lonmin plc morgan stanley basic metals conference 2005 · cost per pgm ounce before by product...
TRANSCRIPT
Lonmin Plc FINAL RESULTS 2006
Final Results - 2006
2
Lonmin Strategy
• Capture and build growth to supply robust market demand for PGMs
• Create a culture of safe production, operational excellence and innovation
• Focus on the long term sustainability of communities impacted by our operations
Final Results - 2006
3
Highlights
• Record EBIT of US$842 million up 141% and underlying EPS up 163% to 312.1 cents
• Record mine production and sales
• Marikana C1 costs of own production net of by product credits of R2,441 up 8.8%
• Limpopo C1 costs per PGM ounce in concentrate of R3,891 down 5.1%
• Six Sigma programme continues to deliver with R330 million of net EBIT benefit
• First Platinum major to successfully convert old order mining rights
• Full year dividend increased by 39% to US$1.00 per share (final dividend 55 cents)
Acquisition of AfriOre
Final Results - 2006
5
Acquisition of AfriOre
•AfriOre core asset is 74% of Akanani PGM deposit
•Entered into binding agreement with AfriOre under which the Board of AfriOre agrees to support and recommend a cash offer by Lonmin for AfriOre at C$8.75 per share
•Definitive agreement subject to
• Satisfactory due diligence
• Regulatory approvals
• AfriOre shareholder approval
•Offer values AfriOre at US$441 million
•Current Timetable
• Complete due diligence – December 2006
• Complete offer – January 2007
•Finance through existing debt facilities
Final Results - 2006
6
Akanani Project Location
Lonmin Operations and Projects
Limpopo
Marikana
NorthamAmandelbult
Union
Crocodile River
Pretoria
RustenburgImpala
Bafokeng - Rasimone
Waterval
Blue Ridge
Marula
Kennedy’s Vale
Der BrochenSheba’s Ridge
PPRust
Kroondal
BooysendalEverest SouthTwo Rivers
Modikwa
Twickenham
Paschaskraal
Lebowa
Loskop
Pandora
Millennium
Mphatlele
Grootboom
Pilanesburg
Akanani
N 0 100 km
Final Results - 2006
7
Project Resources
Akanani Mineral Holdings
Platreef Outcrop
Fault
Drill Hole in Progress
Drill Hole Complete,
Proposed Drill Hole
LEGEND
INFERRED RESOURCE ESTIMATE*(September 2006)
800 to 2,000 metres - P2 Unit of the SPAWidth Tonnes 3PGM+Au Ni Cu(m) (Mt) (g/t) M.oz (%) (%)
19.0 249.1 4.2 33.7 0.24 0.14
*Source: Snowden Mining Industry Consultants
INFERRED RESOURCE
AREA
Amplats PPRustOperations
Grades:Platinum – 1.8 g/tPalladium – 2.0 g/tRhodium – 0.2 g/tGold – 0.2 g/t3PGE+Au – 4.2 g/t
Final Results - 2006
8
Lonmin Conceptual Project
•Low cost mechanised mine producing 250,000 ounces Platinum and 500,000 ounces total PGMs per annum
•Approximately 5 million tonnes hoisted per annum
•Estimated workforce of 1,500
•First production targeted for 2013
•Initial estimates of around US$600 to 700 million of attributable capital for mine and concentrator
•26% BEE owned - new order prospecting rights granted in June 2006
•2 year feasibility and engineering study at cost of around US$25 million per year
Operations
Final Results - 2006
10
0
5
10
15
20
25
2003 2004 2005 2006 20070
2
4
6
8
10
12
14
16
18
20
LTIF Severity Rate
Marikana
Industrial Fatalities
2003 12
2004 8
2005 6
2006 4
Safety – Significant Improvement
LTIF
R p
er m
illion
man
hou
rs w
orke
d
Target
Severity R
ate (Days)
Note – 2 industrial fatalitiesat Limpopo in 2006
Final Results - 2006
11
0
24
6
8
1012
14
16
2004 2005 2006 2007
Underground Opencast
0
200
400
600
800
1000
1200
1400
1600
2005 2006 2007
FORECAST
Limpopo Production (Tonnes Mined Thousands)
FORECAST
NB includes Pandora JV tonnes
Record Mine Production
Marikana Production (Tonnes Mined Million)
Final Results - 2006
12
Process Division
• Planned Smelter rebuild in February completed in record 27 days at cost of US$8 million
• 11 day Smelter shutdown in April to repair leak
• PMR fire in September
• PMR refined production of 1.4 million ounces of total PGMs
• Smelter outages and reduced throughput had significant impact on Process Division unit costs (R80 per PGM ounce sold)
Final Results - 2006
13
New Generation Platinum Mines
.
