1 commissioning challenges of the lhc jörg wenninger cern accelerators and beams department...
TRANSCRIPT
1
Commissioning challenges of the LHCCommissioning challenges of the LHC
Jörg Wenninger CERN Accelerators and Beams
Department Operations groupFebruary 2008
• LHC overview• Magnets• Luminosity• High ‘energy’ issues• Hardware & beam commissioning
2Rüdiger Schmidt Bullay Oktober 2007 2
The CERN Beschleuniger Komplex
CERN (Meyrin)
LHC
SPSControl room
ATLAS
LHCB
CMS
ALICE
7 years of construction to replace
LEP: 1989-2000
in the same 26.7 km tunnel by
LHC : 2008-2020+
3
IR6: Beam dumping system
IR4: RF + Beam
instrumentation
IR5:CMS
IR1: ATLAS
IR8: LHC-BIR2:ALICE
Injection ring 2
Injection ring 1
IR3: Momentum collimation (normal
conducting magnets)
IR7: Betatron collimation
(normal conducting magnets)
Beam dump blocks
LHC Layout8 arcs. 8 long straight sections (insertions), ~ 700 m long.beam 1 : clockwisebeam 2 : counter-clockwiseThe beams exchange their positions (inside/outside) in 4 points to ensure that both rings have the same circumference !
The main dipole magnets define the geometry of
the circle !
4
Top energy/GeV Circumference/m Linac 0.12 30PSB 1.4 157CPS 26 628 = 4 PSBSPS 450 6’911 = 11 x PSLHC 7000 26’657 = 27/7 x SPSLEIR
CPS
SPS
Booster
LINACS
LHC
3
45
6
7
8
1
2
Ions
protons
Beam 1
Beam 2
TI8
TI2
Note the energy gain/machine of 10 to 20 – and not more !The gain is typical for the useful range of magnets !!!
The CERN Accelerator Complex
5
LHC – yet another collider?
The LHC surpasses existing accelerators/colliders in 2 aspects : The energy of the beam of 7 TeV that is achieved within the size
constraints of the existing 26.7 km LEP tunnel.
LHC dipole field 8.3 T
HERA/Tevatron ~ 4 T
The luminosity of the collider that will reach unprecedented values for a hadron machine:
LHC pp ~ 1034 cm-2 s-1
Tevatron pp 2x1032 cm-2 s-1
SppbarS pp 6x1030 cm-2 s-1
The combination of very high field magnets and very high beam intensities required to reach the luminosity targets makes operation of the LHC a great challenge !
A factor 2 in field
A factor 4 in size
A factor 100 in luminosity
LHC Magnets & Arc Layout
6
The Superconductor
7
Temperature [K]
Applie
d f
ield
[T
]Superconducting
state
Normal state
Bc
Tc
The DIPOLE field of 8.3 Tesla required to achieve 7 TeV/c can only be obtained with superconducting magnets !
The material determines:
Tc critical temperature
Bc critical field
LHC magnets use NbTi, with a typical usable current density @ 4.2 K
2000 A/mm2 @ 6T
To reach 8-10 T, the temperature must be lowered to 1.9 K – superfluid Helium:
Very low viscosity coil penetration.
Large specific heat (2000 x conductor / unit volume).
Large heat conduction (3000 x Cu).
The superconducting cable
8
1 mm
6 m
Typical value for operation at 8T and 1.9 K: 800 A
NbTi cable
width 15 mm
A.Verweij
A.Verweij
Dipole magnets
9
Dipole length 15 m
The coils must be aligned very precisely to ensure a good field
quality (i.e. ‘pure’ dipole)
To collide two counter-rotating proton beams, the beams must be in separate vaccum chambers (in the bending sections) with opposite B field
direction.
There are actually 2 LHCs and the magnets have a 2-magnets-in-one design!
Dipole field map - cross-section
10
Superconducting coil
Beam
Iron
Non-magnetic
collars
B = 8.33 Tesla I = 11800 A
11Rüdiger Schmidt 11
Beam tube
Superconducting coil
Non-magnetic collars
Ferromagnetic iron
Steel cylinder for Helium
Insulation vacuum
Supports
Vacuum tank
Weight (magnet + cryostat) ~ 30 tons, Length 15 m
LHC arc : not just dipoles…
12
Dipole- und Quadrupol magnets– Provide a stable trajectory for particles with nominal momentum.
