ma&d phases 1 and 2
TRANSCRIPT
Page 1
TCP/ZAM/3601 TRAINING REPORT
MA&D Phases 1 and 2
By…Makweti Sishekanu, National Consultant – MA&D
Submitted to…Jeremy Mbairamadji, PhD
Sioma 25-29th September 2017
Page 2
INTRODUCTION
The MA&D training contributes to the implementation of the TCP/ZAM/3601 entitled,
Sustainable Forest and Woodland Management for Food and Nutrition Security, in the Western
Province of Zambia. The project intends to increase and enhance food and nutritional security
through production, utilization and sale of forest products among selected rural communities in
Sesheke and Sioma Districts. The MA&D training feeds directly into the overarching objective of
this project; to improve food and nutrition security of rural communities through
commercialization of forest products for increased incomes and enhanced access nutritious foods
for effective and sustainable forest management. In particular, it is expected that the training will
lead to achievement of the following specific objectives:
i. To increase household incomes through the harvesting, processing and commercialization
of forest products;
ii. To enhance food and nutrition security at household and community levels by sharing
knowledge and promoting the widespread consumption of nutritious forest foods.
This report is structured to outline the learning activities, processes, achievements, challenges and
lesson learned from each of the five training days. The report also attempts to clarify certain
unplanned developments that emerged each day, how the challenges were addressed and
suggestions for improvements in the subsequent phases of the training, especially phase 3. Each
of the five training days is evaluated from two fronts; (i) the participants’ overall impression about
the logistical arrangements and, (ii) the participants’ overall impressions about the facilitation of
the training. To provide a glimpse into the realities of the training experiences, the report employs
the use of pictures to depict critical moments of the training each day.
Methodology and Training approach
The training is conducted in Lozi, the local language of the area and all training materials are
translated for that purpose. The training adopts different pedagogical tools as indicated in the
program in Annex 1. A Participatory Rural Appraisal (PRA) method was employed taking care of
local context, participants’ moods, group dynamics, literacy and their levels of conceptualization.
Different facilitative approaches starting with story-telling through guided discussions, brain
storming and quizzes, group work and cross examinations, field work, role play were adopted and
a pictorial power point presentation to close the training on Day 5. These pedagogical tools have
proven effective evinced from the daily evaluation results by the participants themselves at the end
of each day.
Design of the Training program
The training targets a total of 60 participants constituting of 15 facilitators; one from Wildlife and
National Parks; one from Community Development; two from forests Department, and 11
community facilitators from among the community forest producers. In this training, facilitators
and producers are trained together while the 15 facilitators assist the consultant by taking the
leading roles in group work sessions and field surveys. The facilitators will also be crucial in
preparing for the second cycle of the training.
Page 3
The remoteness of the three community areas had a significant bearing on nearly all the challenges
faced during the training. Four drivers, one from FAO and 3 from Forests Department including
the project vehicle, were starting off as early as 04; 00 AM to drive utmost 30km across sandy
terrains to pick up the community producers from the three areas. After which, one driver was
required to drive 20 kilometers to pick up the consultant from his lodging place. To complicate
this challenge, Sioma District has no filling station, meaning, drivers needed to drive more than
100km to the nearest filling station in Senanga District. As such, the trainings could not be
executed as planned according to the training program in Annex 1, as the participants needed time
to settle down for breakfast as their first activity having been required to wake up very early in the
morning each day.
Therefore, training sessions were only starting after 09:00 hours, and squeezing the lessons of each
day between 09; 30 and at least 16: 00 hours inevitably demanded changes in the timetable as the
participants had to be driven back to their distant communities before dusk. These changes also
meant a compromise in the delivery of the training. Clearly, transport stands out as key to the
success or failure of this program. Therefore, two suggestions are hereby put forward for
improvements in the subsequent phase:
i. Accommodate all the participants in the nearest location right in Sioma Boma. The
advantage of this option is a reduction in driving time for the drivers and conservation of
fuel in the cars, given the fact that Sioma District has no filling station. It will also guarantee
adequate time to commence and end trainings sessions every morning and evening,
respectively. There may not be need for four vehicles running around long distances every
morning and evening to ferry the participants under this option. The disadvantage of this
option however, is the lack of accommodation in Sioma. This challenge would mean that
participants arrange their own accommodation within Sioma Boma and paid an allowance.
