LISSON ARCHESENTERPRISE HUB – TECHSHOP OPTION29/01/14
LISSON ARCHESENtErpriSE HuB 24/11/15
2 LISSON ARCHES ENTERPRISE HUB
The following study explores the feasibility of introducing a mezzanine level into a section of the floor space of the enterprise hub. The hub forms part of a current proposal submitted to Westminster Council’s Planning Department in November 2012. The study was instructed by WCC on the 21st of January 2014 to review possible spatial requirements for a potential tenant and how additional floor space could be incorporated within the envelope.
The scope of the study is limited to plans at each level, long and short sections and a schedule of areas.
The following constraints should be noted:
1 Structure/MEP
Excluded from the study is an assessment of the structural and servicing implications of inserting a mezzanine level. This will require developing in order to clarify what headroom height within the mezzanine levels can be achieved. The floor-to-floor heights within the proposed mezzanine areas would be approximately 3.0metres. A structural solution to minimize floor build ups and any down stand beams will require reviewing at an early stage to clarify the viability of the resulting head room for the proposed uses.
2 Entrances/Servicing
Two principal access points have been included in the planning submitted drawings and are constrained by varying site levels on Lisson Gove and Bernhardt Crescent. The principal public and main entrance is off Lisson Grove at the southwestern end of the building with a further service access/secondary entrance provided to the rear off Bernhardt Crescent. It is not intended as part of this study to alter the position or level of these access points. A servicing and delivery bay area is already included in the proposal.
3 Internal circulation
The principal access stairs form ground floor to -2 levels have been re-configured slightly with an open accommodation stair included to link the intermediate levels of the mezzanine floors. There is an escape stair from the elderly housing above that is
retained and unaltered. Discussions with a major lift manufacturer have confirmed that a ‘through- lift’ with intermediate stops is available.
4 Elevation to Bernhardt Crescent
The short section highlights an area of floor that will need to be removed to allow the potential for a mezzanine level to be inserted. This will require changes to the elevation treatment to Bernhardt Crescent.
5 Fire safety
Escape distances need to be limited to 25 metres in one direction or 45 metres in two directions. These distances will need checking when the layout of the spaces is developed. On the mezzanine level the distance to the short section of stair is below 19 metres and then two alternative routes are available. The current layout is for a single tenant, the additional difficulties of one tenant passing through another tenancy would be negated. The sprinkler system designed into the residential spaces above is not necessary for the enterprise space but it is recommended that extending it to be considered, as the infrastructure will already be provided. If the enterprise space is not sprinkled, a two-hour fire rated compartment construction will be required. A fire engineer/building control officer will need to be consulted to verify that the arrangement being proposed is acceptable
LISSON ARCHESINTRODUCTION
3LISSON ARCHES ENTERPRISE HUB
The site is centrally located mid-way between Edgware Rd to the south, St Johns Wood Rd to the north west, Park Rd and Regents to the north east and Marylebone to the south. The amenities of Regents Park are close by and within a very connected public transport network that includes Marylebone train and tube station 5 minutes walk away from Lilestone St. The Regents Canal is only a few minutes walk from the Lisson Arches site to the north west.
This London site forms a part of a first phase of an overall plan (the Futures Plan) to improve the neighbourhood including; improvements to street and public landscaping, community facilities, growing arts and cultural scene, new space for start up business’s and to provide new private and affordable homes. The immediate area to the south of the sites benefits from an historic street market that is the commercial and social heart of this part of Westminster.
Rev. Date Description
Job Name
Title
Scale
Job No.
Revision
Status
Drawing No. Date.
unless noted
permitted and notify
before
in this document includes proprietary rights of mae. Any party in receipt of the document shall receive and hold the same in confidence and agrees not to duplicate or otherwise reproduce the document in whole or in part, nor disclose the contents of the same without the written consent of mae.
Lisson Grove1222
Proposed Site Plan
Pre-Planning
1222/00_PP100
1:500@A1
06.09.13 D
A 08.05.13 Site 1Building footprint reduced due to apartment size changing.