Sextupole magnets– Correct the trajectories for off momentum particles (‚chromatic‘ errors).
Multipole-corrector magnets– Sextupole - and decapole corrector magnets at end of dipoles– Used to compensate field imperfections if the dipole magnets. To stabilize
trajectories for particles at larger amplitudes – beam lifetime !
~ 8000 superconducting magnets ae installed in the LHC
QF QD QFdipolemagnets
small sextupolecorrector magnets
decapolemagnets
LHC Cell - Length about 110 m (schematic layout)
sextupolemagnets
13J. Wenninger - ETHZ - December 2005 13
1232 main dipoles +
3700 multipole corrector magnets
(sextupole, octupole, decapole)
392 main quadrupoles +
2500 corrector magnets (dipole, sextupole, octupole)
Regular arc:
Magnets
14J. Wenninger - ETHZ - December 2005 14
Regular arc:
Cryogenics
Supply and recovery of helium with 26 km long cryogenic distribution line
Static bath of superfluid helium at 1.9 K in cooling loops of 110 m length
Connection via service module and jumper
15J. Wenninger - ETHZ - December 2005 15
Insulation vacuum for the cryogenic distribution line
Regular arc:
Vacuum
Insulation vacuum for the magnet cryostats
Beam vacuum for
Beam 1 + Beam 2
16J. Wenninger - ETHZ - December 2005 16
Regular arc:
Electronics
Along the arc about several thousand electronic crates (radiation tolerant) for:
quench protection, power converters for orbit correctors and instrumentation (beam, vacuum + cryogenics)
Tunnel view
17
Complex interconnects
18CERN visit McEwen
Many complex connections of super-conducting cable that will be buried in a cryostat once the work is finished.
This SC cable carries 12’000 Afor the main dipoles
Vacuum chamber
19
Beamenvel. ~ 1.8 mm @ 7 TeV
50 mm
36 mm
The beams circulate in two ultra-high vacuum chambers made of Copper that are cooled to T = 4-20 K.
A beam screen protects the bore of the magnet from image currents, synchrotron light etc from the beam.
Cooling channel (Helium)
Beam screen
Magnet bore
Luminosity
20
Luminosity challenges
21
The event rate N for a physics process with cross-section is proprotional to the collider Luminosity L:
To maximize L:
•Many bunches (k)
•Many protons per bunch (N)
•A small beam size u = ()1/2
: characterizes the beam envelope (optics),
varies along the ring, mim. at the collision points.
: is the phase space volume occupied by the beam (constant along the ring).
**
2
4 yx
fkNL
k = number of bunches = 2808N = no. protons per bunch = 1.15×1011
f = revolution frequency = 11.25 kHzx,y = beam sizes at collision point (hor./vert.) = 16 m
LN
High beam “brillance” N/
(particles per phase space
volume)
Injector chain performance
!Small envelope
Strong focusing !
Beam enveloppe
2222
Fits through the hole of a needle!
ARC ARC
ATLAS collision
point
The beam size follows the local beam optics :• In the arcs the optics follows a regular pattern.
• In the long straight sections, the optics is matched to the ‘telescope’ that provides very strong focusing at the collision point.
Collision point size (rms, defined by ‘*’):CMS & ATLAS : 16 m LHCb : 22 – 160 m ALICE : 16 m (ions) / >160 m (p)
Combining beams for collisions
23
200 m
inner quadrupoletriplet
separationdipole (warm)
recombinationdipole
quadrupoleQ4
quadrupoleQ5
ATLAS or CMS
inner quadrupoletriplet
separationdipole
recombinationdipole
quadrupoleQ4
quadrupoleQ5
collision point
beam I
Example for an LHC insertion with ATLAS or CMS
24 m
beamdistance194 mm
beam II
The 2 LHC beams circulate in separate vacuum chambers in most of the ring, but they must be brought together to collide.