• Mechanisation and Automation
• Safe Production
• Integrated logistics and maintenance planning systems
• Teamwork
• Employee friendly facilities
Final Results - 2006
14
New Generation Platinum Mine Development
Tonn
es H
oist
ed (‘
000)U
S$ m
0
2000
4000
6000
8000
10000
12000
14000
2006 2007 2008 2009 2010 2011 20120
20
40
60
80
100
120
140
160
180
200
Hossy Saffy K4 Rowland ARM Other ULP mechanisation DDT jigs/hybrid methods Limpopo Capex
11.9 million tonnesTotal capex spend - US$490 million
Final Results - 2006
15
Modern Mining Methods
.
Final Results - 2006
16
Increased Productivity and Lower Costs
Ran
d pe
r ton
neA
verage tonnes per person
CONVENTIONAL
180.0
190.0
200.0
210.0
220.0
230.0
240.0
250.0
260.0
270.0
280.0
2006 2007 2008 2009 2010 2011 20120
50
100
150
200
250
Average tonnes per underground employee - mechanised Rand cost per tonne
Financial Results
John RobinsonFinance Director
Final Results - 2006
18
Summary of Operating Results
12 months to30 Sept 2006
US$m
12 months to30 Sept 2005
US$m
Revenue 1,855 1,128
EBIT 842 350
Underlying EBIT 830 362
Underlying EBIT margin (%) 45% 32%
Profit before tax 633 319
Underlying profit before tax 827 339
Attributable profit 313 158
Basic EPS (cents) 219.5 111.5
Underlying attributable profit 445 168
Underlying EPS (cents) 312.1 118.5
Final Results - 2006
19
EBIT Variances
350 12 (22) 340 12
579 37 (126)
842
0
100
200
300
400
500
600
700
800
900
1,000
1,100
2005Reported
EBIT
2005Re-orgCosts
2005Smelter
Insurance
2005Base
2006HouseSales
2006Price
2006Volume
2006Costs
2006Reported
EBIT
$m
Final Results - 2006
20
Cost Analysis
Voluntary total $48m
Involuntary total $61m26
14 8
59
18 7
8 6 (37)
17 126
0
20
40
60
80
100
120
140
160
SHEC Exploration& Tech Dev
Changeof
CostingBasis
Inflation /Other Costs
EmployeeBenefitsStructure
ProcessDivision
Pyromets
ProcessDivision
New Plant
Royalties ForeignExchange
Impact
Dep'n Total
$m
Final Results - 2006
21
Cost per PGM Ounce Sold
12 months to 30 Sept 06
Rand per ounce sold
12 months to 30 Sept 05
Rand per ounce sold
Variance%
Marikana:MiningProcess Division (including smelter re-build)Shared Business ServicesMovement in physical stock
2,030384460(33)
1,889261347(11)
Cost per PGM ounce before by product creditsBase metal credits
2,841(400)
2,486(243)
14.3%
C1 cost per PGM ounce sold net of by product creditsAmortisationOther items
2,441227
-
2,243253(28)
8.8%
C2 cost per PGM ounce sold own production 2,668 2,468 8.1%
Limpopo:C1 costs per PGM ounce sold net of by product credits 3,891 4,102 (5.1)%
Final Results - 2006
22
Free Cash Generated
12 months to30 Sept 2006
US$m
12 months to30 Sept 2005
US$m
Operating Profit 842 350
Working Capital - Debtors- Other
Depreciation and other items
(249)4782
(22)(22)
71
Net cash inflow from operating activitiesInterest and finance costsTax paid
722(31)
(185)
377(27)(79)
Trading cash flowCapital expenditureProceeds from asset held for saleAssociate dividend received Minority dividends paid
506(182)
28-
(62)
271(190)
-2
(27)
Free cash flow 290 56
Trading cash flow per share (cents)Free cash flow per share (cents)
354.9c203.4c
191.2c39.5c
Final Results - 2006
23
Free Cash Utilised
12 months toSept 2006
US$m
12 months toSept 2005
US$m
Free cash flow
Acquisition of subsidiary/minority interest
Purchase of other financial assets
Dividends paid to Lonmin shareholders
Issue of ordinary share capital
290
(14)
(36)
(124)
15
56
(212)
1
(102)
6
Decrease/(increase) in net debt
Opening net debt
Effect of exchange rate changes
Net borrowings in subsidiaries acquired
131
(585)
(4)
-
(251)
(272)
(2)
(60)
Closing net debt (458) (585)
Final Results - 2006
24
Balance Sheet Summary
30 September2006
US$m
30 September2005
US$m
Equity
Minority
Net debt
Gearing
1,089
223
458
27%
838
166
585
41%
Final Results - 2006
25
Pro-forma Debt Estimate
12 months to30 Sept 2006
US$m
Net debt as at 30 September 2006 458
Convertible bond (216)
242
Abnormal debtors (200)
42
AfriOre 441
Pro-forma net debt 483
Markets
Ian FarmerChief Strategic Officer
Final Results - 2006
27
PGM Market Overview
• Market in fundamental deficit for 6 years• Underpinned by legislated autocatalyst
demand• Jewellery demand keeps tension on price• Demand growth at circa 5% CAGR through
2010• Few mine expansion opportunities globally
