lubber run community center - arlingtonva.us

102
Lubber Run Community Center Community Meeting #4 July 19, 2017 OCULUS

Upload: others

Post on 05-May-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Lubber Run Community Center - arlingtonva.us

Lubber Run Community CenterCommunity Meeting #4July 19, 2017

OCULUS

Page 2: Lubber Run Community Center - arlingtonva.us

300 N Park Dr

Arlington, VA 22203

Lubber Run Community Center

N

Page 3: Lubber Run Community Center - arlingtonva.us

1. Review of final building concept design2. Focus on site elements for community feedback as CMAR

collaboration begins3. Update community on next steps

Goals for Tonight

3

3

Page 4: Lubber Run Community Center - arlingtonva.us

Agenda7:00 Welcome Mark Schwartz

Goals for Tonight Jane Rudolph

7:05 Project Overview

Project Timeline

Community Process

7:15 Final Building Concept Joe Celentano

7:30 Building Q + A Joe Celentano

7:45 Park Concept Don Hoover

8:15 Park Q + A Don Hoover

8:30 Break to Information Stations

Park Design Information and Feedback Don Hoover / OCULUS

Building 3D Station Andres Pacheco

8:55 Wrap Up and Look Ahead Joe Celentano

4

Page 5: Lubber Run Community Center - arlingtonva.us

Early Visioning Highlights 2015 Highlights from community visioning session and survey:

• Preserve and maximize green space• Improve site access and safety• Integrate the building into the park• Improve outdoor courts and playground• Include:

• Outdoor multi-purpose athletic courts• Exercise rooms/fitness• Gymnasium• Multi-purpose flexible use spaces Lubber Run Visioning Session

5

5

Page 6: Lubber Run Community Center - arlingtonva.us

Project Highlights 2016 • County Board work session on Lubber Run Scope in April 2016 • County Board adopted CIP in July 2016 with guidance on Lubber Run:

• Build up to four stories along with underground parking to enable more green space• Include gym, relocate senior program from Culpepper Garden, continue DPR

preschool• Consolidate DPR staff at Lubber Run and 3700 S Four Mile Run in new center• Office use remain subservient to the community center in form and function of the

overall facility• Bond passed November 2016 with $46.5M in new bonds for design and construction for

replacement of the Lubber Run Center• Use of Alternative Delivery Methods Work session in November 2016• Construction Manager at Risk (CMAR) Alternative Delivery Method• LEED Silver (County Standard) & Net Zero Study

6

6

Page 7: Lubber Run Community Center - arlingtonva.us

CMAR CONTRACT AWARDED

• Construction Manager Risk Contract Awarded by County Board on Tuesday, July 18

Request for Proposals No. 17-223-RFP award to James G. Davis Construction Company• Received 8 proposals• Total contract award:$39,960,000.00

Cost of Work $34,849,347.00Construction Management Fee $900,000.00General Conditions Fee $1,250,653.00Construction Total Cost/GMP $37,000,000.00

*County-held contingency $2,960,000

• Advantages: pre-construction service (estimating, value analysis, scheduling and constructability), earlier price protection through the GMP, and minimize change orders.

7

Page 8: Lubber Run Community Center - arlingtonva.us

PROJECT TIMELINE 8

Page 9: Lubber Run Community Center - arlingtonva.us

COMMUNITY PROCESS 9

Page 10: Lubber Run Community Center - arlingtonva.us

Spring 2015• Over 100 attending early visioning sessions with Cox, Graae & Spack architects

• 262 responses to early visioning survey

Winter - Fall 2017 • Four community meetings (February, March, May and July 19)

o February 8 – 200 attendeeso March 22 & 25 – 120 attendeeso May 17 – 75 attendees

• 250+ responses via on-line survey post community meetings• In-person/outreach:

March - Walter Reed Senior Center focus group - 30 - Gates of Ballston residents on-site survey – 29- Lubber Run Elementary Afterschool program - 35

April – clipboard survey of outdoor court use - 47May – June – pushed out on-line survey to Lubber Run preschool, elementary, and teen program participantsJune – clipboard survey of outdoor court use - 43

• All in person community meetings supported with free child care and Spanish language translation

COMMUNITY PROCESS 10

Page 11: Lubber Run Community Center - arlingtonva.us

VMDO - Full Range of Experience 11

Page 12: Lubber Run Community Center - arlingtonva.us

VMDO – Arlington Projects 12

Elementary School at JeffersonDiscovery Elementary SchoolAwards for Discovery Elementary:2017 COTE Top Ten Award, AIA Committee on the Environment2016 Honor Award, AIA Central Virginia2016 Honorable Mention, Learning by Design2016 Project of Distinction, Association for Learning Environments2015 Award of Excellence, Design Arlington Awards Program

Page 13: Lubber Run Community Center - arlingtonva.us

BASIS OF DESIGN 13

Page 14: Lubber Run Community Center - arlingtonva.us

Kick-off Meeting with the Community

COMMUNITY MEETING #1 14

Different tools were used to determineguidance from the community.