Over a distance of about 260 m, the beams circulate in the same vacuum chamber and they are a total of ~ 120 encounters in ATLAS, CMS, ALICE and LHCb.
Crossing angle
2424
IP
From the point of view of beam dynamics, colliding beams is one of the worst things one can do to a beam due to the very non-linear fields of the opposing beams (diffusion to large amplitudes, lifetime reduction…).
To avoid un-necessary direct beam encounters wherever the beams share a common vacuum:
COLLIDE WITH A CROSSING ANGLE IN ONE PLANE !
The price to pay :
A reduction of the luminosity due to the finite bunch length of 7.6 cm and the non-head on collisions L reduction of ~ 17%.
Crossing planes & angles•ATLAS Vertical 280 rad•CMS Horizontal 280 rad•LHCb Horizontal 300 rad•ALICE Vertical 400 rad
7.5 m
Bunch Pattern
25 25
The nominal LHC pattern consists of 39 groups of 72 bunches (spaced by 25 ns), with variable spacing between the groups to accommodate the rise times of the fast injection and extraction magnets (‘kickers’).
There is a long 3 s hole (5)for the LHC dump kicker (see later).
72 bunches
Stored Energy & Protection
26
The price of high fields & high luminosity…
27
When the LHC is operated at 7 TeV with its design luminosity & intensity,
the LHC magnets store a huge amount of energy in their magnetic fields:
per dipole magnet Estored = 7 MJ
all magnets Estored = 10.4 GJ
the 2808 LHC bunches store a large amount of kinetic energy:
Ebunch = N x E = 1.15 x 1011 x 7 TeV = 129 kJ
Ebeam = k x Ebunch = 2808 x Ebunch = 362 MJ
To ensure safe operation will be a major challenge for the LHC operation crews !
Protection of the machine components from the beam is becoming a major issues for all new high power machines (LHC, SNS, …).
> 1000 x above damage limit for
accelerator components !
Stored Energy
28
Increase with respect to existing accelerators :
•A factor 2 in magnetic field
•A factor 7 in beam energy
•A factor 200 in stored energy
Comparison…
29
The energy of an A380 at 700 km/hour
corresponds to the energy stored in the LHC
magnet system :Sufficient to heat up and melt 12 tons of Copper!!
The energy stored in one LHC beam corresponds
approximately to… 90 kg of TNT
Quench
30
A quench corresponds to the phase transition from the super-conducting to a normal conducting state.
Quenches are initiated by an energy in the order of few mJ– Movement of the superconductor (friction and heat dissipation)
‚training‘ quenches of the magnets until coils are stable.– Beam losses.– Cooling failures.– ...
When part of a magnet quenches, the conductor becomes resistive, which can lead to excessive local energy deposition (temperature rise !!) due to the appearance of Ohmic losses. To protect the magnet:
– The quench must be detected.– The energy is the magnet circuit must be extracted.– The magnet current has to be switched off within << 1 second.
Quench : discharge of energy
3131
Magnet 1 Magnet 2
Power Converter
Magnet 154
Magnet i
Protection of the magnet after a quench:• The quench is detected by measuring the voltage increase over coil : R ~ 0 to
R > 0 !• The energy is distributed in the magnet by force-quenching using quench
heaters.• The current in the quenched magnet decays in < 200 ms.• The current of all other magnets flows through a ‚bypass‘ diode that can stand
the current for 100-200 s.• The current of all other magnets is dischared into the dump resistors.
Discharge resistor
Dump Resistors
3232
Those large air-cooled resistors can absorb the 1 GJ stored in a dipole magnet circuit (they heat up to few hundred degrees Celsius).
If it does not work…
3333P.Pugnat
During magnet testing the 7 MJ stored in one magnet were released into one spot of the coil (inter-turn short)
Operational margin of SC magnet
34
Temperature [K]
App
lied
field
[T]
Superconductingstate
Normal state
Bc
Tc
9 K
Applied Field [T] Bc critical field
1.9 K
quench with fast loss of ~1010 p ~ 0.01% of total int.
