditions................. 183 Figure IV.C-17a Study Intersections (1-19) Cumulative Year 2015 Baseline No Project

    Conditions........................................................................................... 184

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 T A B L E O F C O N T E N T S

    iv N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008)

    Figure IV.C-17b Study Intersections (20-25) Cumulative Year 2015 Baseline No Project Conditions................................................................................185

    Figure IV.C-18a Study Intersections (1-19) Cumulative Year 2015 Baseline Plus Project Conditions................................................................................190

    Figure IV.C-18b Study Intersections (20-25) Cumulative Year 2015 Baseline Plus Project Conditions................................................................................191

    Figure IV.C-19a Study Intersections (1-19) Cumulative Year 2030 Baseline No Project Intersection Volumes............................................................................195

    Figure IV.C-19b Study Intersections (20-25) Cumulative Year 2030 Baseline No Project Intersection Volumes ................................................................196

    Figure IV.C-20a Study Intersections (1-19) Cumulative Year 2030 Baseline Plus Project Intersection Volumes ................................................................198

    Figure IV.C-20b Study Intersections (20-25) Cumulative Year 2030 Baseline Plus Project Intersection Volumes ................................................................199

    Figure IV.E-1 Noise Monitoring Locations ..................................................................295 Figure IV.G-1 Regional Faults.....................................................................................332 Figure IV.K-1 OCHS Properties Within and Adjacent To the Project Site ......................411 Figure IV.L-1 MacArthur BART Parking Lot and Frontage Road...................................427 Figure IV.L-2 MacArthur BART Plaza ..........................................................................428 Figure IV.L-3 Existing Buildings on the Project Site....................................................429 Figure IV.L-4 Views of Surrounding Areas .................................................................431 Figure IV.L-5 Photo Viewpoint Locations ...................................................................436 Figure IV.L-6 Conceptual Visual Simulation from Viewpoint 4....................................437 Figure IV.L-7 Conceptual Visual Simulation from Viewpoint 6....................................438 Figure IV.L-8 Conceptual Visual Simulation from Viewpoint 5....................................439 Figure IV.L-9 Conceptual Visual Simulation from Viewpoint 1....................................440 Figure IV.L-10 Conceptual Visual Simulation from Viewpoint 2....................................441 Figure IV.L-11 Conceptual Visual Simulation from Viewpoint 3....................................442 Figure IV.L-12 Project Shadow Patterns .......................................................................448 Figure IV.L-13 Project Shadow Patterns .......................................................................449 Figure IV.L-14 Project Shadow Patterns .......................................................................450 Figure IV.L-15 Project Shadow Patterns .......................................................................451 Figure IV.L-16 Project Shadow Patterns .......................................................................452 Figure IV.L-17 Project Shadow Patterns .......................................................................453 Figure V-1A Conceptual Plan, Existing Zoning Alternative ........................................468 Figure V-1B Conceptual Cross-Section, Existing Zoning Alternative..........................469 Figure V-2A Conceptual Site Plan, Mitigated Reduced Building/Site Alternative ........476 Figure V-2B Conceptual Cross-Section, Mitigated Reduced Building/Site

    Alternative ...........................................................................................477 Figure V-3A Conceptual Plan, Full BART Replacement Parking Alternative ................485 Figure V-3B Conceptual Cross-Section, full BART Replacement Parking Alternative...486 Figure V-4A Conceptual Plan, Tower Alternative ......................................................493 Figure V-4B Conceptual Cross-Section, Tower Alternative ........................................494

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R T A B L E O F C O N T E N T S

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008) v

    Figure V-5A Conceptual Plan, Increased Commercial Alternative ............................. 510 Figure V-5B Conceptual Cross-Section, Increased Commercial Alternative ............... 511 Figure V-6A Full BART Parking Replacement Alternative Visual Simulation ............... 531 Figure V-6B Full BART Parking Replacement Alternative Visual Simulation ............... 532 Figure V-6C Full BART Parking Replacement Alternative Visual Simulation ............... 533 Figure V-6D Full BART Parking Replacement Alternative Visual Simulation ............... 534 Figure V-6E Full BART Parking Replacement Alternative Visual Simulation ............... 535 Figure V-6F Full BART Parking Replacement Alternative Visual Simulation ............... 536 Figure V-7A Tower Alternative Visual Simulation ..................................................... 537 Figure V-7B Tower Alternative Visual Simulation ..................................................... 538 Figure V-7C Tower Alternative Visual Simulation ..................................................... 539 Figure V-7D Tower Alternative Visual Simulation ..................................................... 540 Figure V-7E Tower Alternative Visual Simulation ..................................................... 541 Figure V-7F Tower Alternative Visual Simulation ..................................................... 542 Figure V-8A Tower Alternative Shadow Patterns ...................................................... 543 Figure V-8B Tower Alternative Shadow Patterns ...................................................... 544 Figure V-8C Tower Alternative Shadow Patterns ...................................................... 545 Figure V-8D Tower Alternative Shadow Patterns ...................................................... 546 Figure V-8E Tower Alternative Shadow Patterns ...................................................... 547 Figure V-8F Tower Alternative Shadow Patterns ...................................................... 548 Figure V-9A Increased Commercial Alternative Visual Simulation............................. 549 Figure V-9B Increased Commercial Alternative Visual Simulation............................. 550 Figure V-9C Increased Commercial Alternative Visual Simulation............................. 551 Figure V-9D Increased Commercial Alternative Visual Simulation............................. 552 Figure V-9E Increased Commercial Alternative Visual Simulation............................. 553 Figure V-9F Increased Commercial Alternative Visual Simulation............................. 554

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 T A B L E O F C O N T E N T S

    vi N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008)

    List of Tables

    Table II-1 Summary of Impacts, Conditions of Approval (COA) and Mitigation Measures (MM).......................................................................................11

    Table II-2 Recommendations..................................................................................45 Table III-1 Project Site Parcels and BART Plaza.........................................................50 Table III-2 Summary of Proposed Development .......................................................63 Table III-3 Phasing Schedule ...................................................................................68 Table III-4 Required Permits and Approvals.............................................................73 Table IV.B-1 Relationship of Project to Relevant Plans and Policies ...........................108 Table IV.C-1 AC Transit Service Summary.................................................................135 Table IV.C-2 AC Transit Loads, Boardings and Alightings (Average Weekday)............136 Table IV.C-3 MacArthur BART Station Train Schedule................................................142 Table IV.C-4 Peak Hour Load Factors by Line at MacArthur BART Station...................142 Table IV.C-6 MacArthur BART Station and Systemwide All Day Access Mode

    Shares..................................................................................................143 Table IV.C-5 MacArthur BART Station Fare Gate Queues (AM and PM Peak Periods) ...143 Table IV.C-7 Level of Service Criteria for Unsignalized Intersections .........................160 Table IV.C-8 Level of Service Criteria for Signalized Intersections .............................161 Table IV.C-9 Existing Conditions Intersection Level of Service Summary ...................162 Table IV.C-10 Vehicle Collision Data Summary by Type (2000-2006) ..........................165 Table IV.C-11 Pedestrian/Bicycle Collision Data Summary by Type (2000-2006)..........165 Table IV.C-12 Project Vehicle Trip Generation ............................................................172 Table IV.C-13 Existing Plus Project Intersection Level of Service Summary ..................186 Table IV.C-14 Cumulative Year 2015 Baseline Intersection Level of Service

    Summary..............................................................................................188 Table IV.C-15 Cumulative Year 2015 Baseline Plus Project Mitigated Intersection

    Level of Service Summary .....................................................................193 Table IV.C-16 Cumulative Year 2030 Baseline Intersection Level of Service

    Summary..............................................................................................200 Table IV.C-17 Cumulative Year 2030 Baseline Plus Project Mitigated Intersection