• Market continues in surplus• Scope for demand growth
Palladium
Platinum
• Niche illiquid market• > 90% autocat demand• Demand forecast to grow
Rhodium
California Dreamin’
Final Results - 2006
28
Evolution of Pt Demand - 1995 to 2010
0
1000
2000
3000
4000
5000
6000
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
000'
s ozs
Autocat Jewellery Industrial
Price Pivot onAutocat focus
Jewellery absorbsMarket surplus
Diesel momentumReinforces industrialemphasis (5% p.a. CAGR)
Final Results - 2006
29
Medium-Term Supply Considerations
• SA (and Zimbabwe) recognised as the principal sources of new mine supply
• Challenging economics of new and replacement mines/expansions (higher capex, costs and lead times)
• SA social & licensing implications
• Inducement price of at least US$1000 per Platinum ounce is required to bring on new 20 year life of mine production
• Smelting capacity constraints may limit ‘Junior’ project development in the long term
Project (new entry) Based Pt Price
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
$2,000
R 5.000 R 6.000 R 7.000 R 8.000 R 9.000
Exchange Rate
USD
/ oz
P
West limb East limb Shallow East limb Deap
Final Results - 2006
30
Platinum Potential Scenarios - 2010
+ Supply
Demand
+Industrial demanddominates
-
-
Tug of war
Jewellery demanddominates Supply shrinks
2000
2005
1995
2010?
DEMAND > SUPPLY
DEMAND > SUPPLY
DEMAND = SUPPLY
DEMAND < SUPPLYGrowth of Jewellery
Market
Brownfields low cost supply
expansion and rapid growth of
autocatalyst market
Expensive new capacity
required to meet demand growth
Building Growth
Brad MillsChief Executive Officer
Final Results - 2006
32
800
850
900
950
1000
1050
1100
2005 2006 2007 2008 2009 2010 2011 20120
50
100
150
200
250
300
Marikana Base Profile Pt oz (000) Limpopo Phase 1 Pt oz (000) Marikana base capex US$m Marikana and Limpopo base capex US$m
Base Profile
100% Marikana and Limpopo production and capex numbers in today’s money to take the Platinum production to a sustainable 1 million ounces from Marikana and 75,000 ounces from Limpopo
Plat
inum
oun
ces
(000
’s)
Capital spend (U
S$ m)
Final Results - 2006
33
0
20
40
60
80
100
120
140
160
180
200
2007 2008 2009 2010 2011 20120
20
40
60
80
100
120
140
Marikana Growth Pt oz (000) Limpopo Phase 1 Growth Pt oz (000)Marikana Growth Capex (07 money) US$m Limpopo growth phase 1 capex (07 money) US$m
Plat
inum
oun
ces
(000
’s)
Capital expenditure (U
S$ m
)
Marikana and Limpopo Growth Profile
MARIKANAGrowth – 175,000 Pt oz paTotal capex spend - US$250 millionLIMPOPOGrowth – 12,000 Pt oz paTotal capex spend - US$27 million
Final Results - 2006
34
Metallurgical Expansion to 1.4m Ounces
Capital expenditure (U
S$ m
)Pl
atin
um o
unce
s (0
00’s
)
0
50
100
150
200
250
300
350
400
450
2005 2006 2007 2008 2009 2010 2011 20120
10
20
30
40
50
60
70
80
Metallurgical Capacity Growth Pt oz (000) Metallurgical Expansion Capex (07 money) US$m Metallurgical Sustaining Capex (07 money) US$m
Capacity Growth – 400,000 Pt oz paTotal capex spend - US$148 million
Final Results - 2006
35
800
850
900
950
1000
1050
1100
1150
1200
1250
1300
2005 2006 2007 2008 2009 2010 2011 20120
50
100
150
200
250
300
350
400
Marikana Base Profile Pt oz (000) Limpopo Phase 1 Base Pt oz (000) Marikana Growth Pt oz (000)Limpopo Phase 1 Growth Pt oz (000) Sustaining Capex US$m Total Committed Capex US$m
Committed Growth Profile
Growth – 300,000 Platinum oz paTotal growth capex - US$830 mSustaining capex – US$112m pa
Final Results - 2006
36
Growth Projects
• Expect to completing pre-feasibility studies on Limpopo phase 2 and Pandora by end
March 2007
• Limpopo 2
• Lonmin effective interest 75%
• Currently estimate in 2011 at full production will add around 93,000 Platinum ounces
per annum to Lonmin account
• Pandora
• Lonmin interest 42.5% and manager of project
• Currently estimate in 2012 at full production will add around 55,000 Platinum ounces
per annum to Lonmin account
• Capital estimates for these projects will be released at the completion of the pre-feasibility
tollgate and approval to commence full feasibility
Final Results - 2006
37
Production Growth Profile
Plat
inum
oun
ces
(000
’s)
Committed Projects and Pre-feasibility Projects
800
850
900
950
1000
1050
1100
1150