With the experience from this phase of training sessions, there is no guarantee that the
villagers will use that money for such a purpose but would rather walk long distances from
their villages to the training center. Secondly, there will definitely be a need to adjust the
budgets upwards to cover accommodation of 60 participants for five days.
ii. Increase the number of vehicles from four to five so no driver has to make more than one
trip to ferry participants from their villages. Prepare drums of fuel to purchase fuel in bulk
from Senanga and store it for refueling right in Sioma. This option does not change the
distance which each drive has to drive to ferry the participants but it will require each drive
to make only one trip in the morning and evening. The participants will still need to be
given time to have breakfast in the morning and driven back on time at least by 16; 00
hours. Compromises in the training will still be inevitable in order to accommodate this
reality. The option will equally require an upward adjustment to the budgets especially for
fuel.
Page 4
DAY 1, MONDAY 25th SEPTEMBER 2017
Introduction of all participants: A total of 61 participants (38 males and 23 females) registered on
Day 1. Sioma District Commissioner, Mr. Maurice Litula officially opened the training
recognizing the esteemed presence of the Barotse Royal Establishment (BRE) Induna seated as
one of the participants. The training opened with a Brain-teasing story in Annex 2, meant to create
critical thinking around what enterprise should be, what it should NOT be and community
cooperation around exploitation of local resources. From the story, key lessons are hidden in the
concept of community-based enterprises.
Introduction to MA&D was opened with Phase 1 Lesson 1 of Annex 3. The supporting training
materials for the lesson are designed to ask questions that lead participants in the way of identifying
what the forest resources are, and where they are found. Out of this session, a total of nine
prominent product interest groups were identified, namely - (i) Honey (ii) Seto (devil’s claw) (iii)
Mungongo (Schinziophyton rautanenii) (iv) Timber (v) Wild fruits (vi) Grass (vii) Wildlife (viii)
Crafts and, (ix) Mbowa (Mushroom). The products are all seemingly promising measured against
the community’s challenges which came out as follows:
Lack of Leadership Training, 17%
Lack of Electricity, 8%
Transport problems, 8%
Unclear regulations, 17%Lack of
equipment/technology, 8%
Poor market, 38%
Poor community cooperation, 8%
ENTERPRISE CHALLENGES FROM DAY 1
Page 5
Reference to poor market as a challenge in this case means lack of buyers; the producers have to
travel very long distances to a place where they can sell, often compounded by lack of transport.
Before lunch, participants were challenged into a brain storming exercise that stimulated their
thinking around why and how they would engage in an enterprise; what needs do they recognize
as critical for such engagements aided by material in Annex 4? This was done through role play
of selected participants after which everybody broke into groups formed around the five areas of
sustainable enterprise development for which the groups cross examined each other’s ‘reasoning
using the five criteria of enterprise development set out in Annex 5.
Using these five areas as criteria, participants were guided into assessing opportunities, risks and
challenges within their market setup. In their groups formed around the five areas of sustainable
enterprise development, participants went through a screening process of selecting products which
seemed promising from their perspectives. It was easier and practical to form five groups around
the five areas of sustainable enterprise development than to form more than ten groups around the
different products interests. Essentially, it must be justified that forming a group around economy
and finance, for instance, did not divorce the group from examining their products-interests around
the other four areas of sustainable enterprise development. The group formation around one of the
five criteria of sustainable enterprise development only helped each group to be specific about
what they needed to focus on in scrutinizing the other groups’ product interests. This approach
was successful in ensuring that group discussions were more focused rather haphazard in a large
group of 60 people.
