lighting conductor

2
16 Visit our w eb site at: w w w.electri ca lreview.co.uk T E S T A N D M E A S U R E M E N T Electrical Review • Vol 238 No 5 Unless organisations instigate a proper testing and maintenance programme, they will only know if their lightning protection system is working properly when they suffer a strike. By that time they could have suffered catastrophic damage to their buildings and business, says Mike Henshaw, managing director at Omega Red Group Lightning protection  – test before a strike M ost building services would simply not function correctly if faults or defects were present but the correct operation of a lig htning protection system only becomes obvious when it is called upon to protect a structure. For this reason it is eve n mor e vital to ensure that fully traine d and accredited engineers undertake regular testing and maintenance works o n vulnerable structures and sites. The current in a lig htning strike is likely to be in the range of 2,000 - 200,000A and so an eff ecti ve operational system is vital to ensure the protection of assets. The vast majority of structures in the UK use BS6651 to inform their design, testing and maintenance works in relation to lig htning protection. This standard states a “ competent person” should carry out inspec tions so a good rule of thumb is to look for contractors with third-party accreditation of their ability to desi gn and r eport on lig htning protections sys tems, accre ditation such as that provided by Atlas (Association of Technical Lightning and Access Specialists). BS6651 covers all aspects of Lightning Protection but sections 31-34 are of par ticular relevance for testing and maintenance. As large parts of the lightning protection system may be hidden or inaccessible after completion, it is par ticularly i mportant , and indeed a requirement of the code, that each component of a lightning protection system should be inspected during the construction stages of an installation. Special attention must be given to any part of the system that will be concealed upon completion. These components may be hidden for aesthetic reasons or the component may be an integral part of the structure. Inspec tions should be carried out not on ly during the installation process but also upon completion and at regular intervals thereafter. Figure one shows damage that has been identied through regular inspections. The rst picture shows the conductor has been bent into an ‘s’ shape next to the clamp. This ‘s’ would create inductance during any further lightning current ow and may result in a ashove r from the conductor to adjace nt conductive parts, which could cause re or other undesirable mechanical effec ts. The second picture shows loose tapes, probably caused by the mechanical effects of a lightning strike dislodging poorly tted xings. Further strikes would cause a whiplash effect on the tap e and may damage further xings or rip the conductor away from the system completely, thus leaving it incomplete. Visual inspection of an installation should take into account the following ke y points and observations recorded in the detailed inspection report: inspec tions should be repeated at xed intervals, preferably not exceeding 12 months. If the intervals are xed at 11 months, the system will have been inspected throughout every season of the year over a period of 11 years the mechanic al condition of all conductors, bonds, joints and earth elec trodes should be checked and any observations noted • if a part is unable to be inspe cted, this should be noted • the bonding of any recently ins talled/ added services should be checked. This section deals with testing the earth electrodes on the system, although reference is made to a vis ual or measured test of any joints or bonds. In practice, it is usual for inspections of components to be undertaken rather than for testing to be carried out. Electrode testing requires experience and expertise to ensure that any t est carried out is meaningful and reects the resistance of the electrode under test. Too frequently, Omega is handed client information presenting resistance readings that are obviously continuity tests and not true eart h-resi stance tests. There are two appropriate methods of testing lightning protection earths: ‘Fall of Potential/ the 61.8% method’ and ‘Dead Earth’. ‘Fall of Potential’ is the recommended method and involves the electrode under test; two reference electrodes, a set of leads and a four-pole test meter. The electrode under test is isolate d and connec ted to the meter as shown in gure two for the ‘Fall of Potential’ or gure three for the ‘61.8%’ method. In tur n, the test meter is connected to the two reference electrodes, which are driven approximately 300mm into the ground and located typic ally 25 and 50 metres away from th e electrode under test. A test is made and the direct resistance of the elec trode under test is recorded on the meter. This method, however, is only practical if the electrode to be tested is located adjacent to virgin ground where test electrodes can be driven. In reality, in town and city centres for example, this is very often not the case. The presence of buried services and pipes may also have an inue nce on the test current and t he nal test value may be corrupted as a result of these external inuences. Reference electrodes should therefore be sited away from such potential disturbances . Fig.1 Damage that has been identi ed through regular inspections

Upload: wwijethunge

Post on 10-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Lighting Conductor

8/8/2019 Lighting Conductor

http://slidepdf.com/reader/full/lighting-conductor 1/2

16 V is i t o u r w e b s i t e a t : w w w . e l e c t r ic a lr e v i e w . c o . u k

T E S T A N D M E A S U R E M E N T

Electrical Review • Vol 238 No 5

Unless organisations instigate a proper testing and maintenance programme, they will

only know if their lightning protection system is working properly when they suffer a

strike. By that time they could have suffered catastrophic damage to their buildings

and business, says Mike Henshaw, managing director at Omega Red Group

Lightning protection – test before a strike

M

ost building services would simply

not function correctly if faults or

defects were present but the correct

operation of a lightning protectionsystem only becomes obvious when it is called

upon to protect a structure. For this reason it is

even more vital to ensure that fully trained and

accredited engineers undertake regular testing

and maintenance works on vulnerable

structures and sites. The current in a lightning

strike is likely to be in the range of 2,000 -

200,000A and so an effective operational

system is vital to ensure the protection of assets.

