lhc emittance measurement preparation during lhc commissioning lboc meeting february 17, 2015 maria...

40
LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

Upload: frank-walker

Post on 13-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

Emittance Measurement Preparation

during LHC Commissioning

LBOC Meeting February 17, 2015

Maria Kuhn – February 17, 2015

Page 2: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

MotivationGoal for LHC commissioning: operational emittance measurement tools at end of first two months with beam

− Measure optics

− Obtain optimum wire scanner working point

− Operational BSRT

− Quantify emittance growth through the LHC cycle

Motivation:

o Status quo after LS1:

− No fully trustable emittance measurements for LHC Run 1

o Problems:

− Instruments could not be fully commissioned at the start of Run 1

• Parasitic commissioning not possible, MDs not sufficient

− Instruments partially not working

2

Page 3: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

First 2 Months of LHC Commissioning

Instrument

Task Injection energy

Flattop energy

Squeezed optics

Wire scanner

Confirm BLM thresholds: find wire scan limits

~ 30 min ~ 30 min

Orbit bump calibration: validate calibration of all eight wire scanners

~ 80 min ~ 80 min

Qualify photo-multiplier saturation: find optimum wire scanner working points

~ 180 min

~ 180 min

Optics measure-

ments

K-modulation in IR4: measure b in the vicinity of the transverse profile monitors

~ 60 min ~ 60 min ~ 60 min

K-modulation in the IPs: measure b*

~ 240 min

3

Need low intensity beams – very few bunchesExtra time needed to set up beams and the

machine

Page 4: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Wire Scanners

o Orbit bump calibration

o Photomultiplier saturation measurements

4

Page 5: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

o Orbit bumps at injection and flattop energy

− For all 8 wire scanners

• Operational and spare LHC wire scanners

o Going from +3 mm to -3 mm in 1 mm steps

− Usually takes ~ 10 min per wire scanner and energy

~ 80 min in total per energy plateau

Wire Scanner Orbit Bump Calibration

5

• Single bunches • ~ 5 - 10 bunches • Low bunch

intensity• Before: upper

wire scanner intensity limit to be checked

• BSRT in parallel if possible

Page 6: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Wire Scanner Photomultiplier Saturation

o Find optimum wire scanner working point!

o Change filter and voltage of wire scanner photomultipliers

− All 8 wire scanners in parallel

− ~ 3 hour in total per energy plateau

6

• Single bunches • ~ 5 - 10 bunches • Low bunch

intensity

Example photomultiplier saturation curve of a wire scanner in the Booster. Courtesy G. Sterbini

Page 7: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 16/02/2015

New LHC Wire Scanner Application

Layout of the new operational wire scanner application for the LHC:

7

• Wire scan limits with sublimation limits and BLM thresholds will be implemented in front end (like in 2012).

• New photomultipliers installed!

Page 8: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

K-Modulation

o Beta function measurements in IR4

− Turn-by-turn phase advance measurents absolutely necessary

• including optics measurements through the ramp (not possible with k-modulation)

o b* measurements!

8

Page 9: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

IP4

o Measure b at quadrupoles in IR4 at injection, flattop and with squeezed optics

o One quadrupole at a time (~ 5 – 10 min per quadrupole)

− Step or sine modulation possible

− ~ 1 hour required per beam mode

o Required beam conditions:

− Transverse damper off

− Injection tunes (less coupling)

− Only one nominal bunch or pilot beam

K-Modulation in IR4

Beam 1

MQY.5L4.B1 MQY.5R4.B1 MQY.6R4.B1 MQM.7R4.B1

Beam 2

MQY.5L4.B2 MQY.5R4.B2 MQY.6L4.B2

9

Page 10: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

o Measure b* at triplets in IP1/2/5/8 with squeezed optics

o One quadrupole at a time (~ 60 min per IP)

− Step or sine modulation possible

− ~ 4 hours in total

o Required beam conditions:

− Transverse damper off

− Only one nominal bunch or pilot beam

− Small amplitudes: with collision tunes

• Therefore, if possible, use injection tunes

− Without IR bumps in

− At 80 cm b*

K-Modulation in the IPs

Left MQXA1.L1 MQXA1.L2 MQXA1.L5 MQXA1.L8

Right MQXA1.R1 MQXA1.R2 MQXA1.R5 MQXA1.R8

10

Page 11: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

New K-Modulation Tool for the CCC

o K-modulation application

− Tune acquisition + filtering

− Enter modulation amplitude in or

− Automatic measurement – pre-defined modulation functions

− Integrated into LHC control system – pre-calculated modulation limits

− Online analysis

o Additional measurement mode: SINUSOIDAL EXCITATION − Smaller amplitude and higher

frequency than for step function

− In principle sinusoidal excitation transparent for Quench Protection System (QPS)

o Tested sinusoidal k-modulation in the SPS in November 2014

− Low energy (26 GeV)

− Tune chirp on 11

Page 12: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

SPS K-Modulation 12.November 2014

Screenshot of the application:

− Note: very good tune signal and response in the vertical plane!

12

Page 13: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Planning

o Wire scanner calibration and k-modulation into LHC commissioning plan

o LHC commissioning planning: slides from Jorg‘s LMC talk (December 10, 2014)

13

Page 14: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

LHC Commissioning - Requests1. Injection – probe bunch

− 60 min dedicated k-modulation in IR4 at 450 GeV

− Optional: 30 min parasitic wire scans to confirm BLM thresholds

2. Ramp – probe bunch

− 60 min dedicated k-modulation in IR4 at 6.5 TeV

− Optional: 30 min parasitic wire scans to confirm BLM thresholds

3. Squeeze - probe bunch

− 60 min dedicated k-modulation in IR4 with squeezed optics

− 240 min dedicated k-modulation to measure b*

4. Injection – nominal bunch

− 80 min dedicated wire scanner orbit bump calibration

− 180 min (parasitic) wire scanner photomultiplier saturation studies

5. Ramp, squeeze, collide – nominal bunch

− 80 min dedicated wire scanner orbit bump calibration

− 180 min (parasitic) wire scanner photomultiplier saturation studies14

Page 15: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Injection – probe bunch

Injection

Squeeze

Ramp

Collide

First turn.Capture and closed orbit.

o No bumps (Xing & separation) at this stage.

Tune, chromaticity & optics - measure & correct.RF loops, correct buckets.Basic instrumentation checks (calibrations, signal

swaps,…).Settings up of orbit and tune feedbacks.

o Systematic check of tune, chromaticity and orbit corrector circuit polarities.

flat

probe

1 hour dedicated k-modulation in IR4 needed

0.5 hours parasitic wire scans needed to confirm BLM thresholds

15

Page 16: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Ramp – probe bunch

Injection

Squeeze

Ramp

Collide

First ramps with probe bunches, orbit and tune feedbacks ON. o Flat orbit, coarse collimators (TCP, TCDQ).

Optics measurement and correction on flat top.o On the fly optics measurements in the ramp.

Coarse collimator setup / check on flat top.o Preparation for squeeze – TCP and TCDQ.

Dump checks at different energies along ramp.

flat

probecoarse

1 hour dedicated k-modulation in IR4 at flattop energy needed

16

0.5 hours parasitic wire scans needed to confirm BLM thresholds at flattop energy

Page 17: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Squeeze – probe bunch

Injection

Squeeze

Ramp

Collide

Squeeze in steps to 40 cm, optics measurements, orbit & tune & Q’ corrections.

o Flat orbit, coarse collimators (TCP, TCDQ).

Repeat with optics corrections in place, measure corrected optics.

o Iterate corrections (or cycles) if required.

Local triplet apertures to asses b* reach.o Confirm measurements at injection.o At b* of 40 or 80 cm – tbd.

40 cm

flatprobe

coarse

1 hour dedicated k-modulation in IR4 with squeezed optics needed

17

4 hours k-modulation to measure b*

Page 18: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

Injection – nominal bunch

M. Kuhn - 17/02/2015

Injection

Squeeze

Ramp

Collide

Establish flat reference orbit for cycle.Switch on bumps (Xing and separation) and experiments magnets. Injection and transfer line fine setup.Alignment of collimators and protection devices (dump, injection).Aperture measurements (global, local: triplets, injection, dump).Beam instrumentation checkout.RF and ADT set up. FIDEL measurements and corrections.And much more.

bumps

nominaltight

80 min dedicated wire scanner orbit bump calibration + 3 hours (parasitic) wire scanner photomultiplier saturation studies

18

Page 19: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

RSC – nominal bunch

Injection

Squeeze

Ramp

Collide

Ramp nominal bunch with longitudinal blowup.