    Level of Service Summary .....................................................................202 Table IV.C-18 Project Effects on AC Transit Ridership................................................214 Table IV.C-19 Project Effects on BART Ridership.........................................................216 Table IV.C-20 AC Transit Average Weekday Loads (With and Without Project) .............217 Table IV.C-21 AC Transit Travel Times (With and Without Project)...............................218 Table IV.C-22 BART Average Weekday Loads (With and Without Project) .....................219 Table IV.C-23 Estimated Peak Parking Demand...........................................................223 Table IV.D-1 Federal and State Ambient Air Quality Standards ..................................228 Table IV.D-2 Health Effects of Air Pollutants .............................................................230 Table IV.D-3 San Francisco Bay Area Attainment Status.............................................234 Table IV.D-4 Ambient Air Quality Monitoring Data ....................................................239 Table IV.D-5 Project Regional Emissions in Pounds Per Day ......................................245

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R T A B L E O F C O N T E N T S

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008) vii

    Table IV.D-6 Construction Emission Estimates ......................................................... 247 Table IV.D-7 CO Concentrations for Existing and Existing Plus Project Conditions.... 249 Table IV.D-8 CO Concentrations for Cumulative Year 2015 Baseline With and

    Without the Project .............................................................................. 250 Table IV.D-9 CO Concentrations for Cumulative Year Baseline 2030 With and

    Without the Project .............................................................................. 252 Table IV.D-10 Oakland Community-wide GHG Emissions Summary – 2005

    (tons/year) .......................................................................................... 258 Table IV.D-11 Estimated CO2e Emissions from the Proposed Project (Tons/Year) ....... 276 Table IV.E-1 Definitions of Acoustical Terms ........................................................... 282 Table IV.E-2 Typical A-Weighted Sound Levels ......................................................... 284 Table IV.E-3 Summary of EPA Noise Levels .............................................................. 285 Table IV.E-5 Construction Vibration Damage Criteria............................................... 286 Table IV.E-4 Summary of Human Effects in Areas Exposed to 55 dBA Ldn................ 286 Table IV.E-6 Noise Land Use Compatibility Matrix.................................................... 288 Table IV.E-7 City of Oakland Construction Noise Standards at Receiving Property

    Line, dBA............................................................................................. 289 Table IV.E-8 City of Oakland Operational Noise Standards at Receiving Property

    Line, dBA............................................................................................. 290 Table IV.E-9 Short-Term Ambient Noise Monitoring Results, dBA ............................. 294 Table IV.E-10 Meteorological Conditions During Ambient Noise Monitoring............... 294 Table IV.E-11 Existing Traffic Noise Levels, dBA ........................................................ 296 Table IV.E-12 Typical Construction Equipment Maximum Noise Levels, Lmax ............ 299 Table IV.E-13 Existing with Project Traffic Noise Levels, dBA ..................................... 302 Table IV.E-14 Cumulative 2015 Baselinea Without Project Traffic Noise Levels, dBA.... 302 Table IV.E-15 Cumulative 2015 Baseline Plus Project Traffic Noise Levels, dBA .......... 303 Table IV.E-16 Cumulative 2030 Baseline Without Project Traffic Noise Levels, dBA..... 303 Table IV.E-17 Cumulative 2030 Baseline Plus Project Traffic Noise Levels, dBA .......... 304 Table IV.G-1 Modified Mercalli Scale ........................................................................ 334 Table IV.I-1 Neighborhood Schools......................................................................... 368 Table IV.J-1 Projected Wastewater Generation......................................................... 391 Table IV.K-1 Oakland Cultural Heritage Survey Significance Ratings ......................... 400 Table IV.K-2 Property Ratings/Historical Resource Status for Buildings Within

    Project Site .......................................................................................... 410 Table IV.K-3 Property Ratings/Historical Resource Status for Buildings Adjacent to

    Project................................................................................................. 412 Table V-1 Project and Alternatives....................................................................... 457 Table V-2 No Project/No Build Alternative Scenario Compared to the Proposed

    Project................................................................................................. 463 Table V-3 Existing Zoning Alternative Scenario Compared to the Proposed

    Project................................................................................................. 466 Table V-4 Existing Zoning Alternative Scenario Trip Generation ........................... 470

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 T A B L E O F C O N T E N T S

    viii N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\00_TOC-LATEST.doc (1/30/2008)

    Table V-5 Mitigated Reduced Building/Site Alternative Scenario Compared to the Proposed Project ............................................................................475

    Table V-6 Mitigated Reduced Building/Site Alternative Trip Generation.................479 Table V-7 Full BART Replacement Parking Alternative Scenario Compared to

    the Proposed Project ............................................................................487 Table V-8 Tower Alternative Scenario Compared to the Proposed Project..............492 Table V-9 Tower Alternative Vehicle Trip Generation ............................................496 Table V-10 Existing Plus Tower Alternative Intersection Level of Service

    Summary..............................................................................................497 Table V-11 Cumulative Year 2015 Baseline Intersection Level of Service

    Summary (Tower Alternative)................................................................499 Table V-12 Cumulative Year 2030 Baseline Intersection Level of Service

    Summary (Tower Alternative)................................................................501 Table V-13 CO Concentrations for Tower Alternative Conditions ............................503 Table V-14 Tower Alternative Regional Emissions in Pounds Per Day ......................504 Table V-15 Existing with Tower Alternative Traffic Noise Levels, dBA......................504 Table V-16 Cumulative Year 2015 Baseline with Tower Alternative Traffic Noise

    Levels, dBA ..........................................................................................505 Table V-17 Cumulative Year 2030 Baseline with Tower Alternative Traffic Noise

    Levels, dBA ..........................................................................................505 Table V-18 Increased Commercial Alternative Scenario Compared to the

    Proposed Project ..................................................................................509 Table V-19 Increased Commercial Alternative Vehicle Trip Generation....................513 Table V-20 Existing Plus Increased Commercial Alternative Intersection Level of

    Service Summary..................................................................................514 Table V-21 Cumulative Year 2015 Baseline Intersection Level of Service

    Summary (Increased Commercial Alternative) .......................................516 Table V-22 Cumulative Year 2030 Baseline Intersection Level of Service

    Summary (Increased Commercial Alternative) .......................................518 Table V-23 CO Concentrations for Increase Commercial Alternative Conditions......520 Table V-24 Increased Commercial Alternative Regional Emissions in Pounds Per

    Day ......................................................................................................521 Table V-25 Existing with Increased Commercial Alternative Traffic Noise Levels,

    dBA......................................................................................................521 Table V-26 Cumulative Year 2015 Baseline Plus Increased Commercial

    Alternative Traffic Noise Levels, dBA.....................................................522 Table V-27 Cumulative Year 2030 Baseline with Increased Commercial

    Alternative Traffic Noise Levels, dBA.....................................................523 Table V-28 Increased Commercial Alternative Projected Wastewater Generation .....524 Table V-29 Summary of Project and Alternative Impacts .........................................527

  • N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\1-Introduction.doc (1/30/2008) 1

    I. INTRODUCTION

    A. PURPOSE OF EIR In compliance with the California Environmental Quality Act (CEQA), this Draft Environmental Impact Report (EIR) describes the environmental consequences of the proposed MacArthur Transit Village Project (project). This EIR is designed to inform City staff, the Planning Commission, City Council, Redevelopment Agency, San Francisco Bay Area Rapid Transit District (BART), other responsible and interested agencies, and the general public of: (1) the proposed project and the potential environmental consequences of the project, (2) mitigation measures recommended to lessen or avoid significant adverse impacts, and (3) a reasonable range of feasible alternatives to the project. The information contained in the EIR will be reviewed and considered by public agencies prior to making a decision to approve, reject, or modify the proposed project. The City of Oakland (City) is the lead agency for environmental review of the proposed project, and BART is a Responsible Agency.

    B. PROPOSED PROJECT The 8.2-acre project site is located in North Oakland, within the block bound by 40th Street, Telegraph Avenue, West MacArthur Boulevard, and State Route 24, as shown in Figure I-1. The project site includes the BART parking lot, the BART plaza, Frontage Road between West MacArthur Boulevard and 40th Street, and seven privately owned parcels. The MacArthur Transit Village Project seeks to redevelop and revitalize an underutilized site in Oakland to create a vibrant transit village that provides pedestrian-oriented, mixed-use development (residential, commercial and community services) that enhances the character of the neighborhood and improves access to (for all travel modes) and ridership of BART. The project would include five buildings with up to 675 units of high-density multi-family housing, up to 44,000 square feet of neighborhood-serving commercial, and 5,000 square feet of community or childcare facility space. Up to 113 units, approximately 17 percent of the units (20 percent of total market-rate units), would be below market-rate, with the remainder of the units being market-rate residential units. The project includes approximately 700 residential, commercial and community use parking spaces and 300 BART parking spaces. The proposed project also includes several public infrastructure upgrades, including two new streets in the project site, improvements to the existing access road that connects 40th

  • Emeryville

    Berkeley

    W. MACARTHUR BLVD.

    HO

    LLIS

    ST.