Group ONE (The Natural Resource Group)
The group argued in justification of their products, that they were available, plenty, market was
perceived to be good and they had multiple uses for their selected products. These products were
– (i) Muwawa (Strychnos pungens) (ii) muhuluhulu (Strychnos cocculoides) (iii) Muzauli
(Gilbourtia coleosperma) (iv) Mumbole (Vangueriopsis lanciflora) (v) Seeto (Devil’s claw) (vi)
Malasha (Charcoal) (vi) Mumaka, (vii) Munola (viii) Namulomo (Ficus verruculosa) (ix)
Mungongo (Schinziophyton rauteneii) (x) Munzinzila, and (xi) Linosi (honey). After screening all
these products using the five areas of sustainable enterprise, Group ONE was only left with three
products – Timber, Seeto and Charcoal. The other four groups, i.e., law/regulations group,
sociocultural group, economy/finance group and the technology groups cross examined Group
ONE on their three products prompting them to think more in terms of the other four areas of
sustainable enterprise development. It was ultimately observed that Economy and Finance were
the major factors influencing the screening.
Page 6
Group TWO (The sociocultural group)
The group worked hard to scrutinize every promising product enterprise against the taboos, culture
and norms of the area. The
group is equally cross
examined by other groups
around the potential
influences which other four
areas of sustainable
enterprise could have on
their selected products.
Group TWO selected five
promising products as
follows - (i) Timber, (ii)
Seeto, (iii) Thatching grass,
(iv) Mungongo and (v)
honey. After the screening
process, the group only
remains with two – Timber
and Seeto. Notwithstanding
the final selection, the group
failed to satisfy the questions
Page 7
from the Group THREE below, technologies and harvesting techniques where timber harvesting
was concerned.
Group THREE (The technology/product development and research group)
The group is subjected to the same process of cross examination by other groups. Initially, group
three has five promising products, i.e., (i) Timber (ii) Thatching grass (iii) Seeto, and (iv) Honey.
After thorough screening through the five areas of sustainable enterprise development, the group
remains with Timber only. The Natural resource and the Economy and Finance criteria of
sustainable enterprise development played a major role in this elimination process.
Group FOUR (The law and regulations group)
The group highlighted regulatory lacunas as the key challenge in the area for enterprise
development of products like Seeto (Devil’s claw). The group identified five promising products
as – (i) Mungongo (ii) Seeto (iii) honey (iv) thatching grass and (v) Muhuluhulu. Using the five
areas of sustainable enterprise development, the group narrowed down their products to one –
Mungongo, which they had to justify to the other four groups who questioned the product’s
sustainability against technology, sociocultural issues, natural resource base and it economic and
financial viability. What was interesting in the group’s analysis was the role of legal regulation in
the elimination of Seeto (Devil’s claw) from their list of promising products. This is against the
fact the Devil’s claw is the most economically lucrative product in the area – the green gold of the
forests.
Group FIVE (The economy and finance group)
Group five raised only one
question for everything
presented in the training – are
these products making
economic sense? The group
selected five promising
products; (i) Timber (ii)
Charcoal (iii) honey (iv)
Seeto, and (v) Thatching
grass. However, the group
concluded in their final
analysis using the five areas of
sustainable enterprise
development that only Reeds
and Charcoal made
economic sense. Through
further cross examination by
the other four groups, Reeds
were eliminated for being a
river/marshland resource
Page 8
rather than a forest product. Eventually, the group remained with only one product to showcase –
Charcoal.
Key lesson of the day
Not all products, regardless of how promising they may seem at face value, are sustainably fit for
enterprise development in the context of MA&D.
Training had to cease before 16; 00 hours because the participants had a long tedious journey back
to their villages.