Keep/Toss/Build

Building Location

Positive/Negative reactions to precedent images

Page 15: Lubber Run Community Center - arlingtonva.us

COMMUNITY MEETING #2 15

Page 16: Lubber Run Community Center - arlingtonva.us

COMMUNITY MEETING #2 SCHEMES

COMPACT PORTAL

EMBEDDED RIBBON

16

Page 17: Lubber Run Community Center - arlingtonva.us

17

COMMUNITY MEETING #2 SCHEMES INPUT 17

Page 18: Lubber Run Community Center - arlingtonva.us

COMMUNITY MEETING #2 SCHEMES INPUT SUMMARY

TOO TALL/BIG

TOTAL

45

50

30

9218

PRESERVES NATURETOO TALL/BIG

PRESERVES NATURE

FORMS BARRIER

SCALE OF BUILDING

RAMPS NOT USABLE

INTEGRATES W/ NATURELARGER FOOTPRINT

THEMES

60 32

13 17

31 19

24 21

Page 19: Lubber Run Community Center - arlingtonva.us

COMMUNITY MEETING #2 SCHEMES INPUT SUMMARY

PRESERVES NATURE TOO TALL/BIG

PRESERVES NATURE FORMS BARRIER

SCALE FROM PARK RAMPS NOT USABLE

INTEGRATES W/ NATURE LARGER FOOTPRINT

TOO TALL/BIG

TOTAL

45

50

30

9219

Page 20: Lubber Run Community Center - arlingtonva.us

Mass building in NE corner without overwhelming park and saving as many trees as possible

Integrate building into nature and engage park

Building layout should foster a sense of community, inclusion and connectivity

KEY THEMES FROM CM#2 20

Page 21: Lubber Run Community Center - arlingtonva.us

GYM MASSING 21

Page 22: Lubber Run Community Center - arlingtonva.us

GYM MASSING 22

Page 23: Lubber Run Community Center - arlingtonva.us

GYM MASSING

• Mass building in NE corner• Save trees

23

Page 24: Lubber Run Community Center - arlingtonva.us

REACH TO LUBBER RUN 24

Page 25: Lubber Run Community Center - arlingtonva.us

REACH TO LUBBER RUN 25

Page 26: Lubber Run Community Center - arlingtonva.us

REACH TO LUBBER RUN

• Mass building in NE corner• Save trees • Integrate into nature

26

Page 27: Lubber Run Community Center - arlingtonva.us

EMBEDDED BAR 27

Page 28: Lubber Run Community Center - arlingtonva.us

COURTYARD / BAR 28

Page 29: Lubber Run Community Center - arlingtonva.us

COURTYARD / BAR

• Mass building in NE corner• Save trees • Integrate into nature• Courtyard open to nature• Engage park

29

Page 30: Lubber Run Community Center - arlingtonva.us

OFFICES 30

Page 31: Lubber Run Community Center - arlingtonva.us

OFFICES 31

Page 32: Lubber Run Community Center - arlingtonva.us

OFFICES

• Mass building in NE corner• Save trees • Integrate into nature• Courtyard open to nature• Engage park• Reduce scale of offices

from park

32

Page 33: Lubber Run Community Center - arlingtonva.us

LOBBY NODE

• Mass building in NE corner• Save trees • Integrate into nature• Courtyard open to nature• Engage park• Reduce scale of offices

from park• Centralized main entry• Maximize connectivity• Foster community• Accessible design

33

Page 34: Lubber Run Community Center - arlingtonva.us

COMMUNITY MEETING 3 BLDG. FOOTPRINT 34

• Mass building in NE corner• Save trees • Integrate into nature• Courtyard open to nature• Engage park• Reduce scale of offices

from park• Centralized main entry• Maximize connectivity• Foster community• Accessible design