    32ND ST.

    HO

    RTO

    N S

    T.

    CH

    RIS

    TIE

    AVE.

    SHEL

    LMO

    UN

    DAV

    E.

    WES

    T ST

    .

    MACA THUR

    WES

    T ST

    .TT

    PROJECTLOCATION

    FIGURE I-1

    SOURCE: CALIFORNIA STATE AUTOMOBILE ASSOCIATION, 2000.

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\Figures (01/08)

    MacArthur Transit Village Project EIRProject Location and

    Regional Vicinity Map

    FIGURE I-1

    Legend

    Project Site

    feet

    40000 2000 Cumulative Project Study Area for Select Topics(Land Use, Transportation, Operational Noise and Aesthetics)

    2

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R I . I N T R O D U C T I O N

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\1-Introduction.doc (1/30/2008) 3

    Street with MacArthur Boulevard, the renovation of the existing BART entry plaza, inter-modal improvements, a new intermodal area, and a new public plaza adjacent to the commercial space.

    C. EIR SCOPE The City of Oakland circulated two Notices of Preparation (NOP), which stated that all environmental topics identified in Appendix G of the CEQA Guidelines would be evaluated in the EIR. The first NOP was published on February 15, 2006, and the public comment period for the scope of the EIR lasted from February 15, 2006 to March 16, 2006. Due to changes in the project description, a second NOP was circulated on June 13, 2007. The public comment period lasted from June 13, 2007 to July 13, 2007. Both NOPs were sent to property owners within 500 feet of the project site. The NOPs were also sent to responsible and trustee agencies, organizations, and interested individuals. Additionally, the NOPs were sent to the State Clearinghouse. Two scoping sessions were held for the project. The first was a public scoping session for public agencies on February 28, 2006. Additionally, a scoping meeting was held in conjunction with a Planning Commission meeting on March 15, 2006. Comments received by the City on the NOP at the agency scoping meeting and at the public scoping meeting were taken into account during the preparation of the EIR. NOP comments were received from public agencies, area property owners and concerned citizens regarding a wide range of issues to be addressed in this EIR. Topic areas that were most widely referenced in the NOP comments letters include transportation, parking, air quality, noise, visual resources, storm drainage and water quality, utilities and infrastructure. Additionally, several comments related to non-CEQA topics (i.e., building design and architecture and crime). The NOPs and written comments received are included in Appendix A. The following environmental topics are addressed in this EIR:

    A. Land Use B. Public Policy C. Transportation, Circulation and Parking D. Air Quality E. Noise and Vibration F. Hydrology and Water Quality G. Geology, Soils and Seismicity H. Public Health and Hazards I. Public Services J. Utilities and Infrastructure K. Cultural and Paleontological Resources L. Aesthetic Resources

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 I . I N T R O D U C T I O N

    4 N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\1-Introduction.doc (1/30/2008)

    Environmental topics not warranting detailed evaluation (agricultural resources, biological resources, mineral resources, and population and housing) are discussed in Chapter VI.D, under Effects Found Not to be Significant.

    D. REPORT ORGANIZATION This EIR is organized into the following chapters:

    Chapter I – Introduction: Discusses the overall EIR purpose; provides a summary of the proposed project; describes the EIR scope; and summarizes the organization of the EIR.

    Chapter II – Summary: Provides a summary of the impacts that would result from implementation of the proposed project, and describes Standard Conditions of Approval and mitigation measures recommended to avoid or reduce significant impacts.

    Chapter III – Project Description: Provides a description of the project objectives, project site, site development history, the proposed development, and required approval process.

    Chapter IV – Setting, Impacts, Standard Conditions of Approval, and Mitigation Measures: Describes the following for each environmental technical topic: existing conditions (setting); Standard Conditions of Approval; significance criteria; potential environmental impacts and their level of significance; Standard Conditions of Approval relied upon to ensure significant impacts would not occur; and mitigation measures recommended when necessary to mitigate identified impacts. Cumulative impacts are also discussed in each technical topic section. Potential adverse impacts are identified by levels of significance, as follows: less-than-significant impact (LTS), significant impact (S), and significant and unavoidable impact (SU). The significance level is identified for each impact before and after implementation of the recommended mitigation measure(s).

    Chapter V – Alternatives: Provides an evaluation of seven alternatives to the proposed project. Three of the alternatives are included to meet the CEQA requirement that require an EIR to describe a range of reasonable alternatives to the project, which would feasibly attain most of the basic objectives of the project, but would avoid or substant-ially lessen any of the significant effects of the project. The CEQA alternatives include the: No Project/No Build Alternative; Existing Zoning Alternative; and Mitigated Reduced Building/Site Alternative. Three additional planning alternatives to the project are also considered: Proposed Project with Full BART Replacement Parking Alternative; Tower Alternative; and Increased Commercial Alternative. These alternatives are evaluated primarily to consider variants to the project that may be desirable to the project developer, the City, BART, and/or members of the community, but might not lessen or avoid any of the significant, adverse environmental effects of the project.

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R I . I N T R O D U C T I O N

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\1-Introduction.doc (1/30/2008) 5

    Chapter VI – CEQA-Required Assessment Conclusions: Provides the required analysis of growth-inducing impacts; significant irreversible changes; effects found not to be significant; and significant unavoidable and cumulative impacts.

    Chapter VII – Report Preparation: Identified preparers of the EIR, references used, and the persons and organizations contacted.

    Appendices: The appendices contain the NOPs and written comments submitted on the NOPs; traffic, air quality and noise modeling data and supporting analysis; the Water Supply Assessment; and Land Use Database and Cumulative Growth Scenario.

    All supporting technical documents and the reference documents are available for public review at the City of Oakland Community and Economic Development Agency, Planning Division, under case number ER06004. The Draft EIR is available for public review for the period identified in the Notice of Availability attached to the front of this document. During this time, written comments on the Draft EIR may be submitted to the City of Oakland Community & Economic Development Agency, Planning Division at the address indicated on the Notice of Availability. Responses to all comments received on the environmental analysis in the Draft EIR during the specified review period will be included in the Response to Comments/Final EIR.

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 I . I N T R O D U C T I O N

    6 N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\1-Introduction.doc (1/30/2008)

  • N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\2-Summary.doc (1/30/2008) 7

    II. SUMMARY

    A. PROJECT UNDER REVIEW This EIR has been prepared to evaluate the potential environmental effects of the MacArthur Transit Village project. The project site includes the BART parking lot, the BART plaza, Frontage Road between West MacArthur Boulevard and 40th Street, and seven privately-owned parcels. The MacArthur Transit Village Project seeks to redevelop and revitalize an underutilized site in Oakland to create a vibrant transit village that provides pedestrian-oriented, mixed-use development (residential, commercial and community services) that enhances the character of the neighborhood and improves access to (for all travel modes) and ridership of BART. The 8.2-acre project site is located in North Oakland, within the block bound by 40th Street, Telegraph Avenue, West MacArthur Boulevard, and State Route 24 (SR-24), as shown in Figure I-1. The project would include five buildings with up to 675 units of high-density multi-family housing, up to 44,000 square feet of neighborhood-serving commercial, and 5,000 square feet of community space or childcare facility space. Approximately 17 percent of the units (20 percent of total market-rate units) would be below market-rate (affordable), with the remainder of the units being market-rate condominiums. The project includes approximately 700 residential, commercial and community use parking spaces and 300 BART patron parking spaces. The proposed project is described in detailed in Chapter III, Project Description.

    B. SUMMARY OF IMPACTS AND MITIGATION MEASURES This summary provides an overview of the analysis contained in Chapter V, Setting, Impacts, Standard Conditions of Approval, and Mitigation Measures. CEQA requires a summary to include discussion of: (1) potential areas of controversy; (2) significant impacts; (3) cumulative impacts; (4) significant irreversible and unavoidable impacts; and (5) alternatives to the proposed project. Each of these topics are summarized below.