Collimator setup (IR7+3) on flat top.Ramp and squeeze to 80 cm with bumps

(Xing & separation).o Align TCTs: FT, end of squeeze.

Collide - find collisions (if not already done).

o Align TCTs and TCLs, possibly also roman pots.

80 cm

bumps

bumps bumps

nominaltight

19

80 min dedicated wire scanner orbit bump calibration + 3 hours (parasitic) wire scanner photomultiplier saturation studies at flattop energy

Measure cycles with wire scanner and BSRT (parasitic)

Page 20: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Emittance Measurements

o Injection

o Ramp

o Flattop

o Squeeze

o Collisions

20

Page 21: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

After LHC Cycle Setupo Requirement: BSRT has to be commissioned early on as well!

o Measurements with few bunches during many ramps

− Mainly with wire scanners and BSRT

o Measurements with few bunches during the entire cycle including collisions

− Mainly with wire scanners and BSRT

− (BGI not possible for protons, BGV only later in 2015)

− Comparison with emittance from luminosity if applicable

o Comparison of transverse profile measurements during Van der Meer scans at the end of LHC commissioning phase

− With wire scanners, BRST and LHCb SMOG

− Comparison with emittance from luminosity

21

Not possible! Beam intensity

too high.

Page 22: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

2015 Q2o From Mike‘s LMC talk (Jan 28, 215)

22

Use the first week of collisions to compare emittances from wire scans and BSRT to emittances from luminosity and LHCb SMOG data during stable beams!

Page 23: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

Stable beams

M. Kuhn - 17/02/2015

Injection

Squeeze

Ramp

Collide

First stable beams with few bunches.

80 cm

bumps

bumps bumps

bumps

STABLE BEAMS

nominaltight

Squeeze + collide part to be repeated for medium b* (20-40 m).

Measure parasitically with wire scanners and BSRT. Close LHCb Velo and measure with SMOG in parallel!

23

Page 24: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Planning First Week of Collisions

o Tentative dates: week 21 (May 18 – 22, 2015)

o Wire scan limit at 6.5 TeV: ~ 10 bunches per beam!

o ATLAS/CMS luminosity not calibrated before Van der Meer scans, but could be analysed later

− Need colliding bunches

o For LHCb SMOG the Velo needs to be closed

− Need stable beams declared

− Minimum 1 colliding bunch per beam

− At least 6 non colliding bunches for meaningful measurement

• Could collide in ATLAS/CMS to obtain emittance from lumi in parallel

− Minimum stable beams time ~ 1 hour

24

Page 25: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Emittance Measurements Run 2o During LHC Run 1 it was possible

to measure bunch-by-bunch emittances of the first 144 bunch batch at injection of physics fills

− Can be compared to emittanc from peak luminosity

− Important for evolution of growth through the year

o Considerations for emittance measurements during LHC Run 2

− Injection scans

• Problem: wire scans not possible with 288 bunches!

− Question: start of filling scheme with 144 bunches possible?

• To be able to measure emittances at injection of physics fills

25

Page 26: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

SummaryDuring LHC commissioning we want to:

1. Measure beta functions

2. Fully calibrate wire scanners and BSRTs

3. Quantify transverse emittance growth during the LHC cycle

− Including injection, ramp, squeeze, and collisions

Due to time constraints and high beam current we will not have the possibility to complete these measurements during the run!

26

Page 27: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Thanks for your attention!

Questions? Comments?