Daily Evaluations
The consultant sat with the project team to review participant’s impressions about the training at
the end of the day. What were the participants’ overall impression about the logistical
arrangements of the day?
A. Satisfaction – representing all the things (too numerous to mention) which participants
expressed as good and/or recommendable
B. Dissatisfaction – representing all the things which participants expressed as bad, not
recommendable, the things for which they sort improvements. This included sentiments
such as – inadequate food, inadequate water, water was too warm, transport delayed to pick
the participants, participants needed to be paid allowances (which was the most prominent
complaint), participants needed T-shirts and participants complained about keeping time.
C. Demands to be paid an allowance – notably prominent among the dissatisfactory issues
as it represented the major complaint from the participants
D. No comments – represents those who had no comment to write, notwithstanding nor taking
for granted the hidden meanings of this silence
What were the participants’ overall impression about the logistical arrangements of the training?
0%
10%
20%
30%
40%
50%
60%
Satisfaction Dissatisfaction Demand to be paidallowances
No comments
Evaluation of Day 1
Series 1 Series 2 Series 3
Page 9
What were the participant’s overall impressions of the consultant’s facilitation of the day: Very
Poor; Poor; bad; Not bad; Fair; Good; Very Good, OR Excellent?
Attendance
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
Very Poor Poor Bad Not bad Fair Good Very Good Excellent
Evaluation of the consultant
Column1 Series 2 Series 3
Total61
Males38
Females23
DAY 1
Total Males Females
Page 10
DAY 2, TUESDAY 26th SEPTEMBER 2017
Recap of the five areas of sustainable enterprise development
Having demonstrated understanding on the analytical use of the five areas of sustainable enterprise
development, participants were guided to understand the market for their selected products. By the
second day, it was then clear that the subsequent sessions were to be based on four selected
products – Timber, Charcoal, Seeto and Mungongo; all having passed through the screening test
of the five areas of sustainable enterprise development.
Specific objective of the day; at the end of the session, participants were to be able to demonstrate
an understanding of the term ‘market’ and the market system within which the different products
were to be marketed and not just sold off.
With the aid of the teaching material in Annex 6, particular emphasis was laid on understanding
the value chain movements of each product from its production (where it is converted from a
resource) through to consumption. A number of challenges were discussed coming from the
analysis of product movements around different value chains: (i) poor market – having no or very
few buyers who could buy the products within Sioma Boma (ii) lack of processing equipment –
the producers had no choice but to give away the products in raw form without processing (iii)
transport problems – are varied in nature. There are long distances involved to move products from
one are to another coupled by the mode of transport (use of oxen) which was proving unreliable
over such long distances (iv) lack of electricity – as much of Sioma is not electrified (v) lack of
trainings – the communities have had different trainings offered by different NGOs in different
areas of community development but no training had ever been offered around enterprise
development (vi) poor community cooperation – communities felt they were being swindled by
occasional middlemen because the producers were formally organized around forest management.
Each individual worked in isolation of the other to produce by themselves and for themselves. This
challenge pointed to the moral of the story in Annex 2, and (vii) unclear regulations – was a
common challenge for products like the Devil’s claw. The problem seems to have persisted ever
since the government suspended the Statutory Instrument (SI) to regulate the production and
conveyance of the same product. The suspension of the SI has created a vacuum of regulatory
authority where it is no longer clear who was in charge of the product among three institutions;
the Forest Department, Wildlife authority and the Local council?
At the end of the day, each participant was given a brainstorming exercise (as homework) to think
about how the selected products from the screening process moved or would move around the
value chains into the market system. This exercise served to introduce analysis of the market for
each of the four products aided by the material in Annexes 7 and 8.
Because market analysis is only complete with field surveys, the last session of the day was
reserved for facilitators in preparation for field visits the following day. It was logistically
impossible to involve all the 61 participants in the field survey using four station wagon vehicles
across vast distances. This part of the training was designed as such from inception, to avert the
challenge of teaching a large number of 60 people. The primary purpose of the facilitator’s session
was to prepare for data collection in a guided manner that seeks to capture the relevant information
Page 11
around the five areas of sustainable enterprise development. Training material in Annex 9 was
designed to provide that guidance.