    1. Potential Areas of Controversy Letters and verbal comments received on the Notices of Preparation (NOP) (February 15, 2006 and June 13, 2006) raised a number of topics that the commentors wanted addressed in the EIR, including transportation, parking, air quality, noise, visual resources, storm drainage and water quality, utilities and infrastructure impacts that may result from the proposed project. In addition, some of the comments offered in the NOP comment letters addressed the merits of the project itself and not the potential adverse environmental

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 I I . S U M M A R Y

    8 N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\2-Summary.doc (1/30/2008)

    impacts that are the subject of this EIR. Verbal comments offered by those in attendance at the CEQA Scoping Sessions, held on February 28, 2006 and March 15, 2006, included many of the comments offered in writing as comments on the NOP. Copies of the NOPs and written comment letters are included in Appendix A.

    2. Significant Impacts Under CEQA, a significant impact on the environment is defined as “…a substantial, or potentially substantial, adverse change in any of the physical conditions within the area affected by the project including land, air, water, minerals, flora, fauna, ambient noise, and objects of historic or aesthetic significance.”1 Implementation of the proposed project has the potential to result in adverse environmental impacts related to transportation. Transportation impacts would be significant without the implementation of Standard Conditions of Approval and mitigation measures, but, with the exception of two intersections (#3 and #22), would be reduced to a less-than-significant level if the Standard Conditions of Approval and mitigation measures noted in this report are implemented. Impacts are anticipated to be less than significant for all other environmental topics.

    3. Alternatives to the Proposed Project Chapter V includes the analysis of three alternatives to the proposed project to meet the requirements of CEQA to analyze a range of reasonable alternatives to the project that would feasibly attain most of the project’s basic objectives and avoid or substantially lessen any of the significant effects of the project. The three project CEQA alternatives analyzed in Chapter V include:

    The No Project/No Build Alternative, which assumes the continuation of existing conditions within the project site.

    The Existing Zoning Alternative, which assumes development in accordance with the existing zoning (C-28 and R-70) and General Plan land use designation (Neighborhood Center Mixed-Use). The Existing Zoning Alternative would include demolition of all existing buildings and the BART parking lot and remediation of hazardous materials on-site. Development under this alternative would include 530 dwelling units, 44,000 square feet of commercial space (this may include a community space) and approximately 1,015 parking spaces (including 300 exclusive BART parking spaces). Development would consist of five new buildings (including a parking garage). Structures within the existing C-28 zone (properties adjacent to MacArthur Boulevard and Telegraph Avenue) would have a maximum height of 55 feet and structures within the R-70 zone (properties currently developed with the BART parking lot) would have a maximum height of 40 feet. This alternative would include new access/circulation improvements and BART plaza improvements.

    114 California Code Regs. 15382; Public Resources Code 21068.

  • J A N U A R Y 2 0 0 8 M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R I . S U M M A R Y

    N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\2-Summary.doc (1/30/2008) 9

    The Mitigated Reduced Building/Site Alternative, which assumes development would only occur on the BART parking lot. The Mitigated Reduced Building/Site Alternative would include demolition of the BART parking lot, but all other buildings and uses would remain. Development under this alternative would include four five- to six-story structures with approximately 200 dwelling units, 20,000 square feet of commercial space and 750 parking spaces (including 300 exclusive BART parking spaces).

    Three additional planning alternatives to the project are also considered in this EIR. These alternatives may not lessen or avoid any of the significant, adverse environmental effects of the project as they are evaluated primarily to consider variants to the project that may be desirable to the project developer, the City, BART, and/or members of the community. The planning/project merit alternatives analyzed in Chapter V include:

    The Proposed Project with Full BART Replacement Parking Alternative, which assumes the proposed project is developed with a 600-space parking garage for BART patrons (as opposed to a 300-space parking garage for BART patrons). Parking spaces under the Proposed Project with Full BART Replacement Parking would be approximately 1,300 with 600 exclusive BART parking spaces. All other project components remain the same (up to 675 residential units, 44,000 square feet of commercial area and 5,000 square feet of community space or childcare facility). Site improvements and circulation pattern are the same the proposed project.

    The Tower Alternative, which assumes a 23-story tower building would be constructed at Building D. Under the proposed project, Building D is a four-story residential building. In the Tower Alternative, residential units would increase to 868 units with 720 market-rate and 148 affordable units (as opposed to 675 residential units with 562 market-rate and 113 affordable units) and parking would increase to approximately 1,210 parking spaces, including 300 exclusive BART parking spaces. All other project components remain relatively similar with 34,000 square feet of commercial area and 7,500 square feet of community space or childcare facility. Site improvements and circulation pattern are the same the proposed project.

    The Increased Commercial Alternative, which assumes 172,000 square feet of commercial office development, would occur at Building A. Under the proposed project, Building A is a five- to six-story mixed-use building with 230 market-rate units above 26,000 square feet of ground floor commercial and live/work flex space. Under the Commercial Alternative, 172,000 square feet of commercial office space is introduced onto the site with 475 residential units (395 market-rate and 80 affordable units), 27,000 square feet of commercial commercial area and 5,000 of community space or childcare facility. Site improvements and circulation pattern are the same the proposed project.

  • M A C A R T H U R T R A N S I T V I L L A G E P R O J E C T E I R J A N U A R Y 2 0 0 8 I I . S U M M A R Y

    10 N:\2007\1407011 MacArthur BART Transit Village EIR\Documents\Public Review Draft\2-Summary.doc (1/30/2008)

    4. Significant Unavoidable and Cumulative Impacts As discussed at the end of each topical section in Chapter IV, Setting, Impacts and Mitigation Measures, the project would not significantly contribute to any significant cumulative impacts for any topics other than transportation. The project would significantly contribute to cumulative impacts at the following intersections:

    Telegraph Avenue/52nd Street and Claremont Avenue intersection (#2)

    Telegraph Avenue/51st Street intersection (#3)

    West Street/40th Street intersection (#8)

    the Telegraph Avenue/40th Street intersection (#13)

    Market Street/MacArthur Boulevard intersection (#16)

    Telegraph Avenue/MacArthur Boulevard intersection (#20)

    Broadway/MacArthur Boulevard intersection (#22) The project’s contribution to the cumulative impact at each of the above intersections can be mitigated to a less-than-significant level except at intersection #3 and intersection #22. No other significant and unavoidable impacts would result.

    C. SUMMARY TABLE Information in Table II-1, Summary of Impacts, City Standard Conditions of Approval and Mitigation Measures has been organized to correspond with environmental issues discussed in Chapter IV. The table is arranged in four columns: (1) impacts; (2) level of significance prior to mitigation (when mitigation is necessary); (3) required Standard Conditions of Approval and/or recommended mitigation measures; and (4) level of significance after implementation of Standard Conditions of Approval and/or mitigation. Levels of significance are categorized as follows: LTS = Less Than Significant; S = Significant; and SU = Significant and Unavoidable. A series of mitigation measures is noted where more than one mitigation measure is required to achieve a less-than-significant impact, and alternative mitigation measures are identified when available. For a complete description of potential impacts and recommended mitigation measures, please refer to the specific discussions in Chapter IV. Table II-2 lists recommended improvements identified throughout the document to address project issues not considered significant environmental impacts under CEQA. The recommendations should be considered by the City during the review of the project’s merits, independent of the CEQA impacts and mitigation measures. The failure to adopt such recommendations, however, would not result in any new impacts or the increase in severity of previously identified impacts.

  • JA

    NU

    AR

    Y 2

    00

    8

    MA

    CA

    RT

    HU

    R T

    RA

    NS

    IT V

    ILL

    AG

    E P

    RO

    JE

    CT

    EIR

    II.