Quench with fast loss of ~106-7 p
~0.01-0.1 ppm of the total int.8.3 T / 7 TeV
0.54 T / 450 GeV
QUENCH
Tc critical temperatur
e
Temperature [K]
The LHC is ~1000 times more critical than TEVATRON,
HERA, RHIC
‘Cohabitation’
35
Even to reach a luminosity of 1033 cm-2 s-1, i.e. 10% of the design, requires unprecedented amounts of stored beam energy.
The stored energy will be circulating a few cms from extremely sensitive super-conducting magnets, which can quench following a fast loss of less than 1 part per million of the beam:
>>> requires a very large collimation system (> 100 collimators).
LHC commissioning has to be much more rigorous than what was done for previous machines – no shortcuts and dirty ‘tricks’ can be used to go ahead as soon as the intensities exceed a few % of the design.
>>> Predictions on the commissioning duration are particularly tricky!
Collimation
3636
Primary collimator
Secondary collimators Absorbers
Protectiondevices
Tertiarycollimators
Tripletmagnets
Experiment
Beam
Primaryhalo particle Secondary halo
Tertiary halo
+ hadronic showers
hadronic showers
A multi-stage halo cleaning (collimation) system with over 100 collimators has been designed to protect the sensitive LHC magnets from beam induced quenches :
Halo particles are first scattered by the primary collimator (closest to the beam).The scattered particles (forming the secondary halo) are absorbed by the secondary collimators, or scattered to form the tertiary halo.
Primary and secondary collimators are made of Carbon to survive severe beam impacts !
The collimators must be very precisely aligned (< 0.1 mm) to guarantee efficiency above 99.9% at nominal intensities.
the collimators will have a strong influence on detector backgrounds !!
Collimation @ 7 TeV
3737
1 mm
Opening ~3-5 mm
The collimator opening corresponds roughly to the size of Spain !
For colliders like HERA, TEVATRON, RHIC, LEP collimators are/were used to reduce backgrounds in the experiments ! But the machines can/could actually operate without collimators !
At the LHC collimators are essential for machine operation as soon as we have more than a few % of the nominal beam intensity !
Beam Dumping System IR6
3838
Q5R
Q4R
Q4L
Q5L
Beam 2
Beam 1
Beam dump block
Kicker magnets to
paint (dilute) the beam
about 700 m
about 500 m
15 fast ‘kicker’ magnets
deflect the beam to the
outside
When it is time to get rid of the beams (also in case of emergency!) , the beams are ‘kicked’ out of the ring by a system of kicker magnets and send into a dump block !
Septum magnets deflect
the extracted beam vertically
quadrupoles
Dump Block…
39 39
Approx. 8 m
concrete shielding
beam absorber (graphite)
The ONLY element in the LHC that can withstand the impact of the full beam !
The block is made of graphite (low Z material) to spread out the hadronic showers over a large volume.
It is actually necessary to paint the beam over the surface to keep the peak energy densities at a tolerable level !
Unscheduled beam loss & protection
40
Beam loss over multiple turns due to many types of failures.
Passive protection - Failure prevention (high reliability systems).- Intercept beam with collimators and absorber
blocks.
Active protection systems have no time to react !
Active Protection- Failure detection (by beam and/or equipment
monitoring) with fast reaction time (< 1 ms).- Fire beam dumping system
Beam loss over a single turn during injection, beam dump or any other fast ‘kick’.
In the event a failure or unacceptable beam lifetime, the beam must be dumped immediately and safely into the beam dump
blockTwo main classes for failures (with more subtle sub-classes):
The LHC machine protection (interlock) system is designed for high reliability with a design target of < 1
failure in 1000 years.
LHC Commissioning :
the road to first beam
41
Injector status : beam at the gate to the LHC
42L.R. Evans – EDMS Document No. 521217
SPC
2
TI 8 commissioning
TI 8 commissioning / V.Mertens / TCC, 29.10.2004
First shot on BTVI87751 on 23 October 2004, 13:39
TV screen at end transfer line
Beam image taken less than 50 m away from the
LHC tunnel in IR8 (LHCb) !
The LHC injectors are ready after a long battle to achieve nominal beam brightness.