Daily evaluations
The consultant sat with the project team to review participant’s impressions about the training at
the end of the day.
What were the participants’ overall impression about the logistical arrangements of the training?
What were the participant’s overall impressions about the consultant’s facilitation for the day?
0%
10%
20%
30%
40%
50%
60%
Satisfaction Dissatisfaction Demands for allowances No comments
Evaluation of Day 2
Series 1 Series 2 Series 3
0%
5%
10%
15%
20%
25%
30%
35%
40%
Very Poor Poor Bad Not Bad Fair Good Very Good Excellent
Evaluation of the consultant
Series 1 Series 2 Series 3
Page 12
Attendance
DAY 3, WEDNESDAY 27th SEPTEMBER 2017
Field Day with facilitators
Total61
Females25
Males38
Day 2
Total Females Males
Page 13
Day 3 formed a critical part of analyzing the local market situations of the four selected products.
Field work was designed to augment the session on Introduction to Market Surveys on Day 2. On
field day mission were a total of 15 facilitators from the community and 5 facilitators from the
District. The consultant plus five other logistical personnel from the project team giving us a total
of 26 people divided into four Product-based Groups, i.e., Mungongo, Timber, Seeto and
Charcoal, which had to use four vehicles. It was clear that there was a problem with the selection
of community facilitators prior to the training. A number of community facilitators had to be
handpicked during the training session of Day 2.
Teaching material in Annex 8 was designed to guide the facilitator into what exactly they had to
look for in the field. That is notwithstanding the fact that they would encounter unexpected
information and circumstances either on their way or right in their field work. The findings from
field work were designed to complete the community producers’ home work on the introduction
to market surveys and analysis. This was to be presented the following day on Day 4.
Mungongo processing facility in Sioma (the only Mungongo processing facility in the entire
Western Province of Zambia)
Page 14
Each of the four groups went its own way until evening. Before the end of the day, the field work
teams reconvened at the Training Center to summarize their findings in their respective groups
and to evaluate the day’s work. The biggest impression of the day was that facilitators learned that
there were significant differences between information they thought they knew about the area and
the reality of things on the ground.
Daily Evaluations
What were the participants’ overall impressions about the logistical arrangements of the training?
What were the participant’s overall impressions about the consultant’s facilitation of the day?
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
Satisfaction Dissatisfaction Demands for allowances No comments
Evaluation of Day 3
Series 1 Series 2 Series 3
0%
5%
10%
15%
20%
25%
30%
35%
40%
Very Poor Poor Bad Not Bad Fair Good Very Good Excellent
Evaluation of the consultant
Series 1 Series 2 Series 3
Page 15
Attendance
DAY 4, 28th SEPTEMEBR 2017
Facilitators and producers reconvene
Day four started with ironing out logistical issues that emerged from an emotive discussion at close
of Day two, where participants demanded to be paid money instead of being given food. More
than half an hour was spent ironing out the issue before training could resume. It became clear
from the discussion that this issue was never addressed or overlooked during the initial
sensitization phase of the project. BRE representative in the group concluded the matter when he
asserted that the project team was to be excused for its ignorance of the fact that it was a custom
to pay people whenever they were called to leave their homes for such programs. Meanwhile, that
the project team became well aware of the custom, there was no more excuse for them not to pay
the participants. This development was communicated to Ms. Celestina Lwatula at FAO in Lusaka,
who escalated the issue to FAO Country Rep. It was then decided, for the sake of completing the
training, that the project team gives in to the demands of the participants. With the BRE Induna’s
caution, it is beyond doubt that the issue will have to be clear from the beginning of phase 3 training
and participants paid.
On resumption, participants were taken through their homework from Day 2 based on Annex 6.