    SU

    MM

    AR

    Y

    LTS

    = L

    ess

    Th

    an S

    ign

    ific

    ant

    , SU

    = S

    ignif

    ican

    t an

    d U

    nav

    oid

    able

    , S

    = S

    ignif

    ican

    t

    N:\

    20

    07

    \14

    07

    01

    1 M

    acA

    rthur

    BAR

    T T

    ransi

    t V

    illag

    e EI

    R\D

    ocu

    men

    ts\P

    ublic

    Rev

    iew

    Dra

    ft\2

    -Su

    mm

    ary.

    doc

    (1/3

    0/2

    008

    )

    11

    Tab

    le I

    I-1

    Su

    mm

    ary

    of

    Imp

    act

    s, C

    on

    dit

    ion

    s o

    f A

    pp

    roval

    (CO

    A)

    an

    d M

    itig

    ati

    on

    Measu

    res (

    MM

    )

    Imp

    act

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    ho

    ut

    M

    M

    Sta

    nd

    ard

    CO

    A/M

    M

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    h

    MM

    /CO

    A

    A. L

    AN

    D U

    SE

    No

    signif

    icant

    land u

    se im

    pact

    s w

    ould

    occ

    ur.

    B. P

    UBLIC

    PO

    LIC

    Y

    No

    signif

    icant

    public

    pol

    icy

    impact

    s w

    ould

    occ

    ur.

    C. T

    RA

    NSPO

    RT

    AT

    ION, C

    IRC

    ULA

    TIO

    N A

    ND

    PA

    RK

    ING

    No

    signif

    icant

    const

    ruct

    ion p

    erio

    d t

    ransp

    orta

    tion

    -rel

    ate

    d im

    pact

    s w

    ould

    occ

    ur

    wit

    h im

    ple

    men

    tati

    on o

    f th

    e C

    ity

    Standard

    Con

    dit

    ions

    of A

    ppro

    val lis

    ted in t

    his

    table

    .

    CO

    A T

    RA

    NS-1

    : Pri

    or

    to t

    he

    issu

    ance

    of

    each

    build

    ing p

    erm

    it, th

    e pro

    ject

    spon

    sor

    and c

    onst

    ruct

    ion

    contr

    acto

    r sh

    all m

    eet

    wit

    h t

    he

    Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n

    and o

    ther

    appro

    pri

    ate

    Cit

    y of

    Oak

    lan

    d a

    gen

    cies

    to d

    eter

    min

    e tr

    affi

    c m

    anag

    emen

    t st

    rate

    gie

    s to

    red

    uce

    , to

    the

    max

    imum

    exte

    nt

    feas

    ible

    , tr

    affi

    c co

    nges

    tion

    an

    d t

    he

    effe

    cts

    of

    par

    king d

    eman

    d b

    y co

    nst

    ruct

    ion

    work

    ers

    duri

    ng c

    onst

    ruct

    ion

    of

    this

    pro

    ject

    an

    d o

    ther

    nea

    rby

    pro

    ject

    s th

    at c

    ould

    be

    sim

    ult

    aneo

    usl

    y un

    der

    co

    nst

    ruct

    ion

    . The

    pro

    ject

    sponso

    r sh

    all dev

    elop a

    const

    ruct

    ion

    man

    agem

    ent

    pla

    n

    for

    revi

    ew a

    nd a

    ppro

    val by

    the

    Cit

    y Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n.

    Th

    e pla

    n

    shal

    l al

    so b

    e su

    bm

    itte

    d t

    o B

    ART a

    nd A

    C T

    ran

    sit

    for

    revi

    ew a

    nd c

    om

    men

    t. T

    he

    pla

    n s

    hal

    l in

    clude

    at lea

    st t

    he

    follo

    win

    g ite

    ms

    and

    req

    uir

    emen

    ts:

    A

    set

    of

    com

    pre

    hen

    sive

    tra

    ffic

    contr

    ol m

    easu

    res,

    in

    cludin

    g s

    ched

    ulin

    g o

    f m

    ajor

    truck

    tri

    ps

    and d

    eliv

    erie

    s to

    avo

    id p

    eak

    traf

    fic

    hours

    , det

    our

    sign

    s if

    re

    quir

    ed, la

    ne

    closu

    re p

    roce

    dure

    s, s

    ign

    s, c

    ones

    for

    dri

    vers

    , an

    d d

    esig

    nat

    ed

    con

    stru

    ctio

    n a

    cces

    s ro

    ute

    s.

    N

    oti

    fica

    tion

    pro

    cedure

    s fo

    r ad

    jace

    nt

    pro

    per

    ty o

    wn

    ers

    and p

    ublic

    saf

    ety

    per

    sonnel

    reg

    ardin

    g w

    hen

    maj

    or

    del

    iver

    ies,

    det

    ours

    , an

    d lan

    e cl

    osu

    res

    will

    occ

    ur.

    Lo

    cati

    on

    of

    const

    ruct

    ion

    sta

    gin

    g a

    reas

    for

    mat

    eria

    ls, eq

    uip

    men

    t, a

    nd v

    ehic

    les

    (must

    be

    loca

    ted o

    n t

    he

    pro

    ject

    sit

    e).

    Id

    enti

    fica

    tion o

    f hau

    l ro

    ute

    s fo

    r m

    ove

    men

    t of

    const

    ruct

    ion

    veh

    icle

    s th

    at

    would

    min

    imiz

    e im

    pac

    ts o

    n v

    ehic

    ula

    r an

    d p

    edes

    tria

    n t

    raff

    ic, ci

    rcula

    tion

    an

    d

    safe

    ty; an

    d p

    rovi

    sion

    for

    mon

    itori

    ng

    surf

    ace

    stre

    ets

    use

    d f

    or

    hau

    l ro

    ute

    s so

    th

    at a

    ny

    dam

    age

    and d

    ebri

    s at

    trib

    uta

    ble

    to t

    he

    hau

    l tr

    uck

    s ca

    n b

    e id

    enti

    fied

    an

    d c

    orr

    ecte

    d b

    y th

    e pro

    ject

    applic

    ant.

    LTS

  • MA

    CA

    RT

    HU

    R T

    RA

    NS

    IT V

    ILL

    AG

    E P

    RO

    JE

    CT

    EIR

    J

    AN

    UA

    RY

    20

    08

    II

    . S

    UM

    MA

    RY

    LTS

    = L

    ess

    Th

    an S

    ign

    ific

    ant

    , SU

    = S

    ignif

    ican

    t an

    d U

    nav

    oid

    able

    , S

    = S

    ignif

    ican

    t

    12

    N

    :\20

    07

    \14

    07

    01

    1 M

    acA

    rthur

    BAR

    T T

    ransi

    t V

    illag

    e EI

    R\D

    ocu

    men

    ts\P

    ublic

    Rev

    iew

    Dra

    ft\2

    -Su

    mm

    ary.

    doc

    (1/3

    0/2

    008

    )

    Tab

    le I

    I-1

    Su

    mm

    ary

    of

    Imp

    act

    s, C

    on

    dit

    ion

    s o

    f A

    pp

    roval

    (CO

    A)

    an

    d M

    itig

    ati

    on

    Measu

    res (

    MM

    )

    Imp

    act

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    ho

    ut

    M

    M

    Stan

    dard

    CO

    A/M

    M

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    h

    MM

    /CO

    A

    CO

    A T

    RA

    NS-

    1 c

    onti

    nued

    Tem

    pora

    ry c

    onst

    ruct

    ion

    fen

    ces

    to c

    onta

    in d

    ebri

    s an

    d m

    ater

    ial an

    d t

    o s

    ecure

    th

    e si

    te.

    Pr

    ovi

    sion

    s fo

    r re

    mova

    l of

    tras

    h g

    ener

    ated

    by

    pro

    ject

    con

    stru

    ctio

    n a

    ctiv

    ity.

    A

    pro

    cess

    for

    resp

    on

    din

    g t

    o,

    and

    tra

    ckin

    g,

    com

    pla

    ints

    per

    tain

    ing t

    o

    const

    ruct

    ion

    act

    ivit

    y, in

    cludin

    g iden

    tifi

    cati

    on

    of

    an o

    n-s

    ite

    com

    pla

    int

    man

    ager

    .