B 20.06.13 Redline Boundary Updated
C 15.07.13 Site 2Redline Boundary Updated
D 06.09.13 Site 2 - BUidling Footprint and lilestone site boundary altered following pre-app feedback
London Marylebone
Baker Street
Regent’s Park
Lord’s Cricket Ground
Marylebone Rd
St John’s W
ood Rd
A 41 Park Rd
Edgware Rd
Lisson Grove
Lisson Arches
Lilestone Street
Lilesto
ne Stre
et
Bernhardt Crescent
Jermone C
rescent
Church
Street
Luto
n Stre
et
Fram
pton
Stre
et
Rossmore
Road
Lisson Grove
Lisson Grove
LISSON ARCHESLOCATION
University of Westminster Architecture Department
4 LISSON ARCHES ENTERPRISE HUB
The Lisson arches site comprises mostly vacant land within the Church Street ward, and is bordered by Lisson Grove to the south and Bernhardt Crescent to the north. The topography of the land is downward sloping, with the gradient falling as you travel south east. The site currently includes both hard standing surfaces (parking bays, tarmac zones adjacent to the existing pavement and a paved access ramp) in addition to some soft (vegetated) surfaces.
View 2 taken along Lisson Grove at the junction of Church St shows the gable of Chequers house in the distance and Wycombe house to the right. The main bus stop is visible on Lisson Grove.
The site is a triangular piece of land and includes a gated ramp area ( redundant fire access ramp) on Lisson Grove and the area leading up to and including the former railway tunnel on Bernhardt Crescent. The site contains two disused railway/vehicular arches which are currently inaccessible and closed at the Capland ST end by a brick wall. There is a 900mm diameter live Thames Water main running across the site visible in view 3. This Water main at this point in Lisson Grove becomes exposed to avoid the shallow structural depth of the Bridge structure. The diversion of this main is being incorporated into the design of the lower ground floor levels. Belvedere heights( 9 storey’s) is visible across Lisson Grove.
Also clearly visible in view 3 is a pedestrian ramp linking Bernhardt crescent to Lisson Grove. Detailed reference to it’s usage and proposals for it’s replacement are covered in the transport assessment. An escape stair and integral refuse chute is visible to the gable end of Chequers. A turning head in the road visible to the right of the picture allows refuse and emergency vehicles access to the base of the stair tower. The proposals retain this current
Predominant land uses in the immediate vicinity includes residential of varying tenure, in addition to some social and community uses, currently found at Lilestone Street.
View 3 - Exisitng Lisson Arches Site looking from Wycombe House with existing water main pipe in the foreground, Chequers’ House to the right and Belvedere Heights in the background
View 1: Aerial view of exisitng Lisson Arches site View 2: Exisitng Lisson Arches Site looking from Church Street
Belevedere Heights
Chequers House
pedestrian ramp
water main
redundant road
disused railway tunnels
Lisson Grove
redundant fire access ramp
Jerome Crescent
view 2
view 3
LISSON ARCHESENtErpriSE HuB
5LISSON ARCHES ENTERPRISE HUB
Photograph of site model with Lisson Arches
Lisson Archess
Lisson GroveChurch Street
LISSON ARCHESENtErpriSE HuB
6 LISSON ARCHES ENTERPRISE HUB
This computer generated image taken from the south east illustrates the proposal on an Autumn day. Chequers House is visible behind the building with Wycombe House visible over the top of the trees. The placement of the enterprise entrance at this juncture on Lisson Grove provides activity on the street mid way between the new Health hub building and the new sheltered housing of Lisson Arches. Trees are retained at either end of the proposal with the planting on the residents roof terrace visible above the enterprise space parapet.
LISSON ARCHESENtErpriSE HuB
Perspective view looking north-west along Lisson Grove, with the enterprise entrance in the foreground
7LISSON ARCHES ENTERPRISE HUB
Perspective sketch looking along Bernhardt Crescent Perspective view looking south-east along Lisson Grove
LISSON ARCHESENtErpriSE HuB
This computer generated image is taken from the north west and shows the residential entrance to the apartments in the foreground with the residents’ terrace visible in the distance.
