    Definitions

    Purpose of projects

    Project management

    Stakeholders

    Project life cycle Planning tools & techniques

    Post-implementation review

  • 7/31/2019 Projects Managing Projects 2012 13

    3/55

    What is a project?

    ...a managed collection of activities to

    bring about a desired change(CCTA, 1997)

    ...a temporary endeavour undertaken

    to create a unique product or service

    (PMBoK, 1996)

  • 7/31/2019 Projects Managing Projects 2012 13

    4/55

    Why do we have projects?

    solve a particular problem

    exploit a new opportunity

    part of the requirements of your degree

    demonstrate theory in a practical example

  • 7/31/2019 Projects Managing Projects 2012 13

    5/55

  • 7/31/2019 Projects Managing Projects 2012 13

    6/55

    Stakeholder analysis

    Astakeholderin a project is a personor organisation who:

    is involved with...

    is affected by...

    can affect the outcome of...the project

  • 7/31/2019 Projects Managing Projects 2012 13

    7/55

  • 7/31/2019 Projects Managing Projects 2012 13

    8/55

    Project life cycle

    Four phase life cycle

    ...there are other models in use

  • 7/31/2019 Projects Managing Projects 2012 13

    9/55

    Project life cycle

    Four basic phases

    conceptualisation

    definition/plan

    execution/implementation

    finishing/completion

  • 7/31/2019 Projects Managing Projects 2012 13

    10/55

  • 7/31/2019 Projects Managing Projects 2012 13

    11/55

    Why plan?

    Planning has its own costs

    Benefits must outweigh costs Good planning will benefit the project

    Bad planning can add to the cost offailure

    Don't over-plan allow flexibility too detailed may be impossible to achieve

  • 7/31/2019 Projects Managing Projects 2012 13

    12/55

    If we fail toplan

    weplanto fail!

    1212

    Why plan?

  • 7/31/2019 Projects Managing Projects 2012 13

    13/55

  • 7/31/2019 Projects Managing Projects 2012 13

    14/55

  • 7/31/2019 Projects Managing Projects 2012 13

    15/55

  • 7/31/2019 Projects Managing Projects 2012 13

    16/55

    What STEEPLE factorscan youidentify for your final year project?

  • 7/31/2019 Projects Managing Projects 2012 13

    17/55

    Clear project objectives are vitalto planning

    Allow successof the project to be evaluated

    Enableprioritiesto be set

    Enable conflictsto be resolved

    Provide direction and motivation

    Published so key stakeholders are aware of them

    Must be SMART

    Enable evaluationat the end

    o ... did you meet the objectives? ...if not, why not?

    Objectives

  • 7/31/2019 Projects Managing Projects 2012 13

    18/55

    Objectives

    = Specific and written down

    = Time-framed

    = Agreed, Aligned, Achievable

    = Measurable

    = Realistic, Relevant

    S

    MA

    RT

  • 7/31/2019 Projects Managing Projects 2012 13

    19/55

    SMART Objectives

    Increase UK sales volume of ring binders by 5% by 30 June 2013

    Example:

    the objective is:

    specific and written down

    measurableincrease UK sales volume of ring binders by 5%

    achievableby the staff concerned, agreedby those involved,

    alignedto the requirements of the organisation

    relevantto organisations sales targets, realisticin terms of

    outlets

    time-framedby 30 June 2013

  • 7/31/2019 Projects Managing Projects 2012 13

    20/55

    What SMART objectivescan youidentify for your final year project?

    At the end of the project report, reflecton how well SMART objectives have

    been met

  • 7/31/2019 Projects Managing Projects 2012 13

    21/55

  • 7/31/2019 Projects Managing Projects 2012 13

    22/55

    2222

    Work Breakdown Structure

    work packagescould include:

    Analyse existing system

    Design and develop new system

    Test new system

    Implement new system

    Evaluate new system Analyse & interpret results

    Write project report

  • 7/31/2019 Projects Managing Projects 2012 13

    23/55

  • 7/31/2019 Projects Managing Projects 2012 13

    24/55

    2424

    Work Breakdown Structure

    taskscould include: identify key staff in client organisation

    set questions for questionnaire

    dummy run of questionnaire

    draft chapters for project report

    prepare slides for presentation

    amend questions for questionnaire

    issue questionnaire

    analyse data from questionnaire

    write report

    have report proof read

    submit report

  • 7/31/2019 Projects Managing Projects 2012 13

    25/55

    Work Breakdown Structuremust match Gantt chart

    Project Breakdown: complete structure

    Task 1.1.1

    Task 1.1.2

    Task 1.1.3

    Task 1.1.4

    Activity 1.1

    Task 1.2.1

    Task 1.2.2

    Task 1.2.3

    Activity 1.2

    Task 1.3.1

    Task 1.3.2

    Activity 1.3

    WP 1 WP 2 WP 3

    Task 4.1.1Task 4.1.2

    Task 4.1.3

    Activity 4.1

    Task 4.2.1Task 4.2.2

    Task 4.2.3

    Task 4.2.4

    Task 4.2.5

    Activity 4.2

    WP 4

    Complete Project

  • 7/31/2019 Projects Managing Projects 2012 13

    26/55

  • 7/31/2019 Projects Managing Projects 2012 13

    27/55

  • 7/31/2019 Projects Managing Projects 2012 13

    28/55

    Resources

    Human you

    your supervisor

    your client

    your end-users...

    Other Equipment

    Tools

    Office space

    Information

    Raw materials

    and so on ...

