Ir. M. Blomme PPP EXPERT MEETING – 7/6/12 Brussels N74 North South Connection Limburg

Upload: claeshe

Post on 27-Jul-2015

147 views

Category:

Business


0 download

TRANSCRIPT

Ir. M. Blomme PPP EXPERT MEETING – 7/6/12

Brussels

N74 North South Connection Limburg

N74 North-South Connection Limburg

1. Project information

• Description of the project: completion of the missing link between North of Limburg and the E314 Highway

• 11 km roads, of which 2,5 km tunnels• 3 major exchanges• More than 40% of total cost: civil works

(tunnel, viaduct, bridges)

1. Project information

• Challenges:• Expropriation • European protection zones : mitigitation• DBFM-minded environmental and planning

reports• Parallel procedures

13

Man

agem

entc

omité

NO

OR

DZU

IDVE

RBI

ND

ING

28

april

200

8

Toelichting Planalternatieven

OMLEIDING

SEGMENT 1

SEGMENT 2

Helchteren

N715

SEGMENT 0

N74

13

KENMERKEN BASISALTERNATIEF SEGMENT 1 : noord

Toelichting Planalternatieven

SEGMENT 3

SEGMENT 4

SEGMENT 5

Houthalen

N715

E314

1. Project information

• DBFM • Construction cost: € 380 mio• Construction period est. 3 years• Maintenance 30 years

2 . Stakeholders

• Public meetings:• Local government: +• Environmental groups: +/-• Economic organisations: +• Action commitee: -

• Dry Run Reference Design: evaluation by planning authorities

• System Engineering vs ER and spatial planning

• Risk management reports

3. Tendering process

• Selection fase, 5 bidders• Tendering fase:

• 1st offer (evaluation ongoing): limited information, limited design costs

• 2nd offer (max. 3 bidders, 2013): full technical proposal

3. Tendering procedure

3. Tendering proces:

• First offer evaluation by authority and experts

• Acceptance criteria:• Price (maximum limit)• Technical criteria

• Design quality and project vision• Management Plan• Technical quality

• Focus on “added value” and differences between offers

3. Tendering proces:

• Detailed offer on segment 5 (landscape vision, architecture of bridges, building management plan)

3. Tendering process

• Functional criteria derived from enviromental report: degree of freedom contractor vs. rigidity administrative conditions

• Dont say:• “build a noise barrier 3 meters high”

• but say:• “maintain the noise level below 3dbA under

the current level”

Conclusion

• DBFM procedure = top end contractors

• Degree of creativity• Limited validity period of financing:

• max. 3 months• 9 months required (financial close after

building permit)