Page 1: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

Lecture 19

Chapter 10

A Portfolio Approach to Managing IT Projects

Page 2: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

2

Announcements

• Final Exam overview today

• Business Plans returned today

• Grades for presentations etc. on Thursday

• Group project due Thursday

Page 3: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

3

Final Exam Outline

• 8 – 11am, Wednesday June 13

• Exam is CLOSED book– No notes or text allowed

• Three sections:– Short answer questions– Long Answer questions– Case study questions

Page 4: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

4

Question 1: Find New Zealand on a world map…

Page 5: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

5

Final Exam Sample Questions

Short answer:• What is the difference between security and

reliability?• How does standardization affect business

opportunities? • In what ways is IT infrastructure different from

other infrastructure resources?• Cite an example from one of the cases we

studied that shows how IT professionals with experience in one industry can bring changes to another industry

Page 6: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

6

Final Exam Sample Questions

Long answer (1 page, ~250 words)

• Discuss what risks are associated with major IT projects, and what a company can do to mitigate against them

• Describe the challenges associated with educating users of IT in a company, and what IT-focused companies can do to help their employees

Page 7: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

7

Case study questions

• You will receive a copy of a case in class Thursday

• Prepare in advance – ie read case before exam!

• Questions will be short and long answer from the case

• Identify and analyze core issues

Page 8: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

8

IT Portfolio Management

Page 9: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

9

IT Disasters are still common

• Companies fail to realize risk of project

• Multiple projects lead to larger aggregate risk

• Different projects require different management

Page 10: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

10

Portfolio View of IT

Page 11: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

11

Financial Perspective

Page 12: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

12

Sources of Implementation Risk

1. Project Size

2. Experience with Technology

3. Requirements Volatility

• See fig 10.1

Page 13: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

13

Fig 10.1 Effect of Adding Risk Factors on Project Risk

Page 14: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

14

Barriers to Perspective

Page 15: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

15

Governance

Page 16: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

16

Strategic Grid and Governance

Page 17: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

17

Project Categories and Degree of Risk

Page 18: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

18

Risk Assessment

• Figure 10.3 Risk profile questionnaire

• Higher risk score, higher management approval required

• Repeated several times throughout project

• Different perspectives on risk expectation can lead to disaster

Page 19: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

19

Portfolio Risk

• Multiple projects can add or reduce risk

• Low-risk not always good

• All high-risk is vulnerable

• Identify risks in all projects, then consider combined portfolio of risks

• See fig 10.5

Page 20: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

20

Fig 10.5 Risk and Return Distribution for Portfolio of Projects

Page 21: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

21

Project Implementation Dip

• Most projects don’t go smoothly all the way

• New system going live common point

• Expectations not always realistic

• Short term downward shift may be necessary

• All happens in middle of business cycle and worker turnover

• Need to focus on end goal to get through value of change when people are complaining

• Ideally see it before it comes and get people ready

Page 22: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

22

Fig 10.4 Expectations vs. reality

Page 23: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

23

Questions, Presentations, Break

Page 24: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

24

Project Management

• No single correct plan

• Management Tools– External integration tools– Internal integration tools– Formal planning tools– Formal result controls

• See table 10.1: Tools for project management

Page 25: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

25

Table 10.1 Tools for Project Management

Page 26: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

26

Influences on Tool Selection

• Low requirements volatility/low tech projects– Easy to manage– Least common– PERT (program evaluation review technique)– CPM (critical path method)

• Low requirements volatility/high tech projects– Difficult to manage– Eg. Converting mainframe system, developing web access– Outputs well defined– Technical complexity drives characteristics of successful

manager– Formal planning not likely to add as much value

Page 27: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

27

Influences on Tool Selection (ctd)

• High requirements volatility/low tech projects– Involve users in design, development and implementation– Develop user support– Formal planning and control tools help– Close, aggressive management of external integration– Leadership from management not technologists

• High Requirements Volatility/high-tech projects– Managers need technical expertise– Ill-defined projects common– Formal tools useful once clarity is reached in direction– Cross effects of different factors becomes important

Page 28: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

28

Project Management• Relative Contribution of Management Tools

– Depends on specific project– Results-oriented tools work in structured/formal environment– Depends on corporate culture

• Emergence of Adaptive Project Management Methods– Approaches to design, deployment, implementation and

investment that assume a need to gather information and learn as one goes.

– Not really effective universal methods yet• Software Development Life Cycles

– SDLC breaks down development into stages:– Analysis and design– Construction– Implementation– Operation and maintenance

Page 29: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

29

Project Management (ctd.)

• Adaptive Methodologies– Quickly build rough preliminary version– Iterate through stages rather than finish every stage– Fast cycle through stages– Aim to deliver limited functionality fast– Require skilled staff

• Adaptive Methods and change management– Intensely involve users in evaluating outcomes– Strictly control migration of system features from

development, testing to production– Separating stages avoids major problems

Page 30: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

30

Process Consistency and Agility in Project Management

• Balancing tension between process consistency and process agility

• Tools useful one place shouldn’t necessarily be applied to everything

• Success in balance often includes minimal formalization

• Flow– Understand interrelationships between projects

• Completeness– Keeping track of all tasks in project

• Visibility– Getting info on status of rest of project

Page 31: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

31

Business Plan Feedback

• Lots of interesting ideas

• Make sure the highlights stand out – don’t make a VC look for the main points

• Simple presentation improvements go a long way – spell check, section headings, …

Page 32: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

32

Grading for Business Plan

• Exec summary /10• Bus opportunity articulated /10• Strategy and milestones /10• Marketing /5• Operations plan /5• Management /5• Financials /5• Convincing case /10• Presentation /20

• Total /80

Page 33: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects

33

Grade summary (out of 80)

• Lower quartile: 55

• Median: 62

• Upper quartile: 67

• Mean = 60.33

Page 34: Lecture 19 Chapter 10 A Portfolio Approach to Managing IT Projects