Page 35: Lubber Run Community Center - arlingtonva.us

COMPACTED CONCEPT DESIGN FOOTPRINT

• Remove north gym storage

35

Page 36: Lubber Run Community Center - arlingtonva.us

• Remove north gym storage• Shorten forest wing and

angle to open up courtyard

36COMPACTED CONCEPT DESIGN FOOTPRINT

Page 37: Lubber Run Community Center - arlingtonva.us

• Remove north gym storage• Shorten forest wing and

angle to open up courtyard• Shift building north to

increase park space

37COMPACTED CONCEPT DESIGN FOOTPRINT

Page 38: Lubber Run Community Center - arlingtonva.us

• Remove north gym storage• Shorten forest wing and

angle to open up courtyard• Shift building north to

increase park space• Reduce size of PV roof

38COMPACTED CONCEPT DESIGN FOOTPRINT

Page 39: Lubber Run Community Center - arlingtonva.us

SITE OVERLAY - CURRENT DESIGN 39

N

Page 40: Lubber Run Community Center - arlingtonva.us

BUILDING DIAGRAM – CURRENT DESIGN 40

PARKING UNDER GREEN ROOF

BUILDING UNDER GREEN ROOF

BUILDING

N

Page 41: Lubber Run Community Center - arlingtonva.us

SITE DIAGRAM – AREAS 41

N

Page 42: Lubber Run Community Center - arlingtonva.us

SITE DIAGRAM – AREAS 42

N

Page 43: Lubber Run Community Center - arlingtonva.us

SITE AREAS 43

EXISTING CONCEPT DESIGN

SURFACE PARKING 46,140 sf 0 sf

PLAYGROUND 7,265 sf 9,508 sf

OUTDOOR COURTS 3,863 sf 10,505 sf

CASUAL USE PARK SPACE 34,055 sf 59,637 sf

(partially park on structure)

COVERED OUTDOOR SPACE 250 sf 4,230 sf

Page 44: Lubber Run Community Center - arlingtonva.us

FINAL CONCEPT DESIGN 44

Page 45: Lubber Run Community Center - arlingtonva.us

EXTERIOR ANIMATION 45

Page 46: Lubber Run Community Center - arlingtonva.us

CONCEPT DESIGN PLANS – COURTYARD LEVEL 46

Page 47: Lubber Run Community Center - arlingtonva.us

CONCEPT PLANS – PARK LEVEL 47

Page 48: Lubber Run Community Center - arlingtonva.us

EAST/WEST SECTION 48

Page 49: Lubber Run Community Center - arlingtonva.us

NORTH/SOUTH SECTION 49

Page 50: Lubber Run Community Center - arlingtonva.us

NORTH/SOUTH SECTION 50

Page 51: Lubber Run Community Center - arlingtonva.us

INTERIOR ANIMATION 51

TO BE UPDATED

Page 52: Lubber Run Community Center - arlingtonva.us

• Net Zero Feasibility (underway)• Traffic (completed – under review w/ County Traffic

Engineering & Operations)• Parking (completed – under review w/ County Traffic

Engineering & Operations)• Tree Survey (completed)• Site Survey (completed)• Geotechnical (completed)

Studies

STUDIES STATUS

52

52

Page 53: Lubber Run Community Center - arlingtonva.us

NEXT STEPS 53

• Interior and exterior materials will be finalized with CMAR input• Indoor running track• Extent of sustainable design elements• Final traffic measures will be finalized with DES input

COUNTY BOARD DIRECTION:

ITEMS PENDING:

“A majority of Board members had concerns about the lack of clarity in the final stages of the public engagement process,” Fisette said. “We felt we needed to delay official endorsement of this scheme for our new Lubber Run Community Center until our September meeting, to give the public and the appropriate commissions a chance to weigh-in on it and propose refinements within the current massing scheme.” In voting for the delay, the Board majority emphasized that the additional review by the public and commissions are not intended to produce “fundamental changes” to the concept design.

Page 54: Lubber Run Community Center - arlingtonva.us

Q + A

FINAL BUILDING CONCEPT DESIGN Q+A

54

Page 55: Lubber Run Community Center - arlingtonva.us

PARK DESIGN FROM MEETING #3

What we Heard

• Concern for quality of park where constructed over garage and building.

• Concern about proximity of courts to adjacent residences.

• Concern that size of proposed playground is smaller than existing playground.

• Concern that boardwalk installation will negatively impact existing trees and necessitate tree removals.

55

Page 56: Lubber Run Community Center - arlingtonva.us

PARKS CONSTRUCTED OVER BUILDING STRUCTURES

Lurie Garden - Millennium Park, ChicagoGreat Lawn - Millennium Park, Chicago

Maggie Daley Park - Millennium Park, Chicago

What we Heard

• Concern for quality of park where constructed over garage and building.