    Su

    bje

    ct t

    o C

    ity

    revi

    ew a

    nd a

    ppro

    val, p

    rior

    to s

    tart

    of

    const

    ruct

    ion

    , a

    const

    ruct

    ion

    work

    er t

    ran

    sport

    atio

    n d

    eman

    d m

    anag

    emen

    t (T

    DM

    ) pro

    gra

    m

    shal

    l be

    imple

    men

    ted t

    o e

    nco

    ura

    ge

    const

    ruct

    ion

    work

    ers

    to c

    arpool or

    use

    al

    tern

    ativ

    e tr

    ansp

    ort

    atio

    n m

    odes

    in

    ord

    er t

    o r

    educe

    the

    ove

    rall

    num

    ber

    of

    vehic

    le t

    rips

    asso

    ciat

    ed w

    ith c

    onst

    ruct

    ion

    work

    ers.

    Id

    enti

    fica

    tion a

    nd m

    ainte

    nan

    ce o

    f ve

    hic

    ula

    r, b

    icyc

    le, ped

    estr

    ian

    and t

    ransi

    t ac

    cess

    to a

    nd f

    rom

    the

    BAR

    T S

    tati

    on.

    It is

    anti

    cipat

    ed t

    hat

    this

    Const

    ruct

    ion

    Tra

    ffic

    Man

    agem

    ent

    Plan

    would

    be

    dev

    eloped

    in

    the

    conte

    xt

    of

    a la

    rger

    Const

    ruct

    ion

    Man

    agem

    ent

    Plan

    , w

    hic

    h w

    ould

    ad

    dre

    ss o

    ther

    iss

    ues

    such

    as

    hours

    of

    con

    stru

    ctio

    n o

    n-s

    ite,

    lim

    itat

    ion

    s on

    nois

    e an

    d d

    ust

    em

    issi

    on

    s, a

    nd o

    ther

    applic

    able

    ite

    ms.

    TRA

    NS-

    1:

    Th

    e ad

    dit

    ion

    of

    pro

    ject

    tra

    ffic

    would

    ca

    use

    a s

    ignif

    ican

    t im

    pac

    t at

    the

    Tel

    egra

    ph

    A

    ven

    ue/

    51

    st S

    tree

    t in

    ters

    ecti

    on (

    #3

    ) un

    der

    C

    um

    ula

    tive

    Yea

    r 2

    01

    5 B

    asel

    ine

    Plus

    Proje

    ct

    con

    dit

    ions.

    Th

    e pro

    ject

    would

    contr

    ibute

    to L

    OS

    E oper

    atio

    ns

    duri

    ng

    the

    PM p

    eak

    hour

    and in

    crea

    se

    crit

    ical

    move

    men

    t av

    erag

    e del

    ay b

    y m

    ore

    than

    6

    seco

    nds.

    S TRA

    NS-

    1:

    Opti

    miz

    e si

    gn

    al t

    imin

    g (i.e.

    , ad

    just

    the

    allo

    cati

    on

    of

    gre

    en t

    ime

    for

    each

    inte

    rsec

    tion

    appro

    ach

    ) at

    the

    Tel

    egra

    ph A

    ven

    ue/

    51

    st S

    tree

    t in

    ters

    ecti

    on a

    nd

    coord

    inat

    e si

    gnal

    ph

    asin

    g a

    nd t

    imin

    g w

    ith t

    he

    adja

    cent

    Tel

    egra

    ph A

    ven

    ue/

    52

    nd

    Stre

    et a

    nd C

    lare

    mont

    Ave

    nue

    inte

    rsec

    tion

    an

    d o

    ther

    inte

    rsec

    tion

    s in

    the

    sam

    e co

    ord

    inat

    ion

    gro

    up

    . To im

    ple

    men

    t th

    is m

    easu

    re, th

    e p

    roje

    ct s

    ponso

    r sh

    all

    sub

    mit

    a s

    ign

    al o

    pti

    miz

    atio

    n p

    lan

    to C

    ity

    of

    Oak

    land’s

    Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n f

    or

    revi

    ew a

    nd a

    ppro

    val. T

    he

    pla

    n s

    hal

    l co

    nsi

    st o

    f si

    gnal

    tim

    ing

    par

    amet

    ers

    for

    the

    signal

    s in

    the

    coord

    inat

    ion g

    roup.

    Th

    e pro

    ject

    spon

    sor

    shal

    l fu

    nd

    the

    cost

    of

    pre

    par

    ing a

    nd im

    ple

    men

    ting t

    he

    pla

    n.

    LTS

  • JA

    NU

    AR

    Y 2

    00

    8

    MA

    CA

    RT

    HU

    R T

    RA

    NS

    IT V

    ILL

    AG

    E P

    RO

    JE

    CT

    EIR

    II.

    SU

    MM

    AR

    Y

    LTS

    = L

    ess

    Th

    an S

    ign

    ific

    ant

    , SU

    = S

    ignif

    ican

    t an

    d U

    nav

    oid

    able

    , S

    = S

    ignif

    ican

    t

    N:\

    20

    07

    \14

    07

    01

    1 M

    acA

    rthur

    BAR

    T T

    ransi

    t V

    illag

    e EI

    R\D

    ocu

    men

    ts\P

    ublic

    Rev

    iew

    Dra

    ft\2

    -Su

    mm

    ary.

    doc

    (1/3

    0/2

    008

    )

    13

    Tab

    le I

    I-1

    Su

    mm

    ary

    of

    Imp

    act

    s, C

    on

    dit

    ion

    s o

    f A

    pp

    roval

    (CO

    A)

    an

    d M

    itig

    ati

    on

    Measu

    res (

    MM

    )

    Imp

    act

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    ho

    ut

    M

    M

    Stan

    dard

    CO

    A/M

    M

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    h

    MM

    /CO

    A

    TRA

    NS-

    1 c

    onti

    nued

    As

    show

    n in

    Tab

    le IV

    .C-1

    5, af

    ter

    imple

    men

    tati

    on

    of

    this

    mea

    sure

    , th

    e in

    ters

    ecti

    on

    would

    conti

    nue

    to o

    per

    ate

    at L

    OS

    E duri

    ng t

    he

    PM p

    eak

    hour.

    H

    ow

    ever

    , th

    e in

    crea

    se in

    ave

    rage

    del

    ay f

    or

    the

    crit

    ical

    move

    men

    ts w

    ould

    be

    reduce

    d t

    o les

    s th

    an t

    he

    6-s

    econ

    d t

    hre

    shold

    of

    sign

    ific

    ance

    . N

    o s

    ign

    ific

    ant

    effe

    cts

    would

    res

    ult

    fro

    m im

    ple

    men

    tati

    on

    of

    this

    mea

    sure

    .

    TRA

    NS-

    2:

    Th

    e ad

    dit

    ion

    of

    pro

    ject

    tra

    ffic

    would

    ca

    use

    a s

    ignif

    ican

    t im

    pac

    t at

    the

    Mar

    ket

    Stre

    et/M

    acA

    rthur

    Boule

    vard

    inte

    rsec

    tion (#1

    6)

    un

    der

    Cum

    ula

    tive

    Yea

    r 2

    01

    5 B

    asel

    ine

    Plus

    Proje

    ct

    con

    dit

    ions.

    Th

    e pro

    ject

    would

    deg

    rade

    inte

    rsec

    tion

    oper

    atio

    ns

    from

    LO

    S D

    to L

    OS

    E d

    uri

    ng

    the

    PM p

    eak

    hour.

    S TRA

    NS-

    2: C

    han

    ge

    the

    sign

    al c

    ycle

    len

    gth

    to 9

    0 s

    econds

    and o

    pti

    miz

    e si

    gnal

    ti

    min

    g (i.e.

    , ad

    just

    the

    allo

    cati

    on

    of

    gre

    en t

    ime

    for

    each

    inte

    rsec

    tion

    appro

    ach

    ) at

    th

    e M

    arke

    t St

    reet

    /Mac

    Art

    hur

    Boule

    vard

    inte

    rsec

    tion

    . To im

    ple

    men

    t th

    is m

    easu

    re,

    the

    pro

    ject

    spon

    sor

    shal

    l su

    bm

    it a

    sig

    nal

    opti

    miz

    atio

    n p

    lan

    to C

    ity

    of

    Oak

    lan

    d’s

    Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n f

    or

    revi

    ew a

    nd a

    ppro

    val. T

    he

    pla

    n s

    hal

    l co

    nsi

    st

    of

    sign

    al t

    imin

    g p

    aram

    eter

    s fo

    r th

    e M

    arke

    t St

    reet

    /Mac

    Art

    hur

    Boule

    vard

    in

    ters

    ecti

    on

    . Th

    e pro

    ject

    spon

    sor

    shal

    l fu

    nd t

    he

    cost

    of

    pre

    par

    ing a

    nd

    imp

    lem

    enti

    ng t

    he

    pla

    n.