Beam was sent down both ~3 km long transfer lines to the LHC.
Filling exercise from SPS to LHC
43
Extraction of a high intensity beam from the SPS to the LHC transfer lines was tested towards both rings in the fall of 2007.
Ready to go …
LHC Machine Commissioning
44
Commissioning of the LHC equipment (‘Hardware commissioning’) has started in 2005 and is now in full progress. This phase includes:
Testing of ~8000 magnets (most of them superconducting). 27 km of cryogenic distribution line (QRL). 4 vacuum systems, each 27 km long. > 1600 magnet circuits with their power converters (60 A to 13000 kA). Protection systems for magnets and power converters. Checkout of beam monitoring devices. Etc…
Hardware commissioning sequence
45
The present LHC commissioning phase is designated as ‘Hardware Commissioning’. The most ‘visible’ job is the commissioning of the magnets and their powering systems.
When all magnets of one of the eight LHC sectors installed and interconnected:
Vacuum system is pumped to nominal pressure. Magnets are cooling down to 1.9 (4.5) Kelvin. The Cool down proceeds in steps,
interleaved with electrical tests (HV insulation, ground faults…). Connection of the power converter to the magnets. Commissioning of the power converter + interlock system + magnet
protection system (low current). Commissioning of magnet powering + magnet protection system (high
current). Powering of all magnets in a sector to nominal current.
This commissioning sequence is run individually on each of the 8 LHC sectors (arcs).
Circuit by circuit
46
Each electrical circuit (magnet group + power converter) has to pass a number of tests before it is released as ‘commissioned’.
For the large circuits, there are more than 10 intermediate steps. Each step is validated by system experts.
Commissioning status
47
Installation and interconnections finished for magnets.
Cryogenics :
- Sector 78 (IR8IR7) was cooled down to 1.9 K in June/July 2007.
- Sector 45 is presently at 1.9 K.
- Sectors 56 and 78 : cool down in progress, expected at 1.9 K mid-March. Magnet powering :
- Commissioning of sector 78 in June/July 2007:
>> All circuits with individual magnets commissioned (except triplets).
>> The main magnets were commissioned to 1 TeV: limited by electrical non-conformities that were repaired during a warm up in September-October.
- Commissioning of sector 45 in progress (until mid-February).
Other systems (RF, beam injection and extraction, beam instrumentation, collimation, interlocks, etc) are essentially on schedule for first beam in 2008.
Cool-down
48
From 300K to 80K pre-cooling with 1200 tons of liquid N2 (60 trucks).
LHC He inventory: 100 tons.
The duration of the first cool-down of one arc/sector is ~6 weeks
(nominal ~ 2 weeks). So far this was too optimistic… The cool down of sector 45 took ~8-9
weeks, delayed by heat isolation problems in certain cells etc The stability of the cryogenics so far proves to be ‘delicate’.
Xmas break
01/10/07
1.9 K
High field
quenches
Approaching 7 TeV
49
Main dipole magnet high field ramps for sector 45 started some days ago.
The first ‘re-training’ quenches occurred around 5.6 TeV. After 3 ramps/training quenches, the magnets have reached 6 TeV. 1 TeV/1500 A to go…
31/01/2008
Currentdischarge into
dump resistors
Quench at 10270
A > 6 TeV
Injection level
Cryo Recovery
50
1.9 K
After a high current/energy quench, the temperature in the affected magnet(s) increases above 20 K.
Recovery is ‘slow’ – few hours.
>> Progress is slow !
51
K. Foraz TS-IC-PL 12 23 34 45 56 67 78 81
12345678910111213141516171819212223242526272829
20
303132333435
12345678910111213141516171819212223242526272829
20
303132333435
Power limitation
It is still possible to have a beam test through 78
around 21st May… Assumes very fast cool-down of
each sector (6 weeks)
Inner triplet interconnect
Flushing
Cool-down
Warm up
Powering Tests
CV maintenance
LHC Schedule, status Week 03LHC Schedule, status Week 03
Focus for 2008:Get beam in at 450 GeV asap !!The HWC will be ‘paused’ to make room for a beam test, presently expected around JUNE!