1200
1250
1300
1350
1400
1450
2005 2006 2007 2008 2009 2010 2011 2012
Marikana Base Profile Pt oz (000) Limpopo Phase 1 Pt oz (000) Marikana Growth Pt oz (000)Limpopo Phase 1 Growth Pt oz (000) Limpopo Phase 2 (attributable) Pt oz (000) Pandora (attributable) Pt oz (000)
Final Results - 2006
38
Opportunity Capture and Value Creation
NPV
Time
CAPTURE & DISCOVER BUILD OPERATE
EXPLORATIONLoskopSudbury
LuwumbuMibango
Monts de Cristal
Platmin(22%) Southern
Platinum
IncwalaImpala buyoutAfriOre
Exploration risk Development risk Operations risk
A Unique Investment
Final Results - 2006
40
Unique Commodity Sector
• Strong Medium and Longer term market fundamentals
• Current demand underpinned by EU and US Clean Air legislation
• Longer term demand underpinned by the rapidly growing global middle class’s demand for PGM related products
• clean fuel efficient cars
• flat screen TVs
• hard disk drives for computers
• energy (petroleum catalysis and fuel cells)
• Platinum jewellery
• Supply growth fundamentally constrained by scarcity of resources and technical barriers to entry into the business
• Consolidated industry with 3 major primary producers
Final Results - 2006
41
Lonmin - A Unique Investment Choice
• Capture and build strong growth to supply robust market demand for PGMs• Targeting growth to 1.4 million ounces in 2012
• Developing options to grow to 2 million ounces Platinum per annum
• High quality investment and exploration portfolio
• Create a culture of safe production, operational excellence and innovation• Commitment to safe production – DuPont training, Fatal risk protocols, ICAMs
• Maintain and improve our low cost position – Six Sigma and Shared Business Services
• Create a new generation of Platinum mines – mechanisation, Sandvik partnership
• Employee alignment – New Era Labour Agreement, Gainshare programme
• Focus on the long term sustainability of communities impacted by our operations• New Order Mining Licence, ICMM standards, Social and Labour Plans
Appendix
Final Results - 2006
43
2007 Targets
• Production of around 1.02 to 1.04 million saleable ounces of Platinum
• C1 cost of own production at Marikana per PGM ounce sold of around R2,450 to R2,500 net of by product credits
• C1 cost per ounce in concentrate for Limpopo of around R3,000 to R3,250 per PGM ounce
• Capital expenditure expected to be around US$370 million
• Exploration spend of around US$20 million
• Additional net EBIT benefit from Six Sigma programme of R400 million
• Start up of mechanised stoping at both Hossy and Saffy shafts
Final Results - 2006
44
C1 and C2 Costs
C1Cash operating costs per Platinum Group Metal ounce sold for own production, including mining, smelting and refining, shared services (including overheads), net of by product credits
C2C1 costs plus non recurring cash costs, one off accounting refinements, amortisation and other non cash items
Limpopo C1
Cash operating costs per saleable Platinum Group Metal ounce contained in concentrate, including mining and shared services
Marikana
Final Results - 2006
45
EBIT Reconciliation
2006 2005$m $m
Revenue from C1 / C2 Refined PGM metal sales 1,229 954
C1 / C2 Ounces (m) 1.3 1.5C2 cost (Rand / ounce) 2,668 2,468Total C2 cost (Rand m) 3,423 3,683
6.48 6.28 Total C2 cost ($m) (528) (586)
C1 / C2 refined metal sales EBIT 701 368
Net contribution from concentrate / toll sales / other 176 17
877 385
Final Results - 2006
46
Green Legislation Penetration 2006 - 2010
17
3
Euro 3 or equivalent or less
Euro 4 or equivalent
Euro 5 or equivalent or greater
16
2
2219
2 3
3
106
10 11
2
Autocat PGM Demand1995-2010
The chart on the left shows evolvingemissions standards across theworld and the figures in each circlerepresent millions of vehicles sold
0
1000
2000
3000
4000
5000
6000
'000
ozs
1995 1997 1999 2001 2003 2005 2007 2009
Platinum Palladium RhodiumSource: Lonmin
Final Results - 2006
47
Autocatalyst Demand
•Driven by globally legislated emissions controls- progressively broader and tighter
• Diesel is the PLATINUM story- 50% of Pt autocat demand- 9% growth 2004 on 2005, 17% growth in EU- Diesel Loadings : EU 8g Pt; initial US
10-15g Pt vs. Petrol 1g Pt & 4g Pd- 50% of car sales in Europe are diesel- US fuel purity improved 2006- BMW/Ford launch high performance diesel
