lighting conductor
TRANSCRIPT
8/8/2019 Lighting Conductor
http://slidepdf.com/reader/full/lighting-conductor 1/2
16 V is i t o u r w e b s i t e a t : w w w . e l e c t r ic a lr e v i e w . c o . u k
T E S T A N D M E A S U R E M E N T
Electrical Review • Vol 238 No 5
Unless organisations instigate a proper testing and maintenance programme, they will
only know if their lightning protection system is working properly when they suffer a
strike. By that time they could have suffered catastrophic damage to their buildings
and business, says Mike Henshaw, managing director at Omega Red Group
Lightning protection – test before a strike
M
ost building services would simply
not function correctly if faults or
defects were present but the correct
operation of a lightning protectionsystem only becomes obvious when it is called
upon to protect a structure. For this reason it is
even more vital to ensure that fully trained and
accredited engineers undertake regular testing
and maintenance works on vulnerable
structures and sites. The current in a lightning
strike is likely to be in the range of 2,000 -
200,000A and so an effective operational
system is vital to ensure the protection of assets.
The vast majority of structures in the UK use
BS6651 to inform their design, testing and
maintenance works in relation to lightning
protection. This standard states a “ competent
person” should carry out inspections so a good
rule of thumb is to look for contractors with
third-party accreditation of their ability to
design and report on lightning protectionssystems, accreditation such as that provided by
Atlas (Association of Technical Lightning and
Access Specialists).
BS6651 covers all aspects of Lightning
Protection but sections 31-34 are of par ticular
relevance for testing and maintenance.
As large parts of the lightning protection
system may be hidden or inaccessible after
completion, it is par ticularly important , and
indeed a requirement of the code, that each
component of a lightning protection system
should be inspected during the construction
stages of an installation. Special attention must
be given to any part of the system that will be
concealed upon completion. These components
may be hidden for aesthetic reasons or the
component may be an integral part of the
structure.Inspections should be carried out not on ly
during the installation process but also upon
completion and at regular intervals thereafter.
Figure one shows damage that has been
identified through regular inspections. The first
picture shows the conductor has been bent into
an ‘s’ shape next to the clamp. This ‘s’ would
create inductance during any further lightning
current flow and may result in a flashover from
the conductor to adjacent conductive parts,
which could cause fire or other undesirablemechanical effects.
The second picture shows loose tapes,
probably caused by the mechanical effects of a
lightning strike dislodging poorly fitted fixings.
Further strikes would cause a whiplash effect
on the tape and may damage further fixings or
rip the conductor away from the system
completely, thus leaving it incomplete.
Visual inspection of an installation should
take into account the following key points and
observations recorded in the detailed inspection
report:
• inspections should be repeated at fixed
intervals, preferably not exceeding 12
months. If the intervals are fixed at 11
months, the system will have been inspected
throughout every season of the year over aperiod of 11 years
• the mechanical condition of all conductors,
bonds, joints and earth electrodes should be
checked and any observations noted
• if a part is unable to be inspected, this should
be noted
• the bonding of any recently installed/addedservices should be checked.
This section deals with testing the earth
electrodes on the system, although reference is
made to a visual or measured test of any joints
or bonds. In practice, it is usual for inspections
of components to be undertaken rather than
for testing to be carried out.
Electrode testing requires experience and
expertise to ensure that any test carried out is
meaningful and reflects the resistance of the
electrode under test. Too frequently, Omega is
handed client information presenting resistance
readings that are obviously continuity tests and
not true earth-resistance tests.
There are two appropriate methods of
testing lightning protection earths: ‘Fall of
Potential/the 61.8% method’ and ‘Dead Earth’.‘Fall of Potential’ is the recommended
method and involves the electrode under test;
two reference electrodes, a set of leads and a
four-pole test meter. The electrode under test is
isolated and connected to the meter as shown
in figure two for the ‘Fall of Potential’ or figure
three for the ‘61.8%’ method. In turn, the test
meter is connected to the two reference
electrodes, which are driven approximately
300mm into the ground and located typically
25 and 50 metres away from the electrode
under test.
A test is made and the direct resistance of
the electrode under test is recorded on the
meter. This method, however, is only practical
if the electrode to be tested is located adjacent
to virgin ground where test electrodes can be
driven. In reality, in town and city centres forexample, this is very often not the case. The
presence of buried services and pipes may also
have an influence on the test current and the
final test value may be corrupted as a result of
these external influences. Reference electrodes
should therefore be sited away from such
potential disturbances.Fig.1 Damage that has been identifiedthrough regular inspections
8/8/2019 Lighting Conductor
http://slidepdf.com/reader/full/lighting-conductor 2/2
18 V is i t o u r w e b s i t e a t : w w w . e l e c t r ic a lr e v i e w . c o . u k
T E S T A N D M E A S U R E M E N T
Electrical Review • Vol 238 No 5
Where practical conditions dictate that the
‘Fall of Potential’ method cannot be used, the
‘Dead/Known Earth’ method is really the only
practical alternative. However, it is important
to be aware this method is open to error and
misrepresentation if the test engineer is notcompetent to determine an appropriate dead
earth or interpret the readings, which is why it
is essential to use an Atlas accredited engineer
to undertake tests of this nature.