Towards beam…
52
“As usual” the latest schedule is VERY aggressive: Assumes parallel commissioning of almost the entire machine, while the initial schedules assumed parallel commissioning of only 1/4 LHC in parallel.
There is a strong push for beam tests @ 450 GeV, even before the magnets are commissioning to nominal field:
>>> Get beam in asap at injection.
A beam test of a few weeks at 450 GeV of 1 or 2 sectors or of the entire machine will be performed, possibly as soon as June.
Planning is delicate due to interference with the experiments installation and hardware commissioning.
Various scenarios are been evaluated, including beam tests in certain sectors in parallel with hardware commissioning in others !!
LHC machine cycle (commissioning)
5353
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
energy ramp
preparation and access
beam dump
injection phase
collisions
collisions
450 GeV
7 TeV
start of the ramp Squeeze
Step by step
54
Beam commissioning will start with single low intensity bunches:• Get the beams around and establish an orbit.
• Capture the beams in the RF systems.
• Commissioning all beam instrumentation.
• Understand /check the behaviour of the SC magnets at injection (field drifts due to ‘super-conducting eddy currents’).
• Etc…
Then there will more or less parallel branches to:• Establish operation with both beams together.
• Increase intensity & number of bunches.
• Ramp, ‘squeeze’ (focus more at IP).
• Collide …
If all goes very well… 2 months !
Please take this as a LOWER limit…
Operation phases
55
Parameter Phase A Phase B Phase C Nominal
k / no. bunches 43-156 936 2808 2808
Bunch spacing (ns) 2021-566 75 25 25
N (1011 protons) 0.4-0.9 0.4-0.9 0.5 1.15
Crossing angle (rad)
0 250 280 280
*/*nom) 2 1 1
* (m, IR1&5) 32 22 16 16
L (cm-2s-1) 6x1030-1032 1032-1033 (1-2)x1033 1034
Beam commissioning will proceed in phases with increased complexity: Number of bunches and bunch intensity. Crossing angle (start without crossing angle !). Less focusing at the collision point.
It will most likely take YEARS to reach design luminosity !!!
Summary
56
We are getting there at last !!!!
• After many years of delay the LHC is taking shape in the tunnel.
• The first sector is approaching 7 TeV.
• The entire machine could be at 1.9 K around June.
Beam is knocking at the door :
• The injectors are ready.
• There is a strong push/pressure to inject beam as soon as possible and perform some beam commissioning at 450 GeV – we may have beam in at least one sector in June 2008.
• Although in the best of all Worlds we could achieve collisions after 2 months, the road to 7 TeV collisions is long.... Be patient !!
For more details on the LHC, have a look at the 2nd Hadron Collider Summer School site : http://indico.cern.ch/conferenceDisplay.py?confId=6238
‘RF fingers’ problems
57
RF bellows are used to maintain electrical contact between adjacent pieces of vacuum chamber (essential for beam stability).
The bellows must cope with the thermal expansion of ~ 4 cm between 1.9 K and room temperature (when the magnets are cooled down/warmed up).
Bellows are installed at every interconnection (1700 in total).
At room temperature
At operating temperature
59
Damaged bellows
60
RF fingers that bend into the beam are a classic problem for accelerators. RHIC suffered a lot from it…
So no excuses for not being careful in design and manufacturing ! And yet it happened ! X-ray imaging of some bellows revealed bend fingers in
the sector that was tested in July and warmed up since then for repair.
Cause & solution for RF fingers
61
The fingers bend due to a combination of a wrong ‘finger angle’ PLUS a gap between the magnet apertures larger than nominal (still inside specification).
Only few interconnects are affected. Complete survey of one sector was performed using X-ray techniques. Repair is not difficult…once the bad fingers are found.
>> This problem will stay around until every sector is warmed up again in 200X…
‘Solution’: A small (ping-pong size) ball equipped
with a 40MHz transmitter is blown through the beam vacuum pipe with compressed air.
Beam position monitors are used to follow the ball as it rolls inside the vacuum chamber until it stops or exits on the other end..