The vast majority of structures in the UK use

BS6651 to inform their design, testing and

maintenance works in relation to lightning

protection. This standard states a “ competent

person” should carry out inspections so a good

rule of thumb is to look for contractors with

third-party accreditation of their ability to

design and report on lightning protectionssystems, accreditation such as that provided by

Atlas (Association of Technical Lightning and

Access Specialists).

BS6651 covers all aspects of Lightning

Protection but sections 31-34 are of par ticular

relevance for testing and maintenance.

As large parts of the lightning protection

system may be hidden or inaccessible after

completion, it is par ticularly important , and

indeed a requirement of the code, that each

component of a lightning protection system

should be inspected during the construction

stages of an installation. Special attention must

be given to any part of the system that will be

concealed upon completion. These components

may be hidden for aesthetic reasons or the

component may be an integral part of the

structure.Inspections should be carried out not on ly

during the installation process but also upon

completion and at regular intervals thereafter.

Figure one shows damage that has been

identified through regular inspections. The first

picture shows the conductor has been bent into

an ‘s’ shape next to the clamp. This ‘s’ would

create inductance during any further lightning

current flow and may result in a flashover from

the conductor to adjacent conductive parts,

which could cause fire or other undesirablemechanical effects.

The second picture shows loose tapes,

probably caused by the mechanical effects of a

lightning strike dislodging poorly fitted fixings.

Further strikes would cause a whiplash effect

on the tape and may damage further fixings or

rip the conductor away from the system

completely, thus leaving it incomplete.

Visual inspection of an installation should

take into account the following key points and

observations recorded in the detailed inspection

report:

• inspections should be repeated at fixed

intervals, preferably not exceeding 12

months. If the intervals are fixed at 11

months, the system will have been inspected

throughout every season of the year over aperiod of 11 years

• the mechanical condition of all conductors,

bonds, joints and earth electrodes should be

checked and any observations noted

• if a part is unable to be inspected, this should

be noted

• the bonding of any recently installed/addedservices should be checked.

This section deals with testing the earth

electrodes on the system, although reference is

made to a visual or measured test of any joints

or bonds. In practice, it is usual for inspections

of components to be undertaken rather than

for testing to be carried out.

Electrode testing requires experience and

expertise to ensure that any test carried out is

meaningful and reflects the resistance of the

electrode under test. Too frequently, Omega is

handed client information presenting resistance

readings that are obviously continuity tests and

not true earth-resistance tests.

There are two appropriate methods of

testing lightning protection earths: ‘Fall of

Potential/the 61.8% method’ and ‘Dead Earth’.‘Fall of Potential’ is the recommended

method and involves the electrode under test;

two reference electrodes, a set of leads and a

four-pole test meter. The electrode under test is

isolated and connected to the meter as shown

in figure two for the ‘Fall of Potential’ or figure

three for the ‘61.8%’ method. In turn, the test

meter is connected to the two reference

electrodes, which are driven approximately

300mm into the ground and located typically

25 and 50 metres away from the electrode

under test.

A test is made and the direct resistance of

the electrode under test is recorded on the

meter. This method, however, is only practical

if the electrode to be tested is located adjacent

to virgin ground where test electrodes can be

driven. In reality, in town and city centres forexample, this is very often not the case. The

presence of buried services and pipes may also

have an influence on the test current and the

final test value may be corrupted as a result of

these external influences. Reference electrodes

should therefore be sited away from such

potential disturbances.Fig.1 Damage that has been identifiedthrough regular inspections

Page 2: Lighting Conductor

8/8/2019 Lighting Conductor

http://slidepdf.com/reader/full/lighting-conductor 2/2

18 V is i t o u r w e b s i t e a t : w w w . e l e c t r ic a lr e v i e w . c o . u k

T E S T A N D M E A S U R E M E N T

Electrical Review • Vol 238 No 5

Where practical conditions dictate that the

‘Fall of Potential’ method cannot be used, the

‘Dead/Known Earth’ method is really the only

practical alternative. However, it is important

to be aware this method is open to error and

misrepresentation if the test engineer is notcompetent to determine an appropriate dead

earth or interpret the readings, which is why it

is essential to use an Atlas accredited engineer

to undertake tests of this nature.