    As

    show

    n in

    Tab

    le IV

    .C-1

    5, af

    ter

    imple

    men

    tati

    on

    of

    this

    mea

    sure

    , th

    e in

    ters

    ecti

    on

    would

    oper

    ate

    at L

    OS

    C d

    uri

    ng

    both

    AM

    an

    d P

    M p

    eak h

    ours

    . N

    o

    signif

    ican

    t ef

    fect

    s w

    ould

    res

    ult

    fro

    m im

    ple

    men

    tati

    on o

    f th

    is m

    easu

    re.

    LTS

    TRA

    NS-

    3:

    Th

    e ad

    dit

    ion

    of

    pro

    ject

    tra

    ffic

    would

    ca

    use

    a s

    ignif

    ican

    t im

    pac

    t at

    the

    Tel

    egra

    ph

    A

    ven

    ue/

    52

    nd S

    tree

    t an

    d C

    lare

    mont

    Ave

    nue

    inte

    rsec

    tion

    (#

    2)

    un

    der

    Cum

    ula

    tive

    20

    30

    Bas

    elin

    e Pl

    us

    Proje

    ct c

    ond

    itio

    ns.

    Th

    e p

    roje

    ct w

    ould

    co

    ntr

    ibute

    to L

    OS

    F oper

    atio

    ns

    and in

    crea

    se

    inte

    rsec

    tion

    ave

    rag

    e del

    ay b

    y m

    ore

    than

    2

    sec

    on

    ds

    duri

    ng

    the

    AM

    pea

    k h

    our;

    would

    co

    ntr

    ibute

    to L

    OS

    E oper

    atio

    ns

    and

    in

    crea

    se

    crit

    ical

    move

    men

    t av

    erag

    e del

    ay b

    y m

    ore

    than

    6

    sec

    on

    ds

    duri

    ng

    the

    PM p

    eak

    hour.

    S TRA

    NS-

    3:

    Imp

    lem

    ent

    the

    follo

    win

    g m

    easu

    res:

    Pr

    ohib

    it lef

    t-tu

    rns

    from

    nort

    hboun

    d T

    eleg

    raph A

    ven

    ue

    into

    wes

    tboun

    d 5

    2nd

    Stre

    et d

    uri

    ng

    the

    pea

    k co

    mm

    ute

    tim

    es (i.e.

    , 7:0

    0 a

    .m. to

    9:0

    0 a

    .m. an

    d 4

    :00

    p.m

    . to

    6:0

    0 p

    .m.)

    . C

    urr

    entl

    y, a

    sm

    all vo

    lum

    e of

    traf

    fic

    use

    s th

    is m

    ove

    men

    t (a

    bout

    10 p

    eak

    hour

    veh

    icle

    s),

    wh

    ich

    can

    be

    div

    erte

    d t

    o 5

    1st

    Str

    eet.

    Th

    us,

    the

    pea

    k hour

    pro

    hib

    itio

    n o

    n lef

    t-tu

    rns

    would

    not

    resu

    lt in

    exce

    ssiv

    e an

    d

    circ

    uit

    ous

    div

    ersi

    on

    s.

    C

    han

    ge

    signal

    cyc

    le len

    gth

    to 1

    20

    sec

    on

    ds

    and o

    pti

    miz

    ing

    sig

    nal

    tim

    ing

    (i.e.

    , ad

    just

    the

    allo

    cati

    on

    of

    gre

    en t

    ime

    for

    each

    inte

    rsec

    tion

    appro

    ach

    ) at

    the

    Tel

    egra

    ph

    Ave

    nue/

    52

    nd S

    tree

    t an

    d C

    lare

    mont

    Ave

    nue

    inte

    rsec

    tion

    ; co

    ord

    inat

    e si

    gnal

    tim

    ing a

    nd p

    has

    ing

    wit

    h t

    he

    adja

    cent

    Tel

    egra

    ph A

    venue/

    51

    st S

    tree

    t in

    ters

    ecti

    on

    and o

    ther

    inte

    rsec

    tion

    s in

    the

    sam

    e co

    ord

    inat

    ion

    gro

    up.

    LTS

  • MA

    CA

    RT

    HU

    R T

    RA

    NS

    IT V

    ILL

    AG

    E P

    RO

    JE

    CT

    EIR

    J

    AN

    UA

    RY

    20

    08

    II

    . S

    UM

    MA

    RY

    LTS

    = L

    ess

    Th

    an S

    ign

    ific

    ant

    , SU

    = S

    ignif

    ican

    t an

    d U

    nav

    oid

    able

    , S

    = S

    ignif

    ican

    t

    14

    N

    :\20

    07

    \14

    07

    01

    1 M

    acA

    rthur

    BAR

    T T

    ransi

    t V

    illag

    e EI

    R\D

    ocu

    men

    ts\P

    ublic

    Rev

    iew

    Dra

    ft\2

    -Su

    mm

    ary.

    doc

    (1/3

    0/2

    008

    )

    Tab

    le I

    I-1

    Su

    mm

    ary

    of

    Imp

    act

    s, C

    on

    dit

    ion

    s o

    f A

    pp

    roval

    (CO

    A)

    an

    d M

    itig

    ati

    on

    Measu

    res (

    MM

    )

    Imp

    act

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    ho

    ut

    M

    M

    Stan

    dard

    CO

    A/M

    M

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    h

    MM

    /CO

    A

    TRA

    NS-

    3 c

    onti

    nued

    To im

    ple

    men

    t th

    ese

    mea

    sure

    s, t

    he

    pro

    ject

    sp

    on

    sor

    shal

    l su

    bm

    it t

    he

    follo

    win

    g t

    o

    Cit

    y of

    Oak

    lan

    d’s

    Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n f

    or

    revi

    ew a

    nd a

    ppro

    val:

    Si

    gn

    ing

    pla

    ns

    to p

    roh

    ibit

    lef

    t-tu

    rns

    from

    nort

    hbound T

    eleg

    raph A

    ven

    ue

    into

    w

    estb

    oun

    d 5

    2nd S

    tree

    t.

    Si

    gn

    al t

    imin

    g p

    lan

    s fo

    r th

    e si

    gnal

    s in

    the

    coord

    inat

    ion

    gro

    up.

    Th

    e p

    roje

    ct s

    pon

    sor

    shal

    l fu

    nd

    the

    cost

    of

    pre

    par

    ing a

    nd

    im

    ple

    men

    ting t

    hes

    e pla

    ns.

    As

    show

    n in

    Tab

    le IV

    .C-1

    7, af

    ter

    imple

    men

    tati

    on

    of

    this

    mea

    sure

    , th

    e in

    ters

    ecti

    on

    would

    conti

    nue

    to o

    per

    ate

    at L

    OS

    F duri

    ng t

    he

    AM

    pea

    k hour.

    H

    ow

    ever

    , th

    e in

    crea

    se in

    inte

    rsec

    tion

    ave

    rage

    del

    ay w

    ould

    be

    red

    uce

    d t

    o les

    s th

    an t

    he

    two-s

    econd t

    hre

    shold

    of

    sign

    ific

    ance

    . Th

    e in

    ters

    ecti

    on

    would

    oper

    ate

    at

    LOS

    C d

    uri

    ng t

    he

    PM p

    eak

    hour

    afte

    r im

    ple

    men

    tati

    on

    of

    this

    mea

    sure

    . Th

    e in

    crea

    se in

    sig

    nal

    cyc

    le len

    gth

    may

    res

    ult

    in

    addit

    ional

    del

    ay f

    or

    ped

    estr

    ians

    and

    bic

    ycle

    s. H

    ow

    ever

    , n

    o s

    ignif

    ican

    t ef

    fect

    s w

    ould

    res

    ult

    fro

    m im

    ple

    men

    tati

    on o

    f th

    is m

    easu

    re.

