LNG Calibration Facility
Metrology for LNG workshop
19th May 2015, Brøndby, Denmark
Oswin Kerkhof (VSL), Marina Safonova (IMS Group)
Contents
Part I (Oswin Kerkhof, VSL)
• LNG Calibration Facility (flow and composition)
• Background
• Research goals
• Functional & Metrological Design Requirements
Part II (Marina Safonova, IMS Group)
• Engineering and Fabrication capabilities
• Process Description
A three step approach
Primary Standard
Completed,
EMRP project
Mid-scale standard
Sufficient for Small Scale LNG
Project in progress
Full scale facilities
Building traceability for LNG flow metering
5 - 25 m3/h
40 – 200 kg/min
5 – 200/400 m3/h
40 – 1600/3200 kg/min
200 - 4000 m3/h
FLOW MEASUREMENTS
1. Validating the uncertainty of flow standard
– Mass flow 40 - 1600 kg/min => Target uncertainty 0,15%*
– Volume flow 5 – 200 m3/h => Target uncertainty 0,20%*
* Requires further reducing measurement uncertainty of primary standard down to 0,10%
FLOW MEASUREMENTS
2. Investigate performance of at least two types of mass flow
and volume flow standards
– Readings as a function of flow, pressure, temperature
– Extrapolation functions (to what respect is a water calibration
representative for LNG use of a flow meter?)
– Installation effects (different flow profiles, near boiling conditions, …)
COMPOSITION MEASUREMENTS
• Validating the uncertainty of composition standard
– Cross validation with reference liquefier(s)
– Uncertainty target: 0,2% on calorific value
Design Requirements
FUNCTIONAL DESIGN REQUIREMENTS
METROLOGICAL DESIGN REQUIREMENTS
DESIGN STANDARDS
FLOW STANDARD
General
• Traceable to primary standard
• No boil-off, venting of methane to air minimized
Control parameters
• Flow Rate 5 – 200 m3/h (40 - 1600 kg/min)
Expandable to 400 m3/h
• Line pressure 1 – 10 barg(g)
• Temperature -123 to -175 °C (1 to 20 °C below boiling point)
• Composition Measurable (Mustang system), not controllable
FLOW STANDARD
Production performance
• Capacity 1 Meter under Test (MuT) per day
• Schedule of MuT 1 – 6” (expandable to 8”)
• US/DS piping 40D upstream, 8D downstream
• Calibration of two meters in series possible
• Types of MuT Coriolis, USM, Turbine, dP-type, Vortex and other
FLOW STANDARD
Metrological design rules
• LNG velocities are low to avoid flashing / bubbles.
• No double bends out of plane (swirl!), no straighteners (delta-P!)
• Temperature measurement at the position of flow meters
better than 0,1°C
• Smallest possible interconnected volumes to avoid in- and expiratory
effects during calibration time window
COMPOSITION STANDARD
• Special design sampler (subcooled conditions)
• Vaporization at conditions above critical pressure
• Gas Chromatograph
• Sampling flow rate at 7,5 ml/min (LNG) / 5 l/min (gas)
• Connectable to small volume reference LNG (liquefier system NPL and/or
Effectech)
• Connectable to LNG calibration loop
Sponsors and Project Partners
18
Engineering & Fabrication by
IMS Group
© IMS Group, LLP
IMS Group
Metrology Project Engineering and Management
Highly rated by FPAL/Achilles professional buyers community
Dedicated fabrication shops in UK & Russia
Support project life cycle from concept to Commissioning
Serve both onshore and offshore oil and gas sectors around the world
World-wide collaboration in measurement product development
ISO 9001, 14001 and 18001 accredited, VSL CMC Certified (prover calibration), NMI
Leading Metrology System
Integrator
© IMS Group, LLP
Core Services
Conceptual and Front End Engineering for all Core Products and related Sites
EPC (Engineer, Procure, Construct) Metering and Allocation Sites for Natural Gas, Crude Oil and Hydrocarbon Fuels
Technical Audits and Modernization of Fiscal Metering Systems, Pipeline Surge Protection and Water Hammer.
Maintenance of Field Metering and Automation Equipment including Central Control Systems
Metrological Services, including Calibration & Verification of Field Meters (P, T, Flow, Density, Viscosity), Approvals and Procedures
© IMS Group, LLP
OGS, Swansea, UK • 1200m² Carbon Steel Workshop
• 300m² Stainless Steel Workshop
• 2400m² Assembly Workshop
• 2, 3.2, 7.5, 8 & 20 tonne cranes
• Flow Calibration Rig: 1800m²/h
OGS, Ely, UK • 1000m² Assembly Workshop
• 250m² R & D Workshop
• Flow Characterisation Loop
• Multiphase Test Loop
• Assembly and Testing of Supervisory System Control Panels
• Assembly and Testing of Analyser Houses and Cabinets
• Assembly of USM, Helical Turbine Meters
Engineering and Fabrication
© IMS Group, LLP
• Territory: 3.0 hectare
• Location: Kaliningrad, Russia, Free Economic zone
• Office space: 1,670 sq. m.
• Workshop space: 8 500 sq. m.
• Warehouse: 900 sq.m., heated
• Certified NDT Laboratory
• ISO 9001:2008 certified
• Equipment:
3.5, 5, 12 & 20 ton overhead cranes
Flow calibration rig
Shot-blasting chamber
Painting chamber
Welding Equipment («ARGUS LIMITED»)
Fabrication OGSB Kaliningrad, Russia
Inspection & Testing
ALL Our FACTORIES perform the following Quality testing
• Visual Inspection
• Magnetic Particle Inspection
• Dye Penetration Inspection
• Positive Material Identification
• Radiographic Testing
• Ultrasonic Testing
• Hydrostatic testing
• Pneumatic testing
• Leak testing
• Paint inspections
• Flow testing
LNG Calibration Facility
Thank you for your attention