BB
AOV E M
FLUE RISER
DRY RISER
RWP
SVP
SVP
RWP
FLOOR DRAIN
FLOOR DRAIN
RWP
RWP
RWP RWP
B C D F G H I J K L M
0203
0405
0102
0304
05
B C D F G H I J K L M
01
A
A
E
E
A A
CC
BERNHARDT CRESCENT
JEROME CRESCENTGas meter room
UKPNSub-Statio
n
Telecoms/ BT
intake /Electricalswitchroo
m
Alternative Supply Switch Room
Refuse Storage Scooter and Bicycle Storage
Wall-mountedbike storage
UnisexBathroom
s
Plant room
UnisexShowers
Workshop AreaLower Ground -2
Access.WC
Entrancelobby
F F Lift14 P Capacity
EntranceLobby Workshop Area
Lower Ground -2 Mezzanine
Stair 03
Stair 05
Stair 02 Stair 04
Stair 01
Refusestorage
BB
Rev. Date DescriptionNOTES:1. Measurements are based on metric system2. All levels are in meters to Principal Datum (PD) unless noted otherwise3. Do not scale drawing4. Figure dimensions are to be followed5. Do not use for construction unless expressly permitted6. Contractor should verify all conditions on site and notify contract administrator of any variations from dimensions before constructionThe data contained in this document includes proprietary rights of mae. Any party in receipt of the document shall receive and hold the same in confidence and agrees not to duplicate or otherwise reproduce the document in whole or in part, nor disclose the contents of the same without the written consent of mae.
mæ LLP Architects1 Naoroji StreetLondon WC1X 0GBt: +44 (0)20 7704 6060f: +44 (0)20 7833 2473e: offi [email protected]
Title
Scale
Job No.
Status
1222
Information 1:100@A1
Proposed Lower Ground -2 - Enterprise
Drawn By
NWChecked By
NW
Client
Westminster City Council
Job Name
Lisson Arches
Date24.01.14
Drawing No.SK052
Revision
B
PROJECT NOTES1. This is a design intent drawing for information only and is not to be used for construction2. To be read in conjunction with general arrangement drawings and coordination with MEP,Civil/Structural and Landscape Stage D+ design tender packages3. Package is to D+ level of detail only, and is subject to further detailed design development, checking & SE/M&E/Acoustics/Fire design landscape co-ordination4. In the event of descrepancies, refer to the most detailed drawing5. Window details shown indicatively, refer to plan drawings for opening styles6. For annotated material references refer to 1222-01_Outline Specifications:
Section 2.1 External Envelope Section 2.2 Room Data Sheets Section 2.3 Internal Doors7. Samples of all materials to be provided in adequated time for client and statutory authority approval
0 1 2 3 4 5 m1:100
A 29.10.15 Update to stage D+ information Key
Enterprise areaA 29.10.15 Update to stage D+ information
B 30.10.15 'Code of Measuring Pracitce' area update
RWP
RWP
RWP
SVP
SVP
SVP
SVP
SVP
RWP
RWP
RWP
RWP
SVP
RWP
SVP
RWP RWP
FF300x750 ECU
900x500 HIU
AOV E M
FLUE RISER
RWP
RWP
DRY RISER
B C D F G H I J K L M
0203
0405
0102
0304
05
B C D F G H I J K L M
01
A
A
E
E
A A
CC
BERNHARDT CRESCENT
JEROME CRESCENT
F F Lift14 P Capacity
Guest room
Communal Laundry
Cleaners' cupboard
1B1P/WA
Plant room
Workshop AreaLower Ground -1 Mezzanine
Stair 03
Stair 05
Stair 02Stair 04
Stair 01
BB
Rev. Date DescriptionNOTES:1. Measurements are based on metric system2. All levels are in meters to Principal Datum (PD) unless noted otherwise3. Do not scale drawing4. Figure dimensions are to be followed5. Do not use for construction unless expressly permitted6. Contractor should verify all conditions on site and notify contract administrator of any variations from dimensions before constructionThe data contained in this document includes proprietary rights of mae. Any party in receipt of the document shall receive and hold the same in confidence and agrees not to duplicate or otherwise reproduce the document in whole or in part, nor disclose the contents of the same without the written consent of mae.
mæ LLP Architects1 Naoroji StreetLondon WC1X 0GBt: +44 (0)20 7704 6060f: +44 (0)20 7833 2473e: offi [email protected]
Title
Scale
Job No.