    TRA

    NS-

    4:

    Th

    e ad

    dit

    ion

    of

    pro

    ject

    tra

    ffic

    would

    ca

    use

    a s

    ignif

    ican

    t im

    pac

    t at

    the

    Tel

    egra

    ph

    A

    ven

    ue/

    51

    st S

    tree

    t in

    ters

    ecti

    on (

    #3

    ) un

    der

    C

    um

    ula

    tive

    Yea

    r 2

    03

    0 B

    asel

    ine

    Plus

    Proje

    ct

    con

    dit

    ions.

    Th

    e pro

    ject

    would

    contr

    ibute

    to L

    OS

    F oper

    atio

    ns

    duri

    ng

    both

    AM

    and P

    M p

    eak

    hours

    ; w

    ould

    in

    crea

    se c

    riti

    cal m

    ove

    men

    t av

    erag

    e del

    ay

    by

    more

    than

    4 s

    econ

    ds

    duri

    ng

    the

    AM

    pea

    k

    hour;

    an

    d w

    ould

    in

    crea

    se inte

    rsec

    tion

    ave

    rage

    del

    ay b

    y m

    ore

    than

    2 s

    econ

    ds

    duri

    ng

    the

    PM p

    eak

    hour.

    S TRA

    NS-

    4:

    Imp

    lem

    ent

    the

    follo

    win

    g m

    easu

    res:

    C

    han

    ge

    signal

    cyc

    le len

    gth

    to 1

    20

    sec

    on

    ds

    and o

    pti

    miz

    e si

    gnal

    tim

    ing

    (i.e.

    , ad

    just

    the

    allo

    cati

    on

    of

    gre

    en t

    ime

    for

    each

    inte

    rsec

    tion

    appro

    ach

    ) at

    the

    Tel

    egra

    ph

    Ave

    nue/

    51

    st S

    tree

    t in

    ters

    ecti

    on

    an

    d c

    oord

    inat

    e si

    gnal

    phas

    ing

    and

    tim

    ing w

    ith t

    he

    adja

    cent

    Tel

    egra

    ph A

    ven

    ue/

    52

    nd S

    tree

    t an

    d C

    lare

    mont

    Ave

    nue

    inte

    rsec

    tion

    and o

    ther

    inte

    rsec

    tion

    s in

    the

    sam

    e co

    ord

    inat

    ion

    gro

    up.

    To

    imp

    lem

    ent

    this

    mea

    sure

    , th

    e pro

    ject

    spon

    sor

    shal

    l su

    bm

    it a

    sig

    nal

    opti

    miz

    atio

    n p

    lan

    to C

    ity

    of

    Oak

    lan

    d’s

    Tra

    nsp

    ort

    atio

    n S

    ervi

    ces

    Div

    isio

    n f

    or

    revi

    ew a

    nd a

    ppro

    val. T

    he

    pla

    n s

    hal

    l co

    nsi

    st o

    f si

    gnal

    tim

    ing p

    aram

    eter

    s fo

    r th

    e si

    gnal

    s in

    the

    coord

    inat

    ion g

    roup

    . Th

    e p

    roje

    ct s

    pon

    sor

    shal

    l fu

    nd t

    he

    cost

    of

    pre

    par

    ing a

    nd

    im

    ple

    men

    ting t

    he

    pla

    n.

    SU

  • JA

    NU

    AR

    Y 2

    00

    8

    MA

    CA

    RT

    HU

    R T

    RA

    NS

    IT V

    ILL

    AG

    E P

    RO

    JE

    CT

    EIR

    II.

    SU

    MM

    AR

    Y

    LTS

    = L

    ess

    Th

    an S

    ign

    ific

    ant

    , SU

    = S

    ignif

    ican

    t an

    d U

    nav

    oid

    able

    , S

    = S

    ignif

    ican

    t

    N:\

    20

    07

    \14

    07

    01

    1 M

    acA

    rthur

    BAR

    T T

    ransi

    t V

    illag

    e EI

    R\D

    ocu

    men

    ts\P

    ublic

    Rev

    iew

    Dra

    ft\2

    -Su

    mm

    ary.

    doc

    (1/3

    0/2

    008

    )

    15

    Tab

    le I

    I-1

    Su

    mm

    ary

    of

    Imp

    act

    s, C

    on

    dit

    ion

    s o

    f A

    pp

    roval

    (CO

    A)

    an

    d M

    itig

    ati

    on

    Measu

    res (

    MM

    )

    Imp

    act

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    ho

    ut

    M

    M

    Stan

    dard

    CO

    A/M

    M

    Level o

    f

    Sig

    nif

    ican

    ce

    Wit

    h

    MM

    /CO

    A

    TRA

    NS-

    4 c

    onti

    nued

    As

    show

    n in

    Tab

    le IV

    .C-1

    7, af

    ter

    chan

    gin

    g t

    he

    signal

    cyc

    le a

    nd t

    urn

    s, t

    he

    inte

    rsec

    tion

    would

    conti

    nue

    to o

    per

    ate

    at L

    OS

    F duri

    ng t

    he

    PM p

    eak

    hour,

    an

    d

    the

    incr

    ease

    in

    ave

    rag

    e del

    ay f

    or

    the

    crit

    ical

    move

    men

    ts w

    ould

    conti

    nue

    to b

    e m

    ore

    than

    the

    4-s

    econd t

    hre

    shold

    of

    signif

    ican

    ce.

    Th

    us,

    this

    mea

    sure

    is

    not

    suff

    icie

    nt

    to m

    itig

    ate

    the

    impac

    t to

    a les

    s-th

    an-s

    ignif

    ican

    t le

    vel. In

    addit

    ion

    , th

    e in

    crea

    se in

    sig

    nal

    cyc

    le len

    gth

    may

    res

    ult

    in

    addit

    ion

    al d

    elay

    for

    ped

    estr

    ian

    s an

    d b

    icyc

    les.

    To h

    elp f

    urt

    her

    min

    imiz

    e im

    pac

    ts a

    t th

    is inte

    rsec

    tion

    , a

    Tra

    nsp

    ort

    atio

    n

    Dem

    and M

    anag

    emen

    t (T

    DM

    ) p

    rogra

    m s

    hal

    l b

    e im

    ple

    men

    ted

    at

    the

    pro

    ject

    sit

    e to

    en

    coura

    ge

    more

    res

    iden

    ts a

    nd

    em

    plo

    yees

    to s

    hif

    t fr

    om

    dri

    ving a

    lone

    to

    oth

    er m

    odes

    of

    trav

    el. Po

    tenti

    al T

    DM

    mea

    sure

    s m

    ay in

    clude,

    but

    are

    not

    limit

    ed t

    o, tr

    ansi

    t ti

    cket

    subsi

    die

    s, a

    war

    enes

    s pro

    gra

    ms,

    dir

    ect

    tran

    sit

    sale

    s,

    pro

    vidin

    g a

    guar

    ante

    ed r

    ide

    hom

    e pro

    gra

    m,

    and p

    arki

    ng

    man

    agem

    ent

    stra

    tegie

    s. T

    he

    effe

    ctiv

    enes

    s of

    the

    TD

    M p

    rogra

    m s

    hal

    l be

    regula

    rly

    mon

    itore

    d, an

    d if

    nec

    essa

    ry a

    dju

    sted

    to m

    eet

    its

    goal

    s. T

    he

    pro

    ject

    applic

    ant

    shal

    l su

    bm

    it t

    he

    TD

    M p

    rog

    ram

    to t

    he

    Cit

    y fo

    r it

    s re

    view

    an

    d a

    ppro

    val. T

    he

    pla

    n s

    hal

    l al

    so b

    e su

    bm

    itte

    d t

    o B

    AR

    T f

    or

    revi

    ew a

    nd c

    om

    men

    t. T

    he

    pro

    ject

    ap

    plic

    ant

    shal

    l al

    so b

    e re

    spon

    sib

    le f

    or

    fun

    din

    g a

    nd

    im

    ple

    men

    ting t

    he

    TD

    M

    pro

    gra

    m.

    Th

    e co

    mpon

    ents

    of

    the

    pro

    pose

    d T