They presented their analyses of various forest products in different value chains. The aim of this
exercise was to gather the participants’ perceptions, understanding and misunderstandings of the
opportunities and challenges that would come with each of the selected products in different value
chains.
Total26
Females12
Males14
Day 3
Total Females Males
Page 16
But to consolidate the producers’ perceptions and understandings, facilitators presented their field
survey findings from Day 3. Because producers did not take part in field surveys, facilitators’
presentations were designed to augment the producers’ understandings and to clarify the
misunderstandings about the outlook of local product value chains for the selected four products.
One of the misunderstandings that had to be cleared in this session was a heated discussion around
the seasonality of Mungongo. Facilitators in the Mungongo group discovered the truth about the
issue from the field survey, that Mungongo was, indeed, seasonal.
Facilitators’ Charcoal Group
The group was led by facilitator from the department of Wildlife and National Parks. His presence
as a participant in the training was very crucial for clarifications around the role of his department
in the legal regulation of Devil’s claw. The group discovered a simple and small value chain of
Charcoal production and trade in Sioma. The group found out that there were very few producers
of Charcoal in Sioma, if not one man, who works hard to satisfy local demand from the traditional
method of earth kilns. From the facilitators’ field survey findings scrutinized against the five areas
of sustainable enterprise, Charcoal stood out as a promising product for enterprise development.
Page 17
Facilitators’ Mungongo Group
The group was led by a female facilitator from
the department of Social welfare and
Community Development. The group noted that
the resource base was huge with an abundance
of the product available in more months of the
year than its off-season period. Family labor is
mainly employed in picking Mungongo which
is consumed at household level and sold to the
only processor within Sioma. The product is
sold in its raw/unprocessed form to a South
African processor based in Sioma.
Mungongo in the village storage shed
Page 18
Facilitators’ Seeto Group
The group was led by a male community facilitator who has also been used by other NGOs like
WWF as a community facilitator. The group found that regulatory irregularities were the
commonest hindrance for enterprise development with the famous Devil’s claw. The product is on
high demand in Zambia and across the border in Namibia. It is harvested selectively from
communal forests but incidences of harvesters straying into the Sioma Ngweze National Park are
not uncommon. Harvesters of Seeto in Sioma have not undergone any form of training in as far as
harvesting is concerned, but rely on techniques informed by indigenous knowledge. Middlemen
are the key players and trendsetters in the business – they work with Namibian middlemen across
the border who sale the product to Namibian-based Germans. The price of the product fluctuates
according to the season in which it is harvested. But on a good working day, a community harvester
is able to harvest 2x50kg bags of the product, which shrinks to less than 10kg when dried and
processed by the community harvesters before selling it. Wildlife authorities and the local council
do confiscate the product, bulked in their offices but the confiscated product does find its way
secretly back into the value chain. If not confiscated, producers are levied for conveyance without
official receipts. But has legal authority to levy them is a different matter all together.
Page 19
Facilitators’ Timber Group
The group was led by the female
District Forest Officer (DFO) of Sioma
District. The group had the greatest
challenge of having to travel more than
80 km to the first point of their field
survey. The group noted that the
harvest of timber is done on a large
scale and heavily mechanized but well
regulated. They are very few
community producers involved in the
timber business right from its
production. When they are, it is those
casual laborers engaged in loading and
offloading logs on and off trucks.
Primary production is marred with
numerous challenges which are mainly
mechanical in nature and complicated
by the long distances from the primary
production areas to the main market in
Lusaka and or Livingstone.
The day closed with an introduction to enterprise ideas based on facilitators’ field survey findings
and producers’ value chain analyses of the selected products. The participants had to be paid lunch
allowance and allowed ample time to buy their own lunches. As such, the day’s training had to be
closed at 13: 30 hours, another compromise that needed to be made to accommodate some of the
challenges. First, it took more than an hour to disburse payments to each participants. Secondly,
the participants needed ample time to move around the market looking for lunch, and thirdly, the
participants needed to be ferried back home on time at least by 16:00hors. It was discovered later
on, that the participants did not use the money for lunch but rather sacrificed to stay hungry and
keep the money for subsistence back home. In the evaluation, a few participants complained of
hunger.