Freeway ParkSeattle, WA

Constructed 1976

Klyde Warren Park - Dallas, TX

56

Page 57: Lubber Run Community Center - arlingtonva.us

PARK DESIGN DIAGRAM

LUBBER RUN NATURE LAWN COURTS STREET

PASSIVE ACTIVE

57

Page 58: Lubber Run Community Center - arlingtonva.us

PROPOSED PARK DESIGN 58

Page 59: Lubber Run Community Center - arlingtonva.us

PARK DESIGN Diagram

What we Heard

• Concern about proximity of courts to adjacent residences.

59

Page 60: Lubber Run Community Center - arlingtonva.us

SITE SECTION ACourtsEarth Mound3rd Street Entry Courtyard

GarageEntry

60

Page 61: Lubber Run Community Center - arlingtonva.us

PARK GRADES

+ 265PARK LEVEL

+249

+220

+258

+264+265

+261

+226

+232

+257COURTYARD LEVEL

+251COURTYARD LEVEL

251+

+255

+272

+256

+250

+238

61

Page 62: Lubber Run Community Center - arlingtonva.us

EXISTING TREES

Current Scheme removes: 109 Trees(shown in red)

Schemes from Community Meeting #2 removed between 70 – 161 trees

Total trees surveyed on site: 469

62

Page 63: Lubber Run Community Center - arlingtonva.us

PROPOSED NEW TREES

Trees to be Removed: 109 Trees

Proposed New Trees: 125 trees

63

Page 64: Lubber Run Community Center - arlingtonva.us

PARK LIGHTING

New Street Lights Arlington Standard

Bollard Lights

Court Lights

64

Page 65: Lubber Run Community Center - arlingtonva.us

0.15 miles

0.25 miles

0.2 miles

0.35 miles

PARK WALKING LOOPS 65

Page 66: Lubber Run Community Center - arlingtonva.us

PROPOSED PARK DESIGN

Boardwalk

CourtyardTerrace

EntryTerrace

Park Pathways

66

Page 67: Lubber Run Community Center - arlingtonva.us

PROPOSED PARK DESIGN

Park Pathways

Stabilized Aggregate PavingPorous Pavers

Exposed Aggregate Concrete

Asphalt Paving

Concrete Paving

67

Page 68: Lubber Run Community Center - arlingtonva.us

PROPOSED PARK DESIGN

Concrete Pavers Brick PaversAsphalt PaversStone Pavers

Brick Paver Blend

Terrace Pavement(pavers)

68

Page 69: Lubber Run Community Center - arlingtonva.us

PARK BOARDWALKS and Lubber Run Stair

Boardwalk LayoutZig-zag between trees

Norwell Bike Trail -Norwell, MA

Helical pier supports

What we Heard

• Concern that boardwalk installation will negatively impact existing trees and necessitate tree removals.

Rocky Run ParkArlington, VA

Construction MethodologiesHand constructionNon-invasive foundations

69

Page 70: Lubber Run Community Center - arlingtonva.us

MULTIPURPOSE COURT

Multi-Purpose surface

Multi-Purpose Court - Game StripingBasketball - Pickleball - Hockey/Futsal - Fulbito