Status
1222
Information 1:100@A1
Proposed Lower Ground -1 Floor Plan
Drawn By
NWChecked By
NW
Client
Westminster City Council
Job Name
Lisson Arches
Date24.01.14
Drawing No.1222-01_SK051
Revision
A
PROJECT NOTES1. This is a design intent drawing for information only and is not to be used for construction2. To be read in conjunction with general arrangement drawings and coordination with MEP,Civil/Structural and Landscape Stage D+ design tender packages3. Package is to D+ level of detail only, and is subject to further detailed design development, checking & SE/M&E/Acoustics/Fire design landscape co-ordination4. In the event of descrepancies, refer to the most detailed drawing5. Window details shown indicatively, refer to plan drawings for opening styles6. For annotated material references refer to 1222-01_Outline Specifications:
Section 2.1 External Envelope Section 2.2 Room Data Sheets Section 2.3 Internal Doors7. Samples of all materials to be provided in adequated time for client and statutory authority approval
0 1 2 3 4 5 m1:100
Type 12VerticalLouvers
A 29.10.15 Update to stage D+ information Key
Enterprise area
900x500 HIU
FFFF
900x500 HIU
DRY RISER
B C D F G H I J K L M
0203
0405
0102
0304
05
B C D F G H I J K L M
01
A
A
E
E
Hairdressers'room
Entrance lobby
Manager's office
Scooterstorage
Residential entrance
Enterprise entrance
Enterprise lobby1B1P/WA
1B1P/WA
Workshop Area
BERNHARDT CRESCENT
LISSON GROVE
JEROME CRESCENT
A A
CC
CHEQUERS HOUSE
WYCOMBE HOUSE
Stair 03
Stair 05
Stair 02
Stair 04
Stair 01
Stair 05
Workshop AreaGround FloorMezzanine
BB
Rev. Date DescriptionNOTES:1. Measurements are based on metric system2. All levels are in meters to Principal Datum (PD) unless noted otherwise3. Do not scale drawing4. Figure dimensions are to be followed5. Do not use for construction unless expressly permitted6. Contractor should verify all conditions on site and notify contract administrator of any variations from dimensions before constructionThe data contained in this document includes proprietary rights of mae. Any party in receipt of the document shall receive and hold the same in confidence and agrees not to duplicate or otherwise reproduce the document in whole or in part, nor disclose the contents of the same without the written consent of mae.
mæ LLP Architects1 Naoroji StreetLondon WC1X 0GBt: +44 (0)20 7704 6060f: +44 (0)20 7833 2473e: offi [email protected]
Title
Scale
Job No.
Status
1222
Information 1:100@A1
Proposed Ground Floor Plan - Enterprise
Drawn By
NWChecked By
NW
Client
Westminster City Council
Job Name
Lisson Arches
Date24.01.14
Drawing No.1222-01_SK050
Revision
B
PROJECT NOTES1. This is a design intent drawing for information only and is not to be used for construction2. To be read in conjunction with general arrangement drawings and coordination with MEP,Civil/Structural and Landscape Stage D+ design tender packages3. Package is to D+ level of detail only, and is subject to further detailed design development, checking & SE/M&E/Acoustics/Fire design landscape co-ordination4. In the event of descrepancies, refer to the most detailed drawing5. Window details shown indicatively, refer to plan drawings for opening styles6. For annotated material references refer to 1222-01_Outline Specifications:
Section 2.1 External Envelope Section 2.2 Room Data Sheets Section 2.3 Internal Doors7. Samples of all materials to be provided in adequated time for client and statutory authority approval
0 1 2 3 4 5 m1:100
Type 12VerticalLouvers
Type 12
HorizontalLouvers
A 29.10.15 Update to stage D+ information Enterprise area
Key
B 30.10.15 'Code of Measuring Pracitce' area update
13LISSON ARCHES ENTERPRISE HUB
LISSON ARCHESENtErpriSE HuB