The ‘dead earth’ can be any low-resistance

earth not directly or fortuitously connected to

the earth under test. A connection is made

from a suitable earth to the test meter, which is

in turn connected to the electrode under test as

in figure four, which shows the lightning

protection system acting as the known

‘dead/known’ earth. A reading is then taken

and the ohmic value achieved is effectively the

series resistance of the electrode under test and

the dead earth.

The ‘Dead Earth’ method has some

advantages when using the lightning protection

system as the low-resistance ‘dead/known’

earth, as, due to the equipotential bonding

required to other incoming services, it should

provide a low-resistance earth path. Testclamps, or the clamp to the rod in the

inspection pit, should be opened and the meter

connected to the rod/rod side of the test clamp

and the other side of the test meter connected

to the system side of the test clamp.

A reading can then be taken, which will

show the series resistance of the electrode under

test and the rest of the system together with

other connected parallel electrical and other

earth paths.

As these other parallel paths usually have a

relatively low combined resistance, the meter

reading is effectively the resistance of the

electrode under test as, if correctly selected, the

‘dead’ earth that is used is normally of such

low value that it has little impact on the final

result.

In addition to providing an ohmic value forthe electrode under test, this method also

verifies the circuit to the dead earth source and

by virtue of this, the electrical condition of the

joints in the system. If the connections from the

top of the test clamp to the air termination

through to the other earths on the system and

other parallel paths were loose or damaged,

they would provide a high

resistance, which the meter

reading would reflect. This

situation should then be

investigated so that any

high-resistance joints canbe addressed.

Where no access to an

electrode is possible and,

for example, the pile

foundations have been

utilised as the earth

termination, it is recommended that individual

reference rods are installed around the structure

and tested upon completion. These do not

necessarily form a part of the

installation but may be used as

comparisons against the

original pile foundation test

results. In short, if the reference

rod values have not increased

year on year then it can be

assumed neither has the

resistance of the pilefoundations.

The ‘Dead/known earth’ test

method also applies to clamp-

on CT type testers where

disconnection is not required,

although this type of testing is not always

practical.

At least two types of test are recommended,

one for each of the individual electrodes in

isolation and a second for a combined value.

The requirements of BS6651 are an overall

system resistance (excluding bonding to any

services) of 10Ω and each electrode not

exceeding 10 times the number of earth

electrodes on the system.

Any disconnection of the system should be

preceded with a test to ensure that it is not ‘live’and no testing should be carried out dur ing

storm conditions.

Failure to keep up to date, accurate records

can result in hidden parts of a system not being

adequately attended to and potentially

unnecessary remedial works being proposed

and executed, as a full assessment of the

installation has not been made. At the time of

the annual test and inspection, the following

records are needed either on site or in an

accessible place.

BS6651 states that the following records

should be kept:

• drawings of the lightning protection

system

• details of the geology (nature of the soil

and details of any special earthing

arrangements)• type and position of the earth electrodes

• test conditions and results obtained

• details of any alterations to the system,

including additions and repairs

• the name of the person responsible for

the system.

In order to comply with the

Construction Design and M anagement

Regulations, these records should be provided

at the completion of t he original installation for

inclusion in the project Health and Safety file.

The person responsible for the upkeep of the

building should recover the lightning protection

system records from this file and present them

to the engineer undertaking the first post-

installation inspection and test. Details of the

inspections should be recorded so tha t the

required information can be updated and

maintained. The programme of tests andinspections will identify what, if any,

maintenance is needed. BS6651 states that

attention should be given to the following:

• earthing

• evidence of corrosion or conditions likely to

lead to corrosion

• alterations and additions to the structure that

may affect the lightning protection system

(e.g. changes in the use of the building, the

installation of crane tracks, erection of radio

and television aerials).

Statistics show the UK alone is subjected to

around two million strikes per year and, in

order to ensure your lightning protection

system is operational when called upon,

bearing in mind you have no way of

determining when that may be, anymaintenance work should be carried out with

appropriate expediency.

In the hands of experienced engineers,

proper testing and maintenance of lightning

protection systems can become a routine, but

very necessary, part of a comprehensive safety

programme. At the very least the consequences

of not taking a thorough approach could incur

unnecessary costs but, given the destructive

potential of a lightning strike, those

consequences could be much worse.

Fig.3 61. 8% Method Test

Fig.2 Fall of Potential Test

Fig.4 Dead/Known Earth Test