70

Page 71: Lubber Run Community Center - arlingtonva.us

PARK SEATING 71

Page 72: Lubber Run Community Center - arlingtonva.us

PARK SEATING

Park Bench Seating• bench with back• wood seats with metal frame• all metal

72

Page 73: Lubber Run Community Center - arlingtonva.us

PARK SEATING

Lounge Seating

Lounge Seating• Comfort• Relaxation

73

Page 74: Lubber Run Community Center - arlingtonva.us

PARK SEATING

Picnic Tables

Tables & Chairs

Picnic Tables

Tables & Chairs

74

Page 75: Lubber Run Community Center - arlingtonva.us

PARK SEATING

Sloped Lawn Seating

Seat Walls

SlopedLawn Seating

SlopedLawn Seating

Seat Walls

Seat Walls

75

Page 76: Lubber Run Community Center - arlingtonva.us

CENTRAL LAWN – POTENTIAL CASUAL USE ACTIVITIES

Croquet Badminton Lawn Volleyball Frisbee

Bocce

Pitch & Catch

Relax

76

Page 77: Lubber Run Community Center - arlingtonva.us

CENTRAL LAWN – POTENTIAL SPECIAL EVENTS

Imagination Play EventGames Day on the Lawn

Movie Night on the Lawn

77

Page 78: Lubber Run Community Center - arlingtonva.us

WEST WING LAWN 78

Page 79: Lubber Run Community Center - arlingtonva.us

WEST WING LAWN – POTENTIAL PROGRAMMING

Yoga Classes

Boot Camp ClassesSenior / Youth GardenOutdoor Classroom

79

Page 80: Lubber Run Community Center - arlingtonva.us

EXISTING PLAYGROUND

Existing Play Elements

• Toddler & Single Swings

• 4 ft. slides and 2 ft. slide

• Climbers

• Playhouses

• Rockers

• Sand, mulch, and synthetic surfaces

80

Page 81: Lubber Run Community Center - arlingtonva.us

PLAYGROUND SIZE

Existing Playground7,267 s.f.

Proposed Playground 9,648 s.f.

What we Heard

• Concern that size of proposed playground is smaller than existing playground.

Natural Elements not included

81

Page 82: Lubber Run Community Center - arlingtonva.us

PLAYGROUND – Proximity to Relevant Facilities

Courtyard-Level Restroom

Park-Level Restroom

Preschool Room at Courtyard Level

82

Page 83: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

What We Heard

Playground Character• Natural Character

Play Elements• Natural Elements• Climbable Elements• Earth Mounds

• Tree House/Tower• Swings

83

Page 84: Lubber Run Community Center - arlingtonva.us

PARK PLAY

TotsOlderKids

NaturalElements

SwingsSeatingPavilion

Lawn Play

Court Play

84

Page 85: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN – Option 1

Tots OlderKids

NaturalElement

Swings

SeatingPavilion

85

Page 86: Lubber Run Community Center - arlingtonva.us

PlayMound

HillSecretPaths

Climbing Tower

Net Structure

Play Seating

Park PavilionShaded Seating

TreeLogs

PicnicTables

Bench Seating

4’ Hill Slide

Tots’ Play Wall & Play Cubes

PLAYGROUND DESIGN – Option 1 86

Page 87: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

Net Structure

87

Page 88: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

Climbing Tower(provides garage ventilation)

Insp

iratio

n

88

Page 89: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

Swings• two toddler swings• four swings for older kids• one group swing

89

Page 90: Lubber Run Community Center - arlingtonva.us

PLAYGROUND SIZE

Hill Slide

90

Page 91: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

NaturalElements

Existing Play Tree

91

Page 92: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN Toddler Play

INSPIRATION

Play Mound‘King of the Hill’

Scurry up the Hill

Park PavilionShaded Seating

Secret Paths through

the Garden

92

Page 93: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN

Play WallCustom – similar to image

Play CubeCustom – smaller than image

INS

PIR

ATIO

N

Toddler Play 93

Page 94: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN – Option 2

Tots

OlderKids

NaturalElements

GroupSwings

Tots

HillSlide

94

Page 95: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN – Option 2

15’ Hill Slide

Climbing Tower

Net Structure

Play Seating

Park PavilionShaded Seating

GroupSwings

Tree Logs

Bench Seating

Play Platform

Tots’ Play Wall & Play Cubes

+51

95

Page 96: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN – Option 3

OlderKids

NaturalElements

GroupSwings

Tots

HillSlides

NaturalElements

96

Page 97: Lubber Run Community Center - arlingtonva.us

PLAYGROUND DESIGN – Option 3

Climbing TowerNet Structure

Park PavilionShaded Seating

GroupSwings

Play Tree Logs

Bench Seating

4’ Hill Slide

Tot Play

+51

9’ Hill Slide

97

Page 98: Lubber Run Community Center - arlingtonva.us

PLAYGROUND SIZE1 2 3

Swings

Swings

Swings

TotsMound

15’ Hill Slide 9’ Hill Slideand

4’ Hill Slide

NetClimber

NetClimber

NetClimber

98

Page 99: Lubber Run Community Center - arlingtonva.us

PARK Q + A 99

Page 100: Lubber Run Community Center - arlingtonva.us

BREAK TO INFORMATION STATIONS

100

Page 101: Lubber Run Community Center - arlingtonva.us

NEXT STEPS 101

Page 102: Lubber Run Community Center - arlingtonva.us

NEXT STEPS

Thank you for Coming!

UPCOMING ENGAGMENT OPPORTUNTIES :

THURSDAY, JULY 276 pm - SITE WALKTHROUGH WITH VMDO – Lubber Run Community Center 7 pm - PFRC MEETING– Lubber Run Community Center

https://parks.arlingtonva.us/; search Lubber Run Project

102