in the US- Current US diesel 4% vs EU 50%, increase
to 10% creates 300k oz. Pt.- Trucks being legislated (US : 2006)
: - Off road/marine diesels to follow post 2010(similar market size to on road)
- Global roll-out of US/EU standards
0.000.200.400.600.801.001.201.401.601.802.00
'94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10
g/bh
p ho
ur
US Heavy Diesel
Emission Legislation
Final Results - 2006
48
Platinum Outlook Beyond 2010
0
100
200
300
400
500
2000 2005 2010 2015 2020 2025 2030 2035 2040
China
India
UnitedStates
29
21
55
Per 100peoplein 2040
Source: Economist/Goldman Sachs
Forecasts of car ownership, m
Final Results - 2006
49
Platinum Outlook Beyond 2010
Middle-class bulgeChinese urban households by annual income
% of total
Source : McKinsey0%
20%
40%
60%
80%
100%
1985 1995 2005 2015* 2025*
Poor Lower-middle class Upper-middle class Mass affluent Global affluent
* Forecasts
66 109 191 280 373Urban households, m
Final Results - 2006
50
Disclaimer
•This presentation, which is personal to the recipient and has been issued by Lonmin, comprises slides for a presentation in relation to the proposed recommended acquisition of AfriOre by Lonmin, and is solely for use at such presentation.•This presentation includes forward-looking statements. Information contained in this presentation relating to AfriOre has been compiled from public sources. All statements other than statements of historical fact included in this announcement, including without limitation those regarding Lonmin's plans, objectives and expected performance, are forward-looking statements. Lonmin has based these forward-looking statements on its current expectations and projections about future events, including numerous assumptions regarding its present and future business strategies, operations, and the environment in which it will operate in the future. •Forward-looking statements generally can be identified by the use of forward-looking terminology such as 'ambition', 'may', 'will', 'could', 'would', 'expect', 'intend', 'estimate', 'anticipate', 'believe', 'plan', 'seek' or 'continue', or negative forms or variations of similar terminology. Such forward-looking statements involve known and unknown risks, uncertainties, assumptions and other factors related to Lonmin, including, among other factors: (1) the risk that the businesses of Lonmin and AfriOre will not be integrated successfully; (2) material adverse changes in economic conditions generally or in relevant markets or industries in particular; (3) fluctuations in demand and pricing in the mineral resource industry and fluctuations in exchange rates; (4) future regulatory and legislative actions and conditions affecting Lonmin's and AfriOre's operating areas; (5) obtaining and retaining skilled workers and key executives; and (6) acts of war and terrorism. •By their nature, forward-looking statements involve risks, uncertainties and assumptions and many relate to factors which are beyond Lonmin's control, such as future market conditions and the behaviour of other market participants. Actual results may differ materially from those expressed in forward-looking statements. Given these risks, uncertainties, and assumptions, you are cautioned not to put undue reliance on any forward-looking statements. In addition, the inclusion of such forward-looking statements should under no circumstances be regarded as a representation by Lonmin that Lonmin will achieve any results set out in such statements or that the underlying assumptions used will in fact be the case. •Other than as required by applicable law or the applicable rules of any exchange on which Lonmin's securities may be listed, Lonmin has no intention or obligation to update or revise any forward-looking statements included in this presentation after the publication of this presentation.•This presentation is for information only and does not constitute or form part of any offer or invitation to sell, or any solicitation of any offer to purchase, any shares in AfriOre or Lonmin or any other securities, nor shall it or any part of it nor the fact of its distribution form the basis of, or be relied upon in connection with, any contract or investment decision related thereto.