The ‘dead earth’ can be any low-resistance
earth not directly or fortuitously connected to
the earth under test. A connection is made
from a suitable earth to the test meter, which is
in turn connected to the electrode under test as
in figure four, which shows the lightning
protection system acting as the known
‘dead/known’ earth. A reading is then taken
and the ohmic value achieved is effectively the
series resistance of the electrode under test and
the dead earth.
The ‘Dead Earth’ method has some
advantages when using the lightning protection
system as the low-resistance ‘dead/known’
earth, as, due to the equipotential bonding
required to other incoming services, it should
provide a low-resistance earth path. Testclamps, or the clamp to the rod in the
inspection pit, should be opened and the meter
connected to the rod/rod side of the test clamp
and the other side of the test meter connected
to the system side of the test clamp.
A reading can then be taken, which will
show the series resistance of the electrode under
test and the rest of the system together with
other connected parallel electrical and other
earth paths.
As these other parallel paths usually have a
relatively low combined resistance, the meter
reading is effectively the resistance of the
electrode under test as, if correctly selected, the
‘dead’ earth that is used is normally of such
low value that it has little impact on the final
result.
In addition to providing an ohmic value forthe electrode under test, this method also
verifies the circuit to the dead earth source and
by virtue of this, the electrical condition of the
joints in the system. If the connections from the
top of the test clamp to the air termination
through to the other earths on the system and
other parallel paths were loose or damaged,
they would provide a high
resistance, which the meter
reading would reflect. This
situation should then be
investigated so that any
high-resistance joints canbe addressed.
Where no access to an
electrode is possible and,
for example, the pile
foundations have been
utilised as the earth
termination, it is recommended that individual
reference rods are installed around the structure
and tested upon completion. These do not
necessarily form a part of the
installation but may be used as
comparisons against the
original pile foundation test
results. In short, if the reference
rod values have not increased
year on year then it can be
assumed neither has the
resistance of the pilefoundations.
The ‘Dead/known earth’ test
method also applies to clamp-
on CT type testers where
disconnection is not required,
although this type of testing is not always
practical.
At least two types of test are recommended,
one for each of the individual electrodes in
isolation and a second for a combined value.
The requirements of BS6651 are an overall
system resistance (excluding bonding to any
services) of 10Ω and each electrode not
exceeding 10 times the number of earth
electrodes on the system.
Any disconnection of the system should be
preceded with a test to ensure that it is not ‘live’and no testing should be carried out dur ing
storm conditions.
Failure to keep up to date, accurate records
can result in hidden parts of a system not being
adequately attended to and potentially
unnecessary remedial works being proposed
and executed, as a full assessment of the
installation has not been made. At the time of
the annual test and inspection, the following
records are needed either on site or in an
accessible place.
BS6651 states that the following records
should be kept:
• drawings of the lightning protection
system
• details of the geology (nature of the soil
and details of any special earthing
arrangements)• type and position of the earth electrodes
• test conditions and results obtained
• details of any alterations to the system,
including additions and repairs
• the name of the person responsible for
the system.
In order to comply with the
Construction Design and M anagement
Regulations, these records should be provided
at the completion of t he original installation for
inclusion in the project Health and Safety file.
The person responsible for the upkeep of the
building should recover the lightning protection
system records from this file and present them
to the engineer undertaking the first post-
installation inspection and test. Details of the
inspections should be recorded so tha t the
required information can be updated and
maintained. The programme of tests andinspections will identify what, if any,
maintenance is needed. BS6651 states that
attention should be given to the following:
• earthing
• evidence of corrosion or conditions likely to
lead to corrosion
• alterations and additions to the structure that
may affect the lightning protection system
(e.g. changes in the use of the building, the
installation of crane tracks, erection of radio
and television aerials).
Statistics show the UK alone is subjected to
around two million strikes per year and, in
order to ensure your lightning protection
system is operational when called upon,
bearing in mind you have no way of
determining when that may be, anymaintenance work should be carried out with
appropriate expediency.
In the hands of experienced engineers,
proper testing and maintenance of lightning
protection systems can become a routine, but
very necessary, part of a comprehensive safety
programme. At the very least the consequences
of not taking a thorough approach could incur
unnecessary costs but, given the destructive
potential of a lightning strike, those
consequences could be much worse.
Fig.3 61. 8% Method Test
Fig.2 Fall of Potential Test
Fig.4 Dead/Known Earth Test