  • 7/31/2019 Projects Managing Projects 2012 13

    29/55

    Milestones

    Milestones

    significant eventsin the project plan

    normally correspond to key deliverables interim report to project supervisor

    interim presentation on project progress

    final presentation

    submission of project report

    milestones and dates are agreed with key

    stakeholders at the baseline plan stage

    milestones often become fixed

  • 7/31/2019 Projects Managing Projects 2012 13

    30/55

    What milestonescan you identify foryour final year project?

    Final submission of project?

  • 7/31/2019 Projects Managing Projects 2012 13

    31/55

    Gantt chartsmust match WBS

    ID Task Name Duration

    1 Task 1 3 days

    2 Task 2 2 days

    3 Task 3 5 days

    4 Task 4 3 days

    5 Task 5 6 days

    6 Task 6 3 days

    7 Task 7 4 days

    8 Task 8 1 day

    T F S S M T W T F S S M T W T F

    12 Mar '00 19 Mar '00

  • 7/31/2019 Projects Managing Projects 2012 13

    32/55

    Gantt charts

    Gantt charts show tasks/activities against time

    Tasks could include:

    request Jones paper from library

    request Smith paper from author

    review paper by Jones

    review paper by Smith interview subjects

    set questions for questionnaire

    issue questionnaire

    analyse data from questionnaire

    write report

    have report proof read

    submit report

    cite references

    build references section

  • 7/31/2019 Projects Managing Projects 2012 13

    33/55

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Can set questions while requesting and reviewing papers

    Might not need two full weeks

  • 7/31/2019 Projects Managing Projects 2012 13

    34/55

    34

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Might be able to start this taskearly

    ...and finish early

  • 7/31/2019 Projects Managing Projects 2012 13

    35/55

    35

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Might not haveto start this task straight away

    Might want to delaywhile doing other things

  • 7/31/2019 Projects Managing Projects 2012 13

    36/55

  • 7/31/2019 Projects Managing Projects 2012 13

    37/55

  • 7/31/2019 Projects Managing Projects 2012 13

    38/55

  • 7/31/2019 Projects Managing Projects 2012 13

    39/55

    39

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Analyse data before interviewing subjects

  • 7/31/2019 Projects Managing Projects 2012 13

    40/55

    4040

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Interview subjects before writing report

  • 7/31/2019 Projects Managing Projects 2012 13

    41/55

    4141

    Gantt charts

    Time line:

    week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    Week10

    Week11

    week12

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from q'naire

    have report proof read

    Write report

    Cite references

    Build References section

    Submit report

    Have report proof read before submission

    i k

  • 7/31/2019 Projects Managing Projects 2012 13

    42/55

    Risk Management:Analyse and Assign Risks

    Identify: What are the potential risks?

    Assess: What is the impactof each risk?

    What is the likelihoodof the risk occurring?

    How can the risk bepreventedor identified early?

    What needs to be doneif the risk does occur?

    Allocate: To whom can I assignthe risk?

    this will be you!

  • 7/31/2019 Projects Managing Projects 2012 13

    43/55

    43

    What riskscan you identify in your planfor your final year project?

    What couldpossiblygo wrong?

  • 7/31/2019 Projects Managing Projects 2012 13

    44/55

  • 7/31/2019 Projects Managing Projects 2012 13

    45/55

  • 7/31/2019 Projects Managing Projects 2012 13

    46/55

    46

    What resourcescan you identify foryour final year project?

    How will tasks be balanced withactivities on other modules?

  • 7/31/2019 Projects Managing Projects 2012 13

    47/55

    Network diagrams

    Powerful tools to represent and optimisecomplex schedules

    Not as intuitive as Gantt charts Planning rather management reporting tool

  • 7/31/2019 Projects Managing Projects 2012 13

    48/55

    Critical path methodMust match Gantt chart and WBS

    10

    0,0

    20

    2,2

    50

    7,970

    12,12

    80

    15,15

    30

    6,7

    40

    8,9

    60

    5,5

    A

    2

    B

    4

    D

    3

    C

    5

    E

    2 F

    3G

    3

    H

    7

    I

    3

    EETLET

    Critical path

    The longest path

    through the network isthe shortesttimethe project can take

    The critical path is the path withzero float; anydelay will mean

    the whole projectwill be late

  • 7/31/2019 Projects Managing Projects 2012 13

    49/55

  • 7/31/2019 Projects Managing Projects 2012 13

    50/55

  • 7/31/2019 Projects Managing Projects 2012 13

    51/55

  • 7/31/2019 Projects Managing Projects 2012 13

    52/55

    Post-implementation review (PIR)

    Includes:

    identification offaults & suggested enhancements

    agreement on what needs to go in a future release

    success of project in terms ofbudget / timescale

    success of system in meeting objectives

    development practicesthat worked well or badly

    Chaffey (2003)

    Can you identify further workrelated to your project?

  • 7/31/2019 Projects Managing Projects 2012 13

    53/55

    How PIR helps future projects

    Learn from what has been done:

    avoid failure in the future

    employ techniques found to be useful

    reinforcegood practice

  • 7/31/2019 Projects Managing Projects 2012 13

    54/55

    Conclusion

    Project life cycle

    basic framework for any project

    going on holiday

    organising an event

    final year project

    Planning tools & techniques

    useful methods to help you plan what you are going to do

    what you have done so far

    what there is left to do

  • 7/31/2019 Projects Managing Projects 2012 13

    55/55

    Further reading

    Bentley C (1997) PRINCE 2: A Practical Handbook Oxford:Butterworth-Heinemann

    Brooks F. (1995) The Mythical Man-Month (Anniversary Edition),

    Harlow: Addison-Wesley Burke R (2003). Project Management: Planning and Control

    Techniques, Chichester: Wiley

    Central Computer & Telecommunications Agency (1997) PRINCE2: An Outline, London: The Stationery Office

    Field M & Keller L (1998) Project Management, Oxford:International Thomson Business Press