27

Page 28: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Spare Slides

28

Page 29: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

K-Modulation Overview

Set Up60 min

Injection10

min

K-mod

IR460

min

Prepare + ram

p30

min

K-mod

IR460 min

Squeeze 30

min

K-mod

IR4 + IPs300 min

450 GeV injection energy

6.5 TeV collision energy

• Single bunches • One or two nominal

bunches• Transverse damper off• Injection tunes

In total ~ 10 hours measurememt time

Optional dump + re-inject

29

Page 30: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 17/02/2015

Wire Scanner Calibration Overview

Set Up30 min

Injection10 min

Orbit bumps

80 min

PM saturation60 min

Prepare + ramp30 min

Orbit bumps

80 min

PM saturation60 min

Squeeze + collide60 min

450 GeV injection energy

6.5 TeV collision energy

optional

• Single bunches • ~ 5 - 10 bunches • Low bunch intensity• Upper wire scanner

intensity limit to be checked

In total ~ 6 – 8 hours measurememt time

Optional dump + re-inject

30

Page 31: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

First Measurements in the SPSo Requirements

− Relatively long magnetic plateau (10 s or more)

− Low energy (26 GeV)

− Good tune signal (turn on chirp)

o Note: SPS magnets are conventional (room-temperature) electromagnets

31

o Testing sinusoidal k-modulation:

− Modulation to quadrupole directly at power converter

− Power converter parameters: number of periods, amplitude, frequency

Page 32: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

SPS Tune Signalo Easily detectable tune peak in the vertical plane

32

Page 33: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

K-Modulation Analysis (1)o Unfortunately power converter data was not saved correctly

o Repeated measurement on 13 November 2014

− Caveat: tune acquisition not during entire cycle

o Reminder:

33

𝜷𝒙 ,𝒚 ≈𝟒𝝅∆𝑸 𝒙 ,𝒚

𝒍 ∙∆𝒌

Window for fitting: discard half cosine at start and end of modulation.

Fit both curves with sine to get amplitude :

with offset and phase

Example:

Page 34: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

o and obtained from fit to sinusoidal modulation

o from transfer function

− For now neglecting absolute transfer fct error and transfer fct error fromhysteresis effects

K-Modulation Analysis (2)

34

Vertical beta function:

0.4 % uncertainty from fit

Nominal:

First tests of sinusoidal k-modulation were successful - proof of principle.

To do: implement analysis in the application! Work in progress: further tests in the SPS and the LHC will follow.

Page 35: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

Measurement Precision Comparison

o Comparison of b function measurement accuracy:

35

Accelerator b uncertainty Method Year

Tevatron 10 % BPM phase advance

1995

LEP ~ 1% K-modulation 2001

SPS ~ 5 - 10 % BPM phase advance

2012

LHC IP1/5 3 – 5 % K-modulation 2011

LHC wire scanner

1.3 – 10.9 % K-modulation 2012

LHC wire scanner

0.7 – 9.4 % BPM phase advance

2012

Page 36: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

LHC Inner Triplet – b* Measurement

MQXA3MQXB2

MQXB2MQXA1

36

IP1/5

Q3 Q1Q2

𝑰𝑸𝟏= 𝑰𝑹𝑸𝑿+𝑰 𝑹𝑻𝑸𝑿 𝟏

𝑰𝑸𝟐= 𝑰𝑹𝑸𝑿+𝑰 𝑹𝑻𝑸𝑿 𝟐

𝑰𝑸𝟑= 𝑰𝑹𝑸𝑿

Modulation of quadrupole Q1 with power converter RTQX1

Nested circuits!

Page 37: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

First Step Modulation in the LHCo Power converter in simulation, no beam

37

Page 38: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

First Sinusoidal Modulation in the LHC

o Power converter in simulation, no beam

38

Page 39: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

First Sinusoidal Modulation of the LHC Triplets

o Power converter in simulation, no beam

39

Page 40: LHC Emittance Measurement Preparation during LHC Commissioning LBOC Meeting February 17, 2015 Maria Kuhn – February 17, 2015

LHC

M. Kuhn - 03/12/2014

Quench Protection System (QPS)

o Quench detector output while the power converter of the corresponding circuit performs a sinusoidal current modulation:

− sinusoidal current of 15 A amplitude and a frequency of 0.25 Hz resulting in a maximum dI/dt of about 24 A/s

− maximum inductance of 21 mH per coil 250 mV sinusoidal voltage

o The common mode caused by sinusoidal excitation is well suppressed: For QPS the sinusoidal excitation will be transparent!

40

J. Steckert

The green line is the voltage difference between the compared coils in the magnet which are used to detect a quench.