Daily evaluations
The consultant and the project team assessed the participants’ evaluative comments for the day
and particularly noted the issue of hunger emerging out of the dissatisfactory issues. The level of
dissatisfaction was remarkably low most likely because of the allowances paid. What were the
participants’ overall impressions about the logistical arrangements for the training?
Page 20
What were the participants’ overall impressions about the consultant’s facilitation for the day?
0%
10%
20%
30%
40%
50%
60%
Satisfaction Dissatisfaction Demand for allowances No comments
Evaluation of Day 4
Series 1 Series 2 Series 3
0%
5%
10%
15%
20%
25%
30%
35%
40%
Very poor Poor Bad Not Bad Fair Good Very Good Excellent
Evaluation of the Consultant
Series 1 Series 2 Series 3
Page 21
Attendance
DAY 5, FRIDAY 29th SEPTEMBER 2017
The key objectives of the day were
Total60
Males39
Females21
Day 4
Total Males Females
Page 22
(i) To consolidate the development of enterprise ideas around the four selected products
from day four’s work, and
(ii) To demonstrate an understanding of product value chains desired by the participants.
All the 60 participants had to be subsumed into four product interest groups with Charcoal divided
into two groups because more participants expressed interest in the product. Ultimately, it was to
be interesting to see two different enterprise ideas emerging around the same product.
Charcoal Group ‘A’ Enterprise Idea
The group assessed their potential Charcoal enterprise from both an individual and a group
perspective. Having learned from their findings in the field survey, it was noted that an individual
approach was too labor-intensive and would be cost ineffective. Therefore, the group concluded
that a group or cooperative approach was a better option. The group justified their simple enterprise
idea based on the attempt to avert the challenges noted with the product; labor-intensity and
unreliable transport. Cross examined by other groups against the five areas of enterprise
development, the group was convinced that their Charcoal enterprise idea was promising. But
whether it would be profitable or not was a question for phase 3.
Charcoal Group ‘B’ Enterprise
Idea
Interesting from the Charcoal
presentations were the different
ideas emerging around the same
product. Group B highlighted the
challenges involved in the
production and trading of
charcoal; transport, labor and the
poor quality of Charcoal being
key. The group further outlined
the opportunities in Charcoal and
weighed them against the
challenges. Hence the group
builds its idea around sidestepping
these challenges. What is salient
from group ‘B’ is their focus on
the quality of charcoal being an
incentive for a higher price than
group ‘A’. But like group ‘A’,
group ‘B’ equally adopts a
cooperative enterprise because it solves the labor puzzle in the production of Charcoal. The
enterprise idea is promising with rough estimates of ZMW 72, 000 annually from 4 kilns. Whether
these estimated projections are realistic or not is a question for phase 3 training. But to protect the
idea, the group sees need for introduction of community bye-laws around communal forests.
Page 23
Timber Group Enterprise Idea
Timber group presented two ideas, both group-based ideas. The first idea is based on selective
harvesting of trees that go into a local communal carpentry. The idea is informed by the need for
construction timber in the newly created District of Sioma which is in dire need of infrastructure
developments. In the second idea, the community cooperative goes into a partnership with a chain
saw owner for a stipulated period of time as the community producers realize their need for heavy
and costly machinery. The timber group outlined two different value chains for each of the two
ideas while wary of the fact that timber has huge challenge with production costs but huge profits
too. How profitable will this idea be was reserved for phase 3.
Seeto Group Enterprise Idea
Page 24
The group is alive to the fact
that lack of government
regulations for the exploitation
of the product is the single
major challenge for enterprise
development. But having been
reassured by the Forest
Department that GRZ was
working on putting a lasting
solution to the problem, the
group had the incentive to
settle for the product – around
which, a group-based business
idea was developed. The
group argued that the
harvesting and primary
processing were too laborious
for an individual enterprise
while acknowledging the fact
that the product was too economically lucrative to be left only for Namibians. The group’s idea
was simple and built around the need to eliminate the middleman. The group raised a critical
argument, questioning why it was easy for the Namibian traders to move around the enterprise in
and out of the country while it was extremely difficult for the Zambians to do the same! The group
could not find an answer to this question during their field survey.
Mungongo Group Enterprise Idea
The group identified the lack of processing machinery as their greatest hurdle, as Mungongo is an
extremely hard nut to crack. The group envisions a cooperative system of enterprise in partnership
with the South African Mungongo processor in Sioma. This idea was informed by the observation
from the field survey that even the South African processor in Sioma was the only one in the entire
province who had the sort of machinery designed to crack and squeeze the nut into oil in a
complicated mechanical process. The group learned that the processor had his machine patented
as he designed it himself. The details of the envisioned partnership which the community producers
are planning will be seen and evaluated in phase 3. Fortunately for the producers, the South African
processor guarantees to play his part in working with organized community producers.
Page 25
The session with producers ended with a recap of the training from Monday to Friday by selected
participants who had been recorded on video from Day 1. The video snapshots were beamed
through power point presentation to give the participants an unexpected pleasure of seeing
themselves talking on a large screen. In the next cycle of training, participants will be expected to
understand whether their enterprise ideas are profitable or not, as they will be taken through the
details of planning and building an Enterprise.
Facilitator’s session
The last session of the day was with facilitators to underscore the principles of MA&D facilitation
according to Annex 10. The session was also designed to prepare the facilitators for phases 3 and
4 of the second cycle. Facilitators were reminded of the fact that the end of this phase was not the
end of the MA&D process but rather a break to enable them gather more information around their
enterprise ideas.
The consultant and the project team reviewed the participants’ evaluations of the day.
Page 26
Daily evaluations
What were the participants’ overall impressions about the logistical arrangements of the training
for the day? It must be noted that the demand for allowances shot as the highest grievance after
being paid on Day 4. Essentially, this indicates three possibilities – (i) that the participants were
still not adequately informed that the Day 4 allowances were meant to cover the two remaining
days (ii) participants’ expectations were not properly managed right from the sensitization of the
project, and (iii) as the saying goes – that it is very difficult to satisfy villagers.
What are the participants’ overall impressions about the consultant’s facilitation of the day?
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
Satisfaction Dissatisfaction Demand for allowances No comments
Evaluation of Day 5
Series 1 Series 2 Series 3
0%
5%
10%
15%
20%
25%
30%
Very poor Poor Bad Not bad Fair Good Very Good Excellent
Evaluation of the consultant
Series 1 Series 2 Series 3
Page 27
Attendance
Mean 5-Day attendance
Total55
Males36
Females19
Day 5
Total Males Females
61 61
20
60
555140.00%
0
10
20
30
40
50
60
70
Day 1 Day 2 Day 3 Day 4 Day 5 Average
Average attendance
Series 1 Series 2 Series 3
Page 28
MA&D NATIONAL CONSULTANCY
TORs
1. Contribute to the design of MA&D training of facilitators and communities
2. Develop training materials for the MA&D training and report
3. Conduct the trainings in MA&D to the targeted facilitators to help them implement the
outcomes of the TCP through all cycles of the training
4. Assist the participants (facilitators) to gather information for cycle II
5. Conduct MA&D training to communities with the help of trained facilitators
6. Develop feedback to work plans developed by training participants
7. Support facilitators and communities in the implementation of MA&D activities in the field
8. Coach forest product interest groups in implementing their EDPs tailored to market needs
and forest products